JPH10292541A - Precast concrete panel for supporting floor slab and construction method of floor foundation - Google Patents

Precast concrete panel for supporting floor slab and construction method of floor foundation

Info

Publication number
JPH10292541A
JPH10292541A JP10119297A JP10119297A JPH10292541A JP H10292541 A JPH10292541 A JP H10292541A JP 10119297 A JP10119297 A JP 10119297A JP 10119297 A JP10119297 A JP 10119297A JP H10292541 A JPH10292541 A JP H10292541A
Authority
JP
Japan
Prior art keywords
precast concrete
steel
steel girder
floor slab
concrete plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP10119297A
Other languages
Japanese (ja)
Inventor
Takashi Iwasaki
隆 岩崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
Kawasaki Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Steel Corp filed Critical Kawasaki Steel Corp
Priority to JP10119297A priority Critical patent/JPH10292541A/en
Publication of JPH10292541A publication Critical patent/JPH10292541A/en
Withdrawn legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a precast concrete panel useful for achieving the omission of small steel beams and also stiffening members without creating any shortage of strength against the lateral buckling of a large steel beam. SOLUTION: A precast concrete panel 2 is erected between mutually adjacent large beams 1 functioning as the foundation of a floor slab of a building and has both the functions of support and formwork. In this case, its both side portions respectively have a suspending wall 3 covering the side surface of the large steel beam 1, and ribs 4 connecting diagonally the large steel beam 1 to the precast concrete panel 2 are coupled to the suspending walls 3 at certain intervals in the longitudinal direction of the large steel beam 1.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、建築物の基礎構
造材である大梁に鉄骨を用いる、ビルなどにおいて、そ
の鉄骨大梁上で床スラブを支持するプレキャストコンク
リート板および、このプレキャストコンクリート板を用
いて行う床基礎の構築方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a precast concrete plate for supporting a floor slab on a steel girder in a building or the like in which a steel girder is used as a girder which is a basic structural material of a building. Floor construction method.

【0002】[0002]

【従来の技術】従来、鉄骨大梁上に床スラブを構築する
には、床スラブの型枠の設置を簡便にするために、プレ
キャストコンクリート板やデッキ板が用いられている。
すなわち、図1に示すように、鉄骨大梁20の隣接相互間
に鉄骨小梁21を架け渡し、その上に、例えばプレキャス
トコンクリート板22を載置し、これを型枠にして、床ス
ラブ23を打設することによって、床スラブを構築してい
る。さらに、鉄骨大梁20には、大地震などの際に大きな
荷重が加わって塑性化することもあるから、特に横座屈
を防止するために、鉄骨大梁20と鉄骨小梁21との間に、
方杖状に補剛材24を配置して、鉄骨大梁の下フランジの
水平移動を防止している。
2. Description of the Related Art Conventionally, in order to construct a floor slab on a steel girder, a precast concrete plate or a deck plate is used to simplify installation of a floor slab formwork.
That is, as shown in FIG. 1, a steel beam 21 is bridged between adjacent steel beams 20 and a precast concrete plate 22, for example, is placed thereon. The floor slab is constructed by casting. Furthermore, since a large load may be applied to the steel girders 20 in the event of a large earthquake or the like, the steel girders may be plasticized.In particular, in order to prevent lateral buckling, between the steel girders 20 and the steel girders 21,
The stiffeners 24 are arranged in a toe shape to prevent horizontal movement of the lower flange of the steel girder.

【0003】従って、鉄骨大梁とプレキャストコンクリ
ート板との間に、鉄骨小梁、さらには補剛材を必要とす
るため、鉄骨加工や設置などに要する工数が増加するこ
とが問題になっている。また、鉄骨構造では、火災時に
も十分な強度を維持させるために、鋼材の表面にロック
ウール等の耐火材を被覆することが必須であり、この鋼
材への耐火被覆施工の工数増加も問題である。
[0003] Therefore, since a steel beam and a stiffener are required between the steel beam and the precast concrete plate, the number of steps required for steel frame processing and installation is increased. In addition, in steel structures, it is essential to coat the surface of steel with refractory materials such as rock wool in order to maintain sufficient strength in the event of a fire. is there.

【0004】これに対して、実開平2−68008号公
報には、鉄骨小梁を省略した構造が提案されているが、
横座屈を防止するための斜材は依然として必要である
上、横座屈に対する強度を十分に確保できない、おそれ
がある。すなわち、斜材とプレキャストコンクリート板
との間はボルトで締結されるが、スラブ内に精度よくイ
ンサート金物を埋設することは困難であるため、斜材と
鉄骨梁との間のボルト孔は、施工性を考えて長穴として
いる。この過大なボルト孔はせん断耐力を低下する原因
となり、また、このような考慮をしたとしても、床スラ
ブと鉄骨梁間をボルトで施工できる精度で建方すること
は困難が予想される。
On the other hand, Japanese Utility Model Laid-Open Publication No. 2-68008 discloses a structure in which steel beams are omitted.
Diagonal members for preventing lateral buckling are still required, and there is a possibility that sufficient strength against lateral buckling cannot be ensured. That is, the bolts are fastened between the diagonal members and the precast concrete plate, but it is difficult to bury the insert hardware accurately in the slab. Considering the nature, it is a long hole. This excessive bolt hole causes a decrease in the shear strength, and even if such considerations are taken, it is expected that it will be difficult to construct the floor slab and the steel beam with the accuracy that can be constructed with bolts.

【0005】[0005]

【発明が解決しようとする課題】そこで、この発明は、
鉄骨小梁さらには補剛材の省略を、鉄骨大梁の横座屈に
対する強度不足をまねくことなく達成するのに役立て
る、プレキャストコンクリート板を提供するとともに、
このプレキャストコンクリート板を用いた、床基礎の有
利な構築方法について提案することを目的とする。
SUMMARY OF THE INVENTION Therefore, the present invention
Along with providing a precast concrete plate that helps to achieve omission of steel beams and stiffeners without causing insufficient strength against lateral buckling of steel beams,
An object of the present invention is to propose an advantageous construction method of a floor foundation using the precast concrete plate.

【0006】[0006]

【課題を解決するための手段】この発明は、建築物の床
スラブの基礎となる鉄骨大梁の隣接相互間に架設され、
床スラブの支持および型枠の機能を兼備する、プレキャ
ストコンクリート板であって、その両側部は、鉄骨大梁
の側面を覆う懸垂壁をそれぞれ有し、該懸垂壁に、鉄骨
大梁およびプレキャストコンクリート板の間を斜めに結
合するリブを、鉄骨大梁の長手方向に間隔を置いて設け
たことを特徴とする床スラブ支持用プレキャストコンク
リート板である。
SUMMARY OF THE INVENTION The present invention is provided between adjacent steel girders which form the basis of a building floor slab,
A precast concrete plate having both the function of supporting a floor slab and the function of a formwork, and both sides of the precast concrete plate have hanging walls covering the side surfaces of the steel girders. A precast concrete plate for supporting a floor slab, characterized in that ribs which are connected diagonally are provided at intervals in the longitudinal direction of the steel beam.

【0007】ここで、リブは、プレキャストコンクリー
ト板を鉄骨大梁の隣接相互間に架設した際、鉄骨大梁の
側面との間で、モルタルが充填される空間を区画する、
チャンネル形状であることが、有利に適合する。
Here, the rib defines a space filled with mortar between the precast concrete plate and the side surface of the steel beam when the precast concrete plate is laid between adjacent steel beams.
The channel shape advantageously fits.

【0008】また、この発明は、建築物の鉄骨大梁上に
床スラブを施工するに当たり、該鉄骨大梁の隣接相互間
に、上記プレキャストコンクリート板を架設して、鉄骨
大梁の側面を懸垂壁で覆うとともに、鉄骨大梁およびプ
レキャストコンクリート板の間を斜めに結合するリブと
鉄骨大梁とで区画される空間に、モルタルを充填するこ
とを特徴とする床スラブの構築方法である。とりわけ、
リブと鉄骨大梁とで区画される空間に、鉄骨大梁の下端
から少なくとも鉄骨大梁成の1/6以上に到る高さまで
モルタルを充填することが、好ましい。
According to the present invention, when a floor slab is constructed on a steel girder of a building, the precast concrete plate is erected between adjacent steel girder beams, and a side wall of the steel girder is covered with a suspension wall. A method of constructing a floor slab characterized by filling a space defined by a rib and a steel girder obliquely connecting between a steel girder and a precast concrete plate with mortar. Above all,
It is preferable that the space defined by the rib and the steel girder be filled with mortar from the lower end of the steel girder to at least a height of 1/6 or more of the steel girder.

【0009】[0009]

【発明の実施の形態】さて、図2に、I型鋼による鉄骨
大梁1の隣接相互間に架設した、プレキャストコンクリ
ート板(以下、PC板という)2を示す。PC板2は、
その両側部に、鉄骨大梁1の隣接相互間に架設した際、
図3に示すように、鉄骨大梁1の側面に沿って、これを
覆う懸垂壁3を、それぞれ有する。ここに、PC板2の
架設後は鉄骨大梁1の側面が露出されないため、この側
面に対する耐火被覆の施工は不要となる。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 2 shows a precast concrete plate (hereinafter, referred to as a PC plate) 2 installed between adjacent steel girders 1 made of I-beam. PC board 2
When erected on both sides between adjacent steel girders 1,
As shown in FIG. 3, a suspension wall 3 is provided along the side surface of the steel girder 1 to cover the same. Here, after the PC board 2 is erected, the side surface of the steel beam 1 is not exposed, so that it is not necessary to apply the fireproof coating to this side surface.

【0010】さらに、懸垂壁3は、図4に示すように、
鉄骨大梁1およびプレキャストコンクリート板2の下面
の間を斜めに結合するリブ4を、鉄骨大梁1の長手方向
に間隔を置いて複数有する。
[0010] Further, as shown in FIG.
A plurality of ribs 4 are provided at a distance in the longitudinal direction of the steel girder 1 so as to obliquely connect the lower surfaces of the steel girder 1 and the precast concrete plate 2.

【0011】このリブ4は、図4および図5に示すよう
に、PC板2を鉄骨大梁1の隣接相互間に架設した際、
鉄骨大梁1の側面側に開口するチャンネル形状になるた
め、鉄骨大梁1の側面とリブ4との間に三角柱状の空間
5が形成される。一方、リブ4の上面には、モルタルの
導入穴6を設け、ここから空間5内にモルタル7を充填
することによって、リブ4を鉄骨大梁1に強固に結合し
て、リブ4の補剛材としての機能が強化される結果、鉄
骨大梁1の横座屈を有効に抑制する構造が得られる。
As shown in FIGS. 4 and 5, the ribs 4 are provided when the PC board 2 is laid between adjacent steel girders 1.
Since the channel shape is open to the side surface of the steel beam 1, a triangular prism-shaped space 5 is formed between the side surface of the steel beam 1 and the rib 4. On the other hand, a mortar introduction hole 6 is provided on the upper surface of the rib 4, and the mortar 7 is filled into the space 5 from the mortar introduction hole 6, whereby the rib 4 is firmly connected to the steel beam 1 and a stiffener for the rib 4 is provided. As a result, a structure that effectively suppresses lateral buckling of the steel girder 1 is obtained.

【0012】次に、上記PC板2を用いた床スラブの構
築方法について、図6を参照して説明する。まず、同図
(a) に示すように、所定の間隔で設置した鉄骨大梁1の
隣接相互間に、同図(b) に示すように、PC板2を架設
する。その後、同図(c) に示すように、PC板2の導入
穴6からモルタル7を鉄骨大梁1とリブ4との間の空間
5に充填する。
Next, a method of constructing a floor slab using the PC board 2 will be described with reference to FIG. First, the figure
As shown in (a), a PC board 2 is erected between adjacent steel girders 1 installed at predetermined intervals, as shown in FIG. Thereafter, as shown in FIG. 1C, the mortar 7 is filled into the space 5 between the steel girder 1 and the rib 4 through the introduction hole 6 of the PC board 2.

【0013】ここで、モルタル7は、鉄骨大梁1の下端
から少なくとも大梁成の1/6以上かつスタッドボルト
が十分耐力を発揮できる、かぶりがとれる高さまで充填
することが好ましい。なぜなら、短い断面H形状の梁の
横座屈は、圧縮側となる1/6断面の面外への反りによ
って決まるからである。なお、モルタルを充填する鉄骨
大梁1の下フランジに、図4に示すように、スタッドボ
ルト8を設置しておくことが好ましい。
Here, it is preferable that the mortar 7 is filled from the lower end of the steel girder 1 to at least 1/6 or more of the girder structure and to a height at which the stud bolt can sufficiently exert the strength and the fog can be removed. This is because the lateral buckling of a beam having a short H-shaped section is determined by out-of-plane warpage of the 1/6 section on the compression side. In addition, it is preferable to install a stud bolt 8 on the lower flange of the steel girder 1 to be filled with mortar as shown in FIG.

【0014】そして、鉄骨大梁1とリブ4との間にモル
タル7を充填したのち、同図(d) に示すように、PC板
2を型枠として、その上にコンクリートを打設すれば、
床スラブ9の構築が完了する。ここで、図3および4に
示すように、鉄骨大梁1の上フランジにスタッドボルト
10を設置してコンクリートの打設を行うことが好まし
い。
After filling the mortar 7 between the steel girder 1 and the rib 4, as shown in FIG. 3D, the PC board 2 is used as a mold and concrete is cast on it.
Construction of the floor slab 9 is completed. Here, as shown in FIGS. 3 and 4, a stud bolt is
It is preferable to install concrete at 10 and to cast concrete.

【0015】最後に、鋼材の露出面に対して耐火被覆を
行う必要があるが、以上の構成において唯一の鋼材であ
る鉄骨大梁1は、その側面はPC板2の懸垂壁3で覆わ
れ、かつ上面は床スラブ9で覆われているため、残る下
面のみに耐火被覆11を施せばよい。
Lastly, it is necessary to provide a fire-resistant coating on the exposed surface of the steel material. The steel girder 1 which is the only steel material in the above configuration is covered with the suspension wall 3 of the PC plate 2 on the side surface. Further, since the upper surface is covered with the floor slab 9, only the remaining lower surface needs to be provided with the fireproof coating 11.

【0016】[0016]

【発明の効果】この発明のPC板を床基礎の構築に用い
ることによって、従来不可欠であった、鉄骨小梁さらに
は補剛材の省略が実現され、同時に残る鉄骨大梁の側面
はPC板の懸垂壁で覆われるため、鉄骨加工や設置など
に要する工数、さらには耐火被覆施工の工数を格段に減
少することができる。しかも、鉄骨小梁さらには補剛材
の省略によっても、大梁の横座屈に対する強度は必要十
分のレベルに維持されるのである。
By using the PC board of the present invention for the construction of a floor foundation, the omission of steel beams and stiffeners, which has been indispensable in the past, is realized, and at the same time, the side surfaces of the steel beam are left. Since it is covered with the suspension wall, the man-hour required for steel frame processing and installation, and furthermore, the man-hour for fireproof coating can be significantly reduced. Moreover, even if the steel beam and the stiffener are omitted, the strength of the large beam against lateral buckling is maintained at a necessary and sufficient level.

【図面の簡単な説明】[Brief description of the drawings]

【図1】従来の床スラブの基礎構造を示す図である。FIG. 1 is a view showing a basic structure of a conventional floor slab.

【図2】鉄骨大梁間にプレキャストコンクリート板を架
設した状態を示す図である。
FIG. 2 is a view showing a state where a precast concrete plate is erected between steel girders.

【図3】図2のA−A線の沿う断面図である。FIG. 3 is a sectional view taken along line AA of FIG. 2;

【図4】図2のB−B線の沿う断面図である。FIG. 4 is a sectional view taken along line BB of FIG. 2;

【図5】図2のC−C線の沿う断面図である。FIG. 5 is a sectional view taken along line CC of FIG. 2;

【図6】床スラブを構築する手順を示す図である。FIG. 6 is a diagram showing a procedure for constructing a floor slab.

【符号の説明】[Explanation of symbols]

1 鉄骨大梁 2 プレキャストコンクリート板 3 懸垂壁 4 リブ 5 空間 6 導入穴 7 モルタル 8 スタッドボルト 9 床スラブ 10 スタッドボルト 11 耐火被覆 DESCRIPTION OF SYMBOLS 1 Steel girder 2 Precast concrete board 3 Suspended wall 4 Rib 5 Space 6 Introducing hole 7 Mortar 8 Stud bolt 9 Floor slab 10 Stud bolt 11 Fireproof coating

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 建築物の床スラブの基礎となる鉄骨大梁
の隣接相互間に架設され、床スラブの支持および型枠の
機能を兼備する、プレキャストコンクリート板であっ
て、その両側部に、鉄骨大梁の側面を覆う懸垂壁をそれ
ぞれ有し、該懸垂壁に、鉄骨大梁およびプレキャストコ
ンクリート板の間を斜めに結合するリブを、鉄骨大梁の
長手方向に間隔を置いて設けたことを特徴とする床スラ
ブ支持用プレキャストコンクリート板。
1. A precast concrete plate which is installed between adjacent steel girders as a foundation of a floor slab of a building and has a function of supporting a floor slab and a formwork. A floor slab having a suspension wall that covers a side surface of a girder, and a rib that diagonally connects between the steel girder and the precast concrete plate is provided on the suspension wall at intervals in a longitudinal direction of the steel girder. Precast concrete board for support.
【請求項2】 リブは、プレキャストコンクリート板を
鉄骨大梁の隣接相互間に架設した際、鉄骨大梁の側面と
の間で、モルタルが充填される空間を区画する、チャン
ネル形状である請求項1に記載の床スラブ支持用プレキ
ャストコンクリート板。
2. The rib according to claim 1, wherein when the precast concrete plate is laid between adjacent steel girders, the rib defines a space filled with mortar between the ribs and the side of the steel girders. The precast concrete plate for supporting the floor slab according to the above.
【請求項3】 建築物の鉄骨大梁上に床スラブを施工す
るに当たり、該鉄骨大梁の隣接相互間に、請求項1に記
載のプレキャストコンクリート板を架設して、鉄骨大梁
の側面を懸垂壁で覆うとともに、鉄骨大梁およびプレキ
ャストコンクリート板の間を斜めに結合するリブと鉄骨
大梁とで区画される空間にモルタルを充填することを特
徴とする床基礎の構築方法。
3. When a floor slab is constructed on a steel girder of a building, the precast concrete plate according to claim 1 is erected between adjacent steel girder beams and a side wall of the steel girder is suspended by a suspension wall. A method of constructing a floor foundation, characterized in that a mortar is filled in a space defined by a rib and a steel girder that obliquely connects between a steel girder and a precast concrete plate while covering the steel girder.
【請求項4】 リブと鉄骨大梁とで区画される空間に、
鉄骨大梁の下端から少なくとも鉄骨大梁成の1/6以上
に到る高さまでモルタルを充填する請求項3に記載の床
基礎の構築方法。
4. A space defined by a rib and a steel girder,
The method for constructing a floor foundation according to claim 3, wherein the mortar is filled from a lower end of the steel girder to at least a height of 1/6 or more of the steel girder.
JP10119297A 1997-04-18 1997-04-18 Precast concrete panel for supporting floor slab and construction method of floor foundation Withdrawn JPH10292541A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10119297A JPH10292541A (en) 1997-04-18 1997-04-18 Precast concrete panel for supporting floor slab and construction method of floor foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10119297A JPH10292541A (en) 1997-04-18 1997-04-18 Precast concrete panel for supporting floor slab and construction method of floor foundation

Publications (1)

Publication Number Publication Date
JPH10292541A true JPH10292541A (en) 1998-11-04

Family

ID=14294097

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10119297A Withdrawn JPH10292541A (en) 1997-04-18 1997-04-18 Precast concrete panel for supporting floor slab and construction method of floor foundation

Country Status (1)

Country Link
JP (1) JPH10292541A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100411598B1 (en) * 2000-04-17 2003-12-18 주식회사 국민씨아이 Construction Method for Slab and Lining of Structures with Composite Space Panel
CN105714968A (en) * 2016-02-24 2016-06-29 郭猛 Concrete floor optimized design method capable of relieving earthquake damages on strong beams and weak columns
CN114790788A (en) * 2022-05-07 2022-07-26 中建八局总承包建设有限公司 Inclined-hanging clean water plate curtain wall and construction method thereof
CN117306684A (en) * 2023-11-29 2023-12-29 中国船舶集团国际工程有限公司 Box board assembled steel structure-concrete composite floor support plate combined building structure system

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100411598B1 (en) * 2000-04-17 2003-12-18 주식회사 국민씨아이 Construction Method for Slab and Lining of Structures with Composite Space Panel
CN105714968A (en) * 2016-02-24 2016-06-29 郭猛 Concrete floor optimized design method capable of relieving earthquake damages on strong beams and weak columns
CN105714968B (en) * 2016-02-24 2019-02-19 郭猛 Mitigate the concrete floor optimum design method of the weak column earthquake of brutal
CN114790788A (en) * 2022-05-07 2022-07-26 中建八局总承包建设有限公司 Inclined-hanging clean water plate curtain wall and construction method thereof
CN114790788B (en) * 2022-05-07 2023-07-14 中建八局总承包建设有限公司 Obliquely-hung clean water plate curtain wall and construction method thereof
CN117306684A (en) * 2023-11-29 2023-12-29 中国船舶集团国际工程有限公司 Box board assembled steel structure-concrete composite floor support plate combined building structure system
CN117306684B (en) * 2023-11-29 2024-02-27 中国船舶集团国际工程有限公司 Box board assembled steel structure-concrete composite floor support plate combined building structure system

Similar Documents

Publication Publication Date Title
US4918897A (en) Construction system for detention structures and multiple story buildings
US5048257A (en) Construction system for detention structures and multiple story buildings
US4219978A (en) Pre-cast reinforced concrete building panel wall structure
JP2002339451A (en) Precast concrete slab, its manufacturing method, precast concrete slab for balcony, and outer thermal insulating structure
SK161099A3 (en) Building framework
JPH10292541A (en) Precast concrete panel for supporting floor slab and construction method of floor foundation
JP3466961B2 (en) Reinforcement method for existing load-bearing walls with openings
JPH11107293A (en) Foundation structure of building, foundation construction method, and block for foundation
JPH09264050A (en) Building structure
JPH084195A (en) Panel for building
JPH0444550A (en) Semi-precast rc building
JP2734946B2 (en) Construction method of concrete wall structure
JPH0470444A (en) Partition wall of concrete building and execution method thereof
JP3207276B2 (en) How to build a unit building
JP3209822B2 (en) Behind the hut wall structure
JPH057350Y2 (en)
JPS59138644A (en) Constructon of synthetic floor consisting of pc beam or ps beam and deck plate floor slab concrete
JPH0738507Y2 (en) Hollow slab
KR20210157674A (en) Seismic retrofit structure for building and seismic retrofit method using the same
JPH0716807Y2 (en) Structure of steel girder end
JPH05248021A (en) Light weighted floor construction
JPH0262672B2 (en)
JPH06294174A (en) Attic space separation wall construction
JPH01102156A (en) Slab structure
JPS62170640A (en) Outer wall structure of building

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20040706