JPS5865819A - Anchor device - Google Patents

Anchor device

Info

Publication number
JPS5865819A
JPS5865819A JP16540181A JP16540181A JPS5865819A JP S5865819 A JPS5865819 A JP S5865819A JP 16540181 A JP16540181 A JP 16540181A JP 16540181 A JP16540181 A JP 16540181A JP S5865819 A JPS5865819 A JP S5865819A
Authority
JP
Japan
Prior art keywords
steel wire
fixing body
load
plate
anchor device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP16540181A
Other languages
Japanese (ja)
Other versions
JPS6053136B2 (en
Inventor
Kunimitsu Yamada
邦光 山田
Tetsuo Toyokawa
豊川 哲郎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kensetsu Kiso Engineering Co Ltd
Original Assignee
Kensetsu Kiso Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kensetsu Kiso Engineering Co Ltd filed Critical Kensetsu Kiso Engineering Co Ltd
Priority to JP16540181A priority Critical patent/JPS6053136B2/en
Publication of JPS5865819A publication Critical patent/JPS5865819A/en
Publication of JPS6053136B2 publication Critical patent/JPS6053136B2/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • E02D5/808Ground anchors anchored by using exclusively a bonding material

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

PURPOSE:To make easier the drawing of a steel wire after being used in a removal type anchor device by a method in which a groove provided in a load- resistant plate in a fixing body is isolated by a partition wall and a PC steel wire hooked to the fixing body is regulated by a pressing plate. CONSTITUTION:An anchor device has a fixing body 1 hooking an unbond PC steel wire 2, and on a load-resistant plate 3 formed at the basal portion of the fixing body 1, two rows of curved grooves 7 are provided with a partition wall 8. Also, a pressing plate 10 is provided in the face of the grooves 7 in a manner that it can freely move back and forth owing to the coupling of a threaded pipe integrally connected to the pressing plate with the partition plate 5 of the fixing body 1. When being used, the PC steel wire 2 is hooked on the load-resistant plate 3 and then inserted into an excavated pit A, cement mortar is placed, and the PC steel wire 2 is tensioned and fixed by a grip 12, etc. When removing the anchor device, the grip 12 is removed and one end of the steel wire 2 is pulled out with the aid of a jack, etc.

Description

【発明の詳細な説明】 この発明は除去式のアンカー装置に関するものである。[Detailed description of the invention] This invention relates to a removable anchor device.

擁壁、山留壁等を支持するアースアンカー装置に射いて
工事終了後撤去する除去式アンカー装置が種々開発提案
されている。その一つにアンボンドの緊張鋼材を、地盤
の削孔底に挿入した定着体の耐荷板に引掛けてU状に配
置しておき、削孔内を充填して緊張鋼材の両端を擁壁園
等に固定して使用し、撤去に際しては前記固定を外し、
緊張鋼材の一端を引張ることにより撤去する工法が知ら
れてい志。そして以上の工法でU状に配置するためシー
ス等を使用する場合は問題ないがpc鋼より線とポリエ
チレンパイプの間にグリスを入れたアンボンドPC鋼線
を複数本並列して使用する場合、アンボンドPC鋼線が
接触すると摩擦抵抗によって引抜きが困難となり、また
アンボンドpc @@が弾発力によって拡がる傾向にあ
ってアンボンドpc @@と耐荷板との間に隙間を生じ
、コンクリートを充填して定着体を定着する際その隙間
にコンクリートが入り、アンボンドPC鋼線の引抜きを
困難とする要因になることがある。
Various types of removable anchor devices have been developed and proposed, which are attached to earth anchor devices that support retaining walls, mountain retaining walls, etc. and are removed after construction is completed. One method is to place unbonded tension steel materials in a U-shape by hooking them onto the load-bearing plates of an anchor inserted into the bottom of a hole in the ground. etc., and when removing it, remove the said fixing,
There is a known method of removing tension steel by pulling one end of it. There is no problem when using a sheath etc. to arrange in a U shape with the above construction method, but when using multiple unbonded PC steel wires in parallel with grease between the PC steel stranded wire and the polyethylene pipe, unbonded When the PC steel wires come into contact, it becomes difficult to pull them out due to frictional resistance, and the unbonded PC @@ tends to spread due to the elastic force, creating a gap between the unbonded PC @@ and the load-bearing plate, which is filled with concrete and fixed. When the body is fixed, concrete may enter the gap, making it difficult to pull out the unbonded PC steel wire.

