JPH108466A - Steel pipe holding device for driving steel pipe pile - Google Patents

Steel pipe holding device for driving steel pipe pile

Info

Publication number
JPH108466A
JPH108466A JP15957096A JP15957096A JPH108466A JP H108466 A JPH108466 A JP H108466A JP 15957096 A JP15957096 A JP 15957096A JP 15957096 A JP15957096 A JP 15957096A JP H108466 A JPH108466 A JP H108466A
Authority
JP
Japan
Prior art keywords
steel pipe
pile
pipe pile
holding device
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15957096A
Other languages
Japanese (ja)
Inventor
Isamu Kuramoto
勇 倉本
Masanori Kajiwara
正憲 梶原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP15957096A priority Critical patent/JPH108466A/en
Publication of JPH108466A publication Critical patent/JPH108466A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To minimize the number of times of steel pipe joining in pile driving work by conducting a steel pipe to be driven from the opened side of an annular frame into this frame through a horizontal movement, and clamping the outer periphery of the steel pipe with clamping claws. SOLUTION: A movable frame 8b acts to open, and a steel pipe pile 9 to hold a crane is horizontally moved as its vertical attitude is kept, and conducted into the inside of an annular frame 8 to make the movable frame 8b act to close, and a connecting piece 13 is connected to a receiving member 14 through a connecting pin 15. In this state, a hydraulic cylinder 12 is actuated to carry out clamping, and the steel pipe pile 9 is thereby clamped on its outer periphery with clamping claws 10. As the steel pipe pile 9 is held by the steel pipe holding device of a steel pipe pressing-in machine 7, an excavated soil is made muddy by a jetted water in the lower end part of the steel pipe pile 9. The steel pipe pile 9 is lowered and driven using the annular frame 8 as a guide, and weldedly fixed at the butted spot of two steel pipe piles.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、主として、湾岸の
防波堤などの施工に際して、特に、既存のヨットハーバ
ーの出入り口を跨いで、杭打ち施工が行われる、施工条
件が限定された港湾での、鋼管杭の打設に際して使用さ
れる鋼管杭打設用の鋼管保持装置に関するものである。
BACKGROUND OF THE INVENTION The present invention relates mainly to the construction of breakwaters on a bay shore, particularly in harbors where construction conditions are limited, where pile driving is carried out across the entrance of an existing yacht harbor. The present invention relates to a steel pipe holding device for driving a steel pipe pile, which is used for driving a steel pipe pile.

【0002】[0002]

【従来の技術】港湾の岸壁施工に鋼管杭の連続打設を行
う場合、例えば、特開平3−169913号公報に開示
されているような、従来の自走式の鋼管用杭打ち装置を
用いると、装置自体に、圧入(杭打ち)機、掘進機、鋼
管内に土砂を埋め戻す圧密機などを装備する上、自走の
ための機構が必要で、かなりの重量となり、施工現場へ
の杭打ち装置の持ち込み、移動、持ち出しにクレーンを
使用することが困難である。
2. Description of the Related Art When a steel pipe pile is continuously driven for pier construction in a harbor, a conventional self-propelled steel pipe pile driving apparatus as disclosed in Japanese Patent Application Laid-Open No. 3-169913 is used. In addition, the equipment itself is equipped with a press-in (pile driving) machine, a digging machine, a consolidation machine that fills the soil in the steel pipe, etc., and a mechanism for self-propelling is required, and it becomes quite heavy, It is difficult to use a crane to bring, move, and take out the pile driver.

【0003】特に、湾岸に既存設備があり、陸上からの
装置や材料の搬入、搬出が困難な場合、海上からフロー
ティング・クレーンを用いて、機材の搬入、搬出を余儀
なくされる条件では、施工自体が非常に困難に、あるい
は、不可能になる。そこで、クレーンによる搬入、搬出
および移動が可能な、例えば、130トン級の鋼管用圧
入機を用いて、鋼管杭の打設を実現する施工法が、現況
の施工現場で必要となった。
[0003] In particular, when existing facilities are located on the Gulf and it is difficult to carry in and carry out equipment and materials from land, the construction itself must be carried out under conditions that require the use of floating cranes to carry in and out equipment from the sea. Becomes very difficult or impossible. Therefore, there is a need at the current construction site for a construction method for driving a steel pipe pile using a 130-ton class steel pipe press-fitting machine that can be carried in, carried out, and moved by a crane.

