JPH11270135A - Sheathing plate engineering method of earth floor slab construction joint - Google Patents
Sheathing plate engineering method of earth floor slab construction jointInfo
- Publication number
- JPH11270135A JPH11270135A JP9060998A JP9060998A JPH11270135A JP H11270135 A JPH11270135 A JP H11270135A JP 9060998 A JP9060998 A JP 9060998A JP 9060998 A JP9060998 A JP 9060998A JP H11270135 A JPH11270135 A JP H11270135A
- Authority
- JP
- Japan
- Prior art keywords
- steel
- dam
- joint
- dowel
- sheathing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、土間スラブの打継
部分を形成するための土間スラブ打継部分のせき板工法
に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a dam construction method for a joint between slabs of a slab for forming a joint between slabs of a slab.
【0002】[0002]
【従来の技術】土間スラブは主要構造部材ではないが、
コンクリートのクラックが少ない高品質のものが要求さ
れるようになってきている。打継部分についても誘発目
地兼用の打継目地を設け、クラックの発生しにくい構造
にしている。ところで、従来では、土間スラブ打継部分
を形成する場合、木製のせき板にダボ筋穴をあけて、打
ち継ぎ目鉄筋を入れ差筋でせき板を固定してコンクリー
ト打設していた。2. Description of the Related Art Slab slabs are not the main structural members,
There is a growing demand for high quality concrete with few cracks. The joint is also provided with a joint that also serves as an induction joint, so that cracks are less likely to occur. By the way, conventionally, when forming a joint between slabs, a dowel hole is made in a wooden dam, a seam reinforcing bar is inserted, and the dam is fixed with a reinforcing bar and concrete is cast.
【0003】[0003]
【発明が解決しようとする課題】したがって、従来の工
法によると、木製せき板を用いるため打ち継ぎ目にクラ
ックが発生したり、木製せき板が移動しやすく打ち継ぎ
面が直線にならなかったりするという問題点があった。
また、ダボ筋の位置が決まらない、工事毎にダボ筋用の
穴をせき板に設けなければならない等の別の問題点も有
していた。Therefore, according to the conventional construction method, cracks are generated at the joints because the wooden dam is used, and the wooden dams are easily moved and the joint surface is not straight. There was a problem.
There are also other problems such as the position of the dowel streak is not determined, and a hole for the dowel streak must be provided in the dam for each construction.
【0004】本発明の目的は、従来技術における上記の
問題点を解決することができる、目地のラインが直線と
なり且つ施工が容易となる土間スラブ打継部分のせき板
工法を提供することにある。[0004] It is an object of the present invention to provide a method of damming a joint between slabs between slabs, which can solve the above-mentioned problems in the prior art and has a straight joint line and easy construction. .
【0005】[0005]
【課題を解決するための手段】上記課題を解決するため
の本発明の特徴は、土間スラブ打継部分のせき板工法に
おいて、ダボ筋を通すためのダボ筋孔と地盤に打ち込ま
れる固定用鋼棒を通す鋼棒孔とが形成された鋼製せき板
を用意し、該鋼製せき板を所定位置に設置した後前記固
定用鋼棒を前記鋼棒孔を通して地盤に打ち込んで固定す
ると共に、前記ダボ筋孔にダボ筋を差し込み、しかる後
コンクリートの打設を行うことにより土間スラブ打継部
分を形成するようにした点にある。A feature of the present invention to solve the above-mentioned problems is that, in a dam construction method of a joint portion between soil slabs, a dowel hole for passing a dowel bar and a fixing steel to be driven into the ground. Prepare a steel dam with a steel rod hole through which the rod is formed, and after fixing the steel dam in a predetermined position, drive the fixing steel rod into the ground through the steel rod hole and fix it, The present invention is characterized in that a dowel is inserted into the dowel hole, and then concrete is cast to form a joint between slabs.
【0006】鋼製せき板は鋼棒孔に通された鋼棒を地盤
に打ち込むことにより所定位置にしっかりと固定され
る。この鋼製せき板のダボ筋孔にダボ筋を差し込んでコ
ンクリート打設を行うので打継面がきれいなコンクリー
ト面に形成されると共に打継面が直線となる。この結
果、目地のラインが直線となり且つ施工が容易となる。[0006] The steel dam is firmly fixed at a predetermined position by driving a steel rod passed through a steel rod hole into the ground. Since the dowel is inserted into the dowel hole of the steel dam, concrete is cast, so that the joint surface is formed into a clean concrete surface and the joint surface is straight. As a result, the joint line becomes a straight line and the construction is facilitated.
【0007】[0007]
【発明の実施の形態】以下、図面を参照して本発明の実
施の形態の一例につき詳細に説明する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below in detail with reference to the drawings.
【0008】図1は本発明による工法に使用する鋼製せ
き板の一例を示す斜視図である。鋼製せき板1は、断面
コ字形の鋼材から成り、その垂直部1Aにはダボ筋を差
し込んでセットするためのダボ筋孔2A〜2Iが略等間
隔で長孔の形態で設けられている。一方、鋼製せき板1
の水平部1B、1Cには、この鋼製せき板1を地盤に固
定するための鋼棒を通すための鋼棒孔3A〜3D及び4
A〜4Dがそれぞれあけられている。鋼棒孔3Aは鋼棒
孔4Aに対向しており、したがって、鋼棒を鋼棒孔3A
から入れて鋼棒孔4Aから出すように通すことができ
る。他の鋼棒孔3B〜3D及び4B〜4Dについても同
様である。FIG. 1 is a perspective view showing an example of a steel dam used in the method according to the present invention. The steel dam 1 is made of a steel material having a U-shaped cross section, and dowel holes 2A to 2I for inserting and setting dowels are provided in the vertical portion 1A in the form of elongated holes at substantially equal intervals. . On the other hand, steel dam 1
In the horizontal portions 1B and 1C, steel rod holes 3A to 3D and 4 for passing a steel rod for fixing the steel dam 1 to the ground.
A to 4D are opened. The steel rod hole 3A is opposed to the steel rod hole 4A.
From the steel rod hole 4A. The same applies to the other steel rod holes 3B to 3D and 4B to 4D.
【0009】次に、図2を参照して、図1に示した鋼製
せき板1を用いて土間スラブ打継部分を形成するための
せき板工法につき説明する。Next, with reference to FIG. 2, a description will be given of a dam board construction method for forming a joint portion between soil slabs using the steel dam board 1 shown in FIG.
【0010】先ず図2の(a)に示されるように、地盤
10上の所定の位置に鋼製せき板1を位置決めし、固定
用の鋼棒11を鋼棒孔3Aから4Aに向けて通し、鋼棒
11の先端を地盤10中に打ち込んで鋼製せき板1を固
定する。図2の(a)では見えていないが、鋼棒孔3
A、4Aのみならず、残りの鋼棒孔3B〜3D及び4B
〜4Dについても同様にして固定用の鋼棒を打ち込み、
鋼製せき板1を4本の鋼棒によって所要の位置にしっか
りと固定する。First, as shown in FIG. 2 (a), a steel dam 1 is positioned at a predetermined position on the ground 10, and a fixing steel rod 11 is passed through the steel rod holes 3A to 4A. Then, the tip of the steel rod 11 is driven into the ground 10 to fix the steel dam 1. Although not visible in FIG.
A, 4A as well as the remaining steel rod holes 3B-3D and 4B
In the same way for ~ 4D, drive in a steel bar for fixing,
The steel dam 1 is firmly fixed in a required position by four steel rods.
【0011】次に、図2の(b)に示すように、ダボ筋
孔2A〜2Iのそれぞれにダボ筋12を差し込んでセッ
トする。図2の(b)では9本のダボ筋のうちダボ筋孔
2Aに差し込まれた1本のみが見えている。Next, as shown in FIG. 2 (b), the dowel stoma 12 is inserted into each of the dowel stoma holes 2A to 2I and set. In FIG. 2B, only one of the nine dowel streaks inserted into the dowel stoma hole 2A is visible.
