JPS6117651A - Concrete slab by in-site casting - Google Patents
Concrete slab by in-site castingInfo
- Publication number
- JPS6117651A JPS6117651A JP13639984A JP13639984A JPS6117651A JP S6117651 A JPS6117651 A JP S6117651A JP 13639984 A JP13639984 A JP 13639984A JP 13639984 A JP13639984 A JP 13639984A JP S6117651 A JPS6117651 A JP S6117651A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- embedded
- embedding
- embedded material
- concrete slab
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Underground Or Underwater Handling Of Building Materials (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
く技術分野〉
この発明は、現場I込みによるコンクリートスラブに関
する。さらに詳細にいえば、スラブを中空化するために
合成樹脂の発泡体等による埋込材を埋設した現場打込み
による中空コンクリートスラブに関する。DETAILED DESCRIPTION OF THE INVENTION Technical Field The present invention relates to a concrete slab constructed on-site. More specifically, the present invention relates to a hollow concrete slab cast on-site in which an embedded material such as a synthetic resin foam is embedded to make the slab hollow.
く背景及び従来技術〉
近年、集合住宅、一般ビル、QJili@の中高層の建
築物の施工については、現場打込みによる」ンクリート
スラブを形成して施工しており、スラブの軽量化、防音
、小梁の除去による室内空間の拡大、及び長大スパンの
確保を図るためにスラブを中空化することが広く行なわ
れている。中空化のための埋込材として鉄板を中空筒に
したもののほか、最近では合成樹脂発泡体による板状体
も用いられている。Background and Prior Art> In recent years, construction of apartment complexes, general buildings, and mid-to-high-rise buildings has been carried out by forming concrete slabs by pouring on-site, which has been used to reduce the weight of slabs, improve soundproofing, and improve the performance of small beams. It is widely practiced to make slabs hollow in order to expand indoor space by removing them and to ensure long spans. In addition to hollow cylinders made of iron plates as embedding materials, recently plate-shaped bodies made of synthetic resin foam have also been used.
ところが、前記鉄板を中空筒にしたものにてスラブ内の
非コンクリート部分の比率を高めるには、中空筒の配設
ピッチを狭間隔にすることが必要となる。従って上記中
空筒を埋込材とし・て現場施工する場合、先ず、下端筋
の組立工程を終了後、電気・給排水害の設備配管をなし
、次いで中空筒をセツティングし、さらに中空筒の上に
て上端筋の組立を終rさけ、中空筒の狭い間隔部分にて
に端と下端の筋へ梁形筋を構成するS形のスターシップ
を掛は合わせて配筋を終え、コンクリートを打設するも
のである。そしてS形の上記スターシップは中空筒ヒツ
ティング後であるため安定ざl!得るが取付けが面倒な
ため、中空筒のセツティング前に配筋させると、自立性
に乏しくて安定させ難く、中空筒のセツティング時に配
筋状態が崩れたりし易く、施工し難いものであった。し
か1)電気等の設備配管についても中空筒のセツティン
グ後に中空筒の長さ方向と直交する方向に配管しようと
してもスラブの上下層が薄肉のため鉄筋等が邪魔になり
、“Jf後的な配管が殆んど不可能で中空筒セツティン
グ前に配管せねばならぬものであった。However, in order to increase the ratio of non-concrete portions in the slab by forming hollow cylinders from the iron plates, it is necessary to narrow the pitch at which the hollow cylinders are arranged. Therefore, when performing on-site construction using the above-mentioned hollow cylinder as an embedded material, first, after completing the assembly process of the lower end reinforcement, install the equipment piping for electrical and water supply and drainage damage, then set the hollow cylinder, and then install the top of the hollow cylinder. Finished assembling the upper end reinforcements at , then hooked the S-shaped starships that make up the beam reinforcements to the end and lower end reinforcements in the narrow space of the hollow cylinder, finished the reinforcement arrangement, and poured concrete. It is something to do. And the S-type starship mentioned above is stable because it has been hit with a hollow cylinder! However, it is difficult to install, so if the reinforcement is arranged before setting the hollow cylinder, it is difficult to stabilize due to lack of independence, and the condition of the reinforcement tends to collapse when setting the hollow cylinder, making it difficult to install. Ta. However, 1) Regarding equipment piping such as electricity, even if you try to pipe in a direction perpendicular to the length direction of the hollow cylinder after setting the hollow cylinder, the upper and lower layers of the slab are thin, so reinforcing bars etc. will get in the way. It was almost impossible to install proper piping, and the piping had to be done before setting the hollow tube.