【0004】そこで、本発明者は、既に、施工現場の周
囲に既存設備があり、施工条件が厳しい場合でも、小型
軽量な鋼管用圧入機を用いて、鋼管杭の打設が実現でき
る、鋼管杭の打設工法を提唱している。
[0004] Therefore, the present inventor has proposed that a steel pipe pile can be driven using a small and lightweight steel pipe press-in machine even when there are existing facilities around the construction site and construction conditions are severe. He has proposed a pile driving method.

【0005】[0005]

【発明が解決しようとする課題】しかし、このような現
場では、施工箇所の直上に、橋梁などの障害物が存在す
る場合があり、この際には、鋼管杭の長さを、予め、短
くして置かないと、上記障害物のために、鋼管杭を竪に
した状態で、鋼管圧入機のクランパー(鋼管保持装置)
に挿入することができない。これは、従来の鋼管圧入機
に用いられるクランパーが、円環状のフレームの内側
に、該フレームの半径方向に移動可能なクランプ爪を配
置した構成になっていて、上方から鋼管杭をフレーム内
に挿入するためである。
However, in such a site, there may be an obstacle such as a bridge just above the construction site. In this case, the length of the steel pipe pile is reduced in advance. If not, the clamper of the steel pipe press-in machine (steel pipe holding device) with the steel pipe pile upright due to the obstacle
Can not be inserted into This is because the clamper used in the conventional steel pipe press-fitting machine has a configuration in which a clamp claw that can move in the radial direction of the frame is arranged inside the annular frame, and the steel pipe pile is inserted into the frame from above. This is for insertion.

【0006】例えば、グランドレベルに対して障害物が
5mの高さにあるとした場合、通常、鋼管圧入機のクラ
ンパーの上縁、即ち、上記フレームの上縁からグランド
レベルまでが1.5m程度あることから、5m長さの鋼
管杭を採用することができず、特別に、3.5m以下
の、短い鋼管杭を用意しなければならない。これは、必
要な鋼管杭の施工長さを得るために、鋼管継ぎの回数を
倍増しなければならないことを意味し、製作コスト、施
工工程、時間の増加をもたらし、全体として、不経済な
結果をもたらす。
For example, if the obstacle is at a height of 5 m with respect to the ground level, usually, the upper edge of the clamper of the steel pipe press-in machine, that is, from the upper edge of the frame to the ground level is about 1.5 m. For this reason, a steel pipe pile having a length of 5 m cannot be employed, and a short steel pipe pile having a length of 3.5 m or less must be prepared. This means that the number of steel pipe joints must be doubled in order to obtain the required length of steel pipe piles, resulting in increased production costs, construction processes, and time, and as a whole, uneconomical results. Bring.

【0007】また、鋼管杭には、その下端外周におい
て、排土用に、ベルト状の環部材が装着してあって、打
設の際の孔部土壁が、鋼管外周に押し付けられるのを防
止している。このため、鋼管杭をクランパーに挿入する
際には、環部材が通過するだけのクリアランスが必要で
あり、次に、クランプ爪で鋼管の外周を保持する際に
は、各クランプ爪を、油圧手段などを用いて、鋼管外周
面に向けて、かなり前進させる必要があり、クランパー
の構成が複雑となるだけでなく、クランプ制御も面倒で
ある。
Further, a belt-shaped ring member is attached to the steel pipe pile at the outer periphery at the lower end thereof for discharging the earth, and it is necessary to prevent the hole soil wall at the time of driving from being pressed against the outer periphery of the steel pipe. Preventing. For this reason, when inserting the steel pipe pile into the clamper, it is necessary to provide a clearance that allows the ring member to pass through. Next, when holding the outer circumference of the steel pipe with the clamp claws, each of the clamp claws is moved by hydraulic means. It is necessary to move the steel tube toward the outer peripheral surface of the steel pipe considerably by using such a method. This not only complicates the structure of the clamper but also complicates the clamp control.

【0008】本発明は、上記事情に基づいてなされたも
ので、クランパーの上縁からグランドレベルまでの長さ
を有効に活用して、施工ラインの上に、橋梁などの障害
物があっても、相当程度、長さを持った鋼管杭を用い
て、杭の打設作業が行え、鋼管継ぎの回数をできるだけ
少なくするように工夫した、鋼管杭打設用の鋼管保持装
置を提供することを目的としている。
[0008] The present invention has been made based on the above circumstances, and effectively utilizes the length from the upper edge of the clamper to the ground level so that even if there is an obstacle such as a bridge on the construction line. It is intended to provide a steel pipe holding device for driving a steel pipe pile, which is capable of performing a pile driving operation using a steel pipe pile having a considerable length, and reducing the number of steel pipe joints as much as possible. The purpose is.

【0009】[0009]

【課題を解決するための手段】このため、本発明では、
所定の施工ラインに沿って鋼管杭を連続的に打設する鋼
管杭の打設に際して、打設すべき鋼管を、その外周から
クランプする鋼管保持装置において、クランプ爪を内周
に装備した環状フレームは、水平方向に関して、互いに
開閉可能な、固定フレームと、該固定フレームにヒンジ
された可動フレームとから構成されており、打設すべき
鋼管は、環状フレームの開放された側から水平移動で上
記環状フレーム内に誘導され、クランプ爪で外周をクラ
ンプされることを特徴とする。
Therefore, in the present invention,
An annular frame equipped with a clamp claw on an inner periphery of a steel pipe holding device for clamping a steel pipe to be driven from an outer periphery thereof when the steel pipe pile is continuously driven along a predetermined construction line. Is composed of a fixed frame, which can be opened and closed with respect to the horizontal direction, and a movable frame hinged to the fixed frame.The steel pipe to be cast is horizontally moved from the open side of the annular frame. It is guided in the annular frame, and the outer circumference is clamped by a clamp claw.

【0010】この場合、上記固定フレームは、施工ライ
ン後方側の半円弧状の抱持部材で、また、施工ライン前
方に対して開放されるように、上記固定フレームにヒン
ジされた、施工ライン前方側の半円弧状の抱持部材で構
成されていることが、好ましい実施の形態である。
In this case, the fixed frame is a semicircular holding member on the rear side of the construction line, and is hinged to the fixed frame so as to be open to the front of the construction line. It is a preferred embodiment that it is constituted by a semicircular holding member on the side.

【0011】従って、この装置を用いて鋼管杭の打設を
行えば、杭打ちに際して、仮に、施工ラインの上方に、
橋梁などの障害物があっても、鋼管継ぎの回数を低減す
ることができ、施工時間の短縮、および、高い経済性を
発揮できることになる。
[0011] Therefore, if a steel pipe pile is driven by using this apparatus, when the pile is driven, it is supposed that the pile is temporarily placed above the construction line.
Even if there is an obstacle such as a bridge, it is possible to reduce the number of steel pipe joints, thereby shortening the construction time and exhibiting high economic efficiency.

【0012】[0012]

【発明の実施の形態】以下、本発明の鋼管の保持装置を
用いて、鋼管杭を打設する工法を、図面を参照しなが
ら、具体的に説明する。ここでは、先ず、普通の、例え
ば、60トン級の、所謂、やどかりタイプの鋼矢板用圧
入機1(特に、この実施の形態では、H鋼兼用圧入機を
用いるとよい)およびカウンターウエイト2を使用し
て、図1ないし図3に示すように、施工ライン3の開始
端の延長線上に4枚程度の反力用鋼矢板4を打設する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A method for driving a steel pipe pile using the steel pipe holding device of the present invention will be specifically described below with reference to the drawings. Here, first, an ordinary, for example, a 60-ton class, so-called, Yadatori type steel sheet pile press-fitting machine 1 (in particular, in this embodiment, an H-steel press-fitting machine is preferably used) and a counterweight 2 are used. As shown in FIGS. 1 to 3, about four steel sheet piles 4 for reaction force are cast on the extension of the starting end of the construction line 3.

【0013】その上で、鋼矢板4に鋼矢板用圧入機1を
支持させると共に、図4ないし図6に示すように、施工
ライン3上の所要位置3aに支持鋼材(例えば、H鋼)
5を打設し、図7および図8に示すように、鋼矢板4と
支持鋼材5との間で、施工ライン3に沿って、その左右
に導枠材6、6を架設する。
Then, the steel sheet pile press-fitting machine 1 is supported on the steel sheet pile 4 and, as shown in FIGS. 4 to 6, a supporting steel material (for example, H steel) is placed at a required position 3a on the construction line 3.
7 and 8, between the steel sheet pile 4 and the supporting steel material 5, along the construction line 3, guide frame members 6, 6 are laid on the left and right sides thereof.