【0012】次に、図2の(c)に示されるように、鋼
製せき板1を型枠として打設コンクリートを流し込み、
これによりコンクリート土間スラブ13を形成する。Next, as shown in FIG. 2 (c), casting concrete is poured using the steel dam 1 as a formwork.
Thereby, the concrete soil slab 13 is formed.
【0013】しかる後、コンクリート土間スラブ13を
形成する打設コンクリートの強度が所定レベルに達した
ならば、鋼棒11を引き抜き、鋼製せき板1を撤去す
る。この結果、図2の(d)に示されるように、コンク
リート土間スラブ13のコンクリート打継面13Aは鋼
製せき板1のためきれいなコンクリート面に形成され、
且つ鋼製せき板1は鋼棒11により地盤10上の所要の
位置にしっかりと固定されているためその目地ラインを
直線とすることができる。Thereafter, when the strength of the cast concrete forming the concrete soil slab 13 reaches a predetermined level, the steel rod 11 is pulled out and the steel dam 1 is removed. As a result, as shown in FIG. 2D, the concrete joint surface 13A of the concrete soil slab 13 is formed as a clean concrete surface because of the steel dam 1.
In addition, since the steel dam 1 is firmly fixed to a required position on the ground 10 by the steel rod 11, the joint line can be made straight.
【0014】このように、図2に示した工法によれば、
土間スラブの打継部分は目地ラインが直線となり、且つ
木製のせき板を用いた従来の工法に比べて施工が容易と
なる。なお、鋼製せき板1は何回でも繰り返し再使用す
ることができることは勿論である。Thus, according to the method shown in FIG.
The joint part of the soil slab has a straight joint line and is easier to construct than a conventional construction method using a wooden dam. The steel dam 1 can of course be reused any number of times.
【0015】なお、図1に示した鋼製せき板1の寸法は
一般用のせき板であり、長さが1800mmであるが、
長さ800mmのものをさらに用意し、適宜に長さ調整
を行うことができるのは勿論である。この場合にはダボ
筋孔及び鋼棒孔の数は少なくすることができる。The dimensions of the steel weir 1 shown in FIG. 1 are general weirs and have a length of 1800 mm.
It is needless to say that a length of 800 mm can be further prepared and the length can be adjusted appropriately. In this case, the number of dowel holes and steel rod holes can be reduced.
【0016】[0016]
【発明の効果】本発明によれば、上述の如く、鋼製せき
板を使用し、地盤に固定して施工するので、施工精度を
向上させることができ、クラックの防止を図ることがで
きる。さらに、打継面の精度も向上し、きれいなコンク
リート面とすることができる。According to the present invention, as described above, since a steel dam is used and fixed to the ground for construction, construction accuracy can be improved and cracks can be prevented. Further, the accuracy of the joint surface is improved, and a clean concrete surface can be obtained.
【図1】本発明による工法に使用する鋼製せき板の一例
を示す斜視図。FIG. 1 is a perspective view showing an example of a steel dam used in the method according to the present invention.
【図2】図1に示した鋼製せき板を用いて土間スラブ打
継部分を形成するための本発明の方法によるせき板工法
の実施の形態の一例を説明するための工程図。FIG. 2 is a process diagram for explaining an example of an embodiment of a dam board construction method according to the method of the present invention for forming a joint between slabs using the steel dam shown in FIG. 1;
1 鋼製せき板 2A〜2I ダボ筋孔 3A〜3D、4A〜4D 鋼棒孔 10 地盤 11 鋼棒 12 ダボ筋 13 コンクリート土間スラブ DESCRIPTION OF SYMBOLS 1 Steel dam 2A-2I Dowel hole 3A-3D, 4A-4D Steel rod hole 10 Ground 11 Steel rod 12 Dowel bar 13 Concrete slab
Claims (1)
て、ダボ筋を通すためのダボ筋孔と地盤に打ち込まれる
固定用鋼棒を通す鋼棒孔とが形成された鋼製せき板を用
意し、該鋼製せき板を所定位置に設置した後前記固定用
鋼棒を前記鋼棒孔を通して地盤に打ち込んで固定すると
共に、前記ダボ筋孔にダボ筋を差し込み、しかる後コン
クリートの打設を行うことにより土間スラブ打継部分を
形成するようにしたことを特徴とする土間スラブ打継部
分のせき板工法。In a damping method for a joint between soil slabs, a steel dam is prepared in which a dowel hole for passing a dowel and a steel rod hole for passing a fixing steel rod driven into the ground are formed. Then, after installing the steel dam in a predetermined position, the fixing steel rod is driven into the ground through the steel rod hole and fixed, and a dowel is inserted into the dowel hole, and then concrete is poured. A dam construction method for a joint between slabs, wherein the joint between slabs is formed by performing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9060998A JPH11270135A (en) | 1998-03-20 | 1998-03-20 | Sheathing plate engineering method of earth floor slab construction joint |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9060998A JPH11270135A (en) | 1998-03-20 | 1998-03-20 | Sheathing plate engineering method of earth floor slab construction joint |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH11270135A true JPH11270135A (en) | 1999-10-05 |
Family
ID=14003230
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP9060998A Pending JPH11270135A (en) | 1998-03-20 | 1998-03-20 | Sheathing plate engineering method of earth floor slab construction joint |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH11270135A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007297802A (en) * | 2006-04-28 | 2007-11-15 | Fujita Corp | Depositing implement for floor concrete |
CN100370095C (en) * | 2002-12-22 | 2008-02-20 | 邱则有 | Hole constructing component for in situ cast steel bar reinforced concrete |
-
1998
- 1998-03-20 JP JP9060998A patent/JPH11270135A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100370095C (en) * | 2002-12-22 | 2008-02-20 | 邱则有 | Hole constructing component for in situ cast steel bar reinforced concrete |
JP2007297802A (en) * | 2006-04-28 | 2007-11-15 | Fujita Corp | Depositing implement for floor concrete |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204645268U (en) | A kind of infilled wall tie bar built-in fitting | |
KR20190042193A (en) | Method for constructing wall structure using precast double wall | |
JPH11270135A (en) | Sheathing plate engineering method of earth floor slab construction joint | |
CN106401276A (en) | Construction method for wall column binding bars of frame type building block enclosing wall | |
JP3707006B2 (en) | New method for opening openings in existing masonry walls | |
JPH11229402A (en) | Foundation and construction for steel frame structure | |
JP3511159B2 (en) | Concrete casting method | |
CN214219295U (en) | Special formwork for construction of water-stable road surface base layer | |
JPH08296231A (en) | Construction method for stabilizing slope, and construction method for extension in slope | |
JPH0452815B2 (en) | ||
JPS61134422A (en) | Method of building precast concrete underground continuous wall | |
JP3061724U (en) | Foundation blocks and building foundations | |
JPS6138028A (en) | Construction of foundation | |
CN117738339A (en) | Concrete basement outer wall crack induction structure and construction method thereof | |
JPH08105059A (en) | Concrete strip footing and forming method thereof | |
JP2004225349A (en) | Placing joint structure of concrete floor, placing joint member of concrete floor and its form | |
JP3289163B2 (en) | How to build underground structures | |
JPH0791060A (en) | Construction method of earthen floor concrete successive placing part | |
JP2002332647A (en) | Precast concrete block for retaining wall and fixing method therefor | |
JPH03260222A (en) | Construction of slope frame and block structure | |
JPH11336091A (en) | Execution method of joint bar for nonbearing wall in ground form construction method | |
JPH0886013A (en) | Method of constructing balcony and precast concrete member for construction of balcony | |
JPH01165815A (en) | Construction of continuous underground wall | |
CN109162363A (en) | A kind of structure and its technique for accelerating high structures masonry project progress and overall stability | |
JPH11303284A (en) | Floor slab with stepped section |