JPS6053137B2 - Embankment construction method - Google Patents

Embankment construction method

Info

Publication number
JPS6053137B2
JPS6053137B2 JP4566282A JP4566282A JPS6053137B2 JP S6053137 B2 JPS6053137 B2 JP S6053137B2 JP 4566282 A JP4566282 A JP 4566282A JP 4566282 A JP4566282 A JP 4566282A JP S6053137 B2 JPS6053137 B2 JP S6053137B2
Authority
JP
Japan
Prior art keywords
net
embankment
covering
earth
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP4566282A
Other languages
Japanese (ja)
Other versions
JPS58164822A (en
Inventor
靖久 徳原
邦光 山田
昌彦 坂口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP4566282A priority Critical patent/JPS6053137B2/en
Publication of JPS58164822A publication Critical patent/JPS58164822A/en
Publication of JPS6053137B2 publication Critical patent/JPS6053137B2/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams

Description

【発明の詳細な説明】 本発明は盛土堤体の前面に土留めを行ないつつ逐次各層
の堤体を形成する盛土堤体構築工法に関するものである
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing an embankment body in which each layer of embankment body is sequentially formed while retaining the earth in front of the embankment body.

従来堤体を構築する場合にはコンクリート、間知石また
はブロック等で堤体の前面に士留めを行ないながら併わ
せて盛土を行なつている。
Conventionally, when building an embankment, the front of the embankment is secured with concrete, interstitial stones, blocks, etc., and at the same time, embankment is carried out.

しカルこのような構築工法は次のような欠点を有するも
のであつた。
However, this construction method had the following drawbacks.

〈イ〉 提体前面を被覆するコンクリート擁壁は独立の
構造ではなく、一体でかつ剛体の構造物として構築され
る。
<B> The concrete retaining wall covering the front of the structure will not be an independent structure, but will be constructed as an integral and rigid structure.

従つて地盤の沈下時には沈下に追従できずにキレツやク
ラック等を発生する場合がある。
Therefore, when the ground subsides, it may not be able to follow the subsidence, resulting in breaks, cracks, etc.

〈口〉 盛土作業と土留め作業を交互に行なわなければ
ならず施工性が悪い。〈ハ〉 施工性が悪いため工期が
長くなりかつ経費高となる。また最近では土砂とその中
に抵抗体として埋め込まれた帯状のストリップとの摩擦
力を利用して土留壁を構築するいわゆるテールアルメ工
法が利用されている。
<Entrance> Embankment work and earth retaining work must be carried out alternately, resulting in poor construction efficiency. 〈C〉 Due to poor workability, the construction period will be long and costs will be high. Recently, the so-called Terre Alme construction method has been used to construct earth retaining walls using the frictional force between earth and sand and strips embedded therein as resistors.

しカルこの工法も次のような欠点を有する。This construction method also has the following drawbacks.

〈イ> プレキヤスト部材の組み合わせによつて被覆体
を形成するので多少の変形には順応できるが、地盤の沈
下に対しては完全に追従できない。〈口〉 プレキヤス
ト部材やストリップ材をコンクリートや鋼板で構成する
ため運搬架設が困難な場合がある。
<A> Since the covering is formed by a combination of precast members, it can adapt to some deformation, but it cannot completely follow the subsidence of the ground. <Exposure> Because precast members and strip materials are constructed of concrete or steel plates, transporting and erecting them may be difficult.

〈ハ〉 施工管理上、ストリップ材の敷き込み、スキン
材とストリップ材の連結、スキン材と接する部分の盛土
の転圧・締固め作業はかなりの熟練技術を必要とする。
本発明は以上説明した従来の盛土堤体構築工法の欠点を
改善するためになされたもので、施工性、経済性に優れ
かつ地盤が沈下した場合でも堤体の安定を維持すること
のできる盛士堤体構築工法を提供することを目的とする
。次に実施例について説明する。
<C> In terms of construction management, the laying of strip materials, the connection of skin materials and strip materials, and the rolling and compaction of the embankment in contact with the skin materials require considerable skill.
The present invention has been made in order to improve the drawbacks of the conventional embankment construction method described above, and is a embankment that is superior in construction efficiency and economical efficiency, and is capable of maintaining the stability of the embankment even when the ground subsides. The purpose is to provide a body construction method. Next, an example will be described.

