JPS61254720A - Construction work of embankment - Google Patents
Construction work of embankmentInfo
- Publication number
- JPS61254720A JPS61254720A JP9381085A JP9381085A JPS61254720A JP S61254720 A JPS61254720 A JP S61254720A JP 9381085 A JP9381085 A JP 9381085A JP 9381085 A JP9381085 A JP 9381085A JP S61254720 A JPS61254720 A JP S61254720A
- Authority
- JP
- Japan
- Prior art keywords
- embankment
- foundation
- cofferdam
- hardened
- self
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims description 24
- 239000007788 liquid Substances 0.000 claims abstract description 16
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 11
- 230000000087 stabilizing effect Effects 0.000 claims description 10
- 239000003381 stabilizer Substances 0.000 abstract description 11
- 229910000831 Steel Inorganic materials 0.000 abstract description 9
- 239000010959 steel Substances 0.000 abstract description 9
- 239000002689 soil Substances 0.000 abstract description 7
- 238000009412 basement excavation Methods 0.000 abstract description 6
- 238000000034 method Methods 0.000 abstract description 6
- 238000002156 mixing Methods 0.000 abstract description 3
- 238000007599 discharging Methods 0.000 abstract 2
- 238000005728 strengthening Methods 0.000 abstract 1
- 239000004576 sand Substances 0.000 description 5
- 238000002347 injection Methods 0.000 description 3
- 239000007924 injection Substances 0.000 description 3
- 239000004568 cement Substances 0.000 description 2
- 239000000654 additive Substances 0.000 description 1
- 230000000996 additive effect Effects 0.000 description 1
- 239000000440 bentonite Substances 0.000 description 1
- 229910000278 bentonite Inorganic materials 0.000 description 1
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 description 1
- 239000011400 blast furnace cement Substances 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000010440 gypsum Substances 0.000 description 1
- 229910052602 gypsum Inorganic materials 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 239000013535 sea water Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/30—Foundations made with permanent use of sheet pile bulkheads, walls of planks, or sheet piling boxes
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
- Foundations (AREA)
Abstract
Description
【発明の詳細な説明】
(産業上の利用分野)
この発明は、橋脚、橋台などの基礎を水海中に形成する
際に設けられる築島の構築工法に関する。DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) The present invention relates to a method for constructing a rocky island when forming foundations for bridge piers, abutments, etc. in water.
(従来の技術)
周知のように、水海中に形成される橋脚、橋台などの基
礎の施工においては、水海底の直接把削ができないため
、予め基礎の形成予定地に水海面上に突出する築島を構
築して、その後に例えばケーソン工法、連続地中壁工法
などにより基礎を形成している。(Prior art) As is well known, when constructing foundations such as bridge piers and abutments that are formed underwater, it is not possible to directly grasp the seabed, so it is necessary to prepare a site that protrudes above the surface of the water at the site where the foundation is to be formed. A built-up island is constructed, and then the foundation is formed using, for example, the caisson construction method or the continuous underground wall construction method.
築島は、外力(波、流速など)を考慮して築島面積を決
め、従来一般的には第2図に示すような方法で構築して
いた。The area of the island was determined by considering external forces (waves, current speed, etc.), and conventionally the island was constructed using the method shown in Figure 2.
同図に示す方法は、まず、基礎1の構築予定地に連結金
具付の土焔矢板、例えば鋼管矢板2を密接して海底部3
下に打設して、予定地を囲繞する締切工を行う。The method shown in the figure is to first place earthen sheet piles with connecting fittings, such as steel pipe sheet piles 2, in close contact with the site where the foundation 1 is planned to be constructed, and
A cofferdam will be constructed to surround the planned site by pouring the cofferdam underneath.
次いでw4管矢板2で囲んだ部分に土砂4を投入して埋
め戻し、築島5を構築する。Next, the area surrounded by the W4 pipe sheet piles 2 is filled with earth and sand 4 to be backfilled, and a built-up island 5 is constructed.
