JPH11293834A - Method for constructing floor of building - Google Patents

Method for constructing floor of building

Info

Publication number
JPH11293834A
JPH11293834A JP11273498A JP11273498A JPH11293834A JP H11293834 A JPH11293834 A JP H11293834A JP 11273498 A JP11273498 A JP 11273498A JP 11273498 A JP11273498 A JP 11273498A JP H11293834 A JPH11293834 A JP H11293834A
Authority
JP
Japan
Prior art keywords
floor
girder
construction
structural frame
members
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP11273498A
Other languages
Japanese (ja)
Inventor
Nobutaka Kuwano
信敬 桑野
Yoshinobu Kurose
義宣 黒瀬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Metal Products Co Ltd
Original Assignee
Nippon Steel Metal Products Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Metal Products Co Ltd filed Critical Nippon Steel Metal Products Co Ltd
Priority to JP11273498A priority Critical patent/JPH11293834A/en
Publication of JPH11293834A publication Critical patent/JPH11293834A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To further enhance the efficiency of constructing a floor by use of field reassembling construction method. SOLUTION: Each girder comprises two girder component members 13 having laterally symmetrical cross-sectional shapes. The inside girder component member 13 is prepared for each of the girders on the four sides of one floor section. The four girder component members 13 are arranged in a rectangular shape on the ground and the adjacent girder component members 13 are coupled together by welding ties rods 14 thereto. Beams 15 are welded to the girder component members 13 and all of deck plates 1 of the floor section are put thereon to construct a floor structure frame 16. The floor structure frame 16 is hoisted to a construction floor by a crane and the ends of the girder component members 13 are joined to corresponding columns 4. The two girder component members 13 aligned at the boundary between the floor structure frames 16 installed on the adjacent floor sections serve as girders. Thus, the girders and most of floor members can be preassembled on the field, so that work done at high places is remarkably reduced and so that the number of times of crane hoisting is reduced. Since the rigidity of the floor structure frame is great, the need for any special lifting jigs is eliminated and a temporary reinforcing frame is also not necessary.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は,建築物の床を構
築する際に,床を構成する部材の一定部分を予め地上で
組み付けておき,これをクレーンで施工階に吊り上げて
敷設する,いわゆる地組工法と呼ばれる建築物の床構築
方法に関する。
BACKGROUND OF THE INVENTION The present invention relates to a so-called "construction of a floor of a building" in which certain parts of the floor are assembled in advance on the ground and then lifted up on a construction floor with a crane. The present invention relates to a floor construction method of a building called a terrain construction method.

【0002】従来より,建築物の鉄筋コンクリート床や
合成床板を構築する床構築方法として,予め地上で,4
本の柱で囲まれた矩形状の床区画内の複数のデッキプレ
ート(床板)を一体に組み付けておき,これをクレーン
で施工階(今デッキプレートを敷設しようとしている施
工中の階)に吊り上げて敷設する,いわゆる地組工法と
呼ばれる建築物の床構築方法が種々提案されている(特
公昭59−10453号等参照)。なお,デッキプレー
トは鉄筋コンクリート床の場合は単なるコンクリート型
枠であり,合成床板の場合は型枠兼強度部材である。従
来の一般的な地組工法では,地上で,図10に示すよう
にデッキプレート1と小梁2とを組み付けて大組床パネ
ル3を構成し,この大組床パネル3を,図示略の吊り治
具を用いてクレーンで施工階に吊り上げ,次いで,図1
1に示すように,柱4間に接合された例えばH形鋼等に
よる大梁5,6上に載置し,かつ,小梁2の両端を大梁
6に接合する。この場合,通常,主として小梁2の端部
を大梁6に接合するためのボルト締めや溶接作業を容易
に行えるように,デッキプレート幅方向の最端部(大梁
6側のもの)にあるデッキプレートは大組床パネル3か
ら除外しておく。したがって,この除外したデッキプレ
ートの部分は,大組床パネル3を施工階の大梁5,6に
乗せた時点で隙間7,8(ハッチングで示す)となる。
なお,9は前記の除外したデッキプレートを受けるため
のデッキ受けであり,柱4の近傍で大梁5,6間に溶接
固定している。
Conventionally, as a floor construction method for constructing a reinforced concrete floor or a composite floorboard of a building, a method of constructing a floor on the ground in advance has been proposed.
A plurality of deck plates (floor plates) in a rectangular floor section surrounded by pillars are assembled together, and this is lifted by a crane to the construction floor (floor under construction where the deck plates are being laid). There have been proposed various floor construction methods of buildings called so-called ground construction method (see Japanese Patent Publication No. 59-10453). The deck plate is a mere concrete formwork in the case of a reinforced concrete floor, and is a formwork and strength member in the case of a composite floorboard. In a conventional general ground construction method, a deck plate 1 and small beams 2 are assembled on the ground to form a large floor panel 3 as shown in FIG. 10, and this large floor panel 3 is not shown. Using a lifting jig, lift it up to the construction floor with a crane.
As shown in FIG. 1, the beam is placed on girders 5, 6 made of, for example, H-section steel or the like joined between the columns 4, and both ends of the girder 2 are joined to the girders 6. In this case, usually, the deck at the extreme end in the width direction of the deck plate (the one on the girder 6 side) so that bolting and welding work for joining the end of the girder 2 to the girder 6 can be easily performed. The plate is excluded from the large floor panel 3. Therefore, the part of the removed deck plate becomes gaps 7 and 8 (shown by hatching) when the large assembled floor panel 3 is placed on the girders 5 and 6 on the construction floor.
Reference numeral 9 denotes a deck receiver for receiving the excluded deck plate, which is welded and fixed between the beams 5 and 6 near the column 4.

【0003】また,図13に示した大組床パネル3’の
ように,デッキプレート1および小梁2に加えて,1本
の大梁6も地上で予め組み付けておく工法もある(特開
昭61−221436号等参照)。
There is also a construction method in which, in addition to a deck plate 1 and a small beam 2, a single beam 6 is pre-assembled on the ground like a large assembled panel 3 'shown in FIG. 61-221436, etc.).

【0004】[0004]

【発明が解決しようとする課題】上述の各地組工法は,
1つの床区画内の複数のデッキプレート1を予め地上で
組み付けておくものであるから,施工階で行うデッキプ
レート敷設等の高所作業が大幅に削減でき,施工能率が
向上するという長所がある。しかし,大組床パネル3,
3’において除外したデッキプレートは,施工階で敷設
する必要があり,高所作業として残ることになる。ま
た,デッキプレート敷設作業が地上と高所との2度手間
となり,能率的でない。また,鉄骨建方において,図1
0の施工法では全ての大梁を,また図13の施工法では
大半の大梁を,それぞれ単独でクレーン吊りして柱に取
り付ける必要があり,かつ,大組床パネル3,3’から
除外したデッキプレートも別個にクレーンで吊り上げる
必要があり,クレーン吊りの回数が多くなり,作業効率
が低下する。また,大組床パネル3,3’はいずれも,
周囲に枠を持つ構造ではないから,パネルとしての剛性
は弱く,クレーン吊りするためには,専用の吊り治具が
必要であることは勿論,場合により大組床パネル3,
3’に仮設の補強枠を取り付けることも必要となり,煩
雑でありかつ作業性が悪い。また,従来の地組工法は,
大梁についての鉄骨建方の施工能率向上には特に関係し
ないが,鉄骨建方自体の施工能率も向上させることがで
きれば,建築物全体としての施工性が一層向上するの
で,望ましい。
SUMMARY OF THE INVENTION
Since a plurality of deck plates 1 in one floor section are assembled on the ground in advance, there is an advantage that work at heights such as deck plate laying performed on the construction floor can be significantly reduced, and construction efficiency is improved. . However, the large floor panel 3,
The deck plate excluded in 3 'needs to be laid on the construction floor, and will remain as work at height. Also, the work of laying the deck plate is twice as troublesome on the ground and high places, which is not efficient. Fig. 1
In the construction method 0, all the girders were required. In the construction method shown in FIG. 13, most of the girder beams had to be hung by a crane independently and attached to the pillars. The plates also need to be lifted separately by a crane, which increases the number of times the crane is hung and reduces work efficiency. In addition, all of the large floor panels 3, 3 '
Since it is not a structure with a frame around it, the rigidity of the panel is weak, and in order to suspend the crane, a special hanging jig is necessary,
It is also necessary to attach a temporary reinforcing frame to 3 ', which is complicated and poor in workability. In addition, the conventional construction method
Although it is not particularly related to the improvement of the construction efficiency of the steel framing with respect to the girders, it is desirable if the construction efficiency of the steel framing itself can be improved, because the operability of the whole building is further improved.

【0005】本発明は上記従来の欠点を解消するために
なされたもので,柱で囲まれた1つの床区画の床構築に
際して,鉄骨建方も含めて地上における組み付け作業の
比重を大とすることが可能で,高所作業を一層削減する
ことができ,クレーン吊り回数を低減することができ,
専用の吊り治具を必要とせず,また,仮設の補強枠を取
り付けことも必要とせず,これらにより大梁の建方の施
工能率も含めて能率的に床を構築することのできる建築
物の床構築方法を提供することを目的とする。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned conventional drawbacks, and when constructing the floor of one floor section surrounded by pillars, the specific gravity of the assembling work on the ground including the steel frame is increased. Work at high places can be further reduced, and the number of times the crane is suspended can be reduced.
It does not require special hanging jigs, nor does it require the installation of temporary reinforcing frames, which allows the floor to be constructed efficiently, including the construction efficiency of girder construction. The purpose is to provide a construction method.

【0006】[0006]

【課題を解決するための手段】上記課題を解決する請求
項1の建築物の床構築方法は,柱間に接合される大梁材
を左右対称の断面形状をなす2つの大梁構成部材を用
い,地上において,4本の柱で区画される1つの矩形の
床区画を形成する4本の大梁材のそれぞれ内側の大梁構
成部材のみを前記床区画に対応して矩形に配置し,かつ
繋ぎ材により隣接する大梁構成部材どうしを相互に結合
して床構造枠を構成し,次いで,この床構造枠を施工階
に吊り上げ,次いで,この床構造枠の各大梁構成部材の
端部をそれぞれ対応する柱に接合し,次いで,前記床構
造枠上に床板を敷設することを特徴とする。
According to a first aspect of the present invention, there is provided a method of building a floor of a building, comprising: using two girder members having a symmetrical cross section in a girder material to be joined between pillars; On the ground, only the inner girder components of each of the four girder members forming one rectangular floor division defined by four pillars are arranged in a rectangular shape corresponding to the floor divisions, and are connected by connecting members. Adjacent girder components are connected to each other to form a floor structural frame, and then the floor structural frame is lifted to the construction floor, and then the ends of each girder component of the floor structural frame are assigned to a corresponding column. And then laying a floor board on the floor structural frame.

【0007】請求項2の建築物の床構築方法は,柱間に
接合される大梁材を左右対称の断面形状をなす2つの大
梁構成部材を用い,地上において,4本の柱で区画され
る1つの矩形の床区画を形成する4本の大梁材のそれぞ
れ内側の大梁構成部材のみを前記床区画に対応して矩形
に配置し,かつ繋ぎ材により隣接する大梁構成部材どう
しを相互に結合しかつ対向する大梁材間に小梁を渡し接
合して床構造枠を構成し,次いで,この床構造枠を施工
階に吊り上げ,次いで,この床構造枠の各大梁構成部材
の端部をそれぞれ対応する柱に接合し,次いで,前記床
構造枠上に床板を敷設することを特徴とする。
According to a second aspect of the present invention, there is provided a method of building a floor of a building, in which a girder material to be joined between the columns is divided into four columns on the ground by using two girder constituent members having a symmetrical sectional shape. Only the inner girder components of each of the four girder members forming one rectangular floor section are arranged in a rectangular shape corresponding to the floor section, and the adjacent girder components are connected to each other by a connecting member. And the beam structure is constructed by passing the beam between the opposing girders and forming a floor structure frame. Then, this floor structure frame is lifted to the construction floor, and then the ends of each girder component member of the floor structure frame correspond to each other. And then laying a floor plate on the floor structural frame.

【0008】請求項3の建築物の床構築方法は,柱間に
接合される大梁材を左右対称の断面形状をなす2つの大
梁構成部材を用い,地上において,4本の柱で区画され
る1つの矩形の床区画を形成する4本の大梁材のそれぞ
れ内側の大梁構成部材のみを前記床区画に対応して矩形
に配置し,かつ繋ぎ材により隣接する大梁構成部材どう
しを相互に結合しかつ対向する大梁材間に小梁を渡し接
合した後,床板を乗せて床構造枠を構成し,次いで,こ
の床構造枠を施工階に吊り上げ,次いで,この床構造枠
の各大梁構成部材の端部をそれぞれ対応する柱に接合す
ることを特徴とする。
According to a third aspect of the present invention, there is provided a method of constructing a floor of a building, in which a girder member to be joined between the columns is divided into four columns on the ground by using two girder constituent members having symmetrical cross-sectional shapes. Only the inner girder components of each of the four girder members forming one rectangular floor section are arranged in a rectangular shape corresponding to the floor section, and the adjacent girder components are connected to each other by a connecting member. And after passing the small beams between the opposing girders and joining them, the floor plate is put on to construct the floor structural frame, and then this floor structural frame is lifted to the construction floor, and then each of the girders of this floor structural frame It is characterized in that the ends are respectively joined to the corresponding columns.

【0009】請求項4は,請求項1,2または3におけ
る床板が鉄筋コンクリート床または合成床板を構築する
ためのデッキプレートであることを特徴とする。
A fourth aspect of the present invention is characterized in that the floor panel according to the first, second or third aspect is a deck plate for constructing a reinforced concrete floor or a composite floor panel.

【0010】請求項5は,請求項1,2または3におけ
る床板がコンクリートスラブであることを特徴とする。
A fifth aspect of the present invention is characterized in that the floor plate according to the first, second or third aspect is a concrete slab.

【0011】請求項6は,請求項1,2または3におけ
る大梁構成部材としてZ形鋼を用いるとともに,前記床
構造枠を,前記Z形鋼の上側のフランジ端縁が四辺の内
側にくるように配置して構成し,各床区画についてそれ
ぞれ,床構造枠を施工階に吊り上げ柱に接合した後,各
床区画境界の大梁材における対向する大梁構成部材間に
コンクリートを打設して大梁を形成することを特徴とす
る。
According to a sixth aspect of the present invention, a Z-section steel is used as the girder constituting member according to the first, second, or third aspect, and the floor structural frame is positioned such that an upper flange edge of the Z-section steel is positioned inside four sides. After the floor structure frame is connected to the lifting column on the construction floor for each floor section, concrete is cast between the opposing beam members on the girder at the boundary of each floor section. It is characterized by forming.

【0012】請求項7は,請求項1,2または3におけ
る大梁構成部材として溝形鋼を用いるとともに,前記床
構造枠を,前記溝形鋼のフランジ端縁が四辺の内側にく
るように配置して構成し,各床区画についてそれぞれ,
床構造枠を施工階に吊り上げ柱に接合した後,各床区画
境界の大梁材における背中合わせの一対の大梁構成部材
のウエブをボルトで接合して鋼製の大梁を形成すること
を特徴とする。
According to a seventh aspect of the present invention, a channel steel is used as a girder constituent member according to the first, second or third aspect, and the floor structural frame is disposed such that a flange edge of the channel steel is inside four sides. And for each floor section,
After the floor structural frame is joined to the lifting column on the construction floor, the webs of a pair of back girder components of the girders at each floor section boundary are joined by bolts to form a steel girder.

【0013】[0013]

【発明の実施の形態】以下,本発明の実施の形態を図1
〜9を参照して説明する。この実施例の建築物の床構築
方法は,デッキプレートを用いて鉄筋コンクリート床な
いし合成床板を構築する場合のものである。本発明で
は,柱に接合される大梁材を,左右対象の断面形状をな
す2つの大梁構成部材で構成する。なお,本発明におい
て,柱,大梁材,小梁は全て鋼製である。使用する床板
は,鋼製であるデッキプレート,またはコンクリートス
ラブ等であるが,実施例ではデッキプレートである。前
記の大梁材とは,鉄骨構造の建築物の場合は大梁自体で
あり,鉄骨鉄筋コンクリート構造(SRC造)の建築物
の場合は,大梁の一部の鋼材である。
FIG. 1 is a block diagram showing an embodiment of the present invention.
This will be described with reference to FIGS. The floor construction method for a building according to this embodiment is for a case where a reinforced concrete floor or a composite floor plate is constructed using a deck plate. In the present invention, the girder material to be joined to the column is constituted by two girder constituent members having a symmetrical cross-sectional shape. In the present invention, the columns, large beams and small beams are all made of steel. The floor plate to be used is a deck plate made of steel, a concrete slab, or the like. In the embodiment, the floor plate is a deck plate. The girder material is a girder itself in the case of a building having a steel structure, and is a part of the girder in the case of a building having a steel reinforced concrete structure (SRC construction).

【0014】図1〜図6に示した実施例はSRC造の場
合であり,大梁材11は,鉄骨鉄筋コンクリート梁であ
る大梁12(図6参照)の一部を構成する鋼材である。
実施例では,大梁材11を構成する大梁構成部材13と
してZ形鋼を用いている。
The embodiment shown in FIGS. 1 to 6 is a case of SRC construction, and the girder 11 is a steel material constituting a part of a girder 12 (see FIG. 6) which is a steel reinforced concrete beam.
In the embodiment, a Z beam is used as the girder constituent member 13 constituting the girder material 11.

【0015】施工手順を説明すると,4本の柱で区画さ
れる矩形の床区画に対応する四辺の大梁材1について,
それぞれ内側の大梁構成部材13を用意する。地上にお
いて,図1に示すように,前記の用意した4本の大梁構
成部材13を矩形に配置し,かつ,四隅において,隣接
する大梁構成部材13の端部近傍間に繋ぎ材14を配置
しボルト接合して,さらに,図示例では2本の小梁15
を対向する大梁構成部材13間に渡し溶接接合して,小
梁付き矩形枠組み17を作る。図2は図1を模式的に拡
大したA−A断面図である。図1に点線で示した柱4は
位置関係の説明のためである。次いで,当該床区画用の
デッキプレート1を全て図3に示すように,前記小梁付
き矩形枠組み17の上に乗せ,周囲の大梁構成部材13
および小梁15に鋲や栓溶接やスタッド溶接等で固定し
て,床構造枠16を構成する。繋ぎ材14は,隣接する
大梁構成部材13どうしを接合するとともに,端部側の
デッキプレート1を受けるデッキ受けともなる。図4
(イ)は図2の模式的に拡大したB−B断面図,図4
(ロ)は同C−C断面図である。このように,1つの床
区画内のほとんど全ての部材を予め地上で組み付ける。
The construction procedure will be described. For a four-sided giant beam 1 corresponding to a rectangular floor section divided by four pillars,
An inner girder constituent member 13 is prepared. On the ground, as shown in FIG. 1, the four girder components 13 prepared as described above are arranged in a rectangle, and the connecting members 14 are arranged at the four corners between the vicinity of the ends of the adjacent girder components 13. Bolted, and in the example shown, two small beams 15
Is welded between the opposed large beam constituent members 13 to form a rectangular frame 17 with small beams. FIG. 2 is an enlarged cross-sectional view of FIG. Pillars 4 indicated by dotted lines in FIG. 1 are for explaining the positional relationship. Next, as shown in FIG. 3, all the deck plates 1 for the floor section are placed on the rectangular frame 17 with the small beams, and the surrounding large beam constituent members 13 are placed.
Further, the floor structure frame 16 is fixed to the small beam 15 by studs, plug welding, stud welding, or the like. The connecting member 14 joins the adjacent girder constituent members 13 and also serves as a deck receiver for receiving the deck plate 1 on the end side. FIG.
(A) is a schematic enlarged cross-sectional view taken along the line BB of FIG. 2, FIG.
(B) is a sectional view taken along the line CC. In this way, almost all members in one floor section are assembled in advance on the ground.

【0016】前記床構造枠16をクレーンで吊り上げ
て,当該施工階(今デッキプレートを敷設しようとして
いる施工中の階)における当該床区画に搬送し,各大梁
構成部材13の端部を図示例では角形鋼管の柱4に接合
する。図5は当該床区画(図示されている4本の柱4で
囲まれる区域)について床構造枠16を柱4に接合した
状態である。当該床区画の上側および右側は引き続き施
工すべき床区画である。図示は省略するが,柱4側には
大梁材11を受ける大梁受け材を予め溶接固定してお
き,この大梁受け材に大梁構成部材13の端部を継ぎ手
プレートを添えてボルト接合する。当該施工階の全ての
床区画について同様に床構造枠16を柱4に接合して梁
材の鉄骨建方およびデッキプレート1の敷設を終えた
後,床構造枠16上に配筋し,コンクリートを打設する
と,図6に示すように,鉄筋コンクリート床ないし合成
床板が構築されるとともに,大梁材11の内部(すなわ
ち大梁構成部材13である対向する2つのZ形鋼間の空
間)に打設されたコンクリートにより,鉄骨鉄筋コンク
リート梁である大梁12が構築される。こうして,対向
する2つの大梁構成部材13からなる大梁材11は,型
枠として機能すると同時に,強度部材として機能する。
なお,図6では大梁構成部材13にコンクリートと結合
させるためのスタッドボルト18を溶接固定したものと
して図示している(ただし,この場合には,図1の組み
付けを行う前の大梁構成部材13に既に溶接固定してお
く)。また,対向するZ形鋼(大梁構成部材13)の下
側のフランジ端縁13b間は,必要があればフラットバ
ー等を突き合わせ部分に添わせ溶接固定(図示せず)す
るとよい。
The floor structure frame 16 is lifted by a crane and transported to the floor section on the construction floor (floor under construction where the deck plate is to be laid), and the end of each girder component 13 is shown in the drawing. Then, it joins to the column 4 of a square steel pipe. FIG. 5 shows a state in which the floor structural frame 16 is joined to the column 4 for the floor section (the area surrounded by the four columns 4 shown). The upper and right sides of the floor section are floor sections to be subsequently constructed. Although not shown, a girder receiving member for receiving the girder member 11 is fixed to the column 4 side in advance by welding, and the end of the girder constituent member 13 is bolted to the girder receiving member with a joint plate attached thereto. The floor structure frame 16 is similarly joined to the pillars 4 for all the floor sections on the construction floor, and after completing the construction of the steel frame of the beam material and the laying of the deck plate 1, the reinforcement is arranged on the floor structure frame 16 and the concrete is laid. 6, a reinforced concrete floor or a composite floor plate is constructed as shown in FIG. 6, and the casting is carried out inside the girders 11 (that is, in the space between two opposite Z-shaped steels which are the girders constituting members 13). The girders 12, which are steel-framed reinforced concrete beams, are constructed from the concrete thus obtained. In this way, the girder material 11 composed of the two opposing girder constituent members 13 functions not only as a mold but also as a strength member.
FIG. 6 shows that the stud bolt 18 for joining with the concrete is welded and fixed to the girder constituent member 13 (however, in this case, the girder constituent member 13 before the assembly in FIG. 1 is attached). It has already been fixed by welding). If necessary, a flat bar or the like may be attached to the butt portion and fixed by welding (not shown) between the lower flange edges 13b on the lower side of the Z-shaped steel member (girder component 13).

【0017】図7に他の実施例を示す。この実施例は,
大梁材21を構成する大梁構成部材23として溝形鋼を
用いている。この実施例は鉄骨構造の場合であり,大梁
材21自体が大梁となる。この大梁材21は,溝形鋼
(大梁構成部材23)のウエブを背中合わせしてH形状
にしボルト・ナット20でウエブを接合して構成され
る。なお,この床構造枠26を作る手順は,および施工
階に設置する手順は,図1〜図6で説明した実施例の場
合と基本的に同じである。
FIG. 7 shows another embodiment. This embodiment is
A channel steel is used as the girder constituent member 23 constituting the girder material 21. This embodiment is a case of a steel frame structure, and the girder 21 itself becomes a girder. This girder member 21 is formed by joining a web of channel steel (girder component member 23) back to back to form an H shape, and joining the web with bolts and nuts 20. The procedure for making the floor structure frame 26 and the procedure for installing it on the construction floor are basically the same as those in the embodiment described with reference to FIGS.

【0018】なお,大梁構成部材としてZ形鋼を用いた
場合,図8に示すように大梁構成部材13を,図1〜図
6で説明した実施例とは逆の向きに,すなわち,大梁材
11における対向する大梁構成部材13の上側のフラン
ジ端縁13aがそれぞれ内側に向き,下側のフランジ端
縁13bが外側を向く配置とすることも可能である。ま
た,大梁構成部材として溝形鋼を用いた場合,図9に示
すように大梁構成部材23を,図7で説明した実施例と
は逆の向きに,すなわち,フランジ端縁23aがそれぞ
れ内側に向いて角パイプを形成するように用いるこもで
きる。なお,図8,図9の実施例は,大梁材の内部にコ
ンクリートを打設できないから,通常は,鉄骨構造(鉄
骨梁)とする場合である。要するに,大梁材が左右対象
の断面形状をなす2つの鋼材(大梁構成部材)からなる
ものであればよい。
When a Z-section steel is used as the girder component, as shown in FIG. 8, the girder component 13 is turned in the opposite direction to the embodiment described with reference to FIGS. It is also possible to arrange the upper flange edge 13a of the opposing large beam constituent member 13 in 11 to face inward and the lower flange edge 13b to face outward. When a channel steel is used as a girder component, the girder component 23 is turned in the opposite direction to that of the embodiment described with reference to FIG. It can also be used to form a square pipe facing away. In the embodiment of FIGS. 8 and 9, concrete cannot be poured into the inside of the girder, so that the steel beam structure (steel beam) is usually used. In short, it is only necessary that the girder member be composed of two steel members (girder girder members) having a symmetrical cross-sectional shape.

【0019】また,上述の実施例では,予め地上でデッ
キプレートを組み付けているが,地上では,デッキプレ
ートを組み付けずに,大梁構成部材13と小梁15と繋
ぎ材14とからなる小梁付き矩形枠組み17のみで床構
造枠を構成し,これを施工階にクレーンで吊り上げ柱4
に接合した後,デッキプレート1をこの床構造枠(小梁
付き矩形枠組み)上に敷設することも可能である。さら
に,地上では,デッキプレートおよび小梁のいずれも組
み付けずに,大梁構成部材13と繋ぎ材14とからなる
矩形枠組みのみで床構造枠を構成し,これを施工階にク
レーンで吊り上げ柱4に接合した後,小梁15を接合し
かつデッキプレート1を敷設することも可能である。な
お,上述の実施例では,対象とする床区画に小梁を有す
る場合であるが,床区画内に小梁を用いない場合は,地
上で組みつける床構造枠は当然,梁部材として大梁構成
部材を持つのみで小梁は持たない構造となる。
In the above-described embodiment, the deck plate is previously assembled on the ground. However, on the ground, a small beam composed of the girder constituent member 13, the small beam 15, and the connecting member 14 is provided without installing the deck plate. A floor frame is composed of only the rectangular frame 17, and this is lifted by a crane on the construction floor.
After joining, the deck plate 1 can be laid on this floor structural frame (rectangular frame with small beams). Further, on the ground, the floor structure frame is composed of only the rectangular frame composed of the girder constituent members 13 and the connecting members 14 without assembling any of the deck plate and the small beams, and the floor structural frame is lifted on the construction floor by the crane 4 on the construction floor. After joining, it is also possible to join the beams 15 and to lay the deck plate 1. In the above embodiment, the target floor section has small beams. However, when no small beams are used in the floor section, the floor structural frame to be assembled on the ground is naturally a large beam structure as a beam member. The structure has only members and no beams.

【0020】さらに,本発明はデッキプレートを利用す
る床構築に適用して好適であるが,デッキプレートの代
わりにコンクリートスラブ等を用いる場合にも,本発明
の適用は可能である。
Further, the present invention is suitable for application to a floor construction using a deck plate. However, the present invention is also applicable when a concrete slab or the like is used instead of the deck plate.

【0021】[0021]

【発明の効果】本発明によれば,大梁材を左右対象の断
面形状を持つ2つの大梁構成部材から構成したの,全て
の大梁材を地上で組み付けることが可能となり,大梁の
鉄骨建方の施工能率を向上させることができる。そし
て,床を構成する部材のうち,コンクリートを除く殆ど
の部材を地上で組み付けることが可能となるので,高所
作業が著しく削減される。また,殆どの部材を地上で組
み付けることができるので,クレーン吊りの回数は大幅
に削減され,作業性が大幅に向上する。
According to the present invention, the girder is composed of two girder components having right and left symmetrical cross-sectional shapes. However, all the girder can be assembled on the ground, and the girder steel construction method can be used. Construction efficiency can be improved. And, among the members constituting the floor, most members except concrete can be assembled on the ground, so that work at heights is significantly reduced. Also, since most of the members can be assembled on the ground, the number of times of crane suspension is greatly reduced, and workability is greatly improved.

【0022】また,地上で床構造枠を組み付ける際,一
部のデッキプレートを床構造枠から除外することなく,
全てのデッキプレートを組み付けることができるので,
デッキプレート敷設作業が地上と高所との2度手間とな
る問題は発生せず,施工性が良好である。
Further, when assembling the floor structural frame on the ground, some deck plates are not excluded from the floor structural frame,
Since all deck plates can be assembled,
There is no problem that the work of laying the deck plate has to be done twice on the ground and high places, and the workability is good.

【0023】また,床構造枠は周囲に大梁構成部材を枠
として持つ構造であり,剛性が十分大なので,吊り治具
を用いずにそのままクレーン吊りすることが可能であ
り,また,仮設の補強枠を仮に取り付けることも当然不
要であり,施工が著しく簡略化され,作業性が向上す
る。
The floor structural frame has a structure in which a girder component is formed as a frame around the frame, and has a sufficiently high rigidity, so that it can be suspended by a crane without using a suspending jig. It is naturally unnecessary to temporarily attach the frame, which greatly simplifies construction and improves workability.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施例の建築物の床構築方法を説明
する図であり,地上で組み付ける床構造枠の,デッキプ
レート(床板)を乗せる前の小梁付き矩形枠組みの平面
図である。
BRIEF DESCRIPTION OF DRAWINGS FIG. 1 is a diagram illustrating a method of building a floor of a building according to one embodiment of the present invention, and is a plan view of a rectangular frame with small beams before a deck plate (floor plate) is placed on a floor structural frame to be assembled on the ground. is there.

【図2】図1における模式的に拡大したA−A断面図で
ある。
FIG. 2 is an AA cross-sectional view schematically enlarged in FIG.

【図3】図1の小梁付き矩形枠組みにデッキプレートを
乗せて構成した床構造枠の平面図である。
FIG. 3 is a plan view of a floor structure frame configured by placing a deck plate on the rectangular frame with small beams in FIG. 1;

【図4】(イ)は図3における模式的に拡大したB−B
断面図,(ロ)は同C−C断面図である。
FIG. 4A is a schematic enlarged view of BB in FIG.
FIG. 2B is a cross-sectional view of FIG.

【図5】本発明の建築物の床構築方法を説明するもの
で,図3の床構造枠を施工階の当該床区画にクレーンで
吊り上げ,柱に接合した段階の平面図である。
FIG. 5 is a plan view illustrating a method for constructing a floor of a building according to the present invention, in which the floor structural frame of FIG. 3 is lifted to the floor section on a construction floor by a crane and joined to a pillar.

【図6】図5の段階ののち床構造枠上にコンクリートを
打設した状態を示すもので,図5のD−D断面図に対応
する断面図(ただしコンクリート打設後)である。
FIG. 6 is a cross-sectional view corresponding to the DD cross-sectional view of FIG. 5 (after the concrete has been cast), showing a state where concrete is cast on the floor structural frame after the stage of FIG. 5;

【図7】大梁構成部材として溝形鋼を用いて大梁材を構
成した場合の実施例を示すもので,図5のD−D断面図
に対応する図である。
FIG. 7 is a view showing an embodiment in which a girder member is formed by using a channel steel as a girder constituent member, and is a view corresponding to a cross-sectional view taken along line DD of FIG.

【図8】大梁材を構成する大梁構成部材であるZ形鋼
を,図6と逆向きに用いた実施例を説明する図である。
FIG. 8 is a view for explaining an embodiment in which a Z-beam, which is a girder constituent member of the girder material, is used in a direction opposite to that of FIG.

【図9】大梁材を構成する大梁構成部材である溝形鋼
を,図7と逆向きに用いた実施例を説明する図である。
FIG. 9 is a view for explaining an embodiment in which a channel steel, which is a girder constituent member constituting a girder member, is used in a direction opposite to that of FIG.

【図10】従来の建築物の床構築方法を説明するもの
で,地上で組み付けた大組床パネルの平面図である。
FIG. 10 is a plan view of a large floor panel assembled on the ground, for explaining a conventional floor building method of a building.

【図11】従来の建築物の床構築方法を説明するもの
で,図10の大組床パネルを施工階にクレーンで吊り上
げ,柱に接合した段階の平面図である。
FIG. 11 is a plan view illustrating a conventional method of constructing a floor of a building, in which a large assembled floor panel of FIG. 10 is lifted to a construction floor by a crane and joined to a pillar.

【図12】図11における拡大したE−E断面図であ
る。
FIG. 12 is an enlarged sectional view taken along the line EE in FIG. 11;

【符号の説明】[Explanation of symbols]

1 デッキプレート(床板) 4 柱 11 大梁材 21 大梁材(大梁でもある) 12 大梁 13,23 大梁構成部材 14 繋ぎ材 15 小梁 16 床構造枠 17 小梁付き矩形枠組み DESCRIPTION OF SYMBOLS 1 Deck plate (floor board) 4 pillars 11 girders 21 girders (also girders) 12 girders 13, 23 girders 14 connecting members 15 girder 16 floor structure frame 17 rectangular frame with girder

─────────────────────────────────────────────────────
────────────────────────────────────────────────── ───

【手続補正書】[Procedure amendment]

【提出日】平成10年6月29日[Submission date] June 29, 1998

【手続補正1】[Procedure amendment 1]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】図面の簡単な説明[Correction target item name] Brief description of drawings

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施例の建築物の床構築方法を説明
する図であり,地上で組み付ける床構造枠の,デッキプ
レート(床板)を乗せる前の小梁付き矩形枠組みの平面
図である。
BRIEF DESCRIPTION OF DRAWINGS FIG. 1 is a diagram illustrating a method of building a floor of a building according to one embodiment of the present invention, and is a plan view of a rectangular frame with small beams before a deck plate (floor plate) is placed on a floor structural frame to be assembled on the ground. is there.

【図2】図1における模式的に拡大したA−A断面図で
ある。
FIG. 2 is an AA cross-sectional view schematically enlarged in FIG.

【図3】図1の小梁付き矩形枠組みにデッキプレートを
乗せて構成した床構造枠の平面図である。
FIG. 3 is a plan view of a floor structure frame configured by placing a deck plate on the rectangular frame with small beams in FIG. 1;

【図4】(イ)は図3における模式的に拡大したB−B
断面図,(ロ)は同C−C断面図である。
FIG. 4A is a schematic enlarged view of BB in FIG.
FIG. 2B is a cross-sectional view of FIG.

【図5】本発明の建築物の床構築方法を説明するもの
で,図3の床構造枠を施工階の当該床区画にクレーンで
吊り上げ,柱に接合した段階の平面図である。
FIG. 5 is a plan view illustrating a method for constructing a floor of a building according to the present invention, in which the floor structural frame of FIG. 3 is lifted to the floor section on a construction floor by a crane and joined to a pillar.

【図6】図5の段階ののち床構造枠上にコンクリートを
打設した状態を示すもので,図5のD−D断面図に対応
する断面図(ただしコンクリート打設後)である。
FIG. 6 is a cross-sectional view corresponding to the DD cross-sectional view of FIG. 5 (after the concrete has been cast), showing a state where concrete is cast on the floor structural frame after the stage of FIG. 5;

【図7】大梁構成部材として溝形鋼を用いて大梁材を構
成した場合の実施例を示すもので,図5のD−D断面図
に対応する図である。
FIG. 7 is a view showing an embodiment in which a girder member is formed by using a channel steel as a girder constituent member, and is a view corresponding to a cross-sectional view taken along line DD of FIG.

【図8】大梁材を構成する大梁構成部材であるZ形鋼
を,図6と逆向きに用いた実施例を説明する図である。
FIG. 8 is a view for explaining an embodiment in which a Z-beam, which is a girder constituent member of the girder material, is used in a direction opposite to that of FIG.

【図9】大梁材を構成する大梁構成部材である溝形鋼
を,図7と逆向きに用いた実施例を説明する図である。
FIG. 9 is a view for explaining an embodiment in which a channel steel, which is a girder constituent member constituting a girder member, is used in a direction opposite to that of FIG.

【図10】従来の建築物の床構築方法を説明するもの
で,地上で組み付けた大組床パネルの平面図である。
FIG. 10 is a plan view of a large floor panel assembled on the ground, for explaining a conventional floor building method of a building.

【図11】従来の建築物の床構築方法を説明するもの
で,図10の大組床パネルを施工階にクレーンで吊り上
げ,柱に接合した段階の平面図である。
FIG. 11 is a plan view illustrating a conventional method of constructing a floor of a building, in which a large assembled floor panel of FIG. 10 is lifted to a construction floor by a crane and joined to a pillar.

【図12】図11における拡大したE−E断面図であ
る。
FIG. 12 is an enlarged sectional view taken along the line EE in FIG. 11;

【図13】従来の他の建築物の床構築方法を説明するもFIG. 13 illustrates another conventional floor construction method of a building.
ので、地上で組み付けた大組床パネルの平面図である。Therefore, it is a plan view of a large assembled floor panel assembled on the ground.

【符号の説明】 1 デッキプレート(床板) 4 柱 11 大梁材 21 大梁材(大梁でもある) 12 大梁 13,23 大梁構成部材 14 繋ぎ材 15 小梁 16 床構造枠 17 小梁付き矩形枠組み[Description of Signs] 1 Deck plate (floor plate) 4 Pillar 11 Large beam material 21 Large beam material (also a large beam) 12 Large beam 13,23 Large beam component 14 Connecting material 15 Small beam 16 Floor structure frame 17 Rectangular frame with small beam

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 柱間に接合される大梁材を左右対称の断
面形状をなす2つの大梁構成部材を用い,地上におい
て,4本の柱で区画される1つの矩形の床区画を形成す
る4本の大梁材のそれぞれ内側の大梁構成部材のみを前
記床区画に対応して矩形に配置し,かつ繋ぎ材により隣
接する大梁構成部材どうしを相互に結合して床構造枠を
構成し,次いで,この床構造枠を施工階に吊り上げ,次
いで,この床構造枠の各大梁構成部材の端部をそれぞれ
対応する柱に接合し,次いで,前記床構造枠上に床板を
敷設することを特徴とする建築物の床構築方法。
1. A girder material to be joined between columns is formed by using two girder components having symmetrical cross-sectional shapes to form one rectangular floor section divided by four columns on the ground. Only the girder components inside each of the girder members of the book are arranged in a rectangular shape corresponding to the floor section, and the adjacent girder components are connected to each other by a connecting member to form a floor structural frame. The floor structural frame is lifted to the construction floor, and then the ends of each girder structural member of the floor structural frame are joined to the corresponding columns, respectively, and a floor board is laid on the floor structural frame. Building floor construction method.
【請求項2】 柱間に接合される大梁材を左右対称の断
面形状をなす2つの大梁構成部材を用い,地上におい
て,4本の柱で区画される1つの矩形の床区画を形成す
る4本の大梁材のそれぞれ内側の大梁構成部材のみを前
記床区画に対応して矩形に配置し,かつ繋ぎ材により隣
接する大梁構成部材どうしを相互に結合しかつ対向する
大梁材間に小梁を渡し接合して床構造枠を構成し,次い
で,この床構造枠を施工階に吊り上げ,次いで,この床
構造枠の各大梁構成部材の端部をそれぞれ対応する柱に
接合し,次いで,前記床構造枠上に床板を敷設すること
を特徴とする建築物の床構築方法。
2. A method of forming a rectangular floor section divided by four columns on the ground using two large beam structural members having a bilaterally symmetrical cross-sectional shape of a large beam material joined between columns. Only the inner girder components of each of the girder members are arranged in a rectangular shape corresponding to the floor section, and adjacent girder components are connected to each other by a connecting member, and small beams are placed between the opposing girder members. Cross-connect to form a floor structural frame, then lift this floor structural frame to the construction floor, then join the ends of each girder component of the floor structural frame to a corresponding column, and then A floor building method for a building, comprising laying a floor plate on a structural frame.
【請求項3】 柱間に接合される大梁材を左右対称の断
面形状をなす2つの大梁構成部材を用い,地上におい
て,4本の柱で区画される1つの矩形の床区画を形成す
る4本の大梁材のそれぞれ内側の大梁構成部材のみを前
記床区画に対応して矩形に配置し,かつ繋ぎ材により隣
接する大梁構成部材どうしを相互に結合しかつ対向する
大梁材間に小梁を渡し接合した後,床板を乗せて床構造
枠を構成し,次いで,この床構造枠を施工階に吊り上
げ,次いで,この床構造枠の各大梁構成部材の端部をそ
れぞれ対応する柱に接合することを特徴とする建築物の
床構築方法。
3. A rectangular floor section defined by four pillars on the ground is formed by using two girder constituent members having a symmetrical cross-sectional shape in a girder material joined between the pillars. Only the inner girder components of each of the girder members are arranged in a rectangular shape corresponding to the floor section, and adjacent girder components are connected to each other by a connecting member, and small beams are placed between the opposing girder members. After cross-joining, the floor structure is put on the floor plate to construct the floor structure frame, then this floor structure frame is lifted to the construction floor, and then the ends of each girder component of the floor structure frame are connected to the corresponding columns, respectively. A floor building method for a building, characterized in that:
【請求項4】 前記床板が鉄筋コンクリート床または合
成床板を構築するためのデッキプレートであることを特
徴とする請求項1,2または3記載の建築物の床構築方
法。
4. The floor construction method according to claim 1, wherein said floor panel is a deck plate for constructing a reinforced concrete floor or a composite floor panel.
【請求項5】 前記床板がコンクリートスラブであるこ
とを特徴とする請求項1,2または3記載の建築物の床
構築方法。
5. The method according to claim 1, wherein said floor plate is a concrete slab.
【請求項6】 前記大梁構成部材としてZ形鋼を用いる
とともに,前記床構造枠を,前記Z形鋼の上側のフラン
ジ端縁が四辺の内側にくるように配置して構成し,各床
区画についてそれぞれ,床構造枠を施工階に吊り上げ柱
に接合した後,各床区画境界の大梁材における対向する
大梁構成部材間にコンクリートを打設して大梁を形成す
ることを特徴とする請求項1,2または3記載の建築物
の床構築方法。
6. A Z-section steel is used as the girder component, and the floor structural frame is arranged such that an upper flange edge of the Z-section steel is located inside four sides. 2. The method according to claim 1, wherein after the floor structural frame is joined to the lifting column on the construction floor, concrete is poured between opposing large beam components of the large beam at the boundary of each floor section to form a large beam. , 2 or 3 floor construction method of a building.
【請求項7】 前記大梁構成部材として溝形鋼を用いる
とともに,前記床構造枠を,前記溝形鋼のフランジ端縁
が四辺の内側にくるように配置して構成し,各床区画に
ついてそれぞれ,床構造枠を施工階に吊り上げ柱に接合
した後,各床区画境界の大梁材における背中合わせの一
対の大梁構成部材のウエブをボルトで接合して鋼製の大
梁を形成することを特徴とする請求項1,2または3記
載の建築物の床構築方法。
7. A channel steel is used as said girder structural member, and said floor structural frame is arranged and arranged such that a flange edge of said channel steel is inside four sides. After the floor structural frame is joined to the lifting columns on the construction floor, the webs of a pair of back-to-back girders of the girders at each floor section boundary are joined by bolts to form steel girders. The floor construction method for a building according to claim 1, 2, or 3.
JP11273498A 1998-04-08 1998-04-08 Method for constructing floor of building Withdrawn JPH11293834A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11273498A JPH11293834A (en) 1998-04-08 1998-04-08 Method for constructing floor of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11273498A JPH11293834A (en) 1998-04-08 1998-04-08 Method for constructing floor of building

Publications (1)

Publication Number Publication Date
JPH11293834A true JPH11293834A (en) 1999-10-26

Family

ID=14594219

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11273498A Withdrawn JPH11293834A (en) 1998-04-08 1998-04-08 Method for constructing floor of building

Country Status (1)

Country Link
JP (1) JPH11293834A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001193212A (en) * 2000-01-13 2001-07-17 Sanyo Industries Ltd Cradling receiver for ceiling foundation material
WO2008081929A1 (en) 2007-01-04 2008-07-10 Nippon Steel Corporation Floor structure
JP2012012836A (en) * 2010-06-30 2012-01-19 Shimizu Corp Construction method of floor unit for stock on construction story
CN106703073A (en) * 2016-12-30 2017-05-24 中国建筑第八工程局有限公司 Supporting-free steel beam foundation of super-high-rise construction elevator and construction method of supporting-free steel beam foundation

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001193212A (en) * 2000-01-13 2001-07-17 Sanyo Industries Ltd Cradling receiver for ceiling foundation material
JP4523102B2 (en) * 2000-01-13 2010-08-11 三洋工業株式会社 Field reception of ceiling material
WO2008081929A1 (en) 2007-01-04 2008-07-10 Nippon Steel Corporation Floor structure
US8037655B2 (en) 2007-01-04 2011-10-18 Nippon Steel Corporation Floor structure including plate-shaped supporting portion
US8037654B2 (en) 2007-01-04 2011-10-18 Nippon Steel Corporation Floor structure including plate-shaped supporting portion
JP2012012836A (en) * 2010-06-30 2012-01-19 Shimizu Corp Construction method of floor unit for stock on construction story
CN106703073A (en) * 2016-12-30 2017-05-24 中国建筑第八工程局有限公司 Supporting-free steel beam foundation of super-high-rise construction elevator and construction method of supporting-free steel beam foundation

Similar Documents

Publication Publication Date Title
JP4609360B2 (en) Unit building
JPH11293834A (en) Method for constructing floor of building
JPH04323435A (en) Assembling type construction
JP2001173097A (en) Structure of precast composite beam
JP2002364008A (en) Synthesized arch tunnel with large cross section and its work method
JP3579596B2 (en) Unit building and its construction method
JPH11172770A (en) Building unit without column and beam, its building method, and unit building
JP3574625B2 (en) Unit building and its construction method
JP2000080727A (en) Building unit from which column is omitted, and unit building and its construction method
JPS62178634A (en) Framework construction method of structure
JP4449886B2 (en) Unit building
JP2707966B2 (en) Floor construction method using prestressed concrete plate as beam-side formwork
JPH084107A (en) Connecting method for column/beam connection
JPH1162079A (en) Floor block construction method for steel structure frame
JP2972956B2 (en) Column and beam joining method and its structure
JP2661302B2 (en) Grating floor construction method
JP2904043B2 (en) How to build a composite frame
JPH0598703A (en) Multilayer rc core wall structure and construction method thereof
JPH1025815A (en) Unit building
JP2003176696A (en) Prefabricated tunnel and construction method therefor
JPH06306940A (en) Steel framed multi-story building
JP2907047B2 (en) How to build a composite frame
JP2723011B2 (en) Construction method of steel frame reinforced concrete structure
JPH11124914A (en) Arranged structure of building unit
JPH0372138A (en) Wall panel jointing construction

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20050705