〈イ〉 全体の構成 本発明の盛土堤体は被覆ネット1、抵抗ネット2および
連結籠3で構成するが以下各ネットについて説明する。
<A> Overall configuration The embankment body of the present invention is composed of a covering net 1, a resistance net 2, and a connecting cage 3, and each net will be explained below.

く口〉 被覆ネット被覆ネット1は第1図に示すように
強度および柔軟性に優れた帯状の網であり、例えば格子
状や亀甲状または菱形状のような形状の網目を有するも
のを用いる。
As shown in FIG. 1, the covering net 1 is a band-shaped net having excellent strength and flexibility, and has, for example, a grid, hexagonal, or diamond-shaped mesh.

また被覆ネット1は後述するように盛土の前面を被覆し
て土留めを行なうものであるため、土砂の粒径を考慮し
て土砂の流出を阻止できる程度の網目を有するものを使
用する。
Further, since the covering net 1 is used to cover the front surface of the embankment and retain the earth, as will be described later, a net having a mesh size sufficient to prevent the outflow of the earth and sand is used in consideration of the grain size of the earth and sand.

〈口〉 抵抗ネット 抵抗ネット2は前記被覆ネット1と同様な帯状の網であ
る。
<Exposure> Resistance net The resistance net 2 is a belt-shaped net similar to the covering net 1 described above.

抵抗ネット2は強度および柔軟性に優れた例えば合成繊
維や鋼線などで構成する網を使用する。
The resistance net 2 uses a net made of, for example, synthetic fiber or steel wire, which has excellent strength and flexibility.

抵抗ネット2の網目の大きさは被覆ネット1のような制
限はないが土砂中での排水に支障を起こさない程度の大
きさのものを使用する。また抵抗ネット2と被覆ネット
1は同一の網目を有するロール状の網を適宜な長さで切
断し形成することも可能である。
The size of the mesh of the resistance net 2 is not limited as in the case of the covering net 1, but a size that does not interfere with drainage in the earth and sand is used. Further, the resistance net 2 and the covering net 1 can also be formed by cutting a rolled net having the same mesh into appropriate lengths.

〈ハ〉 連結籠 連結籠3も適宜の網目、長さ巾を有し一定の強度をもつ
た網体てあるが、その両端部に爪31を立設する。
<C> Connecting basket The connecting basket 3 is also a mesh body having an appropriate mesh size, length and width, and a certain strength, and claws 31 are provided at both ends thereof.

網目は格子状のものでも、斜材を入れて引張力を均等に
伝達し得るよう構成したものでもよい。
The mesh may be in the form of a lattice, or it may be constructed by inserting diagonal members so that tensile force can be transmitted evenly.

この連結籠3はその爪31を被覆ネット1と抵抗ネット
2に各々係合した後折り曲げ両ネット1,2を連結する
連結具である。〈二〉 土留定規土留定規4,5は合成
樹脂、鋼板、合板等で構成する板体をL字形またはT字
形に組み合わせて形成する定規である。
This connecting cage 3 is a connecting tool that connects the nets 1 and 2 by engaging the claws 31 with the covering net 1 and the resistance net 2, respectively, and then folding them. <2> Earth retaining ruler The earth retaining rulers 4 and 5 are rulers formed by combining plates made of synthetic resin, steel plate, plywood, etc. into an L-shape or T-shape.

この土留定規4,5は盛土堤体の前面に配置さ.れ、盛
土作業の際に土砂の崩壊を防止と堤体の前面の整形を目
的とするものである。
These earth retaining rulers 4 and 5 are placed in front of the embankment body. The purpose is to prevent earth and sand from collapsing during embankment work and to shape the front surface of the embankment body.

従つて土留定規4,5の組み合せの角度は直角に限定す
る必要はなく構築される堤体の前面の傾斜に等しい角度
に設定した定規を形成し使用する−ことができる。
Therefore, the angle of the combination of the earth retaining rulers 4 and 5 need not be limited to a right angle, and a ruler set at an angle equal to the slope of the front surface of the embankment body to be constructed can be formed and used.

次に施工法について説明する。Next, the construction method will be explained.

くイ〉 抵抗ネットの敷設(第3図) 床均しを終えた基盤G上の所定の位置に十分な長さを有
する前記構造の抵抗ネット2を敷設する。
Laying the resistance net (Fig. 3) The resistance net 2 having the above structure and having a sufficient length is laid at a predetermined position on the base G after leveling the floor.

次に敷説された抵抗ネット2の端部近くには第3図に示
すような部分置土を行ない抵抗ネット2の仮抑えを行な
う。
Next, partial soil is placed near the end of the laid resistance net 2 as shown in FIG. 3 to temporarily hold the resistance net 2 in place.

く口〉 被覆ネットの敷設 部分置土によつて仮抑えをされた抵抗ネット2の一端に
は連結籠3を介して被覆ネット1を連結する。
Entrance> The covering net 1 is connected via a connecting cage 3 to one end of the resistance net 2, which has been temporarily held down by the soil where the covering net is laid.

すなわち連結籠3の爪31群を両ネット1,2の端部に
係合させた後、この爪31を内側に折り曲げて両ネット
1,2を連結する。
That is, after the group of claws 31 of the connecting basket 3 is engaged with the ends of both the nets 1 and 2, the claws 31 are bent inward to connect both the nets 1 and 2.

なお第1層においては抵抗ネット2と被覆ネット1をあ
らかじめ連結しておくこともできる。
Note that in the first layer, the resistance net 2 and the covering net 1 may be connected in advance.

門〈ハ〉 盛土材の巻き出し盛土の法面子定位置にL字
形断面を有する土留定規4を設置する。
Gate <C> An earth retaining ruler 4 having an L-shaped cross section is installed at a fixed position on the slope of the embankment where the embankment material is rolled out.

土留定規4は地盤Gと被覆ネット1の間に挿入するよう
に設置することによつて、4法面の位置1と形状の規制
、◎巻き出し土砂の崩壊防止とを達成できる。
By installing the earth retaining ruler 4 so as to be inserted between the ground G and the covering net 1, it is possible to regulate the position 1 and shape of the 4 slopes, and to prevent collapse of the rolled-out earth and sand.

次に部分置土の前面及び背面方向には所定の盛土高さに
遂次土砂の巻き出しを行ない、地盤G上に露出している
ネットを埋設し、転圧して第1層A1を構築する。
Next, earth and sand are successively rolled out to a predetermined embankment height in the front and back directions of the partially laid earth, and the net exposed on the ground G is buried and compacted to construct the first layer A1. .

〈二〉 被覆ネットによる土砂の被覆(第5図)第1層
A1が構築された後、第1層A1の上面を新たな基盤と
してほぼ第1層A1の構築と同様な工程て第2層〜以降
を構築する。
<2> Covering the earth and sand with a covering net (Fig. 5) After the first layer A1 is constructed, the second layer is constructed using the upper surface of the first layer A1 as a new base and using almost the same process as the construction of the first layer A1. Build ~ and beyond.

第5図に示すように第1層A1の上面には部分置土で新
たに敷設された抵抗ネット2″を仮抑えし、その前端を
連結籠3″の爪31に係合する。
As shown in FIG. 5, a newly laid resistance net 2'' is temporarily held on the upper surface of the first layer A1 with partially laid soil, and its front end is engaged with the claw 31 of the connecting cage 3''.

次に第1層A1の被覆ネット1の自由端をはね上げ、第
1層A1の盛土の前端面を包み込むと共にその自由端を
第2層A2の連結籠3゛の爪31に係合して被覆を完了
する。〈ホ〉 第2層の巻き出し 第1層A1を構築する際に使用したL字形断面の土留定
規4を撤去した後、第1層A1を包み込んだ被覆ネット
1の前面上部にT字形断面の新たな土留定規5を配置す
る。
Next, the free end of the covering net 1 of the first layer A1 is flipped up and wrapped around the front end surface of the embankment of the first layer A1, and the free end is engaged with the claw 31 of the connecting cage 3 of the second layer A2 to cover it. complete. <E> Unrolling the second layer After removing the earth retaining ruler 4 with an L-shaped cross section that was used when constructing the first layer A1, a T-shaped cross section is placed on the upper front surface of the covering net 1 that wrapped the first layer A1. A new earth retaining ruler 5 is placed.

(第6図)被覆ネット1″は第1層A1の構築の際と同
様に土留定規5の上に仮置きし、土砂の巻き出しを行な
い第2層〜の巻き出しを完了する。
(FIG. 6) The covering net 1'' is temporarily placed on the earth retaining ruler 5 in the same manner as in the construction of the first layer A1, and the earth and sand are rolled out to complete the unrolling of the second layer.

第1層A1と第2層A2の間に配置された被覆ネット1
″の自由端は、第2層〜の前端面を包み込む状態ではね
上げ、第3層A3を構築する際に連結籠3に連結する。
Covering net 1 placed between first layer A1 and second layer A2
The free end of `` is flipped up in a state that wraps around the front end surface of the second layer ~, and is connected to the connecting basket 3 when constructing the third layer A3.