【0014】この状態で、クレーン(図示せず)を用い
て、鋼矢板用圧入機1を撤去し、次いで、鋼管用圧入機
7を搬入する。そして、図11ないし図13に示すよう
に、クランプ爪10で左右から鋼矢板4を挟持すること
により、鋼矢板4に鋼管用圧入機7を支持させる。
In this state, using a crane (not shown), the press machine 1 for steel sheet piles is removed, and then the press machine 7 for steel pipes is carried in. Then, as shown in FIGS. 11 to 13, the steel sheet pile 4 is supported by the steel sheet pile 4 by holding the steel sheet pile 4 from the left and right with the clamp claws 10.

【0015】この鋼管用圧入機には、本発明に係わる鋼
管保持装置(クランパー)が装備してある。即ち、この
鋼管保持装置は、図9および図10に示すように、施工
ライン3に沿って鋼管杭を連続的に打設する際、打設す
べき鋼管杭9を、その外周からクランプするもので、パ
ッド状のクランプ爪10を内周に装備した環状フレーム
8は、水平方向に関して、互いに開閉可能な、固定フレ
ーム8aと、固定フレーム8aにヒンジされた可動フレ
ーム8bとから構成されている。
This steel pipe press-fitting machine is equipped with a steel pipe holding device (clamper) according to the present invention. That is, as shown in FIGS. 9 and 10, the steel pipe holding device clamps the steel pipe pile 9 to be driven from its outer periphery when continuously driving the steel pipe pile along the construction line 3, as shown in FIGS. The annular frame 8 equipped with pad-shaped clamp claws 10 on the inner periphery is composed of a fixed frame 8a which can be opened and closed in the horizontal direction and a movable frame 8b hinged to the fixed frame 8a.

【0016】なお、この実施の形態では、固定フレーム
8aは、施工ライン後方側の半円弧状の抱持部材で、ま
た、可動フレーム8bは、施工ライン前方に対して開放
されるように、固定フレーム8aに対して、それの一側
に設けたヒンジピン11によってヒンジされた、施工ラ
イン前方側の半円弧状の抱持部材で、それぞれ、構成さ
れている。また、固定フレーム8aには油圧シリンダ1
2で進退される連結子13があり、これには、可動フレ
ーム8bの自由端側にある受け部材14が対応してい
て、それぞれに設けた連結孔13a、14aを介して、
連結ピン15の嵌脱操作で、両者の連結および解離を行
えるようになっている。
In this embodiment, the fixed frame 8a is a semicircular holding member on the rear side of the construction line, and the movable frame 8b is fixed so as to be open to the front of the construction line. Each of the frame 8a is constituted by a semicircular holding member that is hinged by a hinge pin 11 provided on one side of the frame 8a on the front side of the construction line. Also, the hydraulic cylinder 1 is mounted on the fixed frame 8a.
There is a connector 13 which moves forward and backward at 2, and a receiving member 14 corresponding to the free end side of the movable frame 8b corresponds to the connector 13 via connection holes 13a and 14a provided respectively.
The connection and disconnection of the two can be performed by the operation of fitting and removing the connection pin 15.

【0017】従って、鋼管杭9を環状フレーム8内に挿
入する場合に、先ず、施工ラインの前方で、可動フレー
ム8bを開放動作し、クレーンなどで保持された鋼管杭
9を前方から後方に向けて、垂直姿勢のまま、水平に移
動し、環状フレーム8の内側に誘導する。この状態で、
可動フレーム8bを閉動作し、連結ピン15を用いて連
結子13を受け部材14に連結する。この状態で、油圧
シリンダ12を動作して、締め付けを行うことで、鋼管
杭9は、クランプ爪10で、その外周をクランプされる
のである。
Therefore, when inserting the steel pipe pile 9 into the annular frame 8, first, the movable frame 8b is opened in front of the construction line, and the steel pipe pile 9 held by a crane or the like is turned from the front to the rear. Then, while moving vertically, it is moved horizontally and guided inside the annular frame 8. In this state,
The movable frame 8 b is closed, and the connector 13 is connected to the receiving member 14 using the connection pin 15. In this state, by operating the hydraulic cylinder 12 and tightening, the outer periphery of the steel pipe pile 9 is clamped by the clamp claws 10.

