JPS59133008A - Facility for manufacturing concrete material through slidingmolding - Google Patents

Facility for manufacturing concrete material through slidingmolding

Info

Publication number
JPS59133008A
JPS59133008A JP736583A JP736583A JPS59133008A JP S59133008 A JPS59133008 A JP S59133008A JP 736583 A JP736583 A JP 736583A JP 736583 A JP736583 A JP 736583A JP S59133008 A JPS59133008 A JP S59133008A
Authority
JP
Japan
Prior art keywords
lower mold
concrete
steel wire
crane
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP736583A
Other languages
Japanese (ja)
Inventor
義彦 村上
登 太田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuji PS Corp
Original Assignee
Fuji PS Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuji PS Corp filed Critical Fuji PS Corp
Priority to JP736583A priority Critical patent/JPS59133008A/en
Publication of JPS59133008A publication Critical patent/JPS59133008A/en
Pending legal-status Critical Current

Links

Landscapes

  • Devices For Post-Treatments, Processing, Supply, Discharge, And Other Processes (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 この発明は摺動成形によるコンクリート材製造設備に関
し、そのコンクリート材はプレテンション法によるPC
コンクリート材であり、その設備は工事現場に移設し、
壕だ解体すること容易なことを主な特徴とするものであ
る。
[Detailed Description of the Invention] This invention relates to equipment for producing concrete material by sliding forming, and the concrete material is made of PC by pre-tensioning method.
It is made of concrete, and the equipment will be relocated to the construction site.
The main feature is that the trench can be easily dismantled.

本発明者はコンクリート版の摺動成形法、R口ち長尺下
型両縁のレールに上型を載せ、これをウィンチけん引に
より摺動させて下型上の硬練コンクリートを成形する新
規な成形法の開発者でおる。この摺動成形法のための設
備、装置は実用新案第1067941号以来、逐次開発
、出願し、既に実用製品を生産している。
The present inventor has developed a new method for sliding concrete slabs, in which the upper mold is placed on rails on both edges of the R-shaped long lower mold, and the hardened concrete on the lower mold is formed by sliding the upper mold by winch traction. I am the developer of the molding method. Equipment and devices for this sliding molding method have been developed and applied for successively since Utility Model No. 1067941, and practical products have already been produced.

しかしながら、その設備は補助作業工程で未だ手作業に
頼る部分が少くなく、特に100′rrL前後の長尺下
型上に予めPC鋼線を数本ないし十数本配設する作業、
その下型上に硬練コンクリートを均等に落し敷く作業に
人手を要していた。
However, the equipment still relies on manual labor in many auxiliary work processes, especially the work of pre-arranging several to ten or more PC steel wires on a long lower mold of around 100'rrL.
It required manpower to evenly spread the hardened concrete on top of the lower mold.

今回の発明は上の問題点を解消して全工程の総合的機械
化を進めると同時に、これまで原貝IJとして定置設備
として開発してきた上記設備を、前述のように工事現場
に移設したシ、仮工場として設置、解体する事が容易な
ものにすることを特徴とする特にプレテンション設備を
移設可能にするのは画期的な事である。
This invention solves the above problems and promotes comprehensive mechanization of the entire process, and at the same time, the above-mentioned equipment, which has been developed as a stationary equipment for Haragai IJ, is relocated to the construction site as mentioned above. In particular, it is revolutionary to make pre-tension equipment relocatable, which is characterized by its ability to be easily installed and dismantled as a temporary factory.

コンクリート部材にプレストレスを与える方法にはボス
トテンション法とプレテンション法とある。前者はコン
クリート硬化後、その要所に設けた貫通孔にPC鋼線を
通し、グラウトを圧入し、鋼線を緊張させて端部を外面
に固定する。後者は頑丈なプレテンション・ベンチ上で
PC鋼線を緊張させ、その上にコンクリートを打設し、
鋼線全長を緊張状態でコンクリートに固着させる。
There are two methods for applying prestress to concrete members: the post tension method and the pretension method. In the former case, after the concrete has hardened, prestressed steel wires are passed through through holes provided at key points, grout is press-fitted, and the ends are fixed to the outside surface by tensioning the steel wires. The latter involves tensioning the PC steel wire on a sturdy pre-tension bench and pouring concrete on top of it.
The entire length of the steel wire is fixed to the concrete under tension.

