JPS61254734A - Connection of precast steel panel concrete wall - Google Patents

Connection of precast steel panel concrete wall

Info

Publication number
JPS61254734A
JPS61254734A JP9517685A JP9517685A JPS61254734A JP S61254734 A JPS61254734 A JP S61254734A JP 9517685 A JP9517685 A JP 9517685A JP 9517685 A JP9517685 A JP 9517685A JP S61254734 A JPS61254734 A JP S61254734A
Authority
JP
Japan
Prior art keywords
concrete
joint
wall
reinforcement
walls
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP9517685A
Other languages
Japanese (ja)
Other versions
JPH0542538B2 (en
Inventor
江守 克彦
友康 加藤
笹川 和郎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP9517685A priority Critical patent/JPS61254734A/en
Publication of JPS61254734A publication Critical patent/JPS61254734A/en
Publication of JPH0542538B2 publication Critical patent/JPH0542538B2/ja
Granted legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は原子炉建屋等大規模建物の耐力壁をプレキャ
ストした鋼板コンクリート壁を現場で接合して構成する
プレキャスト鋼板コンクリート壁の接合方法に関するも
のである。
[Detailed Description of the Invention] (Industrial Application Field) This invention relates to a method for joining precast steel plate concrete walls that are constructed by joining on-site steel plate concrete walls that are precast load-bearing walls for large-scale buildings such as nuclear reactor buildings. It is.

(発明が解決しようとする問題点) 原子炉建屋等壁厚の大きい耐力壁は現場施工されるのが
一般的であるが、現場作業の能率向上のためプレキャス
ト鋼板コンクリート壁を現場で接合する方法が採られる
。この場合の接合は、壁面から接合端面に突出した鋼板
同士を溶接することによシ行なわれる。
(Problem to be solved by the invention) Large load-bearing walls such as in nuclear reactor buildings are generally constructed on-site, but this method involves joining precast steel plate concrete walls on-site to improve the efficiency of on-site work. is taken. In this case, the joining is performed by welding together the steel plates that protrude from the wall surface to the joining end surface.

ところがこの鋼板を溶接する方法では作業が煩雑となり
、工程が増すため工期の短縮、能率の向上を図ることが
難しく、プレキャスト造としての利点を十分に生かせな
い。
However, this method of welding steel plates is complicated and increases the number of steps, making it difficult to shorten the construction period and improve efficiency, making it impossible to take full advantage of the advantages of precast construction.

この発明はプレキャスト造の利点を生かす目的からなさ
れたもので、簡便な手段で現場作業の迅速化を図ろうと
するものである。
This invention was made to take advantage of the advantages of precast construction, and aims to speed up on-site work with simple means.

(問題点を解決するための手段) 本発明ではプレキャスト鋼板コンクリート壁相互の接合
X部に鉄筋篭を設置し、次いでコンクリートを打設する
ことによシ接合を行なう。
(Means for Solving the Problems) In the present invention, a reinforcing bar cage is installed at the joint X portion between precast steel plates and concrete walls, and then concrete is poured to perform the joint.

鉄筋篭は主筋である縦筋とフープ及びスパイラル筋から
なり、鋼板コンクリート壁の接合端面にはループ筋が水
平に突設されており、接合は鉄筋篭と鋼板コンクリート
壁を所定の位置に設置後、通し筋をループ筋、フープ及
びスパイラル筋に挿通させて配筋し、コンクリートを打
設するものである。
The reinforcing bar cage consists of main longitudinal bars, hoops, and spiral bars. Loop bars are horizontally protruded from the joint end of the steel plate concrete wall, and the joint is made after the reinforcing bar basket and the steel plate concrete wall are installed in the specified position. , Reinforcement is placed by inserting through reinforcement into loop reinforcement, hoop reinforcement, and spiral reinforcement, and concrete is poured.

(実施例) 以下この発明を実施例を示す図面とともに説明する。(Example) The present invention will be described below with reference to drawings showing embodiments.

この接合方法は鉄筋篭Aを所定の接合部aに設置し、プ
レキャスト鋼板コンクリート壁B(以下SC壁B)を鉄
筋篭Aを挾んで相互に突合せて配置するとともに、通し
筋Cを配筋してコンクリートDを打設するものである。
In this joining method, a reinforcing bar A is installed at a predetermined joint a, a precast steel plate concrete wall B (hereinafter referred to as SC wall B) is placed abutting each other with the reinforcing bar A sandwiched between them, and through-bars C are arranged. concrete D is poured.

鉄筋篭Aは主筋である縦筋1を取り巻くようにフープ2
及びスパイラル筋3を配して形成され、縦筋1の継手部
にはカプラー4を装着している。
Rebar cage A has hoop 2 surrounding vertical reinforcement 1, which is the main reinforcement.
and spiral stripes 3, and a coupler 4 is attached to the joint portion of the longitudinal strips 1.

SCC壁上両壁面5,5が鋼板であり、この鋼板が型枠
となり、壁面5,5間にコンクリート6を充てんして構
成される。また接合端面7にはル−プ筋8が水平に突設
され、縦に複数配列している。このSCC壁上主に工場
においてコンクリート6を充てんして製作されるが、コ
ンクリート6は現場で接合部aのコンクIJ −) D
打設時と同時に打設してもよい。
Both wall surfaces 5, 5 on the SCC wall are made of steel plates, this steel plate serves as a formwork, and the space between the wall surfaces 5, 5 is filled with concrete 6. Also, a plurality of loop lines 8 are horizontally protruded from the joint end surface 7 and arranged vertically. This SCC wall is manufactured by filling it with concrete 6 mainly in a factory, but the concrete 6 is filled with concrete 6 at the joint part a on site.
It may be placed at the same time as pouring.

通し筋CはSCC壁上ループ筋8において鉄筋篭Aに係
合させるために配筋され、縦筋1と平行にループ筋8.
7−ブ2及びスパイラル筋3に挿通する。
The through bars C are placed in the loop bars 8 on the SCC wall to engage with the reinforcing bar baskets A, and the loop bars 8.
7- Insert through the tube 2 and spiral muscle 3.

接合手順は次の通りである。The joining procedure is as follows.

第2図に示すようにまず鉄筋篭Aを接合部aに吊込んで
設置し、SCC壁上ループ筋8がフープ2及びスパイラ
ル筋3と互い違いとなるように、ループ筋8をフープ2
,2間尺スパイラル筋3のピッチ間に挿入して配置する
。次いで通し筋Cを配筋し、型枠を組んでコンク!J 
−) Dを打設する。
As shown in FIG. 2, first install the reinforcing bar basket A by suspending it from the joint a, and connect the loop bars 8 to the hoop 2 so that the loop bars 8 on the SCC wall alternate with the hoops 2 and spiral bars 3.
, is inserted between the pitches of the ulnar spiral muscle 3. Next, place reinforcement C, assemble the formwork, and complete the construction! J
-) Pour D.

接合部aにおけるSCC壁上配置の仕方は建物の形状、
接合箇所に応じ、第3図乃至第8図に示す通りとなる。
How to place SCC on the wall at joint a depends on the shape of the building,
Depending on the joint location, it will be as shown in FIGS. 3 to 8.

第3図は直線部、第4図はコーナ一部、第5図はT字型
部、第6図及び第7図は十字型部、第8図はへ字型部の
接合例をそれぞれ示したものである。各接合部a、すな
わちSCC壁上配置の仕方に応じて通し筋Cの本数、配
筋箇所を、またそれに伴い鉄筋篭Aの組み方を調整する
。また第4図、第7図のように壁面5の鋼板を接合端面
7から突出させてSCC壁上製作し、コンクリートDの
打設の際に突出した鋼板を型枠として使用することがで
きる。
Figure 3 shows a straight part, Figure 4 shows a part of a corner, Figure 5 shows a T-shaped part, Figures 6 and 7 show a cross-shaped part, and Figure 8 shows an example of joining a F-shaped part. It is something that The number of through-bars C, the reinforcement locations, and the manner in which the reinforcing bar baskets A are assembled are adjusted accordingly in accordance with the arrangement of each joint a, that is, the SCC on the wall. Further, as shown in FIGS. 4 and 7, the steel plate of the wall surface 5 can be made to protrude from the joint end face 7 to produce an SCC wall, and the protruding steel plate can be used as a formwork when pouring concrete D.

第9図、第10図は接合端面7の詳細を示したものであ
る。                 4・SCC壁
上接合端面7は両壁面5,5と同じく鋼板で構成され、
また製作の際の型枠を兼ねている。接合端面7にはコン
クリートDとの付着を高めるジベル9と水平に突設され
るループ筋8が溶接等により接合される。第10図はル
ープ筋8の接合例を示したもので、ここでは両壁面5,
5の内側に接合された形鋼10に、ループ筋8のアンカ
一部8aを接合端面7に貫通させて溶接しである。ルー
プ筋8は接合端面7に強固に接合されていればよいので
他の溶接手段でも勿論よく、またアンカ一部8aを接合
端面7に貫通させてコンクリート6中に埋設して設ける
方法でもよい。ジベル9についても同様である。
9 and 10 show details of the joint end surface 7. FIG. 4. The SCC wall joint end surface 7 is made of steel plate like both wall surfaces 5, 5,
It also serves as a formwork during production. A dowel 9 that enhances adhesion to the concrete D and a horizontally protruding loop reinforcement 8 are joined to the joint end surface 7 by welding or the like. FIG. 10 shows an example of joining the loop muscles 8. Here, both wall surfaces 5,
The anchor part 8a of the loop reinforcement 8 is passed through the joint end surface 7 and welded to the section steel 10 joined to the inside of the joint 5. As long as the loop reinforcement 8 is firmly connected to the joint end surface 7, other welding means may of course be used, or a method in which the anchor part 8a is penetrated through the joint end surface 7 and buried in the concrete 6 may also be used. The same applies to Jibel 9.

(発明の効果) この発明は以上の構成からなり、現場作業はプレキャス
ト製の鉄筋篭と鋼板コンクリート壁の設置と通し筋の配
筋及びコンクリートの打設のみであるから、施工は合理
化され、それにより工期の短縮化が図れる。
(Effects of the invention) This invention has the above-mentioned configuration, and the only on-site work is installing a precast reinforcing bar cage and a steel plate concrete wall, arranging through-bars, and pouring concrete, so the construction is streamlined. This will shorten the construction period.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の実施による建物例を示した概略図であ
り、第2図は施工手順を示した正面図と断面図である。 第3図は本発明の実施例を示した断面図と正面図であシ
、第4図乃至第8図は他の実施例を示した断面図である
。第9図−工は鋼板コンクリート壁の接合部を示した平
面図であり、■はその縦断面図、■は正面図である。第
10図はループ筋の溶接例を示した断面図である。 A:鉄筋篭、B:プレキャスト鋼板コンクリート壁、C
:通し筋、D:コンクリ−ト ロ:接合部、1:縦筋、2:フープ 3:スパイラル筋、4:カプラー、5:壁面6:コンク
リート、7:接合端面 8:ループ筋、8a:ループ筋のアンカ一部9ニジベル
、10:形鋼。 9 図 ■ 10  図 ■ ■ iユー
FIG. 1 is a schematic diagram showing an example of a building according to the present invention, and FIG. 2 is a front view and a sectional view showing the construction procedure. FIG. 3 is a sectional view and a front view showing an embodiment of the present invention, and FIGS. 4 to 8 are sectional views showing other embodiments. FIG. 9 is a plan view showing the joint of a steel plate concrete wall, ■ is a vertical sectional view thereof, and ■ is a front view. FIG. 10 is a sectional view showing an example of loop reinforcement welding. A: Reinforced cage, B: Precast steel plate concrete wall, C
: Through reinforcement, D: Concrete reinforcement: Joint, 1: Vertical reinforcement, 2: Hoop 3: Spiral reinforcement, 4: Coupler, 5: Wall surface 6: Concrete, 7: Joint end surface 8: Loop reinforcement, 8a: Loop reinforcement Anchor part 9 nijibel, 10: section steel. 9 Figure ■ 10 Figure ■ ■ iU

Claims (1)

