JPS59165765A - Liftable mold frame apparatus - Google Patents

Liftable mold frame apparatus

Info

Publication number
JPS59165765A
JPS59165765A JP3675483A JP3675483A JPS59165765A JP S59165765 A JPS59165765 A JP S59165765A JP 3675483 A JP3675483 A JP 3675483A JP 3675483 A JP3675483 A JP 3675483A JP S59165765 A JPS59165765 A JP S59165765A
Authority
JP
Japan
Prior art keywords
formwork
frame
concrete
template
siebold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP3675483A
Other languages
Japanese (ja)
Other versions
JPH0138941B2 (en
Inventor
勝治 松田
筒井 弘昭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Kizai Forming Co Ltd
Original Assignee
Kawatetsu Kizai Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawatetsu Kizai Kogyo Co Ltd filed Critical Kawatetsu Kizai Kogyo Co Ltd
Priority to JP3675483A priority Critical patent/JPS59165765A/en
Publication of JPS59165765A publication Critical patent/JPS59165765A/en
Publication of JPH0138941B2 publication Critical patent/JPH0138941B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 本発明は昇降可能な型枠装置に関するものであって、こ
の型枠装置を使用してコンクリート施工準備と施行が容
易に行なえるものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a formwork device that can be raised and lowered, and can be used to easily prepare and execute concrete construction.

堰堤、橋脚、擁壁等のコンクリート施工に当り、形成す
べき壁面には型枠を堅固に固定取付は型枠内にコンクリ
ートを打設している。この際に打設したコンクリートが
打上ると先に取付けた型枠をコンクリート面より外して
、その面に沿い上昇させて次回の打設に対応する位置に
固定する。上記堰堤等のコンクリート施行に用いる型枠
は一般に型板の裏面に一組又は二組の脚材が固着され、
脚材の上部につり環が取付レナだ構造のものが用いられ
る。この種の型枠の脚材は、型板から下方に長(突出し
ているもので、上記打設に当っては、前回打上げたコン
クリートに既に埋込んであるアンカーボルトに、シーボ
ルトを介して突出した脚材部分を打上げコンクリ−の面
に強固に固定させるように取付けられる。このようにし
て脚材により型板は次回の打設に必要な位置に確実に固
定される。前回のコンクリート釣上げから次回のコンク
リート打設に当って、このように型枠を上方に引上げる
にはクレーン等のつり上げ装置がつり環を把持して型枠
をつり上げ、型板が打上げコンクリートの所定延長面を
占める位置まで持上げて行なわれる。その上打上げたコ
ンクリート面から型板を外すに当っても、アンカーボル
トを取外したシーボルト附近で脚材と前回打上げのコン
クリート面の間にジヤツキ等を差込んで、型板をコンク
リート面から剥離しなければならず、その作業も煩雑で
ある。そのため型枠の位置変更のためにクレーンを使用
して行なう作業は、相当に厄介であると共に危険を伴う
ものである。
When constructing concrete for dams, bridge piers, retaining walls, etc., formwork is firmly fixed to the wall surface to be formed, and concrete is poured into the formwork. When the poured concrete is poured, the previously installed formwork is removed from the concrete surface, raised along that surface, and fixed in a position corresponding to the next pouring. The formwork used for concrete construction of the above-mentioned dam etc. generally has one or two sets of legs fixed to the back of the template.
A lever structure with a hanging ring attached to the top of the leg material is used. The legs of this type of formwork are long (protruding) downward from the template, and during the above-mentioned pouring, they are inserted through the Siebolds into the anchor bolts that have already been embedded in the previously poured concrete. The legs are firmly fixed to the concrete surface.In this way, the legs securely fix the template in the position required for the next pouring. In order to pull the formwork upward in this way during the next concrete pouring, a lifting device such as a crane grasps the hanging ring and lifts the formwork to a position where the formwork occupies a predetermined extended surface of the poured concrete. Furthermore, when removing the template from the concrete surface that has been launched, insert a jack or similar tool between the leg material and the previously launched concrete surface near the Siebold where the anchor bolts were removed, and remove the template. must be peeled off from the concrete surface, and the work is complicated.Therefore, the work of using a crane to change the position of the formwork is quite troublesome and involves danger.

本発明の型枠装置は、当初従来方法により最下部のコン
クリート打設のためクレーン等で型枠を定位置に据付け
るが、−たん下部コンクリート打上げ後は、これに続く
上方への繰返しコンクリ−ト打設に当っては、型枠の繰
返上昇が極めて容易且つ正確、その上安全に行なえるも
のである。然もこの装置を用いることによって打上げコ
ンクリート面よりの型板の剥離が極めて容易に行なえる
ものである。その要旨を述べれば、各組立体とも内向の
縦案内路の背部にアンカーボルトと螺合すべきシーボル
トの厚みに相当する案内間隔が形成された二組の脚材組
立体を前記縦案内路を互に向合せて且つ平行にして型板
に固着した型枠と、前記縦案内路間にわたって設けられ
た対向する案内路に沿って摺動し上部にシーボルトに噛
合い固定する鉤を有する摺動フレームと、前記型枠とフ
レームを相対動可能に連結する連結子と、前記連結子を
作動する手段からなる型枠装置である。本発明型枠装置
は上記の如くで、型枠を下方から上方に然も打上げコン
クリート面に沿い、その延長方向に繰返し移動させるよ
うにしたもので、従来のようにクレーンによるつり上げ
の繰返しとは全く異なる原理から発想したものである。
The formwork device of the present invention initially installs the formwork in a fixed position using a crane or the like to pour concrete at the lowest part using the conventional method, but after pouring the concrete at the bottom, the formwork is repeatedly placed upwards. During pouring, the formwork can be repeatedly raised very easily, accurately, and safely. Moreover, by using this device, the template can be peeled off from the concrete surface extremely easily. To summarize, in each assembly, two sets of leg assemblies with a guide interval corresponding to the thickness of the Siebold to be screwed into the anchor bolt are attached to the back of the inward vertical guideway. A slide having formworks fixed to a form plate facing each other and parallel to each other, and a hook that slides along opposing guideways provided between the vertical guideways and engages and fixes the Siebold on the upper part. This formwork apparatus includes a frame, a connector that connects the formwork and the frame in a relatively movable manner, and means for operating the connector. The formwork device of the present invention is as described above, and is designed to repeatedly move the formwork from below to above and along the concrete surface in its extension direction, which is different from the conventional method of repeatedly lifting the formwork with a crane. The idea was based on a completely different principle.

以下図面について一実施例を詳細に述べる。型枠(1)
は実質的に従来のものと類似で型板(2)の裏に横に渡
された長い横受材(a、4.5) (この場合山形材)
に他の短かい山形材(6,7,8;6′、7′、8′)
を介して二組の脚材組立体(9,9’ )が取付けられ
ている。脚材組立体は両者とも同一構造であるのでその
一方(9)について述べる。該組立体は、一対の溝形材
(10,11)を腹部の背(12,121)を向合せに
背量を後記シーボルトの棒径の厚みに相当する間隔(1
4)をあけて型板(2)に固着される。溝形材の上部に
はつり3J (15)が取付けられている。
An embodiment will be described in detail below with reference to the drawings. Formwork (1)
is substantially similar to the conventional one and is a long horizontal support (a, 4.5) passed horizontally behind the template (2) (in this case a chevron)
and other short angles (6, 7, 8; 6', 7', 8')
Two sets of leg assemblies (9, 9') are attached via. Since both leg assemblies have the same structure, only one (9) will be described. The assembly consists of a pair of channel members (10, 11) with their abdominal backs (12, 121) facing each other, with the backs spaced at an interval (1) corresponding to the thickness of the Siebold rod diameter described later.
4) and is fixed to the template (2). A hanger 3J (15) is attached to the top of the channel member.

尚(16) (17)は後記のシーボルトを間隔(14
)に置いてナラ) (18) (19)で夫々脚材組立
体に取付けるための座金板である。溝形材(10)の溝
は脚材組立体(9′)の対応の内側溝形材の溝と互に向
合って取付けられる。この場合相手方の対応の溝形材に
換えてH形材又はC形材を用いることも出来る。又溝形
材(11)は溝形材(10)との間にシーボルトの径の
厚みに相当した間隔(ト0をおいて溝形材(10)と並
設されるものであれば必ずしも溝形材に限らすとも構造
上の強度があれば他の長尺物でも差支えない。両脚材組
立体の下端は横材(5o)で固定される。前記溝形材(
10腿対応の溝形材(10’)の対向の溝間傾は上下の
突出シュー (20,21;20’、21’ )ヲm内
テN動可fiFA K して一体に取付げた矩形のフレ
ーム(22)が配され、フレーム(22)の上梁(28
)よりは内方、即ち型板に向いた側に脚材組立体を外れ
た位置(32)を支点(24,24′)として回動可能
に鉤(25,25′)が取付けられている。フレーム(
22)の上梁(2B)の両端から下方に向は一対の内向
傾斜梁(26,26′)があり、梁の下端を結ぶ横材(
27)には油圧シリンダ(28)の下端が枢着され、シ
リンダ(28)の上部より摺動可能に突出したピストン
俸(29)は型板(2)の下横材(5)のほぼ中央で枢
支(8o)されている。(81,81′)は横材(4)
の溝形材(10,10’)の接続部と枢支点(8o)を
結ぶ方杖である。尚油圧シリンダ(28)は必ずしも油
圧によるものに限らず圧縮空気を用いるものでも差支え
ない。その圧油の流入、排出による操作機構は周知のも
のであるので流入口、排出口及び油圧源並びに油圧源と
流入口と排出口とを結ぶ圧油路は図面上省略する。又、
油圧シリンダに代えて、ラックピニョン等による他の機
構によりフレーム(22)と型枠、とを相対動可能に連
結しても差支えない。
In addition, (16) and (17) are the Siebold intervals (14
) (18) and (19) are washer plates for attaching to the leg assembly, respectively. The grooves of the channel (10) are mounted opposite the grooves of the corresponding inner channel of the leg assembly (9'). In this case, an H-shaped member or a C-shaped member can be used instead of the corresponding channel member. Also, if the channel member (11) is installed in parallel with the channel member (10) with an interval corresponding to the thickness of the diameter of the Siebold (t 0) between the channel member (10), the groove member (10) is not necessarily provided. Although it is limited to the shape material, other long materials may be used as long as it has structural strength.The lower end of the leg assembly is fixed with the cross member (5o).The channel member (
The inclination between the opposing grooves of the groove member (10') corresponding to 10 thighs is the upper and lower protruding shoes (20, 21; 20', 21'). A frame (22) is arranged, and an upper beam (28) of the frame (22) is arranged.
), that is, on the side facing the template, a hook (25, 25') is attached so as to be rotatable about a position (32) removed from the leg assembly as a fulcrum (24, 24'). . flame(
22) There is a pair of inwardly inclined beams (26, 26') downward from both ends of the upper beam (2B), and a cross member (
The lower end of a hydraulic cylinder (28) is pivotally connected to 27), and a piston barrel (29) that slidably protrudes from the upper part of the cylinder (28) is located approximately at the center of the lower cross member (5) of the template (2). It is pivoted (8o). (81, 81') is the horizontal member (4)
This is a rod that connects the connecting part of the channel members (10, 10') and the pivot point (8o). Note that the hydraulic cylinder (28) is not necessarily one that uses oil pressure, but may also use compressed air. Since the operation mechanism for inflowing and discharging the pressure oil is well known, the inflow port, the discharge port, the hydraulic pressure source, and the pressure oil passage connecting the hydraulic pressure source, the inflow port, and the discharge port are omitted in the drawing. or,
Instead of the hydraulic cylinder, the frame (22) and the formwork may be connected for relative movement by another mechanism such as a rack and pinion.

本発明装置の作用について述べる。伺脚材をコンクリー
ト面に対して行なう固定は同一であるので一方のみにつ
いて述べる。先ず、フレーム(22)を摺動可能で型板
に対して相対動しうるように一体に取付けた型枠組立体
(L22)をつり環にて吊り乍らコンクリート打設をす
べき位置に据付ける。
The operation of the device of the present invention will be described. Since the method of fixing the supporting pedestals to the concrete surface is the same, only one will be described. First, the formwork assembly (L22), in which the frame (22) is integrally attached so that it can slide and move relative to the template, is suspended from a hanging ring and installed at the position where concrete is to be poured. .

予め、打設した又は前々回に打設したコンクリートA内
に埋込んである、又は他に埋込んであるアンカーボルト
(85)と螺合したシーポル) (86)を間隔(14
)において座金板(17,17’)を介してナツト(1
9,19’ )で溝形材(10,11)間に固定すると
共に、打設すべきコンクリートの厚みに相当する間隔を
おいて前回に打上げたコンクリートBに埋込んだ上部の
アンカーポル) (87)に対しても同様にシーボルト
(88)を座金板(16)、ナラ) (18)によって
溝形材の間に固定する(第1図)。二番目のシーポル)
 (i38)に鉤(25)を掛けてフレームを溝形材に
対して縦方向に移動しないようにする。ここでシリンダ
(28)を作動させて型板(2)を今回コンクリートを
打設すべき位置に正しく移動させ、その位置に停止させ
る。型板(2)には、コンクリート打設の際埋込まれる
アンカ−ポル) (89)の位置に見合う場所にシーボ
ルト(40)を貫通して挿入する孔(41)が設げられ
ている。ここで6部のコンクリート打設を行なう。
Seapol (86) screwed together with an anchor bolt (85) that is embedded in the concrete A that has been cast in advance or the time before the previous cast, or that is embedded elsewhere
) through the washer plates (17, 17') and the nut (1
9, 19') between the channel members (10, 11), and the upper anchor poles embedded in the previously poured concrete B at intervals corresponding to the thickness of the concrete to be poured) ( 87), the Siebold (88) is similarly fixed between the grooves using the washer plate (16) and the oak (18) (Fig. 1). second seapol)
(i38) is hooked (25) to prevent the frame from moving vertically relative to the channel. Here, the cylinder (28) is actuated to move the template (2) correctly to the position where concrete is to be poured this time, and it is stopped at that position. The template (2) is provided with a hole (41) into which the Siebold (40) is inserted through, at a location corresponding to the position of the anchor pole (89) to be embedded during concrete pouring. Six parts of concrete will be poured here.

6部のコンクリート打設に伴い埋込んだアンカーポル)
 (219)と孔を通してシーボルト(40)とを螺着
し、シーボルト(40)も他のシーボルトの如くに溝形
材間に固定してコンクリートの打上げまでその位置を保
つ。コンクリート打上げ後は、最後に結合したシーポル
) (40)をアンカーボルト(39)より外して又溝
形材より外す。ここでポル) (18)を外し方向に緩
め、ボルト(19,19′)を更にアンカーポルl−(
85)方向に螺動さすと溝形材(IL12)の下部はコ
ンク17  )を押す方向に、中部はコンクリートから
離れる方向に僅かに動く。そのため最後に打上ったコン
クIJ −トCに対し型板(2)が剥離方向に動(ので
それによってコンクリ−)Cの面に対し型板(2)が離
れて型板の剥離が容易に行なわれる。次いでシリンダ(
28)を作動させるとピストン棒(29)は第1図の状
態から第3図の状態に上昇し、これに伴って型枠(1)
がフレーム(22)に対して相対運動して上昇する。
(Anchor pole embedded during concrete pouring in section 6)
(219) and the Siebold (40) are screwed together through the hole, and the Siebold (40), like other Siebolds, is fixed between the channels and maintained in its position until concrete is poured. After concrete is poured, remove the last seapol (40) connected from the anchor bolt (39) and from the channel member. Loosen the anchor pole (18) in the direction of removal, and then tighten the bolts (19, 19') further.
85), the lower part of the channel member (IL12) moves slightly in the direction of pushing the concrete 17), and the middle part moves slightly in the direction of moving away from the concrete. Therefore, the template (2) moves in the peeling direction with respect to the concrete IJ-to C that was launched last (thereby, the template (2) separates from the surface of the concrete) C, and the template peels off easily. It is done. Then the cylinder (
28), the piston rod (29) rises from the state shown in Fig. 1 to the state shown in Fig. 3, and along with this, the formwork (1)
moves relative to the frame (22) and rises.

併しフレームは鉤がコンクリートに取付けたシーボルト
(88)に掛ゆられであるので上昇せず溝形材の間隔の
シーポル) (1,1)の直線上に沿って型枠のみが上
昇する。型枠上昇後は前回コンクリート打設時にコンク
リートC内に埋込まれたアンカーポル) (89)と上
昇の除外したシーボルト(40)とを再度結合し、コン
クリートCより突出したシーポル)(40)に型板の下
端を支承さす。
However, the frame does not rise because its hooks are hung on Seabolts (88) attached to the concrete, but only the formwork rises along the straight line of Seapole (1, 1) between the channel members. After the formwork is raised, the anchor pole (89) that was embedded in the concrete C during the previous concrete pouring is reconnected with the Seabolt (40) that was excluded from the rise, and the seabol (40) that protrudes from the concrete C is reconnected. Support the bottom edge of the template.

この状態で鉤(25>を下段のシーボルトから外して(
仮想線図示)シリンダ(28)を作動させてフレーム(
22)を型板に接近するまで上昇させる。
In this state, remove the hook (25) from the lower Siebold (
Actuate the cylinder (28) (shown in phantom line) to open the frame (
22) is raised until it approaches the template.

フレーム上昇後は先に溝形材の間隔(14)に据付けら
れた上段のシーボルト(40)に@(25)ヲ1)けて
フレームの位置をコンクリート面に同定し、更にシリン
ダを調整して型板を正しい位置に移動して固定して、次
回のコンクリート打設の準備を完了する。
After the frame has been raised, first locate the frame on the concrete surface using the upper Siebold (40) installed at the channel spacing (14) @ (25) 1), and then adjust the cylinder. Move the template to the correct position and secure it in place to complete preparations for the next concrete pour.

上記コンクリートの打設はフレーム(22)を型板(2
)に近付けた位置で型枠をコンクリート面に支持させた
状態で最初の打設を行なう。次の打設はこの位置でフレ
ームを固定して型枠を上昇させて上昇位置で型枠を固定
して次回のコンクリート打設の準備を行なった例につい
て述べた。併し型枠がコンクリート面に固定して支持さ
れておれは型板とフレームとは離れていても、近接して
いてもコンクリートの打設には影響するものではなく、
使用現場において型枠の安定度、作業の難易を考慮して
定めることである。
For pouring the above concrete, frame (22) is placed on template (2).
) The first pouring is carried out with the formwork supported on the concrete surface at a position close to . For the next pouring, we have described an example in which the frame is fixed at this position, the formwork is raised, and the formwork is fixed at the raised position to prepare for the next concrete pouring. However, since the formwork is fixed and supported on the concrete surface, it does not affect concrete pouring even if the formwork and frame are separated or close to each other.
This should be determined by considering the stability of the formwork and the difficulty of the work at the site of use.

上記型枠とフレームとの相対動は、フレームのシュー(
20,21)が溝形材の系内溝に沿って動(ので移動が
滑らかで両者の相互位置が當に正しく保たれる。
The relative movement between the formwork and the frame is determined by the frame shoe (
20, 21) move along the internal groove of the channel member (so that the movement is smooth and the mutual position of the two is precisely maintained).

本発明型枠装置は以上の如く型枠とフレームとの尺取り
虫様の運動によって型枠を逐次上方の所定位置に移動さ
せて、その位置に固定させ、固定した場所で型枠の型板
で囲む部分にコンクリートを打設するものである。その
ため従来のように型枠を繰返し打設をする毎にクレーン
等でつり上げることなく、下から持上げるので繰返し作
業が容易である。型枠上昇に当っても脚利、祖立体間の
一定間隔に常にアンカーボルトと結合したシーボルトが
少くとも2個所定の上下方向に距離おいて嵌っているの
で、型枠はシーボルトの延長線上に移動し、上方々動後
に型板位置を横方向に移動調節する必要性はない。その
上コンクリ−ト打設時後のコンク’J−ト面と型板面間
の剥離が極めて簡単で、剥離のためジヤツキ、その他の
頼雑な動作を必要としない。
As described above, the formwork device of the present invention sequentially moves the formwork upward to a predetermined position by the inchworm-like movement of the formwork and frame, fixes it at that position, and surrounds the fixed place with the template of the formwork. This involves pouring concrete into the area. Therefore, the work can be repeated easily because the formwork is lifted from below instead of being lifted up by a crane or the like every time the formwork is repeatedly cast as in the past. Even when the formwork is being raised, at least two Siebolds connected to anchor bolts are always fitted at a certain distance between the leg and base bodies at a predetermined distance in the vertical direction, so the formwork is placed on the extension line of the Siebolds. There is no need to adjust the template position laterally after movement and upward movement. Moreover, peeling between the concrete surface and the template surface after concrete is poured is extremely easy, and peeling does not require jacking or other complicated operations.

【図面の簡単な説明】 図面は本発明型枠装置を示し、第1図と第2図はコンク
リート打設時における型枠位置を示す夫々正面図及び側
面図、第8図と第4図は次回に打設すべき位置に型枠が
移動した状態を示す夫々正面図と仙j面図である。 l:型枠 2:型板 9.9′:脚材組立体1O111
:溝形材 12.18:腹部14:間隔 20.21:
シュー 22:フレーム25:鉤 28:油圧シリンダ
 29:ピストン棒85.87.89:アンカーボルト 36.88.40ニジ−ボルト 特許出願人 川鉄機材工業株式会社 崎【 代 理 人 弁理士  石 川 長  、(”i1号朱
/ 図 rr’ 訊2図 /15
[BRIEF DESCRIPTION OF THE DRAWINGS] The drawings show the formwork apparatus of the present invention, FIGS. 1 and 2 are front and side views showing the position of the formwork during concrete pouring, and FIGS. 8 and 4 are respectively They are a front view and a side view, respectively, showing a state in which the formwork has been moved to a position to be poured next time. l: Formwork 2: Template 9.9': Leg assembly 1O111
: Channel member 12.18: Abdomen 14: Interval 20.21:
Shoe 22: Frame 25: Hook 28: Hydraulic cylinder 29: Piston rod 85. 87. ("i1 No. Vermilion / Figure rr' Volume 2 / 15

Claims (1)

【特許請求の範囲】 (υ 各組立体とも内向の縦案内路の背部にアンカーボ
ルトと螺合すべきシーボルトの厚みに相当する案内間隔
が形成された二組の脚材組立体を前記縦案内路を互に向
合せ且つ平行にして型板に固着した型板と、前記縦案内
路間にわたって設けられ対向する案内路に沿って摺動し
上部にシーボルトに噛合い固定する鉤を有する摺動フレ
ームと、前記型枠とフレームを相対動可能に連結する連
結子と、前記連結子を作動する手段からなる昇降可能な
型枠装置。 (2)各組の脚材組立体は前記シーボルトの厚みに相当
する間隔をおいて腹部の背を向合せに配置した一対の溝
形材からなる特許請求の範囲第1項に記載の型枠装置。 (3)前記型枠とフレームとを連結する連結子は型枠よ
りフレームに向は延出したピストン棒を入れ子株に受入
れてフレームに取付けられたシリンダーからなる特許請
求の範囲第1項に記載の型枠装置。 (線 前記連結子を作動する手段が油圧シリンダである
特許請求の範囲第1項に記載の型枠装置。 (5)前記連結子作動の手段が気圧シリンダである特許
請求の範囲第1項に記載の型枠装置。
[Scope of Claims] (υ In each assembly, two sets of leg assemblies each having a guide interval corresponding to the thickness of the Siebold to be screwed with the anchor bolt are formed at the back of the inward vertical guide path. A slide having a template fixed to the template with paths facing and parallel to each other, and a hook that is provided between the longitudinal guideways, slides along the opposing guideways, and engages and fixes the Siebold on the upper part. A formwork device that can be raised and lowered, comprising a frame, a connector that connects the formwork and the frame so that they can move relative to each other, and means for operating the connector. (2) Each set of leg assemblies has a thickness of The formwork device according to claim 1, comprising a pair of channel members arranged with their abdominal backs facing each other with an interval corresponding to . (3) A connection for connecting the formwork and the frame. The formwork device according to claim 1, wherein the child comprises a cylinder attached to the frame by receiving a piston rod extending from the formwork toward the frame into a nesting stock. The formwork device according to claim 1, wherein the means is a hydraulic cylinder. (5) The formwork device according to claim 1, wherein the means for actuating the connector is a pneumatic cylinder.
JP3675483A 1983-03-08 1983-03-08 Liftable mold frame apparatus Granted JPS59165765A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3675483A JPS59165765A (en) 1983-03-08 1983-03-08 Liftable mold frame apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3675483A JPS59165765A (en) 1983-03-08 1983-03-08 Liftable mold frame apparatus

Publications (2)

Publication Number Publication Date
JPS59165765A true JPS59165765A (en) 1984-09-19
JPH0138941B2 JPH0138941B2 (en) 1989-08-17

Family

ID=12478521

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3675483A Granted JPS59165765A (en) 1983-03-08 1983-03-08 Liftable mold frame apparatus

Country Status (1)

Country Link
JP (1) JPS59165765A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5316431A (en) * 1976-07-30 1978-02-15 Tatsuo Morooka Method of constructing concrete building form device used therefor

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5316431A (en) * 1976-07-30 1978-02-15 Tatsuo Morooka Method of constructing concrete building form device used therefor

Also Published As

Publication number Publication date
JPH0138941B2 (en) 1989-08-17

Similar Documents

Publication Publication Date Title
JPH08144514A (en) Form device having scaffold having raising-lowering function, and construction method of concrete wall or the like by using form device having scaffold
US3807681A (en) Forming system for concrete floor and roof decks
US2705359A (en) Monolithic building construction
US3574905A (en) Device for successively building concrete structures
US2916245A (en) Adjustable scaffold bracket
JPS59165765A (en) Liftable mold frame apparatus
CN208395699U (en) Steel bushing heads into structure
JPH07247695A (en) Construction method for high structure and construction device used therefor
US3314638A (en) Adjustable concrete floor construction apparatus
JP2002146760A (en) Floating type form supporting and construction method for water-surface building
JP3063548B2 (en) Formwork method and equipment
JPH0663364B2 (en) Mobile formwork method and its equipment
JPH059918A (en) Form installing device
US4126407A (en) Methods of shifting heavy and/or loaded structures
JP2868725B2 (en) Seawall repair method
CN111648253B (en) Cast-in-place simply supported beam construction process and construction structure thereof
GB2078669A (en) Improvements In or Relating To a Method for Removing a Concrete Panel from a Form
JPS5916608B2 (en) Concrete formwork method and its equipment
JP3632068B2 (en) Formwork joining mechanism of formwork equipment
US4272465A (en) Method for multi-storied concrete construction and apparatus therefor
JPS5953981B2 (en) Formwork method and its equipment
JPH0681314A (en) Construction method for concrete main tower
JPS594755A (en) Slide type frame apparatus for casting concrete structure
JP2003200470A (en) Simple molding device
JPH10115090A (en) Climb form construction method