JPS60188505A - Construction of temporary constructed bridge - Google Patents

Construction of temporary constructed bridge

Info

Publication number
JPS60188505A
JPS60188505A JP4194384A JP4194384A JPS60188505A JP S60188505 A JPS60188505 A JP S60188505A JP 4194384 A JP4194384 A JP 4194384A JP 4194384 A JP4194384 A JP 4194384A JP S60188505 A JPS60188505 A JP S60188505A
Authority
JP
Japan
Prior art keywords
water
finger
pile body
antibody
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP4194384A
Other languages
Japanese (ja)
Other versions
JPH0319323B2 (en
Inventor
憲二 松村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP4194384A priority Critical patent/JPS60188505A/en
Publication of JPS60188505A publication Critical patent/JPS60188505A/en
Publication of JPH0319323B2 publication Critical patent/JPH0319323B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 技術分野 この発明は、桟橋あるいは橋梁を仮設づるだめの工法に
関する。
DETAILED DESCRIPTION OF THE INVENTION Technical Field The present invention relates to a construction method for temporarily constructing a pier or a bridge.

従来技術 従来、桟橋あるいは橋梁を建設する方法は橋脚の建設と
それに続く桁を構築する工程からなっており、これは仮
設橋であっても、同じである。
BACKGROUND OF THE INVENTION Conventionally, the method of constructing a pier or a bridge consists of the construction of piers and the subsequent construction of girders, and this is the same even for temporary bridges.

ところで、仮設橋であっても、1n脚に当る杭を打つ作
業は大樹りな設備を必要とし、それを用いた作業コスト
も大きなものであった。
By the way, even for temporary bridges, the work of driving piles equivalent to 1n legs required large equipment, and the work cost using it was also large.

この困難を避ける!こめに、従来、浮桟橋あるいは浮橋
が用いられてい1=が、これらは水平および垂直位置の
安定性が悪く、荷重の支持態力も信頼できなかった。
Avoid this difficulty! Conventionally, floating piers or floating bridges have been used, but these have poor horizontal and vertical stability and are unreliable in their ability to support loads.

[1的 この発明は、従来法の上記欠点を解消し、建設が容易で
しかし安定性と信頼性が良い仮設橋の構築方法を提供す
るものである。
[1] This invention solves the above-mentioned drawbacks of the conventional method and provides a method for constructing a temporary bridge that is easy to construct and has good stability and reliability.

構 成 この発明は、船体のように水面に浮くことができる水密
性の細長い箱形の4M造を有する押指ど、これに対して
昇降自在に係合された抗体およびこの抗体を押指に固定
し得る部材どを有する仮設橋部側を所定の位置に配置し
、その位置で抗体を降下させてその先端を水底に接地さ
せ、抗体を押指に固定した後、水密性の上記押指内部に
水を)−またりことによって、杭体に押指と水の重量を
作用させ、抗体を水底に打込み、抗体が所定の荷mに耐
える深さまで沈下した後、この杭体の所定の位置に押指
を固定し、押指内部の水を排出覆る工程を包含する仮設
橋の構築方法である。
Structure This invention provides a push finger having a watertight elongated box-shaped 4M structure that can float on the water surface like a ship's hull, an antibody that is engaged with the push finger so as to be able to rise and fall freely, and this antibody on the push finger. Place the temporary bridge part side that has fixable members etc. at a predetermined position, lower the antibody at that position, touch the tip to the bottom of the water, fix the antibody to the pusher finger, and then attach the watertight pusher finger. The weight of the push finger and water is applied to the pile body by placing water inside) and the weight of the water is driven into the bottom of the water, and after the body sinks to a depth that can withstand a specified load m, This method of constructing a temporary bridge includes the steps of fixing push fingers in position, draining water inside the push fingers, and covering them.

この発明の基本的な考えの概要はつぎのようなものであ
る。
The basic idea of this invention is summarized as follows.

1、押指に水を入れ、押指と水の重量によって、抗体を
水底に打ち込み、水を満たした押指が水面上に完全に現
われた状態で抗体の沈下が止まったとするとこの状態は
、押指の自重ど水の重量の合d1が杭体の支持力と釣合
っているわけである。
1. Fill the push finger with water, use the weight of the push finger and the water to drive the antibody to the bottom of the water, and assume that the antibody stops sinking when the water-filled push finger completely appears above the water surface.This state is as follows. The sum d1 of the dead weight of the push finger and the weight of the water balances the supporting force of the pile body.

2、この状態で押指内の水を抜くと、杭体の支持力は押
指内の水の重量に相当するだけ余力があるはずである。
2. If the water inside the push finger is drained in this state, the supporting force of the stake body should have a surplus equivalent to the weight of the water inside the push finger.

そしてこれが桟橋または橋としての支持力になる。This becomes the supporting capacity of a pier or bridge.

3、更にこの応用として、押指内の水を抜いた後、押指
を水中に浮かばせた状態にお()ばその排水量に相当す
るだ(プの浮力が得られ桟橋または橋の支持力が増大す
ることになる。
3. Furthermore, as an application of this, if the water in the push finger is drained and the push finger is left floating in the water (), a buoyancy equivalent to the amount of water discharged can be obtained, which increases the supporting capacity of the pier or bridge. will increase.

この方法によって仮設した桟橋やm梁は杭体によって支
持されているので浮橋に比較して位置の安定性がよいわ
けである。
Piers and m-beams constructed temporarily using this method are supported by pile bodies, so their positional stability is better than that of floating bridges.

この発明の一興体例を図面を参照して説明すると、第1
図−a乃至fは海岸のように水位の変動のあるところで
この発明を実施する工程を説明したものである。
An example of this invention will be explained with reference to the drawings.
Figures a to f explain the process of implementing the present invention in places where the water level fluctuates, such as on the coast.

第2図はこの発明の方法に用いる押指の一具体例の構造
を示す一部裁断平面図、 第3図は、第2図の押指の一部裁断側面図、第4図は抗
体の上部の構造を示す説明図、第5図は抗体とガイドの
関係を示す説明図である。
FIG. 2 is a partially cutaway plan view showing the structure of a specific example of the pusher finger used in the method of the present invention, FIG. 3 is a partially cutaway side view of the pusher finger shown in FIG. 2, and FIG. FIG. 5 is an explanatory diagram showing the structure of the upper part, and FIG. 5 is an explanatory diagram showing the relationship between the antibody and the guide.

まず第1図−aに示すように押指1を海岸に近い所定の
位置に曵抗して、杭体2を下げその先端部を海底に接地
させる。
First, as shown in FIG. 1-a, the push finger 1 is towed to a predetermined position near the coast, and the pile body 2 is lowered so that its tip touches the seabed.

つぎに、杭体2の先端部に、第3図に示すように、頂上
に滑車を備えたキャップ3を取付け、懸垂索4を架設す
る。この懸垂索4の一端はウィンチ16によって巻き上
げられるようになっている。
Next, as shown in FIG. 3, a cap 3 having a pulley at the top is attached to the tip of the pile body 2, and a suspension cable 4 is installed. One end of the suspension cable 4 is wound up by a winch 16.

押指は内部が仕切1513によって区切られた4つの水
槽12に分かれており、中央に給排水ポンプ11、吸水
弁6、各水槽12に通じる給排水弁7を備えたポンプ室
15がある。給排水ポンプ11からは給排水管5が各水
槽の仕切壁13に設けられている給水弁8および全体の
排水弁9に連結されており、これら弁とポンプとによっ
て各水槽に対する水の給+71水を制御できる。
The inside of the push finger is divided into four water tanks 12 separated by partitions 1513, and in the center there is a pump chamber 15 equipped with a water supply and drainage pump 11, a water intake valve 6, and a water supply and drainage valve 7 communicating with each water tank 12. A water supply and drainage pipe 5 from the water supply and drainage pump 11 is connected to a water supply valve 8 provided on the partition wall 13 of each water tank and an overall drainage valve 9, and these valves and the pump supply +71 water to each water tank. Can be controlled.

杭体2は押指1の外壁に取付けられた杭のる。The pile body 2 is a pile attached to the outer wall of the push finger 1.

この杭体2の接地と懸垂索4の架設が終了したら吸水弁
6を開いてポンプ室15内に水を導入し、更に各水槽の
給排水弁7を開いて各水槽12内に水を導入すると第1
図−bに示すように押指1が沈み始める。水槽12内に
必要量の水が入ったら吸水弁6および給排水弁7を閉じ
る。
When the grounding of the pile body 2 and the erection of the suspension rope 4 are completed, the water intake valve 6 is opened to introduce water into the pump chamber 15, and the water supply and drainage valves 7 of each water tank are opened to introduce water into each water tank 12. 1st
As shown in Figure b, the push finger 1 begins to sink. When the required amount of water enters the water tank 12, the water intake valve 6 and the water supply/drainage valve 7 are closed.

潮位を利用する場合は、ここまでの作業を満潮時に行な
い、この後は懸垂索を張った状態で第1図−〇に示すよ
うに干潮を迎える。
If the tide level is to be used, the work up to this point should be carried out at high tide, and then the ropes will be stretched out until low tide as shown in Figure 1-0.

このとぎに押指1と水槽12内に入った水との合計の重
量が杭体2に作用するので杭体2は水底に打ち込まれる
At this point, the total weight of the push finger 1 and the water that has entered the water tank 12 acts on the pile body 2, so that the pile body 2 is driven into the water bottom.

潮位の変動が小さいか、あるいはそれが全くない内水面
の場合にはウィンチ1Gを作動させて懸垂索4を巻き上
げて押指1を水面上まで上昇させれば杭体に対する作用
は同じである。
In the case of inland water where fluctuations in the tide level are small or not at all, the effect on the pile body will be the same if the winch 1G is activated to wind up the suspension cable 4 and raise the push finger 1 above the water surface.

M イ木 2の it T −h< プン 宇 寸 7
)斗 ’T” r’1i −/ #、1 (’、 n)
操作により押指1のバランスを維持する。また、この際
各水槽への給排水弁7と給排水ポンプ11と給水弁8を
操作することにより各水槽12内の水重量の微調整を行
なって、押指1の水平および6杭への荷重を調節づる。
M Iki 2's it T -h< Pun U size 7
) dou 'T'r'1i −/ #, 1 (', n)
The balance of the push finger 1 is maintained by the operation. At this time, the water weight in each tank 12 is finely adjusted by operating the water supply/drainage valve 7, water supply/drainage pump 11, and water supply valve 8 to each tank, thereby reducing the horizontal load of the push finger 1 and the load on the 6 stakes. Adjustment lever.

こうして6杭の沈下が安定したら排水をする。これには
、各水槽の吸排水弁7および排水弁9を聞き、ボン°プ
室15に水を導入しつつポンプ11を運転して、各水槽
12から流出する水を排水口10から排出する。
Once the sinking of the 6 piles has stabilized, drain the water. To do this, listen to the intake/discharge valve 7 and drain valve 9 of each tank, operate the pump 11 while introducing water into the pump chamber 15, and discharge the water flowing out from each tank 12 from the drain port 10. .

これで杭打ち、押指の準備が完了したことになる。この
後、桟橋または橋としての使用状況に応じ、第1図−d
のように懸垂索をゆるめて押指を下降させてその一部が
水中に没する程度にすればその部分の排水mに相当する
だけ負荷に耐える余力が大になる。
This completes the preparation for stake driving and pushing. After this, depending on the usage situation as a pier or a bridge, Figure 1-d
If the suspension rope is loosened and the push finger is lowered so that part of it is submerged in the water, the remaining power to withstand the load will be increased by the amount equivalent to the drainage m of that part.

こうして仮設した桟橋または橋の使用後、ぞれらを撤去
づるとぎは、上記手順によって押指1を沈めるか、ある
いは干潮を利用して水位が下った状態で杭を切断する。
After the temporary piers or bridges have been used, they are removed and the piles are either submerged using the steps described above, or the piles are cut while the water level is lowered using low tide.

その位置は杭が再び浮上した時の下部ガイドの位置より
下の位置(第1図−eのm位置)で切断する。
The cut is made at a position below the position of the lower guide when the pile floats again (position m in Figure 1-e).

押指1を浮上させるか、または満潮を利用して押指を上
背させ、切断した杭の頂部より下部ガイド14の位置が
高くなったときに杭体2から押指を離脱させることがで
きる。
The pusher finger 1 can be floated or the pusher finger can be moved upward using high tide, and when the position of the lower guide 14 is higher than the top of the cut pile, the pusher finger can be detached from the pile body 2. .

効 果 以上説明したように、この発明によれば、大11)すな
杭打ら作業をせずに、桁材の架設と同時に杭打ち作業を
進めることができ、しがも安定性のJ:い仮設橋を簡単
に設置J5よび撤去覆ることができる。
Effects As explained above, according to the present invention, the pile driving work can be carried out at the same time as the girder material is being erected, without the need for the pile driving work. : Temporary bridges can be easily installed and removed.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図−a乃至第1図−fは、この発明の−具体例の工
程を示す説明図、 第2図は、この発明の方法に用いる押指の具体例の構造
を示す一部裁断平面図、 第3図、上記第2図の押指の一部裁断側面図、第4図は
、抗体の上部の14349を示づ説明図、第5図は、抗
体とガイドの関係を示J゛説明図である。 1・・・押指、2・・・杭体、3・・・キャップ、4・
・・懸垂索、5・・・給排水管、6・・・吸水弁、7・
・・各水槽の給排水弁、8・・・給水弁、9・・・全体
の排水弁、10・・・排水口、11・・・給排水ポンプ
、12・・・水槽、13・・・仕切り壁、14・・・杭
のガイド、15・・・ポンプ空、16・・・ウィンチ、
A・・・潮位を示づ゛目盛、■・・・杭の切断位置、特
許出願人 松 村 憲 二 代理人 弁理士 小 松 秀 岳 代理人 弁理士 旭 宏
Figures 1-a to 1-f are explanatory diagrams showing the steps of a specific example of the present invention, and Figure 2 is a partially cut plane showing the structure of a specific example of the pressing finger used in the method of the present invention. Figure 3 is a partially cutaway side view of the pressing finger in Figure 2 above, Figure 4 is an explanatory diagram showing the upper part of the antibody 14349, Figure 5 is a diagram showing the relationship between the antibody and the guide. It is an explanatory diagram. 1... Pressing finger, 2... Pile body, 3... Cap, 4...
... Suspension rope, 5... Water supply and drainage pipe, 6... Water intake valve, 7.
... Water supply and drainage valve for each water tank, 8 ... Water supply valve, 9 ... Overall drainage valve, 10 ... Drain port, 11 ... Water supply and drainage pump, 12 ... Water tank, 13 ... Partition wall , 14...Pile guide, 15...Pump empty, 16...Winch,
A... Scale indicating the tide level, ■... Cutting position of the pile, Patent applicant: Kenji Matsumura, Patent attorney: Hide Komatsu, Attorney: Hiroshi Asahi, Patent attorney

Claims (1)

【特許請求の範囲】[Claims] 船体のように水面■こ浮くことができる水蜜性の精長い
箱形の構造を有する押指と、これに対して昇降自在に係
合された杭体J3よびこの杭体を押指に固定し得る部材
とを有する仮説橋部材を所定の位置に配置し、その位置
で抗体を降下させてその先端を水底に接地させ、杭体を
押指に固定した後、水密性の上記押指内部に水を満たず
ことによって、杭体に押指と水の重量を作用させ、抗体
を水底に打ち込み、杭体が所定の荷重に耐える深さまで
沈下した後、この杭イホの所定の位置に押指を固定し、
押指内部の水を排出する工程を包含づる仮段橋の構築方
法。
A pusher finger having an elongated, water-like box-shaped structure that can float on the water surface like a ship's hull, a stake body J3 that is engaged with the pusher finger so as to be able to rise and fall freely, and this pile body is fixed to the pusher finger. A hypothetical bridge member having a member to be obtained is placed at a predetermined position, the antibody is lowered at that position, its tip is grounded to the bottom of the water, and the pile body is fixed to the pusher finger, and then the antibody is placed inside the watertight pusher finger. By not filling the pile with water, the weight of the push finger and water acts on the pile body, the antibody is driven into the water bottom, and after the pile body sinks to a depth that can withstand the specified load, the push finger is pushed into the specified position of the pile body. fixed,
A method for constructing a temporary bridge that includes the process of draining water from inside the bridge.
JP4194384A 1984-03-07 1984-03-07 Construction of temporary constructed bridge Granted JPS60188505A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4194384A JPS60188505A (en) 1984-03-07 1984-03-07 Construction of temporary constructed bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4194384A JPS60188505A (en) 1984-03-07 1984-03-07 Construction of temporary constructed bridge

Publications (2)

Publication Number Publication Date
JPS60188505A true JPS60188505A (en) 1985-09-26
JPH0319323B2 JPH0319323B2 (en) 1991-03-14

Family

ID=12622291

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4194384A Granted JPS60188505A (en) 1984-03-07 1984-03-07 Construction of temporary constructed bridge

Country Status (1)

Country Link
JP (1) JPS60188505A (en)

Also Published As

Publication number Publication date
JPH0319323B2 (en) 1991-03-14

Similar Documents

Publication Publication Date Title
US4014177A (en) Marine pier having deeply submerged storage container
US5049004A (en) Underwater building and constructing method thereof
US3528254A (en) Offshore platform structure and construction method
US3516259A (en) Offshore structure method and apparatus
US4063426A (en) Three column tower
CN101837929B (en) Operation method for lifting fan for barge in shoal area
KR860007432A (en) Jacket tower structure and its installation method
US2657540A (en) Method of erecting and positioning marine structures
US3624702A (en) Offshore platform support
GB1580667A (en) Underwater structures
US3186180A (en) Offshore well drilling and oil storage platform
JPS60188505A (en) Construction of temporary constructed bridge
GB1576581A (en) Platforms comprising an underwater structure and in their method of assembly
JPS5837449B2 (en) It&#39;s important to know what&#39;s going on.
NO802944L (en) PROCEDURE FOR SEA-TRANSPORTED FACILITIES FOUNDED ON COUNTRY
US20130074758A1 (en) Anchoring apparatus for wave energy converters
JP2669317B2 (en) Construction method of gravity type offshore structure and its structure
JPH09143922A (en) Pontoon bridge mooring method and device
Gibson et al. The influence of geotechnical engineering on the evolution of offshore structures in the North Sea
CN102535390A (en) Construction method of anti-wave-type offshore platform
GB2196675A (en) Offshore platform system
SU1537750A1 (en) Deep-water stationary offshore platform and method of erecting same
CN115649370A (en) Control method of water surface floating platform
WO2015052295A1 (en) Gravity founding
JPS62174410A (en) Settlement of marine structure