JPH10252202A - Dome construction method - Google Patents

Dome construction method

Info

Publication number
JPH10252202A
JPH10252202A JP7271397A JP7271397A JPH10252202A JP H10252202 A JPH10252202 A JP H10252202A JP 7271397 A JP7271397 A JP 7271397A JP 7271397 A JP7271397 A JP 7271397A JP H10252202 A JPH10252202 A JP H10252202A
Authority
JP
Japan
Prior art keywords
dome
bag member
bag
reinforced concrete
ring member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP7271397A
Other languages
Japanese (ja)
Other versions
JP3087261B2 (en
Inventor
Yoshinori Shigeoka
良則 重岡
Toshima Minato
寿馬 湊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
H P DOHME JAPAN KK
Original Assignee
H P DOHME JAPAN KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by H P DOHME JAPAN KK filed Critical H P DOHME JAPAN KK
Priority to JP09072713A priority Critical patent/JP3087261B2/en
Publication of JPH10252202A publication Critical patent/JPH10252202A/en
Application granted granted Critical
Publication of JP3087261B2 publication Critical patent/JP3087261B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PROBLEM TO BE SOLVED: To form a reinforced concrete wall by means of a simple means, without necessitating construction of a form made of wood or assembling/ disassembling of a large-scaled scaffold. SOLUTION: A supporting member 4 is erected between a ring member 2, which is supported horizontally by a plurality of columns 1, and an annular foundation 3 having a large diameter which is arranged coaxially with the ring member 2. A bag member 5 supported by the supporting member 4 is expanded in order to cast a reinforced concrete wall 6 on the upper surface of the bag member 5. With regard to the internal space of the ring member 2 as well, the bag member 5a is expanded in order to cast a reinforced concrete wall 7 on the upper surface.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、ドームの建設方法
に関する。
[0001] The present invention relates to a method for constructing a dome.

【0002】[0002]

【従来の技術】従来、鉄筋コンクリート製のドームを建
設する場合、ドーム壁としての鉄筋コンクリート壁の厚
さに応じ予め木製等の型枠を建てたり、同型枠の内部に
鉄筋を配置したりしてから、同鉄筋を埋設させるように
型枠内に生コンクリートを充填し固化させることが行な
われている。
2. Description of the Related Art Conventionally, when a dome made of reinforced concrete is constructed, a formwork such as a wooden form is previously built according to the thickness of the reinforced concrete wall as a dome wall, or a reinforcing bar is arranged inside the formwork. In order to bury the reinforcing bars, a form is filled with solid concrete and solidified.

【0003】[0003]

【発明が解決しようとする課題】ところで、前述のよう
な従来のドーム建設方法では、木製型枠等を建てるため
に作業用の足場を組む必要があり、建設すべきドームが
大きくなるにつれ、上記の型枠や足場も著しく大掛かり
になって、これらの組立ておよび解体のために大幅な建
設コストの増加を招くという問題点がある。本発明は、
このような問題点の解消をはかろうとするもので、木製
等の型枠の枠組みや大掛かりな足場の組立て解体を必要
とすることなく簡便な手段で鉄筋コンクリート壁を形成
できるようにしたドーム建設方法を提供することを課題
とする。
By the way, in the conventional dome construction method as described above, it is necessary to assemble a work scaffold to build a wooden formwork and the like. Also, there is a problem that the formwork and the scaffold are significantly large, and assembling and disassembling them significantly increase construction costs. The present invention
A dome construction method which aims to solve such a problem and which can form a reinforced concrete wall by a simple means without the need for assembling and disassembling a frame of a wooden formwork or a large-scale scaffold. The task is to provide

【0004】[0004]

