JPH1096005A - Method for disassembling furnace-bottom part in blast furnace - Google Patents

Method for disassembling furnace-bottom part in blast furnace

Info

Publication number
JPH1096005A
JPH1096005A JP25025696A JP25025696A JPH1096005A JP H1096005 A JPH1096005 A JP H1096005A JP 25025696 A JP25025696 A JP 25025696A JP 25025696 A JP25025696 A JP 25025696A JP H1096005 A JPH1096005 A JP H1096005A
Authority
JP
Japan
Prior art keywords
furnace
blast furnace
layer
blast
brick
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP25025696A
Other languages
Japanese (ja)
Other versions
JP3110684B2 (en
Inventor
Hirotaka Kojima
啓孝 小島
Masao Fujita
昌男 藤田
Hiroya Marushima
弘也 丸島
Keishi Matsuda
惠嗣 松田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
Kawasaki Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Steel Corp filed Critical Kawasaki Steel Corp
Priority to JP08250256A priority Critical patent/JP3110684B2/en
Publication of JPH1096005A publication Critical patent/JPH1096005A/en
Application granted granted Critical
Publication of JP3110684B2 publication Critical patent/JP3110684B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)
  • Working Measures On Existing Buildindgs (AREA)
  • Blast Furnaces (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a disassembling method for furnace-bottom part in a blast furnace, in which the working time is shorter than a conventional method, the cost is low and the working environment is good. SOLUTION: At the time of executing the blowing-down of the blast furnace and the carrying-out and removal of solidified material layer 2 and a furnace- bottom brick layer 1 remaining at the furnace-bottom part to the outside of the furnace, the furnace body of the blast furnace is horizontally cut off at the higher position than the solidified material layer 2. After hanging and fixing the upper furnace body from the cut-off position with supporting columns 4 as it is, the lower furnace body from the cut-off position is removed over the whole periphery of the furnace body to integrally pull out the solidified material layer 2 and the furnace-bottom brick.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、高炉の解体方法に
関し、特に、吹き卸し後の炉底部に残存する凝固物を炉
底煉瓦と一体で解体除去する技術である。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for dismantling a blast furnace, and more particularly, to a technique for dismantling and removing solidified material remaining on a furnace bottom after blowing off integrally with a furnace bottom brick.

【0002】[0002]

【従来の技術】高炉の改修等に際してその炉底部を解体
する従来の作業方法を説明すると、まず、該炉底部を囲
む外周壁の一部の鉄皮や内張煉瓦をバックホー、ショベ
ル等の建設重機で破壊し、該建設重機が炉底部内に侵入
できるような孔を開ける。そして、該炉底部に残存して
いるコークスを、上記建設重機で炉外に押し出して、除
去する。その後、作業者が炉内に入り、削岩機や発破を
用いて、その下に残っている銑鉄、スラグあるいはコー
クスの混合したほぼ300〜500トンの凝固物(1枚
岩のように一体化していることが多い)を砕き、炉外に
搬出すると共に、さらに上記建設重機で、炉底カーボン
煉瓦を破壊し、炉外に搬出する。
2. Description of the Related Art A conventional method of disassembling a furnace bottom when refurbishing a blast furnace or the like will be described. Destroy with heavy equipment and make holes to allow the heavy construction equipment to enter the furnace bottom. Then, the coke remaining in the furnace bottom is extruded out of the furnace by the heavy construction machine and removed. After that, an operator enters the furnace and uses a rock drill or blasting machine to mix approximately 300 to 500 tonnes of coagulated iron (slag or coke) remaining underneath (unified like a monolith). Crushed) and transported to the outside of the furnace, and further, the above construction heavy equipment destroys the bottom carbon brick and transports the brick to the outside of the furnace.

【0003】ところで、高炉の改修工事は、工事期間を
できうるかぎり短縮する必要があるため、炉体内張煉瓦
や上記凝固物が完全に室温に冷却する前に、解体作業が
開始され、しかもその作業環境は、炉底部の前記した孔
と炉頂部のマンホール程度しかない場所で、且つ、粉塵
の発生が多い(所謂3K職場)。また、炉壁や炉底の煉
瓦、及び前記凝固物は固くて重いので、前記孔やマンホ
ールから搬出するには、それらを小さく分割する必要が
ある。そのため、従来の解体作業に要する時間は非常に
長いものであった(長時間作業と高コスト作業)。
[0003] In the refurbishment work of the blast furnace, it is necessary to shorten the construction period as much as possible. Therefore, the dismantling work is started before the bricks in the furnace and the solidified material are completely cooled to room temperature. The work environment is a place where there is only the above-mentioned hole at the bottom of the furnace and a manhole at the top of the furnace, and a lot of dust is generated (a so-called 3K workplace). In addition, since the bricks on the furnace wall and the furnace bottom and the solidified material are hard and heavy, they need to be divided into small pieces in order to carry them out of the holes and manholes. Therefore, the time required for the conventional disassembly work is very long (long work and high cost work).

【0004】そこで、このような悪環境での作業を少し
でも軽減する目的で、例えば、特公昭45−19468
号公報は、高炉の内張煉瓦破砕除去機を開発し、炉内作
業の機械化を提案している。しかしながら、この機械化
技術を採用しても、狭い場所での機械操作となるため、
操作テクニックに熟練を要し、また、1基の高炉に対し
て、十数年に一度の高炉改修のために、特別に専用の高
価な解体装置を製作、準備することは、経済的に好まし
いことではなかった。
[0004] Therefore, for the purpose of reducing the work in such a bad environment as much as possible, for example, Japanese Patent Publication No. 45-19468.
Japanese Patent Application Laid-Open No. H10-216550 has developed a blast furnace lining brick crusher and has proposed the mechanization of work inside the furnace. However, even if this mechanization technology is adopted, since the machine is operated in a narrow place,
It is economically preferable to prepare and prepare specially-used expensive dismantling equipment for blast furnace renovation once every ten years or more, which requires skill in operation techniques and for one blast furnace. That was not the case.

【0005】[0005]

【発明が解決しようとする課題】本発明は、かかる事情
を鑑み、従来より作業時間が短く、コストが安く、作業
環境の良い高炉炉底部の解体方法を提供することを目的
としている。
SUMMARY OF THE INVENTION In view of the foregoing, it is an object of the present invention to provide a method for dismantling a blast furnace bottom having a shorter working time, a lower cost, and a better working environment.

【0006】[0006]

【課題を解決するための手段】発明者は、上記目的を達
成するため効率の良い解体について研究し、炉底凝固物
層を炉底煉瓦層と一体で炉外に搬出、除去することを着
想した。そして、その具現化に鋭意努力し、本発明を完
成させるに至った。すなわち、本発明は、高炉を吹き卸
し、その炉底部に残存する凝固物層及び炉底煉瓦層を炉
外に搬出、除去するに際し、高炉の炉体を、上記凝固物
層より高い位置で水平に切断し、その切断位置より上方
の炉体をそのまま高炉の支柱で懸架、固定した後、上記
切断位置より下方の炉体鉄皮を炉体全周にわたり撤去
し、上記凝固物層及び炉底煉瓦を一体として炉外へ引き
出すことを特徴とする高炉炉底部の解体方法である。
Means for Solving the Problems The inventor studied efficient dismantling to achieve the above object, and conceived of carrying out and removing the bottom solidified layer out of the furnace integrally with the bottom brick layer. did. Then, they worked diligently to realize the present invention and completed the present invention. That is, the present invention blows down the blast furnace and carries out the coagulated material layer and the bottom brick layer remaining at the bottom of the furnace to the outside of the furnace, and removes the furnace body of the blast furnace at a position higher than the solidified layer. After the furnace body above the cutting position is suspended and fixed by the blast furnace column as it is, the furnace shell below the cutting position is removed over the entire circumference of the furnace body, and the solidified material layer and the furnace bottom are removed. This is a method for dismantling the bottom of a blast furnace, wherein the bricks are integrally pulled out of the furnace.

【0007】また、本発明は、上記炉底煉瓦層を、その
底部に沿いワイヤ・ソーで水平に切断して高炉基礎と分
離し、上記凝固物層を載せたまま炉外へ引き出すことを
特徴とする高炉炉底部の解体方法である。さらに、本発
明は、上記炉底煉瓦層を横引き手段、台車及びドーリ架
台を用いて引き出すことを特徴とする高炉炉底部の解体
方法でもある。
The present invention is also characterized in that the furnace bottom brick layer is cut horizontally with a wire saw along the bottom thereof to separate it from the blast furnace foundation, and is drawn out of the furnace with the solidified layer placed thereon. Of the bottom of the blast furnace. Furthermore, the present invention is also a method for dismantling a blast furnace furnace bottom, wherein the furnace bottom brick layer is drawn out using a horizontal pulling means, a truck and a dolly mount.

【0008】本発明では、高炉炉底部の解体を、上記の
ような構成で行うようにしたので、従来より作業時間が
短くて、コストが安く、しかも作業環境を改善した状態
で行えるようになる。
In the present invention, since the bottom of the blast furnace is dismantled with the above-described structure, the working time is shorter, the cost is lower, and the working environment is improved in comparison with the related art. .

【0009】[0009]

【発明の実施の形態】本発明に係る高炉炉底底部の解体
方法をその手順を追い以下に説明する。それは、吹き卸
し操業の最終出銑の後、炉底部にドリルで開口部を設
け、炉床部に滞留している溶銑、スラグをこの開口部か
ら排出してから、炉体上部より注水して炉内残留物及び
炉体の冷却を行った後に、本発明に係る解体方法を実施
する。
BEST MODE FOR CARRYING OUT THE INVENTION A method of dismantling a blast furnace bottom according to the present invention will be described below, following the procedure. After the final tapping of the blow-off operation, an opening is provided in the furnace bottom with a drill, and the hot metal and slag remaining in the hearth are discharged from this opening, and then water is injected from the upper part of the furnace body. After cooling the furnace residue and the furnace body, the dismantling method according to the present invention is performed.

【0010】まず、図2に示すように、炉体の羽口レベ
ルより上部で炉体を支柱4にリフトジャッキ5を介して
懸架する。これはこの後炉底部を切り離すときに炉体上
部を支持するためである。次に炉底煉瓦層1の上に残留
する凝固物層2の上面より高い位置10以下の炉底部の
鉄皮を撤去し、炉体下部を開放する。鉄皮の撤去方法は
いかなる方法でもよいが、鉄皮3を炉底底板レベルより
1000〜2000mm程度上方で水平に切断し、上記
位置10より鉄皮3を縦に切断して花弁型にし、各花弁
型の鉄皮3を位置10のレベルで水平に切断して搬出す
る方法が簡便である。開放された炉体下部の上部のレン
ガを建設重機15で壊し、炉内残留物の内、コークス層
などの容易に崩せるものは、建設重機15で炉外へ排出
除去して、炉底部を水平に移動する(後述)ときに位置
10よりも上の残された炉体鉄皮と接触しないようにす
る。凝固物層2は、通常300〜500tの重量があ
り、直径はほぼ炉床径に近く、また高さは3.5m程度
である。
First, as shown in FIG. 2, the furnace body is suspended from the tuyere level of the furnace body to the column 4 via the lift jack 5. This is for supporting the upper part of the furnace body when the furnace bottom is cut off thereafter. Next, the iron shell at the furnace bottom at a position 10 or less higher than the upper surface of the solidified material layer 2 remaining on the furnace bottom brick layer 1 is removed, and the lower part of the furnace body is opened. The method of removing the steel shell may be any method, but the steel shell 3 is cut horizontally about 1000 to 2000 mm above the bottom plate level, and the steel shell 3 is cut vertically from the position 10 to form a petal. A simple method is to cut the petal-shaped steel bar 3 horizontally at the position 10 and carry it out. The upper brick at the lower part of the opened furnace body is broken by the heavy construction machine 15, and the residue in the furnace that can be easily broken, such as a coke layer, is discharged out of the furnace by the heavy construction machine 15, and the furnace bottom is leveled. (Described later) so as not to come into contact with the remaining furnace shell above the position 10. The coagulated material layer 2 usually has a weight of 300 to 500 tons, a diameter substantially close to the hearth diameter, and a height of about 3.5 m.

【0011】次いで、本発明では図1に示すように、こ
の凝固物層2を炉底煉瓦層1と一体にして、炉外に搬出
するために、高炉基礎6上に敷かれた炉底煉瓦層1を水
平に切断し、上下に分離する。この切断は炉底のカーボ
ンレンガの1〜2段で行う。これは通常このレベルの炉
底レンガは改修時でも健全な状態で残っていることと、
カーボンレンガの切断粉は、後の炉底ブロックを一体引
き出しする際に、摩擦抵抗を下げる効果を持つからであ
る。ここでは、この切断をワイヤ・ソー7で行う例を示
す。炉底煉瓦層を上下に切断するレベルよりも上方で鉄
皮に数箇所孔をコアボーリングで開け、図3(b)に示
すように金具9を介して炉底煉瓦層1と鉄皮3の間を結
合する。その後図3(a)に示すように該ワイヤー・ソ
ー7を通す水平で且つ貫通する孔8を、該炉底煉瓦層1
にコアボーリングを用いて開ける。図4に示すように、
貫通孔8にワイヤ・ソー7を通し、それを稼働すること
で、炉底煉瓦層1を切断する。図中、斜線部はワイヤー
・ソーによる切断面を示す。この切断は、原則として炉
底煉瓦層1の全体を水平面で切り離すことであり、図4
では、ワイヤー・ソー7を4本使用した例である。ただ
し、上記支柱4の間隔が狭い高炉では、炉底煉瓦層1の
直径が大きすぎて、搬出時に支柱4間を該炉底煉瓦層1
が通過できない恐れもある。その場合は、本発明では該
炉底煉瓦層1およびその上にある凝固物層2を縦切り
し、数個のブロックに分割してもよい。
Next, in the present invention, as shown in FIG. 1, the coagulated material layer 2 is integrated with the furnace bottom brick layer 1 and is taken out of the furnace so as to be taken out of the furnace. Layer 1 is cut horizontally and separated vertically. This cutting is performed in one or two stages of carbon brick at the bottom of the furnace. This means that hearth bricks of this level usually remain in good condition even during renovation,
This is because the cutting powder of the carbon brick has an effect of lowering the frictional resistance when the furnace bottom block is pulled out later. Here, an example in which this cutting is performed by the wire saw 7 is shown. Several holes are drilled in the steel shell by core boring above the level at which the hearth brick layer is cut up and down, and as shown in FIG. Join between. Thereafter, as shown in FIG. 3 (a), a horizontal and penetrating hole 8 for passing the wire saw 7 is formed in the hearth brick layer 1
And open using core boring. As shown in FIG.
By passing the wire saw 7 through the through hole 8 and operating the same, the furnace bottom brick layer 1 is cut. In the figure, the hatched portion indicates the cut surface by the wire saw. This cutting is, in principle, to cut the whole of the hearth brick layer 1 on a horizontal plane.
In this example, four wire saws 7 are used. However, in a blast furnace in which the distance between the columns 4 is narrow, the diameter of the bottom layer 1 is too large, and the space between the columns 4 is unloaded during the unloading.
May not be able to pass. In this case, in the present invention, the hearth brick layer 1 and the solidified material layer 2 thereon may be vertically cut and divided into several blocks.

【0012】ワイヤ・ソー7で切断されて高炉基礎6か
ら開放された炉底煉瓦層1及び凝固物層2は、図5に示
すように、前記金物9にワイヤをかけ、図示していない
横持ち手段(例えばウイン4又はジャッキ)で引き、炉
体脇の作業床12に待機させた台車13上に載せる。そ
して、該台車13を移動して、台車13ごと待機中のド
ーリ架台14に載せ、図示していないトレーラ等で高炉
近傍から搬出する。
As shown in FIG. 5, the hearth brick layer 1 and the solidified material layer 2 cut by the wire saw 7 and opened from the blast furnace foundation 6 are wrapped with a wire on the hardware 9, and are not shown. It is pulled by a holding means (for example, a win 4 or a jack), and is placed on a carriage 13 waiting on a work floor 12 beside the furnace body. Then, the truck 13 is moved, mounted on the dolly frame 14 in a standby state together with the truck 13, and is carried out from the vicinity of the blast furnace by a trailer (not shown) or the like.

【0013】上記本発明に係る高炉炉底部の解体方法
を、内容積2600m3 、炉床径11.4mの高炉改修
時に採用してみた。その成績は、鉄皮3の切断から炉底
煉瓦層1及び凝固物層2の一体搬出完了までの作業時間
が2日間であった。従来は、これに相当する作業を5日
間で行っていたので、本発明によって大幅に炉底部の解
体作業が効率良くなったと思われる。また、本発明は、
特別な設備あるいは装置を必要とせず、従来から存在す
るものの利用で実施可能なので、設備費が安く、また工
数の削減もできるので、解体作業が従来より大幅に低減
した。さらに、作業者が炉内に入る機会が従来より減る
ので、所謂3K作業の減少効果もある。
The method of disassembling the blast furnace bottom according to the present invention was applied to refurbishment of a blast furnace having an inner volume of 2600 m 3 and a hearth diameter of 11.4 m. As a result, the work time from cutting of the iron shell 3 to completion of unloading of the furnace bottom brick layer 1 and the solidified material layer 2 was two days. Conventionally, the work corresponding to this was performed in 5 days, and it is considered that the present invention has greatly improved the efficiency of dismantling the furnace bottom. Also, the present invention
Since there is no need for special equipment or equipment, it can be implemented using existing ones, so equipment costs are low and man-hours can be reduced, so that dismantling work has been greatly reduced. Further, since the number of opportunities for workers to enter the furnace is reduced as compared with the conventional case, there is also an effect of reducing so-called 3K work.

【0014】[0014]

【発明の効果】以上述べたように、本発明により、吹き
卸し後に高炉の炉底部に残存する凝固物を炉底煉瓦と一
体で、炉外に搬出、除去ができるようになる。その結
果、炉底部の解体が、従来に比べて短時間で且つ容易に
できるようになった。
As described above, according to the present invention, the solidified material remaining at the bottom of the blast furnace after the blow-off can be carried out of the furnace and removed integrally with the bottom brick. As a result, the furnace bottom can be easily disassembled in a shorter time than before.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る高炉炉底部の解体方法を実施して
いる状況を示す縦断面図である。
FIG. 1 is a longitudinal sectional view showing a state in which a method of dismantling a blast furnace bottom according to the present invention is performed.

【図2】本発明に係る解体方法を実施する前に、鉄皮を
花弁状に開く状況を示す図である。
FIG. 2 is a view showing a situation in which the iron skin is opened in a petal shape before the disassembly method according to the present invention is performed.

【図3】炉底煉瓦層に貫通孔を開け、支持金物を取り付
けた図であり、(a)は炉底部側面、(b)は(a)の
記号Aで示す部分の拡大図である。
3A and 3B are diagrams in which a through hole is opened in a furnace bottom brick layer and a supporting hardware is attached, (a) is a side view of a furnace bottom portion, and (b) is an enlarged view of a portion indicated by symbol A in (a).

【図4】炉底煉瓦の貫通孔にワイヤ・ソーを通した状況
を示す平面図である。
FIG. 4 is a plan view showing a situation where a wire saw is passed through a through hole of a hearth brick.

【図5】切断後の炉底煉瓦層及び凝固物層を一体として
炉外に搬出する状況を示す図である。
FIG. 5 is a view showing a situation in which the furnace bottom brick layer and the solidified material layer after cutting are integrally carried out of the furnace.

【符号の説明】[Explanation of symbols]

1 炉底煉瓦層 2 凝固物層 3 鉄皮 4 支柱 5 リフトジャッキ 6 高炉基礎 7 ワイヤ・ソー 8 貫通孔 9 金具 10 凝固物層の上面より高い位置 11 移動方向 12 作業床 13 台車 14 ドーリー架台 15 建設重機 DESCRIPTION OF SYMBOLS 1 Furnace bottom brick layer 2 Solidified material layer 3 Iron shell 4 Prop 5 Lift jack 6 Blast furnace foundation 7 Wire saw 8 Through hole 9 Metal fitting 10 Position higher than upper surface of solidified material layer 11 Moving direction 12 Work floor 13 Dolly 14 Dolly stand 15 Heavy construction equipment

───────────────────────────────────────────────────── フロントページの続き (72)発明者 丸島 弘也 千葉市中央区川崎町1番地 川崎製鉄株式 会社千葉製鉄所内 (72)発明者 松田 惠嗣 千葉市中央区川崎町1番地 川崎製鉄株式 会社千葉製鉄所内 ──────────────────────────────────────────────────の Continuing on the front page (72) Inventor Hiroya Marushima 1 Kawasaki-cho, Chuo-ku, Chiba Kawasaki Steel Works Co., Ltd. (72) Keiji Matsuda 1-Kawasaki-cho, Chuo-ku, Chiba Kawasaki Steel Co., Ltd. Inside the steelworks