【0018】このようにして、鋼管用圧入機7の鋼管保
持装置(クランパー)で、鋼管杭9を保持しながら、鋼
管杭9の下端部でジェット噴水により、掘削土を泥状化
する。このために、鋼管杭9の下端には、ジェット噴射
のためのノズル16が溶接などの手段で、予め装着され
ている。そして、通常のように、環状フレーム8をガイ
ドとして、鋼管杭9を降下、打設するのである。なお、
この実施の形態では、鋼管杭9は、上下、2本の杭部材
9a、9bに分割されており、図14に示すように、そ
の突き合わせの箇所で、熔着される。
In this way, the excavated soil is muddy by jet fountain at the lower end of the steel pipe pile 9 while holding the steel pipe pile 9 by the steel pipe holding device (clamper) of the steel pipe press-fitting machine 7. For this purpose, a nozzle 16 for jet injection is previously mounted on the lower end of the steel pipe pile 9 by means such as welding. Then, as usual, the steel pipe pile 9 is lowered and driven using the annular frame 8 as a guide. In addition,
In this embodiment, the steel pipe pile 9 is divided into upper and lower two pile members 9a and 9b, and is welded at the abutting portion as shown in FIG.

【0019】この場合、図15および図16に示すよう
に、鋼管杭9の打設最終段階で鋼管保持装置に保持され
る鋼管杭9(上杭部材9a)の上端に、鋼管杭9の上端
の、強度不足による撓み変形を回避するためと、その後
の鋼管用圧入機7を支持させるため、例えば、十字型の
梁板よりなる支持部17aを備えた蓋部材17を、嵌挿
などの手段で装備して、支持部17aを、次の鋼管杭
9’の打設工程に入る際の鋼管圧入機7の支持に使用す
る(図17ないし図21参照)。なお、この実施の形態
では、鋼管杭9を、その杭打ち止め高さ18まで圧入す
るために、図17に示すように、最終的に、環状フレー
ム8には補助杭(ヤットコ)19が装着され、圧入に使
用される。
In this case, as shown in FIGS. 15 and 16, the upper end of the steel pipe pile 9 (the upper pile member 9a) held by the steel pipe holding device at the final stage of the driving of the steel pipe pile 9 is attached to the upper end of the steel pipe pile 9. In order to avoid bending deformation due to insufficient strength and to support the subsequent steel pipe press-fitting machine 7, for example, a cover member 17 provided with a support portion 17a formed of a And the support portion 17a is used to support the steel pipe press-fitting machine 7 when the next steel pipe pile 9 'driving process is started (see FIGS. 17 to 21). In addition, in this embodiment, in order to press-fit the steel pipe pile 9 to its pile driving height 18, an auxiliary pile (Yatco) 19 is finally mounted on the annular frame 8 as shown in FIG. 17. Used for press fitting.

【0020】このような構成では、杭打ちに、クレーン
で搬入、搬出、移動が可能な小型軽量の鋼管用圧入機7
が使用でき、厳しい施工現場に適応することが可能とな
る。また、施工ラインの途中に、既存のヨットハーバー
の出入り口があり、施工ラインが中断されるような施工
条件でも、クレーン、特に、海上からのフローティング
・クレーンで、鋼管用圧入機7の移動が簡単に行える。
そして、この発明の鋼管保持装置を用いて鋼管杭を保持
し、鋼管杭の打設を行えば、杭打ちに際して、仮に、施
工ラインの上方に、橋梁などの障害物があっても、鋼管
継ぎの回数を低減することができ、施工時間の短縮、お
よび、高い経済性を発揮できることになる。
With such a configuration, a compact and lightweight press-fitting machine 7 for steel pipes, which can be carried in, carried out and moved by a crane, into a pile driver.
Can be used and can be adapted to severe construction sites. In addition, there is an entrance to and exit from the existing yacht harbor in the middle of the construction line, and even under construction conditions where the construction line is interrupted, the crane, particularly the floating crane from the sea, makes it easy to move the steel pipe press-fitting machine 7. Can be done.
If the steel pipe pile is held by using the steel pipe holding device of the present invention and the steel pipe pile is driven, even if there is an obstacle such as a bridge above the construction line at the time of the pile driving, the steel pipe joint is formed. Can be reduced, the construction time can be shortened, and high economic efficiency can be exhibited.

【0021】なお、この実施の形態では、クランプ爪1
0は各フレーム8a、8bの内周壁面に直に装着される
パッド形でよい。これは、鋼管杭9を、クレーンで吊持
して、竪てた状態にした上で、施工ライン3の前方か
ら、後方に向けて移動し、鋼管保持装置8内に導入し、
クランプさせることができるので、鋼管杭9の下端外周
に設けた環部材9Xを、従来のように、鋼管保持装置の
内側を通す必要がなく、クランプ爪10で囲む内径が、
鋼管杭9の外径に、ほぼ一致する寸法で、フレーム8
a、8bによる保持内径を設計し、製造することができ
るからである。
In this embodiment, the clamp claw 1
0 may be a pad type which is directly mounted on the inner peripheral wall of each of the frames 8a and 8b. This is because the steel pipe pile 9 is suspended by a crane, and is moved vertically from the front of the construction line 3 to the rear, and is introduced into the steel pipe holding device 8.
Since it is possible to clamp, the ring member 9X provided on the outer periphery of the lower end of the steel pipe pile 9 does not need to pass through the inside of the steel pipe holding device as in the related art.
The size of the frame 8 is approximately the same as the outer diameter of the steel pipe pile 9.
This is because the holding inner diameter according to a and 8b can be designed and manufactured.

【0022】従って、従来のように、各クランプ爪を油
圧で鋼管杭の半径方向に進退するような構成が不要とな
るので、構造が簡素化でき、制御系も、油圧シリンダ1
2の制御だけで良く、極めて単純になる。
Therefore, unlike the related art, there is no need to provide a structure in which each clamp claw is advanced and retracted in the radial direction of the steel pipe pile by hydraulic pressure, so that the structure can be simplified and the control system can be controlled by the hydraulic cylinder 1.
Only two controls are required, which is extremely simple.

【0023】[0023]

【発明の効果】本発明は、以上詳述したようになり、所
定の施工ラインに沿って鋼管杭を連続的に打設する鋼管
杭の打設に際して、打設すべき鋼管を、その外周からク
ランプする鋼管保持装置において、クランプ爪を内周に
装備した環状フレームは、水平方向に関して、互いに開
閉可能な、固定フレームと、該固定フレームにヒンジさ
れた可動フレームとから構成されており、打設すべき鋼
管は、環状フレームの開放された側から水平移動で上記
環状フレーム内に誘導され、クランプ爪で外周をクラン
プされることを特徴とするので、施工ラインの上に、橋
梁などの障害物があっても、相当程度、長さを持った鋼
管杭を用いて、杭の打設作業が行え、鋼管継ぎの回数を
できるだけ少なくすることができる。
The present invention has been described in detail above. When a steel pipe pile is continuously driven along a predetermined construction line, the steel pipe to be driven is removed from its outer periphery. In the steel pipe holding device to be clamped, an annular frame equipped with a clamp claw on the inner periphery is composed of a fixed frame that can be opened and closed with respect to the horizontal direction, and a movable frame hinged to the fixed frame. The steel pipe to be guided is guided into the annular frame by horizontal movement from the open side of the annular frame, and the outer circumference is clamped by clamp claws, so that an obstacle such as a bridge is placed on the construction line. Even if there is, pile driving work can be performed using a steel pipe pile having a considerable length, and the number of steel pipe joints can be reduced as much as possible.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の鋼管杭の保持装置を用いた打設工法を
説明するための準備工程を示す平面図である。
FIG. 1 is a plan view showing a preparatory step for explaining a casting method using a steel pipe pile holding device of the present invention.

【図2】同じく、鋼矢板用圧入機の平面図である。FIG. 2 is a plan view of the press machine for steel sheet piles.

【図3】同じく、側面図である。FIG. 3 is also a side view.

【図4】同じく、次の準備工程を示す平面図である。FIG. 4 is a plan view showing the next preparation step.

【図5】同じく、側面図である。FIG. 5 is also a side view.

【図6】同じく、上記準備工程完了時の側面図である。FIG. 6 is a side view when the preparation process is completed.

【図7】同じく、上記準備工程完了状態の平面図であ
る。
FIG. 7 is a plan view showing a state in which the preparation step is completed.

【図8】同じく、側面図である。FIG. 8 is also a side view.

【図9】本発明の保持装置の一実施例を示す側面図であ
る。
FIG. 9 is a side view showing an embodiment of the holding device of the present invention.

【図10】同じく、平面図である。FIG. 10 is also a plan view.

【図11】本発明の保持装置を用いた施工法の本工程を
示す平面図である。
FIG. 11 is a plan view showing the main step of the construction method using the holding device of the present invention.

【図12】同じく、側面図である。FIG. 12 is also a side view.

【図13】同じく、その経過を示す側面図である。FIG. 13 is a side view showing the progress.

【図14】同じく、鋼管杭の接続を示す側面図である。FIG. 14 is a side view showing the connection of the steel pipe piles.

【図15】同じく、次の経過を示す平面図である。FIG. 15 is a plan view showing the following process.

【図16】同じく、側面図である。FIG. 16 is also a side view.

【図17】同じく、鋼管杭の最終打ち込み状態を示す側
面図である。
FIG. 17 is a side view showing the final driving state of the steel pipe pile.

【図18】同じく、完了状態の側面図である。FIG. 18 is also a side view of the completed state.

【図19】同じく、鋼管用圧入機の施工ライン方向の移
動状態を示す側面図である。
FIG. 19 is a side view showing the state of movement of the steel pipe press-fitting machine in the construction line direction.

【図20】同じく、次の鋼管杭の打ち込み始めの状態を
示す側面図である。
FIG. 20 is a side view showing a state where the driving of the next steel pipe pile is started.

【図21】同じく、次の経過を示す側面図である。FIG. 21 is a side view showing the next process.

【符号の説明】[Explanation of symbols]

1 鋼矢板用圧入機 2 カウンターウエイト 3 施工ライン 3a 所要位置 4 反力用鋼矢板 5 支持鋼材 6 導枠材 7 鋼管用圧入機 8 環状フレーム 8a 固定フレーム(抱持部材) 8b 可動フレーム(抱持部材) 9、9’ 鋼管杭 9a、9b 杭部材 10 クランプ爪 11 ヒンジピン 12 油圧シリンダ 13 連結子 14 受け部材 15 連結ピン 16 ノズル 17 蓋部材 17a 支持部 18 杭打ち止め高さ 19 補助杭(ヤットコ) DESCRIPTION OF SYMBOLS 1 Press-fitting machine for steel sheet piles 2 Counterweight 3 Construction line 3a Required position 4 Steel sheet piles for reaction force 5 Supporting steel material 6 Guide frame material 7 Press-fitting machine for steel pipes 8 Annular frame 8a Fixed frame (holding member) 8b Movable frame (holding) 9, 9 'Steel pipe pile 9a, 9b Pile member 10 Clamp claw 11 Hinge pin 12 Hydraulic cylinder 13 Connector 14 Receiver member 15 Connection pin 16 Nozzle 17 Cover member 17a Supporting part 18 Pile driving height 19 Auxiliary pile (Yatco)

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 所定の施工ラインに沿って鋼管杭を連続
的に打設する鋼管杭の打設に際して、打設すべき鋼管
を、その外周からクランプする鋼管保持装置において、
クランプ爪を内周に装備した環状フレームは、水平方向
に関して、互いに開閉可能な、固定フレームと、該固定
フレームにヒンジされた可動フレームとから構成されて
おり、打設すべき鋼管は、環状フレームの開放された側
から水平移動で上記環状フレーム内に誘導され、クラン
プ爪で外周をクランプされることを特徴とする、鋼管杭
打設用の鋼管保持装置。
1. A steel pipe holding device for clamping a steel pipe to be driven from an outer periphery thereof when driving a steel pipe pile continuously driving a steel pipe pile along a predetermined construction line,
The annular frame equipped with clamp claws on the inner periphery is composed of a fixed frame which can be opened and closed with respect to the horizontal direction, and a movable frame hinged to the fixed frame. A steel pipe holding device for driving steel pipe piles, wherein the steel pipe holding device is guided in the annular frame by horizontal movement from an open side of the steel pipe and is clamped by a clamp claw.
【請求項2】 上記固定フレームは、施工ライン後方側
の半円弧状の抱持部材で、また、施工ライン前方に対し
て開放されるように、上記固定フレームにヒンジされ
た、施工ライン前方側の半円弧状の抱持部材で構成され
ていることを特徴とする請求項1に記載の鋼管杭打設用
の鋼管保持装置。
2. The fixed frame is a semicircular holding member on the rear side of the construction line, and is hinged to the fixed frame so as to be open to the front of the construction line. The steel pipe holding device for driving a steel pipe pile according to claim 1, wherein the steel pipe holding device is constituted by a semicircular arc-shaped holding member.
JP15957096A 1996-06-20 1996-06-20 Steel pipe holding device for driving steel pipe pile Pending JPH108466A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15957096A JPH108466A (en) 1996-06-20 1996-06-20 Steel pipe holding device for driving steel pipe pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15957096A JPH108466A (en) 1996-06-20 1996-06-20 Steel pipe holding device for driving steel pipe pile

