JPH11264886A - Cable trench between buildings and its construction method and block structure used for the construction method - Google Patents

Cable trench between buildings and its construction method and block structure used for the construction method

Info

Publication number
JPH11264886A
JPH11264886A JP10069762A JP6976298A JPH11264886A JP H11264886 A JPH11264886 A JP H11264886A JP 10069762 A JP10069762 A JP 10069762A JP 6976298 A JP6976298 A JP 6976298A JP H11264886 A JPH11264886 A JP H11264886A
Authority
JP
Japan
Prior art keywords
concrete slab
buildings
cable
building
cable trench
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10069762A
Other languages
Japanese (ja)
Inventor
Hidetoshi Saito
英俊 斎藤
Seiji Nakajima
誠治 中島
Katsunori Koike
勝則 小池
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Hitachi Architects and Engineers Co Ltd
Original Assignee
Hitachi Ltd
Hitachi Architects and Engineers Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd, Hitachi Architects and Engineers Co Ltd filed Critical Hitachi Ltd
Priority to JP10069762A priority Critical patent/JPH11264886A/en
Publication of JPH11264886A publication Critical patent/JPH11264886A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Abstract

PROBLEM TO BE SOLVED: To shorten the construction term of a plant having a cable trench between buildings by forwarding the initiation time of cable laying work in the cable trench between buildings. SOLUTION: Supports 4a and 4b and each of beams 1a and 1b are left in a set space 24 of a cable trench between buildings even after forming the upper concrete slab 6a, and by using the supports 4a and 4b as support means for the cable tray 5, the cable tray 5 is placed in the set space 14. Without waiting for the increase of the design strength of the upper concrete slab 6a, the cable is laid in the trench between building in this construction method.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、複数の建屋間の
間に設けられるケーブルトレンチに用いられる技術であ
る。
The present invention relates to a technique used for a cable trench provided between a plurality of buildings.

【0002】[0002]

【従来の技術】原子力発電所には複数の建屋が存在し、
例えば、図1のように、原子炉建屋8とタービン建屋9
と廃棄物建屋10とコントロール建屋11とサービス建
屋12との各建屋が存在している。
2. Description of the Related Art A nuclear power plant has a plurality of buildings,
For example, as shown in FIG. 1, the reactor building 8 and the turbine building 9
And a waste building 10, a control building 11, and a service building 12.

【0003】コントロール建屋11は、各建屋内の設備
を制御する設備を備えているから、各建屋との間で電気
ケーブルなどのケーブル類が多数本引き回されている。
Since the control building 11 is provided with equipment for controlling the equipment in each building, a large number of cables such as electric cables are routed between each building.

【0004】それらのケーブルを通過ささせるためのケ
ーブルトレンチ(ケーブルを敷設するための溝)がコン
トロール建屋11と原子炉建屋8との間に、図1のハッ
チングで示した建屋間隔間に構築される。
[0004] Cable trenches (grooves for laying cables) for passing these cables are constructed between the control building 11 and the reactor building 8 between the building gaps shown by hatching in FIG. You.

【0005】従来では、そのケーブルトレンチは以下の
ようにして構築されていた。
Conventionally, the cable trench has been constructed as follows.

【0006】即ち、図4,図5のように、ケーブルの敷
設ルート、即ちケーブルトレイ5が設置されるルート、
は斜線で示した様に、コントロール建屋11寄りと、原
子炉建屋8寄りと、それらの間の中央との3ルートが存
在する。
That is, as shown in FIGS. 4 and 5, a cable laying route, that is, a route in which the cable tray 5 is installed,
As shown by hatching, there are three routes to the control building 11, the reactor building 8, and the center between them.

【0007】それらの各ルートを包含して囲うようにケ
ーブルトレンチが建設される。
[0007] A cable trench is constructed to encompass and enclose each of these routes.

【0008】その建設に際しては、まずは、原子炉建屋
8とコントロール建屋11とから張り出した各下部コン
クリートスラブ6bを建設する。
In the construction, first, each lower concrete slab 6b projecting from the reactor building 8 and the control building 11 is constructed.

【0009】その建設に際しては各下部コンクリートス
ラブ6bの突端間に地震力を伝達しないように緩衝用の
間隔13を確保しておく。
During the construction, a buffer space 13 is secured between the protruding ends of each lower concrete slab 6b so as not to transmit the seismic force.

【0010】各下部コンクリートスラブ6bが建設され
て各下部コンクリートスラブ6bのコンクリート強度が
支保工4からの荷重を支持するに充分な値になった後
に、図4,図5のように、仮設の支保工4を立てて受梁
1を支持し、その受梁1の上方にデッキプレート2を設
置し、デッキプレート2上に鉄筋を配筋し、デッキプレ
ート2上にコンクリートを打設して原子炉建屋8とコン
トロール建屋11とから張り出した各上部コンクリート
スラブ6aを建設する。
After each lower concrete slab 6b is constructed and the concrete strength of each lower concrete slab 6b becomes a value sufficient to support the load from the shoring 4, as shown in FIGS. A support 4 is erected to support the receiving beam 1, a deck plate 2 is installed above the receiving beam 1, a reinforcing bar is laid on the deck plate 2, concrete is cast on the deck plate 2, and the Each upper concrete slab 6a projecting from the furnace building 8 and the control building 11 is constructed.

【0011】その建設に際しては各上部コンクリートス
ラブ6aの突端間に地震力を伝達しないように緩衝用の
間隔13を確保しておく。
In the construction, a buffer space 13 is secured between the protruding ends of each upper concrete slab 6a so as not to transmit the seismic force.

【0012】各上部コンクリートスラブ6aのコンクリ
ートが固化して各上部コンクリートスラブ6aの設計強
度が出るまで待つ。
Wait until the concrete of each upper concrete slab 6a solidifies and the design strength of each upper concrete slab 6a appears.

【0013】その待つ間、受梁1と支保工4とは各下部
コンクリートスラブ6b上で各上部コンクリートスラブ
6aを支持できる様にケーブルトレンチの設定空間14
内に残存させる。
While waiting, the receiving beam 1 and the shoring 4 are connected to the setting space 14 of the cable trench so that each upper concrete slab 6a can be supported on each lower concrete slab 6b.
To be left inside.

【0014】各上部コンクリートスラブ6aの設計強度
が出た後に、受梁1と支保工4とを各上部と下部との両
コンクリートスラブ6a,6bで挟まれた空間内、即ち
ケーブルトレンチの設定空間14内、から外部へ撤去す
る。
After the design strength of each upper concrete slab 6a is obtained, the receiving beam 1 and the shoring 4 are placed in the space between the upper and lower concrete slabs 6a and 6b, that is, the setting space of the cable trench. Remove from 14 to outside.

【0015】その後に、ケーブルを受けるケーブルトレ
イ5や、ケーブルトレイ受け7や、ケーブルトレイ受け
7が取り付くケーブルトレイサポート3をケーブルトレ
ンチの設定空間14内に装備し、その後にケーブルトレ
イ5にケーブルを載せてケーブルを敷設する。
After that, the cable tray 5 for receiving the cable, the cable tray receiver 7, and the cable tray support 3 to which the cable tray receiver 7 is attached are installed in the setting space 14 of the cable trench. Lay the cable on it.

【0016】上部コンクリートスラブ6aの上方にはシ
ートがかぶせられて、そのシートの上方に土15がグラ
ンドレベル(GL)にまで盛られる。
A sheet is placed above the upper concrete slab 6a, and the soil 15 is piled up to the ground level (GL) above the sheet.

【0017】[0017]

【発明が解決しようとする課題】各上部コンクリートス
ラブ6aの設計強度が出るまでにはおよそ1カ月程度の
期間を要するので、その間、ケーブルトレンチの設定空
間14内から受梁1と支保工4を撤去できず、ケーブル
トレイサポート3やケーブルトレイ受け7やケーブルト
レイ5のケーブルトレンチの設定空間14内への設置作
業が行えない上、当然にケーブルの敷設作業自体もでき
ない。
Since it takes about one month for the design strength of each upper concrete slab 6a to come out, during this time, the receiving beam 1 and the shoring 4 must be removed from the setting space 14 of the cable trench. Since it cannot be removed, the cable tray support 3, the cable tray receiver 7, and the cable tray 5 cannot be installed in the cable trench setting space 14, and the cable laying operation itself cannot be performed.

【0018】このために、上述のようなケーブルトレン
チの構造では、ケーブルトレンチの建設工期が長引き、
且つケーブル敷設工事の時期も遅延し、後につながるい
ろいろな工程を遅延させる原因となる。
For this reason, in the cable trench structure as described above, the construction period of the cable trench is prolonged,
In addition, the time of cable laying work is also delayed, which causes delays in various subsequent steps.

【0019】本発明の目的は、建屋間のケーブルトレン
チ内のケーブル敷設作業を伴うプラントの建設工程を短
縮することにある。
An object of the present invention is to shorten the construction process of a plant which involves laying cables in a cable trench between buildings.

【0020】[0020]

【課題を解決するための手段】上記本発明の目的を達成
するための第1手段は、各建屋から各建屋間の空間に張
り出した上下多段のコンクリートスラブと、前記コンク
リートスラブの突端間に設けられて前記建屋間での地震
力の伝達を緩衝する間隔と、前記各コンクリートスラブ
の上下空間内に装備されたケーブルトレイとを備えた建
屋間ケーブルトレンチの構造において、前記各建屋から
張り出された上段の各コンクリートスラブの直下に前記
上段のコンクリートスラブに沿って且つ地震力の伝達を
緩衝する隙間を隔てて装備された各受梁と、前記各受梁
の少なくとも一方を前記下段のコンクリートスラブ上か
ら支持する支保工とを備え、前記支保工に前記ケーブル
トレイを支持せしめたことを特徴とした建屋間ケーブル
トレンチの構造であり、このような構造であると、支保
工が上部からの荷重を支持できるから上部コンクリート
スラブの強度の確保を達成する期間を待たずして、さら
には支保工をケーブルトレイの支持手段として兼用する
ので支保工は本設扱いとされて支保工を撤去する手間を
伴いもせずに、ケーブルトレイの設置とケーブルトレイ
へのケーブル敷設作業とが行えるという作用が得られ
る。
A first means for achieving the object of the present invention is to provide a concrete slab having a plurality of upper and lower stages projecting from each building into a space between the buildings, and a protruding end of the concrete slab. In the structure of the inter-building cable trench, which is provided with an interval for buffering the transmission of seismic force between the buildings, and a cable tray provided in the upper and lower spaces of each of the concrete slabs, the structure extends from each of the buildings. A receiving beam provided immediately below each of the upper concrete slabs along the upper concrete slab and with a gap for buffering the transmission of seismic force; and at least one of the respective receiving beams is attached to the lower concrete slab. And a supporter supporting from above, wherein the cable tray is supported by the supporter. With such a structure, the shoring can support the load from the upper part, so there is no need to wait for the period to secure the strength of the upper concrete slab, and the shoring is also used as a means for supporting the cable tray. Therefore, the shoring work is regarded as permanent construction, and the operation of installing the cable tray and laying the cable on the cable tray can be performed without the trouble of removing the shoring work.

【0021】同じく第2手段は、第1手段において、上
部の各コンクリートスラブの張り出し長さと各受梁の長
さは、一方の建屋側で短く、他方の建屋側で長い不均等
に設定してあり、少なくとも長尺な受梁は支保工で支持
され、更に、前記支保工でケーブルトレイが支持されて
いることを特徴とした建屋間ケーブルトレンチの構造で
あり、第1手段による作用効果に加えて、張り出し長さ
が長尺なコンクリートスラブは受梁を支保工で支持して
作り、張り出し長さが短尺なコンクリートスラブは受梁
が短くなって、短尺なコンクリートスラブは受梁を片持
支持の状態で採用して支保工無くして作ることができ、
さらには、短尺なコンクリートスラブの下方は狭いにも
かかわらず支保工が存在しないから、短尺なコンクリー
トスラブ側の建設工事とケーブル敷設工事が簡単となる
作用が得られる。
[0021] Similarly, the second means is that, in the first means, the overhang length of each upper concrete slab and the length of each receiving beam are set unequally long on one building side and long on the other building side. There is a structure of a cable trench between buildings, wherein at least a long receiving beam is supported by a shoring, and further, a cable tray is supported by the shoring. In addition to the function and effect of the first means, The concrete slab with a long overhang is made by supporting the beam with a support, the concrete slab with a short overhang is short, and the short concrete slab is cantilevered. It can be made without support and adopted in the state of
Furthermore, since there is no support even though the lower part of the short concrete slab is narrow, an operation of simplifying the construction work and the cable laying work on the short concrete slab side can be obtained.

【0022】同じく第3手段は、各建屋間の間隔間に各
建屋から張り出した下部のコンクリートスラブを建設
し、次に前記下部コンクリートスラブに立てた支保工で
受梁を支持し、前記受梁でデッキプレートを支持し、前
記デッキプレートをコンクリート型枠としてコンクリー
トを打設して前記各建屋から張り出した上部のコンクリ
ートスラブを建設し、さらには前記各コンクリートスラ
ブの向かい合う突端間に地震力の伝達を緩衝する間隔を
設定して前記建屋間の空間に前記各コンクリートスラブ
で上下方向に挟まれた建屋間ケーブルトレンチの設定空
間を建設し、前記建屋間ケーブルトレンチの設定空間に
ケーブルトレイを設置して建設される建屋間ケーブルト
レンチの構造の建設方法において、前記各建屋の一方の
建屋側の上部コンクリートスラブの下方の受梁と他方の
建屋側の上部コンクリートスラブの下方の受梁との間に
地震力の伝達を緩衝する隙間を設定し、さらには前記支
保工にケーブルトレイを支持せしめて、前記支保工と各
受梁とを前記上部コンクリートスラブの建設後において
も前記建屋間ケーブルトレンチの設定空間に残存させる
ことを特徴とした建屋間ケーブルトレンチの構造の建設
方法であり、建設時に上部コンクリートスラブの設計強
度が出るまで受梁と支保工で上部コンクリートスラブを
支持するので、その設計強度が出る以前から建屋間ケー
ブルトレンチの設定空間内でケーブルの敷設作業が行
え、且つ支保工をケーブルトレイの支持手段として本設
化して撤去しなくて済むから、上部コンクリートスラブ
の設計強度を待たずして、さらには支保工の撤去を伴わ
ずに建屋間ケーブルトレンチの設定空間内でケーブルの
敷設作業が行えるという作用が得られる。
[0022] Similarly, the third means is to construct a lower concrete slab projecting from each building between the buildings, and to support a receiving beam with a supporter standing on the lower concrete slab. To support the deck plate, cast concrete using the deck plate as a concrete formwork to construct an upper concrete slab projecting from each of the buildings, and furthermore, to transmit seismic force between the opposite ends of each of the concrete slabs. Constructing a setting space for a cable trench between buildings vertically sandwiched by the concrete slabs in the space between the buildings by setting a buffering interval, and installing a cable tray in the setting space for the cable trench between the buildings. In the method for constructing a structure of a cable trench between buildings to be constructed in a building, an upper concrete on one building side of each of the buildings is provided. Setting a gap for buffering the transmission of seismic force between the lower beam of the upper slab and the lower beam of the upper concrete slab on the other building side, and further supporting the cable tray on the support, A method of constructing a structure of an inter-building cable trench, wherein a support and each beam are left in a set space of the inter-building cable trench even after the construction of the upper concrete slab. Since the upper concrete slab is supported by beams and supports until the design strength of the cable is obtained, the work of laying cables can be performed in the setting space of the cable trench between buildings before the design strength is obtained, and Since it is not necessary to remove it by installing it as a support means, it is not necessary to wait for the design strength of the upper concrete slab, and it is also supported. The effect of enabling laying work cables can be obtained in the configuration space of the building between the cable trenches without removal.

【0023】同じく第4手段は、第3手段において、下
部コンクリートスラブを建設した後に、デッキプレート
と受梁と支保工とケーブルトレイとを相対的位置関係が
建屋間ケーブルトレンチの設定空間内での設置状態と同
じくなるように組み合わせたブロック構造物を、前記下
部コンクリートスラブ上に搬入し、その後に、上部コン
クリートスラブを建設することを特徴とした建屋間ケー
ブルトレンチの構造の建設方法であり、第3手段による
作用に加えて、ケーブルトレンチを作る際に必要な部材
が位置関係が建設位置関係にされた状態でブロック化さ
れたまま一括して建設位置に搬入できて工期が一層短縮
する作用が得られる。
[0023] Similarly, in the fourth means, in the third means, after the lower concrete slab is constructed, the relative positional relationship between the deck plate, the receiving beam, the shoring, and the cable tray is determined in the setting space of the inter-building cable trench. A method of constructing a structure of an inter-building cable trench, characterized by carrying a block structure combined in the same manner as the installation state on the lower concrete slab, and thereafter constructing an upper concrete slab. In addition to the functions of the three means, the members required for forming the cable trench can be collectively transported to the construction position while being blocked in a state where the positional relationship is in the construction positional relationship, and the operation period is further shortened. can get.

【0024】同じく第5手段は、第3手段において、各
建屋のコンクリートスラブの内、一方の建屋のコンクリ
ートスラブの張り出し長さを短くして短尺なコンクリー
トスラブを建設し、他方の建屋のコンクリートスラブの
張り出し長さを長くして長尺なコンクリートスラブを建
設し、前記長尺なコンクリートスラブで上下方向を挟ま
れた空間側での建屋間ケーブルトレンチの建設方法とし
て第4手段の方法を用いたことを特徴とした建屋間ケー
ブルトレンチの構造の建設方法であり、第3手段による
作用効果に加えて、長尺な上部コンクリートスラブ側の
建設を第4手段に示すブロック構造物を用いて効率よく
行い、他方の短尺な上部コンクリートスラブ側での建設
に際しては、受梁は短くて済むので、建屋の壁から片持
支持した状態で受梁を建設に採用できるようになり、短
尺な上部コンクリートスラブの下方には支保工のない状
態でケーブルトレイの設置やケーブルの敷設作業が効率
よく行えるという作用が得られる。
A fifth means is the third means, wherein the concrete slab of each building is shortened to construct a short concrete slab, and the concrete slab of the other building is shortened. A long concrete slab was constructed by extending the overhang length of the concrete slab, and the method of the fourth means was used as a method of constructing the inter-building cable trench on the space side vertically sandwiched by the long concrete slab. A method of constructing a structure of a cable trench between buildings, characterized by the fact that, in addition to the function and effect of the third means, the construction of a long upper concrete slab side is efficiently performed using a block structure shown in a fourth means. In the case of construction on the other short upper concrete slab side, the receiving beam is short, so the beam is supported cantilevered from the building wall. The now be employed in the construction, effect that installation and laying work cables cable tray in the absence of shoring below the short upper concrete slab can be performed efficiently is obtained.

【0025】同じく第6手段は、コンクリート型枠と、
前記コンクリート型枠が装着されて前記コンクリート型
枠を支持する受梁と、前記受梁に装着されて前記受梁を
下方から支持する支保工と、前記支保工に支持されるよ
うに装着されたケーブルトレイと、を一体化して構成し
た建屋間ケーブルトレンチの建設方法に用いるブロック
構造物であり、このブロック構造物は建屋間ケーブルト
レンチの建設に必要な構造物を一体化してあるので、そ
のブロック構造物を建屋間ケーブルトレンチの建設位置
に持ち込むことでその建設位置に建設に必要な複数の部
品が一気に揃い、建設工期を短縮させる作用が得られ
る。
Similarly, the sixth means comprises a concrete formwork,
A receiving beam to which the concrete formwork is mounted to support the concrete formwork, a shoring mounted to the receiving beam to support the receiving beam from below, and mounted to be supported by the shoring It is a block structure used for a method of constructing an inter-building cable trench in which a cable tray and an inter-building cable trench are integrated. Since this block structure integrates a structure necessary for the construction of an inter-building cable trench, the block structure is By bringing the structure to the construction position of the inter-building cable trench, a plurality of components necessary for construction are provided at once at the construction position, and an effect of shortening the construction period is obtained.

【0026】[0026]

【発明の実施の形態】本発明の実施例に係わる原子力発
電所は、図1のように、原子炉建屋8とタービン建屋9
と廃棄物建屋10とコントロール建屋11とサービス建
屋12との各建屋が存在している。
DESCRIPTION OF THE PREFERRED EMBODIMENTS A nuclear power plant according to an embodiment of the present invention comprises a reactor building 8 and a turbine building 9 as shown in FIG.
And a waste building 10, a control building 11, and a service building 12.

【0027】コントロール建屋11は、各建屋内の設備
を制御する設備を備えているから、各建屋との間で電気
ケーブルなどのケーブル類が多数本引き回されている。
Since the control building 11 is equipped with equipment for controlling the equipment in each building, a large number of cables such as electric cables are routed between each building.

【0028】それらのケーブルを通過ささせるためのケ
ーブルトレンチがコントロール建屋11と原子炉建屋8
との間に、図1のハッチングで示した建屋間隔間に建設
される。
Cable trenches for passing these cables are formed in the control building 11 and the reactor building 8.
And between the building intervals shown by hatching in FIG.

【0029】そのケーブルトレンチの設定空間14は、
図2,図3の様に、原子炉建屋8の壁とコントロール建
屋11の壁と各上部コンクリートスラブ6aと各下部コ
ンクリートスラブ6bとで囲われた範囲の空間である。
The setting space 14 of the cable trench is
As shown in FIGS. 2 and 3, the space is a space surrounded by the wall of the reactor building 8, the wall of the control building 11, each upper concrete slab 6a, and each lower concrete slab 6b.

【0030】このようなケーブルトレンチの設定空間1
4は、グランドレベル(GL)より下方に存在してお
り、次のようにして建設される。
Setting space 1 for such a cable trench
4 exists below the ground level (GL) and is constructed as follows.

【0031】まず、原子炉建屋8とコントロール建屋1
1とから各下部コンクリートスラブ6bを張り出して建
設し、各下部コンクリートスラブ6bの互いに接近し合
う突端の間には、地震力が建屋間で伝達しにくい様に、
緩衝用の隙間13を設けてある。
First, the reactor building 8 and the control building 1
1 and each lower concrete slab 6b is extended and constructed. Between the protruding ends of each lower concrete slab 6b, seismic force is hardly transmitted between the buildings.
A buffer gap 13 is provided.

【0032】各下部コンクリートスラブ6bの内、原子
炉建屋8側の下部コンクリートスラブ6bはコントロー
ル建屋11側の下部コンクリートスラブ6bよりも張り
出し長さが短く建設される。
Of the lower concrete slabs 6b, the lower concrete slab 6b on the reactor building 8 side is constructed to be shorter than the lower concrete slab 6b on the control building 11 side.

【0033】ケーブルトレイ5の設置ルートと同じケー
ブルの敷設ルートは図2の斜線で示した様に、コントロ
ール建屋11寄りと、原子炉建屋8寄りと、それらの間
の中央との3ルートが存在する。
As shown by the diagonal lines in FIG. 2, there are three routes for laying the same cables as the route for installing the cable tray 5, namely, the route near the control building 11, the route near the reactor building 8, and the center between them. I do.

【0034】その内の2ルートの下方をカバーする長さ
にコントロール建屋11側の下部コンクリートスラブ6
bの張り出し長さが設定されている。
The lower concrete slab 6 on the control building 11 side has a length covering the lower part of the two routes.
The overhang length of b is set.

【0035】各下部コンクリートスラブ6bの強度が設
計強度になった後に、その設計強度が出る前に予め製作
されていたブロック構造物をコントロール建屋11側の
下部コンクリートスラブ6bの上部にクレーンによって
吊り込む。
After the strength of each lower concrete slab 6b has reached the design strength, the block structure previously manufactured before the design strength is released is suspended by a crane above the lower concrete slab 6b on the control building 11 side. .

【0036】このブロック構造物は、コントロール建屋
11側の下部コンクリートスラブ6bの張り出し長さに
ほぼ匹敵する長さのH型鋼製の長尺な受梁1aと、その
受梁1aの両端近傍において固定されて前記受梁1aを
支持するH型鋼製の各支保工4a,4bと、前記受梁1
aの上部に固定されたデッキプレート2aと、前記支保
工4a,4bに固定された山型鋼製のケーブルトレイ受
け7と、前記ケーブルトレイ受け7に搭載して設置され
たケーブルトレイ5とから構成され、これらのブロック
化された構成部品は建設位置に設置される位置関係と同
じ位置関係でブロック内での相対的位置関係が決定され
ている。
The block structure is composed of a long H-shaped steel beam 1a having a length substantially equal to the overhang length of the lower concrete slab 6b on the control building 11 side, and the vicinity of both ends of the beam 1a. H-shaped steel supports 4a, 4b fixed to support the receiving beam 1a;
a, a deck plate 2a fixed to an upper portion of the cable tray 5, a cable tray receiver 7 made of angle steel fixed to the supports 4a, 4b, and a cable tray 5 mounted on the cable tray receiver 7. The relative positions in the block are determined based on the same positional relationship as that of the constituent components that are configured and arranged in the construction position.

【0037】このようなブロック構造物がコントロール
建屋11側の下部コンクリートスラブ6b上にクレーン
で搬入されたら、建設時にその下部コンクリートスラブ
6bに予め設置しておいたアンカーボルト等を用いて支
保工4a,4bの下端を下部コンクリートスラブ6bに
固定設置する。
When such a block structure is carried into the lower concrete slab 6b on the control building 11 side by a crane, the support 4a is constructed using anchor bolts or the like previously installed on the lower concrete slab 6b during construction. , 4b are fixedly installed on the lower concrete slab 6b.

【0038】他方の原子炉建屋8側の下部コンクリート
スラブ6bの上方においては、H型鋼製の短尺な受梁1
bを上部コンクリートスラブ6aを建設する下端位置の
高さで原子炉建屋8の壁に一端を固定し、他端はその壁
から突き出してある。
Above the lower concrete slab 6b on the other reactor building 8 side, a short beam 1 made of H-section steel is used.
b is fixed at one end to the wall of the reactor building 8 at the height of the lower end position for constructing the upper concrete slab 6a, and the other end protrudes from the wall.

【0039】このように、短尺な受梁1bを原子炉建屋
8の壁から片持支持し、その上にデッキプレート2bを
搭載して両者を固定する。
As described above, the short receiving beam 1b is cantilevered from the wall of the reactor building 8, and the deck plate 2b is mounted thereon to fix them.

【0040】各受梁1a,1bで支持したデッキプレー
ト2a,2b上では、鉄筋を配筋し、コンクリートをデ
ッキプレート2a,2b上に配筋と絡めて打設し、各上
部コンクリートスラブ6aを建設する。
On the deck plates 2a, 2b supported by the respective receiving beams 1a, 1b, reinforcing bars are arranged, concrete is entangled with the reinforcing bars on the deck plates 2a, 2b, and each upper concrete slab 6a is mounted. to build.

【0041】地震力が各建屋間で伝達されることを防ぐ
ために、各上部コンクリートスラブ6a間には緩衝用の
隙間13が作られている。
In order to prevent the seismic force from being transmitted between the buildings, a buffer gap 13 is formed between the upper concrete slabs 6a.

【0042】このような隙間13については各受梁1
a,1b同志間でも同様に設けられている。
With respect to such a gap 13, each of the receiving beams 1
a and 1b are similarly provided between competitors.

【0043】各上部コンクリートスラブ6aを建設する
際のコンンクリート打設作業時の荷重は、原子炉建屋8
側の張り出し長さが短い短尺な上部コンクリートスラブ
6a側では短尺な受梁1bが支持し、コントロール建屋
11側の張り出し長さが長い長尺な上部コンクリートス
ラブ6a側では受梁1aを介して支保工4a,4bが支
持する。
When constructing each of the upper concrete slabs 6a, the load at the time of placing concrete is limited to the reactor building 8
A short receiving beam 1b is supported on the short upper concrete slab 6a side having a short overhang length on the side, and is supported via the receiving beam 1a on a long overhanging long concrete slab 6a side on the control building 11 side. Work 4a, 4b supports.

【0044】その後に、上部コンクリートスラブ6aの
設計強度が出るのを待たずに、予め原子炉建屋8の壁面
に埋め込んでおいた金物にケーブルトレイサポート3を
固定してそのケーブルトレイサポート3に山型鋼製のケ
ーブルトレイ受け7を固定し、そのケーブルトレイ受け
7にケーブルトレイ5を搭載して装着する。
Thereafter, without waiting for the design strength of the upper concrete slab 6a to come out, the cable tray support 3 is fixed to hardware previously embedded in the wall of the reactor building 8, and the cable tray support 3 is mounted on the cable tray support 3. The cable tray receiver 7 made of die steel is fixed, and the cable tray 5 is mounted on the cable tray receiver 7 and mounted.

【0045】このような、ケーブルトレンチの設定空間
14内での組立作業は、原子炉建屋8側の上部コンクリ
ートスラブ6a側下方に支保工4a,4bが一切存在し
ないからその作業の障害となるものがなく、その作業が
円滑に行える。
The assembling work in the cable trench setting space 14 is an obstacle to the work because there are no supports 4a and 4b below the upper concrete slab 6a on the reactor building 8 side. And the work can be done smoothly.

【0046】この後に、ケーブルトレンチの設定空間1
4内で、ケーブルトレイ5へのケーブルの敷設作業を行
う。
Thereafter, the setting space 1 of the cable trench is set.
In 4, the work of laying cables on the cable tray 5 is performed.

【0047】このようなケーブルトレンチの設定空間1
4内での各種の作業を上部コンクリートスラブ6aが設
計強度に成る前から始めてそれら各種の作業を工程上前
倒しで行う。
Setting space 1 for such a cable trench
The various operations in 4 are started before the upper concrete slab 6a reaches the design strength, and the various operations are performed earlier in the process.

【0048】このようなことによって、ケーブルトレン
チの建設工程のみならず、そのケーブルトレンチを含ん
でいる原子力発電所の建設工程が短縮する。
Thus, not only the construction process of the cable trench but also the construction process of the nuclear power plant including the cable trench are shortened.

【0049】コンクリートが固化して上部コンクリート
スラブ6aが設計強度に達した後には、各上部コンクリ
ートスラブの上面に防水シート等のシートをかぶせ、緩
衝用の隙間13は、その隙間13にかけ渡されたプチル
ゴム製の止水板と発泡スチロールで覆われている。その
シート上に土15をグランドレベル(GL)に達するま
で盛る。
After the concrete has solidified and the upper concrete slab 6a has reached the design strength, a sheet such as a waterproof sheet is placed on the upper surface of each upper concrete slab, and the cushioning gap 13 is passed over the gap 13. It is covered with a waterproof board made of butyl rubber and Styrofoam. The soil 15 is piled up on the sheet until it reaches the ground level (GL).

【0050】[0050]

【発明の効果】請求項1の発明によれば、支保工をケー
ブルトレイの支持手段として本設採用して仮設部材の採
用が少なくて済む構造である上、上部コンクリートスラ
ブの設計強度を待たずにケーブルの敷設作業が行える構
造であるから、建屋間ケーブルトレンチを有するプラン
トの工期短縮に貢献できる。
According to the first aspect of the present invention, the shoring is used as a supporting means of the cable tray, and the number of temporary members can be reduced, and the design strength of the upper concrete slab can be maintained. Since the structure allows cable laying work, it can contribute to shortening the construction period of a plant having a cable trench between buildings.

【0051】請求項2の発明によれば、請求項1の発明
による効果に加えて、支保工を全く用いない構造を一部
分に採用して一層プラントの工期を短縮できる。
According to the second aspect of the present invention, in addition to the effect of the first aspect of the present invention, the construction period that does not use any shoring can be partially adopted to further shorten the construction period of the plant.

【0052】請求項3の発明によれば、支保工をケーブ
ルトレイの支持手段として本設採用し、仮設資材の採用
が少なく、さらには上部コンクリートスラブの設計強度
の確保を待たずしてケーブルの敷設作業を許容できる建
設方法であるから、建屋間ケーブルトレンチを有するプ
ラントの工期短縮に貢献できる。
According to the third aspect of the present invention, the shoring is permanently installed as a means for supporting the cable tray, the use of temporary materials is reduced, and the cable is not waited for until the design strength of the upper concrete slab is secured. Since the construction method allows laying work, it can contribute to shortening the construction period of a plant having a cable trench between buildings.

【0053】請求項4の発明によれば、請求項3の発明
による効果に加えて、ケーブルトレンチ内の構造を構成
する複数の部品を一気に建設位置に搬入できるので、一
層プラントの建設工期の短縮に貢献できる。
According to the invention of claim 4, in addition to the effect of the invention of claim 3, a plurality of parts constituting the structure in the cable trench can be carried at once to the construction position, so that the construction period of the plant is further shortened. Can contribute to

【0054】請求項5の発明によれば、請求項3の発明
による効果に加えて、ブロック構造物採用による建設工
程の短縮と、支保工を全く用いない建設工程による短縮
化とを併用してなお一層プラントの建設工期の短縮に貢
献できる。
According to the fifth aspect of the present invention, in addition to the effect of the third aspect of the present invention, the shortening of the construction process by employing the block structure and the shortening by the construction process using no support work are used in combination. This can further contribute to shortening the construction period of the plant.

【0055】請求項6の発明によれば、建屋間ケーブル
トレンチの建設に必要な複数の部品が一気に搬入して建
設位置に揃えさせることができるので、この発明のブロ
ック構造物を採用すると建屋間ケーブルトレンチの建設
工期を短縮させる効果が得られる。
According to the sixth aspect of the present invention, a plurality of parts necessary for the construction of the inter-building cable trench can be carried at once and aligned at the construction position. The effect of shortening the construction period of the cable trench can be obtained.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明が適用される箇所をハッチングで示した
原子力発電所の建屋の平面配置図である。
FIG. 1 is a plan view of a building of a nuclear power plant, in which parts to which the present invention is applied are indicated by hatching.

【図2】本発明による建屋間ケーブルトレンチの支保工
とケーブルトレイの平面配置図である。
FIG. 2 is a plan view of a support for a cable trench between buildings and a cable tray according to the present invention.

【図3】図2のI−I矢視から見た本発明による建屋間
ケーブルトレンチの縦断面図である。
FIG. 3 is a longitudinal sectional view of the cable trench between buildings according to the present invention viewed from the arrow II in FIG. 2;

【図4】従来例の建屋間ケーブルトレンチの支保工とケ
ーブルトレイの平面配置図である。
FIG. 4 is a plan view of a conventional example of supporting a cable trench between buildings and a cable tray.

【図5】図4のII−II矢視から見た従来例の建屋間ケー
ブルトレンチの縦断面図である。
FIG. 5 is a longitudinal sectional view of the cable trench between buildings of the conventional example viewed from the direction of arrows II-II in FIG. 4;

【符号の説明】[Explanation of symbols]

1a,1b…受梁、2a,2b…デッキプレート、3…
ケーブルトレイサポート、4a,4b…支保工、5…ケ
ーブルトレイ、6a…上部コンクリートスラブ、6b…
下部コンクリートスラブ、7…ケーブルトレイ受け、8
…原子炉建屋、11…コントロール建屋、13…隙間。
1a, 1b ... receiving beam, 2a, 2b ... deck plate, 3 ...
Cable tray support, 4a, 4b: Shoring, 5: Cable tray, 6a: Upper concrete slab, 6b ...
Lower concrete slab, 7 Cable tray receiver, 8
... Reactor building, 11 ... Control building, 13 ... Gap.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 小池 勝則 東京都千代田区麹町三丁目5番 株式会社 日立建設設計内 ──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Katsunori Koike 3-5 Kojimachi, Chiyoda-ku, Tokyo Hitachi Construction Design Co., Ltd.

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】各建屋から各建屋間の空間に張り出した上
下多段のコンクリートスラブと、前記コンクリートスラ
ブの突端間に設けられて前記建屋間での地震力の伝達を
緩衝する間隔と、前記各コンクリートスラブの上下空間
内に装備されたケーブルトレイとを備えた建屋間ケーブ
ルトレンチにおいて、 前記各建屋から張り出された上段の各コンクリートスラ
ブの直下に前記上段のコンクリートスラブに沿って且つ
地震力の伝達を緩衝する隙間を隔てて装備された各受梁
と、前記各受梁の少なくとも一方を前記下段のコンクリ
ートスラブ上から支持する支保工とを備え、前記支保工
に前記ケーブルトレイを支持せしめたことを特徴とした
建屋間ケーブルトレンチ。
An upper and lower multi-stage concrete slab projecting from each building to a space between the buildings, an interval provided between protruding ends of the concrete slab to buffer transmission of seismic force between the buildings, In a cable trench between buildings provided with cable trays installed in the upper and lower spaces of the concrete slab, the seismic force is generated along the upper concrete slab directly under each of the upper concrete slabs extending from each of the buildings. Each of the receiving beams is provided with a gap for buffering the transmission, and a shoring supporting at least one of the receiving beams from above the lower concrete slab is provided. The supporting tray supports the cable tray. Cable trench between buildings characterized by the following.
【請求項2】請求項1において、上部の各コンクリート
スラブの張り出し長さと各受梁の長さは、一方の建屋側
で短く、他方の建屋側で長い不均等に設定してあり、少
なくとも長尺な受梁は支保工で支持され、更に、前記支
保工でケーブルトレイが支持されていることを特徴とし
た建屋間ケーブルトレンチ。
2. The structure according to claim 1, wherein the overhang length of each of the upper concrete slabs and the length of each of the receiving beams are unequally set to be short on one building side and long on the other building side. The inter-building cable trench, wherein the long receiving beam is supported by a shoring, and further the cable tray is supported by the shoring.
【請求項3】各建屋間の間隔間に各建屋から張り出した
下部のコンクリートスラブを建設し、次に前記下部コン
クリートスラブに立てた支保工で受梁を支持し、前記受
梁でデッキプレートを支持し、前記デッキプレートをコ
ンクリート型枠としてコンクリートを打設して前記各建
屋から張り出した上部のコンクリートスラブを建設し、
さらには前記各コンクリートスラブの向かい合う突端間
に地震力の伝達を緩衝する間隔を設定して前記建屋間の
空間に前記各コンクリートスラブで上下方向に挟まれた
建屋間ケーブルトレンチの設定空間を建設し、前記建屋
間ケーブルトレンチの設定空間にケーブルトレイを設置
して建設される建屋間ケーブルトレンチの建設方法にお
いて、 前記各建屋の一方の建屋側の上部コンクリートスラブの
下方の受梁と他方の建屋側の上部コンクリートスラブの
下方の受梁との間に地震力の伝達を緩衝する隙間を設定
し、さらには前記支保工にケーブルトレイを支持せしめ
て、前記支保工と各受梁とを前記上部コンクリートスラ
ブの建設後においても前記建屋間ケーブルトレンチの設
定空間に残存させることを特徴とした建屋間ケーブルト
レンチの建設方法。
3. A lower concrete slab projecting from each building is constructed between the buildings, and a supporting beam is supported by a supporter erected on the lower concrete slab, and a deck plate is supported by the receiving beam. Supporting, constructing an upper concrete slab that overhangs from each building by casting concrete with the deck plate as a concrete formwork,
Further, a space for buffering the transmission of seismic force is set between the opposite ends of each of the concrete slabs, and a set space for a cable trench between buildings sandwiched vertically by each of the concrete slabs is constructed in the space between the buildings. A method of constructing a cable trench between buildings, wherein the cable tray is constructed by setting a cable tray in a setting space of the cable trench between buildings, wherein: a receiving beam below an upper concrete slab on one building side of each of the buildings and the other building side; A gap for buffering the transmission of seismic force is set between the upper concrete slab and the lower beam of the upper concrete slab, and further, a cable tray is supported by the shoring, and the shoring and each of the receiving beams are connected to the upper concrete slab. A cable trench between buildings characterized by being left in a set space of the cable trench between buildings even after the slab is constructed. Installation method.
【請求項4】請求項3において、下部コンクリートスラ
ブを建設した後に、デッキプレートと受梁と支保工とケ
ーブルトレイとを相対的位置関係が建屋間ケーブルトレ
ンチの設定空間内での設置状態と同じくなるように組み
合わせたブロック構造物を、前記下部コンクリートスラ
ブ上に搬入し、その後に、上部コンクリートスラブを建
設することを特徴とした建屋間ケーブルトレンチの建設
方法。
4. The construction of claim 3, wherein after the lower concrete slab is constructed, the relative positional relationship between the deck plate, the receiving beam, the shoring, and the cable tray is the same as the installation state of the inter-building cable trench in the set space. A method of constructing a cable trench between buildings, wherein a block structure combined as described above is carried into the lower concrete slab, and thereafter, an upper concrete slab is constructed.
【請求項5】請求項3において、各建屋のコンクリート
スラブの内、一方の建屋のコンクリートスラブの張り出
し長さを短くして短尺なコンクリートスラブを建設し、
他方の建屋のコンクリートスラブの張り出し長さを長く
して長尺なコンクリートスラブを建設し、前記長尺なコ
ンクリートスラブで上下方向を挟まれた空間側での建屋
間ケーブルトレンチの構造の建設方法として請求項4の
方法を用いたことを特徴とした建屋間ケーブルトレンチ
の建設方法。
5. The concrete slab according to claim 3, wherein the length of the concrete slab of one of the concrete slabs in each of the buildings is shortened to construct a short concrete slab.
A long concrete slab is constructed by extending the overhang length of the concrete slab of the other building, and as a construction method of a structure of a cable trench between buildings on the space side vertically sandwiched by the long concrete slab. A method for constructing a cable trench between buildings using the method according to claim 4.
【請求項6】コンクリート型枠と、前記コンクリート型
枠が装着されて前記コンクリート型枠を支持する受梁
と、前記受梁に装着されて前記受梁を下方から支持する
支保工と、前記支保工に支持されるように装着されたケ
ーブルトレイと、を一体化して構成した建屋間ケーブル
トレンチの建設方法に用いるブロック構造物。
6. A concrete formwork, a receiving beam on which the concrete formwork is mounted to support the concrete formwork, a shoring mounted on the receiving beam and supporting the receiving form from below, A block structure used in a method of constructing an inter-building cable trench, in which a cable tray mounted so as to be supported by a worker is integrated.
JP10069762A 1998-03-19 1998-03-19 Cable trench between buildings and its construction method and block structure used for the construction method Pending JPH11264886A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10069762A JPH11264886A (en) 1998-03-19 1998-03-19 Cable trench between buildings and its construction method and block structure used for the construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10069762A JPH11264886A (en) 1998-03-19 1998-03-19 Cable trench between buildings and its construction method and block structure used for the construction method

Publications (1)

Publication Number Publication Date
JPH11264886A true JPH11264886A (en) 1999-09-28

Family

ID=13412151

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10069762A Pending JPH11264886A (en) 1998-03-19 1998-03-19 Cable trench between buildings and its construction method and block structure used for the construction method

Country Status (1)

Country Link
JP (1) JPH11264886A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017187563A1 (en) * 2016-04-27 2017-11-02 三菱日立パワーシステムズ株式会社 Turbine building and nuclear power plant

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017187563A1 (en) * 2016-04-27 2017-11-02 三菱日立パワーシステムズ株式会社 Turbine building and nuclear power plant
CN108885910A (en) * 2016-04-27 2018-11-23 三菱日立电力系统株式会社 Steam turbine building and nuclear power station

Similar Documents

Publication Publication Date Title
US20200190799A1 (en) Prefabricated frame
JP4078367B2 (en) Cable-stayed cable fixing structure
KR100728106B1 (en) Cantilever construction structure of slab for bridge and the method thereof
WO2020138994A1 (en) Beam form system, beam form manufacturing system, and beam form manufacturing and providing method
KR100891347B1 (en) Supporting structure of slab form
JPH11264886A (en) Cable trench between buildings and its construction method and block structure used for the construction method
JP4073746B2 (en) Construction method of corrugated steel web bridge
JP3832651B2 (en) Corrugated steel web bridge construction method
JP2022009519A (en) Superstructure member conveyance facility and superstructure member conveyance method
CN112359965A (en) Precast concrete assembled structure with rib mold structure and construction method thereof
JPH1162085A (en) Formation of surface part and panel thereof
JPH0657710A (en) Construction of concrete main tower
JP2836441B2 (en) Flat slab construction without shoring
KR102226883B1 (en) Insert panel connector installed on various slab and construction method for insert panel using that
JP3826352B2 (en) Assembling the deck unit
JP2674470B2 (en) Floor frame structure by combining precast members
JP2885023B2 (en) Construction method of reinforced concrete slab which does not need support under slab and temporary beam generating peeling
JP4511080B2 (en) Construction method of underground structure
JP3008040B2 (en) Large span composite slab erection method
JP2774066B2 (en) Floor slab made of PC version
KR100379574B1 (en) Installing and separating system of outer steel form wall
JPH10121417A (en) Concrete frame, and method for constructing concrete structure using this concrete frame
JP2987469B2 (en) Staircase structure
JPH03107047A (en) Constructing method for slab
JP2004052369A (en) Floor structure

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20040106