JPH11124612A - Device for assembling and disassembling blast furnace and method for assembling and disassembling thereof - Google Patents

Device for assembling and disassembling blast furnace and method for assembling and disassembling thereof

Info

Publication number
JPH11124612A
JPH11124612A JP28373297A JP28373297A JPH11124612A JP H11124612 A JPH11124612 A JP H11124612A JP 28373297 A JP28373297 A JP 28373297A JP 28373297 A JP28373297 A JP 28373297A JP H11124612 A JPH11124612 A JP H11124612A
Authority
JP
Japan
Prior art keywords
mantel
furnace
furnace body
blast furnace
partial
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP28373297A
Other languages
Japanese (ja)
Other versions
JP4085293B2 (en
Inventor
Shoji Hanabusa
章次 花房
Minoru Hamada
実 浜田
Hidehiro Kashiwamura
秀宏 柏村
Yoshiaki Nakabayashi
義昭 中林
Kojiro Tsutsumi
康次郎 堤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sankyu Inc
Original Assignee
Sankyu Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sankyu Inc filed Critical Sankyu Inc
Priority to JP28373297A priority Critical patent/JP4085293B2/en
Publication of JPH11124612A publication Critical patent/JPH11124612A/en
Application granted granted Critical
Publication of JP4085293B2 publication Critical patent/JP4085293B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide an effective and economical assembling and disassembling device of a blast furnace which can shorten the working time and obtain the safe work. SOLUTION: This device is provided with receiving beams 27 arranged so as to pass through between supporting columns 17 of the furnace body from a casting floor part 9 to both outsides of the furnace body 2, a mantel carriage 29 travelled on the receiving beams 27, the first center hole jackes 32, 33 arranged in the furnace body scaffold 16 and load onto/off from the mantel carriage 29 by hanging up/down the partial mantel 4, the second center hole jack arranged on the furnace body scarffold 16 and supporting the whole or a part loaded to the receiving beams 27 and a tuyere movable safe roof 36 arranged so as to be travellable in the receiving beam 27. The second center hole jack can hang down/up the receiving beams 27 and the mantel carriage 29 in the vertical direction and also, can adjust the horizontal level. The tuyere movable safe roof 36 can execute safely the assembling and the disassembling works to each of the upper side space 40 and the lower side space 41.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、高炉の炉体を組み
立てる又は解体する高炉の組立解体装置及び組立解体方
法に関するものである。尚、以下で使用する「マンテ
ル」は、鉄皮だけのものと、鉄皮にステーブ(又はステ
ーブクーラ)、レンガ等が一体となったものの双方を含
むものとする。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a blast furnace assembling and disassembling apparatus for assembling or disassembling a furnace body of a blast furnace and an assembling and disassembling method. The term "mantel" used below includes both a steel shell alone and a steel shell integrated with a stave (or stove cooler), brick and the like.

【0002】[0002]

【従来の技術】従来、高炉の炉体を組み立て又は解体す
る高炉の組立解体装置或いは組立解体方法は、据付用に
炉頂櫓に取り付けられた揚重機(一般には走行する炉頂
アウトリガークレーン)を利用して、炉体を組み立て又
は解体するものが知られている。
2. Description of the Related Art Conventionally, a blast furnace assembling / disassembling apparatus or assembling / disassembling method for assembling or disassembling a furnace body of a blast furnace uses a lifting machine (generally a traveling top outrigger crane) attached to a top tower for installation. It is known to use or assemble or disassemble a furnace body.

【0003】一方、炉体を例えば5つの大ブロック(ト
ップマンテル、上部シャフトマンテル、下部シャフトマ
ンテル、ボッシュマンテル及びハースマンテル)に分割
し、各ブロックを炉体櫓に設けた昇降設備によって炉底
より取り込むもの(例えば特開平9−143521号公
報)や、炉体を複数のブロックに分割し、各ブロックを
炉体櫓に設けた中空油圧ジャッキを用い操業床より台車
を介して搬出又は搬入するもの(例えば特開昭53−8
7906号公報、特開昭53−87907号公報等)が
知られている。
On the other hand, a furnace body is divided into, for example, five large blocks (top mantel, upper shaft mantel, lower shaft mantel, Bosch mantel, and Haas mantel), and each block is lifted from the furnace bottom by an elevating facility provided in a furnace body turret. What is taken in (for example, Japanese Unexamined Patent Publication No. Hei 9-143521) or what is obtained by dividing a furnace body into a plurality of blocks and carrying out or carrying in each of the blocks from a working floor through a bogie using a hollow hydraulic jack provided in a furnace body tower. (For example, see JP-A-53-8
7906, JP-A-53-87907, etc.) are known.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上記炉
頂櫓に取り付けられた揚重機(炉頂アウトリガークレー
ン)は、吊り上げ能力が通常60〜200トン程度であ
り、炉体は全体重量で数千トン、水平方向にリング状に
分割したリング状マンテルでもステーブの取り付けられ
た状態では数百トン規模となることが通常である。この
ため、炉体を短冊形のピースに分割したもので組立(据
付)乃至解体を行なっていたが、工期がかかり効率的、
経済的ではなかった。
However, the hoisting machine (furnace outrigger crane) attached to the rooftop turret usually has a lifting capacity of about 60 to 200 tons, and the furnace body has a total weight of several thousand tons. Even when a ring-shaped mantel is divided into a ring shape in the horizontal direction, it usually has a scale of several hundred tons when the stave is attached. For this reason, the furnace body was divided into strip-shaped pieces, and assembly (installation) or disassembly was performed.
It was not economic.

【0005】一方、炉体を5つの大ブロックに分割し搬
出又は搬入するものは、ブロック自体の重量が非常に大
きくなり、吊り上げ、吊り下げ等に極めて大規模な仮設
を要すると共に、炉底周りの作業空間を多く必要とし、
高炉全体構造や周辺の空間的制約を受けるもので、汎用
的装置又は方法ではなかった。
On the other hand, when the furnace body is divided into five large blocks and then carried out or carried in, the weight of the blocks themselves becomes extremely large, and extremely large-scale temporary installation for lifting, hanging, etc. is required, and the area around the furnace bottom is required. Requires a lot of work space,
The blast furnace was subject to the overall structure of the blast furnace and the surrounding space, and was not a general-purpose device or method.