被覆ネット1はその上下層間に敷設された抵抗ネット2
と連結することにより、強大な摩擦力を得ている。従つ
て被覆ネット1が支持しきれずに各層前面の土砂が崩壊
することはない。構築される堤体の前面が傾斜している
ような場合にはその傾斜に適する角度を有する土留定規
5を使用する。
The covering net 1 is a resistance net 2 laid between its upper and lower layers.
A powerful frictional force is obtained by connecting with the Therefore, the earth and sand in front of each layer will not collapse due to the covering net 1 being unable to support it. If the front surface of the embankment body to be constructed is inclined, a retaining ruler 5 having an angle suitable for the inclination is used.

(第7図)〈へ〉 その他の実施例 以上の実施例は各層ことに順次構築して所定の堤体を構
築する場合について説明したが、場合によつては堤体の
前面のみの盛土を先行させる方法、または後背部のみの
土砂の巻き出しを先行させる方法も可能である。
(Fig. 7)〈〈〈〈〈〈〈〈〉〈〈〉〈〈〉〈〈〉〈〈〉〈〉〈〈〉〈〈〉〈〈〉〈〈〉〈〉〈Other Examples〉 In the above embodiments, each layer is constructed sequentially to construct a predetermined levee body. It is also possible to carry out the method in advance, or to carry out the unwinding of the earth and sand only from the rear part first.

これは各工事の種類に応じて作業の効率化を図ることが
できる。
This can improve work efficiency depending on the type of construction.

また盛土堤体の設計構造の安定および修景、景観上の配
慮から堤体構築後、被覆ネット1の前面に吹付コンクリ
ート、現場打ちコンクリート等による擁壁、法枠工法等
の被覆体を形成することも可能である。
In addition, from the viewpoint of stability of the design structure of the embankment body, landscaping, and aesthetic considerations, after constructing the embankment body, a retaining wall made of shotcrete, cast-in-place concrete, etc., or a covering body using the sill construction method is formed in front of the covering net 1. It is also possible.

この場合には堤体構築後、放置して可能な限り沈下させ
た後に形成すればキレツやクラック等の発生を防止する
ことがてきる。
In this case, it is possible to prevent the occurrence of chips, cracks, etc. by leaving the embankment and allowing it to sink as much as possible after constructing the embankment.

その他、被覆体の安定・補強のために、巻き出し層の間
にあらかじめアンカーケーブル等を埋設し被覆体の形成
の後に堤体の前面より緊張、定着することも可能である
In addition, in order to stabilize and reinforce the sheathing, it is also possible to bury an anchor cable or the like between the unrolling layers in advance, and then tension and fix it from the front surface of the embankment after the sheathing has been formed.

この場合ポーリング削孔の作業を省略することができる
In this case, the work of polling and drilling can be omitted.

本発明は以上説明したようになるから次のような効果を
期待することができる。
Since the present invention is as explained above, the following effects can be expected.

くイ〉 本発明の工法は各層ごとの前面の土砂を被覆ネ
ット1によつて支持しかつこのネット1に連結された抵
抗ネット2が被覆ネット1に加わる土圧を分散するため
前面の土砂の崩壊を防止することができる。
In the construction method of the present invention, the earth and sand in front of each layer is supported by the covering net 1, and the resistance net 2 connected to this net 1 disperses the earth pressure applied to the covering net 1. Collapse can be prevented.

く口〉 各層ごとに遂次土砂の巻き出しを行なうため施
工及び品質の管理が容易である。
Construction and quality control are easy because the earth and sand are rolled out successively for each layer.

〈ハ〉 土留材として大型材料を必要としないため現場
条件に制限を受けないで施工をすることができる。
<C> Since large-sized materials are not required as earth retaining materials, construction can be carried out without being restricted by site conditions.

〈二〉 盛土の安定・景観上の配慮から堤体構築後に被
覆ネット1前面にコンクリートの吹付・現場打コンクリ
ート等による擁壁、法枠工等の任意の被覆体を形成する
ことができる。
(2) From the viewpoint of embankment stability and aesthetic considerations, any covering body such as a retaining wall, slope work, etc., may be formed on the front of the covering net 1 by spraying concrete or cast-in-place concrete after constructing the embankment body.