この発明は前記従来の間廟点を解決すべく開発したもの
で、以下その詳細を図示した実施例によって説明する。
The present invention was developed to solve the above-mentioned shortcomings of the prior art, and will be described in detail below with reference to illustrated embodiments.

図に詔いて、1は定着体、2はアンボンドPC$11を
示す。
In the figure, 1 indicates the fixing body and 2 indicates the unbonded PC $11.

定着体1は鋳鋼異形鉄筋、グラスファイバーコンクリー
ト等により形成され、基部の耐荷板Sと先端部4との中
間部は中空状とされ、中間に仕切板5,5が設けてあり
、また中間部表面には定着に際しての抵抗となる突起6
が形成して′ある。
The anchoring body 1 is formed of cast steel deformed reinforcing bars, glass fiber concrete, etc., and the intermediate portion between the load-bearing plate S at the base and the tip portion 4 is hollow, and partition plates 5, 5 are provided in the intermediate portion. There are protrusions 6 on the surface that act as resistance during fixing.
is formed.

耐荷板3には並列した湾曲状をなす凹溝7,7が形成さ
れ、少なくともその先端間には仕切壁8が突設状に形成
しである。
Parallel curved grooves 7, 7 are formed in the load-bearing plate 3, and a partition wall 8 is formed in a protruding manner at least between the ends thereof.

基部側の仕切板5の中央には螺子孔9が形成され、基部
に押圧板10を設けた螺杆11が螺子孔9に螺合されて
いる。したがって押圧板10は凹fpI7,7に対向し
て進退自在に設置されること1こなる。
A screw hole 9 is formed in the center of the partition plate 5 on the base side, and a screw rod 11 having a pressure plate 10 at the base is screwed into the screw hole 9. Therefore, the press plate 10 is installed facing the recesses fpI7, 7 so as to be able to move forward and backward.

以上の凹$7.7にアンボンドルc鋼線2を引掛け、抑
圧板10で押えることにより、アンボンドルc鋼線2の
動きを規制する。
The movement of the unbonded C steel wire 2 is restricted by hooking the unbonded C steel wire 2 into the above recess $7.7 and pressing it with the suppression plate 10.

使用に際しては掘削孔A門番3定着体1.アンボンドP
C@82を挿入し、次いで掘削孔A内にモルタルを加圧
注入し、定着体1を掘削凡人の底部に定着し、アンボン
ドルc鋼線2の両端は擁壁B等に挿通し、均等に緊張し
てグリップ12等により固定する。
When using, drill hole A gatekeeper 3 anchor 1. Unbonded P
Insert C@82, then inject mortar under pressure into the excavation hole A, fix the fixing body 1 at the bottom of the excavator, and insert both ends of the unbonded C steel wire 2 into the retaining wall B etc., evenly. Tension and fix with grip 12 or the like.

撤去に際してはグリップ12を外し、アンボンドルc鋼
線2の何れか一湖の備をジヤツキに取付けて引抜く。
When removing it, remove the grip 12, attach one of the unbonded steel wires 2 to the jack, and pull it out.

この発明は以上の構成からなり、定着体には仕切壁によ
って区画された湾曲状の凹溝があり、複数のアンボンド
PC鋼線を相互薔こ分離状態に配置しであるので引抜き
時に相互に影響することがない。またアンボンドルc鋼
線を規制する抑圧板を設けたので凹溝内の所定位置に確
実にセットすることができ、引き抜きを容易ならしめる
ことができる。
This invention has the above-mentioned structure, and the fixing body has a curved groove partitioned by a partition wall, and a plurality of unbonded PC steel wires are arranged so as to be separated from each other, so that they influence each other during drawing. There's nothing to do. Furthermore, since a suppression plate is provided to restrict the unbonded C steel wire, it can be reliably set in a predetermined position within the groove, and it can be easily pulled out.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は地盤へ堀設状態の断面図、第2図は定着体の正
面図、第5図、第4図は定着体の断面図である。 1・・定着体、2−・アンボンドPC鋼線、5・・耐荷
板、4・・先端部、5・・仕切板、6・・突起、7・・
凹溝、8・・仕切壁、9・・螺子孔、10・・押圧板、
11・・螺杆、12・・グリップ、人・・掘Il!lI
孔、B・・擁壁。 特許出願人 建設基礎エンジユ アリング株式会社
FIG. 1 is a cross-sectional view of the fixing body in a state where it is dug into the ground, FIG. 2 is a front view of the fixing body, and FIGS. 5 and 4 are cross-sectional views of the fixing body. 1. Fixing body, 2. Unbonded PC steel wire, 5. Load-bearing plate, 4. Tip, 5. Partition plate, 6. Protrusion, 7.
Concave groove, 8...partition wall, 9...screw hole, 10...pressing plate,
11...Screw rod, 12...Grip, person...Dig Il! lI
Hole, B...retaining wall. Patent applicant Kensetsu Foundation Engineering Co., Ltd.

Claims (1)

【特許請求の範囲】[Claims] 定着体lこ形成した耐荷板に、並列した湾曲状をなす凹
溝を形成し、かつその凹溝間に仕切壁を形成し、その凹
溝にアンボンドPC鋼線を引掛け、かつアンボンドPC
鋼線を規制する抑圧板を凹溝に対向して進退自在に設置
しであることを%徴とするアンカー装置。
On the load-bearing plate formed with the fixing body, parallel curved grooves are formed, a partition wall is formed between the grooves, an unbonded PC steel wire is hung in the groove, and the unbonded PC
This anchor device is characterized by a suppression plate that restricts the steel wire and is installed facing a groove so that it can move forward and backward.
JP16540181A 1981-10-16 1981-10-16 Anchor device Expired JPS6053136B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16540181A JPS6053136B2 (en) 1981-10-16 1981-10-16 Anchor device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16540181A JPS6053136B2 (en) 1981-10-16 1981-10-16 Anchor device

Publications (2)

Publication Number Publication Date
JPS5865819A true JPS5865819A (en) 1983-04-19
JPS6053136B2 JPS6053136B2 (en) 1985-11-22

Family

ID=15811701

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16540181A Expired JPS6053136B2 (en) 1981-10-16 1981-10-16 Anchor device

Country Status (1)

Country Link
JP (1) JPS6053136B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5730556A (en) * 1992-07-01 1998-03-24 Keller Limited Removable ground anchor
KR100818504B1 (en) 2006-12-27 2008-03-31 (주) 공인건설 Tension soil nail and construction method of precast concrete panel using the same
US20140345220A1 (en) * 2013-05-24 2014-11-27 Francesco Ferraiolo Anchoring system for concrete panels in a stabilized earth structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5730556A (en) * 1992-07-01 1998-03-24 Keller Limited Removable ground anchor
KR100818504B1 (en) 2006-12-27 2008-03-31 (주) 공인건설 Tension soil nail and construction method of precast concrete panel using the same
US20140345220A1 (en) * 2013-05-24 2014-11-27 Francesco Ferraiolo Anchoring system for concrete panels in a stabilized earth structure
US9523178B2 (en) 2013-05-24 2016-12-20 Officine Maccaferri S.P.A. Anchoring system for concrete panels in a stabilized earth structure

Also Published As

Publication number Publication date
JPS6053136B2 (en) 1985-11-22

Similar Documents

Publication Publication Date Title
CN108331594B (en) Supporting structure for weak surrounding rock tunnel
US6918567B2 (en) Concrete panel with gripping ribs and method of use
JPS5865819A (en) Anchor device
EP0577421A1 (en) Removable ground anchor
JPS5880022A (en) Anchor device
KR101806190B1 (en) Anchor
JPS622083B2 (en)
JPH0242970B2 (en)
JPH0412772B2 (en)
JP3466768B2 (en) Bridge structure and construction method
KR101165579B1 (en) Single type hybrid inner member and removal anchor structure for load dispersion using the same
JPH0194109A (en) Wall pile and its setting work
JPH10231522A (en) Slope stabilizing construction method
JPH0115725Y2 (en)
JP3347703B2 (en) Retaining wall method
JPH0472009B2 (en)
JP2532575Y2 (en) Construction jig for stress material
JPH0454005B2 (en)
KR0150296B1 (en) Supporter of fabricated retaining wall
JP2694079B2 (en) Construction method of earth anchor
JPH025206B2 (en)
CN116516933A (en) Anchoring device for underground diaphragm wall construction
JP2865152B2 (en) Anchor construction method and hanger used in this method
JP2629142B2 (en) Retaining wall construction method
JP2718591B2 (en) Removal anchor method