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 高炉を吹き卸し、その炉底部に残存する
凝固物層及び炉底煉瓦層を炉外に搬出、除去するに際
し、 高炉の炉体を、上記凝固物層より高い位置で水平に切断
し、その切断位置より上方の炉体をそのまま高炉の支柱
で懸架、固定した後、上記切断位置より下方の炉体鉄皮
を炉体全周にわたり撤去し、上記凝固物層及び炉底煉瓦
を一体として炉外へ引き出すことを特徴とする高炉炉底
部の解体方法。
When the blast furnace is blown off and the solidified layer and the bottom brick layer remaining at the furnace bottom are carried out of the furnace and removed, the furnace body of the blast furnace is horizontally moved at a position higher than the solidified layer. After cutting, the furnace body above the cutting position is suspended and fixed by the blast furnace column as it is, the furnace shell below the cutting position is removed over the entire circumference of the furnace body, and the solidified material layer and the bottom brick are removed. A method for dismantling the bottom of a blast furnace, comprising:
【請求項2】 上記炉底煉瓦層を、その底部に沿いワイ
ヤ・ソーで水平に切断して高炉基礎と分離し、上記凝固
物層を載せたまま炉外へ引き出すことを特徴とする請求
項1記載の高炉炉底部の解体方法。
2. The furnace bottom brick layer is cut horizontally with a wire saw along the bottom thereof to separate it from the blast furnace foundation, and is drawn out of the furnace with the solidified layer placed thereon. A method for dismantling a blast furnace bottom according to claim 1.
【請求項3】 上記炉底煉瓦層を横引き手段、台車及び
ドーリ架台を用いて引き出すことを特徴とする請求項1
又は2記載の高炉炉底部の解体方法。
3. The furnace bottom brick layer is drawn out by using a horizontal pulling means, a bogie, and a dolly mount.
Or the disassembly method of the bottom part of a blast furnace described in 2.
JP08250256A 1996-09-20 1996-09-20 Dismantling method of blast furnace bottom Expired - Fee Related JP3110684B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP08250256A JP3110684B2 (en) 1996-09-20 1996-09-20 Dismantling method of blast furnace bottom

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP08250256A JP3110684B2 (en) 1996-09-20 1996-09-20 Dismantling method of blast furnace bottom

Publications (2)

Publication Number Publication Date
JPH1096005A true JPH1096005A (en) 1998-04-14
JP3110684B2 JP3110684B2 (en) 2000-11-20

Family

ID=17205184

Family Applications (1)

Application Number Title Priority Date Filing Date
JP08250256A Expired - Fee Related JP3110684B2 (en) 1996-09-20 1996-09-20 Dismantling method of blast furnace bottom

Country Status (1)

Country Link
JP (1) JP3110684B2 (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6479011B2 (en) 2000-07-13 2002-11-12 Kawasaki Steel Corporation Method of scrapping furnace bottom section of blast furnace
JP2005298889A (en) * 2004-04-09 2005-10-27 Nippon Steel Corp Method for reconstructing blast furnace
JP2006183105A (en) * 2004-12-28 2006-07-13 Nippon Steel Corp Method for removing furnace body of blast furnace
CN100359103C (en) * 2005-08-30 2008-01-02 上海宝冶建设有限公司 Method for filling slip casting materials into concrete cutting unit
JP2009062561A (en) * 2007-09-05 2009-03-26 Nippon Steel Engineering Co Ltd Method for dismantling furnace bottom part of blast furnace
CN102409119A (en) * 2011-10-28 2012-04-11 中国十九冶集团有限公司 Method for correcting and resetting blast furnace body
CN105821166A (en) * 2015-01-05 2016-08-03 上海宝冶集团有限公司 Extremely large blast furnace modular quick demolition method
CN108642221A (en) * 2018-08-01 2018-10-12 本钢板材股份有限公司 A kind of super-huge blast furnace overhaul quickly takes off furnace system and method
CN109055637A (en) * 2018-09-17 2018-12-21 安徽马钢设备检修有限公司 The hydraulic pressure lift technique of furnace shell installation in a kind of blast furnace overhaul
CN109055638A (en) * 2018-09-17 2018-12-21 安徽马钢设备检修有限公司 A kind of method of last furnace shell and cooled bottom water crossed construction

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102409120B (en) * 2011-10-28 2013-06-12 中国十九冶集团有限公司 Method for replacing bottom of blast furnace

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6479011B2 (en) 2000-07-13 2002-11-12 Kawasaki Steel Corporation Method of scrapping furnace bottom section of blast furnace
JP2005298889A (en) * 2004-04-09 2005-10-27 Nippon Steel Corp Method for reconstructing blast furnace
JP2006183105A (en) * 2004-12-28 2006-07-13 Nippon Steel Corp Method for removing furnace body of blast furnace
CN100359103C (en) * 2005-08-30 2008-01-02 上海宝冶建设有限公司 Method for filling slip casting materials into concrete cutting unit
JP2009062561A (en) * 2007-09-05 2009-03-26 Nippon Steel Engineering Co Ltd Method for dismantling furnace bottom part of blast furnace
CN102409119A (en) * 2011-10-28 2012-04-11 中国十九冶集团有限公司 Method for correcting and resetting blast furnace body
CN105821166A (en) * 2015-01-05 2016-08-03 上海宝冶集团有限公司 Extremely large blast furnace modular quick demolition method
CN108642221A (en) * 2018-08-01 2018-10-12 本钢板材股份有限公司 A kind of super-huge blast furnace overhaul quickly takes off furnace system and method
CN109055637A (en) * 2018-09-17 2018-12-21 安徽马钢设备检修有限公司 The hydraulic pressure lift technique of furnace shell installation in a kind of blast furnace overhaul
CN109055638A (en) * 2018-09-17 2018-12-21 安徽马钢设备检修有限公司 A kind of method of last furnace shell and cooled bottom water crossed construction
CN109055638B (en) * 2018-09-17 2020-05-15 安徽马钢设备检修有限公司 Method for cross construction of blast furnace shell and water-cooled furnace bottom

Also Published As

Publication number Publication date
JP3110684B2 (en) 2000-11-20

Similar Documents

Publication Publication Date Title
JP3110684B2 (en) Dismantling method of blast furnace bottom
KR100982602B1 (en) Method of removing remaining pig iron from blast furnace
RU2274659C2 (en) Method of the furnace relining and the furnace for realization of the direct smelting
JPWO2007135916A1 (en) Method of dismantling the bottom of the blast furnace furnace
WO2006070922A1 (en) Method of dismantling blast furnace body
JP2602407B2 (en) How to remove the contents of the blast furnace bottom from the furnace
JP4802457B2 (en) Method of dismantling the bottom of the blast furnace furnace
KR100958304B1 (en) Relining method of blast furnace
CN101157958A (en) Method for removing blast furnace bottom coagulated remainder iron
JP3591431B2 (en) Dismantling method of blast furnace bottom
JP2003105413A (en) Method for removing residual iron in blast furnace
JP3591432B2 (en) Dismantling method of blast furnace bottom
CN108728599B (en) Blast furnace bottom residual iron dismantling method
CN1250745C (en) Disassembling method for blast-furnace bottom
JP2001003111A (en) Method for dismantling furnace bottom part in blast furnace
JP3858358B2 (en) Dismantling method of blast furnace hearth contents
JP2968122B2 (en) Disassembly and repair method for refractories lining electric furnaces
JP2002030311A (en) Method for dismantling furnace bottom part of blast furnace
JP7496739B2 (en) A method for removing solidified pig iron lumps in a torpedo car
CN208328053U (en) A kind of device not destroying furnace shell replacement blast furnace cooling stave
JP5260135B2 (en) Installation method of tap door device and tap door device.
JPH01168803A (en) Method and device for repairing blast furnace
JPH0196308A (en) Method for operating blow-down in blast furnace
JPH03291311A (en) Method for removing residual iron in blast furnace
JP2003034812A (en) Method of dismantling internal combustion hot-blast stove

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20000905

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080914

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080914

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090914

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090914

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100914

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100914

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110914

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110914

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120914

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120914

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130914

Year of fee payment: 13

LAPS Cancellation because of no payment of annual fees