JPH1122393A - Joint method of steel-made segment - Google Patents

Joint method of steel-made segment

Info

Publication number
JPH1122393A
JPH1122393A JP9196534A JP19653497A JPH1122393A JP H1122393 A JPH1122393 A JP H1122393A JP 9196534 A JP9196534 A JP 9196534A JP 19653497 A JP19653497 A JP 19653497A JP H1122393 A JPH1122393 A JP H1122393A
Authority
JP
Japan
Prior art keywords
segment
neutral axis
segments
joining
web
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP9196534A
Other languages
Japanese (ja)
Other versions
JP3390937B2 (en
Inventor
Takamasa Fukuda
隆正 福田
Takeshi Kouno
剛 弘埜
Yoshio Abe
吉生 安部
Yoshifumi Hattori
佳文 服部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP19653497A priority Critical patent/JP3390937B2/en
Publication of JPH1122393A publication Critical patent/JPH1122393A/en
Application granted granted Critical
Publication of JP3390937B2 publication Critical patent/JP3390937B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To have a sufficient proof stress for bending. SOLUTION: A steel-made segment set only upward of a neutral axis is used for the end plate 2 of the joining face of a segment. At the time of joining, the end plates 2 upward of the neutral axis of the segment 1 are mutually joined by short bolts 3. One end of a splice plate 5 is fixed by a bolt on the web 41 and the lower flange 42 of a main beam 4 orthogonal to the central axis direction of a tunnel for an opening part downward of the neutral axis. The other end of the splice plate 5 is bolt-tightened on the web 41 and the lower flange 42 of the main beam 4 of the adjacent segment 1 to be fixed.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、鋼製セグメントの
継手方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for joining steel segments.

【0002】[0002]

【従来の技術】シールドトンネルの構築においては、シ
ールド掘進機の掘進にともない、その後方にセグメント
を組み立ててトンネルを構築してゆく。このセグメント
の組み立てに際して、従来は短ボルトで組み立てる引張
接合方式が一般に利用されている。
2. Description of the Related Art In the construction of a shield tunnel, a tunnel is constructed by assembling segments behind the shield tunneling machine as the tunnel machine excavates. Conventionally, when assembling the segments, a tension joining method of assembling with short bolts is generally used.

【0003】[0003]

【本発明が解決しようとする課題】しかし、異形断面シ
ールドトンネルに用いるセグメントは、一般の円形シー
ルドトンネルのセグメントと異なり、主桁が曲げ部材と
なる。そのために曲げに対して十分な剛性を備えたセグ
メントの継手方法の開発が必要となっている。
However, the segment used for the shield tunnel of a modified cross section differs from the segment of a general circular shield tunnel, and the main girder is a bending member. Therefore, it is necessary to develop a joint method for a segment having sufficient rigidity against bending.

【0004】本発明は上記したような従来の問題を解決
するためになされたもので、曲げに対して十分な耐力を
持つ、鋼製セグメントの継手方法を提供することを目的
とする。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned conventional problems, and has as its object to provide a method of joining steel segments having sufficient strength against bending.

【0005】[0005]

【課題を解決するための手段】上記のような目的を達成
するために、本発明の鋼製セグメントの継手方法は、セ
グメントの接合面の端板を、中立軸よりも上方のみに設
置した鋼製セグメントを使用し、接合に際しては、セグ
メントの中立軸よりも上方の端板は相互に短ボルトによ
って接合し、中立軸よりも下方の開放部には、トンネル
の中心軸方向と直交する主桁のウェブに添接板の一端を
ボルトで固定し、添接板の他端を、隣接するセグメント
の主桁のウェブにボルト止めし、さらに両セグメントの
主桁下フランジを添接板を用いてボルト止めして行う、
鋼製セグメントの継手方法を特徴としたものである。
In order to achieve the above object, a method for joining steel segments according to the present invention is directed to a method of joining steel segments in which the end plate of the joining surface of the segments is installed only above the neutral axis. When joining, the end plates above the neutral axis of the segments are mutually joined by short bolts, and the opening below the neutral axis has a main girder perpendicular to the central axis direction of the tunnel. One end of the attachment plate is fixed to the web with bolts, the other end of the attachment plate is bolted to the web of the main girder of the adjacent segment, and the lower flange of the main girder of both segments is further attached using the attachment plate. Do it with bolts,
It is characterized by a method of joining steel segments.

【0006】[0006]

【本発明の実施の態様】以下図面を参照しながら本発明
の鋼製セグメントの継手方法の実施例について説明す
る。
Embodiments of the present invention will be described below with reference to the accompanying drawings.

【0007】<イ>セグメントの形状。 本発明の方法では、鋼製のセグメント1を使用する。そ
してこのセグメント1はその接合面の端板を全面に取り
付けず、中立軸よりも上方のみに端板2を設置する。し
たがって端板2の下半分は開放状態である。
<A> Shape of segment In the method according to the invention, a steel segment 1 is used. In this segment 1, the end plate 2 is installed only above the neutral axis without attaching the end plate of the joint surface to the entire surface. Therefore, the lower half of the end plate 2 is open.

【0008】<ロ>端板2の接合。 接合に際して、隣接セグメント1の端板2側を当設する
と、セグメント1の中立軸よりも上方の端板2が接触す
る。そこで端板2を相互に短ボルト3によって接合す
る。
<B> End plate 2 joining. At the time of joining, when the end plate 2 side of the adjacent segment 1 is provided, the end plate 2 above the neutral axis of the segment 1 comes into contact. Then, the end plates 2 are joined to each other by short bolts 3.

【0009】<ハ>添接板のボルト固定。 中立軸よりも下方、すなわち端板2の下方は開放状態で
あるから、トンネルの中心軸方向と直交する主桁4のウ
ェブ41、および主桁4の下側フランジ42の上下面に
添接板5の一端をボルトで固定する。そしてこの添接板
5の他端を、隣接するセグメント1の主桁4のウェブ4
1および下フランジ42にボルト止めする。主桁4には
ボルト穴を開口してあり、添接板5にも同一の位置にボ
ルト穴を開口しておく。したがって、主桁4の両側から
ボルトをセットすることは可能であり、ボルト穴から露
出したねじ部にナットを取り付けて締め付ける。こうし
て両セグメント1のボルトによる固定と同時に、セグメ
ント1の内空側の固定を行う。こうしてセグメント1は
地山側はボルトによる固定、内空側は添接板およびボル
トを用いた摩擦接合による固定を行い、強固に一体化す
る。
<C> Fixing the bolt of the attachment plate. Since the lower part of the neutral shaft, that is, the lower part of the end plate 2 is in an open state, the web 41 of the main girder 4 orthogonal to the central axis direction of the tunnel and the upper and lower surfaces of the lower flange 42 of the main girder 4 5 is fixed at one end with bolts. The other end of the attachment plate 5 is connected to the web 4 of the main girder 4 of the adjacent segment 1.
1 and the lower flange 42. The main girder 4 is provided with a bolt hole, and the attachment plate 5 is also provided with a bolt hole at the same position. Therefore, it is possible to set bolts from both sides of the main girder 4, and a nut is attached to a screw portion exposed from the bolt hole and tightened. In this way, the fixing of the segments 1 on the inner space side is performed simultaneously with the fixing of the segments 1 by the bolts. In this way, the segments 1 are fixed firmly by bolts on the ground side and fixed by friction joining using the attachment plate and bolts on the inner space side.

【0010】[0010]

【本発明の効果】本発明の鋼製セグメント1の継手方法
は以上説明したように、セグメント1の中立軸よりも地
山側は端板2をボルトによって固定し、中立軸より引張
側には添接板5をボルト止めし、摩擦接合によって固定
してある。したがって継手部は、曲げに対して主桁4部
分と同等、もしくはそれ以上の十分な剛性を得ることが
できる。
As described above, the joint method of the steel segment 1 according to the present invention, as described above, fixes the end plate 2 on the ground side from the neutral axis of the segment 1 with bolts, and attaches the end plate 2 to the tension side from the neutral axis. The contact plate 5 is bolted and fixed by friction welding. Therefore, the joint portion can obtain sufficient rigidity against bending, which is equal to or greater than that of the main girder 4 portion.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の鋼製セグメントの継手方法の実施例の
説明図。
FIG. 1 is an explanatory view of an embodiment of a method for joining steel segments according to the present invention.

【図2】増設フランジに添接板を取り付けた状態の説明
図。
FIG. 2 is an explanatory view of a state where an attachment plate is attached to an additional flange.

【図3】セグメントとセグメントとを接合した状態の説
明図。
FIG. 3 is an explanatory view of a state where segments are joined together.

