JPS61146968A - Construction of reinforced concrete pillar - Google Patents

Construction of reinforced concrete pillar

Info

Publication number
JPS61146968A
JPS61146968A JP26548884A JP26548884A JPS61146968A JP S61146968 A JPS61146968 A JP S61146968A JP 26548884 A JP26548884 A JP 26548884A JP 26548884 A JP26548884 A JP 26548884A JP S61146968 A JPS61146968 A JP S61146968A
Authority
JP
Japan
Prior art keywords
shaped
column
members
concrete
hook
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP26548884A
Other languages
Japanese (ja)
Other versions
JPH0376384B2 (en
Inventor
次彦 吉野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP26548884A priority Critical patent/JPS61146968A/en
Publication of JPS61146968A publication Critical patent/JPS61146968A/en
Publication of JPH0376384B2 publication Critical patent/JPH0376384B2/ja
Granted legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は鉄筋コンクリート造構造物における柱の施工方
法に係るものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for constructing columns in reinforced concrete structures.

(従来の技術)及び(発明が解決しようとする問題点)
鉄筋コンクリートのプレハブラーメンは極々の工法が開
発されているか、一般に一部材abの重量が大きく、大
型の揚重機が必要であった。
(Prior art) and (Problem to be solved by the invention)
Prefabricated reinforced concrete frames require extremely advanced construction methods, and the weight of each member AB is generally large, requiring a large lifting machine.

また重tt−軽減する方法として、断面の一部をプレキ
ャスト化する型枠兼用部材も開発されているが、スラブ
版、溝凰梁部材のように、開動向の部材は比較的製作が
容易であるのに対して、柱部材のように中央部を空洞に
するような閉断面部材は製作か困難であった。
In addition, as a method to reduce the weight, a member that doubles as a formwork has been developed by precasting a part of the cross section, but members that open in an open direction, such as slab plates and groove and beam members, are relatively easy to manufacture. On the other hand, it was difficult to manufacture closed-section members with a hollow center, such as pillar members.

(問題点を解決するための手段) 本発明はこのような問題点を解決するために提案された
もので、躯体内に柱主筋の一部及び同主筋を囲繞する帯
筋を内蔵し、且つ同帯筋の躯体7279部からの突出端
部をフック状に曲成してなる複数の溝型またはL型プレ
キャストコンクリート部材によって、相隣る部材の各帯
筋のフック状部が交叉するように方形断面部材を組立て
、前記帯筋のフック状部の交叉部に柱主筋を貫挿したの
ち、前記各溝型またはLmプレキャストコンクリート部
材内に後打ちコンクリートを一体に打設することを特徴
とする鉄筋コンクリート柱の施工方法に係るものである
(Means for Solving the Problems) The present invention was proposed in order to solve these problems, and includes a part of the main column reinforcement and a tie bar surrounding the main reinforcement in the frame, and A plurality of groove-shaped or L-shaped precast concrete members are formed by bending the protruding ends of the 7279 parts of the frame into hook shapes, so that the hook-shaped parts of each of the ties of adjacent members intersect. After assembling the rectangular cross-section members and inserting the main column reinforcement into the intersection of the hook-shaped portions of the stirrups, post-cast concrete is integrally poured into each of the groove-shaped or Lm precast concrete members. This relates to the method of constructing reinforced concrete columns.

(作用) 本発明においては方形断面の鉄筋コンクリート柱を捧、
または狐に分割した溝型またはL型のプレキャストコン
クリート部材を予め製作するとともに、同部材に柱主筋
及び同柱主筋を囲繞する帯筋を内蔵し、且つ同帯筋の前
記部材7ランジ部の端部からの突出端部をフック状に曲
成し、前記溝型またはL型のプレキャストコンクリート
部材によって方形断面の部材を組立てるとともに、相隣
る前記プレキャストコンクリート部材の各帯筋突出端の
フック部を交叉せしめ、同交叉部に柱主筋を挿貫したの
で同柱主筋の大柄作用によって帯筋が拘束され、鉄筋コ
ンクリート柱の補強筋が所定位置に確固とセットされる
(Function) In the present invention, a reinforced concrete column with a rectangular cross section is provided,
Alternatively, a groove-shaped or L-shaped precast concrete member divided into sections is manufactured in advance, and the main reinforcement of the column and a tie bar surrounding the main reinforcement of the column are built into the member, and the end of the flange part of the member 7 of the tie bar is incorporated. The protruding ends from the sections are bent into hook shapes, and a member with a rectangular cross section is assembled using the groove-shaped or L-shaped precast concrete members, and the hook parts of each of the protruding ends of the stirrups of the adjacent precast concrete members are bent. Since the main reinforcing bars of the columns are intersected and inserted through the intersection, the tie bars are restrained by the large action of the main reinforcing bars of the columns, and the reinforcing bars of the reinforced concrete columns are firmly set in the predetermined positions.

