JPS59145824A - Construction of joint work of continuous underground wall - Google Patents

Construction of joint work of continuous underground wall

Info

Publication number
JPS59145824A
JPS59145824A JP1972483A JP1972483A JPS59145824A JP S59145824 A JPS59145824 A JP S59145824A JP 1972483 A JP1972483 A JP 1972483A JP 1972483 A JP1972483 A JP 1972483A JP S59145824 A JPS59145824 A JP S59145824A
Authority
JP
Japan
Prior art keywords
space
concrete
trench
joint
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP1972483A
Other languages
Japanese (ja)
Inventor
Teruo Abe
阿部 照男
Masahiko Ideguchi
井出口 雅彦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ohbayashi Gumi Ltd
Obayashi Gumi Ltd
Original Assignee
Ohbayashi Gumi Ltd
Obayashi Gumi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ohbayashi Gumi Ltd, Obayashi Gumi Ltd filed Critical Ohbayashi Gumi Ltd
Priority to JP1972483A priority Critical patent/JPS59145824A/en
Publication of JPS59145824A publication Critical patent/JPS59145824A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To simplify the construction of joints of a continuous underground wall by a method in which a locking box with a vertically grooved uneven surface is inserted into a trench, concrete is placed, the box is pulled out to form a space for a joint, and coupling iron bars are set into the space. CONSTITUTION:A trench 1a is excavated, a locking box 3 with sides having vertically grooved uneven surfaces and an iron bar cage 2a are inserted into the trench 1a, concrete is placed into the trench 1a and hardened, and the box 3 is pulled out to form a space 4a with large numbers of vertical grooves. In the same way, a trench 1b is excavated in the following wall section B, an iron bar cage (not illustrated) and the locking box 3 are inserted into the trench 1b, concrete is placed into the trench 1b, and the box 3 is pulled out to form a space (not illustrated) leading to the space 4a. An iron bar cage (not illustrated) for connection is inserted into the space and then concrete is placed to complete the construction of the joint work.

Description

【発明の詳細な説明】 この発明は、連続地中壁の打継部の施工方法に関するも
のである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for constructing a joint in a continuous underground wall.

掘削溝に鉄筋前を挿入し、コンクリートを打設すること
を繰り返して構築する場所打鉄筋コンクリート連続地中
壁は、単に土留め壁に留まらず構築物本体壁として利用
される。これは、連続地中壁の単位壁体間の打継部を強
固に連結する技術の進歩によるところが大きい。
Cast-in-place reinforced concrete continuous underground walls, which are constructed by repeatedly inserting reinforcing bars into excavated trenches and pouring concrete, are used not only as earth retaining walls but also as the main walls of structures. This is largely due to advances in technology for firmly connecting joints between unit walls of continuous underground walls.

しかしながら、との打継部の連結方法は多種多様であっ
て、いずれも完全とはいえない。例えば、打継部に仕切
板を設け、これに水平方向の主筋をjlを通させ、次位
壁体側番ご突出させておき、次位壁体のコノクリート打
設時にその鉄筋前と重ね継手にする方法が有力であるが
、この方法は施工が難しく、仕切板をコンクリート中に
埋残すという無駄を生ずる欠点があった。
However, there are a wide variety of methods for connecting the splicing part with the joint, and none of them can be said to be perfect. For example, a partition plate is provided at the joint, and the horizontal main reinforcement is passed through it, and the side number of the next wall is made to protrude, and when pouring the conocret of the next wall, the reinforcement is placed in front of the reinforcing bar and at the lap joint. Although this method is effective, it is difficult to construct and has the disadvantage that the partition plates are left buried in the concrete, which is wasteful.

本発明は、こうした事情に鑑みなされたものであって、
打継部の打継面を凹凸形Ifにすれば、その面↓こ働く
せん断力の伝達の低下を防ぐことに着眼し、敢えて鉄筋
の重ね継手部の相互の鉄筋間に沿って凹凸形吠の打継面
を設けることによって、上記した欠点を排除するもので
ある。
The present invention was made in view of these circumstances, and
By making the joint surface of the joint part uneven If we focused on preventing a decrease in the transmission of shear force acting on that surface, we purposely created a convex-convex shape along between the reinforcing bars of the lapped joint of reinforcing bars. By providing a joining surface, the above-mentioned drawbacks are eliminated.

以下、本発明の実施例を図面を参照しながら説明する。Embodiments of the present invention will be described below with reference to the drawings.

図面は、連続地中壁の打継部の施工の杖態を工程順に示
す平面図であって、各図の左側部分は先行壁体部Aで、
右側部分は次位壁体部ずなわち後行壁体部Bを示す。
The drawings are plan views showing the construction process of the joint part of a continuous underground wall in the order of steps, and the left side of each figure is the preceding wall part A;
The right-hand part shows the next wall part, the trailing wall part B.

まず、第1図に示すように溝1aを掘削し、鉄筋[2a
およびロッキングボックス3を挿入する。ロッキングボ
ックス3は、鉄筋[2aの端部の主筋間にはさまれて配
置され、その主筋に平行な側面を有する筒伏体であって
、その側面が縦溝杖凹凸面を存するよう、例えば鉄骨枠
M3aの外周にデツキプレー)3bを張ったものである
First, as shown in Fig. 1, a groove 1a is excavated,
and insert locking box 3. The locking box 3 is a cylindrical body that is disposed between the main reinforcements at the ends of the reinforcing bars [2a] and has side surfaces parallel to the main reinforcements, and is designed so that the side surfaces have an uneven surface, for example. Detsuki play) 3b is stretched around the outer periphery of a steel frame M3a.

そして溝1a内にコンクリートを打設し、硬化が始まっ
てからロッキングボックス3を引き抜けば、その抜き跡
は、連続地中壁壁体に平行な面に多数の縦溝を有する欠
き込み空間部4aを形成する(第2図)。
Then, concrete is placed in the groove 1a, and when the locking box 3 is pulled out after it begins to harden, the remains of the concrete is a notched space with many vertical grooves in a plane parallel to the continuous underground wall. 4a (Fig. 2).

つぎに、後行壁体部Bに溝1bを掘削する。Next, a groove 1b is excavated in the trailing wall portion B.

掘削の際、仕切板5により、欠き込み空間部4aへの土
砂の流入を防ぐが、掘削後この仕切板を抜き取る。その
際に先行壁体の端面6を壁面切削装置(図示せず。なお
、この装置はドラムカッタ一式掘削機で兼用できる。)
により浅く削っておけば構造上効果がある。
During excavation, the partition plate 5 prevents earth and sand from flowing into the notch space 4a, but this partition plate is removed after excavation. At that time, the end surface 6 of the preceding wall body is cut by a wall cutting device (not shown. Note that this device can also be used as an excavator with a drum cutter set).
If it is cut more shallowly, it will have a structural effect.

さらに、溝1bに後行壁体筋籠2bおよびロッキングボ
ックス3を第3図のように挿入する。これら、の部材お
よび配置は先行壁のものとほぼ同じであるが、コンクリ
ートの側圧を仕切仮によらず反力受7によっている点か
異なる。
Further, the trailing wall reinforcement 2b and the locking box 3 are inserted into the groove 1b as shown in FIG. 3. The members and arrangement of these are almost the same as those of the preceding wall, but the difference is that the lateral pressure of the concrete is handled by the reaction force receiver 7 rather than by the partition.

図面では反力受7をロッキングボックス3に取付けた油
圧シリンダーとしたが、一定の幅の枠組を別に挿入して
もよい。
In the drawing, the reaction force receiver 7 is a hydraulic cylinder attached to the locking box 3, but a frame with a certain width may be inserted separately.

こうして満1bにもコンクリートを打設し、硬化開始後
、同様にロッキングボックス3を引き抜く。すると既に
形成している先行壁体の欠き込み空間部4aに連通ずる
後行壁体欠き込み空間部4bが形成される(第4図)6 そして、その壁面をクリーニングした後、空間部内に接
続用鉄筋[2cを挿入し、コンクリートを打設して打継
部の施工を終るのである。
In this way, concrete is placed in the full area 1b, and after the concrete starts to harden, the locking box 3 is similarly pulled out. Then, a trailing wall recess space 4b is formed which communicates with the recess space 4a of the preceding wall that has already been formed (Fig. 4).6 Then, after cleaning the wall surface, a recess space 4b is formed that communicates with the recess space 4a of the preceding wall. The reinforcing bars [2c] are inserted, concrete is poured, and the construction of the joint is completed.

この結果、先行壁体の水平方向の主筋は、連続地中壁に
平行な打継面を介して接続用鉄筋前2cの水平方向の主
筋と重ね継手を形成し、その間に存在する打継面は縦方
向の条溝を有する凹凸面であるからコンクリートのせん
断力の伝達を損なわず、打継部の構造耐力を高める。
As a result, the horizontal main reinforcement of the preceding wall forms a lap joint with the horizontal main reinforcement of the connecting reinforcing bar 2c through the joint surface parallel to the continuous underground wall, and the joint surface that exists between them. Since it is an uneven surface with vertical grooves, it does not impair the transmission of shear force of the concrete and increases the structural strength of the joint.

なお、本実施例では、後行壁体側にもロッキングボック
スを使用したが、これを用いず、かつ、後行壁体鉄筋1
1R2bと接続用鉄筋前2cとを一体に形成して挿入し
、後行壁体部のNibと先行壁体の欠き込み空間部4a
とに同時にコンクリートを打設しても本発明の効果を損
うものではない。
In this example, a locking box was also used on the trailing wall side, but this was not used and the trailing wall reinforcing bar 1
1R2b and the front connection reinforcing bar 2c are integrally formed and inserted, and the Nib of the trailing wall body and the notch space 4a of the leading wall body are inserted.
Even if concrete is poured at the same time, the effects of the present invention will not be impaired.

以上、本発明は、重ね継手を形成する先行壁体と後行壁
体の相互の水平方向主筋の間に凹凸形状の打継面を設け
るものであるから、打継面のせき板に主筋を貫通させる
必要がなく、従ってそのせき板に代わるロッキングボッ
クスの転用が可能であるから、せき板を埋め残ずことな
く打継部の構造耐力を維持する利点を有する。
As described above, since the present invention provides an uneven joint surface between the horizontal main reinforcements of the leading wall and the trailing wall that form a lap joint, the main reinforcement is provided on the weir plate of the joint surface. There is no need to penetrate the weir, and therefore a locking box can be used in place of the weir plate, which has the advantage of maintaining the structural strength of the joint without leaving the weir plate unfilled.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図ないし第4図は、本発明の実施例を工程順に示す
平面断面図である。 lal lb−・溝、2 a % 2 b % 2 c
 ・−鉄筋前、3・・・ロッキングボックス、3a・・
・鉄骨枠組み、3b・・・デツキプレート、4a、4b
・・・欠き込み空間部、5・・・仕切板、6・・・先行
壁体端面、7・・・反力受 特許出願人 株式会社大杯絹
1 to 4 are plan sectional views showing an embodiment of the present invention in the order of steps. lal lb- groove, 2 a % 2 b % 2 c
・-In front of reinforcing bar, 3... Locking box, 3a...
・Steel frame, 3b...Deck plate, 4a, 4b
... Notch space portion, 5 ... Partition plate, 6 ... Leading wall end face, 7 ... Reaction force receiving patent applicant Oaibe Kinu Co., Ltd.

Claims (1)

【特許請求の範囲】 (+)  1lil削溝に鉄筋前を押入し、コンクリー
トを打設することを繰返して連続地中壁を構築するにあ
たり、鉄筋前の挿入の際、少くとも次位壁体側端部の2
列の主筋の間に、これに沿う面が縦溝状凹凸面であるロ
ッキングボックスを挿入し、コンクリート打設後、これ
を抜き取って、打継部に欠き込み空間部を形成し、この
空間部に次位壁体部と共通する継手部鉄筋を挿入した後
、コンクリートを打設することを特徴とする連続地中壁
打継部の施工方法。 (2) 縦溝状凹凸面がデツキプレートである特許請求
の範囲第1項記載の連続地中壁打継部の施工方法。
[Claims] (+) When constructing a continuous underground wall by repeatedly inserting the reinforcing bar into a 1 liter cut groove and pouring concrete, when inserting the reinforcing bar, at least the next wall side 2 at the end
A locking box whose surface along the main reinforcing bars has an uneven vertical groove is inserted between the rows of main reinforcing bars, and after concrete is poured, it is removed and cut into the joint to form a space, and this space is A method of constructing a joint part of a continuous underground wall, characterized by inserting reinforcing bars at the joint part common to the next wall part, and then pouring concrete. (2) The method for constructing a continuous underground wall joint according to claim 1, wherein the vertically grooved uneven surface is a deck plate.
JP1972483A 1983-02-10 1983-02-10 Construction of joint work of continuous underground wall Pending JPS59145824A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1972483A JPS59145824A (en) 1983-02-10 1983-02-10 Construction of joint work of continuous underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1972483A JPS59145824A (en) 1983-02-10 1983-02-10 Construction of joint work of continuous underground wall

Publications (1)

Publication Number Publication Date
JPS59145824A true JPS59145824A (en) 1984-08-21

Family

ID=12007251

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1972483A Pending JPS59145824A (en) 1983-02-10 1983-02-10 Construction of joint work of continuous underground wall

Country Status (1)

Country Link
JP (1) JPS59145824A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4423149Y1 (en) * 1965-03-05 1969-09-30
JPS5738835B2 (en) * 1979-03-15 1982-08-18

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4423149Y1 (en) * 1965-03-05 1969-09-30
JPS5738835B2 (en) * 1979-03-15 1982-08-18

Similar Documents

Publication Publication Date Title
JPS61122320A (en) Method of coupling continuous underground wall with underground structure
JPS59145824A (en) Construction of joint work of continuous underground wall
JPS59145823A (en) Construction of joint work of continuous underground wall
JP2621485B2 (en) Construction method of underground wall
JPH08246443A (en) Joint construction of great depth continuous underground wall reinforced cage
JP7248558B2 (en) How to build a diaphragm wall
JPH041811B2 (en)
JP3000495B2 (en) Large-scale, deep steel continuous basement wall and method of constructing the same
JPH02136421A (en) Construction method of underground circular continuous wall
JP2558414B2 (en) Construction method of the main retaining wall and the retaining wall
JPS61257529A (en) Underground continuous wall construction work
JPH0144849B2 (en)
JP2987662B2 (en) How to build a continuous underground wall
JP2689743B2 (en) How to build an underground structure
JPS5923107Y2 (en) Concrete U-shaped groove block
JPH0437203B2 (en)
JPH0529236Y2 (en)
JPH0931972A (en) Construction of underground continuous wall
JPH05132927A (en) Construction method of underground continuous wall
JPH0660492B2 (en) Vertical underground construction method for continuous underground wall
JPS63125722A (en) Construction of underground continuous wall
JPS63125725A (en) Construction of underground continuous wall
JPH093879A (en) Building material made of steel having concrete flow hole and building method for concrete structure using the building material made of steel
JPS5822605B2 (en) Underground continuous wall construction method
JPS6313487B2 (en)