JPS6030837B2 - Vertical shaft excavation method - Google Patents
Vertical shaft excavation methodInfo
- Publication number
- JPS6030837B2 JPS6030837B2 JP10942979A JP10942979A JPS6030837B2 JP S6030837 B2 JPS6030837 B2 JP S6030837B2 JP 10942979 A JP10942979 A JP 10942979A JP 10942979 A JP10942979 A JP 10942979A JP S6030837 B2 JPS6030837 B2 JP S6030837B2
- Authority
- JP
- Japan
- Prior art keywords
- shaft
- hole
- excavation
- blasting
- blast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Drilling And Exploitation, And Mining Machines And Methods (AREA)
Description
【発明の詳細な説明】
この発明は上部と下部に坑道を有し、両者を結ぶ立坑を
掘削する場合の立坑掘削工法に関するもので、例えば地
下発電所建設におけるグロリーホールの掘削に用いられ
る。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a shaft excavation method for excavating a shaft having upper and lower shafts connecting the two, and is used, for example, for excavating a glory hole in the construction of an underground power plant.
グロリーホール用の立坑掘削工法には従来人力によるも
の、大口径ボーリングマシンによる機械掘削その他種々
の方法があるが、掘削深度、掘削断面が大きくなるとい
ずれの工法も安全性あるいは機械性能上の制約から施工
が困難となる。Conventionally, there are various methods for excavating vertical shafts for Glory Holes, including manual excavation, mechanical excavation using large-diameter boring machines, etc. However, when the excavation depth and excavation cross section become large, each method has limitations in terms of safety or mechanical performance. Construction becomes difficult.
また、従来鉱山における立坑掘削においては、発破を用
いて立坑を掘削することが行なわれており、クレーター
カット工法等が知られている。しかし、従釆行なわれて
いるクレーターカット工法は一度に大断面の掘削を行な
うのではなく、大断面の掘削を必要とする場合、中央部
分の心抜きを数回先行させ、その後さらに外周部分を払
って行く方式をとっている。この発明はこのような事情
に鑑み開発されたもので、大深度、大断面の掘削を安全
かつ迅速に行なうことができる立坑掘削工法を提供する
ことを目的としている。Furthermore, in conventional shaft excavation in mines, shafts are excavated using blasting, and crater cut methods and the like are known. However, the conventional crater cut method does not excavate a large cross section at once, but when a large cross section needs to be excavated, the central part is punched out several times in advance, and then the outer circumference is further excavated. We are using a pay-as-you-go method. The present invention was developed in view of the above circumstances, and an object of the present invention is to provide a vertical shaft excavation method that allows excavation of large depths and large sections safely and quickly.
以下図示した実施例に基づいて説明する。The following description will be given based on the illustrated embodiment.
施工はまず、立坑C掘削予定位置に所要本数の発破孔1
を穿設する。Construction begins by drilling the required number of blast holes at the planned excavation location for shaft C.
to be drilled.
次に上部孔Aより発破孔1の清掃をした後、孔長を測定
して、各発破孔1の下部に所要量の爆薬3を装薬する。
そしてこれらの爆薬3を同時に爆発させることにより1
ステ−ジの発破が完了する。上述の発破孔1の清掃から
爆薬3による発破までを1ステージとして、これを立坑
C下部よりll頂次繰り返して行くことにより立坑Cの
掘削が行なわれる。第1図は発破孔1の穿孔の様子を示
しており、上部坑Aよりクローラドリル等の最孔穿孔機
2により発破孔1を穿孔する。Next, after cleaning the blasting holes 1 from the upper hole A, the hole length is measured, and a required amount of explosives 3 is charged in the lower part of each blasting hole 1.
By detonating these explosives 3 at the same time, 1
Blasting of the stage is completed. Excavation of the shaft C is carried out by repeating the process from the cleaning of the blast hole 1 described above to blasting with the explosive 3 as one stage from the bottom of the shaft C to the top. FIG. 1 shows how a blast hole 1 is drilled, and the blast hole 1 is drilled from an upper hole A using a deep-hole drilling machine 2 such as a crawler drill.
このとき、発破孔1はできるだけ孔曲りによる偏心の少
ないことが望ましく、スタビライザー等を使用すると良
い。第2図は発破の順序を示したもので、a,b,c,
・・・,iの順で発破が行なわれる。1ステージの掘削
量は地質、装薬量、装薬方法等で差がでるが、作業に慣
れるに従いスムーズな掘削が可能となる。At this time, it is desirable that the blast hole 1 has as little eccentricity as possible due to hole bending, and a stabilizer or the like may be used. Figure 2 shows the order of blasting: a, b, c,
Blasting is performed in the order of ..., i. The amount of excavation in one stage varies depending on the geology, amount of charge, method of charge, etc., but as you get used to the work, it becomes possible to excavate smoothly.
また掘削ずりは下部坑Bより搬出される。なお、図のよ
うな立坑Cにおいて掘削断面8〆程度の場合1ステージ
の発破で2.5〜3凧程度の掘削が可能であった。第3
図は発破孔1の平面的な配置を示したもので、各ステー
ジの発破の前に発破孔1の清掃を行い、孔長を測定し、
正確な装薬を行なう。第4図は装薬方法を示したもので
、発破孔1の先端に密栓5を施し、爆薬3の上下に砂4
,4′を詰めておく。Further, the excavated debris is carried out from the lower shaft B. In addition, in the case of shaft C as shown in the figure, when the excavation cross section was about 8 mm, it was possible to excavate about 2.5 to 3 kites in one stage of blasting. Third
The figure shows the planar arrangement of the blast holes 1. Before each stage of blasting, the blast holes 1 are cleaned, the hole length is measured,
Perform accurate charging. Figure 4 shows the charging method, in which a seal plug 5 is placed at the tip of the blast hole 1, and sand 4 is placed above and below the explosive 3.
, 4'.
密栓5としてはくり粉をナイロン袋に詰めたものやある
いは小さな土のう袋等が用いられる。またこの密栓5、
爆薬3は細いナイロンテープで釣り下げて装着すること
ができる。またリビングストンのクレータ理論によると
良好なクレー夕を形成するためには、最適な装薬量、装
薬長、装薬位置がある。そしてその結果生ずるクレー夕
7の最大深度も1.5の程度である(第5図参照)。実
際に設計以上に装薬量、装薬長を大きくしてもクレー夕
7の深さは変わらない。ただ、それ以奥は孔蓬が拡大す
ることが経験されている(第6図参照)。この事実から
、孔径の拡大する部分8をバーンホールに利用すること
ができる。すなわち、雷管の段数を変え、心抜き部分中
央を最初に爆破(装薬量やや多くなる)し、他はこれに
向かって払って行くことにより、効果的な施工ができる
。なお、このように掘削した立抗Cを地下発電所建設に
おけるグロリーホールとして利用する場合、上部よりベ
ンチカットしたずりをブルドーザーなどで押士して下部
坑レベルへ落し、坑外へ搬出して行くことにより大地下
空間が形成される。As the seal 5, a nylon bag filled with flaking powder, a small sandbag, or the like is used. Also, this sealed plug 5,
Explosive 3 can be attached by hanging it with thin nylon tape. According to Livingstone's crater theory, there are optimal amounts, lengths, and positions for forming good craters. The maximum depth of the resulting clay layer 7 is also approximately 1.5 mm (see Figure 5). In fact, even if the charge amount and charge length are increased beyond the design, the depth of the clay 7 does not change. However, it has been experienced that the pores expand beyond that point (see Figure 6). From this fact, the portion 8 where the hole diameter increases can be used as a burn hole. In other words, effective construction can be achieved by changing the number of stages of detonators, detonating the center of the core part first (the amount of charge will be slightly larger), and discharging the rest towards this direction. In addition, when shaft C excavated in this way is used as a glory hole in the construction of an underground power plant, the bench-cut shear from the upper part is pushed down with a bulldozer, etc., to the lower shaft level, and then carried out of the mine. As a result, a large underground space is formed.
この発明は以上の構成からなり、穿孔、装薬等が上部坑
よりの作業で行なわれ、また掘削は人力によらないため
、施工が非常に安全である。心抜き部分中央の装薬量を
多くして、爆破によるクレー夕‐以奥に生じる拡径部分
をバーンホールとして利用しているため、掘削断面、掘
削深度が大きくとれ、また迅速な施工が行なわれる。作
業が単純であるので、慣れるに従い効率の良い施工が行
なえる。This invention has the above-mentioned structure, and since drilling, charging, etc. are performed from the upper shaft, and the excavation does not require manual labor, construction is very safe. By increasing the amount of charge in the center of the hollowed-out part and using the enlarged diameter part created behind the blasting clay as a burn hole, the excavation cross section and depth can be increased, and construction can be carried out quickly. It will be done. Since the work is simple, as you get used to it, you can perform construction efficiently.
図面はこの発明の実施例を示したもので、第1図は発破
孔の穿孔の様子を示す断面図、第2図は発破の順序を示
す断面図、第3図は発破孔の配置を示す平面図、第4図
は装薬方法を示す断面図、第5図および第6図は心抜き
部分の発破孔の爆破の断面図である。
1・・・・・・発破孔、2・・・・・・長孔穿孔機被、
3・・・・・・爆薬、4,4′……砂、5……密栓、6
……導嬢線、7・・・・・・クレー夕、8・・・・・・
鉱径部分、A・・・・・・上部坑、B・・・・・・下部
坑、C・・・・・・立坑、a,b,c,d,e,f,g
,h,i・・・・・・1ステージの掘削部分。
第1図
第2図
第3図
第5図
第4図
第6図The drawings show an embodiment of the present invention; FIG. 1 is a sectional view showing how the blast holes are drilled, FIG. 2 is a sectional view showing the order of blasting, and FIG. 3 is the arrangement of the blast holes. A plan view, FIG. 4 is a cross-sectional view showing the charging method, and FIGS. 5 and 6 are cross-sectional views of the blasting of the blast hole in the cored portion. 1... Blasting hole, 2... Long hole drilling machine cover,
3...Explosives, 4,4'...Sand, 5...Tight plug, 6
...Doujo Line, 7...Clay Yu, 8...
Mine diameter portion, A... Upper pit, B... Lower pit, C... Vertical shaft, a, b, c, d, e, f, g
, h, i... 1st stage excavation part. Figure 1 Figure 2 Figure 3 Figure 5 Figure 4 Figure 6
Claims (1)
を穿設し、各発破孔1の孔長測定および装薬を行ない、
立坑C下部より順次発破を繰り返して、掘削ずりを下部
坑Bより搬出する立坑掘削工法であつて、雷管の段数を
変え装薬量をやや多くした心抜き部分中央の発破孔1部
分を最初に爆破させ、クレータ7以奥に生じる拡径部分
8をバーンホールとして、これを取巻く他の発破孔1部
分は前記拡径部分8に向けて爆破させることを特徴とす
る立坑掘削工法。1 Required number of blast holes 1 from upper shaft A to shaft C excavation position
, measure the length of each blast hole 1 and charge the blast hole,
This is a shaft excavation method in which blasting is repeated sequentially from the lower part of the shaft C, and the excavated waste is carried out from the lower shaft B.The first part of the blast hole in the center of the hollowed out part where the number of stages of the detonator is changed and the amount of charge is slightly increased is used. A vertical shaft excavation method characterized in that a diameter enlarged part 8 produced in the depths of a crater 7 is used as a burn hole, and the other part of the blast hole surrounding this is blown toward the diameter enlarged part 8.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP10942979A JPS6030837B2 (en) | 1979-08-28 | 1979-08-28 | Vertical shaft excavation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP10942979A JPS6030837B2 (en) | 1979-08-28 | 1979-08-28 | Vertical shaft excavation method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS5634893A JPS5634893A (en) | 1981-04-07 |
JPS6030837B2 true JPS6030837B2 (en) | 1985-07-18 |
Family
ID=14510012
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP10942979A Expired JPS6030837B2 (en) | 1979-08-28 | 1979-08-28 | Vertical shaft excavation method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6030837B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6226751U (en) * | 1985-08-01 | 1987-02-18 |
-
1979
- 1979-08-28 JP JP10942979A patent/JPS6030837B2/en not_active Expired
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6226751U (en) * | 1985-08-01 | 1987-02-18 |
Also Published As
Publication number | Publication date |
---|---|
JPS5634893A (en) | 1981-04-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP0692611B1 (en) | Method for excavating a working face | |
KR102162731B1 (en) | Eco friendly explosive case and Dispersion explosive assembly including this same and Blasting method using this same | |
CN106677786B (en) | A kind of ultra-deep big cross section vertical shaft shaft formatting by one blasting method based on electric detonator | |
CN107762399A (en) | Explosion coordinates rotary drilling rig deep layer one-step pore-creating construction method | |
CN110260735A (en) | A kind of diamond shape major diameter emptying aperture burn cut structure and lane construction technique | |
JP2614396B2 (en) | Shaft excavation method by pre-boring | |
JPS6030837B2 (en) | Vertical shaft excavation method | |
JP3119979B2 (en) | Underground space formation blasting method | |
JP3073277B2 (en) | Excavation method for steel tower foundation holes | |
US3710718A (en) | Method for creating underground cavities employing explosives | |
McKOWN | Perimeter control blasting for underground excavations in fractured and weathered rock | |
JP3486103B2 (en) | How to blast rock | |
CN1164606A (en) | Differential control, nondestructive blasting rock-implanting process for punching, drilling and filling pile for building foundation | |
SU1263868A1 (en) | Method of controlling the strained state of rock about mine working | |
JP2916596B2 (en) | Rock excavation method in the pneumatic caisson method. | |
CN118187671B (en) | Rock stratum perforating device | |
KR100403385B1 (en) | Method of excavating tunnel without exceeding boundary | |
JPS6124511B2 (en) | ||
CN209541585U (en) | Photoface exploision powder charge mechanism | |
JPH0835389A (en) | Excavating method of underground construction | |
JPS6354116B2 (en) | ||
JPH0370078B2 (en) | ||
JPH02217589A (en) | Removal of underground obstruction in excavating work | |
US115115A (en) | Improvement in sinking shafts and excavating tunnels and cuttings | |
SU817253A1 (en) | Method of driving a mine working |