フロントページの続き (72)発明者 服部 佳文 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内Continued on the front page (72) Inventor Yoshifumi Hattori 1-25-1, Nishishinjuku, Shinjuku-ku, Tokyo Taisei Corporation

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】セグメントの接合面の端板を、中立軸より
も上方のみに設置した鋼製セグメントを使用し、 接合に際しては、セグメントの中立軸よりも上方の端板
は相互に短ボルトによって接合し、 中立軸よりも下方の開放部には、 トンネルの中心軸方向と直交する主桁のウェブに、添接
板の一端をボルトで固定し、 添接板の他端を、隣接するセグメントの主桁のウェブに
ボルト止めし、 さらに両セグメントの主桁下フランジを添接板を用いて
ボルト止めして固定して行う、 鋼製セグメントの継手方法
1. A steel segment in which the end plates of the joining surfaces of the segments are provided only above the neutral axis, and at the time of joining, the end plates above the neutral axis of the segments are mutually connected by short bolts. At the opening below the neutral axis, one end of the contact plate is fixed to the web of the main girder perpendicular to the center axis direction of the tunnel with bolts, and the other end of the contact plate is connected to the adjacent segment. Bolting to the web of the main girder, and fixing the lower flanges of the main girder of both segments by bolting using an attachment plate.
JP19653497A 1997-07-07 1997-07-07 Steel segment fitting method Expired - Fee Related JP3390937B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP19653497A JP3390937B2 (en) 1997-07-07 1997-07-07 Steel segment fitting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP19653497A JP3390937B2 (en) 1997-07-07 1997-07-07 Steel segment fitting method

Publications (2)

Publication Number Publication Date
JPH1122393A true JPH1122393A (en) 1999-01-26
JP3390937B2 JP3390937B2 (en) 2003-03-31

Family

ID=16359347

Family Applications (1)

Application Number Title Priority Date Filing Date
JP19653497A Expired - Fee Related JP3390937B2 (en) 1997-07-07 1997-07-07 Steel segment fitting method

Country Status (1)

Country Link
JP (1) JP3390937B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007277953A (en) * 2006-04-07 2007-10-25 Nippon Steel Corp Segment connecting structure and arrangement structure
JP2007277954A (en) * 2006-04-07 2007-10-25 Nippon Steel Corp Connecting structure between segment rings
JP2008255669A (en) * 2007-04-05 2008-10-23 Taisei Corp Segment
JP2009270378A (en) * 2008-05-09 2009-11-19 Taisei Corp Underground structure
JP2012162877A (en) * 2011-02-04 2012-08-30 Taisei Corp Construction method for underground structure, and the underground structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007277953A (en) * 2006-04-07 2007-10-25 Nippon Steel Corp Segment connecting structure and arrangement structure
JP2007277954A (en) * 2006-04-07 2007-10-25 Nippon Steel Corp Connecting structure between segment rings
JP2008255669A (en) * 2007-04-05 2008-10-23 Taisei Corp Segment
JP2009270378A (en) * 2008-05-09 2009-11-19 Taisei Corp Underground structure
JP2012162877A (en) * 2011-02-04 2012-08-30 Taisei Corp Construction method for underground structure, and the underground structure

Also Published As

Publication number Publication date
JP3390937B2 (en) 2003-03-31

Similar Documents

Publication Publication Date Title
JPH1122393A (en) Joint method of steel-made segment
JPH0681312A (en) Joint structure for main girder of bridge and the like
JPH07238635A (en) Web opening part reinforcing method of steel structural beam
JPH1113395A (en) Joining method of steel segment
JP4444555B2 (en) Joint structure of civil engineering structure
JPH04260593A (en) Escalator truss
JPH06101271A (en) Method of joint construction of steel frame girder and joint structure
JPH10115197A (en) Joint structure of steel material and reinforcing plate used therein
JPH11287097A (en) Segment
JP2000027295A (en) Connecting method of column to beam in steel structure
JP3094894B2 (en) Steel segment joint structure
JPH1122392A (en) Joint method of steel-made segment
JPH09125515A (en) Pillar beam connection part structure
JP2660845B2 (en) Iron segment
JP2000096993A (en) Bolt joint of unit shield steel shell in outer shell preceding tunnel method
JPH0849345A (en) Member for reinforcing beam
JP2626854B2 (en) Column-column joint structure
JPH01304236A (en) Joint structure for column and beam
JP2904366B2 (en) Steel segment joint device and steel segment used for the joint device
JP2942704B2 (en) segment
JPH07173870A (en) Column beam joint structure and assembly method thereof
JPH03290565A (en) Erection method of beam
JPH0440323Y2 (en)
JPH02161033A (en) Double-shaft brace and fitting thereof
JP2003120195A (en) Connection structure and connection method for segment

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees