JPS5948252B2 - Caisson installation method - Google Patents
Caisson installation methodInfo
- Publication number
- JPS5948252B2 JPS5948252B2 JP9149581A JP9149581A JPS5948252B2 JP S5948252 B2 JPS5948252 B2 JP S5948252B2 JP 9149581 A JP9149581 A JP 9149581A JP 9149581 A JP9149581 A JP 9149581A JP S5948252 B2 JPS5948252 B2 JP S5948252B2
- Authority
- JP
- Japan
- Prior art keywords
- caisson
- membrane
- rubble
- foundation
- mortar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/16—Jointing caissons to the foundation soil, specially to uneven foundation soil
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
Description
【発明の詳細な説明】
本発明は水底に造成した捨石基礎上にケーソンを据付け
るケーソン据付工法に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a caisson installation method for installing a caisson on a rubble foundation prepared at the bottom of a water body.
一般に海底へのケーソン据付工事においては捨石基礎が
用いられているところである。Generally, rubble foundations are used in the installation work of caissons on the seabed.
この捨石基礎の施工は通常ガツト船等により海上より捨
石を投入した後、捨石基礎の上面を均一に均す必要があ
る。To construct this rubble foundation, it is usually necessary to load the rubble from the sea using a boat or the like, and then level the top surface of the rubble foundation evenly.
その捨石基礎表面の均し方法としては従来、潜水夫によ
る手作業の均し工法、スクリードによる均し工法がある
が、潜水夫による手作業の均し工法ば潜水作業時間に制
限があり、しかも手作業で捨石を一個づつ移動させるも
のであるため能率的でなく、また潜水夫が不足しつつあ
る現在、その人員確保が困難となっており、特に工期の
短縮を計らなければならない大規模工事においては施工
が困難である等の問題がある。Traditional methods of leveling the surface of the rubble foundation include manual leveling by divers and screeding, but manual leveling by divers has a limit on the amount of time required for diving. It is not efficient as it involves moving rubble one by one by hand, and with the current shortage of divers, it is becoming difficult to secure such personnel, especially for large-scale construction projects that require shortening the construction period. There are problems such as difficulty in construction.
また、近年海岸線の開発が進み波浪や水深の面で海象条
件の悪い場所での工事が要求されつつあり、潜水夫によ
る均し作業が不可能な工事計画がなされつつある。Furthermore, as coastlines have been developed in recent years, construction work is being required to be carried out in areas with poor sea conditions in terms of waves and water depth, and construction plans are being made that make leveling work by divers impossible.
またスクリードによる均し工法は、捨石基礎表面に水平
ホッパーを移動させつつ小石を敷設して水平方向に均す
方法であるが、これは大規模に均す事が必要であるため
機械が大型化し、かつ捨石が大きくなるに従って機械の
大きさも幾何級数的に大きくなって高価となる。In addition, the leveling method using a screed involves moving a horizontal hopper to the surface of the rubble foundation and laying pebbles to level the surface in the horizontal direction, but this requires large-scale leveling, which requires a large machine. , and as the rubble becomes larger, the size of the machine becomes exponentially larger and becomes more expensive.
また均した後が必ずしも満足できず補助工法が必要であ
り、しかも準備工事が大規模で大型工事にしか使用し得
す装置類等のための投資額が大きく、使用効率が悪いた
め経済的に不利とならざるを得す、更に投入管理を誤る
ともどり作業が生じる等の問題があった。In addition, the leveling process is not always satisfactory and auxiliary methods are required.Moreover, the preparatory work is large-scale, and the investment amount for equipment that can only be used for large-scale construction is large, making it difficult to use economically. In addition, there were problems such as incorrect input management resulting in return work.
本発明は上述のような各種従来工法の問題にかんがみ、
特に大水深地域における大型のケーソンの設置に際して
、大形の捨石を使用する場合に捨石基礎表面の手作業も
しくは機械力による均し作業を簡略化し、かつ安定した
ケーソンの据付けがなし得られるケーソン据付工法の提
供を目的としたもので゛ありその要旨とするところはケ
ーソンの底面の少くとも周縁部に仮受用の突部を形成し
て中央部分を凹溝を連続もしくは不連続に設け、その凹
溝内にモルタル等注排孔の下端を開口させ、該ケーソン
の底面に気密性膜をたるませて張設し、前記注排孔より
吸気して該膜をケーソン底部の空間内に密着させておき
、該ケーソンを、基礎地盤上に捨石を投下して所望高さ
に造成し、その上面に数箇所に前記ケーソン底面の仮受
用突部に対応させてケーソン仮受部を形成した捨石基礎
上に設置し、その後前記注排孔より膜内にモルタルを注
入してケーソンの底面を捨石基礎間の空隙を埋ることを
特徴としてなるケーソン据付工法に存する。The present invention has been developed in consideration of the problems of various conventional construction methods as mentioned above.
Caisson installation that simplifies manual or mechanical leveling of the rubble foundation surface when large rubble is used, especially when installing large caissons in deep water areas, and allows for stable caisson installation. This method is intended to provide a construction method, and its gist is to form a protrusion for temporary support on at least the periphery of the bottom of the caisson, and to provide continuous or discontinuous grooves in the center of the caisson. The lower end of the mortar injection and drainage hole is opened in the groove, and an airtight membrane is stretched loosely on the bottom of the caisson, and air is sucked through the injection and drainage hole to tightly fit the membrane into the space at the bottom of the caisson. Then, the caisson is built on a rubble foundation with rubble stones thrown onto the foundation ground to a desired height, and temporary support parts for the caisson are formed at several places on the top surface corresponding to the protrusions for temporary support on the bottom of the caisson. The caisson installation method is characterized in that mortar is injected into the membrane through the injection hole and the bottom of the caisson fills the gap between the rubble foundations.
次に本発明の実施の一例を図面について説明する。Next, an example of implementation of the present invention will be described with reference to the drawings.
まず第1図に示すように従来と同様にガツト船等を使用
して水底の基礎地盤上に捨石1を投入する。First, as shown in Fig. 1, rubble 1 is thrown onto the foundation ground at the bottom of the water using a boat or the like as in the past.
この捨石の投入に際しては所望の捨石基礎の断面形状に
近い形状に造成されるように投入管理を行う。When introducing this rubble, the input is controlled so that it has a shape close to the cross-sectional shape of the desired rubble foundation.
このようにして投入された捨石基礎2の表面の数箇所に
ケーソン仮受部3を形成する。Temporary caisson support portions 3 are formed at several locations on the surface of the rubble foundation 2 thrown in this way.
この仮受部3は設置されるケーソンAの据付は高さに合
わせて、その高さを精度よく設定するものであり、その
ケーソン仮受部の形成は例えば第2図イに示すように捨
石1を必要な分だけ均してケーソン仮受部3としてもよ
くまた第2図口に示すように砂袋5を役人造成した捨石
基礎2の表面に積み上げてもよく、更に第2図ハに示す
ように杭4を使用してもよく、この場合膜の立設は捨石
投入前にあらかじめ地盤中に打ち込んでおいてもよく投
入後に打ち込んでもよいものである。The height of this temporary receiving part 3 is precisely set according to the installation height of the caisson A to be installed, and the formation of the temporary receiving part of the caisson is, for example, by using rubble as shown in Fig. 2 A. 1 may be leveled as much as necessary to form the caisson temporary support part 3.Also, sand bags 5 may be piled up on the surface of the rubble foundation 2 constructed by the government as shown in the opening of Figure 2. As shown, piles 4 may be used, and in this case, the membrane may be erected by driving them into the ground before putting in the rubble, or by driving them after putting in the rubble.
これらのケーソン仮受部3の形成作業はいずれも潜水夫
によって行い、常法によりその高さを測定して十数cm
程度の誤差範囲に精度よく仕上げる。The work of forming these temporary caisson support parts 3 was carried out by divers, and the height was measured using a conventional method and was approximately 10 cm.
Accurately finish within a certain error range.
このようにして突設したケーソン仮受部3上にケーソン
Aの底面を仮受けさせるのであるがこのケーソンAは第
3図〜第4図に示すようにその底面に仮受用の突部6が
一体に形成されている。In this way, the bottom surface of the caisson A is temporarily received on the protruding caisson temporary receiving portion 3, and as shown in FIGS. It is formed in one piece.
この突部6は少くともそのケーソン底面の周縁部に連続
して形成し、底面中央部分を凹ませた空間aが形成され
ている。This protrusion 6 is formed continuously at least at the peripheral edge of the bottom of the caisson, and a space a is formed by recessing the center of the bottom.
更にケーソン底面のその凹ませた部分に断面が略半円形
状の凹溝7が形成されている。Further, a groove 7 having a substantially semicircular cross section is formed in the recessed portion of the bottom surface of the caisson.
この凹溝7は格子状配置に複数本を連続させて設けられ
ている。A plurality of grooves 7 are successively provided in a grid-like arrangement.
なお格子状の外に連続することなく、並列配置に設けて
もよいものである。Note that they may be arranged in parallel without being continuous outside the grid.
そして、この凹溝7の複数箇所にモルタル、空気等の注
排孔8の下端が開口されている。The lower ends of the holes 8 for injecting and discharging mortar, air, etc. are opened at a plurality of locations in the groove 7.
この注排孔8はケーソンAの縦壁9内を通りケーソンA
の上端に開口されている。This injection hole 8 passes through the vertical wall 9 of the caisson A.
It is opened at the upper end.
そしてかかる構造のケーソンAには第7図に示すように
底面全体を覆って気密性の膜10を装着している。As shown in FIG. 7, the caisson A having such a structure is equipped with an airtight membrane 10 covering the entire bottom surface.
この膜10は少くともケーソン底部の空間aの内面に沿
って密着され得る程度にたるませて装着し、その周縁部
をケーソン底面の周縁に固着しておくものである。This membrane 10 is installed so as to be loose enough to fit at least closely along the inner surface of the space a at the bottom of the caisson, and its peripheral edge is fixed to the peripheral edge of the bottom of the caisson.
また、この膜10はケーソンAをコンクリート成型と同
時に装着するものであり、第5図に示すようにケーソン
型枠11の底面11aに膜10を敷設した後コンクリー
トを打設する。Further, this membrane 10 is installed at the same time as the caisson A is molded with concrete, and as shown in FIG. 5, concrete is poured after the membrane 10 is laid on the bottom surface 11a of the caisson form 11.
このとき型枠底面11aの上面に部分的にたるみ部分1
2を折り畳んでおいてもよいものである。At this time, there is a partially slack portion 1 on the upper surface of the formwork bottom surface 11a.
2 may be folded.
また、この膜10は第6図に示すように不透気性層10
aと不織布その他連続気泡のスポンジ材等からなる透気
性弾性層10bとからなるものを使用し、透気性弾性層
10bを下側にしてケーソン底面に装置し、ケーソン製
作後ドック内で注水浮上させ脱型する場合ケーソン底面
への水回りを良くし、脱型を容易ならしめるとともに曳
航の際等において膜10の損傷を防止せしめるようにし
ている。Further, this membrane 10 has an air impermeable layer 10 as shown in FIG.
A and an air-permeable elastic layer 10b made of nonwoven fabric or other open-cell sponge material, etc., are installed on the bottom of the caisson with the air-permeable elastic layer 10b facing downward, and after the caisson is fabricated, it is floated with water in a dock. When demolding, water circulation to the bottom of the caisson is improved to facilitate demolding and to prevent damage to the membrane 10 during towing.
なお、膜10の装着はケーソン成型時の他ケーソン成型
後において装着させてもよいものである。The membrane 10 may be attached at the time of molding the caisson or after the caisson is molded.
このようにして膜10を装着したケーソンAを水面上に
浮上させて所望の設置箇所に曳航するのであるがその際
、前述した注排孔8を通して内部の空気を吸引し、ケー
ソン底面と膜10間を真空化し、これによって膜10を
空間aの内面に密着させた状態にしておく、この場合膜
10のたるみは凹溝7内に吸収される。In this way, the caisson A equipped with the membrane 10 is floated above the water surface and towed to the desired installation location. At that time, the air inside is sucked through the above-mentioned injection and discharge hole 8, and the bottom surface of the caisson and the membrane 10 are The gap is evacuated, thereby keeping the membrane 10 in close contact with the inner surface of the space a. In this case, the slack of the membrane 10 is absorbed into the groove 7.
この状態で前述した捨石基礎2のケーソン仮受部3上に
ケーソンの仮受用の突部6を当接させて設置する。In this state, the caisson temporary support protrusion 6 is placed in contact with the caisson temporary support part 3 of the rubble foundation 2 described above.
その後、注排孔8の減圧状態を解除し、その中央部分の
注排孔8′よりモルタル13を注入する。Thereafter, the reduced pressure state of the injection/discharge hole 8 is released, and mortar 13 is injected through the injection/discharge hole 8' in the central portion.
そして注排孔8はモルタル注入検査用として使用する。The injection/discharge hole 8 is used for mortar injection inspection.
このようにしてモルタル注入を行うことによって第8図
に示すようにケーソンAの底面と膜10間にモルタル1
3が充填され、膜10は押し拡げられ捨石基礎2の上面
に密着し、ケーソンAと捨石基礎2間の空隙はモルタル
13により、完全に埋められ、ケーソンA及び後にケー
ソン膜内に充填する土砂の重量は均等に捨石基礎表面に
て支持されることとなる。By injecting mortar in this manner, mortar 1 is placed between the bottom surface of the caisson A and the membrane 10 as shown in FIG.
3 is filled, the membrane 10 is pushed out and brought into close contact with the top surface of the rubble foundation 2, and the gap between the caisson A and the rubble foundation 2 is completely filled with mortar 13, and the caisson A and the earth and sand that will later be filled into the caisson membrane are filled. The weight will be evenly supported on the rubble foundation surface.
本発明のケーソン据付工法は上述のように構成され、ケ
ーソンの設置前の工程として、従来はいずれも捨石基礎
の表面全面を均しており、しかもその均しは荒均し、本
均しの作業が行われていたところであるが本発明は部分
的にケーソン仮受部を設けるのみでよいため、潜水作業
が著しく簡略化されるとともに複数工程の均し作業が不
要となり、更に大がかりな均しのための装置も必要でな
くなり、潜水夫等の特殊技能者も多く要することなく海
象条件の悪い箇所でも能率良く作業ができ、しかも大規
模な工事であっても短期間の施工が可能となったもので
ある。The caisson installation method of the present invention is configured as described above. Conventionally, the entire surface of the rubble foundation is leveled as a process before installing the caisson, and the leveling is rough leveling and regular leveling. However, with the present invention, it is only necessary to partially provide temporary caisson support parts, which greatly simplifies the diving work and eliminates the need for multiple steps of leveling work. This eliminates the need for additional equipment, allows for efficient work even in areas with poor sea conditions, and eliminates the need for many divers and other specialized technicians.Moreover, even large-scale construction can be completed in a short period of time. It is something that
また捨石基礎へのケーソンの設置はまず数箇所の仮受部
上に設置されるものであるため、その仮受部の高さ精度
が容易に得られ、従ってケーソンは精度の高さ位置に設
置が可能となり、しかもケーソン底面と捨石基礎間はモ
ルタルが充填されるため両者の完全密着が可能となり安
定性は極めて高いものとなし得ることとなり、更にモル
タルの注入は気密性膜内になされるため流失がなく、確
実なモルタル充填がなし得られ、据付後の信頼性か゛向
上されたものである。In addition, when installing a caisson on a rubble foundation, it is first installed on several temporary supports, so the height accuracy of the temporary supports can be easily obtained, and therefore the caisson can be installed at the precisely high position. Furthermore, since mortar is filled between the bottom of the caisson and the rubble foundation, complete adhesion between the two is possible, resulting in extremely high stability.Furthermore, the mortar is injected into the airtight membrane. There is no leakage, reliable mortar filling is achieved, and reliability after installation is improved.
更にケーソン底面には上方に凹ませた空間を形成し、し
かも凹溝を設けその凹溝内に注排孔を開口させ、その注
排孔を通して減圧するようにしたことによって曳航中に
おいて膜のたれ下りがなく、しかも膜は空間及び凹溝内
にたるみなく収容され、従って作業中の破損も生じない
ものである。Furthermore, an upwardly recessed space is formed in the bottom of the caisson, and a groove is provided in the groove, and an injection hole is opened in the groove, and the pressure is reduced through the injection hole, thereby preventing membrane sag during towing. There is no downward movement, and the membrane is housed in the space and groove without sagging, so that no damage occurs during operation.
更にまた凹溝はモルタル充填後において生じるレイタン
スが上昇してこれに集中し、従ってその処理も可能であ
りコンクリートの性状が向上される等の種々の効果があ
る。Furthermore, the grooves have various effects such as increasing and concentrating the laitance generated after filling with mortar, making it possible to treat it and improving the properties of concrete.
図面は本発明の実施工程を示すものであり、第1図は投
入された捨石基礎の断面図、第2図イ〜ハはそれぞれ仮
受部の別々の例を示す断面図、第3図はケーソンの断面
図、第4図開底面図、第5図は同成型状態の部分断面図
、第6図は膜の部分拡大断面図、第7図は換装着状態の
部分断面図、第8図はモルタル注入後の状態の断面図で
ある。
1・・・・・・捨石、2・・・・・・捨石基礎、3・・
・・・・ケーソン仮受部、4・・・・・・杭、5・・・
・・・砂袋、6・・・・・・突部、7・・・・・・凹溝
、8・・・・・・注排孔、9・・・・・・縦壁、10・
・・・・・膜、10a・・・・・・不透気性層、10b
・・・・・・透気性弾性層、11・・・・・・ケーソン
型枠、lla・・・・・・底面、12・・・・・・たる
み部分、13・・・・・・モルタル、A・・・・・・ケ
ーソン、a・・・・・・空間。The drawings show the implementation process of the present invention, and Fig. 1 is a cross-sectional view of the poured rubble foundation, Fig. 2 A to C are cross-sectional views showing different examples of temporary support parts, and Fig. 3 is a cross-sectional view of the poured rubble foundation. A cross-sectional view of the caisson, Figure 4 is an open bottom view, Figure 5 is a partial cross-sectional view of the same molded state, Figure 6 is a partial enlarged cross-sectional view of the membrane, Figure 7 is a partial cross-sectional view of the refitted state, and Figure 8 is a cross-sectional view of the state after mortar has been poured. 1...Rubble stone, 2...Rubble foundation, 3...
... Caisson temporary support part, 4 ... Pile, 5 ...
... Sand bag, 6 ... Protrusion, 7 ... Concave groove, 8 ... Injection hole, 9 ... Vertical wall, 10.
...Membrane, 10a...Air impermeable layer, 10b
......Air permeable elastic layer, 11...Caisson formwork, lla...Bottom surface, 12...Sagging portion, 13...Mortar, A...caisson, a...space.
Claims (1)
形成し、中央部分を凹ませて底部に空間を形成し、その
凹ませたケーソン底面に複数の凹溝を連続もしくは不連
続に設け、その凹溝内にモルタル等注排孔の下端を開口
させ、該ケーソンの底面に気密性膜をたるませて張設し
前記注排孔より吸気して該膜をケーソン底部の空間内に
密着させておき、該ケーソンを、基礎地盤上に捨石を投
下して所望高さに造成し、その上面の数箇所に前記ケー
ソン底面の仮受用突部に対応させてケーソン仮受部を形
成した捨石基礎上に設置し、その後前記注排孔より膜内
にモルタルを注入してケーソンの底面と捨石基礎間の空
隙を埋ることを特徴としてなるケーソン据付工法。1. A protrusion for temporary reception is formed at least on the peripheral edge of the bottom of the caisson, a space is formed at the bottom by recessing the central part, and a plurality of grooves are provided continuously or discontinuously on the recessed bottom of the caisson. , the lower end of the mortar injection hole is opened in the groove, and an airtight membrane is loosely stretched over the bottom of the caisson, and air is sucked through the injection hole to tightly fit the membrane into the space at the bottom of the caisson. Then, the caisson was built to a desired height by dropping rubble on the foundation ground, and the caisson temporary support parts were formed at several places on the top surface corresponding to the temporary support protrusions on the bottom of the caisson. A caisson installation method characterized in that the caisson is installed on a foundation, and then mortar is injected into the membrane through the injection hole to fill the gap between the bottom of the caisson and the rubble foundation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9149581A JPS5948252B2 (en) | 1981-06-16 | 1981-06-16 | Caisson installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9149581A JPS5948252B2 (en) | 1981-06-16 | 1981-06-16 | Caisson installation method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS57209332A JPS57209332A (en) | 1982-12-22 |
JPS5948252B2 true JPS5948252B2 (en) | 1984-11-26 |
Family
ID=14027987
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP9149581A Expired JPS5948252B2 (en) | 1981-06-16 | 1981-06-16 | Caisson installation method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5948252B2 (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6027126U (en) * | 1983-07-27 | 1985-02-23 | 大成建設株式会社 | marine structures |
JPS60144426A (en) * | 1984-01-05 | 1985-07-30 | Toyo Kensetsu Kk | Settlement of steel float body on ground under water |
JP2571742B2 (en) * | 1992-09-24 | 1997-01-16 | 實 八木 | Construction method of underwater concrete using concrete block |
EP2597206B1 (en) * | 2011-11-22 | 2014-05-07 | Ceteal | Foundation and method of manufacture |
-
1981
- 1981-06-16 JP JP9149581A patent/JPS5948252B2/en not_active Expired
Also Published As
Publication number | Publication date |
---|---|
JPS57209332A (en) | 1982-12-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS62248713A (en) | Submerged construction of earth and stone structure | |
JPS62288218A (en) | Settlement caisson | |
JPS5948252B2 (en) | Caisson installation method | |
JP4169154B2 (en) | Foundation construction method | |
CN207211176U (en) | A kind of big open caisson of superelevation | |
CN216194845U (en) | Pebble covering layer steel sheet pile cofferdam system | |
JP2718241B2 (en) | Foundation construction method on soft submarine ground | |
CN106917396A (en) | A kind of taper foundation reinforcement method | |
CN208309594U (en) | A kind of slip casting machine for Ruins protection | |
JPH0437205B2 (en) | ||
JPH116164A (en) | Construction method for underground structure | |
JPS63181804A (en) | Breakwater and its construction and concrete caisson therefor | |
JP4132320B2 (en) | Foundation construction method | |
JP2004137807A (en) | Construction method for caisson embankment and caisson embankment | |
JPS62276124A (en) | Installation work of bottom-upped caisson | |
RU2011774C1 (en) | Method for construction of monolithic foundation | |
JPH07216915A (en) | Construction method of underground type storage tank and bottom mounting float | |
JP3269599B2 (en) | How to build an underground tank | |
JP2536108B2 (en) | Foundation construction method for offshore structures | |
JPH03244708A (en) | Ground improvement with movable load | |
JPS6367328A (en) | Construction of high-floor type tank foundation | |
JPH0439535B2 (en) | ||
JPH0612009B2 (en) | Caisson sinking method | |
US828761A (en) | Caisson. | |
JP2023101930A (en) | Raising method |