JPS59158793A - Method of installation of crane in housing - Google Patents

Method of installation of crane in housing

Info

Publication number
JPS59158793A
JPS59158793A JP58032088A JP3208883A JPS59158793A JP S59158793 A JPS59158793 A JP S59158793A JP 58032088 A JP58032088 A JP 58032088A JP 3208883 A JP3208883 A JP 3208883A JP S59158793 A JPS59158793 A JP S59158793A
Authority
JP
Japan
Prior art keywords
crane
running
building
rail
lane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP58032088A
Other languages
Japanese (ja)
Inventor
大野 一夫
永井 久之
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Toshiba Plant Construction Corp
Original Assignee
Toshiba Corp
Toshiba Plant Construction Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp, Toshiba Plant Construction Corp filed Critical Toshiba Corp
Priority to JP58032088A priority Critical patent/JPS59158793A/en
Publication of JPS59158793A publication Critical patent/JPS59158793A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔発明の技術分野〕 本発明は、例えば原子戸建屋内等に設置されるクレーン
の据付工法に係り、待に建屋蝶設時には門型クレーンと
して建屋建設工事との並行使用を可能とし、建屋竣工後
は天井足行うレーンとして使用できるようにした建屋内
クレーンの据付工法に関する。
[Detailed Description of the Invention] [Technical Field of the Invention] The present invention relates to a method of installing a crane installed inside a nuclear detached building, etc., and in which it is used as a gate-type crane in parallel with the building construction work when the building is installed. This invention relates to an installation method for a crane inside a building that can be used as a lane for overhead foot operations after the building is completed.

〔発明の技術的背型〕[Technical background of the invention]

従来の建屋内クレーンの据付工法を、−カとして原子力
発電設備における原子炉建屋の天井走行うレーンを例に
採り第1図ないし第3図を参照して以下説明する。
A conventional method for installing a crane inside a building will be described below with reference to FIGS. 1 to 3, taking as an example a lane for overhead running of a nuclear reactor building in a nuclear power generation facility.

ます、原子炉建屋lが運転操作床面2まで児成したなら
ば、運転操作床面2より上層の原子戸建座壁3および天
井走行うレーン基礎4をそれぞれ建設する。そしてその
後、天井走行うレーン基軸4上に走行レール5を敷設し
、原子炉婬屋壁3内レールυ 面には天井走行の≠冨≠埼への給電用架緋7を張設する
First, once the reactor building l has been completed up to the operation floor 2, the seat wall 3 of the nuclear detached house above the operation floor 2 and the lane foundation 4 for overhead running are constructed, respectively. After that, a running rail 5 is laid on the lane axis 4 for overhead running, and a power feeder 7 for feeding power to ≠Tomi≠Sai for ceiling running is installed on the rail υ surface inside the reactor roof wall 3.

一方、これと併行しであるいは相前後して天井部ζこ屋
根トラス8を配設する。この際、屋根トラス8はその全
数を剣付けるのではなく、後に原子炉建屋1の屋根部分
からクレーンガーダ9およびトロリ10を吊り込むのに
必要な空間を確保するため、数本は据付けないでおく。
On the other hand, a roof truss 8 is provided at the ceiling part ζ in parallel with or before and after this. At this time, rather than installing all of the roof trusses 8, some of them are left uninstalled in order to secure the space necessary to later suspend the crane girder 9 and trolley 10 from the roof of the reactor building 1. put.

次いで、地上において予め組立てておいたクレーンガー
ダ9を、原子炉建屋1の建設に使用した揚重設備等を利
用して原子炉建屋1の天井上方から前記空間を介して吊
り込み、走行レール5上に設置する。そしてその仮、ト
ロリ10を同様の方法により吊り込んでクレーンガーダ
9上に設直し、クレーンガーダ9およびトロI710の
ボルトの本細め工事および電気工事を実施して天井走行
うレーン6を完成させる。
Next, the crane girder 9, which has been assembled in advance on the ground, is suspended from above the ceiling of the reactor building 1 through the space using the lifting equipment used in the construction of the reactor building 1, and the traveling rail 5 Place it on top. Then, the trolley 10 is temporarily suspended and reinstalled on the crane girder 9 using the same method, and the bolt tightening work and electrical work of the crane girder 9 and trolley I710 are performed to complete the overhead running lane 6.

この天井走行うレーン6の組付けと並行しであるいは相
前後して原子gF建屋1側では、クレーンガーダ9およ
びトロIJ 10の吊り込みのために先付けずにおいた
残りの屋根トラス8を傭付け、屋根トラス8上にコンク
リートを打設して屋根11を建設する。そして前記天井
走行うレーン6は、この屋根11のコンクリートが元分
乾床して完成した後に1更用可能となる。
In parallel with or in conjunction with the installation of the overhead running lane 6, the remaining roof truss 8, which was left unattached in order to suspend the crane girder 9 and Toro IJ 10, was installed on the atomic gf building 1 side. , a roof 11 is constructed by pouring concrete on the roof truss 8. The overhead running lane 6 can be reused once after the concrete of the roof 11 is completely dried.

〔背景技術の問題点〕[Problems with background technology]

従来はこのようにして天井走行うレーン6を据付けてい
るが、この方法では、天井走行クレーン6の据付けが早
く完了しても、M根11のコンクリートが光分に乾燥し
て屋根11が完成し、天井走行うレーン6の稼動による
振動、衝撃に光分耐え得る強度になるまで天井走行うレ
ーン6を使用することができないという離点がある。原
子Fm座1の運転操作床面2の完成から原子炉建屋10
屋根11の完成までは6ないし8箇月程度の工期を安し
、この間は天井走行うレーン6を用いて原子炉建屋1へ
の機器等の搬入および据付けを行なうことができないこ
とになる。
Conventionally, the overhead traveling lane 6 is installed in this way, but with this method, even if the installation of the overhead traveling crane 6 is completed quickly, the concrete of the M root 11 dries to light and the roof 11 is completed. However, there is a point where the overhead running lane 6 cannot be used until it has enough strength to withstand the vibrations and shocks caused by the operation of the overhead running lane 6. From the completion of the operation floor 2 of the nuclear Fm seat 1 to the reactor building 10
The construction period will be approximately 6 to 8 months until the roof 11 is completed, and during this time it will not be possible to carry and install equipment into the reactor building 1 using the overhead lane 6.

そこで従来は、運転操作床面2より上層の原子炉娼屋壁
3および屋;[11の完成に先立って原子炉建屋1への
機器等の搬入、裾付けを実施する必要がある場合には、
天井走行うレーン6を用いず仮設の均N設備を用いるよ
うにしているが、仮設燭雉設儒の組立ておよび撤去作業
が必須となってその分工期が焚くなり、またその労費用
も嵩む等の端点がある。
Therefore, conventionally, the reactor brothel wall 3 and the floor above the operation floor 2; ,
Temporary uniform equipment is used instead of overhead lane 6, but it requires assembly and removal of the temporary candlesticks, which lengthens the construction period and increases labor costs. There are endpoints.

〔発明の目的〕[Purpose of the invention]

本発明はかかる現況に鑑みなされたもので、建屋側の工
事とは無関係に4屋内クレーンを使用することができる
建屋内クレーンの据付工法を提供することを目的とする
The present invention was made in view of the current situation, and it is an object of the present invention to provide a construction method for installing an indoor crane, which allows the use of four indoor cranes regardless of the construction work on the building side.

〔発明の概要〕[Summary of the invention]

本発明は、建屋−jの工事とは無関係に建屋内クレーン
を便用することができる手段として、清面上に基面レー
ルを敷設し、車種を有する仮設走行脚をクレーンガーダ
の両端に着脱可能に取付けて悄成される門型クレーンを
前記基面レール上に設直し、この門型クレーンを用いた
機器の移送と娃座の建没工iとを並行して行ない、建屋
竣工後前記門型クレーンの仮設走行脚を撤去しクレーン
ガーダを走行レール上に設置して天井走行うレーンとし
たことを特徴とする。
The present invention, as a means to make it possible to conveniently use the crane inside the building regardless of the construction work on building-j, lays a base rail on the clear surface and attaches and detaches temporary running legs of different vehicle types to both ends of the crane girder. A gantry crane, which can be easily attached and rebuilt, is reinstalled on the base rail, and the transportation of equipment using this gantry crane and the erection and demolition work of Naza are carried out in parallel, and after the building is completed, the above-mentioned It is characterized by removing the temporary running legs of the gate-type crane and installing a crane girder on the running rail to create a lane for overhead running.

〔発明の実施例〕[Embodiments of the invention]

以下本発明実施の一態様を第4図ないし第7図を参照し
て説明する。
One embodiment of the present invention will be described below with reference to FIGS. 4 to 7.

第4図ないし第6図において16は、原子炉建屋1の運
転操作床面2に埋設した埋込プレート12に取付けられ
た門型クレーン用走行レール13上に設置される門型ク
レーンであり、この間型クレーン16には、クレーンガ
ーダ9の両側端から梢内徂uに入った部分にブロック構
造をなし走行車輪付きの仮設走行脚14がボルト締めに
より漬脱0T舵にそイLぞれ取付けられている。この2
組の仮設定行H14のうちの一方には、第4図に示すよ
うに帖也用亀線ドラム15が堰付けられ、このi@ ’
a用tWドラム15を介して給゛畦用゛[4腺17が引
出されている。
In FIGS. 4 to 6, 16 is a portal crane installed on a traveling rail 13 for a portal crane attached to an embedded plate 12 buried in the operation floor 2 of the reactor building 1, At this time, temporary running legs 14 with running wheels, which have a block structure at the part of the crane girder 9 that enters the treeside area U from both ends of the crane girder 9, are attached to the submerged 0T rudder by tightening bolts. It is being This 2
As shown in FIG. 4, a tortoise line drum 15 for choya is attached to one of the temporarily set rows H14 of the set, and this i@'
The four glands 17 for the supply area are drawn out through the TW drum 15 for a.

また両仮設矩行脚14からは、第4図に示すように各2
本のワイヤ18が前記走行レール13の延在方向にそれ
ぞれ引出されており、各ワイヤ18の端部は同一定格の
4台の走行用ウィンチ19にそれぞれ巻回されている。
In addition, from both temporary rectangular walking legs 14, as shown in FIG.
Two wires 18 are drawn out in the extending direction of the running rail 13, and the ends of each wire 18 are wound around four running winches 19 having the same rating.

そしてこれらの走行用ウィンチ19の回転駆動により、
前記門型クレーン16は走行レール上3上を走行するよ
うになっている。またこの門型クレーン16のクレーン
ガーダ9上には、走行レール13の幅方向に慣行するト
ロIJ 10が設直されている。
By rotating these traveling winches 19,
The gantry crane 16 is configured to travel on a traveling rail 3. Further, on the crane girder 9 of this portal crane 16, a conventional Toro IJ 10 is installed in the width direction of the traveling rail 13.

一方、原子炉建屋11i+Ilでは、第6図に示すよう
に門型クレーン16を稼動させながら、原子f′a座愛
3.天井走行うレーン基礎4.走行レール5゜給祇用架
廠7.圧根トラス8.′J6よび屋根11の建設工事が
順次手順を追って実施されるようになっている。そして
屋但11のコンクリートが充分な査生晧経て屋根工部が
完了した後、第6図および第7図に示すようにジヤツキ
20を天井走行うレーン基礎4上に設直して門型クレー
ン16を持ち上げ、仮設走行脚14等を撒去して門型ク
レーン16を天井走行うレーン6として構築するように
なっている。
On the other hand, in the reactor building 11i+Il, as shown in FIG. Lane basics for ceiling running 4. Traveling rail 5゜Storage for feeding 7. Pressure root truss8. 'Construction work on J6 and roof 11 is being carried out step by step. After the roof work has been completed with sufficient concrete on the roof 11, the jack 20 is reinstalled on the lane foundation 4 that runs overhead as shown in Figures 6 and 7. is lifted, the temporary traveling legs 14 and the like are thrown away, and a lane 6 is constructed in which the gate-type crane 16 runs overhead.

次に、建屋内クレーンの据付方法について説明する。Next, the method for installing the crane inside the building will be explained.

まず、原子炉建屋lの連松煉作床面2に埋込プレート1
2を埋設する。この際、門型クレーン16の仮設走行脚
14が後に建設される原子炉建屋壁3と干渉しないよう
に、原子pmm槽壁から一定寸法内側に埋込プレート1
2を埋設する。また運転操作法面2の他の部分の表面よ
り低くなるように埋込プレート12を埋設する。
First, the embedded plate 1 is placed on the continuous pine cultivation floor 2 of the reactor building l.
Bury 2. At this time, in order to prevent the temporary traveling legs 14 of the portal crane 16 from interfering with the reactor building wall 3 that will be constructed later, an embedded plate 1 is placed a certain distance inside from the atomic PMM tank wall.
Bury 2. Further, the embedding plate 12 is buried so as to be lower than the surface of other parts of the driving operation slope 2.

埋込プレート12を埋設して運転操作床1IiJ2を完
成させた後、埋込プレート12上にボルト<により走行
レール13を据付ける。
After embedding the embedding plate 12 to complete the operation floor 1IiJ2, the traveling rail 13 is installed on the embedding plate 12 with bolts.

一方地上では、クレーンガーダ9を組立て、その両端近
傍に、予めボルト締めによりブロック構造に組立てられ
た仮設走行脚14を走行レール13と同一寸法間隔でボ
ルトによりそれぞれ柩付ける。
On the ground, on the other hand, the crane girder 9 is assembled, and temporary traveling legs 14, which have been previously assembled into a block structure by bolting, are bolted near both ends of the crane girder 9 at the same dimensional intervals as the traveling rails 13.

この除、仮設走行脚14の高さは、クレーンガーダ9の
下面が後に建設される走行レール5の上面より梢尚くな
るように設定される。
Other than this, the height of the temporary traveling leg 14 is set so that the lower surface of the crane girder 9 is higher than the upper surface of the traveling rail 5 that will be constructed later.

次いで、仮設走行脚14が取付けられたクレーンガーダ
9を、原子炉建屋1の建設に用いる揚重設 □備等を利
用して前記走行レール13上に設置し、その後同様の方
法lこよりトロリlOを吊り上げてクレーンガーダ9上
に設置する。そして走行レール13の端部に設置した4
台の走行用ウィンチ19と仮設走行脚14とをワイヤ1
8を介して連結する。また一方の仮設走行脚14には給
電用電線ドラム15を柩付け、このドラム15を弁し仮
設の給電用′鑞d17を布設して寛気工挙を行なう。
Next, the crane girder 9 to which the temporary running legs 14 are attached is installed on the running rail 13 using the lifting equipment used for the construction of the reactor building 1, and then the trolley lO is lifted by the same method. is lifted and installed on the crane girder 9. 4 installed at the end of the running rail 13.
The running winch 19 of the stand and the temporary running legs 14 are connected to the wire 1.
Connect via 8. Further, a power supply wire drum 15 is attached to one of the temporary running legs 14, the drum 15 is closed, and a temporary power supply wire d17 is laid to perform the construction.

通気試験等を実施した後、前記給電用電線17を介して
仮設の’d源から同型クレーン161こ給′シし、門型
クレーン16を稼動させてdk−a″4の搬入3よび据
付は等を実施する。前記絽甑用′厄線ドラム15は、仮
設走行脚14の走行と連動して給゛亀用電祿17の巻取
りおよび巻戻しを行なう。
After conducting ventilation tests, etc., the crane 161 of the same type is fed from the temporary 'd source via the power supply wire 17, and the portal crane 16 is operated to carry in and install the dk-a''4. The electric wire drum 15 for the electric wire 15 winds up and rewinds the electric wire 17 for the supply turtle in conjunction with the running of the temporary running legs 14.

一方、門型クレーン16のwhと並行して原子炉建屋1
−では、6g6図に示すように原子炉建屋壁3、天井走
行うレーン基睦4.走行レール5.f@′亀用架繍7.
屋根トラス8.および圧機11の建設工事を顔次手r=
を追って実施する。
On the other hand, the reactor building 1 is located in parallel with the wh of the portal crane 16.
-, as shown in Figure 6g6, the reactor building wall 3, the lane base 4 for running on the ceiling. Traveling rail 5. f@' Turtle embroidery 7.
Roof truss8. And the construction work of press machine 11 will be carried out by r=
will be implemented accordingly.

屋根11のコンクリートが充分な養生を経て屋根工事が
完了したならば、第6図に示すようにジヤツキ加を天井
走行うレーン基礎4゜上に設置して門型クレーン16を
持ち上げる。
When the concrete of the roof 11 has sufficiently cured and the roof work is completed, the jacking is installed on the lane foundation 4° above which the roof runs, as shown in FIG. 6, and the gate type crane 16 is lifted.

次いで、仮設の給電用電線17をトロリ10への接或は
残して配線層えし、成膜走行F#14のドラム15を取
外してもトロリエ0は動作できるようにする。
Next, the temporary power supply wire 17 is connected to the trolley 10 or left in the wiring layer so that the trolley 0 can operate even if the drum 15 of the film forming run F#14 is removed.

また走行用ウィンチ19と仮設走行脚14との間のワイ
ヤ18も取外す。また仮設走行脚14は、谷部のボルト
を緩め、配線層えしたトロリ10を利用して第6図に示
す小ブロツク部材21に分解していく。
The wire 18 between the traveling winch 19 and the temporary traveling leg 14 is also removed. Further, the temporary running legs 14 are disassembled into small block members 21 shown in FIG. 6 by loosening the bolts in the valleys and using the trolley 10 on which wiring is layered.

仮設定行脚14の分解か完了したならば、ジヤツキ肋に
よりクレーンガーダ9を天井走行うレーン基礎4上の走
行レール5の上に設直し、仮設の給電用電線17を撤去
して給電用架臓7より正規の配線工事を行なう。そして
電気試雇寺を実施する。
Once the disassembly of the temporarily set walking leg 14 is completed, the crane girder 9 is reinstalled using jack ribs on the running rail 5 on the lane foundation 4 for overhead running, the temporary power supply wire 17 is removed, and the power supply frame is removed. Perform regular wiring work from step 7. And we will carry out the electric test employment temple.

運転操作床L1iJ2上に残された門型クレーン16用
の走行レール13は、埋込プレート12力)ら取外して
小ブロックに切断する。そして埋込プレート12上には
、他の床面と同じようにハツリ、撒去を行なう。
The travel rail 13 for the portal crane 16 left on the operation floor L1iJ2 is removed from the embedded plate 12) and cut into small blocks. Then, chipping and scattering are performed on the embedded plate 12 in the same way as on other floor surfaces.

また良設走′行脚14が取付けられていたクレーンガー
ダ9下面のボルト孔は、銑板等で基いて塗装を施し、第
7図に示すように天井走行うレーン6として完成させる
In addition, the bolt holes on the lower surface of the crane girder 9, to which the traveling legs 14 were attached, are covered with a pig plate or the like and painted to complete the overhead traveling lane 6 as shown in FIG.

天井走行うレーン6が正規の状態に儲付けられて体動で
きるようになった後、小ブロツク部材21に分解してお
いた仮設走行脚14.走行レール13゜および走行用ウ
ィンチ19寺を天井走行うレーン6を利用して原子炉建
屋1の搬出入口から撤去する。
After the overhead running lane 6 is in a normal condition and the body can move, the temporary running legs 14 are disassembled into small block members 21. The traveling rail 13° and the traveling winch 19 are removed from the loading/unloading entrance of the reactor building 1 using the overhead lane 6.

しかして、原子炉建屋lの運転保作尿面2より土層の部
分の完成を待たすに建庄内クレーン、すなわち門型クレ
ーン16ソ稼動させることができる。
Therefore, the crane within the construction site, that is, the gantry crane 16, can be operated while waiting for the completion of the soil layer from the operational maintenance surface 2 of the reactor building 1.

この粕釆、臓器の搬入および垢付けを原子炉建屋1の建
設工事と並行して行なうことがでさ、・1幾器の搬入お
よび据付けの開始を、原子炉建屋1の完成を臀って行な
う従来方法に比較して6ないし8面月間早くすることが
できる。そしてこの場合、屋根11のコンクIJ = 
トが充分に乾保する前であっても、門型クレーン1bの
荷重支持点は原子Fm屋壁3ではなく運私沫作床囲2で
あるので、硅屋1内クレーンの稼動による屋根11のコ
ンクリートに対する振動、衝撃の影譬は殆んどなく、実
用土問題となることはない。
It is possible to carry out the transport and polishing of the lees and organs in parallel with the construction work of reactor building 1, and to carry out the transport and installation of the 1000 pieces in parallel with the completion of reactor building 1. Compared to the conventional method, the process can be completed 6 to 8 months faster. And in this case, conc IJ of roof 11 =
Even before the roof 11 is sufficiently kept dry, the load support point of the gate type crane 1b is not the atomic Fm building wall 3 but the private splashing floor enclosure 2. There is almost no effect of vibration or impact on concrete, and there is no problem with practical soil.

また、門型クレーン16を用いてa器の搬入および据付
けを行なうので、従来方法と異なり特別な揚重設備が不
要である。
Further, since the gantry crane 16 is used to carry in and install the equipment, no special lifting equipment is required, unlike the conventional method.

なお前記実施の一態様では、原子炉建屋の天井走行うレ
ーンを例に採って説明したが、一般的な建屋内クレーン
にも適用できることは云うまでもない。
In the above-mentioned embodiment, the explanation has been given using an example of a lane that runs overhead in a nuclear reactor building, but it goes without saying that the present invention can also be applied to a general crane inside a building.

〔発明の効果〕〔Effect of the invention〕

以上説明したように本発明は、泰囲上に基面レールを敷
設し、車輪を有する仮設定行脚をクレーンガーダの両端
に看脱可能に柩付けて傳成される門型クレーンを前記基
面レール上に設直し、この門型クレーンを用いた機材の
移送と建屋の建設工事とを並行して行ない、建屋竣工後
前記門型クレーンの仮設走行脚を撒去しクレーンガーダ
を建屋側の走行レール上に設置して天井走行うレーンと
するようにしているので、建屋内クレーンの稼動と建屋
の建設工事とを並行して行なうことができ、また機材移
送用の特別な揚重設備が小袋である。
As explained above, the present invention provides a gate-type crane constructed by laying a base rail on the base and removably attaching temporarily set walking legs with wheels to both ends of the crane girder. The crane will be reinstalled on the rail, and the equipment will be transferred using this gantry crane and the building construction work will be carried out in parallel. After the building is completed, the temporary traveling legs of the gantry crane will be removed and the crane girder will be moved to the building side. Since it is installed on the rails and used as an overhead lane, it is possible to operate the crane inside the building and construct the building at the same time. It is.

この結果、大幅な工期短紬および建設費の削減が可能と
なる。
As a result, it will be possible to significantly shorten the construction period and reduce construction costs.

【図面の簡単な説明】[Brief explanation of drawings]

第1図ないし第3図は原子F建屋内クレーンの従来の据
付工法を工程J[に示す説明図、第4図は本発明に係る
門型クレーンを示す斜視図、第5図ないし第7図は本発
明に係る原子炉建屋内クレーンの据付工法を工程順に示
す説明図である。 1・・・原子炉建屋、2・・・運転昧作床面、3・・・
原子炉建屋!、5.13・・・走行レール、6・・・天
井走行うレーン、9・・・クレーンガーダ、10・・・
トロリ、14・・・仮設走行脚、16・・・門型クレー
ン、加・・・ジヤツキ。 出顧人代理人   宛  股     清弗1図 2 弗2図 峯3図
Figures 1 to 3 are explanatory diagrams showing the conventional installation method of a crane inside the atomic F building in process J[, Figure 4 is a perspective view showing a portal crane according to the present invention, and Figures 5 to 7 FIG. 1 is an explanatory diagram showing the installation method of a crane inside a nuclear reactor building in order of steps according to the present invention. 1... Reactor building, 2... Operational cropping surface, 3...
Reactor building! , 5.13... Traveling rail, 6... Lane for overhead running, 9... Crane girder, 10...
Trolley, 14...Temporary traveling legs, 16...Gate type crane, addition...Jacket. To the client's agent: Kiyohisa Mata Figure 1, Figure 2, Figure 2, Figure 3, Mine.

Claims (1)

【特許請求の範囲】 1、基面上に建設される娃屋壁にクレーン基礎および走
行レールをそれぞれ構築し、走行レール上に走行うレー
ンを据付けるものにおいて、基面上にAltIレールを
敷設し、車輪を有する仮設走行脚をクレーンガーダの側
端に庸脱可V4目に取付けて濃酸される門型クレーンを
前記基面レール上に設置し、この門型クレーンを用いた
嶺材の移送とKJ記建屋の建設工事とを並行して行ない
、建屋竣工後前記門型クレーンの仮設走行脚“を撤去し
クレーンガーダを走行レール上に設置して天井走行うレ
ーンとすることを特徴とする建龜円クレーンの据付工法
。 2、原子炉運転操作床面上に構築される原子炉建座内ク
レーンに適用することを特徴とする特許請求の軛囲第1
項記載の建座内クレーンの据付工法。
[Scope of Claims] 1. A crane foundation and a running rail are constructed on the roof wall constructed on the base, and a lane running on the running rail is installed, in which an AltI rail is laid on the base. Then, a temporary running leg with wheels was attached to the side end of the crane girder with removable V4, and a gate-type crane to be concentrated was installed on the base rail, and the ridge material was constructed using this gate-type crane. The transfer and the construction work of the KJ Ki building are carried out in parallel, and after the building is completed, the temporary running legs of the gate type crane are removed and the crane girder is installed on the running rail to create a lane for overhead running. 2. The first claim of the patent claim, which is applied to a crane in the reactor building built on the reactor operation floor.
Installation method for in-building cranes as described in section.
JP58032088A 1983-02-28 1983-02-28 Method of installation of crane in housing Pending JPS59158793A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP58032088A JPS59158793A (en) 1983-02-28 1983-02-28 Method of installation of crane in housing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP58032088A JPS59158793A (en) 1983-02-28 1983-02-28 Method of installation of crane in housing

Publications (1)

Publication Number Publication Date
JPS59158793A true JPS59158793A (en) 1984-09-08

Family

ID=12349120

Family Applications (1)

Application Number Title Priority Date Filing Date
JP58032088A Pending JPS59158793A (en) 1983-02-28 1983-02-28 Method of installation of crane in housing

Country Status (1)

Country Link
JP (1) JPS59158793A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100417586C (en) * 2006-04-13 2008-09-10 中国机械工业建设总公司 Integral lifting method of large bridge crane and its appts

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100417586C (en) * 2006-04-13 2008-09-10 中国机械工业建设总公司 Integral lifting method of large bridge crane and its appts

Similar Documents

Publication Publication Date Title
US4187659A (en) Home building method and apparatus
JP2005083186A (en) Demolition and removal method for arch bridge
JP4134104B2 (en) Bridge removal method
CN104480915B (en) A kind of anti-rail hydraulic climbing formwork for high gradient slope concreting
CN112875538B (en) Prefabricated overhead box girder hoisting process
JP2011174241A (en) Method for laying floor slab onto bridge girder
JPS59158793A (en) Method of installation of crane in housing
JP2004225529A (en) Continuous laying method for precast concrete slab
CN217079776U (en) Civil engineering building unwrapping wire equipment
CN214091679U (en) Shield constructs simple and easy removal cat ladder device of machine installation
CN210552092U (en) Box girder internal mold integral pulling application equipment
JP2019173365A (en) Method of constructing linear structure
CN221318898U (en) Hoisting device for prefabricated box girder
CN215563337U (en) Steel structure integrated house
CN106437290A (en) Splicing type enclosing wall, fence structure and construction method thereof
JPH0745799B2 (en) Method and apparatus for installing precast plate for tunnel
JP3373318B2 (en) Transfer device
JPS62228974A (en) Method of construction of housing for nuclear power plant
JPH03137399A (en) Method and device for installation of precast plate for tunnel
JPS631724Y2 (en)
JPS62159092A (en) Method of housing construction of nuclear power plant
JPH058305B2 (en)
CN111005564A (en) Construction method based on steel structure on waffle floor
JPH0416596B2 (en)
CN112282779A (en) Long-distance open type TBM (tunnel boring machine) single-head tunneling small-section quick dismantling system and construction method