〈ホ〉 前記の場合、堤体構築後放置し可能な限り沈下
させた後に施工すれば被覆体のキレツやクラック等の発
生を防止することができる。
<E> In the above case, if the embankment is left to settle after construction and is allowed to settle as much as possible, then the occurrence of chips, cracks, etc. in the covering can be prevented.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図:本発明に使用する土留ネットの説明図、第2図
:連結籠の説明斜視図、第3〜6図:断面施工説明図、
第7図:傾斜面を有する場合の施工説明図。 1:被覆ネット、2:抵抗ネット、3:連結籠、4,5
:土留定規。
Figure 1: An explanatory diagram of the earth retaining net used in the present invention, Figure 2: An explanatory perspective view of a connected cage, Figures 3 to 6: A cross-sectional construction explanatory diagram,
Fig. 7: Construction explanatory diagram in case of having an inclined surface. 1: Covered net, 2: Resistance net, 3: Connected cage, 4, 5
: Earth retaining ruler.

Claims (1)

【特許請求の範囲】 1 盛土の層間に敷設した被覆ネットの一端を、同一の
層間に敷設した抵抗ネットに対して連結籠を介して連結
しておき、その被覆ネットの他端を層の上面にはね上げ
て上層の土砂の前端間を被覆し、はね上げた被覆ネット
の端を、 上層の上面に敷設した抵抗ネットに対して連結籠を介し
て連結して、順次上層を構築する、 盛土堤体の構築工法。
[Claims] 1. One end of a covering net laid between layers of embankment is connected to a resistance net laid between the same layers via a connecting cage, and the other end of the covering net is connected to the upper surface of the layer. An embankment body in which the upper layer is successively constructed by flipping up and covering the front edges of the upper layer of earth and sand, and connecting the edge of the flipped up covering net to the resistance net laid on the top surface of the upper layer via a connecting cage. construction method.
JP4566282A 1982-03-24 1982-03-24 Embankment construction method Expired JPS6053137B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4566282A JPS6053137B2 (en) 1982-03-24 1982-03-24 Embankment construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4566282A JPS6053137B2 (en) 1982-03-24 1982-03-24 Embankment construction method

Publications (2)

Publication Number Publication Date
JPS58164822A JPS58164822A (en) 1983-09-29
JPS6053137B2 true JPS6053137B2 (en) 1985-11-22

Family

ID=12725582

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4566282A Expired JPS6053137B2 (en) 1982-03-24 1982-03-24 Embankment construction method

Country Status (1)

Country Link
JP (1) JPS6053137B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6088727A (en) * 1983-10-21 1985-05-18 Fuji:Kk Sheathing work
JP2012219520A (en) * 2011-04-08 2012-11-12 Mitsubishi Plastics Inc Earth retaining structure
JP2012219521A (en) * 2011-04-08 2012-11-12 Mitsubishi Plastics Inc Earth retaining structure

Also Published As

Publication number Publication date
JPS58164822A (en) 1983-09-29

Similar Documents

Publication Publication Date Title
JPS6053137B2 (en) Embankment construction method
JP2597116B2 (en) Embankment foundation and its construction method
US4683689A (en) Modular reinforced building structure and method
KR101018903B1 (en) Stabilizing assembly for preventing soil-flow of slope and greening
JP2000144769A (en) Method of landslide protection work for preparing housing lot
JP2552196B2 (en) How to build a reinforced embankment
US20060239782A1 (en) Methods and apparatuses for shaping concrete slab-on-ground foundations
JPH10317381A (en) Structure for protecting face of slope by retaining wall and method for constructing the same
JPS5932623B2 (en) Slope protection method
JPH04108914A (en) Structure for reinforced banking body
KR102249603B1 (en) Retaining wall construction method
JPS61134434A (en) Method of building concrete retaining wall
JPH03228921A (en) Execution method for concrete foundation work
JP2573157B2 (en) Leg frame method and gauge formwork used in the method
JPH0441213B2 (en)
JPS6136597Y2 (en)
JP3369879B2 (en) Greening structures such as slopes and walls
KR100644093B1 (en) The bottom slab construction method of having used covering members and this which are a post pile
JPH0680249B2 (en) Reinforced embankment construction method
JPS6360168B2 (en)
JPS61172921A (en) Builting method for road levee
JPH0759810B2 (en) Ground improvement method for foundation
JP2676606B2 (en) Construction method
JP3188854B2 (en) Gutter foundation block
JPS6138028A (en) Construction of foundation