JPH11303138A - Method for coupling truck frame for construction machine and its coupling bolt device - Google Patents

Method for coupling truck frame for construction machine and its coupling bolt device

Info

Publication number
JPH11303138A
JPH11303138A JP12961298A JP12961298A JPH11303138A JP H11303138 A JPH11303138 A JP H11303138A JP 12961298 A JP12961298 A JP 12961298A JP 12961298 A JP12961298 A JP 12961298A JP H11303138 A JPH11303138 A JP H11303138A
Authority
JP
Japan
Prior art keywords
bolt
insertion hole
mounting portion
bolt insertion
center frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP12961298A
Other languages
Japanese (ja)
Inventor
Masanori Hotta
正典 堀田
Masataka Sendai
祥考 千代
Mamoru Nomura
守 野村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Construction Machinery Co Ltd
Original Assignee
Hitachi Construction Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Construction Machinery Co Ltd filed Critical Hitachi Construction Machinery Co Ltd
Priority to JP12961298A priority Critical patent/JPH11303138A/en
Publication of JPH11303138A publication Critical patent/JPH11303138A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To enhance workability in coupling a center frame to a truck beam by use of a coupling bolt. SOLUTION: A beam mounting flange 7 of a center frame 2 is coupled to a truck beam 10 by use of a coupling bolt device 21 having a tension jig 23 attached to a bolt main body 22. With the bolt main body 22 placed on the lower surface plate 12 of the truck beam 10, the wire 25 of the tension jig 23 is passed through a bolt hole 7A in the beam mounting flange 7 from a bolt hole 11A in the truck beam 10, and the bolt main body 22 can be easily passed through the bolt holes 11A, 7A by simply pulling upward the wire 25 projecting from the bolt hole 7A. Thus, workability can be enhanced when the beam mounting flange 7 is coupled to the truck beam 10 by use of the bolt main body 22.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、例えば油圧ショベ
ル、油圧クレーン等の下部走行体を構成する建設機械用
トラックフレームの連結方法及びその連結ボルト装置に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of connecting a truck frame for construction equipment constituting a lower traveling body such as a hydraulic shovel, a hydraulic crane, and the like, and a connecting bolt device therefor.

【0002】[0002]

【従来の技術】一般に、建設現場における高所への資材
運搬作業を行う油圧クレーンや、土砂等の掘削作業を行
う油圧ショベル等の建設機械は、泥濘地等の不整地を走
行するためにクローラ式の下部走行体を備えている。
2. Description of the Related Art In general, construction machines such as a hydraulic crane for transporting materials to a high place at a construction site and a hydraulic shovel for excavating earth and sand are used as crawlers for traveling on uneven terrain such as muddy land. It has an undercarriage of the formula.

【0003】そこで、この種の従来技術によるクローラ
式の下部走行体について、図10ないし図13を参照し
つつ説明する。
A crawler-type undercarriage of this type according to the prior art will be described with reference to FIGS. 10 to 13. FIG.

【0004】図10において、1は下部走行体を構成す
るトラックフレームを示し、このトラックフレーム1
は、センタフレーム2と、前,後方向に離間してセンタ
フレーム2に配設され、左,右方向の両端部がセンタフ
レーム2から突出した後述のトラックビーム10,10
と、各トラックビーム10の突出端側に配設され、前,
後方向に延びる左,右のサイドフレーム17,17とを
備えている。
In FIG. 10, reference numeral 1 denotes a track frame constituting a lower traveling body.
Are disposed on the center frame 2 so as to be spaced apart from the center frame 2 in the front and rear directions, and track beams 10, 10, which will be described later, have both left and right ends projecting from the center frame 2.
Disposed on the protruding end side of each track beam 10,
There are left and right side frames 17, 17 extending rearward.

【0005】ここで、センタフレーム2は、図12に示
すように、上面板3と、上面板3と対向する下面板4
と、上面板3と下面板4との間を連結する側面板5とか
らほぼ矩形の箱状に形成されている。また、上面板3の
中央部には上部旋回体(図示せず)を旋回可能に支持す
るための円筒状の丸胴6が設けられている。
Here, as shown in FIG. 12, the center frame 2 includes an upper plate 3 and a lower plate 4 opposed to the upper plate 3.
And a side plate 5 connecting the upper plate 3 and the lower plate 4 to form a substantially rectangular box. Further, a cylindrical round body 6 for supporting an upper revolving body (not shown) in a rotatable manner is provided at a central portion of the upper surface plate 3.

【0006】7,7,…はセンタフレーム2の四隅に配
設されたビーム取付フランジで、各ビーム取付フランジ
7は、図12に示すように、基端側がセンタフレーム2
の側面板5に固着され、L字状に屈曲した先端側が前,
後方向に突出している。また、ビーム取付フランジ7と
センタフレーム2の上面板3との間は連結板8によって
連結され、ビーム取付フランジ7と連結板8との間には
補強用のリブ9,9が固着されている。そして、図13
に示すように、各ビーム取付フランジ7には4個のボル
ト挿通穴7A,7B,7C,7Dがそれぞれ穿設されて
いる。
Are beam mounting flanges arranged at the four corners of the center frame 2, and each of the beam mounting flanges 7 has a base end on the center frame 2 side as shown in FIG.
The front end side which is fixed to the side plate 5 of the
It protrudes backward. A connection plate 8 connects between the beam mounting flange 7 and the upper surface plate 3 of the center frame 2, and reinforcing ribs 9, 9 are fixed between the beam mounting flange 7 and the connection plate 8. . And FIG.
As shown in FIG. 5, four bolt insertion holes 7A, 7B, 7C and 7D are formed in each beam mounting flange 7, respectively.

【0007】10,10は前,後方向に離間してセンタ
フレーム2のビーム取付フランジ7に取付けられ、左,
右方向の両端部がセンタフレーム2から突出した2本の
トラックビームで、各トラックビーム10は、図12に
示すように、上面板11と、下面板12と、上面板11
と下面板12との間を連結する一対の側面板13,13
とからなっている。そして、図13に示すように、トラ
ックビーム10の上面板11には、センタフレーム2の
ビーム取付フランジ7に穿設されたボルト挿通穴7A,
7B,7C,7Dと対応する位置に4個のボルト挿通穴
11A,11B,11C,11Dが穿設されている。ま
た、上面板11の下面側には、各ボルト挿通穴11A〜
11Dを囲んで4個の廻止め部材14,14,…(2個
のみ図示)が固着されている(図12参照)。
The reference numerals 10 and 10 are attached to the beam attachment flange 7 of the center frame 2 while being spaced apart in the front and rear directions.
The right and left ends are two track beams protruding from the center frame 2, and each track beam 10 includes an upper plate 11, a lower plate 12, and an upper plate 11 as shown in FIG.
A pair of side plates 13, 13 for connecting between the
It consists of Then, as shown in FIG. 13, bolt insertion holes 7 </ b> A formed in the beam mounting flange 7 of the center frame 2
Four bolt insertion holes 11A, 11B, 11C, 11D are formed at positions corresponding to 7B, 7C, 7D. Further, on the lower surface side of the upper surface plate 11, each of the bolt insertion holes 11A to
Four detent members 14, 14,... (Only two are shown) are fixed around 11D (see FIG. 12).

【0008】そして、図12に示すように、センタフレ
ーム2に設けたビーム取付フランジ7の下側にトラック
ビーム10を配置した状態で、トラックビーム10の各
ボルト挿通穴11A〜11Dからビーム取付フランジ7
の各ボルト挿通穴7A〜7Dに向けて連結ボルト15,
15,…を挿通し、ビーム取付フランジ7のボルト挿通
穴7A〜7Dから上側に突出した連結ボルト15にナッ
ト16,16を締込むことにより、センタフレーム2の
ビーム取付フランジ7にトラックビーム10が連結され
る構成となっている。
Then, as shown in FIG. 12, in a state where the track beam 10 is disposed below the beam mounting flange 7 provided on the center frame 2, the beam mounting flange is inserted through the bolt insertion holes 11A to 11D of the track beam 10. 7
Connecting bolts 15 toward the respective bolt insertion holes 7A to 7D.
By inserting nuts 16 into the connecting bolts 15 projecting upward from the bolt insertion holes 7A to 7D of the beam mounting flange 7, the track beam 10 is inserted into the beam mounting flange 7 of the center frame 2. It is configured to be connected.

【0009】17,17はトラックビーム10の突出端
側に配設され、前,後方向に延びた左,右のサイドフレ
ームで、図10に示すように、各サイドフレーム17は
前,後方向に離間した2個の角穴17A,17Aを有
し、これら角穴17A内にトラックビーム10の突出端
部を挿入した状態で、連結ボルト(図示せず)等によっ
てトラックビーム10に固着されるものである。そし
て、各サイドフレーム17の前,後方向の両端側に配設
された遊動輪と駆動輪(いずれも図示せず)との間には
履帯18が巻回され、これらサイドフレーム17、遊動
輪、駆動輪、及び履帯18によって左,右のクローラ走
行体19が構成されている。
Reference numerals 17 and 17 denote left and right side frames which are disposed on the protruding end side of the track beam 10 and extend forward and rearward. As shown in FIG. The track beam 10 is fixed to the track beam 10 by connecting bolts (not shown) or the like in a state where the projecting end of the track beam 10 is inserted into these square holes 17A, 17A. Things. A crawler belt 18 is wound between idler wheels and drive wheels (both not shown) disposed at both front and rear ends of each side frame 17, and these side frames 17 and idler wheels are provided. , Drive wheels, and crawler belt 18 form left and right crawler traveling bodies 19.

【0010】そして、上述した従来技術による下部走行
体では、通常、作業現場に搬送するときの重量制限、高
さ制限等に適合するように、下部走行体をセンタフレー
ム2と、トラックビーム10と、クローラ走行体19と
に分割した状態で個別にトレーラ等によって作業現場に
搬送した後、作業現場においてこれらセンタフレーム
2、トラックビーム10、クローラ走行体19を組立て
るようにしている。
In the undercarriage according to the prior art described above, the undercarriage is usually connected to the center frame 2 and the track beam 10 so as to conform to weight restrictions, height restrictions and the like when transported to the work site. After being divided into the crawler traveling body 19 and individually conveyed to a work site by a trailer or the like, the center frame 2, the track beam 10, and the crawler traveling body 19 are assembled at the work site.

【0011】[0011]

【発明が解決しようとする課題】ところで、分割された
状態で作業現場に搬送されたセンタフレーム2と各トラ
ックビーム10とを連結する場合には、図11及び図1
3に示すように、センタフレーム2に設けたビーム取付
フランジ7の下側にトラックビーム10を配置した状態
で、トラックビーム10の各ボルト挿通穴11A〜11
Dからビーム取付フランジ7の各ボルト挿通穴7A〜7
Dに向けて連結ボルト15を挿通し、ビーム取付フラン
ジ7のボルト挿通穴7A〜7Dから突出した連結ボルト
15にナット16,16を締込む連結作業を行う。
By the way, when the center frame 2 transported to the work site in a divided state and each track beam 10 are to be connected, FIG. 11 and FIG.
As shown in FIG. 3, in a state where the track beam 10 is arranged below the beam mounting flange 7 provided on the center frame 2, each of the bolt insertion holes 11A to 11A of the track beam 10 is provided.
D to bolt mounting holes 7A to 7 of beam mounting flange 7
A connection operation is performed in which the connection bolt 15 is inserted toward D, and the nuts 16, 16 are tightened into the connection bolt 15 protruding from the bolt insertion holes 7A to 7D of the beam mounting flange 7.

【0012】ここで、上述の連結作業を行うとき、トラ
ックビーム10のボルト挿通穴11B,11C,11D
と、ビーム取付フランジ7のボルト挿通穴7B,7C,
7Dとに連結ボルト15を挿通するときには、該連結ボ
ルト15の周囲に比較的大きな作業スペースを確保する
ことができる。
Here, when performing the above-mentioned connecting operation, the bolt insertion holes 11B, 11C, 11D of the track beam 10 are used.
And bolt insertion holes 7B, 7C,
When the connecting bolt 15 is inserted through the connecting bolt 7D, a relatively large working space can be secured around the connecting bolt 15.

【0013】しかし、トラックビーム10のボルト挿通
穴11Aとビーム取付フランジ7のボルト挿通穴7Aと
に連結ボルト15を挿通するときには、図12に示すよ
うに、センタフレーム2の側面板5とトラックビーム1
0の側面板13との間に形成された狭隘な空間A内に連
結ボルト15を配置しなければならない。このため、作
業者は、上述の狭隘な空間A内で連結ボルト15を片手
で支持し、トラックビーム10のボルト挿通穴11Aを
手探りしつつ、該ボルト挿通穴11Aからビーム取付フ
ランジ7のボルト挿通穴7Aに連結ボルト15を挿通し
なければならない。この場合、連結ボルト15として
は、例えばM45程度の重量の大きなボルトが用いられ
るため、この連結ボルト15をトラックビーム10のボ
ルト挿通穴11Aからビーム取付フランジ7のボルト挿
通穴7Dに挿通するときの作業性が非常に悪く、作業者
にも大きな負担となってしまうという問題がある。
However, when the connecting bolt 15 is inserted into the bolt insertion hole 11A of the track beam 10 and the bolt insertion hole 7A of the beam mounting flange 7, as shown in FIG. 1
The connecting bolt 15 must be disposed in a narrow space A formed between the side bolt 13 and the side plate 13. For this reason, the worker supports the connecting bolt 15 with one hand in the above-mentioned narrow space A, while groping for the bolt insertion hole 11A of the track beam 10, and inserting the bolt into the beam mounting flange 7 from the bolt insertion hole 11A. The connecting bolt 15 must be inserted into the hole 7A. In this case, since a large bolt having a weight of, for example, about M45 is used as the connection bolt 15, the connection bolt 15 is inserted into the bolt insertion hole 7D of the beam mounting flange 7 from the bolt insertion hole 11A of the track beam 10. There is a problem that the workability is very poor and a heavy burden is imposed on the worker.

【0014】本発明は上述した従来技術の問題に鑑みな
されたもので、連結ボルトを用いてセンタフレームとト
ラックビームとを連結するときの作業性を向上させるこ
とができるようにした建設機械用トラックフレームの連
結方法及びその連結ボルト装置を提供することを目的と
している。
The present invention has been made in view of the above-described problems of the prior art, and has been improved in terms of workability when connecting a center frame and a track beam using connecting bolts. It is an object of the present invention to provide a method of connecting frames and a bolt device for connecting the frames.

【0015】[0015]

【課題を解決するための手段】上述した課題を解決する
ため、本発明は、ビーム取付部を有するセンタフレーム
と、前記センタフレームのビーム取付部にボルトによっ
て連結されるトラックビームとを備えた建設機械用トラ
ックフレームに適用される。
SUMMARY OF THE INVENTION In order to solve the above-mentioned problems, the present invention provides a construction comprising a center frame having a beam mounting portion, and a track beam connected to the beam mounting portion of the center frame by bolts. Applies to truck tracks for machinery.

【0016】そして、請求項1の発明による建設機械用
トラックフレームの連結方法は、連結ボルトを引張り治
具を用いてセンタフレームのビーム取付部側から引張り
トラックビームに設けたボルト挿通穴を介して前記セン
タフレームのビーム取付部に設けたボルト挿通穴に挿通
するボルト挿通工程と、前記ビーム取付部のボルト挿通
穴から突出した前記連結ボルトにナットを締込んで前記
ビーム取付部にトラックビームを連結する連結工程とか
らなる。
In the method of connecting a truck frame for construction equipment according to the first aspect of the present invention, the connecting bolt is pulled from a beam mounting portion side of the center frame through a bolt insertion hole provided in the pulling track beam using a pulling jig. A bolt insertion step of inserting into a bolt insertion hole provided in a beam attachment portion of the center frame, and connecting a track beam to the beam attachment portion by tightening a nut into the connection bolt protruding from the bolt insertion hole of the beam attachment portion. Connecting step.

【0017】このような連結方法を採用したことによ
り、センタフレームのビーム取付部にトラックビームを
連結するときに、引張り治具を用いて連結ボルトをビー
ム取付部側から引張ると、連結ボルトをトラックビーム
のボルト挿通穴を介してビーム取付部のボルト挿通穴へ
と容易に挿通することができる。
By adopting such a connecting method, when connecting the track beam to the beam mounting portion of the center frame, if the connecting bolt is pulled from the beam mounting portion side using a pulling jig, the connecting bolt is moved to the track. The beam can be easily inserted into the bolt insertion hole of the beam mounting portion through the bolt insertion hole of the beam.

【0018】また、請求項2の発明による建設機械用ト
ラックフレームの連結方法は、連結ボルトをトラックビ
ームに設けたボルト挿通穴に向けて直立状態に保持する
ボルト保持工程と、前記連結ボルトを引張り治具を用い
てセンタフレームのビーム取付部側から引張り前記トラ
ックビームに設けたボルト挿通穴を介して前記センタフ
レームのビーム取付部に設けたボルト挿通穴に挿通する
ボルト挿通工程と、前記ビーム取付部のボルト挿通穴か
ら突出した前記連結ボルトにナットを締込んで前記ビー
ム取付部にトラックビームを連結する連結工程とからな
る。
According to a second aspect of the present invention, there is provided a method of connecting a truck frame for a construction machine, comprising: a bolt holding step of holding a connecting bolt upright toward a bolt insertion hole provided in a track beam; and pulling the connecting bolt. A bolt insertion step of pulling from a beam attachment portion side of the center frame using a jig and inserting the bolt into a bolt insertion hole provided in the beam attachment portion of the center frame through a bolt insertion hole provided in the track beam; Connecting a track beam to the beam mounting portion by tightening a nut to the connection bolt protruding from the bolt insertion hole of the portion.

【0019】このような連結方法を採用したことによ
り、連結ボルトをトラックビームに設けたボルト挿通穴
に向けて直立状態に保持した後、この連結ボルトを引張
り治具を用いてビーム取付部側から引張ると、連結ボル
トをトラックビームのボルト挿通穴周囲に衝合させるこ
となく、このボルト挿通穴を介してビーム取付部のボル
ト挿通穴へと容易に挿通することができる。
By adopting such a connecting method, after the connecting bolt is held upright toward the bolt insertion hole provided in the track beam, the connecting bolt is pulled from the beam mounting portion side using a tension jig. When pulled, the connecting bolt can be easily inserted through the bolt insertion hole into the bolt insertion hole of the beam mounting portion without abutting around the bolt insertion hole of the track beam.

【0020】そして、請求項3の発明による建設機械用
トラックフレームの連結ボルト装置は、トラックビーム
に設けられたボルト挿通穴とセンタフレームのビーム取
付部に設けられたボルト挿通穴とに挿通されるボルト本
体と、基端側が前記ボルト本体に着脱可能に取付けら
れ、自由端となった先端側が前記ボルト本体に先立って
前記トラックビームのボルト挿通穴からビーム取付部の
ボルト挿通穴へと挿通される引張り治具とから構成した
ことにある。
According to the third aspect of the present invention, a connecting bolt device for a truck frame for construction equipment is inserted into a bolt inserting hole provided in a track beam and a bolt inserting hole provided in a beam attaching portion of a center frame. A bolt body and a base end side are detachably attached to the bolt body, and a free end end is inserted from a bolt insertion hole of the track beam into a bolt insertion hole of a beam attachment portion prior to the bolt body. And a pulling jig.

【0021】このように構成したことにより、ボルト本
体に取付けられた引張り治具の先端側を、ボルト本体に
先立ってトラックビームのボルト挿通穴からビーム取付
部のボルト挿通穴へと挿通し、ビーム取付部のボルト挿
通穴から突出した引張り治具の先端側を引張るだけで、
ボルト本体をトラックビームのボルト挿通穴からビーム
取付部のボルト挿通穴へと挿通することができる。
With this configuration, the leading end side of the tension jig attached to the bolt body is inserted from the bolt insertion hole of the track beam into the bolt insertion hole of the beam attachment section prior to the bolt body, and Just pull on the tip of the pulling jig that protrudes from the bolt insertion hole of the mounting part,
The bolt main body can be inserted from the bolt insertion hole of the track beam into the bolt insertion hole of the beam attachment portion.

【0022】また、請求項4の発明は、ボルト本体は、
外周側にねじ部が設けられた軸部と、前記軸部の基端側
に設けられた頭部と、前記軸部の先端側に設けられたね
じ穴とから構成し、引張り治具は、前記ボルト本体のね
じ穴に螺合するねじ軸と、前記ねじ軸に取付けられたワ
イヤとから構成したことにある。
According to a fourth aspect of the present invention, the bolt body is
A shaft portion provided with a screw portion on the outer peripheral side, a head provided on a base end side of the shaft portion, and a screw hole provided on a distal end side of the shaft portion, a pulling jig, It is characterized by comprising a screw shaft screwed into a screw hole of the bolt body and a wire attached to the screw shaft.

【0023】このように構成したことにより、ボルト本
体の軸部先端側にねじ軸を介して取付けられたワイヤを
撓ませつつ、このワイヤをボルト本体に先立ってトラッ
クビームのボルト挿通穴からビーム取付部のボルト挿通
穴へと容易に挿通することができる。
With this configuration, the wire attached to the shaft end of the bolt body via the screw shaft is bent, and the wire is attached to the track beam from the bolt insertion hole of the track beam prior to the bolt body. It can be easily inserted into the bolt insertion hole of the part.

【0024】さらに、請求項5の発明は、トラックビー
ムにはボルト本体をボルト挿通穴に向けて直立状態に保
持するボルト保持具を設ける構成としたことにある。
Further, the invention of claim 5 is characterized in that the track beam is provided with a bolt holder for holding the bolt body upright with the bolt body facing the bolt insertion hole.

【0025】このように構成したことにより、ボルト保
持具によって保持されたボルト本体は、トラックビーム
のボルト挿通穴に向けて直立した状態を保つから、引張
り治具をトラックビームのボルト挿通穴からビーム取付
部のボルト挿通穴へと挿通した後、ビーム取付部のボル
ト挿通穴から突出した引張り治具を引張ったときに、ボ
ルト本体を容易にトラックビームのボルト挿通穴からビ
ーム取付部のボルト挿通穴へと挿通することができる。
With this configuration, the bolt body held by the bolt holder is kept upright toward the bolt insertion hole of the track beam, so that the pulling jig is moved from the bolt insertion hole of the track beam to the beam. After inserting the bolt into the bolt insertion hole of the mounting part and pulling the tension jig protruding from the bolt insertion hole of the beam mounting part, the bolt body can be easily inserted from the bolt insertion hole of the track beam to the bolt insertion hole of the beam mounting part. Can be inserted into

【0026】[0026]

【発明の実施の形態】以下、本発明による建設機械用ト
ラックフレームに用いる連結ボルト装置の実施の形態
を、油圧クレーンのトラックフレームに適用した場合を
例に挙げ、図1ないし図9を参照しつつ詳細に説明す
る。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a connecting bolt device used for a truck frame for construction equipment according to the present invention will be described below with reference to FIGS. This will be described in detail.