また、前記鉄板を中空筒にした埋込材の場合、鉄板の厚
さが薄いので外部からの衝撃等によって穴があいたり割
れが生じたりすることがある。従つてこれらの欠陥部か
らの雨水或は工事用水等が中空筒内に侵入し、貯留され
たものが建物完成後に、天井面に浸出する事故も希れに
は生じる可能性がある。Furthermore, in the case of an embedding material in which the iron plate is made into a hollow cylinder, the thickness of the iron plate is thin, so that holes or cracks may occur due to external impact or the like. Therefore, in rare cases, rainwater or construction water from these defective parts may enter the hollow cylinder, and the stored water may leak onto the ceiling surface after the building is completed.
一方、合成樹脂発泡体による埋込材を用いる場合にも、
スラブにおける非コンクリート部分の比率を所定に保持
しつつ充分な弾痕を確保すると共に埋込材の設置作業の
容易化並びに配筋される鉄筋とのコンビネーションの1
で、良好な形状が押込材として特に要求される現状であ
った。On the other hand, when using a synthetic resin foam embedding material,
It maintains the ratio of the non-concrete part of the slab to a specified level while ensuring sufficient bullet holes, and also facilitates the installation work of embedded materials and is one of the combinations with reinforcing bars to be placed.
Therefore, the current situation is that a good shape is particularly required as an indentation material.
く目的〉
この発明は上記問題点に鑑みてなされたものであり、施
工の容易化およびコスト低減化を図れる現場打ち込みに
よるコンクリートスラブを提供することを目的とする。Purpose of the Invention The present invention has been made in view of the above-mentioned problems, and an object of the present invention is to provide a concrete slab cast on-site that facilitates construction and reduces costs.
く構成〉
かかる目的を達成するためのこの発明の現場Iち込みに
よるコンクリートスラブの構成としては、現場打込みさ
れたコンクリート層内に埋込材用固定具と、該同定具に
て支承保持された合成樹脂発泡体からなる多角柱の埋込
材とが梁形筋の間に順次配設されてあり、多角柱の埋込
材の側面は梁形筋を構成するスターシップの垂直部と平
行な垂直面をなし、埋込材の上下面は上下水平な配力筋
と平行な水平面をなし、さらに埋込材は側面と上下面の
間に斜辺部を形成していることを特徴とするものである
。Structure> The structure of the concrete slab cast on-site according to the present invention to achieve the above object includes a fixing device for the embedded material and a support and holding device for the embedded material in the concrete layer poured on-site. Polygonal column embedded materials made of synthetic resin foam are sequentially placed between the beam reinforcements, and the sides of the polygonal column embedded materials are vertically parallel to the vertical part of the starship that makes up the beam reinforcement. The upper and lower surfaces of the embedded material form horizontal planes parallel to the vertically horizontal force distribution bars, and the embedded material is characterized in that a hypotenuse portion is formed between the side surface and the upper and lower surfaces. be.
〈実施例〉
次いでこの発明の実施例について図を参照しながら以ド
に説明する。<Example> Next, an example of the present invention will be described below with reference to the drawings.
(1)は合成樹脂発泡体例えばポリスブレン発泡体にて
形成された多角柱の埋込材であり、対角部に斜辺部(A
)を有する多角柱体で構成されている。(1) is a polygonal column embedding material made of synthetic resin foam, such as polysbrene foam, with oblique sides (A
) is composed of a polygonal prism.