工事現場とPCコンクリート部材製造工場とが離れてい
ると輸送費が巨額になるため、現場付近に仮工場を作る
。その際、用いられるのはスヘて設備の簡単なボストテ
ンション法であった。プレテンション法は通常6o〜1
20?7Lという長大で頑丈なベンチと関係設備を要し
、そのための敷地、建設費の面で簡単に仮工場を作るわ
けにはゆかない。このため、PCコンクリート材製造法
としてはプレテンション法の方が、PC鋼線とコンクリ
ートの完全固着、作業工程の簡易さ、薄肉製品にも適用
できる事等、ボストテンション法より勝っているにかX
わらず、プレテンション法は著しい発展を見ずに今日に
至っているのである。
If the construction site and the PC concrete parts manufacturing factory are far apart, transportation costs would be huge, so a temporary factory will be built near the site. At that time, a simple boss tension method using Schete equipment was used. Pretension method is usually 6o~1
It would require a long, sturdy bench measuring 20 to 7 liters and related equipment, and due to the land and construction costs, it would not be possible to simply build a temporary factory. Therefore, as a method for manufacturing PC concrete materials, the pre-tension method is superior to the post-tension method in terms of complete adhesion of the PC steel wire and concrete, simplicity of the work process, and applicability to thin-walled products. X
However, the pretension method has continued to this day without any significant development.

さて、この発明の構成、実施態様を図面を参照して説明
しよう。
Now, the configuration and embodiments of this invention will be explained with reference to the drawings.

第1〜5図はこの発明一実施例を示すもので、その主要
部をあげると、多数のコンクリート製単位下型/と前後
端の鋼線緊張台コを連結したプレテンションベンチ兼用
下ffjJ10.この下fi10両縁のレールに載り、
ウィンチけん引により摺動しつ\下型lO上のコンクリ
ートを摺動成形する上型//X PC鋼線13を送り、
側面開口部から下型10上へ自重脱出させる鋼線樋3α
、下型/θ上を走9つ\コンクリートを均等に投下する
振動機つきパケット7、養生用蒸気供給装置グ、そして
、下型10上及び下型に沿う製品置場r上を縦横に走シ
得るクレーン?α、?b等である。
Figures 1 to 5 show one embodiment of this invention, and its main parts include a pre-tension bench ffjJ10 which connects a number of concrete unit lower molds and steel wire tensioning tables at the front and rear ends. It rests on the rails on both edges of this lower fi10,
The upper mold slides and forms the concrete on the lower mold lO by winch traction//X The PC steel wire 13 is sent,
Steel wire gutter 3α that allows its own weight to escape from the side opening onto the lower mold 10
, a packet 7 with a vibrator that drops concrete evenly, a steam supply device for curing, and a machine that runs vertically and horizontally over the lower mold 10 and the product storage space r along the lower mold. Get a crane? α,? b etc.

クレーンPa、 Wbは設備移設時、各設備、部材、つ
−!シ単位下型/、鋼線緊張台コ、上型/1等をそのま
\又は分解して運んだ運搬用自動車から所要位置へ、又
はその逆に搬入、搬出し、また生産時は製品を下型10
上から製品置場r1またその置場とへ来た製品運搬車へ
移せるようにした。従ってまずクレーンPa、 Wbを
組立て\準備し、運搬用自動車で上記各部材を送込めば
、逐次、構築でき、構築用クレーンを用意する必要がな
い。クレーンタα、zbはその後、生産用として働くの
である。
When relocating equipment, cranes Pa and Wb are used to remove each piece of equipment, parts, etc. The unit lower mold/, steel wire tensioning stand, upper mold/1, etc. are transported as is or disassembled from the transportation vehicle to the required location, or vice versa, and the product is transported. Lower mold 10
It is now possible to transfer the product from above to the product storage area r1 and to the product transport vehicle that came to that storage area. Therefore, by first assembling/preparing the cranes Pa and Wb and transporting the above-mentioned parts using a transport vehicle, construction can be carried out one after another, and there is no need to prepare a construction crane. Crane operators α and zb then work for production purposes.

従来、移設することなど到底考えられなかったプレテン
ションベンチを、移動できるようにしたのは、これを分
割し組立式にしたからである。特にこの発明の下型10
はコンクIJ −1−製で、それ自体がプレテンション
ベンチを兼ねているので、分割運搬が著しく簡易化した
。第4図にその兼用下型10とその両端の鋼線緊張台−
とを示し、第5図にその下型ioの上に硬練コンクリー
トを敷き、摺動上型/lによシ波形Pcコンクリート版
Cを成形しつ\ある状態の断面を示す。
The pretension bench, which previously would have been unthinkable to relocate, was made movable because it was divided into parts and made into an assembly type. In particular, the lower mold 10 of this invention
is made of Conc IJ-1-, and since it itself doubles as a pre-tension bench, transporting it in parts has been significantly simplified. Figure 4 shows the dual-purpose lower die 10 and the steel wire tensioning tables at both ends of it.
Fig. 5 shows a cross section of the state in which hardened concrete is spread on the lower mold io and a corrugated concrete plate C is being formed on the sliding upper mold /l.

この下型io、上型//を上屋16内に二セット並設し
ている。
Two sets of the lower mold io and the upper mold // are installed side by side in the shed 16.

各単位下型lは三本の長い縦基台/コ上に載って一体に
結合され、両端の緊張台ツもろ共、図示しない鋼棒を通
して締付け、緊張台−によるPC鋼線13の締付は時、
下型/θが湾曲しないようにしている。
Each unit lower mold 1 is placed on three long vertical bases and is joined together, and both tensioning stands at both ends are tightened through steel rods (not shown), and the PC steel wire 13 is tightened by the tensioning stands. is time,
The lower mold/θ is prevented from curving.

単位下型lの両縁には第5図でよく分るようなレール/
弘を有し、下型10全長のレールとなって、上型l/を
摺動させる。また単位下型/は縦方向に蒸気孔≠αを貫
通しており、バッキングを介して次々と接続する事によ
り下型10全長の蒸気養生孔を形成し、蒸気供給装置(
ボイラ)≠に接続している。この実施例はドレン又は戻
り水をタンクに回収して熱効率向上を得ている。
There are rails on both edges of the unit lower mold l, as can be clearly seen in Figure 5.
The upper mold 10 serves as a rail for the entire length of the lower mold 10, on which the upper mold 1/1 slides. In addition, the unit lower mold / passes through the steam hole≠α in the vertical direction, and by connecting one after another through the backing, a steam curing hole of the entire length of the lower mold 10 is formed, and the steam supply device (
boiler) ≠. This embodiment collects drain or return water into a tank to obtain improved thermal efficiency.

摺動上型//も本発明者が開発したもので、下型10上
面との間に製品Cを形成する間隙を保ち、振動機/!に
よって上型材を振動させつ\、ウィンチ!を作動して前
進方向に張ったワイヤロ−プをけん引し移動する。ウイ
ンチタは上型l/に載せず、敷地に固定して上型//を
けん引するようにしてもよい。
The sliding upper mold // was also developed by the present inventor, and maintains a gap between the upper surface of the lower mold 10 to form the product C, and the vibrator /! The upper part is vibrated by the winch! The machine operates to tow and move the wire rope stretched in the forward direction. The winchiter may not be placed on the upper mold l/, but may be fixed on the site and the upper mold // may be towed.

第6図の上屋/乙の片側の柱/7に鋼線供給用C形樋3
αを付けている。これはPC鋼線を下型10の両端の鋼
線緊張台コ、コ間に渡すための設備で、第3図の上屋/
6の端部に第6図に示すようなPC鋼線供給装置3があ
る。
Figure 6: Shed/C-shaped gutter 3 for steel wire supply on pillar/7 on one side of shed
α is attached. This is equipment for passing the PC steel wire between the steel wire tensioning tables at both ends of the lower mold 10, and
At the end of 6, there is a PC steel wire feeding device 3 as shown in FIG.

巻いたPC鋼線を回転台/rに寝かせ、繰出装置/2に
より樋3αへ鋼線/3を送り、その先端が樋3α先端部
の定尺検出器に当ると繰出装置が停まり、切断装置20
が働いて鋼線/3を定尺切断する。
The wound PC steel wire is placed on the rotary table /r, and the steel wire /3 is sent to the gutter 3α by the feeding device /2. When the tip of the wire hits the fixed length detector at the tip of the gutter 3α, the feeding device stops and the wire is cut. device 20
works to cut the steel wire/3 to a fixed length.

そこでその一端を断面C形の樋3αの側面開口部から外
へ垂らすと、鋼線/3は以後、自重で次々と樋3αから
脱出し、各柱/7に付けた傾斜棒コ/上を滑って、下型
10上面の所要位置に落着く。
Then, when one end of the wire is hung outside from the side opening of the gutter 3α with a C-shaped cross section, the steel wires /3 escape from the gutter 3α one after another due to their own weight, and the inclined rods attached to each column /7 are suspended. It slides and settles on the required position on the upper surface of the lower mold 10.

各PC鋼線/3の両端を緊張装置コ、コでくわえ、油圧
ジヤツキココによシ緊張させたら、コンクリートを敷く
工程になる。コンクリート供給装置6はバッチャプラン
トでも、生コンクリートを一時受けておくホツノく−で
あってもよい。
After holding both ends of each PC steel wire/3 with the tensioning devices and tensioning them with the hydraulic jacks, it is time to lay the concrete. The concrete supply device 6 may be a batcher plant or a hot spring that temporarily receives fresh concrete.

第1.2図のように、その下へ入ったノくケラト7に硬
練コンクリートを満たす。/;ケラト7はその下蓋を閉
じ、別に設けたレール上を走って下型10のレール/弘
上に達し、それから下蓋を開き付属振動機7αを作動さ
せながら所要速度で下型10上を走υ、コンクリートを
均等に投下する。
As shown in Figure 1.2, fill the hole 7 below with hardened concrete. /; The Kerato 7 closes its lower lid, runs on a separately provided rail and reaches the rail/Hirokami of the lower mold 10, then opens the lower lid and moves the attached vibrator 7α over the lower mold 10 at the required speed. Run υ and drop the concrete evenly.

この例はパケット7が台車に載って走り、落したコンク
リートを平らにならす機能ももっている。
In this example, the packet 7 runs on a cart and also has the function of leveling dropped concrete.

ガおパケット7の移動は天井走行うレーンタαによって
も、下型/θ沿いに走る自動車によってもよい。
The transport packet 7 may be moved by a laner α that runs overhead, or by a car that runs along the lower mold/θ.

下型10の全長にわたってコンクリートを敷き終るか、
又はその前に摺動上型/、1の前進をはじめる。またボ
イラ弘から下型蒸気孔≠σへの蒸気送給を開始する。成
形後、養生するのでなく、下型10上にコンクリートを
敷いたら直ちに力0警すると硬化が早まる。
Have you finished laying concrete along the entire length of the lower mold 10?
Or, before that, start moving the sliding upper mold/, 1 forward. In addition, steam supply from the boiler Hiro to the lower mold steam hole≠σ will begin. After molding, instead of curing, concrete is laid on the lower mold 10 and the concrete is immediately applied with zero force to speed up the hardening.

摺動上型/lが下型10の一端から他端まで移動して下
型io上面に製品が成形されたら、その上にシートを掛
けて蒸気孔弘αからの熱を上へ迫力よさないようにし、
適温に達したら蒸気を停め、数時間放置すれば製品は取
出せるまで硬イヒしている。一般には夕方の作業終了時
力)ら翌朝の作業開始時までを養生期間に邑てればよい
When the sliding upper mold/l moves from one end of the lower mold 10 to the other and the product is molded on the upper surface of the lower mold 10, a sheet is placed over it to prevent the heat from the steam vent hole α from moving upwards. So,
When the temperature reaches the appropriate temperature, turn off the steam and leave it for a few hours, and the product will be hard enough to take out. Generally, it is sufficient to allow the curing period to last from the end of work in the evening until the start of work the next morning.

下型10は通常100脩前後の長さゆえ、製品を所要長
さに分割して取出せるよう、予め下型10上面に仕切材
を入れておく。製品を取上げるのは第1.2図の天井走
行うレーン5i′σ二台による。
Since the lower mold 10 is usually around 100 feet long, a partition material is placed in advance on the upper surface of the lower mold 10 so that the product can be divided into required lengths and taken out. The products will be picked up by two cars in the overhead running lane 5i'σ shown in Figure 1.2.

長い製品は二台を連結するか、無線で一体操作して吊上
げる。第6図に示すようにクレーンクαへの給電用トロ
リーダクトコ弘は柱に簡単に取付ける。吊上げた製品C
は、上屋の下戸1ら製品置場gへ積出すため四箇所に設
けた連絡台車23に載せ、両側いずれかの屋外クレーン
?bへ渡す。
Long products can be lifted by connecting two units or by operating them together wirelessly. As shown in Fig. 6, the trolley duct for feeding power to the crane α can be easily attached to the pillar. Lifted product C
are placed on connecting trolleys 23 installed at four locations from the lower door 1 of the shed to the product storage area g, and placed on either outdoor crane on either side. Give it to b.

屋外クレーンタbも二台協力して製品を置場rに整理し
て置き、搬出時、これを自動車に積込むのである。上型
//を出発点へ戻すのは天井走行うレーン7αによるほ
か、レールl弘上を逆進させてもよい。
Two outdoor cranes B also work together to organize and place the products in storage area R, and then load them into a car when they are to be taken out. The upper mold // can be returned to the starting point by the overhead running lane 7α, or by reversing the rail l hirojo.

以上は操業時の工程であるが、この設備を例えば山間の
工事現場に移設(本工場で部材を新製して新工場を作る
場合も含める)する工程を次に述べる。
The above is the process during operation, but the process of relocating this equipment to a construction site in the mountains, for example (including the case where a new factory is created by manufacturing new parts at the main factory) will be described next.

第5図は工事現場へ分解して送った上屋16、柱17、
クレーンPar ybを組立ておわり、その屋外クレー
ン9bの下に運搬用自動車ユ675ヨ着いて、単位下型
/を下ろし、これを順次、上屋/6の下の所要位置に二
列に並べている状況を示したものである。下型ioの基
台/2は簡単なものゆえ、運ぶより現場で所要位置に作
る方75(よい。
Figure 5 shows shed 16, pillar 17, which was disassembled and sent to the construction site.
After assembling the crane Par yb, the transport vehicle 675 arrives under the outdoor crane 9b, lowers the unit lower molds, and arranges them in two rows at the required positions under the shed 6. This is what is shown. Since the base/2 of the lower mold IO is simple, it is better to make it at the desired location on site rather than transporting it.

自動車ムが着くとクレーン?bにより一たん荷物を全部
、製品置場rへ下ろす。それ力・ら単位下型lを次々と
クレーンヂb1連絡台車、13、クレーンタαが受渡し
して基台ll上に並べ、組立作業と併行させる。下型1
0を組立てたら、その両端に鋼線緊張台ユを据え、アン
カーボルトに止め、これと下型10全長とをPC鋼線で
締付は固定する。
When the car arrived, there was a crane? By b, all the luggage is unloaded to product storage area r. Then, the unit lower molds 1 are delivered one after another by the crane b1, the connecting trolley, 13, and the crane machine α, and are arranged on the base 11 to perform the assembly work concurrently. Lower mold 1
After assembling 0, install steel wire tension stand units at both ends, fasten them to anchor bolts, and tighten and secure the entire length of the lower die 10 with PC steel wire.

摺動上型//も図では簡単に画いたが、下型上の硬練コ
ンクリートをまず平らにならし、概略成形し、完全成形
し、表面仕上げをする夫々の部材に分解して送り、現場
で組立て、下型/θのレールに載せる。
Sliding upper mold//Although it is simply depicted in the diagram, the hardened concrete on the lower mold is first leveled, roughly formed, completely formed, and disassembled into parts for surface finishing, and then sent. Assemble on site and place on the lower mold/θ rail.

併行的にPC鋼線供給装置3、その樋3αを設置し、ま
た蒸気供給装置≠、下型蒸気孔≠αへの配管を行い、コ
ンクリート供給装置6、パケット7も整備すると、はy
設備が完成する。
At the same time, install the PC steel wire supply device 3 and its gutter 3α, and also install piping to the steam supply device≠ and lower mold steam hole≠α, and also prepare the concrete supply device 6 and packet 7.
The equipment is completed.

上述の実施例は第6図のようなプレハブの上屋/6をも
つ設備で、雨天作業ができ、上屋の柱/7に天井クレー
ンレール訂、給電トロリーダクトJX PC鋼線供給樋
3αを取付けられる点で有利であシ、仮工場として屋根
覆いはシートでも構わないのであるが、さらに簡便な二
実施例を、第7.8図に示す。
The above embodiment is a facility with a prefabricated shed/6 as shown in Fig. 6, which allows work to be done in the rain, and is equipped with an overhead crane rail and a power supply trolley duct JX PC steel wire supply gutter 3α on the pillar/7 of the shed. This is advantageous in terms of installation, and a sheet can be used as the roof covering for a temporary factory, but two simpler embodiments are shown in Fig. 7.8.

第7図は上屋がなく設備が最も簡素な例である。もつと
もPC鋼線、蒸気、コンクリート夫々の供給装置は前例
と変シない。変った点は上屋の柱がないため天井走行う
レーンがなく、前例の屋外クレーン?bが下型10上の
クレーン7αを兼ねている点で、柱がないためPC鋼線
供給用樋3aや給電トロリーダクトは下型10側面に取
付ける。仮シの柱が支脚を設けて取付けてもよい。
Figure 7 shows an example where there is no shed and the equipment is the simplest. Of course, the supply equipment for PC steel wire, steam, and concrete are the same as before. What's different is that there are no pillars on the roof, so there is no lane for overhead running, and it's an outdoor crane like before. b also serves as a crane 7α above the lower mold 10, and since there is no pillar, the PC steel wire supply gutter 3a and the power supply trolley duct are attached to the side of the lower mold 10. A temporary pillar may be attached with supporting legs.

この例の利点はクレーン?bが下型10上から製品置場
♂まで縦横に働けるので、移設時、稼動時ともに運搬作
業が容易になる事である。クレーン?bを門型クレーン
でなく、トラッククレーンにすれば設備がさらに簡素化
する。
What is the advantage of this example? b can work vertically and horizontally from above the lower mold 10 to the product storage area ♂, which facilitates transportation work both during relocation and during operation. crane? If b is used as a truck crane instead of a gate type crane, the equipment will be further simplified.

この第7図の下型ioは下面が平らな製品C′に対する
もので、でき上った製品C′を置場とに積み、逐次、製
品運搬車−7へ積込む状況を示す。
The lower mold io in FIG. 7 is for a product C' having a flat bottom surface, and shows a situation in which the finished product C' is loaded on a storage area and sequentially loaded onto a product transport vehicle-7.

また図の右側にコンクリートパケット7を運搬車コ、r
K安定に積載し、これにより次々と近くの既設生コンク
リート工場からコンクリートを運び、直ちにクレーンタ
bによシパケット7を吊上げ、下型10上に落し敷く方
法をとった場合を画いている。
Also, on the right side of the figure is a truck transporting concrete packet 7.
This figure shows a method in which the concrete is loaded stably, the concrete is transported one after another from a nearby existing ready-mixed concrete factory, the concrete packet 7 is immediately lifted onto the crane machine b, and the concrete is dropped onto the lower mold 10.

第8図の実施例は上屋/6の柱17を中央の一列だけに
したもので、これによシ屋外クレーン2bが屋根の下ま
で働けるようになシ、また柱/7に給電トロリーダクト
2≠や鋼線樋38を取付けられるようになった。また、
この例ではパケット運搬車2とを下型io沿いに走らせ
て、運んで来た生コンクリートを横から落し敷いている
。またトラッククレーンコタを用いて移設時の大型部材
や、積重ねた製品の積出しに当て、クレーンタbは小型
で済むようにしている。
In the embodiment shown in FIG. 8, the pillars 17 of the shed/6 are arranged in only one row in the center, so that the outdoor crane 2b can work under the roof, and the power supply trolley duct is connected to the pillar/7. 2≠ and steel wire gutter 38 can now be installed. Also,
In this example, the packet transport vehicle 2 is run along the lower mold IO, and the fresh concrete that has been carried is poured from the side. In addition, the truck crane kota is used to unload large parts and stacked products during relocation, so that the crane b can be kept small.

下型10上に落したコンクリートは長手方向には均等て
も山積み状になるが、上型/lの前にスクレーバを加え
れば支障ない。
The concrete dropped onto the lower mold 10 will pile up evenly in the longitudinal direction, but if a scraper is added before the upper mold 10, there will be no problem.

以上、小数の実施例によって説明したが、この発明は組
立式のプレテンションベンチ兼用下型を用い、上型を摺
動させてコンクリートを成形する設備に、PC鋼線樋、
蒸気、コンクリートの供給装置、均等投下パケット、そ
してクレーンを加えた移設に適したPCコンクリート版
製造設備であって、上記構成要件は夫々、実施条件に応
じて設計者、現場技術者の周知技術により多様に変化、
応用が行われ得る。コンクリート材はコンクリート版、
梁等、種々の断面形状のものに適用できる。
As described above with reference to a small number of embodiments, the present invention uses a lower mold that also serves as an assembly type pretension bench, and is equipped with a PC steel wire gutter, an equipment for forming concrete by sliding an upper mold,
The PC concrete plate manufacturing equipment is suitable for relocation and includes steam, concrete supply equipment, uniform drop packets, and a crane. Diverse changes,
Applications can be made. Concrete material is concrete version,
It can be applied to objects with various cross-sectional shapes, such as beams.

この発明は従来、工事現場で作るPCコンクリート材は
ボストテンション法に限るとされた常識を覆えした。犬
がかりなプレテンションベンチを長短自在に移設できる
分割、組立式とし、しかも、そのベンチが成形用下型を
兼ねるので、解体、輸送、組立の手数が半減した。また
、下型上及びこれに沿う製品置場上を縦横に走るクレー
ンを設けるので、これを先に現場で組立てることにより
、操業用クレーンを設備移設、組立用にも使え、山間、
へき地の工事現場に構築用クレーンを運ぶ必要がなくな
った。
This invention overturns the conventional wisdom that PC concrete materials made at construction sites were limited to the boss tension method. The dog-like pretension bench is split and assembled so that it can be moved in length or length, and since the bench also serves as the lower mold for molding, the number of steps required for disassembling, transporting, and assembling has been halved. In addition, since a crane is installed that runs horizontally and vertically over the lower mold and over the product storage area along the lower mold, by assembling this on-site first, the operating crane can also be used for equipment relocation and assembly.
There is no longer a need to transport construction cranes to construction sites in remote areas.

しかも、その製造設備は長い連結下型上に摺動上型を移
動させる摺動成形法をとり、硬練コンクリートを用い、
コンクリート敷込みと同時に蒸気加熱を始められるので
、従来のPCコンクリート材成形速度を数倍に高めた。
Moreover, the manufacturing equipment uses a sliding molding method that moves a sliding upper mold onto a long connected lower mold, and uses hardened concrete.
Since steam heating can be started at the same time as concrete is laid, the molding speed of conventional PC concrete materials has been increased several times.

これは全工事の工期短縮に貢献する。This will contribute to shortening the overall construction period.

また作業面で手間どるPC鋼線設置作業とコンク’J 
−ト敷込み作業を、鋼線を所要長さ送給した後、側面開
口部から自重脱出させ下型上へ落す鋼線樋と、進行しつ
\振動によりコンクリートを均等に落すパケットの採用
によシはソ機械化し得た。
In addition, the PC steel wire installation work, which is a time-consuming work, and the CONC'J
- We have adopted a steel wire gutter that feeds the required length of steel wire and then lets it escape under its own weight through a side opening and drops it onto the lower mold, and a packet that drops the concrete evenly by vibration as it progresses. Yoshi could be mechanized.

さらに管理面では、従来のプレテンション製品に不可避
であった現場までの多額の輸送費がなくなる事、従来の
プレテンション設備のように、あらゆる注文に応じられ
る設備とせず、必要最小限で全力稼働、高能率となる規
模に作れ、要すれば何時でも設備を増大(ベンチ兼下型
の延長、増設)できる事、製造設備が工事現場に近いた
め、工事日程にPCコンクリート拐膜製造日程、製品品
質、規格を緊密に打合せられ、製品ストック量が少く、
また作業者を融通し合うことも可能な事、仮設工場から
本格工場へ移行するのも容易な事といった多くの利点を
生むものである。
Furthermore, in terms of management, the large amount of transportation costs to the site that were unavoidable with conventional pre-tensioning products is eliminated, and unlike conventional pre-tensioning equipment, the equipment does not have to be able to respond to every order, but instead operates at full capacity with the minimum necessary. , it can be manufactured on a scale that achieves high efficiency, the equipment can be expanded at any time if necessary (extension and expansion of the bench/lower mold), and the manufacturing equipment is close to the construction site, so the construction schedule can be adjusted to include the PC concrete membrane manufacturing schedule and the product. Quality and specifications are closely discussed, and product stock is small.
It also has many advantages, such as being able to exchange workers and making it easy to transition from a temporary factory to a full-scale factory.

この発明により、品質面でも生産性でもボストテンショ
ン法よシ優れたプレテンション法のPCコンクリート材
製造設備が、はじめて移設可能となり、その長所を工事
現場で発揮できるようになる効果は大きく、特にボスト
テンション法に適さない薄肉コンクリート版に現場でプ
レテンションを与えて供給できる効果は極めて大きい。
This invention has made it possible for the first time to relocate PC concrete manufacturing equipment using the pre-tension method, which is superior to the post-tension method in terms of quality and productivity. The effect of being able to pre-tension and supply thin concrete slabs that are not suitable for the tension method on-site is extremely large.

【図面の簡単な説明】[Brief explanation of drawings]

第1.2図はこの発明一実施例の平面及び立面図、第5
図は同じく拡大した側面図、第4図は下型兼プレテンシ
ョンベンチの実施例説明図、第5図は下型と、その上を
摺動してコンクリートを成形しつ\ある上型を示す部分
断面図、第6図はPC鋼線供給装置の説明図、第7.8
図は別の二実施例の側面図である。 3α・・・PC鋼線樋、≠・・・養生用蒸気供給装置、
7・・・コンクリートパケット、りα、りb・・・クレ
ーン、IO・・・プレテンションベンチ兼用下型、//
・・・摺動上型。
Figure 1.2 is a plan and elevation view of one embodiment of this invention, Figure 5
The figure is an enlarged side view, Figure 4 is an explanatory diagram of an embodiment of the lower mold/pretension bench, and Figure 5 shows the lower mold and the upper mold that is sliding over it to form concrete. Partial sectional view, Figure 6 is an explanatory diagram of the PC steel wire supply device, Figure 7.8
The figures are side views of two other embodiments. 3α...PC steel wire gutter, ≠...Curing steam supply device,
7... Concrete packet, Ri α, Ri b... Crane, IO... Lower mold that also serves as pretension bench, //
...Sliding type.

Claims (1)

【特許請求の範囲】 多数のコンクリート製単位下型と前後端の鋼線緊張台を
連結したプレテンションベンチ兼用下型と、この下型両
縁のレールに載って移動して下型上のコンクリートな摺
動成形する上型と、PC鋼線を下型上へ供給する鋼線樋
と、上記下型上を走りつ\コンクリートを均等に投下す
る振動機つきパケットと、養生用蒸気供給装置と、上記
下型上及び下型に沿う製品置場上を縦横に走り得るクレ
ーンとを備え、 上記各設備、部材はすべて、そのま\又は分解し、て上
記クレーンによシ搬入、搬出可能である事を特徴とする
摺動成形によるコンクリート材製造設備。
[Claims] A lower mold that also serves as a pretension bench, which connects a large number of unit lower molds made of concrete with steel wire tension stands at the front and rear ends, and a concrete lower mold on the lower molds that moves on rails on both edges of the lower mold. An upper mold for sliding forming, a steel wire gutter that supplies the PC steel wire onto the lower mold, a packet with a vibrator that runs over the lower mold and evenly drops concrete, and a curing steam supply device. , equipped with a crane that can run vertically and horizontally over the product storage area above and along the lower mold, and all of the above equipment and components can be carried in and out by the crane either as they are or disassembled. Concrete manufacturing equipment using sliding forming, which is characterized by:
JP736583A 1983-01-21 1983-01-21 Facility for manufacturing concrete material through slidingmolding Pending JPS59133008A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP736583A JPS59133008A (en) 1983-01-21 1983-01-21 Facility for manufacturing concrete material through slidingmolding

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP736583A JPS59133008A (en) 1983-01-21 1983-01-21 Facility for manufacturing concrete material through slidingmolding

Publications (1)

Publication Number Publication Date
JPS59133008A true JPS59133008A (en) 1984-07-31

Family

ID=11663938

Family Applications (1)

Application Number Title Priority Date Filing Date
JP736583A Pending JPS59133008A (en) 1983-01-21 1983-01-21 Facility for manufacturing concrete material through slidingmolding

Country Status (1)

Country Link
JP (1) JPS59133008A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102069201B1 (en) * 2019-09-05 2020-02-11 천숙희 concrete curing equipment with improved steam thermal efficiency for architecture and civil structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4847913A (en) * 1971-10-22 1973-07-07
JPS55108552A (en) * 1979-02-09 1980-08-20 Fuji Ps Concrete Precast concrete board for embeddinggtype molding flask* and method and device for making said board
JPS57181816A (en) * 1981-02-04 1982-11-09 Borcoman Mircea Method and device for manufacturing prestressed concrete
JPS57207011A (en) * 1981-06-16 1982-12-18 Fuji Ps Concrete Sliding molding device for pc concrete block

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4847913A (en) * 1971-10-22 1973-07-07
JPS55108552A (en) * 1979-02-09 1980-08-20 Fuji Ps Concrete Precast concrete board for embeddinggtype molding flask* and method and device for making said board
JPS57181816A (en) * 1981-02-04 1982-11-09 Borcoman Mircea Method and device for manufacturing prestressed concrete
JPS57207011A (en) * 1981-06-16 1982-12-18 Fuji Ps Concrete Sliding molding device for pc concrete block

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102069201B1 (en) * 2019-09-05 2020-02-11 천숙희 concrete curing equipment with improved steam thermal efficiency for architecture and civil structure

Similar Documents

Publication Publication Date Title
US4372906A (en) Method and apparatus for pre-casting steel reinforced concrete box-like modules
CN107119574B (en) A kind of Cantilever Construction Method of arch rib bridge girder
US4261150A (en) Prefabricated construction elements provided with a reinforcement operating as a caisson, equipment for producing such elements and method of fabrication and application in building erection
US4495131A (en) Method for pre-casting steel reinforced concrete box-like modules
US3153302A (en) Building construction
US4272050A (en) Method and apparatus for pre-casting steel reinforced concrete box-like modules
US4761126A (en) Traveling concrete casting mold
US3999913A (en) Concrete shaping and stressing means
US3879914A (en) Method of making a platform structure
US5383319A (en) Method of erecting a foundation structure for a building substructure
US3938922A (en) Means for forming a prestressed slab including collapsible bulkheads
US4131405A (en) Apparatus for producing structural panels
JPS59133008A (en) Facility for manufacturing concrete material through slidingmolding
US3194532A (en) Apparatus for pouring floors of a multi-story building
US3767153A (en) Platform structure
CN114193607B (en) Portable reinforcement mould of prefabricated box girder
CN212001599U (en) Large-span variable-space assembly type building
JP3603957B2 (en) On-site manufacturing method for PC members
EP0183805A1 (en) Building system and portable masonry plant suitable therefor
CN111021544A (en) Large-span variable-space assembly type building and construction method thereof
JPH10219708A (en) Precast concrete block for continuous footing and continuous footing method by use thereof
US3405903A (en) Form structure for roof slab and truss
JP2001182494A (en) Floor slab construction method in shield tunnel
RU199196U1 (en) MULTI-CAPACITY PRE-STRESSED CERAMZITE CONCRETE OVERLAPPING PLATE WITH INCREASED ANCHORING OF THE VALVES
JPS6353350B2 (en)