【0006】又、炉体を複数のブロックに分割し操業床
レベルにて搬出又は搬入するものは、鋳床より高いレベ
ルに位置する操業床レベルと2床近傍の環状管との高さ
方向の間隙が小さく、各ブロックの高さを大きく取れず
制約がある。これを回避するためには、環状管の撤去が
必要であり、これを復旧する作業も生ずることから多大
の労力を要する。又、搬出又は搬入に対しても制限され
る等の問題もあった。
[0006] Further, the furnace body divided into a plurality of blocks and carried out or carried in at the operating floor level is characterized in that the operating floor level located at a level higher than the casting bed and the annular pipe near the two beds in the height direction. The gap is small and the height of each block cannot be made large, which is a limitation. In order to avoid this, it is necessary to remove the annular pipe, and a large amount of labor is required because a work for restoring the annular pipe also occurs. In addition, there is also a problem that the carrying-out or carrying-in is restricted.

【0007】上記高炉炉体の組立、解体は、高炉新設時
のマンテル組立、据付においても全く同様であった。
[0007] The assembly and dismantling of the blast furnace furnace body were completely the same in the assembly and installation of the mantel when the blast furnace was newly installed.

【0008】本発明の課題は、高炉の組立解体装置及び
組立解体方法において、工期短縮と安全作業が可能で、
且つ効率的、経済的なことである。
An object of the present invention is to provide a blast furnace assembling and disassembling apparatus and an assembling and disassembling method capable of shortening a construction period and performing a safe operation.
It is efficient and economical.

【0009】[0009]

【課題を解決するための手段】上記課題を解決するため
本発明は、高炉炉体を水平方向に複数に分割した部分マ
ンテルを順次組み立てる又は解体する高炉の組立解体装
置において、前記高炉の鋳床部から炉体両外側に前記高
炉の炉体櫓の支持柱間を通して設けられた受梁と、該受
梁上を走行可能に設けられた台車と、前記炉体櫓に設け
られ前記部分マンテルを吊り上げ又は吊り下げて前記台
車に積み込み又は積み下す第1の吊手段とを備えたこと
である。
SUMMARY OF THE INVENTION In order to solve the above problems, the present invention relates to a blast furnace assembly and disassembly apparatus for sequentially assembling or disassembling partial mantels obtained by dividing a blast furnace body into a plurality of parts in a horizontal direction. A receiving beam provided between the supporting columns of the furnace tower of the blast furnace on both sides of the furnace body from the portion, a bogie provided so as to be able to run on the receiving beam, and the partial mantel provided on the furnace tower. And first suspending means for suspending or suspending and loading or unloading the carriage.

【0010】受梁は、炉体櫓の支持柱間を通して高炉の
鋳床部から炉体両外側に設けられたので、空間的制約を
受けることが比較的少なく、且つ強度的に無理なく必要
十分な強度のある梁を設けることが可能になる。台車
は、この受梁上を走行可能に設けられているので、部分
マンテルを高炉の鋳床部から炉体中心部に、又は炉体中
心部から鋳床部に速やかに搬送することが出来る。更
に、高炉の炉体櫓に設けられた第1の吊手段は、取り扱
うべき部分マンテルの重量に対応して使用基数を決め、
合計容量を決めるので吊り上げ又は吊り下げ能力を必要
十分に持たせることが出来、容易に前記台車に積み込み
又は積み下すことが出来る。炉体の部分マンテルへの分
割数及び取り付けられるステーブの重量は、第1の吊手
段の能力とこの吊手段を支持する炉体櫓の強度をもとに
最適な選択が行なわれる。従って、本高炉の組立解体装
置は、工期短縮と安全作業が可能で、効率的、経済的で
ある。
[0010] Since the receiving beams are provided on both sides of the furnace body from the cast floor of the blast furnace through the supporting columns of the furnace body tower, there are relatively few space restrictions, and the strength is reasonably necessary and sufficient. It is possible to provide a beam having high strength. Since the cart is provided so as to be able to travel on the receiving beam, the partial mantel can be quickly transferred from the cast floor of the blast furnace to the center of the furnace body or from the center of the furnace to the cast floor. Furthermore, the first suspending means provided on the furnace tower of the blast furnace determines the number of units to be used according to the weight of the partial mantel to be handled,
Since the total capacity is determined, it is possible to provide a sufficient lifting or hanging ability, and it is possible to easily load or unload the truck. The number of divisions of the furnace body into partial mantels and the weight of the attached stave are optimally selected based on the capacity of the first suspending means and the strength of the furnace tower supporting the suspending means. Therefore, the assembly and disassembly apparatus for the blast furnace is capable of shortening the construction period and safe work, and is efficient and economical.

【0011】更に、上記高炉の組立解体装置において、
前記炉体櫓に設けられ、前記受梁にかかる荷重の全て又
は一部を支持する第2の吊手段を備えたことである。受
梁にかかる荷重の全て又は一部を支持する第2の吊手段
は、上記高炉の組立解体装置の作用に加え、受梁に要求
される力学的断面性能を小さくする。
Further, in the assembly and disassembly apparatus for the blast furnace,
A second suspending means is provided on the furnace tower to support all or a part of the load applied to the receiving beam. The second suspending means for supporting all or a part of the load applied to the receiving beam reduces the mechanical sectional performance required for the receiving beam in addition to the operation of the assembly and disassembly device for the blast furnace.

【0012】更に、上記第2の吊手段は、前記受梁及び
台車を垂直方向に吊り上げ又は吊り下げて支持すると共
に、水平レベルの調整が可能なものである。第2の吊手
段は、上記第2の吊手段の作用に加え、部分マンテルの
吊り上げ又は吊り下げ作業の自由度を大きくし、且つマ
ンテルに設ける吊りブラケットを不要にする。
[0012] Further, the second suspending means supports the receiving beam and the bogie while being suspended or suspended in a vertical direction, and is capable of adjusting a horizontal level. The second suspending means, in addition to the function of the second suspending means, increases the degree of freedom in lifting or suspending the partial mantel, and eliminates the need for a suspending bracket provided on the mantel.

【0013】更に、上記いずれかの高炉の組立解体装置
において、前記受梁に沿って走行可能に設けられた安全
天井を備え、該安全天井の上側空間と下側空間で各々安
全に組立、解体作業が出来ることである。受梁に沿って
走行可能に設けられた安全天井は、上記いずれかの高炉
の組立解体装置の作用に加え、安全天井の着脱作業を迅
速、容易にし、高炉の組立、解体作業を効率化する。
Further, in any one of the above-mentioned disassembly and disassembly apparatus for a blast furnace, a safety ceiling provided so as to be able to run along the receiving beam is provided, and safety assembly and disassembly are respectively performed in a space above and below the safety ceiling. You can work. The safety ceiling provided so as to be able to travel along the receiving beam, in addition to the operation of any of the above-described blast furnace assembly and disassembly devices, makes the installation and removal of the safety ceiling quick and easy, and makes the blast furnace assembly and disassembly work more efficient. .

【0014】又、高炉炉体を水平方向に複数に分割した
部分マンテルを順次搬入し組み立てる又は順次搬出し解
体する高炉の組立解体方法において、前記高炉の鋳床部
と炉体との間に設けられた受梁上を該炉体櫓の支持柱間
を通って走行する台車に前記部分マンテルを載置して搬
入又は搬出する搬入搬出工程と、前記高炉の炉体櫓に設
けられた吊手段によって前記部分マンテルを前記台車か
ら吊り上げて炉体を組み立てる又は前記部分マンテルを
前記炉体から分離して前記台車に吊り下げて炉体を解体
する組立解体工程と、前記受梁に沿って走行可能に設け
られた安全天井を必要な時に着脱して前記炉体の底部組
立又は解体を行なう炉体底部組立解体工程とを含むこと
である。
In a method of assembling and disassembling a blast furnace in which a plurality of partial mantels obtained by dividing a blast furnace furnace body in a horizontal direction are sequentially loaded and assembled or sequentially removed and dismantled, a method is provided between the cast floor portion of the blast furnace and the furnace body. A loading and unloading step of loading and unloading the partial mantel by placing the partial mantel on a carriage that travels between the supporting columns of the furnace tower, and a suspending means provided on the furnace tower of the blast furnace An assembling / disassembling step of lifting the partial mantel from the bogie to assemble a furnace body or separating the partial mantel from the furnace body and suspending the partial mantel from the bogie to disassemble the furnace body, and running along the receiving beam A bottom assembly and disassembly process of assembling or disassembling the bottom of the furnace body by attaching and detaching the safety ceiling provided in the furnace when necessary.

【0015】上記搬入搬出工程、組立解体工程及び炉体
底部組立解体工程とを含む高炉の組立解体方法は、空間
的制約を受けることが比較的少なく、部分マンテルを高
炉の鋳床部から炉体中心部に、又は炉体中心部から鋳床
部に速やかに搬送することが出来る。更に、台車の部分
マンテルを容易に吊り上げ又は吊り下げることが出来
る。更に、安全天井を容易に着脱出来るので、安全天井
の上側の作業と独立して炉体の底部組立又は解体を安
全、効率的に行なうことが出来る。従って、工期短縮と
安全作業が可能で、効率的、経済的である。
In the method of disassembling and disassembling a blast furnace, which includes the above-mentioned loading / unloading step, assembling / disassembling step and furnace body bottom assembling / disassembling step, there is relatively little space restriction, and the partial mantel is moved from the cast floor of the blast furnace to the furnace body. It can be quickly conveyed to the center or from the center of the furnace body to the casting bed. Further, the partial mantel of the cart can be easily lifted or suspended. Further, since the safety ceiling can be easily attached and detached, the bottom assembly or disassembly of the furnace body can be performed safely and efficiently independently of the work above the safety ceiling. Therefore, the construction period can be shortened and safe work can be performed, which is efficient and economical.

【0016】[0016]

【発明の実施の形態】以下、本発明に係る高炉の組立解
体装置及び組立解体方法の実施の形態を図面に基づいて
詳細に説明する。尚、図1〜5において、同一又は同等
部分には同一符号を付けて示す。
BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, embodiments of a disassembly apparatus and a disassembly method for a blast furnace according to the present invention will be described in detail with reference to the drawings. In FIGS. 1 to 5, the same or equivalent parts are denoted by the same reference numerals.

【0017】図1は、本発明に係る高炉の組立解体装置
の一実施の形態を示す正面図である。本実施の形態の高
炉の組立解体装置25は、高炉炉体2を水平方向に複
数、この場合は11ブロックに分割して予め製作してお
いた部分マンテル4を順次搬入して組み立てるか又は既
設の高炉炉体2を、例えば水平方向に11ブロックの部
分マンテル4に分割して順次取り外し解体するものであ
る。
FIG. 1 is a front view showing an embodiment of an apparatus for disassembling and assembling a blast furnace according to the present invention. The assembling and disassembling apparatus 25 for a blast furnace according to the present embodiment is configured such that the blast furnace body 2 is divided into a plurality of pieces in the horizontal direction, in this case, divided into 11 blocks, and the partial mantels 4 which have been manufactured in advance are sequentially loaded and assembled or assembled. Is divided into 11 blocks of partial mantels 4 in the horizontal direction, for example, and sequentially removed and dismantled.

【0018】更に、高炉の鋳床部9から炉体2両外側
に、この炉体櫓の支持柱17間を通して設けられた受梁
27と、この受梁27上を走行可能に設けられたマンテ
ル台車(台車)29と、炉頂アウトリガークレーンとは
別に高炉の炉体櫓16に設けられ、部分マンテル4を吊
り上げ又は吊り下げてマンテル台車29に積み込み又は
積み下す第1の吊手段として第1のセンターホールジャ
ッキ32、33とを備える。
Further, from the casting bed 9 of the blast furnace to both outer sides of the furnace body 2, a receiving beam 27 provided between the supporting columns 17 of the furnace tower and a mantel movably provided on the receiving beam 27. A trolley (trolley) 29 and a furnace top tower 16 of a blast furnace are provided separately from the furnace top outrigger crane, and a first suspending means for lifting or suspending the partial mantel 4 and loading or unloading it on the mantel trolley 29 is provided as a first suspending means. Center hole jacks 32 and 33 are provided.

【0019】更に、組立解体装置25は、炉体櫓16に
設けられ、受梁27にかかる荷重の全て又は一部を支持
する第2の吊手段として第2のセンターホールジャッキ
を備える。第2のセンターホールジャッキは、図1に図
示していないが、適宜必要な個所に設置され、例えば3
床22や2床21或いは8床23等に設けられる。この
場合、第2のセンターホールジャッキは、受梁27及び
マンテル台車29を垂直方向に吊り上げ又は吊り下げて
支持すると共に、水平レベルの調整が可能なものであ
る。尚、受梁27を炉体櫓16の内外に分割し、炉体櫓
16の内側の受梁27にかかる荷重の全て又は一部を第
2の吊手段で支持する場合においては、この第2の吊手
段の容量は受梁27全体を支持する場合に比し小さくな
り、より経済的であることはいうまでもない。
Further, the assembling and disassembling apparatus 25 is provided in the furnace tower 16 and has a second center hole jack as a second suspending means for supporting all or a part of the load applied to the receiving beam 27. Although not shown in FIG. 1, the second center hole jack is appropriately installed at a necessary place, for example, 3
It is provided on the floor 22, the second floor 21, the eight floor 23, and the like. In this case, the second center hole jack supports the receiving beam 27 and the mantel trolley 29 by being lifted or suspended in the vertical direction, and is capable of adjusting the horizontal level. When the receiving beam 27 is divided into the inside and outside of the furnace tower 16 and all or a part of the load applied to the receiving beam 27 inside the furnace tower 16 is supported by the second suspension means, Needless to say, the capacity of the suspending means becomes smaller as compared with the case where the whole receiving beam 27 is supported, and it is more economical.

【0020】第1及び第2のセンターホールジャッキ
は、油圧によって上下に移動するテンションバーを中心
軸に持つもので、1基当りの吊り上げ又は吊り下げ容量
は、例えば200トンで、このセンターホールジャッキ
の他に油圧ポンプユニット、電気制御装置等を備え、公
知のものを使用することが出来る。油圧ポンプユニッ
ト、電気制御装置等は、複数基のセンターホールジャッ
キの上下移動速度や移動量を制御し、センターホールジ
ャッキを複数基設けることによって、数百トンの合計容
量となり、例えば鉄皮及びステーブを有する部分マンテ
ルの重量が500トンあれば、3〜4基のセンターホー
ルジャッキを使用することになる。
The first and second center hole jacks each have a tension bar which moves up and down by hydraulic pressure on a center axis. The lifting capacity or hanging capacity per unit is, for example, 200 tons. In addition, a hydraulic pump unit, an electric control device, and the like are provided, and a known pump can be used. Hydraulic pump units, electric control devices, etc. control the vertical movement speed and movement amount of multiple center hole jacks, and by providing multiple center hole jacks, the total capacity is several hundred tons, for example, steel shell and stave If the partial mantel having the weight of 500 tons is used, three to four center hole jacks will be used.

【0021】図2は、図1の I−I 線断面図である。高
炉の組立解体装置25は、受梁27に沿って走行可能に
設けられた羽口可動安全天井(安全天井)36を備えて
おり、この羽口可動安全天井36の上側空間40と下側
空間41で各々安全に組立、解体作業が出来るようにな
っている。部分マンテル4を載置したマンテル台車29
は、受梁27の上側フランジ28a上面を走行可能に形
成され、複数の転動ローラを有するチルタンク30が設
けられて受梁27の上面を走行する。図2では部分マン
テル4をマンテル台車29の台車ガーダー42上に載置
して搬送する一実施の形態を図示した。これに対し二本
の受梁27上に、二つに分けたマンテル台車29のそれ
ぞれを配置し、チルタンク30によって走行可能にし
て、この二台のマンテル台車29に、部分マンテル4に
取り付けたブラケットを介して部分マンテル4を支持載
置して搬送する装置も本実施の形態の一つである。この
装置では、図2に示したマンテル台車29における載置
のための台車ガーダー42を廃することが可能であり、
環状管14の下端と受梁27の上面間の空間を、より有
効に利用することが可能となる。尚、これらマンテル台
車29をチルタンク30を用いず、公知のスライドベア
リングを用い、受梁27上を摺動させることも選択可能
な走行装置である。受梁27は、鋳床11上に複数の受
座13を介して設置され、鋳床11に片持ち或いは必要
に応じて受梁27の先端側27a(図1)を図示されて
いない横梁を介して炉体支柱17に支持される。
FIG. 2 is a sectional view taken along the line II of FIG. The assembling and disassembling apparatus 25 of the blast furnace has a tuyere movable safety ceiling (safety ceiling) 36 provided so as to be able to travel along the receiving beam 27, and an upper space 40 and a lower space of the tuyere movable safety ceiling 36. At 41, assembly and disassembly operations can be performed safely. Mantel cart 29 with partial mantel 4 placed
Is formed so as to be able to run on the upper surface of the upper flange 28a of the receiving beam 27, is provided with a chill tank 30 having a plurality of rolling rollers, and runs on the upper surface of the receiving beam 27. FIG. 2 illustrates an embodiment in which the partial mantel 4 is mounted on the carriage girder 42 of the mantel carriage 29 and transported. On the other hand, each of the divided mantel carts 29 is arranged on the two receiving beams 27 and can be driven by the chill tank 30, and the brackets attached to the partial mantels 4 are attached to the two mantel carts 29. A device for supporting and mounting the partial mantel 4 via the interface and transporting it is also one of the present embodiments. In this device, it is possible to eliminate the trolley girder 42 for mounting on the mantel trolley 29 shown in FIG.
The space between the lower end of the annular pipe 14 and the upper surface of the receiving beam 27 can be used more effectively. It is to be noted that the mantel cart 29 does not use the chill tank 30 but uses a known slide bearing, and is a traveling device that can be slid on the receiving beam 27. The receiving beam 27 is installed on the cast floor 11 through a plurality of receiving seats 13, and cantilevered on the cast floor 11 or, if necessary, attaches the front side 27 a (FIG. 1) of the receiving beam 27 to a horizontal beam (not shown). It is supported on the furnace body support 17 via.

【0022】更に、羽口可動安全天井36は、受梁27
の下側フランジ28b内面に設置されたレール上を、上
記チルタンク30と同じ構造のチルタンク37(車輪)
が転動し走行する。羽口可動安全天井36の下側には分
廻し用ビーム38が設けられ、ハースマンテル4d内の
作業に供される。そして、受梁27と部分マンテル4を
載置したマンテル台車29の全体は、その荷重の全部又
は一部を先に記した第2のセンターホールジャッキによ
り、ワイヤー35を介して吊り上げられる。
Further, the tuyere movable safety ceiling 36 is
A chill tank 37 (wheel) having the same structure as the chill tank 30 is mounted on a rail installed on the inner surface of the lower flange 28b.
Rolls and runs. A split beam 38 is provided below the tuyere movable safety ceiling 36, and is used for work inside the Haasmantel 4d. The entire mantel trolley 29 on which the receiving beam 27 and the partial mantel 4 are placed is lifted via the wire 35 by the second center hole jack described above, in which all or part of the load is applied.

【0023】以上の構造を有する本実施の形態の高炉の
組立解体装置25は、次のように作用する。即ち、受梁
27は、炉体櫓の支持柱17間を通して高炉の鋳床部9
から炉体両外側に設けられ、且つ受梁の受座13も低く
出来るので、鋳床上面12のレベルと環状管14との高
さ方向の間隙を鋳床11より高いレベル位置にある操業
床上にマンテル台車29を設ける場合に比べ大きくと
れ、空間的制約を受けることが比較的少ない。更に、炉
体2の部分マンテル4への分割個数を少なく出来、且つ
強度的に無理なく必要十分な強度のある受梁27を設け
ることが可能になる。マンテル台車29は、この受梁2
7上を走行可能に設けられているので、部分マンテル4
を高炉の鋳床部9から炉体中心部3に、又は炉体中心部
3から鋳床部9に速やかに搬送することが出来る。
The blast furnace assembly and disassembly apparatus 25 according to the present embodiment having the above structure operates as follows. That is, the receiving beam 27 passes between the support columns 17 of the furnace tower and the cast floor 9 of the blast furnace.
And the receiving seat 13 of the receiving beam can be lowered, so that the gap in the height direction between the level of the cast floor upper surface 12 and the annular pipe 14 is set higher than the casting floor 11 on the operating floor. Compared with the case where the mantel trolley 29 is provided, and there is relatively little space restriction. Further, the number of divisions of the furnace body 2 into the partial mantels 4 can be reduced, and the receiving beam 27 having necessary and sufficient strength can be provided without difficulty in strength. The mantel trolley 29 is
7 so that it can run on
Can be quickly conveyed from the cast floor 9 of the blast furnace to the furnace center 3 or from the furnace center 3 to the cast floor 9.

【0024】そして、鋳床部9を利用して受梁27を設
けることは、部分マンテル4のマンテル台車29からグ
ランドレベル(GL)への搬出又はグランドレベル(G
L)からマンテル台車29への搬入にも利便性がある。
その上、受梁27の仮設に鋳床部9の天井クレーン10
を利用することも出来る。
The provision of the receiving beam 27 using the cast floor section 9 can be carried out from the mantel cart 29 of the partial mantel 4 to the ground level (GL) or the ground level (G).
L) is also convenient to carry into the mantel trolley 29.
In addition, the temporary crane 10 of the cast floor 9
Can also be used.

【0025】更に、高炉の炉体櫓16に設けられた第1
のセンターホールジャッキ32、33は、取り扱うべき
部分マンテル4の重量に対応して使用基数を決め、合計
容量を決めるので吊り上げ又は吊り下げ能力を必要十分
に持たせることが出来、容易に前記マンテル台車29に
積み込み又は積み下すことが出来る。従って、本高炉の
組立解体装置25は、工期短縮と安全作業が可能で、効
率的、経済的である。
Further, a first blast furnace provided in a furnace tower 16 of the blast furnace is provided.
The center hole jacks 32, 33 determine the number of units to be used in accordance with the weight of the partial mantel 4 to be handled, and determine the total capacity, so that the lifting capacity or the suspending capacity can be sufficiently provided, and the mantel truck can be easily manufactured. 29 can be loaded or unloaded. Therefore, the assembling and disassembling apparatus 25 of the blast furnace is capable of shortening the construction period and safe work, and is efficient and economical.

【0026】更に、受梁27にかかる荷重の全て又は一
部を支持する第2のセンターホールジャッキは、受梁2
7にかかる荷重を軽減し、受梁27に要求される力学的
断面性能を小さくし、且つ、部分マンテル4の吊り上げ
又は吊り下げ作業の自由度を大きくし、吊り上げ又は吊
り下げのブラケットを不要にする。又、受梁27に沿っ
て走行可能に設けられた羽口可動安全天井36は、安全
天井の着脱作業を迅速、容易にし、高炉の組立、解体作
業を効率化する。そして、安全天井の上側空間40と下
側空間41とで各々安全に組立、解体作業が出来る。
Further, the second center hole jack for supporting all or a part of the load applied to the receiving beam 27 is
7 is reduced, the mechanical cross-sectional performance required for the receiving beam 27 is reduced, and the degree of freedom of lifting or hanging the partial mantel 4 is increased, so that a lifting or hanging bracket is not required. I do. In addition, the tuyere movable safety ceiling 36 provided so as to be able to travel along the receiving beam 27 makes the work of attaching and detaching the safety ceiling quick and easy, and makes the assembly and dismantling work of the blast furnace more efficient. Then, the assembling and disassembling operations can be safely performed in the upper space 40 and the lower space 41 of the safety ceiling.

【0027】次に、本実施の形態の高炉の組立解体方法
について、図1〜5に基づいて説明する。
Next, a method of assembling and disassembling a blast furnace according to the present embodiment will be described with reference to FIGS.

【0028】先ず、図1、2において、本実施の形態の
高炉の組立解体方法は、高炉炉体2を水平方向に複数に
分割したリング状の部分マンテル4を順次搬入し組み立
てる又は順次搬出し解体する方法である。即ち、高炉の
鋳床部9と炉体2との間に設けられた受梁27上を炉体
の支持柱17間を通って走行するマンテル台車29に部
分マンテル4を載置して搬入又は搬出する搬入搬出工程
と、高炉の炉体櫓16に設けられた吊手段としての第1
のセンターホールジャッキ32、33によって部分マン
テル4をマンテル台車29から吊り上げて炉体2を組み
立てる又は部分マンテル4を炉体から分離してマンテル
台車29に吊り下げて炉体2を解体する組立解体工程
と、受梁27に沿って走行可能に設けられた羽口可動安
全天井36を必要な時に着脱して炉体の底部組立又は解
体を行なう炉体底部組立解体工程とを含むものである。
First, referring to FIGS. 1 and 2, a method for assembling and disassembling a blast furnace according to the present embodiment is such that a ring-shaped partial mantel 4 obtained by dividing a blast furnace body 2 into a plurality of parts in the horizontal direction is sequentially loaded and assembled or sequentially unloaded. It is a method of dismantling. That is, the partial mantel 4 is placed on a mantel truck 29 that travels between the support pillars 17 of the furnace body on a receiving beam 27 provided between the cast floor portion 9 of the blast furnace and the furnace body 2, and is carried in or out. A loading / unloading process for unloading, and a first as a suspending means provided on the furnace body tower 16 of the blast furnace.
Assembling and disassembling step of assembling the furnace body 2 by lifting the partial mantel 4 from the mantel trolley 29 by the center hole jacks 32 and 33 or separating the partial mantel 4 from the furnace body and suspending the partial mantel 4 on the mantel trolley 29 to disassemble the furnace body 2 And a bottom assembly / disassembly process of assembling or disassembling the bottom of the furnace body by attaching and detaching the tuyere movable safety ceiling 36 provided so as to be able to travel along the receiving beam 27 when necessary.

【0029】図3は、本発明に係る高炉の組立解体装置
による組立解体を示し、(A)は羽口マンテル撤去の正
面図、(B)は炉体解体の正面図である。図3(A)に
示すように、先ず、炉体2を炉体櫓にダブルリングガー
ダー18を介して支持しておく。この状態で羽口マンテ
ル4eをピースに切断し、鋳床部9の天井クレーン10
によって鋳床部9に移動し搬出する。尚、羽口マンテル
4eの切断下端レベルは、受梁27上端と環状管14の
下端との間に、その後の部分マンテル4の解体及び据付
けを容易に行なえる空間が取られるように決められてい
る。羽口マンテル4eを撤去した後、図3(B)に示す
ように、鋳床11に受梁27を敷設し、マンテル台車2
9を走行可能に設置する。この際、受梁27に羽口可動
安全天井36を可動可能に設置する。
FIGS. 3A and 3B show disassembly and disassembly by the assembly and disassembly apparatus for a blast furnace according to the present invention, wherein FIG. 3A is a front view of removing the tuyere mantel, and FIG. As shown in FIG. 3A, first, the furnace body 2 is supported on a furnace body tower via a double ring girder 18. In this state, the tuyere mantel 4e is cut into pieces, and the overhead crane 10
To move to the cast floor section 9 and carry it out. The cut lower end level of the tuyere mantel 4e is determined so as to provide a space between the upper end of the receiving beam 27 and the lower end of the annular pipe 14 so that the subsequent partial mantel 4 can be easily disassembled and installed. I have. After removing the tuyere mantel 4e, as shown in FIG. 3B, a receiving beam 27 is laid on the cast floor 11, and the mantel truck 2
9 is installed so that it can run. At this time, the tuyere movable safety ceiling 36 is movably installed on the receiving beam 27.

【0030】羽口可動安全天井36の上側空間40にお
いては、炉体2の下端側から所定の高さ寸法のリング状
部分マンテル4を略水平に切断して切り出す。この時、
切り出された部分マンテル4を支持するように、炉体櫓
の下部デッキフレーム(通称3床レベル)に設けられた
複数の第1のセンターホールジャッキ32によってバラ
ンスがとれるように吊っておく。この切り出された部分
マンテル4をマンテル台車29上に載置し、受梁27に
沿って鋳床部9に移送する。鋳床部9に移送された部分
マンテル4は、図示していないクレーンによって搬出さ
れる。
In the upper space 40 of the tuyere movable safety ceiling 36, a ring-shaped partial mantel 4 having a predetermined height is cut substantially horizontally from the lower end side of the furnace body 2. At this time,
In order to support the cut-out partial mantel 4, it is suspended so as to be balanced by a plurality of first center hole jacks 32 provided on a lower deck frame (commonly called three floor level) of the furnace tower. The cut partial mantel 4 is placed on a mantel cart 29 and transferred to the cast floor 9 along the receiving beam 27. The partial mantel 4 transferred to the cast floor section 9 is carried out by a crane (not shown).

【0031】同時に、炉体上部のガス捕集マンテル等の
トップマンテル4aをアウトリガークレーン20によっ
て解体する。羽口可動安全天井36の下側空間41にお
いては、残銑を処理する作業が同時に行われる。以上の
作業によって、炉体の解体が行われる。
At the same time, the top mantel 4a such as a gas collecting mantel at the upper part of the furnace body is dismantled by the outrigger crane 20. In the lower space 41 of the tuyere movable safety ceiling 36, the operation of processing the remaining pig iron is performed at the same time. The furnace body is dismantled by the above operation.

【0032】図4は、図3と同様の組立解体を示し、
(C)はトップマンテル〜シャフトマンテル槽内引込、
吊上、組立の正面図、(D)はハースマンテル据付の正
面図である。図4(C)に示すように、外部で予め製作
された部分マンテル、即ちガス捕集マンテル等のトップ
マンテル4aや図示していないシャフトマンテル等は、
図示していない公知の重量物搬送台車で鋳床部9まで搬
送され、図示していないクレーンによってマンテル台車
29に載置される。部分マンテル4を載置したマンテル
台車29は、炉体中心部3側に移送される。移送された
部分マンテル4は、例えば炉体櫓の8床23に設置され
た第1のセンターホールジャッキ33によって吊り上げ
られ組み立てられる。
FIG. 4 shows an assembly disassembly similar to FIG.
(C) Top mantel-shaft mantel pulling in tank,
FIG. 3D is a front view of the lifting and assembly, and FIG. As shown in FIG. 4C, a partial mantel manufactured in advance outside, that is, a top mantel 4a such as a gas collecting mantel, a shaft mantel not shown, and the like are:
It is conveyed to the cast floor section 9 by a known heavy object transporting trolley not shown, and is mounted on the mantel trolley 29 by a crane not shown. The mantel trolley 29 on which the partial mantel 4 is placed is transferred to the furnace body center 3 side. The transferred partial mantel 4 is lifted and assembled by, for example, a first center hole jack 33 installed on the eight floor 23 of the furnace tower.

【0033】図4(D)に示すように、ハースマンテル
4dは、上記トップマンテル、シャフトマンテルと同様
に鋳床部9に引き込まれ、マンテル台車29に載置され
る。更に、ハースマンテル4dは、マンテル台車29に
よって炉体中心部3側に移送される。移送されたハース
マンテル4dは、、例えば炉体櫓の3床に設置された第
1のセンターホールジャッキ32によって吊り上げら
れ、マンテル台車29が鋳床部9側に戻された後、炉底
24に据え付けられる。
As shown in FIG. 4D, the hearth mantel 4d is drawn into the cast floor 9 like the top mantel and the shaft mantel, and is placed on the mantel cart 29. Further, the hearth mantel 4d is transferred to the furnace body center 3 by the mantel cart 29. The Haas mantel 4d transferred is lifted by, for example, a first center hole jack 32 installed on the three floors of the furnace tower, and after the mantel cart 29 is returned to the cast floor section 9 side, the hearth mantel 4d is moved to the furnace bottom 24. Installed.

【0034】図5は、図3と同様の組立解体を示し、
(E)は3床大梁上仮置の正面図、(F)はボッシュマ
ンテル据付の正面図である。図5(E)に示すように、
トップマンテル4a、シャフトマンテル4b等は、ブラ
ケット6を介して、3床大梁部に置かれた図示されてい
ない4〜8基の油圧ジャッキに支持されて3床大梁部上
に仮置される。次に、図5(F)に示すように、ボッシ
ュマンテル4cが引き込まれ、炉体中心部3に移送さ
れ、上記シャフトマンテル4b下端に接続される。更
に、前記3床大梁部の油圧ジャッキで仮置された上方の
マンテルのレベルを調整しつつ羽口マンテルを取り込
み、上端、下端をそれぞれ、ボッシュマンテル4cと炉
底マンテル4dと接続することで炉体の組立が完了す
る。
FIG. 5 shows an assembly disassembly similar to FIG.
(E) is a front view of temporary installation on a three-floor girder, and (F) is a front view of Bosch mantel installation. As shown in FIG.
The top mantel 4a, the shaft mantel 4b, and the like are supported by four to eight hydraulic jacks (not shown) placed on the three-floor girder via the bracket 6, and are temporarily placed on the three-floor girder. Next, as shown in FIG. 5 (F), the Bosch mantel 4c is pulled in, transferred to the furnace body center portion 3, and connected to the lower end of the shaft mantel 4b. Further, the tuyere mantel is taken in while adjusting the level of the upper mantel temporarily placed by the hydraulic jack of the three-bed girders, and the upper end and the lower end are connected to the Bosch mantel 4c and the hearth mantel 4d, respectively. The body assembly is completed.

【0035】本実施の形態の高炉の組立解体方法は、搬
入搬出工程、組立解体工程及び炉体底部組立解体工程と
を含み、空間的制約を受けることが比較的少なく、部分
マンテル4を高炉の鋳床部9から炉体中心部3に、又は
炉体中心部3から鋳床部9に速やかに搬送することが出
来る。更に、台車の部分マンテル4を容易に吊り上げ又
は吊り下げることが出来る。更に、安全天井36を容易
に着脱出来るので、安全天井36の上側の作業と独立し
て炉体の底部組立又は解体を安全、効率的に行なうこと
が出来る。尚、マンテルを一部残置して流用する場合
も、一部の手順を調整することで容易に実施することが
出来る。従って、工期短縮と安全作業が可能で、効率
的、経済的である。
The method of assembling and disassembling the blast furnace according to the present embodiment includes a carry-in / out step, an assembling / disassembling step, and a furnace body bottom assembling / disassembling step. It can be conveyed promptly from the cast bed section 9 to the furnace body center section 3 or from the furnace body center section 3 to the cast bed section 9. Further, the partial mantel 4 of the cart can be easily lifted or hung. Furthermore, since the safety ceiling 36 can be easily attached and detached, the bottom assembly or disassembly of the furnace body can be performed safely and efficiently independently of the work above the safety ceiling 36. It is to be noted that, even when a part of the mantel is left as it is, it can be easily implemented by adjusting a part of the procedure. Therefore, the construction period can be shortened and safe work can be performed, which is efficient and economical.

【0036】[0036]

【発明の効果】本発明の高炉の組立解体装置及び組立解
体方法によれば、工期短縮と安全作業が可能で、且つ効
率的、経済的である。
According to the apparatus and method for assembling and disassembling a blast furnace of the present invention, the construction period can be shortened and safe operation can be performed, and it is efficient and economical.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る高炉の組立解体装置の一実施の形
態を示す正面図である。
FIG. 1 is a front view showing an embodiment of an assembly and disassembly apparatus for a blast furnace according to the present invention.

【図2】図1の I−I 線断面図である。FIG. 2 is a sectional view taken along line II of FIG. 1;

【図3】本発明に係る高炉の組立解体装置による組立解
体を示し、(A)は羽口マンテル撤去の正面図、(B)
は炉体解体の正面図である。
3A and 3B show disassembly and disassembly by a disassembly and disassembly apparatus for a blast furnace according to the present invention, wherein FIG.
FIG. 2 is a front view of the furnace body dismantling.

【図4】図3と同様の組立解体を示し、(C)はトップ
マンテル〜シャフトマンテル槽内引込、吊上、組立の正
面図、(D)はハースマンテル据付の正面図である。
4A and 4B show a disassembled disassembly similar to that of FIG. 3, wherein FIG. 4C is a front view of drawing, lifting and assembling from the top mantel to the shaft mantel, and FIG. 4D is a front view of installation of the Haasmantel.

【図5】図3と同様の組立解体を示し、(E)は3床大
梁上仮置の正面図、(F)はボッシュマンテル据付の正
面図である。
FIG. 5 shows the same disassembly and disassembly as in FIG. 3, wherein (E) is a front view of a temporary placement on a three-beam girder, and (F) is a front view of Bosch mantel installation.

【符号の説明】[Explanation of symbols]

2 炉体 4 部分マンテル 9 鋳床部 16 炉体櫓 17 支持柱 25 高炉の組立解体装置 27 受梁 29 マンテル台車(台車) 32、33 第1のセンターホールジャッキ(第1の吊
手段) 36 羽口可動安全天井(安全天井) 40 上側空間 41 下側空間
2 Furnace body 4 Partial mantel 9 Cast floor part 16 Furnace body tower 17 Support pillar 25 Blast furnace assembling and disassembling device 27 Receiving beam 29 Mantel trolley (trolley) 32, 33 First center hole jack (first suspension means) 36 blades Mouth movable safety ceiling (safety ceiling) 40 Upper space 41 Lower space

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 高炉炉体を水平方向に複数に分割した部
分マンテルを順次組み立てる又は解体する高炉の組立解
体装置において、前記高炉の鋳床部から炉体両外側に前
記高炉の炉体櫓の支持柱間を通して設けられた受梁と、
該受梁上を走行可能に設けられた台車と、前記炉体櫓に
設けられ前記部分マンテルを吊り上げ又は吊り下げて前
記台車に積み込み又は積み下す第1の吊手段とを備えた
ことを特徴とする高炉の組立解体装置。
A blast furnace assembly dismantling apparatus for sequentially assembling or disassembling partial mantels obtained by dividing a blast furnace furnace body into a plurality of parts in a horizontal direction, comprising: A support beam provided between the support columns,
A bogie provided so as to be able to run on the receiving beam, and a first suspending means provided on the furnace body tower for lifting or suspending the partial mantel and loading or unloading the bogie. Blast furnace assembly and disassembly equipment.
【請求項2】 請求項1において、前記炉体櫓に設けら
れ、前記受梁にかかる荷重の全て又は一部を支持する第
2の吊手段を備えたことを特徴とする高炉の組立解体装
置。
2. The blast furnace assembly and disassembly apparatus according to claim 1, further comprising a second suspending means provided on the furnace body tower to support all or a part of the load applied to the receiving beam. .
【請求項3】 請求項2において、前記第2の吊手段
は、前記受梁及び台車を垂直方向に吊り上げ又は吊り下
げて支持すると共に、水平レベルの調整が可能なもので
あることを特徴とする高炉の組立解体装置。
3. The apparatus according to claim 2, wherein the second suspending means supports the receiving beam and the bogie by lifting or suspending the same in a vertical direction, and is capable of adjusting a horizontal level. Blast furnace assembly and disassembly equipment.
【請求項4】 請求項1乃至3のいずれかにおいて、前
記受梁に沿って走行可能に設けられた安全天井を備え、
該安全天井の上側空間と下側空間で各々安全に組立、解
体作業が出来ることを特徴とする高炉の組立解体装置。
4. A safety ceiling according to claim 1, further comprising a safety ceiling provided so as to be able to run along said receiving beam.
A disassembly and disassembly apparatus for a blast furnace, wherein assembly and disassembly operations can be performed safely in a space above and below the safety ceiling.
【請求項5】 高炉炉体を水平方向に複数に分割した部
分マンテルを順次搬入し組み立てる又は順次搬出し解体
する高炉の組立解体方法において、前記高炉の鋳床部と
炉体との間に設けられた受梁上を該炉体の支持柱間を通
って走行する台車に前記部分マンテルを載置して搬入又
は搬出する搬入搬出工程と、前記高炉の炉体櫓に設けら
れた吊手段によって前記部分マンテルを前記台車から吊
り上げて炉体を組み立てる又は前記部分マンテルを前記
炉体から分離して前記台車に吊り下げて炉体を解体する
組立解体工程と、前記受梁に沿って走行可能に設けられ
た安全天井を必要な時に着脱して前記炉体の底部組立又
は解体を行なう炉体底部組立解体工程とを含むことを特
徴とする高炉の組立解体方法。
5. A method of assembling and disassembling a blast furnace in which partial mantels obtained by dividing a blast furnace furnace body into a plurality of parts in a horizontal direction are sequentially loaded and assembled or sequentially unloaded and dismantled, provided between the cast floor portion of the blast furnace and the furnace body. A loading / unloading step of loading and unloading the partial mantel by placing the partial mantel on a carriage traveling between the supporting columns of the furnace body on the received receiving beam, and a suspending means provided on the furnace tower of the blast furnace. Assembling the furnace body by lifting the partial mantel from the bogie or disassembling the furnace body by separating the partial mantel from the furnace body and suspending the partial mantel from the bogie, so that the furnace can run along the receiving beam; A furnace bottom assembly dismantling step of attaching and detaching the provided safety ceiling when necessary to assemble or disassemble the furnace bottom.
JP28373297A 1997-10-16 1997-10-16 Blast furnace assembly / disassembly apparatus and assembly / disassembly method Expired - Fee Related JP4085293B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP28373297A JP4085293B2 (en) 1997-10-16 1997-10-16 Blast furnace assembly / disassembly apparatus and assembly / disassembly method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP28373297A JP4085293B2 (en) 1997-10-16 1997-10-16 Blast furnace assembly / disassembly apparatus and assembly / disassembly method

Publications (2)

Publication Number Publication Date
JPH11124612A true JPH11124612A (en) 1999-05-11
JP4085293B2 JP4085293B2 (en) 2008-05-14

Family

ID=17669390

Family Applications (1)

Application Number Title Priority Date Filing Date
JP28373297A Expired - Fee Related JP4085293B2 (en) 1997-10-16 1997-10-16 Blast furnace assembly / disassembly apparatus and assembly / disassembly method

Country Status (1)

Country Link
JP (1) JP4085293B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001214210A (en) * 2000-01-31 2001-08-07 Sankyu Inc Installation method of blast furnace component
JP2022071888A (en) * 2020-10-29 2022-05-17 有限会社大洋産業 Method for dismantling suspended structure
CN114674154A (en) * 2022-03-24 2022-06-28 广东韶钢松山股份有限公司 Maintenance method for hot blast stove

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001214210A (en) * 2000-01-31 2001-08-07 Sankyu Inc Installation method of blast furnace component
JP2022071888A (en) * 2020-10-29 2022-05-17 有限会社大洋産業 Method for dismantling suspended structure
CN114674154A (en) * 2022-03-24 2022-06-28 广东韶钢松山股份有限公司 Maintenance method for hot blast stove
CN114674154B (en) * 2022-03-24 2024-01-09 广东韶钢松山股份有限公司 Maintenance method for hot blast stove

Also Published As

Publication number Publication date
JP4085293B2 (en) 2008-05-14

Similar Documents

Publication Publication Date Title
KR100468106B1 (en) Method and apparatus for short-term relining or construction of blast furnace
CN204958963U (en) Jacking device that converter trunnion ring was changed
JP3539885B2 (en) Mobile suspension apparatus for furnace body ring block, blast furnace body dismantling method, and blast furnace body construction method
CN104210958A (en) RH steel ladle vehicle-mounted lifting method and device
JP4126469B2 (en) Blast furnace body disassembly and assembly equipment
JP4085293B2 (en) Blast furnace assembly / disassembly apparatus and assembly / disassembly method
JP4472115B2 (en) Blast furnace assembly method
JP2001248161A (en) Method for installing concrete block on face of slope and truck and device for installing it
JP4841809B2 (en) Blast furnace construction method
JPH11124611A (en) Device for assembling and disassembling blast furnace and method for assembling and disassembling thereof
JP4592860B2 (en) Blast furnace component installation method
JPS6213514A (en) Carriage for replacing converter
JP3046552B2 (en) Blast furnace furnace construction method
CN206901598U (en) A kind of gap bridge crossbeam removes handling apparatus
JP3583354B2 (en) Suspension device for furnace body ring block for blast furnace renovation
US3804392A (en) Blast furnace top structure
CN112814690B (en) Shield construction system and shield construction method
JP3656523B2 (en) Furnace body support method during blast furnace renovation
JP2000144220A (en) Method for building, dismantling and repairing blast furnace
JP4064002B2 (en) Dismantling method of blast furnace mantel
JPH01168803A (en) Method and device for repairing blast furnace
JPH0940338A (en) Carrying device for escalator frame
JP2000143139A (en) Hoisting jig for crane
JP3565123B2 (en) Foundation reinforcement method and foundation reinforcement structure for blast furnace ring block suspension device in blast furnace furnace ring block method
JP4583536B2 (en) Ring mantel centering method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040510

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050325

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070904

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20071105

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080122

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080206

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110228

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120229

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130228

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140228

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees