JPS58113410A - Horizontal setting work of gravity structure - Google Patents
Horizontal setting work of gravity structureInfo
- Publication number
- JPS58113410A JPS58113410A JP20965781A JP20965781A JPS58113410A JP S58113410 A JPS58113410 A JP S58113410A JP 20965781 A JP20965781 A JP 20965781A JP 20965781 A JP20965781 A JP 20965781A JP S58113410 A JPS58113410 A JP S58113410A
- Authority
- JP
- Japan
- Prior art keywords
- bag
- filler
- caisson
- gravity
- crushed stones
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/16—Jointing caissons to the foundation soil, specially to uneven foundation soil
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
Abstract
Description
【発明の詳細な説明】
本発明は、コンクリートケーソンやブロックのような重
力式構造物の水平設置工法に関するものである○海底油
田、港湾工事等の基礎工事にケーソンやブロックは欠か
せないものであるが、これをh紙上に水平に設置する工
法は今なお確立されていない。促米は、第1図に示すよ
うに、海底1を休り下けて砕石2を敷きつめ、この上に
コンクリートケーソン3を載置した後、油田基地等を建
設していた。砕石2はダイバーによってある程度ならさ
れるが、それ程の水平面、平坦面は期待できない。従っ
てm2図に示すようにケーソンが傾いたまま載置される
虞れがあり、これを匡正することは至難の技である。ま
た砕石面が平坦でなければ、ケーソンの荷重は接してい
る砕石のみに集中することになり、極めて不安定となる
。これをケーソン側からみれば、砕石と接触している部
分が極端に破損し易くなるわけである。この柚のコンク
リートケーソンはバラスト水用等の空′@部分4a 、
4bが設けられており、底面もそれ程の肉厚はない。[Detailed Description of the Invention] The present invention relates to a horizontal installation method for gravity-type structures such as concrete caissons and blocks. Caissons and blocks are indispensable for foundation work such as undersea oil fields and port construction. However, the method of installing it horizontally on h paper has not yet been established. As shown in Figure 1, Yakumei laid down the seabed 1, laid down crushed stone 2, placed concrete caisson 3 on top of this, and then built an oil field base. Although the crushed stone 2 is leveled to some extent by the diver, it cannot be expected that the surface will be that horizontal or flat. Therefore, there is a risk that the caisson will be placed tilted as shown in Figure m2, and it is extremely difficult to correct this. Furthermore, if the crushed stone surface is not flat, the load of the caisson will be concentrated only on the crushed stones that are in contact with it, making it extremely unstable. Looking at this from the caisson side, the parts that are in contact with crushed stone are extremely susceptible to damage. This Yuzu concrete caisson has an empty part 4a for ballast water, etc.
4b, and the bottom surface is not that thick.
従って破搗の虞れは一層大さいと云わねばならない。Therefore, it must be said that the risk of failure is even greater.
そこで本発明の弟1目的は、砕石面を匡正してケーソン
を水平に設置することにある。弟2の目的はケーソンの
全底面を砕石上に当接させて、ケーソンの向重分布を均
等にすることにある。この目的を達成するため、本発明
では砕石上に袋を展設し、これに充填剤を注入して固化
させてからり−ソンを載置させている。以下添付図面に
従って本発明の実施例を詳述する。Therefore, the first object of the present invention is to straighten the crushed stone surface and install the caisson horizontally. The purpose of younger brother 2 is to bring the entire bottom of the caisson into contact with the crushed stone and to equalize the distribution of the load on the caisson. In order to achieve this purpose, in the present invention, a bag is spread over crushed stone, a filler is injected into the bag, and the bag is solidified, and then the Karason is placed thereon. Embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
第3図は充填剤用の袋6を斜視図で示したものである。FIG. 3 shows a perspective view of the bag 6 for filler.
袋6には充填剤の注入管7a、7bが内挿され、各々の
注入管7a、7bには充填剤の流出孔8が徐数設けられ
ている。注入管7a、7bの一端は袋外に突出しており
、これに充填剤送入用のホース(第4図参照)が接続さ
れる。又2本の注入管7m。Filler injection tubes 7a and 7b are inserted into the bag 6, and each injection tube 7a and 7b is provided with a number of filler outlet holes 8. One end of the injection pipes 7a, 7b protrudes outside the bag, and a hose for feeding the filler (see FIG. 4) is connected to this end. Also two injection pipes 7m.
7bは袋6にある程度の剛性を与えるから、採石面上に
沈下させ易いというメリットもある。従って現場の状況
によシ袋6を容易に展設できるときは、注入管を省略し
て直接袋内に充填剤を注入してもよい。袋6は布、ゴム
等が使用されるが、ファプリーシートを用いると充填剤
が圧入されるに伴なって袋内に入り込んだ水が目地から
排出される点で有利である。Since 7b gives the bag 6 some degree of rigidity, it also has the advantage of being easy to sink on the quarry surface. Therefore, if the bag 6 can be easily expanded due to the site conditions, the filler may be directly injected into the bag without the injection tube. The bag 6 may be made of cloth, rubber, or the like, but the use of Fapley sheet is advantageous in that water that has entered the bag as the filler is press-fitted can be discharged from the joints.
次に第4図に従って本発明の施工順序を説明する。まず
砕石2上に袋6を展設する。この作業はダイパーが行な
ってもよいし、クレーンで吊p降してもよい。浮力で浮
上がらないように空気な抜いておくのは勿論であるが、
それでも袋6が大きくなると作業が難しくなる。このよ
うな場合には袋6を巻いた状態で沈下させてから、海底
で展開させればよい。次に袋6から突出した注入管7m
。Next, the construction sequence of the present invention will be explained according to FIG. First, the bag 6 is placed on the crushed stone 2. This work may be performed by a dialer, or may be lifted and lowered by a crane. Of course, it is important to remove air so that it does not float up due to buoyancy,
Even so, the larger the bag 6, the more difficult the work will be. In such a case, the bag 6 may be rolled up and lowered, and then unfolded on the seabed. Next, the injection tube 7m protruding from the bag 6
.
7bの端部にホース9を接続し、ホース9の他端を海面
上に突出させる。次いでクレーンによシケーソン3を沈
下させるが、袋6からlO〜20c+a離れた位置で一
旦留めておく。当然この状態でケーソン3は水平を保っ
ている。ここでホース9の上端からモルタル等の充填剤
を圧入すると、袋6は膨張して上面はケーソンの底面に
当接し、下面は砕石2の隙間に入シ込む。従って袋内の
充填剤が固化すれば、袋6の上面は全て水平な平坦面を
構成する。(図中、説明の都合上袋内の注入管を省略し
た)後はクレーンの吊り具10を外すだけでケーソン3
は完全に水平に設置されることとなる。尚、ケーソンが
極めて大きい場合、袋はかなりの数を必要とするが、中
央付近に敷設された袋に対しては充填剤の注入が困難と
なる。このような場合には袋の注入管同士をジヨイント
で連結すれはよい。A hose 9 is connected to the end of 7b, and the other end of the hose 9 is made to protrude above the sea surface. Next, the sicaison 3 is lowered by a crane, but is temporarily held at a position 10~20c+a away from the bag 6. Naturally, Caisson 3 remains horizontal in this state. When a filler such as mortar is press-fitted from the upper end of the hose 9, the bag 6 expands so that the upper surface contacts the bottom surface of the caisson, and the lower surface enters the gap between the crushed stones 2. Therefore, once the filler in the bag is solidified, the entire top surface of the bag 6 forms a horizontal flat surface. (In the diagram, the injection pipe inside the bag is omitted for convenience of explanation.) After that, just remove the crane hoist 10 and the caisson 3
will be installed completely horizontally. Note that if the caisson is extremely large, a considerable number of bags will be required, and it will be difficult to inject filler into the bags placed near the center. In such cases, it is best to connect the injection tubes of the bags with a joint.
斜上の如く本発明の工法によれば、重力式構造物を水平
に設置できると共に、構造物の荷重分布も均等化される
から、安定した基礎工事を行なえる利点がある0According to the construction method of the present invention, such as diagonal construction, gravity-type structures can be installed horizontally, and the load distribution of the structure is equalized, so there is an advantage that stable foundation construction can be carried out.
第1図は海底に設置されたケーソンの簡略図、第2図は
コンクリートケーソンの底部付近を示す拡大図、第3図
は充填剤用の袋を示す斜視図、第4図は本発明工法を示
した簡略図である01・・海底、2−砕石、3・・・コ
ンク1ノートケーソン、5・水面、6・充填剤用の袋、
7m、7b・・注入管、8・・充填剤の流出孔
−4/〒
第1図
第3図
w!44図
45−Figure 1 is a simplified diagram of a caisson installed on the seabed, Figure 2 is an enlarged view of the bottom of the concrete caisson, Figure 3 is a perspective view of a bag for filler, and Figure 4 shows the construction method of the present invention. The simplified diagram shown is 01: seabed, 2: crushed stone, 3: concrete, 1 note caisson, 5: water surface, 6: bag for filler,
7m, 7b...Injection pipe, 8...Filling agent outflow hole-4/〒 Figure 1 Figure 3 w! 44Figure 45-
Claims (1)
底にvWtするに当たって、 まず、海底に敷きつめられた砕石上に充填剤用の袋を展
設し、次いで1記構造物を吊り降して前記袋と僅かの隙
間を残した位置でこれを一旦止め、前記袋内に充填剤を
仕入して固化させた後に繭記構造物を験上VC載置する
ことを特徴とする重力式構造物の水平設置工法。[Claims] When placing gravity-type structures such as concrete caissons and blocks on the seabed, first, a bag for filler is laid out on crushed stones spread on the seabed, and then the structure described in 1 is suspended. The method is characterized in that the cocoon structure is temporarily placed on a VC after being lowered and temporarily stopped at a position leaving a slight gap with the bag, and a filler is introduced into the bag and solidified. Horizontal installation method for gravity structures.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP20965781A JPS58113410A (en) | 1981-12-28 | 1981-12-28 | Horizontal setting work of gravity structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP20965781A JPS58113410A (en) | 1981-12-28 | 1981-12-28 | Horizontal setting work of gravity structure |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS58113410A true JPS58113410A (en) | 1983-07-06 |
Family
ID=16576430
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP20965781A Pending JPS58113410A (en) | 1981-12-28 | 1981-12-28 | Horizontal setting work of gravity structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS58113410A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS61242212A (en) * | 1985-04-17 | 1986-10-28 | Mitsui Eng & Shipbuild Co Ltd | Installation work of marine structure |
EP2348215A1 (en) * | 2009-12-29 | 2011-07-27 | Kyowa Co., Ltd. | Method for planarizing unevenness of the seabed |
CN103669383A (en) * | 2013-12-13 | 2014-03-26 | 中交第一航务工程局有限公司 | Method for installing and leveling caisson on seabed ground |
-
1981
- 1981-12-28 JP JP20965781A patent/JPS58113410A/en active Pending
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS61242212A (en) * | 1985-04-17 | 1986-10-28 | Mitsui Eng & Shipbuild Co Ltd | Installation work of marine structure |
JPH0342377B2 (en) * | 1985-04-17 | 1991-06-27 | ||
EP2348215A1 (en) * | 2009-12-29 | 2011-07-27 | Kyowa Co., Ltd. | Method for planarizing unevenness of the seabed |
US8657529B2 (en) | 2009-12-29 | 2014-02-25 | Kyowa Co., Ltd. | Method for planarizing unevenness of the seabed |
CN103669383A (en) * | 2013-12-13 | 2014-03-26 | 中交第一航务工程局有限公司 | Method for installing and leveling caisson on seabed ground |
CN103669383B (en) * | 2013-12-13 | 2015-12-02 | 中交第一航务工程局有限公司 | A kind of method of installation and leveling caisson on ground, seabed |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3788026A (en) | Stack-wall | |
CN103741657B (en) | The construction method of large-sized multifunction waterborne traffic accident | |
CN106245678B (en) | Outer wall of basement single side formwork construction method based on steel pipe truss | |
CN104060629B (en) | The superimposed wall construction method in covered back-digging subway station and portable side wall formwork jumbo | |
CN105220874A (en) | The construction method of basement superelevation exterior wall self-supporting single side formwork system | |
CN110924307A (en) | Trestle construction method for bare rock geology | |
US4146348A (en) | Method for executing impermeable construction joints for diaphragm walls | |
CN203924116U (en) | Portable side wall formwork jumbo | |
CN104264682B (en) | A kind of anchor draws the lagging pile first floor to add concrete beam method for supporting | |
JPS58113410A (en) | Horizontal setting work of gravity structure | |
WO2023178905A1 (en) | Non-bottom sealed double-wall steel cofferdam structure and construction method therefor | |
US3592012A (en) | Laterally reinforced offshore platform | |
CN211171994U (en) | Occlusive pile and diaphragm wall combined foundation pit supporting structure | |
JP4888293B2 (en) | Earth retaining wall made of parent pile sheet pile, water stop structure of earth retaining wall made of parent pile side sheet pile, construction method of earth retaining wall made of parent pile side sheet pile, and retaining wall of earth retaining wall made of parent pile side sheet pile Water method | |
CN210975862U (en) | Large-size foundation slab construction structure | |
JP2001241287A (en) | Construction method of shaft, assembly method of structural body used for construction method, and assembly device used for assembly method | |
CN219862751U (en) | Novel prestressed concrete foundation pit support pile | |
CN211690822U (en) | Be applied to enclosed construction among building construction process | |
CN211421151U (en) | Double-walled steel cofferdam based on picture peg | |
JP2000017643A (en) | Working method for pile head portion of diagonally assembled pile body | |
CN216948431U (en) | Template supporting structure for pipe gallery bottom plate backfilling area on counterfort dock wall | |
JP3311226B2 (en) | Construction method of wave-break water-permeable breakwater | |
JPS5911015B2 (en) | How to install shoring in the reverse winding method | |
JP3564502B2 (en) | New buried box height adjustment method and apparatus for existing buried boxes | |
JP3639084B2 (en) | Retaining wall block having a coupling structure and method for constructing retaining wall using the retaining wall block |