【特許請求の範囲】[Claims] (1)縦筋とフープ及びスパイラル筋で形成された鉄筋
篭を所定の接合部に設置した後、両壁面が鋼板で構成さ
れ、壁面間にコンクリートが充てんされるとともに、接
合端面に複数のループ筋が水平に突設されたプレキャス
ト鋼板コンクリート壁を接合部に相互に突合せて配置し
、次いで通し筋をフープ、スパイラル筋及びループ筋に
挿通してコンクリートを打設することを特徴とするプレ
キャスト鋼板コンクリート壁の接合方法。
(1) After installing a reinforcing bar cage made of vertical bars, hoops, and spiral bars at a specified joint, both walls are made of steel plates, concrete is filled between the walls, and multiple loops are placed on the joint end face. A precast steel plate characterized in that precast steel concrete walls with horizontally protruding reinforcements are arranged so as to butt against each other at joints, and then concrete is poured by inserting through reinforcements into hoops, spiral reinforcements, and loop reinforcements. How to join concrete walls.
JP9517685A 1985-05-02 1985-05-02 Connection of precast steel panel concrete wall Granted JPS61254734A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9517685A JPS61254734A (en) 1985-05-02 1985-05-02 Connection of precast steel panel concrete wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9517685A JPS61254734A (en) 1985-05-02 1985-05-02 Connection of precast steel panel concrete wall

Publications (2)

Publication Number Publication Date
JPS61254734A true JPS61254734A (en) 1986-11-12
JPH0542538B2 JPH0542538B2 (en) 1993-06-28

Family

ID=14130437

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9517685A Granted JPS61254734A (en) 1985-05-02 1985-05-02 Connection of precast steel panel concrete wall

Country Status (1)

Country Link
JP (1) JPS61254734A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06136856A (en) * 1992-10-21 1994-05-17 Penta Ocean Constr Co Ltd Method of connecting precast concrete member
JP2020084408A (en) * 2018-11-15 2020-06-04 ジオスター株式会社 Reinforcing-bar connecting joint, structure of reinforcing-bar connecting joint and connecting method of precast concrete member
JP2020190158A (en) * 2019-05-23 2020-11-26 鹿島建設株式会社 Method for constructing structure, and structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06136856A (en) * 1992-10-21 1994-05-17 Penta Ocean Constr Co Ltd Method of connecting precast concrete member
JP2020084408A (en) * 2018-11-15 2020-06-04 ジオスター株式会社 Reinforcing-bar connecting joint, structure of reinforcing-bar connecting joint and connecting method of precast concrete member
JP2020190158A (en) * 2019-05-23 2020-11-26 鹿島建設株式会社 Method for constructing structure, and structure

Also Published As

Publication number Publication date
JPH0542538B2 (en) 1993-06-28

Similar Documents

Publication Publication Date Title
JPH09203143A (en) Connection method of perpendicular part of wall plate of wall precast reinforced concrete
JPH07292783A (en) Connective structure of prestressed concrete members
CN116220266B (en) Floor structure
WO2020186857A1 (en) Connection structure provided among precast reinforced concrete structure bodies and reinforcing steel configuration method for reinforced concrete structure bodies
JPS61254734A (en) Connection of precast steel panel concrete wall
JP2003313951A (en) Beam-column joint structure of building having composite structure
JP2774908B2 (en) Precast concrete member joining method
KR20000061241A (en) Precast concrete beam and connecting method with the other building elements
JP3643809B2 (en) Connection structure of precast concrete foundation blocks
JPS6039401Y2 (en) joint reinforcing bars
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPH11141055A (en) Method of jointing slab reinforcement and beam main reinforcement to core wall
JPH03275839A (en) Connection construction of reinforced concrete column and steel beam
JPH0728270Y2 (en) PC concrete pillar for rebar
JPS62228544A (en) Construction of wall body in atomic reactor building
JPH0827783A (en) Precast concrete member containing steel pipe and its connection
JPS6025574B2 (en) wall prefab building structure
JPH0427341B2 (en)
JPS6319661B2 (en)
JPH0253576B2 (en)
JPS5941566A (en) Construction of building by precast concrete member
CN115262777A (en) Construction process of section steel concrete structure for super high-rise building
JPH0349336B2 (en)
JPS63167834A (en) Precast reinforced concrete beam member
JPH0541777B2 (en)

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees