JPS60109499A - Concrete solidifying apparatus - Google Patents
Concrete solidifying apparatusInfo
- Publication number
- JPS60109499A JPS60109499A JP58217298A JP21729883A JPS60109499A JP S60109499 A JPS60109499 A JP S60109499A JP 58217298 A JP58217298 A JP 58217298A JP 21729883 A JP21729883 A JP 21729883A JP S60109499 A JPS60109499 A JP S60109499A
- Authority
- JP
- Japan
- Prior art keywords
- vibrator
- compaction
- concrete
- jack
- oscillator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
本発明はシールドトンネル構築の場所打ちコンクリート
の締固め装置に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a compaction device for cast-in-place concrete for constructing shield tunnels.
シールドトンネル構築工法としては従来は一次覆工、裏
込め注入、二次覆工の三工程によシ構成される複雑な工
法が採用されていたが稜近に到り上記の工法の欠点を改
良し、場所打ちコンクリート打設により1回のコンクリ
ート打設によりトンネル覆工をおこなう工法が採用きれ
ている。この場所打ちコンクリートにおいては一度に大
量のコンクリートが注入されるのでトンネル工事におけ
るこの覆工コンクリートの締固めはコンクリートの強度
維持ならびに品質上重要な要素と寿っている。Conventionally, the shield tunnel construction method used was a complicated method consisting of three steps: primary lining, backfill injection, and secondary lining, but as we approached the ridge, we improved the drawbacks of the above method. However, the method of lining tunnels using cast-in-place concrete casting in a single concrete casting process has been adopted. In cast-in-place concrete, a large amount of concrete is injected at once, so compaction of the lining concrete during tunnel construction is an important factor in maintaining the strength and quality of the concrete.
従来このトンネルにおける覆工コンクリートの締固めは
、その型枠に取付けられたバイブレータによシ行なわれ
ているのが殆んどであり、またその締固め時間も経験的
な値が採用されている。従って(1)型枠の表面付近に
のみ締固めが集中すること、(2)充分に締固められた
か否かの定量的な把握が困難であること、などの欠点を
有していた。Conventionally, most of the compaction of concrete lining in tunnels has been carried out using vibrators attached to the formwork, and empirical values have been adopted for the compaction time. . Therefore, it has disadvantages such as (1) compaction is concentrated only near the surface of the formwork, and (2) it is difficult to quantitatively determine whether or not compaction has been sufficiently achieved.
本発明は、以上のような従来の欠点を改良するとともに
効率のよい締固めをおこない得るコンクリートの締固め
装置を提供することを目的とするものであり、その構成
は電動力により締固め振動を発生させるバイブレータ−
の発振器および突き棒と、このバイブレータの挿入、引
抜きをおこなうバイブレータジヤツキにて構成された締
固め装置において、バイブレータの入力電流を検知する
検知器と、パワーユニットおよび電磁弁により挿入、引
抜き制御がおこなわれるバイブレータジヤツキならびに
計算機構を有し、上記の検知器よりの信号にもとづき計
算機構によシバイブレータの作動時間を算出するととも
にバイブレータの挿入および引抜き時期を算出し、バイ
ブレータジヤツキを作動させる如く構成されたコンクリ
ートの締固め装置であシ、これを実施例の図面について
説明すると、第1図は装置の構成及び作用をあられす略
断面および制御のブロック図であり、1はトンネル掘削
のシールドマシンのスキンプレート、2はトンネル覆工
の型枠であシ3は既に打設が完了した個所のコンクリー
ト覆工部、4はコンクリート注入が行なわれたばかりの
未締固め部であり、これは妻型枠5によシコンクリート
がトンネル内部に流出するのを防止している。第2図は
この妻型枠5の正面部分図であ多妻型枠5の正面部には
注入されたコンクリート締固め用のバイブレータを挿入
するためにその円周に適宜間隔を維持して塞ぎ板6が取
付けられている。The object of the present invention is to provide a concrete compaction device that can improve the above-mentioned conventional drawbacks and perform efficient compaction, and its configuration uses electric power to suppress compaction vibrations. vibrator to generate
The compaction device consists of an oscillator and thrust rod, and a vibrator jack that inserts and extracts the vibrator.Insertion and extraction are controlled by a detector that detects the input current of the vibrator, a power unit, and a solenoid valve. It has a vibrator jack and a calculation mechanism that calculates the operating time of the vibrator based on the signal from the above-mentioned detector, and also calculates the timing of inserting and removing the vibrator, and operates the vibrator jack. This is a concrete compaction device constructed as shown in FIG. The skin plate of the machine, 2 is the formwork for the tunnel lining, 3 is the concrete lining part where pouring has already been completed, and 4 is the uncompacted part where concrete has just been poured. The formwork 5 prevents concrete from flowing into the tunnel. Fig. 2 is a front partial view of this multi-gable formwork 5.The front part of the multi-gable formwork 5 is provided with a closing plate at an appropriate interval around its circumference in order to insert a vibrator for compacting the poured concrete. 6 is installed.
塞ぎ板6は例えば硬質ゴムの如くある程度の強度を有し
、且弾性のある材質にて作られ、第3図の如くその中央
部に切込み7を設けることによシ内部に注入されたコン
クリートの流出は充分に防止する強度は有しているが、
パイブレークなどの剛性を有する突き棒などは挿入容易
となっている。バイブレータの突き神8はこの塞ぎ板6
の弾性部の切込み7よりコンクリートの未締固め部4に
挿入される。バイブレータ−は突き棒8、電動力による
発振器9および液圧または空圧などにより推進および引
抜き制御されるバイブレータジヤツキ1oにより構成さ
れる。The closing plate 6 is made of a material with a certain degree of strength and elasticity, such as hard rubber, and has a notch 7 in its center as shown in FIG. Although it has sufficient strength to prevent leakage,
A rigid push rod such as a pie break can be easily inserted. The vibrator's thrusting god 8 is this blocking plate 6
It is inserted into the uncompacted part 4 of the concrete through the cut 7 of the elastic part. The vibrator is composed of a thrust rod 8, an electric oscillator 9, and a vibrator jack 1o whose propulsion and extraction are controlled by hydraulic or pneumatic pressure.
11は電源であυ、検知器12を介して発振器9および
計算機構13を介してバイブレータジヤツキ10用パワ
ーユニツト14に電力が供給される。検知器12は発振
器9に送られる電力の電流値を検知し、この電流信号を
計算機構13に送る。計算機構13は前記の電流信号に
基づき電磁弁15を作動させバイブレータジヤツキ10
の推進および引抜きの制御をおこなうとともに発振器9
の負荷電流値より締固め時間を算出する機構を有してい
る。Reference numeral 11 denotes a power supply, and power is supplied to a power unit 14 for the vibrator jack 10 via a detector 12, an oscillator 9, and a calculation mechanism 13. The detector 12 detects the current value of the power sent to the oscillator 9 and sends this current signal to the calculation mechanism 13. The calculation mechanism 13 operates the solenoid valve 15 based on the above-mentioned current signal, and the vibrator jack 10
The oscillator 9 controls the propulsion and extraction of the
It has a mechanism to calculate the compaction time from the load current value.
以上の如く構成されている装置においてこれを作動せし
める場合は先づバイブレータの突き棒8がバイブレータ
ジヤツキ10によシ推進され塞ぎ板6部より打設された
コンクリートの未締固め部4に挿入され発振器9によシ
振動が突き棒8に伝えられ締固めが開始される。この場
合突き棒8が充分にコンクリート中に挿入されていない
過程ならびにコンクリートの締固めが不充分な過程にお
いては発振器9の負荷電流は小さく、つぎに突き棒8が
充分にコンクリート中に挿入されかつ締固めが進行する
とともに発振器9の負荷電流は大きくなる。従ってここ
で検知器12により発振器9に送られる電流値を検知す
ることによシ締固めの程度を検知することができる。更
にこの1本の突き棒8により締固めるコンクリートの量
においても、この量が多い場合には締固めに時間がかが
り、この量が少い場合には早く締固めが完了し、この傾
向は検知器12にて検知される電流値の時間に対する増
加の割合を検知することにょシ締固めの途中においても
締固め時間を計算することができる。ここで発振器9の
電流値が突き棒8の挿入程度および締固め程度より定め
られる最適締固めの値に達したならば作業が完了し計算
機構13よシミ磁井15を介してバイブレータジヤツキ
10が作動し、突き神8が抜き出され、締固め作業の1
−サイクルが完了する。When operating the apparatus configured as described above, the vibrator thrust rod 8 is first propelled by the vibrator jack 10 and inserted into the uncompacted part 4 of the poured concrete through the closing plate 6. The oscillator 9 transmits the vibration to the thrust rod 8, and compaction is started. In this case, the load current of the oscillator 9 is small in the process where the ramming rod 8 is not fully inserted into the concrete or when the concrete is insufficiently compacted; As the compaction progresses, the load current of the oscillator 9 increases. Therefore, by detecting the current value sent to the oscillator 9 by the detector 12, the degree of compaction can be detected. Furthermore, regarding the amount of concrete compacted by this single ramming rod 8, if this amount is large, compaction will take time, and if this amount is small, compaction will be completed quickly, and this tendency can be detected. The compaction time can be calculated even during compaction by detecting the rate of increase in the current value detected by the device 12 over time. When the current value of the oscillator 9 reaches the optimum compaction value determined from the insertion degree of the ramming rod 8 and the compaction degree, the work is completed and the vibrator jack 10 is activated, Tsukigami 8 is pulled out, and compaction work 1 is started.
- The cycle is complete.
本発明に係るコンクリートの締固め装置は上記の如き構
成および作用を有するものであり、従って従来コンクリ
ートの締固めの定量的な把握は困難で多分に経験的な勘
に頼っていたものを定量的に電流値にて把握することに
ょシ確実に締固めを行いうるとともに無駄な締固めをお
こなうこともなく、またバイブレータがコンクIJ −
トの内部にまで達するので表面のみ々らず、内部をも確
実に締固めをおこなうことができ、作業時間を短縮する
とともに品質のよいコンクリート覆工ができるものであ
る。The concrete compaction device according to the present invention has the above-described configuration and function, and therefore quantitatively grasps the compaction of concrete, which was previously difficult to grasp and relied largely on empirical intuition. Compaction can be performed reliably by checking the current value, and unnecessary compaction is not performed.
Since it reaches the inside of the concrete, it is possible to reliably compact not only the surface but also the inside, reducing work time and producing high-quality concrete lining.
第1図は本発明の装置の構成作用をあられす略断面およ
び制御のブロック図、第2図は第1図の妻型枠の正面部
分図、第3図は塞ぎ板の拡大正面図である。
8・・・突き棒 9・・・発振器 10・・・ジヤツキ
11・・・電源 12・・・検知器 13・・・計算
機構 14・・・パワーユニット 15・・・電磁弁
出 願 人 株式会社 間 綴
代 理 人 弁理士 高 雄次部
第1図Fig. 1 is a schematic cross-sectional view and control block diagram showing the configuration and operation of the device of the present invention, Fig. 2 is a partial front view of the gable form shown in Fig. 1, and Fig. 3 is an enlarged front view of the closing plate. . 8... Thrust rod 9... Oscillator 10... Jacket 11... Power supply 12... Detector 13... Calculation mechanism 14... Power unit 15... Solenoid valve applicant: Company, Ltd. Tsuzuriyo Rihito Patent Attorney Yuji Taka Department Figure 1
Claims (1)
バイブレータジヤツキの挿入、引抜き制御をおこなうパ
ワーユニットおよび電磁弁と、上記検知器よシの信号に
もとづきバイブレータおよびパイプレークジヤツキを制
御する計算機構よシなシ、上記検知器よシの信号にもと
づき計算機構によシバイブレータの作動時間の算出およ
びバイブレータジヤツキによる挿入、引抜きを制御する
如く構成せられたコンクリートの締固め装置。(1) A detector that detects the input current of the vibrator,
A power unit and a solenoid valve that control the insertion and withdrawal of the vibrator jack, and a calculation mechanism that controls the vibrator and pipe release jack based on the signals from the above-mentioned detector. A concrete compaction device configured to calculate the operating time of a vibrator by a calculation mechanism and to control insertion and withdrawal by a vibrator jack.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP58217298A JPS60109499A (en) | 1983-11-18 | 1983-11-18 | Concrete solidifying apparatus |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP58217298A JPS60109499A (en) | 1983-11-18 | 1983-11-18 | Concrete solidifying apparatus |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS60109499A true JPS60109499A (en) | 1985-06-14 |
JPH0363640B2 JPH0363640B2 (en) | 1991-10-01 |
Family
ID=16701941
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP58217298A Granted JPS60109499A (en) | 1983-11-18 | 1983-11-18 | Concrete solidifying apparatus |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS60109499A (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63103199A (en) * | 1986-10-16 | 1988-05-07 | 三井建設株式会社 | Shield excavator |
JPS63141294U (en) * | 1987-03-10 | 1988-09-16 | ||
JPH01167494U (en) * | 1988-05-13 | 1989-11-24 | ||
JPH0381498A (en) * | 1989-08-22 | 1991-04-05 | Komatsu Ltd | Direct-placing concrete lining construction method of shield drilling machine |
JPH03233096A (en) * | 1990-02-08 | 1991-10-17 | Taisei Corp | Device for filling of tail void |
JP2015169002A (en) * | 2014-03-07 | 2015-09-28 | 前田建設工業株式会社 | Processing unit of compaction property of fresh concrete |
JP2015169001A (en) * | 2014-03-07 | 2015-09-28 | 前田建設工業株式会社 | Method of determination of compaction property of fresh concrete |
JP2017096070A (en) * | 2015-11-27 | 2017-06-01 | 鹿島建設株式会社 | Concrete placing method and concrete placing structure |
EP4311640A1 (en) * | 2022-07-25 | 2024-01-31 | Wacker Neuson Produktion GmbH & Co. KG | Concrete compacting device with measurement of the compaction progress |
-
1983
- 1983-11-18 JP JP58217298A patent/JPS60109499A/en active Granted
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63103199A (en) * | 1986-10-16 | 1988-05-07 | 三井建設株式会社 | Shield excavator |
JPS63141294U (en) * | 1987-03-10 | 1988-09-16 | ||
JPH01167494U (en) * | 1988-05-13 | 1989-11-24 | ||
JPH0381498A (en) * | 1989-08-22 | 1991-04-05 | Komatsu Ltd | Direct-placing concrete lining construction method of shield drilling machine |
JPH03233096A (en) * | 1990-02-08 | 1991-10-17 | Taisei Corp | Device for filling of tail void |
JP2015169002A (en) * | 2014-03-07 | 2015-09-28 | 前田建設工業株式会社 | Processing unit of compaction property of fresh concrete |
JP2015169001A (en) * | 2014-03-07 | 2015-09-28 | 前田建設工業株式会社 | Method of determination of compaction property of fresh concrete |
JP2017096070A (en) * | 2015-11-27 | 2017-06-01 | 鹿島建設株式会社 | Concrete placing method and concrete placing structure |
EP4311640A1 (en) * | 2022-07-25 | 2024-01-31 | Wacker Neuson Produktion GmbH & Co. KG | Concrete compacting device with measurement of the compaction progress |
Also Published As
Publication number | Publication date |
---|---|
JPH0363640B2 (en) | 1991-10-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS60109499A (en) | Concrete solidifying apparatus | |
JPH0711233B2 (en) | Non-removing earth construction device for foundation piles and non-removing earth construction method for foundation piles | |
JPH08177395A (en) | Lining concrete compaction device for tunnel construction method | |
JPS60105800A (en) | Construction of shield tunnel | |
JPS5924099A (en) | Method of shield construction | |
JPH0828190A (en) | Cast-in-place lining shield construction method and shield excavating machine | |
GB1530228A (en) | Apparatus for use in the production of a concrete rammed pile | |
JP3305665B2 (en) | Backing equipment of earth retaining support frame | |
JPS60109498A (en) | Concrete casting method | |
JP2681511B2 (en) | Vertical shaft structure of shield machine starting part, its construction method, and start / arrival method of shield machine using the structure | |
JPS5724720A (en) | Increasing method for pull resistance of structure material driven into ground | |
JPH0381498A (en) | Direct-placing concrete lining construction method of shield drilling machine | |
JPH05295994A (en) | Direct placing shield lining method | |
JPS6238485B2 (en) | ||
JPS579920A (en) | Extracting method for pile and equipment thereof | |
JP2526312B2 (en) | Shield machine and in-situ lining type shield construction method using the machine | |
JP2534898B2 (en) | In-situ concrete concrete tunneling method | |
JPH0631553B2 (en) | Shield excavation method and shield excavator for implementing this method | |
JPS63103199A (en) | Shield excavator | |
JPH05118194A (en) | Sealing method of lining in cast-in-place lining shield method | |
JP3217751B2 (en) | Formwork plate for forming concrete pile riser | |
JPH01247698A (en) | Cast-in-place shield construction | |
JPH08158360A (en) | Treating method for extra-fill concrete on cast-in place concrete pile | |
JPH01271600A (en) | Concrete placing for cast-in-place concrete lining construction | |
JPH0243499A (en) | Method and device for executing cast-in-place lining shield |