しかる後、例えば築島5の上面から掘削し、支持地盤層
まで達する基礎1を連続地中壁工法等で形成する。Thereafter, for example, excavation is performed from the top surface of the rocky island 5, and a foundation 1 that reaches the supporting ground layer is formed using a continuous underground wall construction method or the like.
ここで、基礎1の施工前に土砂4を投入しただけの築島
5が透水性であるため、適宜個所にデープウェル6を設
は築島5内の排水を行ったり、あるいは、基礎1の形成
前に地盤改良処!7等を行うなどの補助工法も併用され
ていた。Here, since the Tsukijima 5 which has only been filled with earth and sand 4 before the foundation 1 is constructed is water permeable, deep wells 6 are installed at appropriate locations to drain the Tsukishima 5, or before the foundation 1 is formed. Ground improvement office! Supplementary construction methods such as 7th grade were also used.
(発明が解決しようとする問題点)
第2図に示す築島工法では、土砂4を投入して埋め戻し
た築島5のため、均質な土質を得ることが難しく、また
、築島5の強度も調整することが困難であった。(Problems to be Solved by the Invention) In the Tsukishima construction method shown in Figure 2, it is difficult to obtain homogeneous soil quality because the Tsukishima 5 is backfilled with earth and sand 4, and the strength of the Tsukishima 5 is also adjusted. It was difficult to do so.
しかも、築島5が透水性であるため、特に連続地中壁工
法で基礎1を形成する際には、掘削孔の安定性を確保す
るために補助工法の併用を必要とし、工期が長期化し、
工費が嵩むという欠点があった。Moreover, since the Tsukijima 5 is permeable, especially when forming the foundation 1 using the continuous underground wall construction method, it is necessary to use auxiliary construction methods in order to ensure the stability of the excavation hole, which lengthens the construction period.
The disadvantage was that the construction costs were high.
この発明は、このような問題点に鑑みてなされたもので
あって、その目的とするところは、均質な土質が得られ
るとともに任意な強度調整ができ、しかも補助工法を不
要にして工期の短縮と工費の低減化が達成できる築島の
構築工法を提供することにある。This invention was made in view of these problems, and its purpose is to obtain homogeneous soil quality, enable arbitrary strength adjustment, and shorten the construction period by eliminating the need for auxiliary construction methods. The purpose of the present invention is to provide a method of constructing a rocky island that can reduce construction costs.
(問題点を解決するための手段) 上記目的を達成するため、この発明は、橋脚。(Means for solving problems) In order to achieve the above object, the present invention provides a bridge pier.
橋台などの基礎を水海中に形成する際に設けられる築島
の構築工法において、該基礎の形成予定地に締切工を施
した後に、該締切工内の水を排出しつつその内部に自硬
性安定液を置換注入し、該締切工内の該自硬性安定液を
硬化させて築島となすことを特徴とする。In the construction method of Tsukishima, which is used when forming foundations such as bridge abutments in the water, after constructing a cofferdam at the site where the foundation is planned to be formed, water within the cofferdam is drained and the interior of the cofferdam is self-hardened and stabilized. It is characterized by displacing and injecting a liquid to harden the self-hardening stabilizing liquid in the cofferdam to form a built island.
(作 用)
締切工内に置換注入された自硬性安定液は、時間の経過
によって硬化し、締切工と一体となって築島が形成され
る。(Function) The self-hardening stabilizing liquid injected into the cofferdam hardens over time, and forms a built-up island together with the cofferdam.
自硬性安定液中の成分を適宜調整すれば、硬化時間およ
び硬化強度の任意な設定が可能となる。By appropriately adjusting the components in the self-hardening stabilizer, it is possible to arbitrarily set the curing time and curing strength.
(実 施 例)
以下、本発明の好適な実施例について添附図面を参照に
して詳細に説明する。(Embodiments) Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.
第1図は本発明に係る築島構築工法の一実施例を示して
いる。FIG. 1 shows an embodiment of the Tsukishima construction method according to the present invention.
同図に示す工法は、前述した従来の方法と同じように、
基礎1の形成予定地を取り囲むようにして連結金具骨の
鋼管矢板2を密接して海底面3下打設して締切工を施す
。The construction method shown in the figure is the same as the conventional method described above.
Steel pipe sheet piles 2 of connecting metal frames are closely placed under the seabed 3 so as to surround the site where the foundation 1 is planned to be formed, and cofferdam work is performed.
次いで、鋼管矢板2で囲繞した内部の海水を、例えばそ
の上方部からポンプによって排水しつつ、海底面3に近
接してトレミー管などを介して自硬性安定液10を置換
注入する。Next, while the seawater inside the steel pipe sheet pile 2 is drained from the upper part thereof using a pump, the self-hardening stabilizing liquid 10 is replaced and injected close to the seabed surface 3 through a tremie pipe or the like.
自硬性安定液10は、硬化剤、例えばセメント。The self-hardening stabilizer 10 is a hardening agent, such as cement.
高炉セメントなどと、ベントナイト2添加剤を適宜比率
で水に混合したものであって、場合によっては粘土や現
地土砂を混入してもよい。It is a mixture of blast furnace cement and bentonite 2 additive in water in an appropriate ratio, and clay or local earth and sand may be mixed in depending on the case.
ここで、自硬性安定液10の置換注入に先立ち、鋼管矢
板2で囲繞した部分の海底面3上の泥土を浚渫し、硬化
した安定液1oと海底面3の良好な接合強度が得られる
ようにすることが好ましい。Here, prior to the replacement injection of the self-hardening stabilizing liquid 10, the mud on the seabed surface 3 in the area surrounded by the steel pipe sheet piles 2 is dredged so as to obtain good bonding strength between the hardened stabilizing liquid 1o and the seabed surface 3. It is preferable to
また、自硬性安定液10の注入量は、この実施例では鋼
管矢板2の上端まで行わず、海面の潮位変位(HL−L
L)のほぼ中間位置に留めているが、勿論上端近傍まで
注入してもよい。In addition, the injection amount of the self-hardening stabilizing liquid 10 is not injected up to the upper end of the steel pipe sheet pile 2 in this embodiment, but is determined based on the tidal level displacement of the sea surface (HL-L).
Although the injection is kept at approximately the middle position of L), it is of course possible to inject to the vicinity of the upper end.
注入された自硬性安定液10は、時間の経過によって硬
化し、硬化後に5〜20 kg / ciの強度と10
−6〜10−’am/sea程度の透水係数となり、鋼
管矢板2とともに一体となって築島11が構築される。The injected self-hardening stabilizer 10 will harden over time, and after hardening it will have a strength of 5-20 kg/ci and 10
The hydraulic conductivity is approximately -6 to 10-'am/sea, and the built-up island 11 is constructed integrally with the steel pipe sheet pile 2.
なお、この実施例では硬化した自硬性安定液10の上面
にセメントと石膏とを配合した強化W112を設けてい
るが、これは基礎1を形成する際に築島11上に載置さ
れる掘削機械などの重量を考慮し、より大きな安全性を
確保するために形成したものであって、重量によっては
必ずしも必要としない。In this embodiment, a reinforced W 112 made of cement and gypsum is provided on the upper surface of the hardened self-hardening stabilizer 10, but this is because the excavating machine placed on the Tsukishima 11 when forming the foundation 1 This design was designed to ensure greater safety in consideration of the weight of the vehicle, and may not necessarily be necessary depending on the weight.
築島11の構築が終わると、その上端から溝孔を掘削し
、コンクリートを打設して地中連続壁による基礎1の形
成が行われる。When the construction of the island 11 is completed, a trench is excavated from its upper end, concrete is poured, and the foundation 1 is formed using an underground continuous wall.