上記埋込材(1)は支承部材(21)と固定部材(22
)とで構成される埋込材用1i!lI定A(21により
コンクリート層内部に強固に支承保持されている。即ち
、埋込材(1)は、脚(21a)有する支承部材(21
)上に載置されていると共に、支承部材(21)に起立
固定された固定部材(22)の挿通軸(22a)が、そ
の挿入部(11)に挿通されており、挿通軸(22a)
頭部に設けられた、刺し刃状の係止部(22c)を有す
る押えプレート(22b)によって上面が押えられて固
定されている。上記支承部材(21)の脚(21a)に
ついては、先端部が錆の発生により、直往上げの天井に
シミが生ずるのを防止する等の目的で防錆処理を施すの
が望ましい。The embedded material (1) includes a supporting member (21) and a fixing member (22).
) for embedding material consisting of 1i! The embedded material (1) is firmly supported and held inside the concrete layer by the support member (21) having legs (21a).
), and the insertion shaft (22a) of the fixing member (22), which is fixed upright on the support member (21), is inserted into the insertion portion (11), and the insertion shaft (22a)
The upper surface is pressed and fixed by a presser plate (22b) having a stabbing blade-like locking part (22c) provided on the head. As for the legs (21a) of the support member (21), it is desirable that the tips thereof be subjected to rust prevention treatment in order to prevent stains from forming on the directly raised ceiling due to rust.
この防錆処理の具体例としては、脚(21a)の先端に
合成樹脂のキャップ(21c)を被せたり、先 、端
に直接メッキ処理を施す場合がある(第2図参照)。Specific examples of this anti-rust treatment include covering the tips of the legs (21a) with synthetic resin caps (21c), or directly plating the tips and ends (see Figure 2).
そして、上記固定具(2)及び該固定具(2)によって
支承保持された埋込材(1)は、必要な鉄筋例えばド端
主筋(31)、下端配力筋(31’)、梁形筋を構成す
るスターラップ(32)、l:端主筋(33)、上端配
力jlW(33’)と共に現場打ちされたコンクリート
層内にて梁形筋の間に所定間隔毎に配設されており、多
角形の埋込材(1)の側面(B)はスターラップ(32
)の垂直部(32’)と平行な垂直面をなし、上下面(
C)(C’)は上下の水平な配力筋(33’)(31’
)と平行な水平面をなし、ざらに埋込材(1)は側面(
B)と上下部(C)(C’)の間に斜辺部(A)を形成
して、埋込材fl) (11相互間のスラブ梁状部(4
)には、埋込材(1)の斜辺部(A)にて上下に傾斜拡
開部(D)が構成されている。The fixing device (2) and the embedded material (1) supported and held by the fixing device (2) are equipped with necessary reinforcing steel such as do-end main reinforcement (31), lower-end distribution reinforcement (31'), beam-shaped Stirrups (32), l: which constitute the reinforcements, are placed at predetermined intervals between the beam-shaped reinforcements in the concrete layer cast on site, together with the main end reinforcements (33) and the upper end distribution jlW (33'). The sides (B) of the polygonal embedding material (1) are covered with stirrups (32
) forms a vertical plane parallel to the vertical part (32') of the upper and lower surfaces (
C) (C') is the upper and lower horizontal distribution bars (33') (31'
), and the rough embedded material (1) forms a horizontal plane parallel to the side surface (
A hypotenuse part (A) is formed between the upper and lower parts (C) and (C'), and the slab beam-like part (4
), an inclined widening part (D) is formed vertically at the oblique side part (A) of the embedding material (1).
このような傾斜拡開部(D)を構成すれば、スラブ梁状
部(4] [4)相互間が連続的なアーチ構造となるの
で、埋込材(1)上下部分のスラブ強度を補強し得て非
常に優れた性能を発揮できることになる。If such an inclined expansion part (D) is configured, a continuous arch structure will be formed between the slab beam parts (4) [4], thereby reinforcing the slab strength of the upper and lower parts of the embedded material (1). As a result, extremely excellent performance can be achieved.