Publications (1)

Publication Number Publication Date
JPH108466A true JPH108466A (en) 1998-01-13

Family

ID=15696614

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15957096A Pending JPH108466A (en) 1996-06-20 1996-06-20 Steel pipe holding device for driving steel pipe pile

Country Status (1)

Country Link
JP (1) JPH108466A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007154484A (en) * 2005-12-02 2007-06-21 Giken Seisakusho Co Ltd Pile press-fitting attachment and pile press-fitting method
CN102478138A (en) * 2010-11-22 2012-05-30 中交上海航道局有限公司 Quick connector for dredge pipes of cutter suction dredger
JP2013104282A (en) * 2011-11-16 2013-05-30 Nippon Steel & Sumitomo Metal Steel wall
JP2015161129A (en) * 2014-02-28 2015-09-07 株式会社技研製作所 Pile-member joint method and junction structure of pile-member
CN110130345A (en) * 2019-05-15 2019-08-16 中地君豪建筑工程有限公司 Static pressure pile driver and tubular pole welding method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007154484A (en) * 2005-12-02 2007-06-21 Giken Seisakusho Co Ltd Pile press-fitting attachment and pile press-fitting method
CN102478138A (en) * 2010-11-22 2012-05-30 中交上海航道局有限公司 Quick connector for dredge pipes of cutter suction dredger
JP2013104282A (en) * 2011-11-16 2013-05-30 Nippon Steel & Sumitomo Metal Steel wall
JP2015161129A (en) * 2014-02-28 2015-09-07 株式会社技研製作所 Pile-member joint method and junction structure of pile-member
CN110130345A (en) * 2019-05-15 2019-08-16 中地君豪建筑工程有限公司 Static pressure pile driver and tubular pole welding method

Similar Documents

Publication Publication Date Title
US3763654A (en) Pile driving and drawing apparatus
US7877933B2 (en) Mounting of offshore structures
JPH108466A (en) Steel pipe holding device for driving steel pipe pile
JP2783528B2 (en) Casting method for steel pipe piles
JP2002088779A (en) Jacket structure and method for setting jacket structure
JP3204616B2 (en) Steel pipe press-fitting method in narrow space area with sky restriction
JP2001049663A (en) Steel pipe holder for driving steel pipe pile
JP3589921B2 (en) Piling device
JP2011241578A (en) Boring machine
JP4955478B2 (en) Pile ground improvement system
JPH10280376A (en) Pile driving method for constructing marine stage and method for constructing the sea stage
JP2003155747A (en) Work machine for pulling out pile
JP2553027B2 (en) Pile driver using circular pit
JP3616898B2 (en) Method for joining underground structures using propulsion device
JPH0643224Y2 (en) Steel pipe pile placing device
JPH0357248B2 (en)
KR102524910B1 (en) Water jet cutting methods for cutting pile that supports top side when dismantling offshore structures in underwater
JPS61250229A (en) Method and apparatus for penetration of steel sheet pile
JPH0238623A (en) Driving of steel pipe pile
JP2001262569A (en) Pile pulling-out method and pile pulling-out work machine
JPH0813539A (en) Underwater walking type dredging method and dredger
JPH10280404A (en) Pile driving method for constructing offshore stage and offshore stage construction method
JPS5968410A (en) Method and apparatus for constructing pier
JPS63189524A (en) Jet pipe fitting device for pile driving
CN116971790A (en) Method for quickly establishing soil pressure of shield originating first ring