JPH11319609A - Unit for feeding ball to ball mill - Google Patents

Unit for feeding ball to ball mill

Info

Publication number
JPH11319609A
JPH11319609A JP13198598A JP13198598A JPH11319609A JP H11319609 A JPH11319609 A JP H11319609A JP 13198598 A JP13198598 A JP 13198598A JP 13198598 A JP13198598 A JP 13198598A JP H11319609 A JPH11319609 A JP H11319609A
Authority
JP
Japan
Prior art keywords
ball
balls
ball mill
chute
shute
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP13198598A
Other languages
Japanese (ja)
Inventor
Shinsuke Nakano
真輔 中野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Metal Mining Co Ltd
Original Assignee
Sumitomo Metal Mining Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Metal Mining Co Ltd filed Critical Sumitomo Metal Mining Co Ltd
Priority to JP13198598A priority Critical patent/JPH11319609A/en
Publication of JPH11319609A publication Critical patent/JPH11319609A/en
Withdrawn legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide the unit for feeding balls to a ball mill capable of exactly measuring the number of balls and feeding smoothly the balls and also hardly causing a trouble resulted from clogging of the balls. SOLUTION: In the ball feed unit to the ball mill 18 consisting of a shute 2 discharging the ball by rotating, an orientating machine 5 disposed at a front of the shute 2, arranging the balls discharged from the shute 2 and carrying out them to a carrying-out mechanism and a transporting machine transporting the balls carried out from the carrying-out mechanism and charging them to the ball mill 18, a weir plate 17 enable of discharging only one bank of balls is provided at a tip of the shute 2 and the orientating machine 5 is formed in a form like rod freely rotatable around a central axis and a notch in a form like gutter having a divide on its surface is formed in an axial direction. Moreover in the ball feed unit of the ball mill 18, a feed passage 16 in which at least three round rods are arranged side by side in parallel with a desired distance is disposed preferably at the tip part of the transporting machine.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、固形物をボールで
粉砕するボールミルに、ボールを供給する装置に関する
ものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an apparatus for supplying a ball to a ball mill for pulverizing solids with the ball.

【0002】[0002]

【従来の技術】一般に、ボールミルで固形物を粉砕する
場合には、所定時間運転する毎に直径の異なる数種類の
鋼鉄製ボールを所望量追加していく必要がある。従来、
このボールの供給作業は、ボールミルの運転中或いは運
転を一旦停止してから、作業員が所望量のボールを手作
業でボールミルに投入することにより行われていた。し
かし、この作業は手数が掛かるばかりでなく、作業環境
が悪い場所での重労働なので、安全衛生上の問題があっ
た。
2. Description of the Related Art In general, when pulverizing a solid material with a ball mill, it is necessary to add a desired amount of several types of steel balls having different diameters each time the ball is operated for a predetermined time. Conventionally,
The operation of supplying the ball has been performed in such a manner that an operator manually inputs a desired amount of the ball into the ball mill during or after the operation of the ball mill is temporarily stopped. However, this work is not only time-consuming, but also involves heavy work in a place with a poor working environment.

【0003】その対策として、例えば実開平5−490
46号記載のようなボール供給装置が開発されている。
この装置は図1、図2に示すように、複数の回動可能な
シュート2、12にそれぞれ直径の異なるボール4、4
a(4aは不図示)を常時貯留しておく。そして、例え
ばこのボール4をボールミル18に供給する必要が生じ
たら、所望のシュートを回動傾斜させて、その前方に配
設された図5に示すような円筒状の整列機5の樋状の切
り欠き5aに一列に整列させる。
As a countermeasure, for example, Japanese Utility Model Laid-Open No. 5-490
A ball supply device as described in No. 46 has been developed.
As shown in FIGS. 1 and 2, the apparatus includes a plurality of rotatable chutes 2, 12 each having a ball 4, 4 having a different diameter.
a (4a is not shown) is always stored. Then, for example, when it becomes necessary to supply the ball 4 to the ball mill 18, the desired chute is rotated and inclined, and a gutter-like shape of a cylindrical aligning machine 5 disposed in front of the chute as shown in FIG. Align the notches 5a in a line.

【0004】次に、この整列機5を回転させると、切り
欠き5aのボール4は下方に配設されたチェンコンベア
6に落下して水平に搬出され、前方のバケットコンベア
8に移載される。このとき、チェンコンベア6の先端部
に配設された光電管9によってボール数が計測され、設
定された数に達したらチェンコンベア6や整列機5は停
止し、シュート2も水平状態に復帰する。そして、バケ
ットコンベア8の前方には、図6のように鉄板製で折れ
曲がった形状の供給路15が配設されており、供給され
た所望量のボールがボールミルに投入されるようになっ
ている。尚、ボール4aについても上記と同様の供給が
行える。
Next, when the aligning machine 5 is rotated, the balls 4 in the notches 5a fall onto the chain conveyor 6 disposed below, are horizontally carried out, and are transferred to the front bucket conveyor 8. . At this time, the number of balls is measured by the photoelectric tube 9 disposed at the tip of the chain conveyor 6, and when the number reaches the set number, the chain conveyor 6 and the aligning machine 5 stop, and the chute 2 returns to the horizontal state. A supply path 15 made of an iron plate and bent is provided in front of the bucket conveyor 8 as shown in FIG. 6 so that a supplied desired amount of balls is put into a ball mill. . It should be noted that the same supply as described above can be performed for the ball 4a.

【0005】しかしながら、上記ボールミル供給装置で
は、直径の異なるボールをそれぞれ必要量だけ自動的に
供給することができるようになってはいるが、時には図
5に示すように、整列機5の切り欠き5a上に複数のボ
ール4が重なった状態となることがある。この状態で、
ボール4がチェンコンベア6に落下すると、ボール数の
計測に誤差が生じたり、ボールミル18前の供給路15
内でボール4が閉塞して装置の故障原因になることがあ
った。
[0005] However, in the above-mentioned ball mill supply device, balls having different diameters can be automatically supplied by a required amount, but sometimes, as shown in FIG. There may be a case where a plurality of balls 4 are superimposed on 5a. In this state,
If the balls 4 drop onto the chain conveyor 6, an error may occur in the measurement of the number of balls, or the supply path 15 in front of the ball mill 18
In some cases, the ball 4 was clogged, causing a failure of the device.

【0006】[0006]

【発明が解決しようとする課題】本発明は、ボール数を
正確に計測して円滑にボールを供給することが可能であ
り、且つボール供給時におけるボールの閉塞に起因する
故障をなくすことができるボールミルへのボール供給装
置を提供することを目的とする。
SUMMARY OF THE INVENTION According to the present invention, it is possible to supply a ball smoothly by accurately measuring the number of balls, and to eliminate a failure due to a blockage of the ball during the supply of the ball. An object of the present invention is to provide a ball supply device for a ball mill.

【0007】[0007]

【課題を解決するための手段】本発明によるボールミル
へのボール供給装置は、ボールを回動して排出するシュ
ートと、該シュートの前方に配設され、該シュートから
排出されたボールを並べて搬出機構に搬出する整列機
と、該搬出機構により搬出されたボールをボールミルに
搬送して装入する搬送機とからなるボールミルへのボー
ル供給装置において、該シュートの先端にボールを一列
だけ排出可能とする堰板を設け、該整列機を中心軸の周
りに回転自在な棒状とし、その表面に区切りを有する樋
状の切り欠きを軸方向に形成することを特徴とする。
A ball supply device for a ball mill according to the present invention comprises a chute for rotating and discharging a ball, and a chute disposed in front of the chute for discharging and discharging the ball discharged from the chute. In a ball supply device to a ball mill comprising an aligning machine for unloading to a mechanism and a transfer machine for transferring and charging the ball unloaded by the unloading mechanism to a ball mill, a single line of balls can be discharged to the tip of the chute. A dam plate is provided, and the aligner is formed in a rod shape rotatable about a central axis, and a gutter-shaped notch having a partition on its surface is formed in the axial direction.

【0008】更に、上記ボールミルへのボール供給装置
で、前記搬送機の先端部に、少なくとも三本の丸棒を所
望間隔で平行に並設した供給路を配設すると好適であ
る。
Further, in the above-described apparatus for supplying balls to a ball mill, it is preferable that a supply path in which at least three round bars are arranged in parallel at a desired interval is provided at the tip of the transfer machine.

【0009】[0009]

【作用】上記ボール供給装置では上述した構成により、
ボールが重なったり滞留したりすることがなく、一定数
のボールを排出することを可能とし、供給するボール数
の計数精度を向上させることができる。
According to the above-mentioned ball supply device,
It is possible to discharge a certain number of balls without the balls overlapping or staying, and to improve the counting accuracy of the number of balls to be supplied.

【0010】また、上記丸棒を並設した供給路の配設に
より、供給路の勾配が小さい場合や供給路の形状が曲線
状でも、ボールはシュートに沿って転動し一個ずつ順次
円滑にボールミルに装入されることになる。
[0010] Further, by providing the supply path in which the round bars are juxtaposed, even when the gradient of the supply path is small or the shape of the supply path is curved, the balls roll along the chute and are smoothly moved one by one sequentially. It will be charged into a ball mill.

【0011】[0011]

【発明の実施の形態】以下、具体的な実施形態の基づい
て説明するが、本発明はかかる実施形態の限定されるも
のではない。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, the present invention will be described based on specific embodiments, but the present invention is not limited to these embodiments.

【0012】本発明によるボール供給装置の構造は、図
1及び図2に示す如く、大部分は上述したボール供給装
置と同様である。
The structure of the ball supply device according to the present invention is, for the most part, similar to that of the above-described ball supply device, as shown in FIGS.

【0013】即ち、架台1の上方には第一のシュート2
が設けられ、シュート2は回動自在なように前方下端部
を軸支されている。シュート2はその底面裏に電動ジャ
ッキ3を取着され、傾動可能になっている。シュート2
の先端部には、後述する整列機5の切り欠き5aにボー
ルが重なって供給されないように、ボール4の直径より
もやや大きい空隙のある堰板17が配設されている。
That is, the first chute 2 is provided above the gantry 1.
The chute 2 is rotatably supported at its lower front end. The chute 2 has an electric jack 3 attached to the back of the bottom surface, and can be tilted. Shoot 2
At the front end of the ball, a weir plate 17 having an air gap slightly larger than the diameter of the ball 4 is provided so that the ball is not supplied to the notch 5a of the aligning machine 5 described later.

【0014】シュート2の前方には整列機5が配設され
ている。整列機5は図3に示す如く、円筒状でシュート
2の全幅に亘る長さを有し、部分的に切り欠き5aを形
設されている。整列機5はチェン7aを介しモーター7
によって、中心軸の周りを回転可能である(図1)。切
り欠き5aは、ボール4の直径よりもやや大きい寸法の
樋状に形成されており、切り欠き5aの間には、ボール
4一個毎に区切れるように仕切り5bが設けられてい
る。整列機5の上端部の高さは、ボール4がシュート2
から整列機5に落下しないように、シュート2の底面よ
りもやや高くなっている。整列機5の上方には、シュー
ト2の堰板17が位置している。
An aligning machine 5 is provided in front of the chute 2. As shown in FIG. 3, the aligning machine 5 is cylindrical, has a length that covers the entire width of the chute 2, and is partially formed with a notch 5a. The aligner 5 is driven by a motor 7 via a chain 7a.
Can rotate around the central axis (FIG. 1). The notch 5a is formed in a gutter shape having a size slightly larger than the diameter of the ball 4, and a partition 5b is provided between the notches 5a so as to be separated for each ball 4. The height of the upper end of the aligning machine 5 is such that the ball 4 is
Is slightly higher than the bottom surface of the chute 2 so as not to fall into the aligning machine 5 from above. Above the aligning machine 5, the weir plate 17 of the chute 2 is located.

【0015】整列機5の前方下方には、整列機5の長さ
よりも長いチェンコンベア6が配設されており、図示し
ていないモーターで駆動されるようになっている。ま
た、チェンコンベア6のボール搬出部分には光電管9が
配設され、これがチェンコンベア6で移動され搬出され
るボール4の数を計測し、予め設定された数量に達した
ら、整列機5、チェンコンベア6は停止し、シュート2
は水平に復帰する構成である。
A chain conveyor 6 longer than the length of the aligning machine 5 is provided below and in front of the aligning machine 5, and is driven by a motor (not shown). Further, a photoelectric tube 9 is disposed at a ball discharge portion of the chain conveyor 6, and the photoelectric tube 9 is moved by the chain conveyor 6 to measure the number of balls 4 to be discharged. Conveyor 6 stops and shoot 2
Is a configuration for returning horizontally.

【0016】チェンコンベア6の前方にはバケットコン
ベア8が配設され、バケットコンベア8の先端部分から
ボールミル18の装入口上方まで、曲線状に傾斜した供
給路16が配設されている。供給路16では図4に示す
如く、四本の丸棒16aが所望間隔で平行に並設され、
この丸棒16a間の空間をボール4が移動するようにな
っている。丸棒16aはボール4が移動可能なように設
ければよく、少なくとも三本以上であればその数は適宜
である。尚、供給路16の形状は適宜であり、図4の如
き円筒形に限定されるものではない。
A bucket conveyor 8 is provided in front of the chain conveyor 6, and a supply path 16 which is inclined in a curved manner is provided from a tip portion of the bucket conveyor 8 to a position above a loading port of the ball mill 18. In the supply path 16, as shown in FIG. 4, four round bars 16a are arranged in parallel at desired intervals.
The ball 4 moves in the space between the round bars 16a. The round bar 16a may be provided so that the ball 4 can be moved, and the number thereof is appropriate as long as it is at least three or more. The shape of the supply path 16 is appropriate, and is not limited to the cylindrical shape as shown in FIG.

【0017】更に、第一のシュート2、堰板17及び整
列機5に隣接した位置には、これらと同様な構造で、第
二のボール4aの直径に対応した寸法の第二のシュート
12、堰板19及び整列機13が配設され、チェンコン
ベア6の下方には排出部分に光電管10を有する第二の
チェンコンベア14が配設されている。整列機13はモ
ーター11によって中心軸の周りを回転可能である。
尚、上記の各装置は使用するボールの種別など必要に応
じて増減すればよい。
Further, at a position adjacent to the first chute 2, the weir plate 17 and the aligning machine 5, a second chute 12 having a structure similar to these and having a size corresponding to the diameter of the second ball 4a is provided. A weir plate 19 and an aligner 13 are provided, and a second chain conveyor 14 having a photoelectric tube 10 at a discharge portion is provided below the chain conveyor 6. The aligning machine 13 is rotatable around a central axis by a motor 11.
The above devices may be increased or decreased as necessary, such as the type of ball used.

【0018】次に、上記ボール供給装置の動作について
説明する。まず、各シュート2、12には直径の異なる
ボール4、4aを搬入貯留しておく。そして、チェンコ
ンベア6、バケットコンベア8を始動してから、電動ジ
ャッキ3を始動してシュート2を傾動させると、ボール
4が整列機5と堰板17で塞ぎ止められた状態となる。
Next, the operation of the ball supply device will be described. First, balls 4 and 4a having different diameters are loaded and stored in the chutes 2 and 12, respectively. Then, when the chain conveyor 6 and the bucket conveyor 8 are started, and the electric jack 3 is started to tilt the chute 2, the balls 4 are blocked by the aligning machine 5 and the weir plate 17.

【0019】この状態でモーター7を始動して整列機5
を回転させると、ボール4は切り欠き5aに一列に縦列
して装入され、更には仕切り5bで切り欠き5a毎にボ
ール4は一個ずつ区分して装入される。また、堰板17
があるため、ボール4は切り欠き5aで重なり合うこと
はない。そして、整列機5を更に回転させると、ボール
4はチェンコンベア6に落下して搬出される。このと
き、シュート2内の他のボール4は整列機5の円筒部で
塞ぎ止められている。
In this state, the motor 7 is started and the aligning machine 5 is started.
Is rotated, the balls 4 are loaded in the cutouts 5a in tandem, and the balls 4 are separately loaded one by one in the cutouts 5a by the partitions 5b. In addition, weir plate 17
Therefore, the ball 4 does not overlap with the notch 5a. Then, when the aligning machine 5 is further rotated, the balls 4 fall onto the chain conveyor 6 and are carried out. At this time, the other balls 4 in the chute 2 are closed by the cylindrical portion of the aligning machine 5.

【0020】一方、チェンコンベア6で搬送されたボー
ル4は、先端部分の光電管9で一個ずつ計測されながら
バケットコンベア8に移載され、バケットコンベア8で
搬送されたボール4は供給路16を転動し、一個ずつ円
滑にボールミル18に装入される。更に、整列機5を連
続して回転させてボール4を順次ボールミル18に装入
し、ボール4が所望量に達したら整列機5とチェンコン
ベア6を停止させ、シュート2を水平に復帰させる。
On the other hand, the balls 4 conveyed by the chain conveyor 6 are transferred to the bucket conveyor 8 while being measured one by one by the photoelectric tube 9 at the front end. The ball mill 18 is smoothly moved one by one. Further, the aligning machine 5 is continuously rotated to load the balls 4 sequentially into the ball mill 18, and when the balls 4 reach a desired amount, the aligning machine 5 and the chain conveyor 6 are stopped, and the chute 2 is returned to the horizontal.

【0021】また、必要があれば前述と同様にして、第
二のシュート12、第二の整列機13及び第二のチェン
コンベア14を駆動し、種別の異なるボール4aを所望
量追加する。尚、ボールミル18へのボール装入作業
は、ボールミル18の運転中或いは停止時に関わらず、
随時行うことができる。また、各装置の制御は図示して
いない制御盤で自動又は手動で行うことができる。
If necessary, the second chute 12, the second aligner 13, and the second chain conveyor 14 are driven in the same manner as described above, and a desired amount of balls 4a of different types is added. In addition, the ball charging operation to the ball mill 18 is performed regardless of whether the ball mill 18 is operating or stopped.
It can be done at any time. Control of each device can be performed automatically or manually by a control panel (not shown).

【0022】[0022]

【発明の効果】以上詳細に説明したように、本発明によ
るボールミルへのボール供給装置は上記構成であるか
ら、ボール数を正確に計測して円滑にボールを供給する
ことが可能となり、且つボール供給時におけるボールの
閉塞に起因する故障をなくすことができる効果を奏す
る。
As described above in detail, the apparatus for supplying a ball to a ball mill according to the present invention has the above-described configuration, so that the number of balls can be accurately measured and the balls can be supplied smoothly. There is an effect that a failure due to blockage of the ball at the time of supply can be eliminated.

【0023】更に、上記ボール供給装置を使用すること
により、ボールミルへのボール装入作業はボールミルの
運転中或いは停止時に関わらず、随時遠隔制御で行うこ
とが可能となるので、作業員の安全性とボールミルの作
業効率を向上させ、実用上顕著な効果が得られる。
Further, by using the above-mentioned ball supply device, the operation of charging the ball into the ball mill can be performed by remote control at any time irrespective of the operation or stoppage of the ball mill. In addition, the work efficiency of the ball mill is improved, and a practically remarkable effect is obtained.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明によるボール供給装置の正面図。FIG. 1 is a front view of a ball supply device according to the present invention.

【図2】図1の(A)一(A)線矢視図。FIG. 2 is a view taken along line (A)-(A) of FIG.

【図3】整列機の主要部の斜視図。FIG. 3 is a perspective view of a main part of the aligning machine.

【図4】図1の(B)一(B)線矢視図。FIG. 4 is a view taken along line (B)-(B) of FIG. 1;

【図5】従来の整列機の主要部の斜視図。FIG. 5 is a perspective view of a main part of a conventional aligning machine.

【図6】従来の供給路の斜視図。FIG. 6 is a perspective view of a conventional supply path.

【符号の説明】[Explanation of symbols]

2 シュート 4 ボール 5 整列機 5a 切り欠き 5b 仕切 6 チェンコンベア 8 バケットコンベア 9 光電管 16 供給路 16a 丸棒 17 堰板 18 ボールミル 2 Chute 4 Ball 5 Aligner 5a Notch 5b Partition 6 Chain conveyor 8 Bucket conveyor 9 Phototube 16 Supply path 16a Round bar 17 Weir plate 18 Ball mill

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 ボールを回動して排出するシュート
と、該シュートの前方に配設され、該シュートから排出
されたボールを並べて搬出機構に搬出する整列機と、該
搬出機構により搬出されたボールをボールミルに搬送し
て装入する搬送機とからなるボールミルへのボール供給
装置において、 該シュートの先端にボールを一列だけ排出可能とする堰
板を設け、該整列機を中心軸の周りに回転自在な棒状と
し、その表面に区切りを有する樋状の切り欠きを軸方向
に形成することを特徴とするボールミルへのボール供給
装置。
1. A chute for rotating and ejecting a ball, an aligning machine disposed in front of the chute, for aligning and ejecting the ball ejected from the chute to an ejection mechanism, and ejected by the ejection mechanism. In a ball supply device for a ball mill, comprising a transfer device for transferring and charging a ball to a ball mill, a weir plate capable of discharging a single line of balls is provided at the tip of the chute, and the aligning device is arranged around a central axis. A ball supply device for a ball mill, comprising a rotatable rod shape and a gutter-shaped notch having a partition on its surface formed in an axial direction.
【請求項2】 前記搬送機の先端部に、少なくとも三
本の丸棒を所望間隔で平行に並設した供給路を配設する
ことを特徴とする請求項1記載のボールミルへのボール
供給装置。
2. A ball supply apparatus for a ball mill according to claim 1, wherein a supply path in which at least three round bars are arranged in parallel at a desired interval is disposed at a tip end of said transporter. .
JP13198598A 1998-05-14 1998-05-14 Unit for feeding ball to ball mill Withdrawn JPH11319609A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13198598A JPH11319609A (en) 1998-05-14 1998-05-14 Unit for feeding ball to ball mill

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13198598A JPH11319609A (en) 1998-05-14 1998-05-14 Unit for feeding ball to ball mill

Publications (1)

Publication Number Publication Date
JPH11319609A true JPH11319609A (en) 1999-11-24

Family

ID=15070868

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13198598A Withdrawn JPH11319609A (en) 1998-05-14 1998-05-14 Unit for feeding ball to ball mill

Country Status (1)

Country Link
JP (1) JPH11319609A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009260177A (en) * 2008-04-21 2009-11-05 Nippon Oil Corp Activated charcoal for electric double-layer capacitor electrode and manufacturing method thereof
CN103008068A (en) * 2012-12-31 2013-04-03 中南大学 Automatic ball feeding method with accuracy control
CN103056002A (en) * 2012-12-05 2013-04-24 南京梅山冶金发展有限公司 Automatic ball adding machine
CN104785331A (en) * 2015-04-02 2015-07-22 湖南易控自动化工程技术有限公司 Gear rotating ball adder
JP2021181050A (en) * 2020-05-19 2021-11-25 Jfeスチール株式会社 Rod replacement device and method of rod mill

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009260177A (en) * 2008-04-21 2009-11-05 Nippon Oil Corp Activated charcoal for electric double-layer capacitor electrode and manufacturing method thereof
CN103056002A (en) * 2012-12-05 2013-04-24 南京梅山冶金发展有限公司 Automatic ball adding machine
CN103008068A (en) * 2012-12-31 2013-04-03 中南大学 Automatic ball feeding method with accuracy control
CN104785331A (en) * 2015-04-02 2015-07-22 湖南易控自动化工程技术有限公司 Gear rotating ball adder
JP2021181050A (en) * 2020-05-19 2021-11-25 Jfeスチール株式会社 Rod replacement device and method of rod mill

Similar Documents

Publication Publication Date Title
JP6723655B2 (en) Weighing device
JPH11319609A (en) Unit for feeding ball to ball mill
JPH0158448B2 (en)
JP2003214936A (en) Combination weighing apparatus
JPH01275322A (en) Method and device for aligning wood such as log, bar, etc. in parallel
JP2710494B2 (en) Control method of transport screw
JP2579006Y2 (en) Crop sorting equipment
JP2545420Y2 (en) Ball supply device to ball mill
US7015399B2 (en) Combination calculation method and combination measuring device
JP3611914B2 (en) Weighing box packing equipment
JP2673065B2 (en) Combination weighing machine
JPH065651Y2 (en) Magazine buffer
JP2002107210A (en) Automatic feeding device and combined metering device equipped with same
CN218402550U (en) Material distribution equipment
JP7366498B2 (en) Goods supply device and weighing system equipped with it
JPH0692318A (en) Apparatus and method for packing farm product
CN212158036U (en) Bamboo strip drying device
JP3392537B2 (en) Combination weighing method and combination weighing device
JP3077783B2 (en) Work counting device
JPH0729048Y2 (en) Fixed-size material alignment supply device
JPH08217299A (en) Core transferring device
JP3465965B2 (en) Combination weighing system
JPH08238460A (en) Length selecting apparatus for long material
JP2022055461A (en) Combination weighing machine
JPH05178418A (en) Drum can storage equipment

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20050802