次に上記構造のコンクリートスラブの施J法としては、
まず、敷設されたコンクリートパネル(P)上に、埋込
材(1)の端部、中間部、埋込材相互の境界部等の挿通
部(11)に対応させて支承部材(21)及び挿通軸(
22a)用の固定部材(23)を立設する(第4図およ
び第5図参照)。この固定部材(23)は、コンクリー
トパネル(P)に対接させる支持リング(23a)とこ
の支持リング(23a)の内径部途中まで螺合させて立
上げられた両ネジボルト(23b)で構成されている。Next, the J method for concrete slabs with the above structure is as follows:
First, on the laid concrete panel (P), support members (21) and Insertion shaft (
A fixing member (23) for 22a) is erected (see FIGS. 4 and 5). This fixing member (23) is composed of a support ring (23a) that is brought into contact with the concrete panel (P), and a double-threaded bolt (23b) that is screwed up halfway into the inner diameter of this support ring (23a). ing.
固定に際しては、内径部にネジを形成した支持リング(
23a)をコンクリートパネル(P)裏面側からボルト
(24) 、ワッシャ(25) 、ナツト(26)等を
用いて固定した後、支持リング(23a)上部に両ネジ
ボルト(23b)を螺合し、この直上に支承部材(21
)を配置し、そのL面の透孔(21b)に内径ネジを形
成した鍔付きスリーブ(27)を挿入して両ネジボルト
(23b)へ螺合し、これを締付けることによって行な
うものである(第2図参照)。When fixing, use a support ring (with a thread formed on the inside diameter).
After fixing 23a) from the back side of the concrete panel (P) using bolts (24), washers (25), nuts (26), etc., screw the double-threaded bolts (23b) onto the upper part of the support ring (23a), Directly above this is the support member (21
), insert a flanged sleeve (27) with an internal thread into the through hole (21b) on its L side, screw it onto both threaded bolts (23b), and tighten it ( (See Figure 2).
次に、挿通軸(22a)を[記鍔付きスリーブ(21)
に螺合して起立固定しく第4図参照)、埋込材(1)を
、その挿通部(11)内に挿通軸(22a)を挿入しつ
つ支承部材(21)上に載置する。そして、挿通軸(2
2a)の頭部に、刺し刃状の係止部(22G)を有する
押えプレート(22b)を挿入し、プツト(22d)で
締付けて埋込材(1)を固定する(第5図参照)。この
状態でコンクリ−1−を打設し、埋込材(1)および支
承部材(21)等をコンクリートで囲続すればすれば、
前述したコンクリートスラブを形成できることになる。Next, insert the insertion shaft (22a) into the flanged sleeve (21).
(see FIG. 4), and place the implant (1) on the support member (21) while inserting the insertion shaft (22a) into the insertion portion (11). Then, insert the insertion shaft (2
Insert the holding plate (22b) having a stabbing blade-like locking part (22G) into the head of 2a), and tighten it with the pins (22d) to fix the implant (1) (see Figure 5). . If concrete is poured in this state and the embedded material (1) and support member (21) are surrounded by concrete, then
This means that the concrete slab described above can be formed.
なお、上記において説明を省略したが、下端主筋(31
)および下端配力筋(31’)等の配筋は前記埋込材(
1)の固定作業中にJ5いて適時施すものである。さら
に係止部(22c)を右さない押えプレート(22b)
を使用しても実施可能である。Although the explanation was omitted above, the lower end main reinforcement (31
) and lower end distribution reinforcements (31') are arranged using the embedded material (
This is done at the appropriate time by J5 during the fixing work in step 1). Furthermore, the holding plate (22b) does not move the locking part (22c) to the right.
It can also be implemented using .
なお、施コ上、埋込材を支承させるための前記した組)
゛L構造については、固定部材(23) 、支承部材(
21) 、鍔付きスリーブ(27) 、両ネジボルト(
23b)および挿通軸(22a)を予め組立てて一体化
したものを使用するのが好ましい。In addition, for installation, the above-mentioned set for supporting the embedded material)
Regarding the L structure, the fixing member (23), the supporting member (
21), sleeve with flange (27), double threaded bolt (
23b) and the insertion shaft (22a) are preferably assembled and integrated in advance.
埋込材(1)を固定する固定部材(23)としては、例
えば第6図に示ずごとく、挿通軸(22a)の先端に軸
方向に複数分割された弾性変形可能な分割片(22e)
を構成し、この分割片(22e)を弾性変形させつつコ
ンクリートパネル(P)の穴部(P′)に挿入して先端
の逆止爪(22f)で抜脱防止を行なうもの、第7図に
示すごとく挿通軸(22a)先端にネジ釘(22g)或
はスクリュー釘を構成してコンクリートパネル(P)に
ネジ込むものが考えられるほか、第8図に示づごとく、
挿通軸(22a)先端に、軸方向に複数分割して外方へ
拡開可能とした分割片(22h)を螺合等で着脱自在に
禍成し、挿通軸(22a)と分離した一]記分割片(2
2h)をコンクリートパネル(P)の穴部(P′)に挿
入し、これをビン(22i)の打撃によって外方へ拡開
させて固定した後、挿通軸(22a)を螺合するもの等
積々のものが採用できる。As the fixing member (23) for fixing the implant (1), for example, as shown in FIG. 6, a plurality of elastically deformable divided pieces (22e) are provided at the tip of the insertion shaft (22a) in the axial direction.
This divided piece (22e) is elastically deformed and inserted into the hole (P') of the concrete panel (P), and the non-return claw (22f) at the tip prevents it from coming out, Fig. 7. As shown in Fig. 8, a screw nail (22g) or a screw nail formed at the tip of the insertion shaft (22a) and screwed into the concrete panel (P) is considered, as shown in Fig. 8.
At the tip of the insertion shaft (22a), a plurality of divided pieces (22h) which are divided in the axial direction and can be expanded outward are removably formed by screwing together, and are separated from the insertion shaft (22a).] Recording piece (2
2h) is inserted into the hole (P') of the concrete panel (P), expanded outward by the blow of the bottle (22i) and fixed, and then the insertion shaft (22a) is screwed into the hole, etc. Many things can be adopted.
また、埋込材(1)を載置する支承部材(21)として
も、図示したものに限定されず、コンクリートパネル(
P)上に埋込材(1)を浮かせて支承できるものであれ
ば種々の構造のものが採用できる。Further, the supporting member (21) on which the embedded material (1) is placed is not limited to the one shown in the figure, but a concrete panel (
P) Various structures can be adopted as long as they can support the embedded material (1) floating thereon.
さらに、埋込材(1)を形成する合成樹脂の発泡体とし
ては、前述したボリスヂレン発泡体のほか、ポリエチレ
ン、ポリプl]ピレン、ポリ塩化ビニル及びこれらを主
体とするコポリマー等から製造される発泡体をもって形
成したものも使用可能である。Furthermore, as the synthetic resin foam forming the embedding material (1), in addition to the aforementioned borisdylene foam, foams manufactured from polyethylene, polypropylene, polyvinyl chloride, copolymers mainly composed of these, etc. Those formed with a body can also be used.
く効果〉
以上のごとく構成されたこの発明による現場打込みによ
るコンクリートスラブによれば、埋込材用固定具と、合
成樹脂発泡体からなる多角柱の埋込材とが梁形筋の間に
順次配設されであり、多角柱の埋込材の側面は梁形筋を
構成するスターシップの垂直部と平行な垂直面をなして
いるので、従来の中空筒埋設の場合に比しコンクリート
スラブ中の非コンクリート部分をさほど少なくせずに埋
込材間の間隔を多くとり得て梁形筋を組み易くしており
、予めr場生産された安定的形状を有する梁形筋を埋込
材のセツティング前に設置しておくことも可能で、安定
した状態で梁形筋を設定し易くなる。また梁形筋の間へ
事後的に埋込材をセツティングする場合にも埋込材が軽
量な合成樹脂発泡体製でしかもその上下面が上手の水平
な配力筋と平行な水平面を有する安定形状ゆえ取扱いお
よびセツティングもし易いものである。さらに上記埋込
材はその側面と上下面の間に斜辺部を形成しているもの
ゆえ、スラブ梁状部は上下が傾斜拡開され、スラブ梁状
部相互間が連続的なアーヂ構造となり、スラブ強度を増
強でき、優れた性能を発揮できる。このため、よりY内
空間を広くできるほか、配筋作業も容易であってコンク
リートスラブのコスト低減に大ぎく貢献できることにな
る。According to the cast-in-place concrete slab of the present invention constructed as described above, the fixing device for the embedding material and the embedding material in the form of a polygonal column made of synthetic resin foam are successively placed between the beam reinforcements. The sides of the polygonal column embedding material form a vertical plane parallel to the vertical part of the starship that makes up the beam reinforcement, so compared to the case of conventional hollow tube embedding, the side surface of the polygonal column embedding material is It is possible to increase the spacing between the embedded materials without significantly reducing the non-concrete parts, making it easier to assemble beam reinforcements. It is also possible to install it before setting, making it easier to set beam bars in a stable state. In addition, when setting the embedded material between the beam bars afterwards, the embedded material is made of lightweight synthetic resin foam, and its upper and lower surfaces have horizontal surfaces parallel to the horizontal distribution bars. Due to its stable shape, it is easy to handle and set up. Furthermore, since the above-mentioned embedded material forms a hypotenuse between its side surface and the upper and lower surfaces, the slab beam-like portions are expanded at an angle at the top and bottom, and the slab beam-like portions form a continuous arch structure. The slab strength can be increased and excellent performance can be demonstrated. Therefore, not only can the space inside the Y be made wider, but also the reinforcing work is easier, which greatly contributes to reducing the cost of concrete slabs.
なお、この発明では埋込材として合成樹脂発泡体からな
るものを構成しているので、電気等の設備配管について
は埋込材のセツティング後であっても、必要に応じて埋
込材の一部を切欠或は穿孔することにより、上下が薄肉
部となる必要コンクリート断面を保持しつつ自由に配管
することができる。また埋込材の切欠および穿孔の方向
を斜めにすることもできるなど、最短距離で自由に配管
することができるので、現場打込みによるコンクリート
スラブの施工上配管上の節約にも役立つ。In addition, since this invention uses a synthetic resin foam as the embedding material, the embedding material can be changed as necessary even after the embedding material is set for electrical equipment piping. By notching or perforating a portion, piping can be freely installed while maintaining the necessary concrete cross section with thin walls on the top and bottom. In addition, the direction of the notches and holes in the embedded material can be made diagonally, allowing piping to be installed over the shortest possible distance, which is useful for saving on piping during construction of concrete slabs cast on-site.
さらに埋込材が合成樹脂発泡体ゆえに雨水或は工事用水
が埋込材内に貯留したりする不都合も併せ無くなり好都
合となる。Furthermore, since the embedding material is made of synthetic resin foam, the inconvenience that rainwater or construction water may accumulate in the embedding material is also eliminated, which is advantageous.
図はこの発明の実施例を示すものであり、第1図は断面
図、第2図は支承部材の取付は状態を示す正面図、第3
図は埋込材用固定具の要部分解斜視図、第4図及び第5
図は施工途中を示す斜視図、第6図〜第8図は他の実施
例を示す断面図である。
(1)・・・埋込材、(′2J・・・埋込材用固定具、
(21)・・・支承部材、(23)・・・固定部材、(
22a)・・・挿通軸、(31)・・・を端止筋、(3
1’)・・・下端配力筋、(32)・・・スターラップ
、(33)・・・上端主筋、(33’)・・・上端配力
筋、(4)・・・スラブ梁状部、(A)・・・埋込材の
斜辺部、(B)・・・側面、(C)(C’)・・・上下
面、(D)・・・傾斜拡開部、(P)・・・コンクリー
トパネル。The figures show an embodiment of the present invention, and FIG. 1 is a sectional view, FIG. 2 is a front view showing how the support member is installed, and FIG.