しかるのち前記各プレキャストコンクリート部材によっ
て形成された方形断面の部材の中央空洞部に後打ちコン
クリートを打設し、同打設コンクリートを前記各プレキ
ャストコンクリート部材と一体化することによって、鉄
筋コンクリート柱が構成される。
Thereafter, a reinforced concrete column is constructed by pouring post-cast concrete into the central cavity of a member having a rectangular cross section formed by each of the precast concrete members, and integrating the poured concrete with each of the precast concrete members. Ru.

(発明の効果) 本発明によればこのように予め製作された溝型またはL
型のプレキャストコンクリート部材によって方形断面の
柱外郭部材を組立て、前記各プレキャストコンクリート
部材を型枠として、その内部空洞部に後打ちコンクリー
トを打設して、同打設コンクリートと前記各プレキャス
トコンクリート部材とが一体化された鉄筋コンクリート
柱を施工するようにしたので施工が簡単であシ、また前
記各プレキャストコンクリート部材が方形断面を分割し
た溝型、またはL聖断面に形成されているので軽量で、
大型揚重機を必要とせず、施工が簡略化される。
(Effect of the invention) According to the present invention, the groove type or L
A column outer frame member with a rectangular cross section is assembled using precast concrete members of the mold, and using each of the precast concrete members as a formwork, post-cast concrete is poured into the internal cavity, and the cast concrete and each of the precast concrete members are combined. Since the reinforced concrete columns are integrated into one piece, construction is easy, and since each of the precast concrete members is formed into a groove shape with a divided rectangular cross section or an L-shaped cross section, it is lightweight.
Construction is simplified as large lifting equipment is not required.

また前記各プレキャストコンクリート部材には柱主筋の
一部と、同柱主筋を囲繞する帯筋が内蔵され、且り同帯
筋の部材フランジの端部突出部がフック状に曲成され、
同プレキャストコンクリート部材組立時において前記フ
ック状部が交叉され、この交叉部に柱主筋が貫挿される
ので、同柱主筋の大柄作用によって帯筋が拘束され、柱
主筋及び帯筋よ多構成された柱補強筋が所定位置に確固
と配筋され、構造的に信頼性のある鉄筋コンクリート柱
が施工されるものである。
Further, each of the precast concrete members has a built-in part of the column main reinforcement and a tie bar surrounding the column main reinforcement, and the protruding end portion of the member flange of the tie bar is bent into a hook shape,
When assembling the precast concrete member, the hook-shaped parts intersect and the column main reinforcement is inserted through this intersection, so the tie bars are restrained by the large action of the column main reinforcement, resulting in a multi-structured structure including the column main reinforcement and tie bars. Column reinforcing bars are firmly placed in designated positions, and structurally reliable reinforced concrete columns are constructed.

また従来工法ではプレキャスト柱と耐震壁との接合部に
難点があったが、本発明においては、耐震壁の厚みだけ
前記プレキャストコンクリート部材のフランジ部分を短
かく製作し、相隣るフランジ部分間の耐震壁端部と、後
打ち柱コンクIJ −一部とを一体化し、構造的に信頼
性の高い耐震壁と柱との接合部を施工できる。
In addition, in the conventional construction method, there was a difficulty in the joint between the precast column and the shear wall, but in the present invention, the flange part of the precast concrete member is shortened by the thickness of the shear wall, and the gap between the adjacent flange parts is shortened by the thickness of the shear wall. By integrating the end of the shear wall and part of the post-cast concrete column IJ, it is possible to construct a structurally reliable joint between the shear wall and the column.

(実施例) 以下本発明を図示の実施例について説明する。(Example) The present invention will be described below with reference to the illustrated embodiments.

囚は鉄筋コンクリート柱の中央部を空洞とした方形部材
を凭分割した溝型のプレキャストコンクリート部材で、
予め柱主筋(1)の一部、及び同柱主筋(1)を囲繞す
る帯筋(2)カ埋設され、同帯筋(2)における前記部
材(4)のフランジ部端部からの突出部が90°曲成さ
れ、フック状部(2α)が形成されている。
The structure is a groove-shaped precast concrete member made by dividing a rectangular member with a hollow center part of a reinforced concrete column into canopies.
A part of the column main reinforcement (1) and the tie reinforcement (2) surrounding the column main reinforcement (1) are buried in advance, and a protrusion from the flange end of the member (4) in the column reinforcement (2) is provided. is bent at 90° to form a hook-shaped portion (2α).

(第1図参照) 而して一双の前記溝型のプレキャストコンクリート部材
図(Alを相対する帯筋(2)のフック状部(2α)が
交叉するように方形枠状に組立て、同フック状部(2α
)の交叉部に柱主筋(1′)を貫挿し、同柱主筋(1′
)によって帯筋(2)を拘束する。
(See Fig. 1) A diagram of a pair of groove-shaped precast concrete members (Al is assembled into a rectangular frame shape so that the hook-shaped parts (2α) of the opposing ties (2) intersect, and the same hook-shaped Part (2α
), insert the column main reinforcement (1') into the intersection of the column main reinforcement (1'
) to restrain the stirrup (2).

しかるのち前記両プレキャストコンクリート部材(A)
CAJ間に後打ちコンク!J−)(B)’z打設して向
後打ちコンクリート(aと前記各プレキャストコンクリ
ート部材図とを一体化して、鉄筋コンクリート柱を施工
する。(第2図参照) 第3図は鉄筋コンクリート柱の両側に耐震壁が配設され
る場合を示し、この場合、前記両プレキャストコンクリ
ート部材(A)の各フランジ部分を耐震壁(C)の厚さ
部分だけ短かくし、同耐震壁(C)と後打ちコンクリー
トCB)との一体化を図るものである。
After that, both precast concrete members (A)
After-hit conch between CAJ! J-) (B)'z Place and post-cast concrete (a and each precast concrete member diagram above are integrated to construct a reinforced concrete column. (See Figure 2) Figure 3 shows both sides of the reinforced concrete column. In this case, each flange part of both precast concrete members (A) is shortened by the thickness of the shear wall (C), and the same shear wall (C) and post-casting are installed. This is intended to integrate with concrete CB).

第4図は鉄筋コンクリート柱に、4方向に亘って耐震壁
(C)が取付けられる場合を示し、この場合、L型のプ
レキャストコンクリート部材(A′)が使用されるもの
である。
FIG. 4 shows a case where shear walls (C) are attached to a reinforced concrete column in four directions, and in this case, an L-shaped precast concrete member (A') is used.

なお前記プレキャストコンクリート部材(A) (A’
)に内蔵された柱主筋(1)には、第5図に示すように
、柱脚部にスプライススリーブ(3)が取付けられ、同
スリーブ(3)を介して、上下の前記プレキャストコン
クリート部材(AJ (A’)の柱主筋(1)が接合さ
れるものでおる。
Note that the precast concrete member (A) (A'
As shown in Fig. 5, a splice sleeve (3) is attached to the column base part of the column main reinforcement (1) built in the column main reinforcement (1), and the upper and lower precast concrete members ( The column main reinforcement (1) of AJ (A') is to be joined.

なお第5図中、(1りは前記コンクリート部材囚(A′
)における柱主筋(1)の突出端部(D)は梁、(E)
はスラブである。
In Fig. 5, (1) is the concrete member (A'
), the protruding end (D) of the column main reinforcement (1) is a beam, (E)
is a slab.

以上本発明を実施例について説明したが、本発明は勿論
このような実施例にだけ局限されるものではなく、本発
明の精神を逸脱しない範囲内で種々の設計の改変を施し
うるものである。
Although the present invention has been described above with reference to embodiments, the present invention is, of course, not limited to such embodiments, and can be modified in various ways without departing from the spirit of the present invention. .

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の方法に使用される溝型プレキャストコ
ンクリート部材の斜面図、第2図乃至第4図は夫々本発
明の方法によって施工された鉄筋コンクリート柱の横断
平面図、第5図はその立面図である。 囚(A′)・・・プレキャストコンクリート部材、(B
)・・・後打ちコンクリート、(1) (1’)・・・
柱主筋、(2)・・・帯筋、(2α)・・・フック状部 代理人 弁理士 岡 本 重 文 外3名 く1 く1 くl
FIG. 1 is a slope view of a channel-type precast concrete member used in the method of the present invention, FIGS. 2 to 4 are cross-sectional plan views of reinforced concrete columns constructed by the method of the present invention, and FIG. It is an elevational view. Prisoner (A')...Precast concrete member, (B
)...Post-cast concrete, (1) (1')...
Column main reinforcement, (2)...Birth bar, (2α)...Hook-like part Agent Patent attorney Shige Okamoto 3 people outside the text

Claims (1)

【特許請求の範囲】[Claims] 躯体内に柱主筋の一部及び同主筋を囲繞する帯筋を内蔵
し、且つ同帯筋の躯体フランジ部からの突出端部をフッ
ク状に曲成してなる複数の溝型またはL型プレキャスト
コンクリート部材によつて、相隣る部材の各帯筋のフッ
ク状部が交叉するように方形断面部材を組立て、前記帯
筋のフック状部の交叉部に柱主筋を貫挿したのち、前記
各溝型またはL型プレキャストコンクリート部材内に後
打ちコンクリートを一体に打設することを特徴とする鉄
筋コンクリート柱の施工方法。
A plurality of groove-shaped or L-shaped precasts made by incorporating a part of the main column reinforcement and a tie bar surrounding the main bar in the frame, and bending the protruding end of the tie bar from the frame flange into a hook shape. Assemble the rectangular cross-section members using concrete members so that the hook-shaped parts of each of the stirrups of adjacent members intersect, and after inserting the column main reinforcement into the intersection of the hook-shaped parts of the stirrups, each of the above-mentioned A method for constructing a reinforced concrete column, characterized by integrally pouring post-cast concrete into a groove-shaped or L-shaped precast concrete member.
JP26548884A 1984-12-18 1984-12-18 Construction of reinforced concrete pillar Granted JPS61146968A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26548884A JPS61146968A (en) 1984-12-18 1984-12-18 Construction of reinforced concrete pillar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26548884A JPS61146968A (en) 1984-12-18 1984-12-18 Construction of reinforced concrete pillar

Publications (2)

Publication Number Publication Date
JPS61146968A true JPS61146968A (en) 1986-07-04
JPH0376384B2 JPH0376384B2 (en) 1991-12-05

Family

ID=17417873

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26548884A Granted JPS61146968A (en) 1984-12-18 1984-12-18 Construction of reinforced concrete pillar

Country Status (1)

Country Link
JP (1) JPS61146968A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01174735A (en) * 1987-12-28 1989-07-11 Fujita Corp Construction of framework member in precast rc framework structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01174735A (en) * 1987-12-28 1989-07-11 Fujita Corp Construction of framework member in precast rc framework structure

Also Published As

Publication number Publication date
JPH0376384B2 (en) 1991-12-05

Similar Documents

Publication Publication Date Title
JP3333786B2 (en) Prefabricated piers and concrete blocks for piers
JP3333787B2 (en) Prefabricated bridge pier
JPS61146968A (en) Construction of reinforced concrete pillar
JPS6134539B2 (en)
JP2759009B2 (en) Precast concrete wall column joining method
JP2917159B2 (en) Column, beam joining method
JPH0350846B2 (en)
JPH0326738B2 (en)
JPH06264414A (en) Prefabrication method of bridge pier and bridge pier concrete block
JPS6198870A (en) Construction method of precast reinforced concrete earthquake-proof wall
JPS62178634A (en) Framework construction method of structure
JPH02261145A (en) Method for setting girder and joist slub
JPH0444550A (en) Semi-precast rc building
JPH0280746A (en) Precast beam
JPH10152887A (en) Precast-concrete-made form
JPH03125735A (en) Structure for connection of column and beam
JP3505662B2 (en) Precast concrete beam and method of using the beam
JP2978011B2 (en) U-shaped beam formwork and method of constructing beam and beam joint using the same
JPS62121249A (en) Construction of pillar/beam connection part
JPS60208534A (en) Concrete building
JPH0366852A (en) Construction method for complex structure of precast reinforced concrete column and steel beam
JPH0414536A (en) Construction of column using thin precast part serving as structural part
JPH02296948A (en) Construction method of reinforced concrete construction slab
JPS59228554A (en) Precast small beam and construction of slab structure using the same
JPH0893102A (en) Hollow pc bearing wall, its production and method of constructing bearing wall by use of the hollow pc bearing wall

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees