JPH11280077A JP10389598A JP10389598A JPH11280077A JP H11280077 A JPH11280077 A JP H11280077A JP 10389598 A JP10389598 A JP 10389598A JP 10389598 A JP10389598 A JP 10389598A JP H11280077 A JPH11280077 A JP H11280077A
Authority
JP
Japan
Prior art keywords
retaining
weir plate
main body
ground
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP10389598A
Other languages
Japanese (ja)
Inventor
Hirosuke Saeki
啓輔 佐伯
Hirotake Hamada
弘武 濱田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Forestry Co Ltd
Original Assignee
Sumitomo Forestry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Forestry Co Ltd filed Critical Sumitomo Forestry Co Ltd
Priority to JP10389598A priority Critical patent/JPH11280077A/en
Publication of JPH11280077A publication Critical patent/JPH11280077A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

PROBLEM TO BE SOLVED: To easily assemble and remove a dam plate for retaining soil. SOLUTION: A dam plate for retaining soil 1 is constituted in such a way that a hollow part 4 in which a pile 3 is inserted into a fringe part on one side of a dam plate main body 2 supporting digged soil on its side is provided and that a connection part 5 is provided in the other fringe part. Here, two adjacent dam plates for retaining soil 1, 1 are mutually connected in the horizontal direction by fitting the hollow part 4 belonging to the dam plate for retaining soil 1 on one side into the connection part 5 belonging to the dam plate for retaining soil 1 on the other side. A ground insertion piece 6 to be inserted into the ground is provided in a lower fringe part of the dam plate main body 2. Reinforcing ribs 7a, 7b in the horizontal direction are provided in the vicinity of upper fringe and lower fringe of the dam plate main body 2, respectively, and the reinforcing rib 7b in the vicinity of the lower fringe part is provided at a ground embedding position, that is, a section which becomes a ground surface position when the ground insertion piece 6 is inserted into the ground.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、主として住宅建築
の基礎工事で使用する土留め用堰板に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an embankment dam plate mainly used for foundation work of a residential building.

【0002】[0002]

【従来の技術】住宅を建築するには、まず基礎の構築箇
所を掘り下げる根切り工事を行い、次いで、根切りされ
た箇所にRC布基礎を構築するのが一般的である。ここ
で、根切りの際には当然ながら掘削土が発生するが、か
かる掘削土は、通常、布基礎構築箇所の脇にとりあえず
仮置きしておき、布基礎構築後に埋め戻すことが多い。
2. Description of the Related Art In order to build a house, it is common practice to first perform excavation work to dig a construction site of a foundation, and then construct an RC cloth foundation at the excavated location. Here, of course, excavated soil is naturally generated at the time of root cutting. However, such excavated soil is usually temporarily placed next to the fabric foundation construction site for the time being, and is often backfilled after construction of the fabric foundation.

【0003】ここで、敷地境界近傍で根切り工事が行わ
れる場合、特に該敷地の地盤面が周囲より高い場合に
は、仮置きされた掘削土が敷地の外側に崩れ落ちやす
く、それが道路境界であれば、道路脇に設置された排水
用の側溝に流れ込んで該側溝を閉塞させたり、隣地境界
であれば、隣りの敷地内に掘削土が崩れ落ちるという問
題が生じる。
[0003] Here, when excavation work is performed near the site boundary, particularly when the ground surface of the site is higher than the surrounding area, the temporarily placed excavated soil easily collapses to the outside of the site, which is likely to be a road boundary. In such a case, there is a problem in that the excavated soil flows into a drainage gutter installed on the side of the road and closes the gutter, or at the boundary of an adjacent land, excavated soil collapses in an adjacent site.

【0004】そのため、従来は、敷地境界近傍に杭を打
ち込み、該杭の内側に足場板をあてがって土留め板とし
ていた。
[0004] Therefore, conventionally, a pile was driven into the vicinity of the site boundary, and a scaffold plate was applied to the inside of the pile to serve as a retaining plate.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、かかる
方法では、結束線等を用いて足場板を一枚一枚杭に結束
する必要があり、そのための作業に多大な時間を要する
とともに、足場板を撤去する際にもやはり一枚一枚結束
線を外さねばならず、かなり面倒な作業となっていた。
However, in such a method, it is necessary to bind the scaffolding plates to the piles one by one using a binding wire or the like, which requires a great deal of time for the operation, and also requires the scaffolding plates to be attached. When removing them, the binding wires had to be removed one by one, which was a rather cumbersome task.

【0006】本発明は、上述した事情を考慮してなされ
たもので、組立並びに撤去が容易な土留め用堰板を提供
することを目的とする。
The present invention has been made in view of the above circumstances, and has as its object to provide an earth retaining weir plate that can be easily assembled and removed.

【0007】[0007]

【課題を解決するための手段】上記目的を達成するた
め、本発明に係る土留め用堰板は請求項1に記載したよ
うに、掘削土を側方支持する堰板本体の一方の縁部に杭
が挿通される中空部を設けるとともに他方の縁部には隣
接する前記中空部に連結される連結部を設けたものであ
る。
In order to achieve the above object, a retaining weir plate according to the present invention is provided with one edge of a weir plate main body for supporting excavated soil laterally. And a connecting portion connected to the adjacent hollow portion is provided on the other edge portion.

【0008】また、本発明に係る土留め用堰板は、前記
中空部を円筒体で形成し、前記連結部を該円筒体の周面
に当接される半円筒体で形成したものである。
Further, in the earth retaining weir plate according to the present invention, the hollow portion is formed of a cylindrical body, and the connecting portion is formed of a semi-cylindrical body which is in contact with a peripheral surface of the cylindrical body. .

【0009】また、本発明に係る土留め用堰板は、前記
中空部を上下二段に分割配置された一対の円筒体で形成
し、前記連結部を該一対の円筒体の間に配置される円筒
体で形成したものである。
Further, in the retaining weir plate according to the present invention, the hollow portion is formed by a pair of cylindrical members divided and arranged in two upper and lower stages, and the connecting portion is disposed between the pair of cylindrical members. It is formed of a cylindrical body.

【0010】また、本発明に係る土留め用堰板は、掘削
土を側方支持する堰板本体の一方の縁部に地盤に打ち込
まれる杭部を設けるとともに他方の縁部には隣接する前
記杭部に連結される連結部を設けたものである。
[0010] In the dam retaining plate according to the present invention, a pile portion driven into the ground is provided at one edge of a dam plate main body for supporting excavated soil laterally, and the other edge is adjacent to the pile. It is provided with a connection portion connected to the stake portion.

【0011】また、本発明に係る土留め用堰板は、前記
堰板本体の下縁部に地中差込片を設けたものである。
[0011] The retaining weir plate according to the present invention is provided with an underground insertion piece at a lower edge portion of the weir plate main body.

【0012】また、本発明に係る土留め用堰板は、前記
堰板本体の下縁部の地盤埋設位置に補強リブを水平方向
に形成したものである。
Further, in the dam retaining plate according to the present invention, a reinforcing rib is formed in a horizontal direction at a position where the lower edge portion of the dam plate main body is buried in the ground.

【0013】請求項1の発明に係る土留め用堰板におい
ては、根切り工事に先だち、まず、堰板本体の一方の縁
部に設けられた中空部に杭を通し、かかる状態で杭を地
盤に打ち込んで土留め用堰板を自立させる。次に、かか
る先行配置された土留め用堰板の連結部に二番目の土留
め用堰板の中空部を連結させ、かかる状態で該中空部に
同様にして杭を通し、地盤に打ち込む。以下、これらの
手順を繰り返して土留め用堰板を次々に連続配置してい
く。
In the retaining weir plate according to the first aspect of the present invention, prior to root cutting work, first, a pile is passed through a hollow portion provided at one edge of the weir plate main body, and the pile is placed in this state. Driving into the ground to make the retaining dam self-supporting. Next, the hollow portion of the second retaining dam plate is connected to the connecting portion of the preceding retaining dam plate, and in this state, a pile is similarly passed through the hollow portion and driven into the ground. Hereinafter, these steps are repeated to successively arrange the retaining weir plates one after another.

【0014】また、請求項4の発明に係る土留め用堰板
においては、まず、堰板本体の一方の縁部に設けられた
杭部を地盤に突き立ててこれを地盤に打ち込み、土留め
用堰板を自立させる。次に、かかる先行配置された土留
め用堰板の連結部に二番目の土留め用堰板の杭部を連結
させ、かかる状態で該杭部を同様にして地盤に打ち込
む。以下、これらの手順を繰り返して土留め用堰板を次
々に連続配置していく。
According to the fourth aspect of the present invention, first, a pile portion provided at one edge of the main body of the dam board is pushed up to the ground, and is driven into the ground. Independently stand the weir plate. Next, the pile portion of the second retaining dam plate is connected to the connecting portion of the precedingly arranged retaining dam plate, and in this state, the pile portion is similarly driven into the ground. Hereinafter, these steps are repeated to successively arrange the retaining weir plates one after another.

【0015】このようにすると、従来のように足場板の
結束作業が不要となり、その分、組立並びに撤去におけ
る作業性が改善される。
This eliminates the need for the work of binding the scaffold plates as in the prior art, thereby improving the workability in assembly and removal.

【0016】請求項1、請求項4の各発明で言うところ
の連結とは、隣接する土留め用堰板同士の面内方向のず
れが防止できれば十分であり、面外方向については掘削
土の土圧が作用する側で非連結状態となっていても差し
支えない。
In the first and fourth aspects of the present invention, the connection means that it is sufficient if the displacement of the adjacent retaining dams in the in-plane direction can be prevented. It may be in a disconnected state on the side where the earth pressure acts.

【0017】請求項1の発明に関し、中空部については
杭が挿通可能であり、連結部は上述したように該中空部
に面内方向にて連結できるものであればどのような構造
でもよいが、前記中空部を円筒体で形成し、前記連結部
を該円筒体の周面に当接される半円筒体で形成したなら
ば、市販されている杭に対しての汎用性や連結時の作業
性が高くなる。また、前記中空部を上下二段に分割配置
された一対の円筒体で形成し、前記連結部を該一対の円
筒体の間に配置される円筒体で形成したならば、どちら
側からでも土圧を受けることができる構成となり、土留
め用堰板の配置方向に注意を払う必要がなくなる。
According to the first aspect of the present invention, any structure may be used as long as the pile can be inserted into the hollow portion and the connecting portion can be connected to the hollow portion in the in-plane direction as described above. If the hollow portion is formed of a cylindrical body, and the connecting portion is formed of a semi-cylindrical body abutting on the peripheral surface of the cylindrical body, if it is versatile or can be connected to a commercially available pile. Workability is improved. Further, if the hollow portion is formed by a pair of cylindrical bodies divided and arranged in two upper and lower stages, and the connecting portion is formed by a cylindrical body disposed between the pair of cylindrical bodies, soil may be formed from either side. The structure can receive the pressure, and it is not necessary to pay attention to the arrangement direction of the retaining dam plate.

【0018】また、請求項1、請求項4の各発明に関
し、堰板本体の下縁部に何も設けなくてもよいが、該下
縁部に地中差込片を設けたならば、堰板本体と地盤との
間に隙間が生じるのを防止することが可能となる。
Further, according to the first and fourth aspects of the present invention, it is not necessary to provide anything at the lower edge of the weir plate body, but if an underground insertion piece is provided at the lower edge, It is possible to prevent a gap from occurring between the dam body and the ground.

【0019】また、堰板本体の下縁部の地盤埋設位置に
補強リブを水平方向に形成したならば、堰板本体の面外
剛性を高めることができるのみならず、該補強リブの位
置を目印として杭や杭部を打ち込むことができるので、
作業がやりやすくなるとともに打ち込み深さを揃えるこ
とができるので土留め作業の品質向上が期待できる。
Further, if reinforcing ribs are formed horizontally in the ground embedding position at the lower edge of the weir plate main body, not only the out-of-plane rigidity of the weir plate main body can be increased, but also the position of the reinforcing rib can be increased. As you can drive a pile or a pile part as a mark,
Since the work becomes easier and the driving depth can be made uniform, the improvement of the quality of earth retaining work can be expected.

【0020】また、堰板本体の形状や構造あるいは材質
は問わないが、例えば、FRPやアルミ合金等の材料で
足場板と同様に横長状に構成することが考えられる。
The shape, structure, or material of the main body of the weir plate is not limited.

【0021】[0021]

【発明の実施の形態】以下、本発明に係る土留め用堰板
の実施の形態について、添付図面を参照して説明する。
なお、従来技術と実質的に同一の部品等については同一
の符号を付してその説明を省略する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a retaining weir plate according to the present invention will be described below with reference to the accompanying drawings.
It is to be noted that the same reference numerals are given to components and the like that are substantially the same as those in the conventional technology, and description thereof will be omitted.

【0022】図1は、本実施形態に係る土留め用堰板を
示した全体斜視図、図2は同じく断面図である。これら
の図でわかるように、本実施形態に係る土留め用堰板1
は、掘削土を側方支持する堰板本体2の一方の縁部に杭
3が挿通される中空部4を設けるとともに、他方の縁部
には連結部5を設けて構成してある。
FIG. 1 is an overall perspective view showing a retaining weir plate according to this embodiment, and FIG. 2 is a sectional view of the same. As can be seen from these figures, the retaining dam plate 1 according to the present embodiment is shown.
Is provided with a hollow portion 4 into which a pile 3 is inserted at one edge of a dam plate body 2 that supports excavated soil laterally, and a connecting portion 5 at the other edge.

【0023】ここで、図2(b)の水平断面図でよくわか
るように、中空部4は円筒体で形成してあり、連結部5
は該円筒体の周面に当接される半円筒体で形成してあ
る。そして、隣接する2つの土留め用堰板1、1は、一
方の土留め用堰板1に属する連結部5に他方の土留め用
堰板1に属する中空部4を嵌め込むことによって面内方
向に相互連結されるようになっている。
Here, as can be clearly understood from the horizontal sectional view of FIG. 2B, the hollow portion 4 is formed of a cylindrical body, and the connecting portion 5
Is formed of a semi-cylindrical body that is in contact with the peripheral surface of the cylindrical body. The two adjacent retaining weir plates 1, 1 are in-plane by fitting a hollow portion 4 belonging to the other retaining weir plate 1 into a connecting portion 5 belonging to one retaining weir plate 1. They are interconnected in a direction.

【0024】一方、堰板本体2の下縁部には地盤に差し
込まれる地中差込片6を設けてある。また、堰板本体2
の上縁近傍と下縁近傍には、水平方向の補強リブ7a、
7bをそれぞれ設けてあり、下縁部近傍の補強リブ7b
については、地盤埋設位置、すなわち地中差込片6を地
盤に差し込んだときにちょうど地表面位置となる箇所に
設けてある。
On the other hand, an underground insertion piece 6 to be inserted into the ground is provided at the lower edge of the weir plate main body 2. In addition, weir board body 2
In the vicinity of the upper edge and the lower edge, a horizontal reinforcing rib 7a,
7b, and reinforcing ribs 7b near the lower edge
Is provided at the ground embedding position, that is, at a position that is exactly the ground surface position when the underground insertion piece 6 is inserted into the ground.

【0025】土留め用堰板1は、例えばアルミ合金等の
板材の本体部分で堰板本体2を形成するとともに本体部
分の上縁近傍と下縁近傍を折り曲げて補強リブ7a、補
強リブ7b及び地中差込片6とし、さらに左右縁部を湾
曲加工して中空部4及び連結部5を形成することで製造
が可能である。
For the retaining dam plate 1, the dam plate main body 2 is formed of a main body portion of a plate material such as an aluminum alloy, and the vicinity of the upper edge and the lower edge of the main body portion are bent to form the reinforcing ribs 7a, 7b, and 7b. Manufacture is possible by forming the hollow portion 4 and the connecting portion 5 by forming the underground insertion piece 6 and further bending the left and right edges thereof.

【0026】本実施形態に係る土留め用堰板1において
は、根切り工事に先だち、堰板本体2の一方の縁部に設
けられた中空部4に杭3を通し、かかる状態で杭3を、
例えば図3に示すような道路脇に設けられた側溝11近
くの地盤に打ち込んで土留め用堰板1を自立させる。
In the retaining weir plate 1 according to the present embodiment, prior to the excavation work, the pile 3 is passed through the hollow portion 4 provided at one edge of the weir plate main body 2, and in this state, the pile 3 To
For example, the soil retaining weir plate 1 is driven into the ground near the gutter 11 provided on the side of the road as shown in FIG.

【0027】このとき、地中差込片6が地盤に差し込ま
れ、さらに補強リブ7bがちょうど地盤面近傍にくるま
で杭3をしっかりと地盤に打ち込む。また、連結部5が
掘削土の仮置き側にくるように土留め用堰板1を配置す
る。
At this time, the underground insertion piece 6 is inserted into the ground, and the pile 3 is firmly driven into the ground until the reinforcing rib 7b comes to just near the ground surface. In addition, the retaining dam plate 1 is arranged so that the connecting portion 5 comes to the temporary placing side of the excavated soil.

【0028】次に、かかる先行配置された土留め用堰板
1の連結部5に図2(b)に示したように、二番目の土留
め用堰板1の中空部4を嵌め込んで連結させ、かかる状
態で該中空部に同様にして杭3を通し、地盤に打ち込
む。以下、これらの手順を繰り返して土留め用堰板1を
次々に連続配置していく。
Next, as shown in FIG. 2B, the hollow portion 4 of the second retaining dam 1 is fitted into the connecting portion 5 of the preceding retaining dam 1. In such a state, the pile 3 is similarly passed through the hollow portion and driven into the ground. Hereinafter, these steps are repeated to successively arrange the retaining weir plates 1 one after another.

【0029】土留め用堰板1の設置が完了したならば、
根切り作業を行い、そのときに発生する掘削土12を図
3に示すように堰板本体2で側方支持する。そして、根
切り、基礎構築、仮置きされた掘削土の埋め戻しあるい
は不要な土砂の搬出といった一連の作業が終了した後、
杭3を引き抜いて土留め用堰板1を回収し、次の建築現
場での転用に備える。
When the installation of the retaining dam plate 1 is completed,
A root cutting operation is performed, and excavated soil 12 generated at that time is laterally supported by the weir plate main body 2 as shown in FIG. Then, after a series of operations such as root cutting, foundation construction, backfilling of temporarily placed excavated soil or carrying out unnecessary earth and sand,
The pile 3 is pulled out, and the retaining dam plate 1 is collected and prepared for the conversion at the next construction site.

【0030】以上説明したように、本実施形態に係る土
留め用堰板1によれば、先行配置されている土留め用堰
板1の連結部5に嵌め込むようにして新たな土留め用堰
板1の中空部4を嵌め込み、かかる状態で該中空部に杭
3を打ち込んで自立させるという手順を次々に繰り返す
ようにしたので、従来のような足場板の結束作業が不要
となり、その分、組立における作業性が改善される。ま
た、撤去する際も杭3を引き抜くだけでよいので、従来
のように結束線を切断する作業が不要となり、ここでも
作業性の改善を図ることが可能となる。
As described above, according to the retaining dam 1 according to the present embodiment, a new retaining dam is inserted into the connecting portion 5 of the preceding retaining dam 1. In this state, the procedure of fitting the hollow portion 4 into the hollow portion 4 and driving the pile 3 into the hollow portion to make it self-supporting is repeated one after another, so that the conventional work of binding the scaffolding plate becomes unnecessary, and the assembly is accordingly performed. Is improved. Also, when removing, it is only necessary to pull out the stake 3, so that the work of cutting the binding wire as in the related art is not required, and the workability can be improved here as well.

【0031】また、本実施形態に係る土留め用堰板1に
よれば、中空部4を円筒体で形成し、連結部5を該円筒
体の周面に当接される半円筒体で形成したので、市販さ
れている杭に対しての汎用性や連結時の作業性が高くな
るとともに、製造コストも安価に抑えることができる。
Further, according to the dam retaining plate 1 according to the present embodiment, the hollow portion 4 is formed of a cylindrical body, and the connecting portion 5 is formed of a semi-cylindrical body which is in contact with the peripheral surface of the cylindrical body. Therefore, general versatility and workability at the time of connection with commercially available piles are improved, and the manufacturing cost can be reduced.

【0032】また、本実施形態に係る土留め用堰板1に
よれば、堰板本体2の下縁部近傍に地中差込片6を設け
るようにしたので、堰板本体2と地盤との間に隙間が生
じるのを防止することが可能となる。そのため、雨天に
おいて土砂混じりの濁水が側溝11に流入するのを未然
に防止することができる。
Further, according to the dam retaining plate 1 according to the present embodiment, the underground insertion piece 6 is provided near the lower edge portion of the dam retaining plate main body 2, so that the dam retaining plate main body 2 and the ground can be connected to each other. It is possible to prevent the formation of a gap between them. Therefore, it is possible to prevent muddy water mixed with earth and sand from flowing into the gutter 11 in rainy weather.

【0033】また、本実施形態に係る土留め用堰板1に
よれば、堰板本体2の下縁部の地盤埋設位置に補強リブ
7bを水平方向に形成したので、上縁近傍に設けた補強
リブ7aとともに堰板本体2の面外剛性を高めることが
できるのみならず、補強リブ7bの位置を目安として杭
3を地盤に打ち込むことができるので、土留め作業がや
りやすくなるとともに、打ち込み深さを揃えることがで
きるので土留め作業の品質向上が期待できる。
In addition, according to the dam retaining plate 1 according to the present embodiment, since the reinforcing ribs 7b are formed in a horizontal direction at the ground embedding position of the lower edge portion of the dam plate main body 2, they are provided near the upper edge. Not only the out-of-plane rigidity of the dam plate body 2 can be increased together with the reinforcing ribs 7a, but also the pile 3 can be driven into the ground using the position of the reinforcing ribs 7b as a guide, so that the soil retaining work is facilitated and the driving is performed. Since the depths can be made uniform, the improvement of the quality of earth retaining work can be expected.

【0034】本実施形態では、土留め用堰板1を自立さ
せるための杭として、通常の杭3を用いるようにした
が、これに代えて図4に示すように侵入防止用フェンス
21の両縁部に設けられた杭22を土留め用堰板1の中
空部4に打ち込むようにしてもよい。
In this embodiment, the ordinary pile 3 is used as a pile for self-supporting the retaining weir plate 1, but instead of this, both the intrusion prevention fences 21 are used as shown in FIG. The pile 22 provided on the edge may be driven into the hollow portion 4 of the retaining dam plate 1.

【0035】また、本実施形態では、中空部4を堰板本
体2と同等の高さを持つ円筒体として形成するととも
に、連結部5を該中空部の周面に当接される半円筒体と
して形成したが、かかる中空部及び連結部は、隣接する
二つの土留め用堰板が面内方向にずれるのを防止するこ
とができるような構成であれば、形状や構造は任意であ
り、例えば図5に示すような土留め用堰板31としても
よい。
In the present embodiment, the hollow portion 4 is formed as a cylindrical body having the same height as the weir plate main body 2, and the connecting portion 5 is formed as a semi-cylindrical body abutting on the peripheral surface of the hollow portion. However, the shape and structure of the hollow portion and the connecting portion are arbitrary as long as the configuration can prevent two adjacent retaining dam plates from shifting in the in-plane direction. For example, an earth retaining weir plate 31 as shown in FIG. 5 may be used.

【0036】同図に示す土留め用堰板31は、上下二段
に分割配置された中空部32a、32bを堰板本体2の
一方の縁部に設けるとともに他方の縁部に中空部32
a、32bの間に挟まれるように寸法決めされた連結部
33を設けてある。
The retaining weir plate 31 shown in FIG. 2 has hollow portions 32a and 32b divided into two upper and lower stages at one edge of the dam plate main body 2 and the hollow portion 32 at the other edge.
A connecting portion 33 sized so as to be sandwiched between a and 32b is provided.

【0037】かかる構成においては、先行配置された土
留め用堰板31の連結部33を挟み込むようにして、隣
接される土留め用堰板31の中空部32a、32bを配
置して連結部33及び中空部32a、32bの材軸を揃
え、かかる状態で杭3を打ち込んで土留め用堰板31を
次々に連続配置していく。
In this configuration, the hollow portions 32a and 32b of the adjacent retaining dam plate 31 are arranged so as to sandwich the connecting portion 33 of the preceding retaining dam plate 31 so that the connecting portion 33 is interposed therebetween. The material axes of the hollow portions 32a and 32b are aligned, and the pile 3 is driven in such a state to continuously arrange the retaining dam plates 31 one after another.

【0038】そのため、堰板本体2は、上述の実施形態
とは異なり、どちら側からでも土圧を受けることができ
る構成となり、土留め用堰板31の配置方向に注意を払
う必要がなくなる。
Therefore, unlike the above-described embodiment, the dam plate main body 2 is configured to receive the earth pressure from either side, and it is not necessary to pay attention to the arrangement direction of the retaining dam plate 31.

【0039】また、本実施形態では、中空部4に杭3を
差し込むようにしたが、かかる構成に代えて図6に示す
ような土留め用堰板41としてもよい。同図に示す土留
め用堰板41も土留め用堰板1とほぼ同様であるが、堰
板本体2の一方の縁部に杭部42を取り付けてある点が
異なる。
In this embodiment, the pile 3 is inserted into the hollow portion 4. However, instead of this configuration, a retaining dam plate 41 as shown in FIG. 6 may be used. The retaining weir plate 41 shown in the figure is substantially the same as the retaining weir plate 1, except that a pile portion 42 is attached to one edge of the weir plate main body 2.

【0040】かかる構成によれば、上述の実施形態とほ
ぼ同様の作用効果が得られるほか、杭3を別途調達する
必要がなくなるという別の効果も奏する。
According to this configuration, substantially the same operation and effect as those of the above-described embodiment can be obtained, and another effect that it is not necessary to separately procure the pile 3 is also obtained.

【0041】また、本実施形態では、補強リブ7a、7
bを設けるようにしたが、土圧を側方支持することがで
きるのであればこれらを省略してもよいし、地中差込片
6についても、地盤との隙間から土砂が流出するおそれ
がないのであれば省略が可能である。
In this embodiment, the reinforcing ribs 7a, 7a
However, if the earth pressure can be laterally supported, these may be omitted, and the underground insertion piece 6 may have a possibility that earth and sand may flow out from a gap with the ground. If not, it can be omitted.

【0042】[0042]

【発明の効果】以上述べたように、請求項1に係る本発
明の土留め用堰板によれば、従来のような足場板の結束
作業が不要となり、その分、組立における作業性が改善
される。また、撤去する際も杭を引き抜くだけでよいの
で、従来のように結束線を切断する作業が不要となり、
ここでも作業性の改善を図ることが可能となる。
As described above, according to the retaining weir plate of the present invention according to the first aspect, the work of binding the scaffold plate as in the prior art is unnecessary, and the workability in assembly is improved accordingly. Is done. Also, when removing, it is only necessary to pull out the pile, so the work of cutting the binding wire as in the past is not necessary,
Here, the workability can be improved.

【0043】また、請求項2に係る本発明の土留め用堰
板によれば、市販されている杭に対しての汎用性や連結
時の作業性が高くなるとともに、製造コストも安価に抑
えることができるという効果も奏する。
Further, according to the retaining weir plate of the present invention according to the second aspect, the versatility and the workability at the time of connection with commercially available piles are improved, and the manufacturing cost is also reduced. It also has the effect that it can be done.

【0044】また、請求項3に係る本発明の土留め用堰
板によれば、どちら側からでも土圧を受けることができ
る構成となり、土留め用堰板の配置方向に注意を払う必
要がなくなるという効果も奏する。
According to the third aspect of the present invention, the earth pressure can be received from either side, and it is necessary to pay attention to the arrangement direction of the earth retaining dam. It also has the effect of disappearing.

【0045】また、請求項4に係る本発明の土留め用堰
板によれば、従来のような足場板の結束作業が不要とな
り、その分、組立における作業性が改善される。また、
撤去する際も杭部を引き抜くだけでよいので、従来のよ
うに結束線を切断する作業が不要となり、ここでも作業
性の改善を図ることが可能となる。また、杭を別途調達
する必要もない。
In addition, according to the retaining weir plate of the present invention according to the fourth aspect, it is not necessary to bind the scaffold plate as in the related art, and the workability in assembly is improved accordingly. Also,
When removing, it is only necessary to pull out the stake, so that the work of cutting the binding wire as in the related art becomes unnecessary, and the workability can be improved here as well. Also, there is no need to separately procure piles.

【0046】また、請求項5に係る本発明の土留め用堰
板によれば、堰板本体と地盤との間に隙間が生じるのを
防止することが可能となる。そのため、雨天において土
砂混じりの濁水が流出するのを未然に防止することがで
きるという効果も奏する。
In addition, according to the retaining weir plate of the present invention according to claim 5, it is possible to prevent a gap from being formed between the weir plate main body and the ground. Therefore, there is also an effect that it is possible to prevent outflow of muddy water mixed with earth and sand in rainy weather.

【0047】また、請求項6に係る本発明の土留め用堰
板によれば、堰板本体の面外剛性を高めることができる
のみならず、補強リブの位置を目安として杭や杭部を地
盤に打ち込むことができるので、土留め作業がやりやす
くなるとともに、打ち込み深さを揃えることができるの
で土留め作業の品質向上が期待できるという効果も奏す
る。
Further, according to the retaining weir plate of the present invention according to claim 6, not only the out-of-plane rigidity of the weir plate main body can be increased, but also the pile or the pile portion can be formed by using the position of the reinforcing rib as a guide. Since it can be driven into the ground, the earth retaining work can be easily performed, and since the driving depth can be made uniform, the effect of improving the quality of the earth retaining work can be expected.

【0048】[0048]

【図面の簡単な説明】[Brief description of the drawings]

【図1】本実施形態に係る土留め用堰板の全体斜視図。FIG. 1 is an overall perspective view of an earth retaining weir plate according to an embodiment.

【図2】同じく本実施形態に係る土留め用堰板の図であ
り、(a)は鉛直断面図、(b)はA―A線に沿う水平断面
図。
FIGS. 2A and 2B are diagrams of a retaining weir plate according to the embodiment, wherein FIG. 2A is a vertical cross-sectional view, and FIG. 2B is a horizontal cross-sectional view along line AA.

【図3】本実施形態に係る土留め用堰板の使用状況を示
した図。
FIG. 3 is a diagram showing a usage state of a retaining weir plate according to the embodiment.

【図4】別の使用態様を示した全体斜視図。FIG. 4 is an overall perspective view showing another mode of use.

【図5】変形例に係る土留め用堰板の全体斜視図。FIG. 5 is an overall perspective view of a retaining wall plate according to a modification.

【図6】別の変形例に係る土留め用堰板の全体斜視図。FIG. 6 is an overall perspective view of an earth retaining weir plate according to another modification.

【符号の説明】[Explanation of symbols]

1、31、41 土留め用堰板 2 堰板本体 3 杭 4、32a、32b 中空部 5、33 連結部 6 地中差込片 7a、7b 補強リブ 42 杭部 DESCRIPTION OF SYMBOLS 1, 31, 41 Earth retaining plate 2 Embankment main body 3 Pile 4, 32a, 32b Hollow part 5, 33 Connecting part 6 Underground insertion piece 7a, 7b Reinforcement rib 42 Pile part

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 掘削土を側方支持する堰板本体の一方の
縁部に杭が挿通される中空部を設けるとともに他方の縁
部には隣接する前記中空部に連結される連結部を設けた
ことを特徴とする土留め用堰板。
1. A weir plate main body that supports excavated soil laterally, a hollow portion through which a pile is inserted is provided at one edge portion, and a connecting portion that is connected to the adjacent hollow portion is provided at the other edge portion. An earth retaining weir plate characterized by the following.
【請求項2】 前記中空部を円筒体で形成し、前記連結
部を該円筒体の周面に当接される半円筒体で形成した請
求項1記載の土留め用堰板。
2. The retaining weir plate according to claim 1, wherein said hollow portion is formed of a cylindrical body, and said connecting portion is formed of a semi-cylindrical body abutting on a peripheral surface of said cylindrical body.
【請求項3】 前記中空部を上下二段に分割配置された
一対の円筒体で形成し、前記連結部を該一対の円筒体の
間に配置される円筒体で形成した請求項1記載の土留め
用堰板。
3. The method according to claim 1, wherein the hollow portion is formed by a pair of cylindrical members divided and arranged in two upper and lower stages, and the connecting portion is formed by a cylindrical member disposed between the pair of cylindrical members. Weir plate for earth retaining.
【請求項4】 掘削土を側方支持する堰板本体の一方の
縁部に地盤に打ち込まれる杭部を設けるとともに他方の
縁部には隣接する前記杭部に連結される連結部を設けた
ことを特徴とする土留め用堰板。
4. A pile portion driven into the ground is provided at one edge of a weir plate main body that laterally supports excavated soil, and a connection portion connected to the adjacent pile portion is provided at the other edge. An earth retaining weir plate characterized by the above-mentioned.
【請求項5】 前記堰板本体の下縁部に地中差込片を設
けた請求項1若しくは請求項4記載の土留め用堰板。
5. The retaining weir plate according to claim 1, wherein an underground insertion piece is provided at a lower edge portion of the weir plate main body.
【請求項6】 前記堰板本体の下縁部の地盤埋設位置に
補強リブを水平方向に形成した請求項1若しくは請求項
4記載の土留め用堰板。
6. The retaining weir plate according to claim 1, wherein a reinforcing rib is formed in a horizontal direction at a ground embedding position at a lower edge portion of the weir plate main body.
JP10389598A 1998-03-31 1998-03-31 Dam plate for retaining soil Withdrawn JPH11280077A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10389598A JPH11280077A (en) 1998-03-31 1998-03-31 Dam plate for retaining soil

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10389598A JPH11280077A (en) 1998-03-31 1998-03-31 Dam plate for retaining soil

Publications (1)

Publication Number Publication Date
JPH11280077A true JPH11280077A (en) 1999-10-12

Family

ID=14366170

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10389598A Withdrawn JPH11280077A (en) 1998-03-31 1998-03-31 Dam plate for retaining soil

Country Status (1)

Country Link
JP (1) JPH11280077A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110965565A (en) * 2019-12-19 2020-04-07 何涛 Intelligent protection system for reconstructing and expanding highway slope

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110965565A (en) * 2019-12-19 2020-04-07 何涛 Intelligent protection system for reconstructing and expanding highway slope

Similar Documents

Publication Publication Date Title
KR101274974B1 (en) Earth retaining wall and construction method thereof
CN111778994A (en) Pipe-jacking working well supporting device for municipal pipeline engineering and construction method
KR101612521B1 (en) Method for constructing underground structures restraining transformation and using external wall
JP2923498B1 (en) Drainage method and earth retaining support used for it
KR101901368B1 (en) A Permanent Retaining Wall Method Using by Double I Beam
JP3896351B2 (en) Construction method of underground wall and construction method of underpass
JPH11280077A (en) Dam plate for retaining soil
JP4981551B2 (en) Wall structure and construction method thereof
JP3072682U (en) Concrete drain block
KR100655383B1 (en) Method of drain construction for basement
KR200369479Y1 (en) The land-side protection wall panel
CN112609731A (en) Flexible permeable cutting retaining wall and construction method
JP2565452B2 (en) Construction method of self-supporting retaining wall
JP3059034U (en) Water collection and penetration joint basin for rainwater etc.
JPS642727B2 (en)
KR102649959B1 (en) Longitudinal and lateral integration structure of pile and structure manufactured using the same
JP2002004263A (en) Ground improving method
JP4272228B2 (en) Construction method of underground structure
KR101352429B1 (en) Water-proofing type temporary soil sheathing construction method using crrugated steel plate segments
JP3407066B2 (en) Method of forming drainage wall continuously in the ground and casing for placing plate-like drainage material
JPS6215343Y2 (en)
JP2667350B2 (en) Underground structures and construction methods
JP3646698B2 (en) Construction method for underground structures
KR101105676B1 (en) Earth retaining wall consrtuction method using two rows pile
CN117822624A (en) Construction method of foundation pit waterproof base layer based on micro-leakage of engagement piles

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20050607