【0027】まず、図1ないし図4は本発明による第1
の実施の形態を示している。なお、本実施の形態では、
上述した従来技術と同一の構成要素に同一符号を付し、
その説明を省略するものとする。
First, FIGS. 1 to 4 show a first embodiment according to the present invention.
Is shown. In the present embodiment,
The same reference numerals are given to the same components as those of the above-described conventional technology,
The description is omitted.

【0028】図1において、21は本実施の形態による
連結ボルト装置を示し、この連結ボルト装置21は、セ
ンタフレーム2のビーム取付フランジ7に穿設されたボ
ルト挿通穴7Aとトラックビーム10の上面板11に穿
設されたボルト挿通穴11Aとに挿通されるボルト本体
22と、ボルト本体22の先端面に取付けられた後述の
引張り治具23とからなっている。
In FIG. 1, reference numeral 21 denotes a connecting bolt device according to the present embodiment. The connecting bolt device 21 is provided on a bolt insertion hole 7A formed in the beam mounting flange 7 of the center frame 2 and above the track beam 10. It comprises a bolt main body 22 inserted into a bolt insertion hole 11A drilled in the face plate 11, and a tension jig 23 described later attached to a tip end surface of the bolt main body 22.

【0029】ここで、ボルト本体22は、図2に示すよ
うに、外周側にねじが設けられた軸部22Aと、軸部2
2Aの基端側に設けられた六角形状の頭部22Bと、軸
部22Aの先端側端面に穿設されたねじ穴22Cとから
構成されている。
As shown in FIG. 2, the bolt main body 22 includes a shaft portion 22A provided with a screw on the outer peripheral side, and a shaft portion 2A.
It is composed of a hexagonal head 22B provided on the base end side of 2A, and a screw hole 22C formed in the front end surface of the shaft portion 22A.

【0030】23はボルト本体22の先端側に着脱可能
に設けられた引張り治具を示し、この引張り治具23
は、ボルト本体22のねじ穴22Cに螺合し、先端側が
環状の取付アイ24Aとなったねじ軸としてのアイボル
ト24と、アイボルト24の取付アイ24Aに連結され
た可撓性を有するワイヤ25とからなり、ワイヤ25の
先端側にはリング26が取付けられている。ここで、ア
イボルト24の取付アイ24A、及びリング26の外径
は、ボルト本体22の軸部22Aの外径よりも小径に形
成されている。
Reference numeral 23 denotes a pulling jig detachably provided on the tip end side of the bolt body 22.
The eye bolt 24 is screwed into the screw hole 22C of the bolt body 22 and has an annular mounting eye 24A on the distal end side as a screw shaft, and a flexible wire 25 connected to the mounting eye 24A of the eye bolt 24. A ring 26 is attached to the distal end side of the wire 25. Here, the outer diameter of the mounting eye 24A of the eye bolt 24 and the outer diameter of the ring 26 are formed to be smaller than the outer diameter of the shaft portion 22A of the bolt body 22.

【0031】そして、引張り治具23は、ボルト本体2
2に先立ってワイヤ25をトラックビーム10のボルト
挿通穴11Aからビーム取付フランジ7のボルト挿通穴
7Aへと挿通し、ビーム取付フランジ7のボルト挿通穴
7Aから上方に突出したリング26を上向きに引張るこ
とにより、ボルト本体22の軸部22Aを、トラックビ
ーム10のボルト挿通穴11Aを介してビーム取付フラ
ンジ7のボルト挿通穴7Aに挿通させるものである。
The tension jig 23 is connected to the bolt body 2.
Prior to 2, the wire 25 is inserted from the bolt insertion hole 11A of the track beam 10 into the bolt insertion hole 7A of the beam mounting flange 7, and the ring 26 projecting upward from the bolt insertion hole 7A of the beam mounting flange 7 is pulled upward. Thus, the shaft portion 22A of the bolt main body 22 is inserted into the bolt insertion hole 7A of the beam mounting flange 7 via the bolt insertion hole 11A of the track beam 10.

【0032】27はビーム取付フランジ7の近傍に位置
してセンタフレーム2の上面板3上に設けられたフック
で、このフック27は、トラックビーム10のボルト挿
通穴11Aとビーム取付フランジ7のボルト挿通穴7A
とにボルト本体22を挿通した後、引張り治具23のリ
ング26を係止しておくものである。
Reference numeral 27 denotes a hook provided on the upper surface plate 3 of the center frame 2 in the vicinity of the beam mounting flange 7. The hook 27 is provided with a bolt insertion hole 11A of the track beam 10 and a bolt of the beam mounting flange 7. Insertion hole 7A
After the bolt body 22 has been inserted through this, the ring 26 of the tension jig 23 is locked.

【0033】本実施の形態による連結ボルト装置21は
上述の如き構成を有するもので、以下、この連結ボルト
装置21を用いたセンタフレーム2とトラックビーム1
0との連結方法について説明する。
The connecting bolt device 21 according to the present embodiment has the above-described configuration. Hereinafter, the center frame 2 and the track beam 1 using the connecting bolt device 21 will be described.
A method of connecting to 0 will be described.

【0034】まず、図3に示すように、センタフレーム
2の側面板5とトラックビーム10の側面板13との間
に形成された狭隘な空間A内に、引張り治具23を取付
けたボルト本体22を挿入し、このボルト本体22をい
ったんトラックビーム10の下面板12上に載置する。
そして、引張り治具23のワイヤ25を撓ませつつ、リ
ング26をトラックビーム10のボルト挿通穴11Aか
らビーム取付フランジ7側のボルト挿通穴7Aへと挿通
し、ビーム取付フランジ7のボルト挿通穴7Aからリン
グ26を突出させる。続いて、ビーム取付フランジ7の
ボルト挿通穴7Aから突出したリング26を上向きに引
張ることにより、図4に示すように、ボルト本体22の
軸部22A先端を、トラックビーム10のボルト挿通穴
11Aを介してビーム取付フランジ7側のボルト挿通穴
7Aへと挿通する(ボルト挿通工程)。
First, as shown in FIG. 3, a bolt body having a tension jig 23 mounted in a narrow space A formed between the side plate 5 of the center frame 2 and the side plate 13 of the track beam 10. The bolt body 22 is inserted, and the bolt body 22 is once placed on the lower plate 12 of the track beam 10.
Then, while bending the wire 25 of the pulling jig 23, the ring 26 is inserted from the bolt insertion hole 11A of the track beam 10 into the bolt insertion hole 7A on the beam mounting flange 7 side, and the bolt insertion hole 7A of the beam mounting flange 7 is formed. The ring 26 is projected from the Subsequently, by pulling the ring 26 protruding from the bolt insertion hole 7A of the beam mounting flange 7 upward, the tip of the shaft portion 22A of the bolt body 22 is connected to the bolt insertion hole 11A of the track beam 10 as shown in FIG. Through the bolt mounting hole 7A on the beam mounting flange 7 side (bolt insertion step).

【0035】そして、1個目のナット16をリング26
側からワイヤ25に挿通し、ビーム取付フランジ7のボ
ルト挿通穴7Aから突出したボルト本体22の軸部22
Aに螺合させ、ボルト本体22がビーム取付フランジ7
のボルト挿通穴7A及びトラックビーム10のボルト挿
通穴11Aから抜出すのを防止する。
Then, the first nut 16 is connected to the ring 26
The shaft portion 22 of the bolt main body 22 that is inserted through the wire 25 from the side and protrudes from the bolt insertion hole 7A of the beam mounting flange 7
A, and the bolt body 22 is connected to the beam mounting flange 7.
Of the track beam 10 from the bolt insertion hole 7A and the track beam 10 from the bolt insertion hole 11A.

【0036】次に、ボルト本体22の頭部22Bを廻止
め部材14に係合させた状態で、スパナ(図示せず)等
を用いてナット16をボルト本体22の軸部22Aに締
込む。その後、2個目のナット16をリング26側から
ワイヤ25に挿通してボルト本体22の軸部22Aに締
込み、各ナット16に対する緩止めを行うことにより、
図1に示すように、センタフレーム2のビーム取付フラ
ンジ7にトラックビーム10を連結することができる
(連結工程)。
Next, with the head 22B of the bolt body 22 engaged with the rotation stopping member 14, the nut 16 is tightened to the shaft portion 22A of the bolt body 22 using a spanner (not shown) or the like. Thereafter, the second nut 16 is inserted into the wire 25 from the ring 26 side and tightened into the shaft portion 22A of the bolt main body 22, and the nuts 16 are loosened.
As shown in FIG. 1, the track beam 10 can be connected to the beam mounting flange 7 of the center frame 2 (connection step).

【0037】そして、引張り治具23のワイヤ25先端
側に取付けたリング26を、センタフレーム2に設けた
フック27に係合させることにより、引張り治具23を
整然とまとめておくことができる。
Then, by engaging the ring 26 attached to the tip end of the wire 25 of the pulling jig 23 with the hook 27 provided on the center frame 2, the pulling jig 23 can be organized in order.

【0038】かくして、本実施の形態による連結ボルト
装置21を用いてセンタフレーム2のビーム取付フラン
ジ7とトラックビーム10とを連結する場合には、セン
タフレーム2とトラックビーム10との間の狭隘な空間
A内に挿入したボルト本体22を、いったんトラックビ
ーム10の下面板12上に載置した状態で、ボルト本体
22に先立って引張り治具23のワイヤ25をトラック
ビーム10のボルト挿通穴11Aからビーム取付フラン
ジ7のボルト挿通穴7Aへと挿通し、ボルト挿通穴7A
から突出したワイヤ25の先端部(リング26)を上方
に引張ることにより、ボルト本体22を容易に各ボルト
挿通穴11A,7Aに挿通することができる。
Thus, when connecting the beam mounting flange 7 of the center frame 2 and the track beam 10 using the connecting bolt device 21 according to the present embodiment, the narrow space between the center frame 2 and the track beam 10 is required. With the bolt body 22 inserted into the space A once placed on the lower plate 12 of the track beam 10, the wire 25 of the pulling jig 23 is passed through the bolt insertion hole 11A of the track beam 10 prior to the bolt body 22. It is inserted into the bolt insertion hole 7A of the beam mounting flange 7, and the bolt insertion hole 7A
The bolt body 22 can be easily inserted into each of the bolt insertion holes 11A and 7A by pulling the distal end (ring 26) of the wire 25 protruding upward from the bolt insertion hole 11A.

【0039】このため、センタフレーム2とトラックビ
ーム10との間の狭隘な空間A内で、ボルト本体22を
用いてビーム取付フランジ7とトラックビーム10とを
連結するときの作業性を大幅に向上させることができ
る。また、例えば作業者が重量物であるボルト本体22
を保持したまま、トラックビーム10のボルト挿通穴1
1Aを手探りしつつ該ボルト挿通穴11A等にボルト本
体22を挿通する作業を不要にでき、作業者の負担を大
幅に軽減することができる。
Therefore, the workability when connecting the beam mounting flange 7 and the track beam 10 using the bolt body 22 in the narrow space A between the center frame 2 and the track beam 10 is greatly improved. Can be done. Further, for example, the bolt body 22 which is heavy
While holding the bolt, the bolt insertion hole 1 of the track beam 10
The operation of inserting the bolt main body 22 into the bolt insertion hole 11A or the like while groping the 1A can be eliminated, and the burden on the operator can be greatly reduced.

【0040】次に、図5ないし図7は本発明による第2
の実施の形態を示し、本実施の形態では、連結ボルトを
直立状態に保持するボルト保持具をトラックビームに設
けたことを特徴としている。なお、本実施の形態では、
上述した第1の実施の形態と同一の構成要素に同一の符
号を付し、その説明を省略するものとする。
Next, FIGS. 5 to 7 show a second embodiment according to the present invention.
The present embodiment is characterized in that a bolt holder for holding a connecting bolt in an upright state is provided on a track beam. In the present embodiment,
The same components as those in the above-described first embodiment are denoted by the same reference numerals, and description thereof will be omitted.

【0041】図5において、31は本実施の形態による
連結ボルト装置を示し、この連結ボルト装置31は、上
述した第1の実施の形態による連結ボルト装置21とほ
ぼ同様に、ボルト本体22と、ボルト本体22の先端面
に取付けられた引張り治具23とを有するものの、トラ
ックビーム10にボルト本体22を直立状態に保持する
後述のボルト保持具32を備えている点が異なってい
る。
In FIG. 5, reference numeral 31 denotes a connecting bolt device according to the present embodiment. The connecting bolt device 31 is substantially the same as the connecting bolt device 21 according to the first embodiment described above, and includes a bolt main body 22 and Although it has a pulling jig 23 attached to the tip end surface of the bolt main body 22, it is different in that the track beam 10 is provided with a bolt holder 32 described below for holding the bolt main body 22 in an upright state.

【0042】32はトラックビーム10の下面板12上
に固着されたボルト保持具で、このボルト保持具32
は、図5及び図6に示すように、4枚の板体32A,3
2B,32C,32Dから矩形の箱状体として形成さ
れ、ボルト挿通穴11Aの真下に配設されている。
Reference numeral 32 denotes a bolt holder fixed on the lower surface plate 12 of the track beam 10.
As shown in FIGS. 5 and 6, four plate bodies 32A, 3
It is formed as a rectangular box from 2B, 32C, and 32D, and is disposed directly below the bolt insertion hole 11A.

【0043】ここで、板体32Aには、ボルト本体22
の軸部22Aに対応した縦穴33Aと、ボルト本体22
の頭部22Bに対応した横穴33BとからなるT字状の
切欠き33が形成されており、この切欠き33を通じて
ボルト保持具32内にボルト本体22を直立状態で挿入
し、各板体32A,32B間にボルト本体22の頭部2
2Bを係合させることにより、ボルト本体22がボルト
挿通穴11Aに向けて直立状態に保持される構成となっ
ている。
Here, the bolt body 22 is attached to the plate 32A.
A vertical hole 33A corresponding to the shaft portion 22A of the
And a lateral hole 33B corresponding to the head 22B of the T-shape, a T-shaped notch 33 is formed, and the bolt body 22 is inserted upright into the bolt holder 32 through the notch 33, and each plate 32A , 32B between the head 2 of the bolt body 22
By engaging 2B, the bolt main body 22 is configured to be held upright toward the bolt insertion hole 11A.

【0044】本実施の形態による連結ボルト装置31は
上述の如き構成を有するもので、以下、この連結ボルト
装置31を用いたセンタフレーム2とトラックビーム1
0との連結方法について説明する。
The connecting bolt device 31 according to the present embodiment has the above-described configuration. Hereinafter, the center frame 2 and the track beam 1 using the connecting bolt device 31 will be described.
A method of connecting to 0 will be described.

【0045】まず、図7に示すように、トラックビーム
10に設けたボルト保持具32内に切欠き33を通じて
ボルト本体22を挿入し、このボルト本体22の頭部2
2Bをボルト保持具32の板体32A,32B間に係合
させることにより、ボルト本体22を直立状態に保持す
る。この状態で、ビーム取付フランジ7の下側にトラッ
クビーム10を配置することにより、ボルト本体22
は、ボルト保持具32によりトラックビーム10のボル
ト挿通穴11Aに向けて直立状態を保持する(ボルト保
持工程)。
First, as shown in FIG. 7, the bolt body 22 is inserted into the bolt holder 32 provided on the track beam 10 through the notch 33, and the head 2 of the bolt body 22 is inserted.
The bolt body 22 is held upright by engaging the bolt 2B between the plates 32A and 32B of the bolt holder 32. In this state, by disposing the track beam 10 below the beam mounting flange 7, the bolt body 22
Hold the upright state toward the bolt insertion hole 11A of the track beam 10 by the bolt holder 32 (bolt holding step).

【0046】次に、図8に示すように、センタフレーム
2の側面板5とトラックビーム10の側面板13との間
に形成された狭隘な空間A内に引張り治具23を挿入
し、引張り治具23のアイボルト24をボルト本体22
の軸部22A先端に取付けると共に、引張り治具23の
ワイヤ25を撓ませてリング26をトラックビーム10
のボルト挿通穴11Aからビーム取付フランジ7側のボ
ルト挿通穴7Aへと挿通する。そして、ビーム取付フラ
ンジ7のボルト挿通穴7Aから突出したリング26を上
方に引張ることにより、図9に示すように、ボルト本体
22の軸部22A先端を、トラックビーム10のボルト
挿通穴11Aを経由してビーム取付フランジ7側のボル
ト挿通穴7Aへと挿通する(ボルト挿通工程)。
Next, as shown in FIG. 8, a tension jig 23 is inserted into a narrow space A formed between the side plate 5 of the center frame 2 and the side plate 13 of the track beam 10, and the tension jig is pulled. Fix the eye bolt 24 of the jig 23 to the bolt body 22
At the tip of the shaft portion 22A, and bend the wire 25 of the pulling jig 23 to move the ring 26 to the track beam 10.
From the bolt insertion hole 11A into the bolt insertion hole 7A on the beam mounting flange 7 side. Then, by pulling the ring 26 projecting from the bolt insertion hole 7A of the beam mounting flange 7 upward, the tip of the shaft portion 22A of the bolt main body 22 passes through the bolt insertion hole 11A of the track beam 10 as shown in FIG. Then, it is inserted into the bolt insertion hole 7A on the beam mounting flange 7 side (bolt insertion step).

【0047】その後、ナット16,16をリング26側
からワイヤ25に挿通し、ビーム取付フランジ7のボル
ト挿通穴7Aから突出したボルト本体22の軸部22A
に螺合させ、これらナット16をスパナ(図示せず)等
を用いて軸部22Aに締込むことにより、第1の実施の
形態の場合と同様、図5に示すように、センタフレーム
2のビーム取付フランジ7にトラックビーム10を連結
することができる(連結工程)。
Thereafter, the nuts 16 and 16 are inserted into the wire 25 from the ring 26 side, and the shaft portion 22A of the bolt body 22 protruding from the bolt insertion hole 7A of the beam mounting flange 7.
, And these nuts 16 are screwed into the shaft portion 22A using a wrench (not shown) or the like, thereby, as shown in FIG. The track beam 10 can be connected to the beam mounting flange 7 (connection step).

【0048】そして、引張り治具23のリング26を、
センタフレーム2に設けたフック27に係合させること
により、引張り治具23を整然とまとめておくことがで
きる。
Then, the ring 26 of the tension jig 23 is
By engaging the hook 27 provided on the center frame 2, the pulling jigs 23 can be arranged neatly.

【0049】かくして、本実施の形態による連結ボルト
装置31を用いてセンタフレーム2とトラックビーム1
0とを連結する場合には、ボルト保持具32によって保
持されたボルト本体22が、トラックビーム10のボル
ト挿通穴11Aに向けて直立状態を保持する。このた
め、ボルト挿通工程において引張り治具23のワイヤ2
5を上方に引張ったときに、ボルト本体22の軸部22
A先端がトラックビーム10のボルト挿通穴11Aの周
囲等に衝合することがなく、ボルト本体22をボルト挿
通穴11Aからビーム取付フランジ7のボルト挿通穴7
Aへと挿通する作業を円滑に行うことができ、センタフ
レーム2とトラックビーム10とを連結するときの作業
性を一層向上させることができる。
Thus, the center frame 2 and the track beam 1 can be moved by using the connecting bolt device 31 according to the present embodiment.
In the case of connecting to the bolt 0, the bolt main body 22 held by the bolt holder 32 holds an upright state toward the bolt insertion hole 11A of the track beam 10. For this reason, in the bolt insertion step, the wire 2
5 is pulled upward, the shaft 22 of the bolt body 22
The tip A does not collide with the periphery of the bolt insertion hole 11A of the track beam 10 or the like, and the bolt main body 22 is moved from the bolt insertion hole 11A to the bolt insertion hole 7 of the beam mounting flange 7.
The work of inserting the center beam 2 into the center beam 2 and the track beam 10 can be further improved.

【0050】なお、上述した第2の実施の形態による連
結ボルト装置31を用いてセンタフレーム2とトラック
ビーム10とを連結する連結方法の場合、ボルト保持工
程において、トラックビーム10に設けたボルト保持具
32内にボルト本体22のみを保持した場合を例に挙げ
たが、本発明はこれに限るものではなく、予め引張り治
具23を取付けたボルト本体22をボルト保持具32内
に保持するようにしてもよい。
In the case of the connecting method for connecting the center frame 2 and the track beam 10 using the connecting bolt device 31 according to the second embodiment described above, the bolt holding step provided on the track beam 10 is performed in the bolt holding step. Although the case where only the bolt body 22 is held in the tool 32 has been described as an example, the present invention is not limited to this, and the bolt body 22 to which the pulling jig 23 is attached in advance is held in the bolt holder 32. It may be.

【0051】また、上述した各実施の形態では、連結工
程において、スパナを用いてボルト本体22にナット1
6を締込むものとして述べたが、本発明はこれに限ら
ず、例えば引張り治具23をボルト本体22から取外し
た状態でソケットレンチを用いてナット16を締込み、
その後、再び引張り治具23をボルト本体22の先端部
に取付けるようにしてもよい。
In each of the above-described embodiments, in the connecting step, the nut 1 is attached to the bolt body 22 using a spanner.
6, the present invention is not limited to this. For example, the nut 16 is tightened using a socket wrench with the tension jig 23 removed from the bolt body 22,
Thereafter, the tension jig 23 may be attached to the tip of the bolt body 22 again.

【0052】さらに、上述した各実施の形態では、油圧
クレーンの下部走行体を構成するトラックフレームを例
に挙げて説明したが、本発明はこれに限らず、例えば油
圧ショベル等の他の建設機械の下部走行体を構成するト
ラックフレームにも適用することができる。
Further, in each of the above-described embodiments, the truck frame constituting the lower traveling body of the hydraulic crane has been described as an example. However, the present invention is not limited to this, and the present invention is not limited to this. Can also be applied to the track frame constituting the lower traveling body of the present invention.

【0053】[0053]

【発明の効果】以上詳述した如く、請求項1の発明にか
かる建設機械用トラックフレームの連結方法によれば、
センタフレームのビーム取付部にトラックビームを連結
するときに、引張り治具を用いて連結ボルトをビーム取
付部側から引張ることにより、連結ボルトをトラックビ
ームのボルト挿通穴を介してビーム取付部のボルト挿通
穴へと容易に挿通することができる。これにより、例え
ばセンタフレームとトラックビームとの間に形成された
狭隘な空間内で、連結ボルトを用いてビーム取付部とト
ラックビームとを連結するときの作業性を大幅に向上さ
せることができる。また、例えば作業者が重量物である
ボルトを保持したまま、トラックビームのボルト挿通穴
を手探りしつつ該ボルト挿通穴にボルトを挿通する作業
を不要にでき、作業者の負担を大幅に軽減することがで
きる。
As described in detail above, according to the method for connecting truck frames for construction equipment according to the first aspect of the present invention,
When connecting the track beam to the beam mounting portion of the center frame, the connecting bolt is pulled from the beam mounting portion side using a tension jig, so that the connecting bolt is bolted to the beam mounting portion through the track beam bolt insertion hole. It can be easily inserted into the insertion hole. Thereby, for example, the workability when connecting the beam mounting portion and the track beam using the connection bolts in a narrow space formed between the center frame and the track beam can be greatly improved. Further, for example, while the worker holds the heavy bolt, it is not necessary to insert the bolt into the bolt insertion hole while groping for the bolt insertion hole of the track beam, thereby greatly reducing the burden on the operator. be able to.

【0054】また、請求項2の発明にかかる建設機械用
トラックフレームの連結方法によれば、連結ボルトをト
ラックビームに設けたボルト挿通穴に向けて直立状態に
保持した状態で、引張り治具を用いて連結ボルトをビー
ム取付部側から引張ることにより、連結ボルトをトラッ
クビームのボルト挿通穴周囲に衝合させることなく、こ
のボルト挿通穴を介してビーム取付部のボルト挿通穴へ
と容易に挿通することができる。
According to the method of connecting a truck frame for construction equipment according to the second aspect of the present invention, the pulling jig is held while the connecting bolt is held upright toward the bolt insertion hole provided in the track beam. By pulling the connecting bolt from the beam mounting part side, it can be easily inserted into the bolt mounting hole of the beam mounting part through this bolt mounting hole without abutting the connecting bolt around the bolt insertion hole of the track beam. can do.

【0055】そして、請求項3の発明にかかる建設機械
用トラックフレームの連結ボルト装置によれば、トラッ
クビームのボルト挿通穴とビーム取付部のボルト挿通穴
とに挿通されるボルト本体に引張り治具を取付ける構成
としたので、ボルト本体に取付けられた引張り治具の先
端側を、ボルト本体に先立ってトラックビームのボルト
挿通穴からビーム取付部のボルト挿通穴へと挿通し、ビ
ーム取付部のボルト挿通穴から突出した引張り治具の先
端側を引張ることにより、ボルト本体をトラックビーム
のボルト挿通穴からビーム取付部のボルト挿通穴へと確
実に挿通することができる。
According to the connecting bolt device for a truck frame for construction equipment according to the third aspect of the present invention, a tension jig is attached to a bolt main body inserted into a bolt inserting hole of a track beam and a bolt inserting hole of a beam mounting portion. The front end of the tension jig attached to the bolt body is inserted through the bolt insertion hole of the track beam into the bolt insertion hole of the beam attachment section prior to the bolt body. By pulling the distal end side of the pulling jig protruding from the insertion hole, the bolt body can be reliably inserted from the bolt insertion hole of the track beam to the bolt insertion hole of the beam mounting portion.

【0056】また、請求項4の発明によれば、連結ボル
ト装置の引張り治具を、ボルト本体のねじ穴に螺合する
ねじ軸と、このねじ軸に取付けられたワイヤとから構成
したので、ボルト本体に先立ってトラックビームのボル
ト挿通穴からビーム取付部のボルト挿通穴へとワイヤを
挿通する作業を、当該ワイヤを撓ませることによって容
易にかつ確実に行うことができる。
According to the fourth aspect of the present invention, the tension jig of the connecting bolt device is constituted by the screw shaft screwed into the screw hole of the bolt body and the wire attached to the screw shaft. The operation of inserting a wire from the bolt insertion hole of the track beam into the bolt insertion hole of the beam mounting portion prior to the bolt body can be easily and reliably performed by bending the wire.

【0057】また、請求項5の発明によれば、トラック
ビームにはボルト本体をボルト挿通穴に向けて直立状態
に保持するボルト保持具を設ける構成としたので、トラ
ックビームのボルト挿通穴からビーム取付部のボルト挿
通穴へと挿通した引張り治具を引張るときに、連結ボル
トがトラックビームのボルト挿通穴周囲に衝合するのを
防止でき、トラックビームのボルト挿通穴からビーム取
付部のボルト挿通穴へと連結ボルトを挿通する作業を確
実に行うことができる。
According to the fifth aspect of the present invention, the track beam is provided with the bolt holding member for holding the bolt body upright toward the bolt insertion hole, so that the beam is inserted from the bolt insertion hole of the track beam. When pulling the tension jig inserted into the bolt insertion hole of the mounting part, the connecting bolt can be prevented from abutting around the track beam bolt insertion hole, and the bolt insertion of the beam mounting part from the track beam bolt insertion hole can be prevented. The work of inserting the connecting bolt into the hole can be reliably performed.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の第1の実施の形態による連結ボルト装
置を、トラックビーム及びセンタフレームのビーム取付
フランジと共に示す縦断面図である。
FIG. 1 is a longitudinal sectional view showing a connecting bolt device according to a first embodiment of the present invention, together with a track beam and a beam mounting flange of a center frame.

【図2】図1中の連結ボルト装置をボルト本体から引張
り治具を取外した状態で示す正面図である。
FIG. 2 is a front view showing the connecting bolt device in FIG. 1 in a state where a tension jig is removed from a bolt main body.

【図3】第1の実施の形態による連結方法において引張
り治具をトラックビームのボルト挿通穴等に挿通した状
態を示す縦断面図である。
FIG. 3 is a longitudinal sectional view showing a state where a tension jig is inserted into a bolt insertion hole of a track beam or the like in the connection method according to the first embodiment.

【図4】第1の実施の形態による連結方法におけるボル
ト挿通工程を示す縦断面図である。
FIG. 4 is a longitudinal sectional view showing a bolt insertion step in the connection method according to the first embodiment.

【図5】本発明の第2の実施の形態による連結ボルト装
置を、トラックビーム及びセンタフレームのビーム取付
フランジと共に示す縦断面図である。
FIG. 5 is a longitudinal sectional view showing a connection bolt device according to a second embodiment of the present invention, together with a track beam and a beam mounting flange of a center frame.

【図6】図5中のボルト保持具を示す矢示VI−VI方向か
らみた横断面図である。
6 is a cross-sectional view of the bolt holder shown in FIG. 5 as viewed from the direction of arrows VI-VI.

【図7】第2の実施の形態による連結方法におけるボル
ト保持工程を示す縦断面図である。
FIG. 7 is a longitudinal sectional view showing a bolt holding step in a connection method according to a second embodiment.

【図8】第2の実施の形態による連結方法において引張
り治具をトラックビームのボルト挿通穴等に挿通した状
態を示す縦断面図である。
FIG. 8 is a longitudinal sectional view showing a state where a tension jig is inserted into a bolt insertion hole or the like of a track beam in the connection method according to the second embodiment.

【図9】第2の実施の形態による連結方法におけるボル
ト挿通工程を示す縦断面図である。
FIG. 9 is a longitudinal sectional view showing a bolt insertion step in the connection method according to the second embodiment.

【図10】従来技術による油圧クレーンのトラックフレ
ームを示す平面図である。
FIG. 10 is a plan view showing a track frame of a conventional hydraulic crane.

【図11】図10中のa部を拡大して示す拡大平面図で
ある。
FIG. 11 is an enlarged plan view showing a portion a in FIG. 10 in an enlarged manner.

【図12】図11中の矢示 XII−XII 方向からみたビー
ム取付フランジとトラックビームとの拡大縦断面図であ
る。
FIG. 12 is an enlarged vertical sectional view of a beam mounting flange and a track beam as viewed from the direction of arrows XII-XII in FIG. 11;

【図13】ビーム取付フランジとトラックビームとを分
割した状態を示す図11と同様位置の拡大平面図であ
る。
FIG. 13 is an enlarged plan view of the same position as FIG. 11 showing a state where a beam mounting flange and a track beam are divided.

【符号の説明】[Explanation of symbols]

1 トラックフレーム 2 センタフレーム 7 ビーム取付フランジ(ビーム取付部) 7A,7B,7C,7D ボルト挿通穴 10 トラックビーム 11A,11B,11C,11D ボルト挿通穴 21,31 連結ボルト装置 22 ボルト本体 22A 軸部 22B 頭部 22C ねじ穴 23 引張り治具 24 アイボルト(ねじ軸) 25 ワイヤ 32 ボルト保持具 DESCRIPTION OF SYMBOLS 1 Track frame 2 Center frame 7 Beam mounting flange (beam mounting part) 7A, 7B, 7C, 7D Bolt insertion hole 10 Track beam 11A, 11B, 11C, 11D Bolt insertion hole 21, 31 Connecting bolt device 22 Bolt body 22A Shaft 22B Head 22C Screw hole 23 Pulling jig 24 Eye bolt (screw shaft) 25 Wire 32 Bolt holder

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 ビーム取付部を有するセンタフレーム
と、前記センタフレームのビーム取付部に連結ボルトに
よって連結されるトラックビームとを備えた建設機械用
トラックフレームの連結方法において、 前記連結ボルトを引張り治具を用いて前記センタフレー
ムのビーム取付部側から引張り前記トラックビームに設
けたボルト挿通穴を介して前記センタフレームのビーム
取付部に設けたボルト挿通穴に挿通するボルト挿通工程
と、 前記ビーム取付部のボルト挿通穴から突出した前記連結
ボルトにナットを締込んで前記ビーム取付部にトラック
ビームを連結する連結工程とからなる建設機械用トラッ
クフレームの連結方法。
1. A method for connecting a track frame for construction machinery, comprising: a center frame having a beam mounting portion; and a track beam connected to the beam mounting portion of the center frame by a connecting bolt. A bolt insertion step of pulling the beam from the beam mounting portion side of the center frame using a tool and inserting the bolt into a bolt insertion hole provided in the beam mounting portion of the center frame through a bolt insertion hole provided in the track beam; Connecting a track beam to the beam mounting portion by tightening a nut to the connection bolt protruding from the bolt insertion hole of the section.
【請求項2】 ビーム取付部を有するセンタフレーム
と、前記センタフレームのビーム取付部に連結ボルトに
よって連結されるトラックビームとを備えた建設機械用
トラックフレームの連結方法において、 前記連結ボルトを前記トラックビームに設けたボルト挿
通穴に向けて直立状態に保持するボルト保持工程と、 前記連結ボルトを引張り治具を用いて前記センタフレー
ムのビーム取付部側から引張り前記トラックビームに設
けたボルト挿通穴を介して前記センタフレームのビーム
取付部に設けたボルト挿通穴に挿通するボルト挿通工程
と、 前記ビーム取付部のボルト挿通穴から突出した前記連結
ボルトにナットを締込んで前記ビーム取付部にトラック
ビームを連結する連結工程とからなる建設機械用トラッ
クフレームの連結方法。
2. A method for connecting a track frame for construction equipment, comprising: a center frame having a beam mounting portion; and a track beam connected to the beam mounting portion of the center frame by a connecting bolt. A bolt holding step of holding the bolt upright toward the bolt insertion hole provided in the beam, and pulling the connection bolt from the beam mounting portion side of the center frame using a pulling jig to remove the bolt insertion hole provided in the track beam. A bolt inserting step of inserting the bolt into the bolt mounting hole provided in the beam mounting portion of the center frame, and tightening a nut into the connecting bolt protruding from the bolt mounting hole of the beam mounting portion, thereby allowing a track beam to be inserted into the beam mounting portion. And a connecting step of connecting truck frames for a construction machine.
【請求項3】 ビーム取付部を有するセンタフレーム
と、前記センタフレームのビーム取付部に連結ボルトに
よって連結されるトラックビームとを備えた建設機械用
トラックフレームの連結ボルト装置であって、 前記トラックビームに設けられたボルト挿通穴とセンタ
フレームのビーム取付部に設けられたボルト挿通穴とに
挿通されるボルト本体と、基端側が前記ボルト本体に着
脱可能に取付けられ、自由端となった先端側が前記ボル
ト本体に先立って前記トラックビームのボルト挿通穴か
らビーム取付部のボルト挿通穴へと挿通される引張り治
具とから構成してなる建設機械用トラックフレームの連
結ボルト装置。
3. A connecting bolt device for a truck frame for construction equipment, comprising: a center frame having a beam mounting portion; and a track beam connected to the beam mounting portion of the center frame by a connecting bolt. The bolt body inserted into the bolt insertion hole provided in the bolt body and the bolt insertion hole provided in the beam mounting portion of the center frame, and the distal end side which is detachably attached to the base end side of the bolt main body and becomes a free end. A connecting frame device for a truck frame for a construction machine, comprising: a pulling jig inserted from a bolt insertion hole of the track beam into a bolt insertion hole of a beam mounting portion prior to the bolt body.
【請求項4】 前記ボルト本体は、外周側にねじが設け
られた軸部と、前記軸部の基端側に設けられた頭部と、
前記軸部の先端側に設けられたねじ穴とから構成し、前
記引張り治具は、前記ボルト本体のねじ穴に螺合するね
じ軸と、前記ねじ軸に取付けられたワイヤとから構成し
てなる請求項3に記載の建設機械用トラックフレームの
連結ボルト装置。
4. The bolt body includes a shaft portion provided with a screw on an outer peripheral side, a head portion provided on a base end side of the shaft portion,
A screw hole provided at a tip end side of the shaft portion, and the pulling jig includes a screw shaft screwed into the screw hole of the bolt body, and a wire attached to the screw shaft. The connecting bolt device for a truck frame for construction equipment according to claim 3.
【請求項5】 前記トラックビームには前記ボルト本体
をボルト挿通穴に向けて直立状態に保持するボルト保持
具を設ける構成としてなる請求項3に記載の建設機械用
トラックフレームの連結ボルト装置。
5. The connection bolt device for a truck frame for a construction machine according to claim 3, wherein the track beam is provided with a bolt holder for holding the bolt body upright toward the bolt insertion hole.
JP12961298A 1998-04-23 1998-04-23 Method for coupling truck frame for construction machine and its coupling bolt device Pending JPH11303138A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12961298A JPH11303138A (en) 1998-04-23 1998-04-23 Method for coupling truck frame for construction machine and its coupling bolt device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12961298A JPH11303138A (en) 1998-04-23 1998-04-23 Method for coupling truck frame for construction machine and its coupling bolt device

Publications (1)

Publication Number Publication Date
JPH11303138A true JPH11303138A (en) 1999-11-02

Family

ID=15013779

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12961298A Pending JPH11303138A (en) 1998-04-23 1998-04-23 Method for coupling truck frame for construction machine and its coupling bolt device

Country Status (1)

Country Link
JP (1) JPH11303138A (en)

Similar Documents

Publication Publication Date Title
JP2005324790A (en) Method of varying gage width of undercarriage for construction machine
JP2014532009A (en) Crawler excavator lower track
US4904151A (en) Loader lift arm structure
JP5328338B2 (en) Telescopic track frame
US5540006A (en) Pickup truck-mounted hydraulic tool carrier
US5570897A (en) Portable quick hitching device
JPH11303138A (en) Method for coupling truck frame for construction machine and its coupling bolt device
JP3873664B2 (en) Vehicle frame structure
JP3583533B2 (en) Electric construction machinery
JP3591931B2 (en) Working device that can be disassembled and assembled
US9284716B2 (en) Work vehicle
JP2519829Y2 (en) Construction structure of jack up device for construction machinery
US20240208434A1 (en) Front attachment system using a common interface for different attachments
JP3685233B2 (en) Ripper equipment
JP2004353398A (en) Revolving construction equipment
US20240206361A1 (en) Front attachment system using a common interface for different attachments
JP2003147804A (en) Construction machine
JP2002266311A (en) Rolling machine
WO2024009932A1 (en) Lower traveling body for construction machine
JP2008274663A (en) Method of transporting boom of work machine
WO2022064920A1 (en) Wheeled construction machine
JPS593009Y2 (en) Auxiliary wheel transport device for agricultural tractors
JP2004196131A (en) Mobile crane equipped with wheel and crawler on bogie
JPH0565776U (en) Mounting structure of undercarriage in tracked excavator
JP3126017B2 (en) Casing driver and coupling pin device