The figures are exploded perspective views of the main parts of the fixing device for embedded materials, Figures 4 and 5.
The figure is a perspective view showing the construction in progress, and FIGS. 6 to 8 are sectional views showing other embodiments. (1)...embedding material, ('2J...fixing device for embedded material,
(21)...Supporting member, (23)...Fixing member, (
22a)...insertion shaft, (31)... is end stop muscle, (3
1')...Bottom distribution reinforcement, (32)...Stirrup, (33)...Top main reinforcement, (33')...Top distribution reinforcement, (4)...Slab beam shape (A)...Hytenuse part of the embedding material, (B)...Side surface, (C) (C')...Top and bottom surfaces, (D)...Slanted expansion part, (P) ...Concrete panel.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP13639984A JPS6117651A (en) | 1984-06-30 | 1984-06-30 | Concrete slab by in-site casting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP13639984A JPS6117651A (en) | 1984-06-30 | 1984-06-30 | Concrete slab by in-site casting |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS6117651A true JPS6117651A (en) | 1986-01-25 |
JPH0241613B2 JPH0241613B2 (en) | 1990-09-18 |
Family
ID=15174252
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP13639984A Granted JPS6117651A (en) | 1984-06-30 | 1984-06-30 | Concrete slab by in-site casting |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6117651A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01163047A (en) * | 1987-11-27 | 1989-06-27 | Toyo Mach & Metal Co Ltd | Bead welding foam molding machine |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5895408U (en) * | 1981-12-22 | 1983-06-28 | 斉藤 武雄 | Beamless slab structure |
-
1984
- 1984-06-30 JP JP13639984A patent/JPS6117651A/en active Granted
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5895408U (en) * | 1981-12-22 | 1983-06-28 | 斉藤 武雄 | Beamless slab structure |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01163047A (en) * | 1987-11-27 | 1989-06-27 | Toyo Mach & Metal Co Ltd | Bead welding foam molding machine |
JPH0622915B2 (en) * | 1987-11-27 | 1994-03-30 | 東洋機械金属株式会社 | Bead fusion foam molding machine |
Also Published As
Publication number | Publication date |
---|---|
JPH0241613B2 (en) | 1990-09-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20080001711A (en) | The construction method of retaining wall | |
US8006451B2 (en) | Building system and method of constructing a multi-walled structure | |
KR101019588B1 (en) | Device for preventing buoyance in hollow concrete slab | |
JPH11172820A (en) | Form method and apparatus for constructing foamed synthetic resin plate drive wall | |
US20050016114A1 (en) | Masonry block anchor bolt assembly | |
JPS6117651A (en) | Concrete slab by in-site casting | |
JP2004003168A (en) | Fixing metal fitting of concrete form | |
KR200249907Y1 (en) | Device for adjusting level of a concrete form | |
KR200241654Y1 (en) | Fastening device for concrete forms | |
KR200321092Y1 (en) | Constructing mould installation | |
KR200238510Y1 (en) | Spacer supporting steel in steel concrete used in construction | |
JPH08144581A (en) | Foundation structure for fence | |
JP4574736B1 (en) | Formwork apparatus and concrete frame construction method using the same | |
JP3292860B2 (en) | Precast retaining wall insert and its manufacturing method | |
KR19990042948A (en) | Support structure of slab for high rise apartment | |
JPS6128804Y2 (en) | ||
JP2002167711A (en) | Treatment method and treatment structure of bridge girder end part and buried form for bridge girder stopper | |
KR200197017Y1 (en) | Slipper type anchoring device for the post tensioning wire | |
JPS6117652A (en) | Construction of concrete slab | |
KR100413365B1 (en) | A fixing structure of a metal's sheeting panel | |
JP2719648B2 (en) | Pillar foundation structure and pillar pier foundation method | |
JPS59177445A (en) | Semi-pc slab construction method and semi-pc panel used therein | |
JPH08260484A (en) | Connecting structure for top board footing | |
JP2024089731A (en) | Installation method of precast wainscot | |
KR200186308Y1 (en) | Crossing column supporter |