JPS6037486A - Method of construction of quick burying joint of undergroundburied steel pipe - Google Patents

Method of construction of quick burying joint of undergroundburied steel pipe

Info

Publication number
JPS6037486A
JPS6037486A JP14311983A JP14311983A JPS6037486A JP S6037486 A JPS6037486 A JP S6037486A JP 14311983 A JP14311983 A JP 14311983A JP 14311983 A JP14311983 A JP 14311983A JP S6037486 A JPS6037486 A JP S6037486A
Authority
JP
Japan
Prior art keywords
gasket
pipe
tube
construction
quick
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP14311983A
Other languages
Japanese (ja)
Inventor
野見山 亢
菊地 庄三
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Heavy Industries Ltd
Original Assignee
Mitsubishi Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Ltd filed Critical Mitsubishi Heavy Industries Ltd
Priority to JP14311983A priority Critical patent/JPS6037486A/en
Publication of JPS6037486A publication Critical patent/JPS6037486A/en
Pending legal-status Critical Current

Links

Landscapes

  • Non-Disconnectible Joints And Screw-Threaded Joints (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 従来の地中埋設鋼管の継手の従来の工法を第1図乃至第
5図について説明する。M1図は従来の工法で現地での
セット直前の状態の概略図。
DETAILED DESCRIPTION OF THE INVENTION A conventional method of constructing a joint for a conventional underground steel pipe will be described with reference to FIGS. 1 to 5. Diagram M1 is a schematic diagram of the state immediately before installation on site using the conventional construction method.

第2図は第1図のP−F矢視図、第3図は第1図の状態
から→印の方向へ引込んでセットした状態の概略図、第
4図は第3図におけるG部断面の詳細図、第5図は第5
図のH部断面の詳細図を示す。通常水道管等は道路を掘
削して埋設されることが多いが、現地継手部の溶接と塗
覆装に長時間を要するため現地工事中に手待ちの時間が
多くコストアップとなっていた。これを解消するためV
こ第1図乃至第5図の如き工法が開発され、しげしげ使
用されていたが、この工法に種々問題がある。
Figure 2 is a view along the P-F arrow in Figure 1, Figure 3 is a schematic diagram of the state shown in Figure 1 when it is pulled in the direction of the → mark, and Figure 4 is a cross section of section G in Figure 3. Detailed view of Figure 5.
A detailed view of the section H in the figure is shown. Normally, water pipes are often buried by excavating roads, but welding and painting on-site joints takes a long time, resulting in a lot of waiting time during on-site construction, which increases costs. To solve this problem, V
Although the construction method shown in FIGS. 1 to 5 has been developed and widely used, there are various problems with this construction method.

1ずこの方法について説明する。olはこれから据付け
ようとする管本体、01°はすでに据付けられた管本体
、02はこれから据付けようとする管本体口1の片側に
取付けられた上半円の裏当金、06は裏当金02と反対
に取付けられた下半周の真当金、 02−1 、02−
2は現地でのシール溶接部、02−3は管本体01を裏
当金02に工場で取付けるときの隅肉溶接部。
1. Zuko's method will be explained. ol is the pipe body that is about to be installed, 01° is the pipe body that has already been installed, 02 is the upper semicircular backing metal attached to one side of the pipe body mouth 1 that is about to be installed, and 06 is the backing metal. Lower half circumference true guard installed opposite to 02, 02-1, 02-
2 is the seal welded part at the site, and 02-3 is the fillet welded part when the pipe body 01 is attached to the backing metal 02 at the factory.

06−1は管本体01°と裏当金05全工場で取付ける
ときの隅肉溶接部、04ijガスケツトストツパ、04
−1は管本体01とガスケットストッパ04を工場で取
付けるときの隅肉溶接部。
06-1 is the fillet welded part when installing the pipe body 01° and backing metal 05 at all factories, 04ij gasket stopper, 04
-1 is the fillet welded part when the pipe body 01 and gasket stopper 04 are attached at the factory.

05はガスケツ)、06はガスケツ)05i締め付ける
ビニール被覆針金、071d仮設用のラグピース、07
−1は管本体01101’全ラグピース07を工場で取
り付けるときの仮付は隅肉溶接部、08はラグピース0
7締付は用ボルトナツト+o9’h管本体01と管本体
01’の現地突き合わせ溶接部である。施工順序はまず
管本体01゛が所定の位置にセットされたら、第1図か
ら第3図のように管本体01を管本体01゜に寄ぜラグ
ピース7に締め付は用ボルトナツト08をセットして締
め付ける。ガスケット05は路面上で予め俄付けておく
締め付は用ボルトナツト08の締め付けが終るとシール
溶接部02−1.o2−2の溶接全行い、その部分の補
修塗、!llを終らせれば、管体外部の作業は終了する
ので外面塗装の乾燥金持って土砂の埋戻しを行う。この
作業をくり返し先へ進んでゆく。管内面は締め付は用ボ
ルトナツト08の締付は後。
05 is a gasket), 06 is a gasket) 05i Vinyl-coated wire for tightening, 071d Rag piece for temporary construction, 07
-1 is the pipe body 01101' When installing all lug pieces 07 at the factory, temporary attachment is the fillet weld, 08 is lug piece 0
7. Tightening is the on-site butt welding of the bolt/nut + o9'h tube body 01 and tube body 01'. The construction order is as follows: First, the pipe body 01゛ is set in the specified position, and as shown in Figs. and tighten. The gasket 05 is pre-tightened on the road surface.After the bolt and nut 08 are tightened, the seal welded portion 02-1. Complete welding of o2-2 and repair painting of that part! Once this is completed, the work on the outside of the pipe will be completed, and the dried money from the exterior painting will be used to backfill with earth and sand. Repeat this process to move forward. Tighten the inner surface of the tube, but tighten bolts and nuts 08 later.

直ちに突き合わせ溶接部09の溶接を開始し。Welding of butt weld part 09 is immediately started.

埋戻し作業とは無関係に作業が進められる。突き合わせ
溶接部09全終ると、ラグピース07゜締め付は用ボル
トナツト08全取外し、この部分や突き合わせ溶接部0
9付近の塗面の補修塗vを行えば内面作業は完了する。
The work will proceed independently of the backfilling work. When the butt weld part 09 is all completed, remove all bolts and nuts 08 for tightening the lug piece 07°, and tighten this part and the butt weld part 0.
The inner surface work will be completed if the repair coating v is applied to the painted surface around 9.

この工法の問題は前の図面のよう上半円はガスケットを
設けるため外面作業は不要であるが上半周のシール溶接
とその後の補修塗りが必要であるためがなりの時間全翼
す。又内面がらの管体の突合わぜ溶接を行うと裏当金外
面の塗装面が焼けるため防食効果が著しく低下する。0
10は管外面。
The problem with this method is that as shown in the previous drawing, a gasket is provided on the upper half of the wing, so no external work is required, but seal welding on the upper half of the circumference and subsequent repair painting are required, which takes some time. In addition, when butt welding is performed on a tube body whose inner surface is empty, the painted surface of the outer surface of the backing metal is burned, and the anticorrosion effect is significantly reduced. 0
10 is the outer surface of the tube.

011ij管内面を示す。011ij shows the inner surface of the tube.

本発明は上記欠点金なくすることを目的として発明され
たものである。
The present invention was invented with the aim of eliminating the above-mentioned disadvantages.

本発明は、ラグピースをボルトナツトで締め付けること
により外部に取付けられたガスケットが締め付けられ地
下水の浸入全防止し、管体を突き合わせ溶接することに
ょクガスヶットがきつく締め付けられ、管外部から接合
作業全皆無にしたことを特徴とする地中埋設鋼管の急速
埋設継手工法に係9.外部の作業がほとんどなく溶接熱
の影響によって塗面の損i¥ない構造とした地中埋設鋼
管の急速埋設継手工法を提供しようとするもので、各パ
イプラインの現地施工に応用でき、降雨時も施工可能、
又トンネル内の敷設(管の外部作業不可能な場合でも可
)時にも使用できるものである。
In the present invention, by tightening the lug piece with bolts and nuts, the externally attached gasket is tightened, completely preventing the infiltration of underground water, and by butt welding the pipe bodies, the gasket is tightly tightened, eliminating any joining work from the outside of the pipe. 9. Concerning a rapid burial joint construction method for underground steel pipes, which is characterized by the following. The aim is to provide a quick-build joint method for underground steel pipes that requires almost no external work and does not cause damage to the painted surface due to the effects of welding heat.It can be applied to on-site construction of each pipeline, and can be used in the event of rain. It is also possible to construct
It can also be used when laying inside tunnels (even when it is impossible to work on the outside of the pipe).

本発明の地中埋設鋼管の急速埋設継手工法の一実施例を
第6図乃至N8図について説明する。
An embodiment of the rapid burial joint construction method for underground steel pipes of the present invention will be described with reference to FIGS. 6 to N8.

第6図は本発明の地中埋設鋼管の急速埋設継手工法の一
実施例の配管順序概略図、第7図は第6図のB部断面の
詳細図、第8図は第6図のA−A矢視図を示す。1′は
先にセットされた管体。
Fig. 6 is a schematic diagram of the piping sequence of an embodiment of the rapid burial joint construction method for underground steel pipes of the present invention, Fig. 7 is a detailed view of the section B in Fig. 6, and Fig. 8 is A in Fig. 6. - Shows a view in the direction of the A arrow. 1' is the tube that was set earlier.

1は後からセットされる方の管体會示し、1−1は先に
セットされた管体1°と後からセットされる方の管体1
を現場にて接合する突合わせ溶接部、2はライナー、2
−1と2−2は管体1とライナ2と全工場にて取付ける
隅肉溶接部。
1 indicates the tube body that will be set later, and 1-1 indicates the tube body 1° that will be set first and the tube body 1 that will be set later.
2 is a liner;
-1 and 2-2 are fillet welds that are attached to the pipe body 1 and liner 2 at all factories.

5は外筒管、3−1はライナ2と外筒管5を工場にて取
付ける隅肉溶接部、4はガスケット押し輪、3−2と4
−1は外筒管3と押し輪4全工場にて取付ける隅肉溶接
部、5はガスケツトストラパル5−1u管体1゛とガス
ケットストッパ5を工場にて取付ける隅肉溶接部、6は
ガスケット、7はグラウト栓、8はラグピース、9はボ
ルトナツト、10は管体1と外筒管3との空間を示す。
5 is the outer tube, 3-1 is the fillet weld where the liner 2 and the outer tube 5 are attached at the factory, 4 is the gasket push ring, 3-2 and 4
-1 is a fillet weld where the outer tube 3 and push ring 4 are attached at the factory, 5 is a fillet weld where the gasket strap 5-1u tube body 1'' and gasket stopper 5 are attached at the factory, and 6 is 7 is a grout plug, 8 is a lug piece, 9 is a bolt nut, and 10 is a space between the tube body 1 and the outer tube 3.

11は管外面、12は管内面を示す。Reference numeral 11 indicates the outer surface of the tube, and 12 indicates the inner surface of the tube.

本発明の作用について説明する。現地でのセット順序は
管体1゛の方向へ管体1を引き込みボルトナツト9でラ
グピース8′t−締め付けることによりガスケット押し
輪4とガスケットストッパ50間のガスケット6が締め
付けられ外部の地下水等が空間10の方へ浸入すること
がなくなり、外部の土砂の埋戻しが可能となる。突き合
わせ溶接部1−1の溶接は外部の作業に関係なく作業で
きるため非常に早い埋設作業が可能となる。ラグピース
8#ボルトナツト9の取外しは突き合わせ溶接部1−1
の溶接の途中で行えば良く、溶接後に突き合わせ溶接部
1−1部付近の塗装の補修を行えば作業は完了する。又
ユーザーの要求により空間10全モルタル等に填充が必
要な場合は予め工場にてグラウト栓7孕設けておき、突
き合わせ溶接部1−1部の溶接完了後管内面より作業を
行う。
The operation of the present invention will be explained. The order of setting at the site is to pull the pipe body 1 in the direction of the pipe body 1' and tighten the lug piece 8't with the bolt nut 9, thereby tightening the gasket 6 between the gasket push ring 4 and the gasket stopper 50, and preventing external groundwater etc. from leaving the space. This prevents intrusion into the direction of 10, making it possible to backfill with external earth and sand. Since the welding of the butt weld portion 1-1 can be performed regardless of external work, very quick burial work is possible. Removal of lug piece 8 #bolt nut 9 is at butt weld part 1-1
The work can be completed by repairing the paint around the butt weld part 1-1 after welding. Further, if it is necessary to fill the entire space 10 with mortar etc. according to the user's request, a grout plug 7 is provided in advance at the factory, and the work is carried out from the inner surface of the tube after welding of the butt weld section 1-1 is completed.

本発明は以上の構成よりなり2次のような効果を奏する
ものである。
The present invention has the above configuration and has the following secondary effects.

(1) ラグピース8をボルトナツト9により締め付け
ることにより、ガスケット押し輪4とガスケットストッ
パ5間にガスケット6が締め付けられるため外部の地下
水等の浸入を防止できる。
(1) By tightening the lug piece 8 with the bolt/nut 9, the gasket 6 is tightened between the gasket push ring 4 and the gasket stopper 5, thereby preventing intrusion of external groundwater, etc.

(2)上記の作用によって空間10内の空気は外部と完
全Vcm断されるため、管外面の溶接後の補修塗りは不
要となり、多少の降雨時でも又墜道内など外部からの作
業不可能な場合や地下水等により水滴がある場合でも施
工可能となる。
(2) Due to the above action, the air in the space 10 is completely cut off from the outside by Vcm, so there is no need to repaint the outer surface of the pipe after welding. Construction is possible even when there are water droplets due to rain or underground water.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は従来の工法で現地でのセット直前の状態の概略
図、第2図は第1図のFF矢視図第3図は第1図の状態
から→印の方向へ引込んでセットした状態の概略図、第
4図は第5図におけるG5Fr面の詳細図、第5図は第
6図のH部所面の詳細図、第6図は本発明の地下埋設鋼
管の急速埋設継手工法の一実施例の配管順序概略図、第
7図は第6図のB部断面の詳細図、第8図t/″i第6
図のAA矢視図を示す。 01・・・・・・これから据付ける管本体、oll・・
・・・すでに据付けられた管本体、02・・・・・・管
本体01の片側に取付けられた上半円の裏当金、03・
・・・・・02と反対に取付けられた下半周の裏当金0
2−1.02−2・・・・・・現地のシール溶接部。 02−3・・・・・・管本体Orと裏当金03の隅肉溶
W部、04・・・・・・ガスケットストッパ、04−1
・・・・・・管本体01とガスケットストッパ04との
隅肉溶接部、05・・・・・・ガスケツ)、06・・・
・・・被覆針金、07・・・・・・ラグピース、07−
1・・・・・・管本体01,01″をラグピースo7を
取付ける仮付は隅肉溶接部、08・・・・・・ボルトナ
ラ)、09・・・・・・管本体01とo i’の現地溶
接部、010・・・・・・管外面、011・・・・・・
管内面、1°・・・・・・先にセットされた管体、1・
・・・・・後からセットされる管体1−1・・・・・・
管体1°と1との現地溶接部、2・・・・・・ライナ、
2−1.2−2・・・・・・管体1とライナ2との隅肉
溶接部、3・・・・・・外筒管、5−1・・・・・・ラ
イナ2と外筒管3との隅肉溶接部、4・・・・・・ガス
ケット押し輪、5−2.4−1・・・・・・外筒管3と
押し輪4の隅肉溶接部、5・・・・・・ガスケットネト
ツバ、5−1・・・・・・管本体1°とガスケットスト
ッパ5の隅肉溶接部、6・・・・・・ガスケット、7・
・・・・・グラウト栓、8・・・・・・ラグピース、9
・・・・・・ボルトナツト、10・・・・・・管体1と
外筒管3との空間。 11・・・・・・管外面、12・・・・・・管内面。 特許出願人 三菱重工業株式会社
Figure 1 is a schematic diagram of the state immediately before setting on site using the conventional construction method, Figure 2 is a view from the FF arrow in Figure 1, and Figure 3 is a schematic diagram of the state immediately before being set on site using the conventional construction method. A schematic diagram of the state, Fig. 4 is a detailed view of the G5Fr surface in Fig. 5, Fig. 5 is a detailed view of the H section in Fig. 6, and Fig. 6 is the rapid burial joint construction method for underground steel pipes of the present invention. FIG. 7 is a detailed cross-sectional view of section B in FIG. 6, FIG.
A view taken along arrow AA in the figure is shown. 01...The main body of the pipe that will be installed from now on, oll...
...The pipe body already installed, 02...The upper semicircular backing plate attached to one side of the pipe main body 01, 03.
...Backing metal 0 on the lower half of the circumference installed opposite to 02
2-1.02-2...Seal welded area on site. 02-3...Fillet weld W part of tube body Or and backing metal 03, 04...Gasket stopper, 04-1
...Fillet weld between the tube body 01 and the gasket stopper 04, 05...Gasket), 06...
...Coated wire, 07...Lag piece, 07-
1...Temporarily attach the lug piece o7 to the tube body 01,01'' at the fillet weld, 08...Bolt hole), 09...Tube body 01 and o i' Field welded part, 010... pipe outer surface, 011...
Tube inner surface, 1°...Pipe body set earlier, 1.
...Pipe body 1-1 to be set later...
Field welded part between tube body 1° and 1, 2... liner,
2-1.2-2...Fillet weld between tube body 1 and liner 2, 3...Outer tube, 5-1...Liner 2 and outside Fillet welded part between cylindrical pipe 3, 4... Gasket push ring, 5-2.4-1... Fillet welded part between outer cylindrical pipe 3 and push ring 4, 5. ... Gasket neck, 5-1 ... Fillet welded part of tube body 1° and gasket stopper 5, 6 ... Gasket, 7.
...Grout plug, 8...Lag piece, 9
... Bolt nut, 10 ... Space between tube body 1 and outer tube 3. 11...Tube outer surface, 12...Tube inner surface. Patent applicant Mitsubishi Heavy Industries, Ltd.

Claims (1)

【特許請求の範囲】[Claims] ラグピース全ボルトナツトで締め付けることにより外部
に取付けられたガスケットが締め付けられ地下水の浸入
全防止し、管体を突き合わせ溶接することによりガスケ
ットがきつく締め付けられ、管外部から接合作業全皆無
にしたことを特徴とする地中埋設鋼管の急速埋設継手工
法O
By tightening all the lug pieces with bolts and nuts, the externally attached gasket is tightened, completely preventing infiltration of underground water, and by butt welding the pipe bodies, the gasket is tightly tightened, eliminating any joining work from the outside of the pipe. Rapid underground joint construction method for underground steel pipes O
JP14311983A 1983-08-06 1983-08-06 Method of construction of quick burying joint of undergroundburied steel pipe Pending JPS6037486A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14311983A JPS6037486A (en) 1983-08-06 1983-08-06 Method of construction of quick burying joint of undergroundburied steel pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14311983A JPS6037486A (en) 1983-08-06 1983-08-06 Method of construction of quick burying joint of undergroundburied steel pipe

Publications (1)

Publication Number Publication Date
JPS6037486A true JPS6037486A (en) 1985-02-26

Family

ID=15331353

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14311983A Pending JPS6037486A (en) 1983-08-06 1983-08-06 Method of construction of quick burying joint of undergroundburied steel pipe

Country Status (1)

Country Link
JP (1) JPS6037486A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01143964A (en) * 1987-11-30 1989-06-06 Nippon Seiki Co Ltd Crossed coil type instrument
US6519619B1 (en) 1999-01-26 2003-02-11 Nec Corporation Circuit for generating periodic function

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01143964A (en) * 1987-11-30 1989-06-06 Nippon Seiki Co Ltd Crossed coil type instrument
US6519619B1 (en) 1999-01-26 2003-02-11 Nec Corporation Circuit for generating periodic function

Similar Documents

Publication Publication Date Title
JPS6037486A (en) Method of construction of quick burying joint of undergroundburied steel pipe
JPH0617575B2 (en) Steel pipe pile connection method
JPH0669574U (en) Cast iron pipe mechanical coupling
JPH05296217A (en) Pipe joint structure using hollow spherical body
JP4301420B2 (en) Pipe repair method
JPS60237290A (en) Method of joining buried pipe body
JP3035856B2 (en) Rise pipe for buried piping
JPH0320637Y2 (en)
JPS58146783A (en) Method of communicating connecting section of pipe
JPH08177393A (en) Shield segment
JP2880413B2 (en) Fixing method and fixture for propulsion pipe at shaft shaft
JPS5921346Y2 (en) pipe fittings
JP3003786U (en) Internal water stop band
JPS61180089A (en) Method of connecting hume pipe
JPS6261835B2 (en)
JPH0615920B2 (en) How to protect joints in buried pipes
JPS622197B2 (en)
JP2530621Y2 (en) Grout injection structure for multi-layer propulsion steel pipe method.
JPS641594Y2 (en)
JPH0640709Y2 (en) Pipe fittings for ground excavation
JPS61175374A (en) Rubber-boot fitting structure
JPH0531347Y2 (en)
JP2000257397A (en) Method for repairing tunnel inner wall
JPH01113178A (en) Method for connecting piping for freon
JPS61286685A (en) Pipe and method of laying construction of pipe