基礎1の形成手段は地中連続壁だけでなくケーソン基礎
でもよい。The means for forming the foundation 1 may be not only an underground continuous wall but also a caisson foundation.
また、締切工も鋼管矢板2に限定されず他の手段であっ
てもよい。Moreover, the cofferdam is not limited to the steel pipe sheet pile 2, but may be other means.
(発明の効果)
以上、実施例で説明したように本発明に係る築島構築工
法によれば、自硬性安定液が硬化することにより、海底
面から上端まで均一した土質の築島が得られ、基礎を形
成する際に掘削が容易に行われるとともに、安定液の配
合比率を変えることで任意且つ広範囲の硬化強度の調整
が可能となり、!礎の掘削用機械やケーソン函体の重置
変化に容易且つ簡単に対応できる。(Effects of the Invention) As explained above in the examples, according to the method for constructing an island according to the present invention, by hardening the self-hardening stabilizing liquid, an island with uniform soil quality from the seabed surface to the top can be obtained, and the foundation Not only is excavation easy to perform when forming, but the curing strength can be adjusted arbitrarily and over a wide range by changing the blending ratio of the stabilizing liquid. It can easily and easily respond to changes in the stacking of foundation excavation machines and caisson boxes.
また、築島の土質が均質且つ安定した強度が得られるた
め、築島全体の面積を従来よりも小さくできる。Furthermore, since the soil of the island is homogeneous and has stable strength, the area of the entire island can be made smaller than before.
さらに、硬化した自硬性安定液は非透水性であって、従
来の砂埋め戻しのように透水性でないため、デープウエ
ル、深層混合などの補助工法を併用することなく基礎の
施工が直接行えるため、大幅な工期の低減と低コスト化
が達成される。Furthermore, since the hardened self-hardening stabilizer is water-impermeable and not water-permeable like conventional sand backfill, foundation construction can be performed directly without using auxiliary construction methods such as deep wells or deep mixing. A significant reduction in construction time and cost will be achieved.
第1図は本発明工法の一例を示す平面図(A)と断面図
(B)、第2図は従来工法の一例を示す平面図(A)と
断面図(B)である。
1・・・・・・・・・基 礎 2・・・・・・・
・・鋼管矢板3・・・・・・・・・海底面 4・
・・・・・・・・土 砂5・・・・・・・・・築 島
6・・・・・・・・・デーブウエル7・・・・・
・・・・地盤改良処理 10・・・・・・自硬性安定液
11・・・・・・築 島(本発明)
12・・・・・・強化層
第11
図
第2図
(B)
L] ″LfFIG. 1 is a plan view (A) and a sectional view (B) showing an example of the construction method of the present invention, and FIG. 2 is a plan view (A) and a sectional view (B) showing an example of the conventional construction method. 1・・・・・・・・・Fundamentals 2.・・・・・・
・・Steel pipe sheet pile 3・・・・・・・・・・・
・・・・・・・・・Earth Sand 5・・・・・・Tsukishima
6・・・・・・・・・Davewell 7・・・・・・
...Soil improvement treatment 10...Self-hardening stabilizer 11...Tsukishima (present invention) 12...Reinforcement layer 11 Figure 2 (B) L ] ″Lf
Claims (1)
る築島の構築工法において、該基礎の形成予定地に締切
工を施した後に、該締切工内の水を排除しつつその内部
に自硬性安定液を置換注入し、該締切工内の該自硬性安
定液を硬化させて築島となすことを特徴とする築島構築
工法。In the construction method of Tsukishima, which is used when forming the foundations of bridge piers, abutments, etc. in the water, after constructing a cofferdam at the site where the foundation is planned to be formed, water inside the cofferdam is removed and self-contained water is added to the interior of the cofferdam. A construction method for constructing an island, which comprises displacing and injecting a hard stabilizing liquid to harden the self-hardening stabilizing liquid within the cofferdam to form a built island.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP60093810A JPH0612012B2 (en) | 1985-05-02 | 1985-05-02 | Tsukishima construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP60093810A JPH0612012B2 (en) | 1985-05-02 | 1985-05-02 | Tsukishima construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS61254720A true JPS61254720A (en) | 1986-11-12 |
JPH0612012B2 JPH0612012B2 (en) | 1994-02-16 |
Family
ID=14092754
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP60093810A Expired - Fee Related JPH0612012B2 (en) | 1985-05-02 | 1985-05-02 | Tsukishima construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0612012B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105421498A (en) * | 2015-11-16 | 2016-03-23 | 同济大学 | Foundation pit anti-seepage and settlement control method based on stereoscopic curtain-well group system |
CN107012792A (en) * | 2017-05-23 | 2017-08-04 | 温州市隆尚建设有限公司 | A kind of construction method of bridge substructure |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6062337A (en) * | 1983-09-13 | 1985-04-10 | Ohbayashigumi Ltd | Construction of underwater foundation |
-
1985
- 1985-05-02 JP JP60093810A patent/JPH0612012B2/en not_active Expired - Fee Related
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6062337A (en) * | 1983-09-13 | 1985-04-10 | Ohbayashigumi Ltd | Construction of underwater foundation |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105421498A (en) * | 2015-11-16 | 2016-03-23 | 同济大学 | Foundation pit anti-seepage and settlement control method based on stereoscopic curtain-well group system |
CN105421498B (en) * | 2015-11-16 | 2017-06-13 | 同济大学 | A kind of foundation ditch water-impervious and subsidence control method based on three-dimensional curtain gang of wells system |
CN107012792A (en) * | 2017-05-23 | 2017-08-04 | 温州市隆尚建设有限公司 | A kind of construction method of bridge substructure |
Also Published As
Publication number | Publication date |
---|---|
JPH0612012B2 (en) | 1994-02-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103958780B (en) | The method for forming cementing retaining wall | |
CN201245846Y (en) | Clamshell excavator stirring concrete enclosure wall | |
CN212316948U (en) | Backfill structure for drainage pipeline in high underground water level area | |
KR100617949B1 (en) | Pile Groups Construction Method of Weak Bedding Bone Using Caission | |
JP2004108142A (en) | Method for construction of a control type revetment | |
CN111455976A (en) | Construction method of self-setting mortar impervious wall by grooving method | |
CN111335263A (en) | Method for building artificial island | |
CN110144871A (en) | A kind of dark creek processing construction method | |
JPS61254720A (en) | Construction work of embankment | |
CN111305050B (en) | Protection process for existing piers on two sides in tunnel construction | |
JP2726611B2 (en) | How to set up an open caisson | |
CN109338909B (en) | Integral pier reinforcing structure and construction method thereof | |
CN108360532B (en) | Construction method of SMW construction method pile cantilever enclosure for foundation pit in soft soil area | |
CN114164726B (en) | Local deep excavation backfill structural roadbed and rapid construction method | |
JP2784314B2 (en) | How to set up an open caisson | |
JP2874906B2 (en) | Shaft construction method | |
CN114960730B (en) | Method and structure for building asphalt core wall dam base without foundation pit | |
JPH0470422A (en) | Open caisson method | |
JPH09125347A (en) | Building method of dam | |
KR200291370Y1 (en) | Concrete caisson structure for earth and sand guard of pier's basis | |
JP3387398B2 (en) | How to penetrate caisson foundation | |
CN110130372A (en) | A kind of construction method in prestress anchorage cable cofferdam | |
JPH1161775A (en) | Method for repair and improvement of harbor and river civil engineering structure | |
CN205804398U (en) | The ruggedized construction on sluice basis | |
JPS5944459B2 (en) | Construction method for offshore structures |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |