JPS59213899A - Method of lining concrete placing construction in method of shielding construction - Google Patents

Method of lining concrete placing construction in method of shielding construction

Info

Publication number
JPS59213899A
JPS59213899A JP58086595A JP8659583A JPS59213899A JP S59213899 A JPS59213899 A JP S59213899A JP 58086595 A JP58086595 A JP 58086595A JP 8659583 A JP8659583 A JP 8659583A JP S59213899 A JPS59213899 A JP S59213899A
Authority
JP
Japan
Prior art keywords
concrete
construction
segment
lining
wire mesh
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP58086595A
Other languages
Japanese (ja)
Other versions
JPS6365800B2 (en
Inventor
細川 芳夫
平昌 青景
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Fujita Kogyo KK
Original Assignee
Fujita Corp
Fujita Kogyo KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp, Fujita Kogyo KK filed Critical Fujita Corp
Priority to JP58086595A priority Critical patent/JPS59213899A/en
Publication of JPS59213899A publication Critical patent/JPS59213899A/en
Publication of JPS6365800B2 publication Critical patent/JPS6365800B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 下水道工事、電設管理設工事用地中トンネル工法どして
シールド推進工法が一般に採用されている。この工法に
おいてはシールド9掘削機によってトンネルを1屈削し
、鋼製セグメントまたはコンクリートセグメントを組立
て、これを反力として掘進し、トンネル貫通後セグメン
ト本体をコンクリートで覆工して完成するものである。
[Detailed Description of the Invention] The shield propulsion method is generally employed in underground tunnel construction methods for sewerage work and electrical facility management construction work. In this construction method, the tunnel is cut once using a Shield 9 excavator, steel segments or concrete segments are assembled, and this is used as a reaction force to dig, and after the tunnel has been penetrated, the segment body is lined with concrete to complete the tunnel. .

前記媛エコンクIJ −1−の施工において、鋼製セグ
メントを外周型枠としてコンクリートを打設するとき、
鋼製セグメントが打設コンクリートの応力変形に対して
拘束作用が働き、そのために硬化コンクリートにひび割
れが発生する。このひび割れを防止するため低発熱セメ
ントを使用したり、打込み時のコンクリート温度を下げ
る、或いはトンネル内雰囲気を保持するだめの通気乾燥
を防止する等の対策が講じられているが、十分な効果が
得られていないのが実情である。
In the construction of the above-mentioned Hime Econch IJ-1-, when concrete is poured using steel segments as the outer peripheral formwork,
The steel segments act as a restraint against the stress deformation of the poured concrete, which causes cracks to occur in the hardened concrete. Measures have been taken to prevent this cracking, such as using low-heating cement, lowering the temperature of the concrete during pouring, and preventing ventilation and drying of the chamber that maintains the atmosphere inside the tunnel, but these measures have not been sufficiently effective. The reality is that we are not getting it.

本発明はこのような問題点を解決するために提案された
もので、セグメント本体より突設されたジノ間に金網を
張設し、同金網と前記本体との間に空隙の形成された銅
製セグメントを外型枠として、その内周側に覆工コンク
リートを打設することを特徴とするシールド9工法にお
ける覆工コンクリート打設工法に係るものである。
The present invention was proposed in order to solve these problems, and consists of a wire mesh stretched between the wire meshes protruding from the segment main body, and a copper wire mesh with a gap formed between the wire mesh and the main body. This relates to a lining concrete casting method in the Shield 9 construction method, which is characterized in that the segment is used as an outer formwork and lining concrete is cast on the inner circumferential side thereof.

コンクリートのひび割れ、亀裂の発生原因は、コンクリ
ート硬化時の発熱による温度応力によるもの、乾燥収縮
によるものに大別されるが、地中トンネ2においては前
者の影響によるものが大きいと考えられる。
The causes of cracks and fissures in concrete can be roughly divided into those caused by temperature stress due to heat generated during concrete hardening, and those caused by drying shrinkage, but in underground tunnel 2, it is thought that the former is the main cause.

而してコンクリートの温度応力は一般に次式で表わされ
ろ。
Therefore, the temperature stress of concrete is generally expressed by the following equation.

σt−ΔT・α・E、−R・・・・・・・・・・・・・
・・・・・(1)イ1しσt :温度応力 (kglc
τ2)7T:温度降下晴CC) α :コンクリートの線膨張係数に?r)Ec:コンク
リートの有効弾性係数(kg/cm’ )R二拘束度 σ7 がコンクリートの硬化後の引張り強度な上廻ると
ひび割れが発生することになる。
σt−ΔT・α・E, −R・・・・・・・・・・・・・
...(1) i1 σt : Temperature stress (kglc
τ2) 7T: Temperature drop CC) α: Linear expansion coefficient of concrete? r) Ec: Effective elastic modulus of concrete (kg/cm') R2 If the degree of constraint σ7 exceeds the tensile strength of concrete after hardening, cracks will occur.

いまΔT=20U、α−1.0X10  江、E、=1
.4×105kg/Crn2.R−1とすると、(1)
式よりσt=20x1.0x10 xl、4x10刈−
20kg/cm”どなる。
Now ΔT=20U, α-1.0X10 E, E, = 1
.. 4×105kg/Crn2. Assuming R-1, (1)
From the formula, σt=20x1.0x10xl, 4x10xl-
20kg/cm" roar.

温度によるひび割れはコンクリートの硬化後傾期間に発
生するものであり、大体3〜7日以内に発生する。コン
クリートの引張強度は圧縮強度の約1イ。であり、硬化
6〜7日程度では7〜10kg/c7n2の引張強度し
か期待できず、上述の計算からは当然ひび割れは発生す
ることになる。
Cracks due to temperature occur during the hardening period of concrete, and generally occur within 3 to 7 days. The tensile strength of concrete is approximately 1 I of its compressive strength. Therefore, after about 6 to 7 days of curing, only a tensile strength of 7 to 10 kg/c7n2 can be expected, and from the above calculation, cracks will naturally occur.

そこで(1)式中、人為的に操作して温度による応力を
低減させることができる。それはΔT¥低下させる。R
を小さくする点にある。
Therefore, in equation (1), stress due to temperature can be reduced by artificial manipulation. It lowers ΔT¥. R
The point is to make it smaller.

而してΔTを低減させることは成る程度の効果があるか
、夏期においてはその効果は殆んど期待できない。従っ
て覆工コンクリートのひび割れ、亀裂を防止するために
は拘束度Rを小さくしないかぎり、所期の目的を達成す
ることはできない。
Therefore, reducing ΔT is only moderately effective, and hardly any effect can be expected in the summer. Therefore, in order to prevent cracks in the concrete lining, the intended purpose cannot be achieved unless the degree of restraint R is reduced.

而して本発明においては前記したようにセグメント本体
より突設されたリプ間に金網を張設して、同金網と前記
本体との間に空隙の形成された鋼製セグメントを外型枠
としてその内周側に覆工コンクリートを打設するように
したので、前記鋼製セグメントと覆工コンクリートとの
間に空隙が形成され、同空隙によって両者の間の縁が切
られ、拘束度Rが減少され、覆工コンクリートのひび割
れ、亀裂の発生が防止され、更にまた前記金網によって
覆工コンクリートのひび割れ、亀裂の発生が抑制される
ものである。
Accordingly, in the present invention, as described above, a wire mesh is stretched between the lips protruding from the segment main body, and the steel segment with a gap formed between the wire mesh and the main body is used as an outer formwork. Since the lining concrete is placed on the inner circumference side, a gap is formed between the steel segment and the lining concrete, and the edge between the two is cut by the gap, and the degree of restraint R is increased. This reduces the number of cracks in the concrete lining and prevents the occurrence of cracks, and furthermore, the wire mesh suppresses the occurrence of cracks in the concrete lining.

以下本発明を図示の実施例について説明する。The present invention will be described below with reference to the illustrated embodiments.

(1,)は鋼製セグメントで、円弧面状本体(1a)よ
りリプ(1h)が突設され、同すノ(1h)には注入材
の注入D (IC)が欠截されている。
(1,) is a steel segment, a lip (1h) is provided protruding from the arcuate main body (1a), and an injection D (IC) for injection material is missing in the same (1h).

而してシールl−″1屈削機によって掘削されたトンネ
ル周面にn1立てられた鋼製セグメント(1)のリプ(
1h)に亘って、コンクリート打設前に金網(2)を張
設する。
Then, the lip (of the steel segment (1) n1 erected on the circumferential surface of the tunnel excavated by the seal l-''1 bending machine)
A wire mesh (2) is stretched for 1 hour) before concrete pouring.

次いで前記セグメント(1)を外型枠として金網(2)
の外側に覆工コンク’) −) (3)を打設する。こ
の際同打設コンクリート(3)に数個所、注入パイプ(
4)を埋設しておく。なお図中(5)は前記セグメント
連結用ボルトである。
Next, the segment (1) is used as an outer formwork to form a wire mesh (2).
Pour concrete lining (3) on the outside of the concrete lining. At this time, the injection pipe (
4) is buried. Note that (5) in the figure is the segment connecting bolt.

前記のように覆工コンクリート(3)が打設されると金
網(2)によって鋼製セグメント(1)と覆工コンク1
.1−ト(3)との間に空隙(6)が形成されることと
なる。
When the lining concrete (3) is placed as described above, the steel segment (1) and the lining concrete 1 are separated by the wire mesh (2).
.. A gap (6) will be formed between the first and second parts (3).

而して打設コンクリートの内部温度が同コンクリート周
辺温度に近い状態になった時点で鋼製セグメント(11
と覆工コンクリート(3)との空隙(6)に前記注入パ
イプ(4)を介して注入材(力を注入充填する。
When the internal temperature of the poured concrete becomes close to the surrounding temperature of the concrete, the steel segment (11
The injection material (force) is injected into the gap (6) between the concrete lining (3) and the concrete lining (3) through the injection pipe (4).

この際注入材(7)は前記セグメント(1)のリプ(1
b)に設けられた注入口(IC)を介して各セグメン)
 (1)と覆工コンク!J −) (3)との間の間隙
(6)に密実に注入充填され、同注入材(7)は金網(
2)を介して覆工コンクリート(3)と一体化され、同
注入材(7)により止水効果が図られるものである。
At this time, the injection material (7) is applied to the lip (1) of the segment (1).
b) Each segment via the injection port (IC) provided in
(1) and lining conch! The gap (6) between J −
2) is integrated with the lining concrete (3), and the same injection material (7) provides a water-stopping effect.

以上本発明を実施例について説明したが、本発明は勿論
このような実施例にだけ局限されるものではなく、本発
明の精神を逸脱しない範囲で種々の設計の改変を施しう
るものである。
Although the present invention has been described above with reference to embodiments, the present invention is, of course, not limited to such embodiments, and can be modified in various ways without departing from the spirit of the present invention.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の方法によって施工されたトンネルの縦
断側面図、第2図はその縦断正面図、第6図は鋼製セグ
メントの部分斜面図である。 (1)・・・鋼製セグメント、(1α)・−・セグメン
ト本体。 (1h)・・・リプ、(2)・・・金網、(3)・・・
覆工コンクリート。 代理人 弁理士  岡 本 重 文 外3名
FIG. 1 is a vertical side view of a tunnel constructed by the method of the present invention, FIG. 2 is a vertical front view thereof, and FIG. 6 is a partial slope view of a steel segment. (1)...Steel segment, (1α)...Segment body. (1h)...Reply, (2)...Wire mesh, (3)...
Lining concrete. Agent: Patent attorney: Shige Okamoto, 3 other people

Claims (1)

【特許請求の範囲】[Claims] セグメント本体より突設されたジノ間に金網を張設し、
同金網と前記本体との間に空隙の形成されたt(”l 
’Idセグメントを外型枠として、その内周側に農工コ
ンクリートを打設することを特徴とするシールド工法に
おける暖エコンクリート打設工法。
A wire mesh is stretched between the wires that protrude from the segment body,
A gap t("l") is formed between the wire mesh and the main body.
A heating concrete pouring method in the shield method, which is characterized by using the Id segment as an outer formwork and pouring agricultural concrete on the inner periphery thereof.
JP58086595A 1983-05-19 1983-05-19 Method of lining concrete placing construction in method of shielding construction Granted JPS59213899A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP58086595A JPS59213899A (en) 1983-05-19 1983-05-19 Method of lining concrete placing construction in method of shielding construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP58086595A JPS59213899A (en) 1983-05-19 1983-05-19 Method of lining concrete placing construction in method of shielding construction

Publications (2)

Publication Number Publication Date
JPS59213899A true JPS59213899A (en) 1984-12-03
JPS6365800B2 JPS6365800B2 (en) 1988-12-16

Family

ID=13891351

Family Applications (1)

Application Number Title Priority Date Filing Date
JP58086595A Granted JPS59213899A (en) 1983-05-19 1983-05-19 Method of lining concrete placing construction in method of shielding construction

Country Status (1)

Country Link
JP (1) JPS59213899A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4839347B2 (en) * 2008-07-01 2011-12-21 エコシビックエンジ株式会社 Structure of lining body and construction method thereof

Also Published As

Publication number Publication date
JPS6365800B2 (en) 1988-12-16

Similar Documents

Publication Publication Date Title
JPS58598A (en) Method of control construction of crack of wall-shaped concrete structure
JPS59213899A (en) Method of lining concrete placing construction in method of shielding construction
JP2730705B2 (en) Improvement method for soft ground
CN105755943B (en) A kind of Arch Bridge Ribs block section and its construction method
JP5411076B2 (en) Tunnel construction method
JP3241356B2 (en) Tunnel reinforcement method
JPH05214887A (en) Method of lining tunnel of steel plate concrete composite construction
JPS637497A (en) Concrete press-in filling method of steel concrete syntheticsegment
JP2657943B2 (en) Waterproof reinforcement method for tunnel concrete
JPS637498A (en) Concrete placing method of steel concrete synthetic segment
JPS59217900A (en) Method of placing construction of lining concrete
JPH01148740A (en) Covering material for shield lining at job site
JP2941172B2 (en) Manufacturing method of PC segment
JPH01198917A (en) Construction of concrete wall
RU2233938C1 (en) Method for grouting concrete gravity dam built on rock foundation
JPS5843560B2 (en) Vertical shield tunnel tonneau
JPH1143949A (en) Caisson sinkage acceleration material and settling method
JPS5697021A (en) Burying method for pipe
JP2747568B2 (en) Resin concrete manhole and its modification method
JP4182004B2 (en) Stripping prevention member, tunnel lining prevention structure, and tunnel lining construction method
JPS6145065A (en) Concrete cast-splicing construction method
JP2757075B2 (en) Concrete placement method in direct-cast concrete lining method
JPS6110671A (en) Prevention of cracking of concrete structure
CN115341585A (en) Composite waterproof structure suitable for underground engineering
JPH01271580A (en) Cooling of concrete column