JPS58151909A - Method for conveying slab - Google Patents

Method for conveying slab

Info

Publication number
JPS58151909A
JPS58151909A JP57033286A JP3328682A JPS58151909A JP S58151909 A JPS58151909 A JP S58151909A JP 57033286 A JP57033286 A JP 57033286A JP 3328682 A JP3328682 A JP 3328682A JP S58151909 A JPS58151909 A JP S58151909A
Authority
JP
Japan
Prior art keywords
slab
blooming
plant
continuous casting
lifter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP57033286A
Other languages
Japanese (ja)
Other versions
JPS638849B2 (en
Inventor
Toshihiko Takeda
俊彦 武田
Mochitsugu Miura
三浦 望嗣
Kakuji Yoshihara
吉原 佳久次
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Sumitomo Metal Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Metal Industries Ltd filed Critical Sumitomo Metal Industries Ltd
Priority to JP57033286A priority Critical patent/JPS58151909A/en
Publication of JPS58151909A publication Critical patent/JPS58151909A/en
Publication of JPS638849B2 publication Critical patent/JPS638849B2/ja
Granted legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B39/00Arrangements for moving, supporting, or positioning work, or controlling its movement, combined with or arranged in, or specially adapted for use in connection with, metal-rolling mills

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Continuous Casting (AREA)
  • Control Of Metal Rolling (AREA)

Abstract

PURPOSE:To make the best possible use of the heat retained in slabs which do not require blooming in a blooming line used alternately and commonly for continuous casting slabs and ingot materials by retreating the succeeding ingot when the slab arrives at the inlet side of a blooming mill. CONSTITUTION:In a producing line for steel plates wherein a continuous casting plant A, a blooming plant B and a hot rolling plant C are coupled directly, the continuous casting slab (a) from the plant A and the ingot material (b) from a holding furnace 1 are both bloomed with the blooming mill 2. The slab (a) is fed through a hot scarfer 3 and a hot shear 4 to the plant C, and the bloomed slab of the material (b) is fed temporarily to a cooling hearth 7. A slab lifter 8 is provided between the mill 2 and the scarfer 3. When the slab (a) which does not require blooming is fed into the line during the blooming work of the material (b) under working, the material (b) under the work is retreated to above the line by the lifter 8, and the slab (a) is passed preferentially so as to be fed to the plant C. The lifter 8 is brought down thereafter to return the material (b) again in the blooming stage and the work is completed.

Description

【発明の詳細な説明】 本発明は連続鋳造スラブとインゴツト材とに対して交互
共用される分塊圧延ラインにおけるスラブ搬送方法に関
する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for conveying slabs in a blooming line which is used alternately for continuous casting slabs and ingot materials.

第1図に示すように、連続鋳造工場Aと、分塊工場Bと
、熱間圧延工場Cとが直結したレイアウトの鋼板製造ラ
インにおいては、設備コストの関係で連続鋳造スラブ(
以下、CCスラブという。)の処理とインゴツト材の処
理とに共用される部分があり、分塊工程においてはCC
スラブαとインゴツト材すを交互に処理するようにして
いる。すなわち、連続鋳造工場Aから送り出されるCC
スラブαも、均熱炉1から送り出されるインゴツト材す
も、共に分塊圧延機2で分塊圧延し、ホットスカーファ
3で表面疵を除去し、さらにホットシャ4で不良部を切
断したのち、CCスラブaは加熱炉5を経て粗圧延機乙
に送られ、また、インゴツト材すの分塊スラブは一時的
に冷却床7に送り込まれて冷却される。
As shown in Figure 1, in a steel plate production line with a layout in which continuous casting factory A, blooming factory B, and hot rolling factory C are directly connected, continuous casting slabs (
Hereinafter, it is called CC slab. ) processing and ingot material processing, and in the blooming process, CC
Slab α and ingot material are processed alternately. In other words, CC sent from continuous casting factory A
Both the slab α and the ingot material sent out from the soaking furnace 1 are bloomed in a blooming mill 2, surface defects are removed in a hot scarfer 3, and defective parts are cut in a hot scarf 4. The CC slab a is sent to the rough rolling mill B through the heating furnace 5, and the blooming slab of the ingot material is temporarily sent to the cooling bed 7 to be cooled.

このような分塊工程では、CCスラブaとインゴツト材
すとが交互に処理されるものであるが、CCスラブの中
には分塊圧延を必要とするものと、これを必要とせずに
直接、熱間圧延工程へ送り込んでよいものがある。しか
るに、分塊工程では前述のようにインゴツト材との交互
処理形式を用いているため、分塊処理を必要としないC
Cスラブの場合でも、前記分塊工程が使用中の場合は分
塊工程を通過させることができないので、分塊工程の入
側で待績させなければならない。このため、CCスラブ
の通板時間が長くなってしまい、自己の保有熱を最大限
有効に活用することが要求されるCCスラブであるにも
かかわらず、前述のロスタイムによって減少してしまい
、熱延加熱炉5での再加熱で大幅に昇温させる必要が生
じていた。
In such a blooming process, CC slab a and ingot material are processed alternately, but some CC slabs require blooming and others are processed directly without the need for this. , some materials may be sent to the hot rolling process. However, since the blooming process uses alternating processing with ingot material as mentioned above, C
Even in the case of C slabs, if the above-mentioned slabbing process is in use, the slab cannot be allowed to pass through the blooming process, so it must be allowed to wait on the entrance side of the blooming process. For this reason, the running time of the CC slab becomes long, and even though the CC slab is required to make the most effective use of its own heat, the heat is reduced due to the aforementioned loss time. It was necessary to significantly raise the temperature by reheating in the spreading heating furnace 5.

したがって、本発明の目的は、分塊圧延工程を必要とし
ないCCスラブを優先的に通板させることのできるスラ
ブ搬送方法を得て、従来のこの種通板ラインにおける欠
点を排除することにある。
Therefore, an object of the present invention is to obtain a slab conveying method that can preferentially pass CC slabs that do not require a blooming process, and to eliminate the drawbacks of conventional plate passing lines of this type. .

本発明においては、先行したインゴツト材が分塊圧延作
業中であるとき、後続するCCスラブに待ち時間が要求
され、しかもその待ち時間が最も長く要求される場所罠
スラブリフタを設け、CCスラブが到着した時点で、先
行のインピット材をスラブリフタで通板ラインから退避
させることを特徴とする。
In the present invention, when the preceding ingot material is in the process of blooming and rolling, a waiting time is required for the following CC slab, and a trapping slab lifter is provided at the location where the waiting time is the longest, and the CC slab is placed at the location where the CC slab arrives. At this point, the preceding impeding material is evacuated from the threading line using a slab lifter.

本発明においては分塊圧延機2とホットスカーファ3と
の間にスラブリフタ8を設置する。このスラブリフタ8
は、例えば第2図に示すように、複数の流体用シリンダ
81を組として使用し、互いに枠組みされて一体となっ
た吊ビーム82によって退避スラブを引き上げて通板ラ
インの上方へリフト保持するものである。非使用時は下
降位置にあり、吊ビーム82はテーブルローラの間に配
置され、スラブの通過に支障を及ぼさない。
In the present invention, a slab lifter 8 is installed between the blooming mill 2 and the hot scarfer 3. This slab lifter 8
For example, as shown in FIG. 2, a plurality of fluid cylinders 81 are used as a set, and the retracted slab is lifted and held above the threading line by a hanging beam 82 that is framed together and integrated. It is. When not in use, it is in the lowered position, and the hanging beam 82 is placed between the table rollers and does not interfere with the passage of the slab.

本発明法においては、通板材料の運搬に何らの障害も生
じない場合は、スラブリフタの使用を必要としないが、
先行するインゴツト材の分塊圧延作業中に、分塊な必要
としないCCスラブが送り込まれてきた場合は、作業中
のインゴツト材すをスラブリフタ8によってライン上方
へ退避させ、これによって空いた分塊工程へCCスラブ
を速やかに通板させて熱延工場へ送り込む。CCスラブ
の通板が完了した時点で、スラブリフタ8を下降させて
、処理途中のインゴツト材すを再び分塊工程へ戻し、作
業を完了させる。
In the method of the present invention, it is not necessary to use a slab lifter if there is no problem in transporting the threaded material.
If an unnecessary CC slab is sent in during the preceding slabbing operation of ingot material, the ingot material being worked on is evacuated to the upper part of the line by the slab lifter 8, and the empty blooming slab is removed. The CC slab is quickly passed through the process and sent to the hot rolling factory. When the threading of the CC slab is completed, the slab lifter 8 is lowered to return the ingot material being processed to the blooming process again to complete the work.

本発明法の実施姉より、通板後のCCスラブの加熱時間
は大幅な減少をみた。すなわち、待ち時間を必要として
いた従来法においては、分塊圧延工程通板後の加熱時間
が5〜6時間を要していたが、本発明法の実施によって
加熱時間は1〜1.5時間にまで短縮された。このため
圧延までの所要時間と消費燃料が大幅に節減され、作業
能率と燃料原単位が著しく向上した。また、通板ライン
上での待ちスは−スを確保する必要性もなくなり、設備
スペースも削減できる効果を得た。
Compared to the implementation of the method of the present invention, the heating time of the CC slab after threading was significantly reduced. In other words, in the conventional method that required waiting time, the heating time after passing through the blooming rolling process required 5 to 6 hours, but by implementing the method of the present invention, the heating time was reduced to 1 to 1.5 hours. It was shortened to . As a result, the time required for rolling and the amount of fuel consumed were significantly reduced, resulting in significant improvements in work efficiency and fuel consumption. Additionally, there is no longer a need to secure a waiting space on the sheet threading line, resulting in a reduction in equipment space.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は連続鋳造、分塊、熱延を直結した圧延ラインの
概略的な平面図。第2図は本発明法に係るスラブリフタ
の略示的な斜視図。 1:均熱炉      2:分塊圧延機6:ホットスカ
ーファ 4:ホットシャ8:スラプリフタ
Figure 1 is a schematic plan view of a rolling line that directly connects continuous casting, blooming, and hot rolling. FIG. 2 is a schematic perspective view of a slab lifter according to the method of the present invention. 1: Soaking furnace 2: Blooming mill 6: Hot scarf 4: Hot shaver 8: Slurp lifter

Claims (1)

【特許請求の範囲】[Claims] 連続鋳造工程、分塊工程、熱間圧延工程が直結されてい
て前記分塊工程が連続鋳造スラブとインゴツト材とに交
互共用されるラインのスラブ搬送方法において、分塊圧
延機とホットスカーファとの間にスラブリフタを設置し
ておき、連続鋳造スラブが分塊圧延機の入側に到着した
時点で、圧延中もしくは圧延完了後のインゴツト材を前
記スラブリフタでライン上方へ退避させ、連続鋳造スラ
ブを先に通板させるようにしたことを特徴とするスラブ
搬送方法。
In a slab conveying method for a line in which a continuous casting process, a blooming process, and a hot rolling process are directly connected, and the blooming process is alternately used for continuous casting slabs and ingot material, A slab lifter is installed in between, and when the continuous casting slab arrives at the input side of the blooming mill, the ingot material being rolled or after rolling is evacuated upward from the line by the slab lifter, and the continuous casting slab is removed. A slab conveying method characterized by passing the slab first.
JP57033286A 1982-03-03 1982-03-03 Method for conveying slab Granted JPS58151909A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP57033286A JPS58151909A (en) 1982-03-03 1982-03-03 Method for conveying slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP57033286A JPS58151909A (en) 1982-03-03 1982-03-03 Method for conveying slab

Publications (2)

Publication Number Publication Date
JPS58151909A true JPS58151909A (en) 1983-09-09
JPS638849B2 JPS638849B2 (en) 1988-02-24

Family

ID=12382284

Family Applications (1)

Application Number Title Priority Date Filing Date
JP57033286A Granted JPS58151909A (en) 1982-03-03 1982-03-03 Method for conveying slab

Country Status (1)

Country Link
JP (1) JPS58151909A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007098469A (en) * 2005-09-12 2007-04-19 Jfe Steel Kk Device for retaining steel material to be rolled, and hot rolling facility equipped with the same
JP2007098468A (en) * 2005-09-12 2007-04-19 Jfe Steel Kk Hot-rolling equipment and hot-rolling method using the same
JP2007144466A (en) * 2005-11-29 2007-06-14 Jfe Steel Kk Apparatus for holding rolled material
JP2008207220A (en) * 2007-02-27 2008-09-11 Jfe Steel Kk Device for retaining rolling stock, and hot rolling facility equipped with the same

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0473336U (en) * 1990-11-01 1992-06-26
CN110029290B (en) * 2019-02-01 2021-03-12 上海加宁新材料科技有限公司 Manufacturing method of ultralow-temperature high-strength non-magnetic stainless steel impeller shaft

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007098469A (en) * 2005-09-12 2007-04-19 Jfe Steel Kk Device for retaining steel material to be rolled, and hot rolling facility equipped with the same
JP2007098468A (en) * 2005-09-12 2007-04-19 Jfe Steel Kk Hot-rolling equipment and hot-rolling method using the same
JP2007144466A (en) * 2005-11-29 2007-06-14 Jfe Steel Kk Apparatus for holding rolled material
JP4561614B2 (en) * 2005-11-29 2010-10-13 Jfeスチール株式会社 Rolled material holding device
JP2008207220A (en) * 2007-02-27 2008-09-11 Jfe Steel Kk Device for retaining rolling stock, and hot rolling facility equipped with the same

Also Published As

Publication number Publication date
JPS638849B2 (en) 1988-02-24

Similar Documents

Publication Publication Date Title
CN112792126B (en) Hot rolling method of bearing steel with large compression ratio
US5094094A (en) Hot-rolling equipment and a method of hot-rolling a slab
JPS58151909A (en) Method for conveying slab
JPS5820301A (en) Hot rolling method and heat treatment furnace for steel material
EP0257540B1 (en) Processing steel slabs
JPS6018201A (en) Line of direct rolling equipment
JP6439938B2 (en) Heating method after cutting continuous cast slab
JP4853000B2 (en) Hot rolling method and hot rolling equipment used therefor
JPS586703A (en) Rolling mill equipment
JP2730845B2 (en) Sizing press device and die changing method thereof
JPH0381012A (en) Heat compensation device in direct rolling process
JP3503581B2 (en) A method for charging a continuously cast hot slab to a heating furnace for hot rolling.
JP3455034B2 (en) Continuous casting method for high carbon special steel
JPS60180604A (en) Rolling method of thick steel plate
JPH089050B2 (en) Metal slab conditioning equipment row
SU1696015A1 (en) Method of producing thick-gauge plate
JPH07238322A (en) Method for preventing surface cracking in steel slab
JPH0372131B2 (en)
JP2785435B2 (en) Method and apparatus for manufacturing non-ferrous metal plate
JPH11207429A (en) Cogging method for steel
JPH07148502A (en) Method for slabbing slab of different width
JPS635837A (en) Cooling method for width rolling reduction pressing die of hot slab
JPH07204708A (en) Production of hot coil
JPH0587338B2 (en)
JPS5519465A (en) Method of supplying bloom from continuous casting process to rolling process