【課題を解決するための手段】前述の課題を解決するた
め、本発明のドーム建設方法は、地盤上に立つ複数の柱
で水平に支持されるリング部材と、同リング部材よりも
大径で同リング部材と同軸的に地盤上に構築される環状
基礎とを設けてから、上記のリング部材と環状基礎との
間に支持部材を架設して同支持部材により袋部材を支持
し、ついで同袋部材を膨張させた後、同袋部材の上面に
沿い鉄筋網を配置して、同鉄筋網を埋設させるように生
コンクリートを吹き付けることにより、上記袋部材の上
面に沿い鉄筋コンクリート壁を形成し、同鉄筋コンクリ
ート壁の固化後に上記袋部材を収縮させ、同袋部材と上
記支持部材とを上記のリング部材および環状基礎から取
り外すことを特徴としている。
In order to solve the above-mentioned problems, a dome construction method according to the present invention comprises a ring member horizontally supported by a plurality of columns standing on the ground, and a ring member having a larger diameter than the ring member. After providing an annular foundation constructed on the ground coaxially with the ring member, a support member is erected between the ring member and the annular foundation, and the bag member is supported by the support member. After inflating the bag member, arranging a reinforced mesh along the upper surface of the bag member and spraying ready-mixed concrete so as to bury the reinforced network, forming a reinforced concrete wall along the upper surface of the bag member, After the reinforced concrete wall is solidified, the bag member is contracted, and the bag member and the support member are detached from the ring member and the annular foundation.

【0005】上述の本発明のドーム建設方法では、リン
グ部材と環状基礎との間に架け渡された支持部材に支持
される袋部材の膨張により、同袋部材の上面にドームの
少なくとも一部の型が形成され、同袋部材の上面に沿い
配置された鉄筋網を埋設させるように生コンクリートを
吹き付けて、その固化により、ドームを形成する鉄筋コ
ンクリート壁が、足場などを要することなく簡便に形成
されるようになる。
In the above-described dome construction method of the present invention, at least a part of the dome is formed on the upper surface of the bag member by the expansion of the bag member supported by the support member bridged between the ring member and the annular base. A mold is formed, and fresh concrete is sprayed so as to bury the reinforcing steel network arranged along the upper surface of the bag member, and by solidification, the reinforced concrete wall forming the dome is easily formed without requiring a scaffold or the like. Become so.

【0006】その際、上記リング部材に関して対称とな
るように上記鉄筋コンクリート壁を形成しながら順次工
事を進めるようにすると、強度的にバランスがとれて安
全に工事を行なうことができる。
At this time, if the construction is proceeded sequentially while forming the reinforced concrete wall so as to be symmetrical with respect to the ring member, the construction can be performed safely with a balance in strength.

【0007】また、多数の同形同大のドームを建設する
場合は、上記の支持部材および袋部材の反復利用が可能
になるので、上記のリング部材と環状基礎との間を36
0度にわたり全面的に覆うように上記支持部材に支持さ
れる袋部材を設けて、膨張した同袋部材の上面に、全ド
ーム壁を形成する鉄筋コンクリート壁を一気に打設し
て、工期を大幅に短縮させることもできる。
In the case of constructing a large number of domes of the same shape and the same size, the above-mentioned support member and bag member can be used repeatedly, so that a gap between the above-mentioned ring member and the annular base is 36.
A bag member supported by the above-mentioned support member is provided so as to cover the entire surface over 0 degrees, and a reinforced concrete wall forming an entire dome wall is cast on the upper surface of the expanded bag member at a stretch, greatly shortening the construction period. It can also be shortened.

【0008】さらに、本発明のドーム建設方法は、初め
に上記の支持部材および袋部材により上記のリング部材
と環状基礎との間を部分的に覆い、同袋部材上面の鉄筋
コンクリート壁の固化後に同袋部材を収縮させてから、
同袋部材を上記支持部材と共に上記のリング部材および
環状基礎に沿って旋回させ、ついで再び上記袋部材を膨
張させた後、同袋部材の上面に沿い鉄筋コンクリート壁
を形成し、以下同様の手順で上記のリング部材と環状基
礎との間に所要の鉄筋コンクリート壁を形成してから、
上記の袋部材および支持部材を上記のリング部材および
環状基礎から取り外すことを特徴としている。
Further, according to the dome construction method of the present invention, first, the support member and the bag member partially cover the space between the ring member and the annular foundation, and after the reinforced concrete wall on the upper surface of the bag member is solidified, the same. After shrinking the bag member,
The bag member is turned along with the support member along the ring member and the annular foundation, and then the bag member is expanded again.After that, a reinforced concrete wall is formed along the upper surface of the bag member. After forming the required reinforced concrete wall between the ring member and the annular foundation,
The bag member and the support member are detached from the ring member and the annular foundation.

【0009】上述のドーム建設方法は、単一のドームを
建設するような場合に有利であり、少数の支持部材およ
び袋部材を上記のリング部材および環状基礎のまわりに
旋回させるようにして反復使用できるので、ドームの建
設コストを低減させることができる。
The above-described method of constructing a dome is advantageous when a single dome is constructed, and is used repeatedly by rotating a small number of support members and a bag member around the ring member and the annular foundation. Therefore, the construction cost of the dome can be reduced.

【0010】また、本発明のドーム建設方法は、上記リ
ング部材の内部空間を覆う中央袋部材を設けて膨張さ
せ、同中央袋部材の上面にも鉄筋網を配置して同鉄筋網
を埋設させるように生コンクリートを吹き付けることに
より、上記中央袋部材の上面に沿い頂部鉄筋コンクリー
ト壁を形成し、同頂部鉄筋コンクリート壁の固化後に、
上記中央袋部材を収縮させて取り外すことを特徴として
いる。
[0010] In the dome construction method of the present invention, a central bag member that covers the inner space of the ring member is provided and inflated, and a reinforcing mesh is disposed on the upper surface of the central bag member so that the reinforcing mesh is buried. By spraying ready-mixed concrete, a top reinforced concrete wall is formed along the upper surface of the central bag member, and after the top reinforced concrete wall is solidified,
The center bag member is contracted and removed.

【0011】上記リング部材の内部の開口については、
同リング部材を小径にすることにより、傘形の屋根など
で容易に覆うことができるが、上述の本発明のドーム建
設方法のように、上記リング部材の内部空間を覆う中央
袋部材を設けて、膨張させた同中央袋部材の上面に頂部
鉄筋コンクリート壁を打設する工法では、上記リング部
材が大径の場合でも、同リング部材の内部開口を閉鎖す
る工事が、簡便かつ安価に行なわれるようになる。
Regarding the opening inside the ring member,
By making the ring member small in diameter, it can be easily covered with an umbrella-shaped roof or the like, but as in the above-described dome construction method of the present invention, a central bag member that covers the internal space of the ring member is provided. In the method of placing a top reinforced concrete wall on the upper surface of the inflated central bag member, even if the ring member has a large diameter, the work of closing the internal opening of the ring member can be performed simply and inexpensively. become.

【0012】[0012]

【発明の実施の形態】以下、図面により本発明の一実施
形態としてのドーム建設方法について説明すると、図1
は本発明の方法により建設中のドームの工事状態を示す
斜視図、図2は図1のドームの完成状態を示す斜視図、
図3は本発明の方法により工事中のドームの縦断面図、
図4は図3のドームの要部を示す平面図、図5は図4の
A−A断面図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A dome construction method according to one embodiment of the present invention will be described below with reference to the drawings.
1 is a perspective view showing a construction state of a dome under construction according to the method of the present invention, FIG. 2 is a perspective view showing a completed state of the dome of FIG. 1,
FIG. 3 is a longitudinal sectional view of a dome under construction according to the method of the present invention;
FIG. 4 is a plan view showing a main part of the dome of FIG. 3, and FIG. 5 is a sectional view taken along line AA of FIG.

【0013】本実施形態のドーム建設方法では、まず地
盤G上に複数の柱1でリング部材2が水平に支持され
る。また、リング部材2よりも大径の環状基盤3が、リ
ング部材2と同軸的に地盤G上の構築される。
In the dome construction method according to the present embodiment, first, the ring member 2 is horizontally supported by the plurality of columns 1 on the ground G. Further, an annular base 3 having a larger diameter than the ring member 2 is constructed on the ground G coaxially with the ring member 2.

【0014】ついで、リング部材2と環状基盤3との間
に、左右および前後にそれぞれ対をなす4個の支持部材
4を45度の相互間隔で架設し、各支持部材4自体の大
きさについても45度の中心角を有するように設定す
る。そして、各支持部材4の全面にわたって、袋部材5
を同支持部材4で支持し、図示しないエアコンプレッサ
ーを用いて各袋部材5を膨張させる。
Next, four support members 4 which form a pair in the left, right, front and rear directions are provided between the ring member 2 and the annular base 3 at an interval of 45 degrees, and the size of each support member 4 itself is determined. Are also set to have a central angle of 45 degrees. Then, over the entire surface of each support member 4, the bag member 5
Are supported by the same support member 4, and each bag member 5 is inflated using an air compressor (not shown).

【0015】このようにして、各袋部材5が上方へ丸味
を帯びた膨張状態になってから、同袋部材5の上面に鉄
筋網6aを配置して、同鉄筋網6aを埋設させるように
生コンクリートを吹き付けることにより、各袋部材5の
上面に沿いドーム壁としての鉄筋コンクリート壁6を形
成する。
In this way, after each bag member 5 is in an inflated state rounded upward, the reinforcing bar net 6a is arranged on the upper surface of the bag member 5, and the reinforcing bar net 6a is embedded. By spraying fresh concrete, a reinforced concrete wall 6 is formed along the upper surface of each bag member 5 as a dome wall.

【0016】そして、鉄筋コンクリート壁6の固化後に
各袋部材5を収縮させてから、支持部材4と共にリング
部材2および環状基盤3に沿って45度にわたり旋回さ
せるようにする。
After the stiffening of the reinforced concrete wall 6, each bag member 5 is contracted and then swiveled 45 degrees along the ring member 2 and the annular base 3 together with the support member 4.

【0017】次いで、再び各袋部材5を膨張させた後、
同袋部材の上面に沿い、鉄筋網6aの配材および生コン
クリートの吹き付けにより鉄筋コンクリート壁6を形成
して、先に固化済みの鉄筋コンクリート壁6と接合させ
るようにする。
Next, after each bag member 5 is inflated again,
Along the upper surface of the bag member, a reinforced concrete wall 6 is formed by distributing the reinforced mesh 6a and spraying ready-mixed concrete, and is joined to the reinforced concrete wall 6 which has been solidified first.

【0018】このようにして、360度にわたり鉄筋コ
ンクリート壁6が形成される。またリング部材2の内部
空間についても、所要の時点で同内部空間を覆う中央袋
部材5aを設けて膨張させ、同中央袋部材5aの上面に
鉄筋網7aを配置して、同鉄筋網7aを埋設させるよう
に生コンクリートを吹き付けることにおり、頂部鉄筋コ
ンクリート壁7を形成する。そして、この頂部鉄筋コン
クリート壁7の固化後に、中央袋部材5aを収縮させて
取り外す操作が行なわれる。
Thus, the reinforced concrete wall 6 is formed over 360 degrees. The inner space of the ring member 2 is also expanded at the required time by providing a central bag member 5a that covers the internal space, and a reinforcing bar mesh 7a is arranged on the upper surface of the central bag member 5a, and the reinforcing bar network 7a is removed. The fresh concrete is sprayed so as to be buried, and the top reinforced concrete wall 7 is formed. Then, after the top reinforced concrete wall 7 is solidified, the central bag member 5a is contracted and removed.

【0019】上述の各袋部材5,5aを形成するシート
としては繊維強化プラスチック製の2〜3mm厚程度のも
のが用いられる。
As the sheet forming each of the above bag members 5, 5a, a sheet made of fiber reinforced plastic and having a thickness of about 2 to 3 mm is used.

【0020】また、生コンクリートの吹き付け作業に
は、図示しない高所作業車に搭載されるウェットコンク
リート噴射ノズルが用いられ、同ノズルには圧縮空気管
および生コンクリート送入管が接続される。そして、こ
の生コンクリート吹き付け作業は、環状基礎3に接続す
る低層部分から順次高層部分に向けて行なわれるが、所
要の壁厚を得るために、生コンクリートの吹き付け操作
は、2,3回に分けて行なわれる。
A wet concrete injection nozzle mounted on an aerial work vehicle (not shown) is used for spraying the ready-mixed concrete, and a compressed air pipe and a ready-mixed concrete feed pipe are connected to the nozzle. The operation of spraying the ready-mixed concrete is performed sequentially from the low-rise portion connected to the annular foundation 3 to the high-rise portion. In order to obtain a required wall thickness, the spraying operation of the ready-mixed concrete is divided into two or three times. It is done.

【0021】さらに、鉄筋コンクリート壁6,7の固化
後に、鉄筋材を引張し、同鉄筋材の端部をコンクリート
材に係止して、同コンクリート材に圧縮応力をかけ、プ
レストレストコンクリート壁とするため、コンクリート
材との相対的な動きが許容されるように、所要の鉄筋材
の外周には予め布または軟質管が施されたり、潤滑材の
コーティングが施されたりする操作が行なわれる。
Further, after the reinforced concrete walls 6 and 7 are solidified, the reinforced material is pulled, the ends of the reinforced concrete material are locked to the concrete material, and a compressive stress is applied to the concrete material to form a prestressed concrete wall. In order to allow relative movement with the concrete material, an operation is performed in which a cloth or a soft tube is previously applied to the outer periphery of the required reinforcing material, or a lubricant coating is applied.

【0022】なお、工事の終了後には、支持部材4や袋
部材5,5aが撤去されるほか、柱1も撤去されて、ド
ームが完成する。
After the construction is completed, the support member 4, the bag members 5, 5a are removed, and the pillar 1 is also removed, thereby completing the dome.

【0023】上述の本実施形態のドーム建設方法では、
リング部材2と環状基礎3との間に架け渡された支持部
材4に支持される袋部材5が膨張すると、同袋部材5の
上面にドームの少なくとも一部の型が形成され、同袋部
材5の上面に沿い配材された鉄筋網6aを埋設させるよ
うに生コンクリートを吹き付けて、その固化により鉄筋
コンクリート壁6が、木枠や足場などを要することなく
簡便に形成される。
In the dome construction method of the present embodiment described above,
When the bag member 5 supported by the support member 4 bridged between the ring member 2 and the annular foundation 3 expands, at least a part of the dome is formed on the upper surface of the bag member 5 and the bag member is formed. Fresh concrete is sprayed so as to embed the reinforcing steel net 6a distributed along the upper surface of 5, and the solidification thereof allows the reinforced concrete wall 6 to be easily formed without requiring a wooden frame or a scaffold.

【0024】その際、図1および図3に示すごとく、リ
ング部材2に関して対称となるように鉄筋コンクリート
壁6を形成しながら順次工事を進めるようにすると、強
度的にバランスがとれて安全に工事を行なうことができ
る。
At this time, as shown in FIGS. 1 and 3, when the construction is carried out sequentially while forming the reinforced concrete wall 6 so as to be symmetric with respect to the ring member 2, the construction can be balanced and the construction can be carried out safely. Can do it.

【0025】また、多数の同形同大のドームを建設する
場合は、上記の支持部材4および袋部材5の反復利用が
可能になるので、リング部材2と環状基礎3との間を3
60度にわたり全面的に覆うように支持部材4に支持さ
れる袋部材5を設けて、膨張した同袋部材5の上面に、
全ドーム壁を形成する鉄筋コンクリート壁6を一気に打
設して、工期を大幅に短縮させることもできる。
When a large number of domes of the same shape and the same size are to be constructed, the above-mentioned support member 4 and bag member 5 can be used repeatedly.
A bag member 5 supported by the support member 4 is provided so as to cover the entire surface over 60 degrees.
The reinforced concrete wall 6 forming the entire dome wall can be cast at a stretch to greatly shorten the construction period.

【0026】さらに、本実施形態のドーム建設方法は、
リング部材2と環状基礎3との間に、全周の一部たとえ
ば45度程度にわたる部分的な鉄筋コンクリート壁6を
順次打設する工法を用いると、単一のドーム建設のよう
な場合に有利であり、少数の支持部材4および袋部材5
をリング部材2および環状基礎3のまわりに旋回させる
ようにして反復使用できるので、ドームの建設コストを
低減させることができる。
Further, the dome construction method of this embodiment
It is advantageous in the case of a single dome construction to use a construction method in which a part of the entire circumference, for example, a partial reinforced concrete wall 6 extending about 45 degrees is sequentially cast between the ring member 2 and the annular foundation 3. Yes, a small number of support members 4 and bag members 5
Can be repeatedly used so as to be swung around the ring member 2 and the annular foundation 3, so that the construction cost of the dome can be reduced.

【0027】また、リング部材2の内部の開口について
は、同リング部材2を小径にすることにより、傘形の屋
根などで容易に覆うことができるが、上述の本実施形態
のドーム建設方法のように、リング部材2の内部空間を
覆う袋部材5aを設けて、膨張させた同袋部材5aの上
面に鉄筋網7aを配置し生コンクリートを吹き付けて鉄
筋コンクリート壁7を打設する工法を用いれば、リング
部材2が大径の場合でも、同リング部材2の内部開口を
閉鎖する工事が、簡便かつ安価に行なわれるようにな
る。
The opening inside the ring member 2 can be easily covered with an umbrella-shaped roof or the like by making the ring member 2 small in diameter. As described above, the bag member 5a that covers the internal space of the ring member 2 is provided, and the reinforcing mesh 7a is disposed on the upper surface of the expanded bag member 5a, and the reinforced concrete wall 7 is cast by spraying fresh concrete. Even if the ring member 2 has a large diameter, the work for closing the internal opening of the ring member 2 can be performed simply and inexpensively.

【0028】[0028]

【発明の効果】以上詳述したように、本発明のドーム建
設方法によれば、次のような効果が得られる。 (1) リング部材と環状基礎との間に架け渡された支持部
材に支持される袋部材の膨張により、同袋部材の上面に
ドームの少なくとも一部の型が形成され、同袋部材の上
面に沿い配置された鉄筋網を埋設させるように生コンク
リートを吹き付けて、その固化により、ドームを形成す
る鉄筋コンクリート壁が、足場などを要することなく簡
便に形成されるようになる。 (2) 上記リング部材に関して対称となるように上記鉄筋
コンクリート壁を形成しながら順次工事を進めるように
すると、強度的にバランスがとれて安全に工事を行なう
ことができる。 (3) 多数の同形同大のドームを建設する場合は、上記の
支持部材および袋部材の反復利用が可能になるので、上
記のリング部材と環状基礎との間を360度にわたり全
面的に覆うように上記支持部材に支持される袋部材を設
けて、膨張した同袋部材の上面に、全ドーム壁を形成す
る鉄筋コンクリート壁を一気に打設して、工期を大幅に
短縮させることもできる。 (4) 上記支持部材および袋部材を上記のリング部材およ
び環状基礎のまわりに旋回させるようにして反復使用す
れば、単一のドームの建設の場合でもコストを低減させ
ることができる。 (5) 上記リング部材の内部空間を覆う中央袋部材を設け
て、膨張させた同中央袋部材の上面に頂部鉄筋コンクリ
ート壁を打設する工法では、上記リング部材が大径の場
合でも、同リング部材の内部開口を閉鎖する工事が、簡
便かつ安価に行なわれるようになる。
As described above, according to the dome construction method of the present invention, the following effects can be obtained. (1) Due to the expansion of the bag member supported by the support member bridged between the ring member and the annular base, at least a part of the mold of the dome is formed on the upper surface of the bag member, and the upper surface of the bag member The fresh concrete is sprayed so as to bury the reinforcing steel mesh arranged along the, and the solidification thereof allows the reinforced concrete wall forming the dome to be easily formed without requiring a scaffold or the like. (2) If the construction is proceeded sequentially while forming the reinforced concrete wall so as to be symmetrical with respect to the ring member, the construction can be performed safely with a balance in strength. (3) When constructing many domes of the same shape and the same size, the above-mentioned support member and bag member can be used repeatedly, so that the entire space between the above-mentioned ring member and the annular base extends over 360 degrees. It is also possible to provide a bag member supported by the support member so as to cover it, and to cast a reinforced concrete wall forming the entire dome wall on the upper surface of the inflated bag member at once, thereby greatly shortening the construction period. (4) The cost can be reduced even when a single dome is constructed by repeatedly using the support member and the bag member around the ring member and the annular foundation. (5) In the construction method in which a central bag member that covers the internal space of the ring member is provided and a top reinforced concrete wall is cast on the inflated upper surface of the central bag member, even if the ring member has a large diameter, the same ring is used. Work for closing the internal opening of the member is performed simply and inexpensively.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の方法により建設中のドームの工事状態
を示す斜視図である。
FIG. 1 is a perspective view showing a construction state of a dome under construction according to the method of the present invention.

【図2】図1のドームの完成状態を示す斜視図である。FIG. 2 is a perspective view showing a completed state of the dome of FIG. 1;

【図3】本発明の方法により建設中のドームの縦断面図
である。
FIG. 3 is a longitudinal sectional view of a dome under construction according to the method of the present invention.

【図4】図3のドームの要部を示す平面図である。FIG. 4 is a plan view showing a main part of the dome of FIG. 3;

【図5】図4のA−A面図である。FIG. 5 is an AA plane view of FIG. 4;

【符号の説明】[Explanation of symbols]

1 柱 2 リング部材 3 環状基礎 4 支持部材 5 袋部材 5a 中央袋部材 6 鉄筋コンクリート壁 6a 鉄筋網 7 頂部鉄筋コンクリート壁 7a 鉄筋網 G 地盤 REFERENCE SIGNS LIST 1 pillar 2 ring member 3 annular foundation 4 support member 5 bag member 5 a central bag member 6 reinforced concrete wall 6 a reinforced mesh 7 top reinforced concrete wall 7 a reinforced mesh G ground

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 地盤上に立つ複数の柱で水平に支持され
るリング部材と、同リング部材よりも大径で同リング部
材と同軸的に地盤上に構築される環状基礎とを設けてか
ら、上記のリング部材と環状基礎との間に支持部材を架
設して同支持部材により袋部材を支持し、ついで同袋部
材を膨張させた後、同袋部材の上面に沿い鉄筋網を配置
して、同鉄筋網を埋設させるように生コンクリートを吹
き付けることにより、上記袋部材の上面に沿い鉄筋コン
クリート壁を形成し、同鉄筋コンクリート壁の固化後に
上記袋部材を収縮させ、同袋部材と上記支持部材とを上
記のリング部材および環状基礎から取り外すことを特徴
とする、ドーム建設方法。
A ring member horizontally supported by a plurality of pillars standing on the ground, and an annular foundation constructed on the ground coaxially with the ring member and having a larger diameter than the ring member. A support member is erected between the ring member and the annular base, the bag member is supported by the support member, and after the bag member is inflated, a reinforcing mesh is arranged along the upper surface of the bag member. Spraying ready-mixed concrete so as to bury the reinforced mesh, thereby forming a reinforced concrete wall along the upper surface of the bag member, and shrinking the bag member after the reinforced concrete wall is solidified, thereby allowing the bag member and the support member to contract. A dome construction method, wherein the dome is removed from the ring member and the annular foundation.
【請求項2】 請求項1に記載のドーム建設方法におい
て、上記鉄筋コンクリート壁を上記リング部材に関して
対称となるように形成しながら、順次工事を進めること
を特徴とする、ドーム建設方法。
2. The dome construction method according to claim 1, wherein the construction is sequentially performed while forming the reinforced concrete wall so as to be symmetrical with respect to the ring member.
【請求項3】 請求項1または2に記載のドーム建設方
法において、初めに上記の支持部材および袋部材により
上記のリング部材と環状基礎との間を部分的に覆い、同
袋部材上面の鉄筋コンクリート壁の固化後に同袋部材を
収縮させてから、同袋部材を上記支持部材と共に上記の
リング部材および環状基礎に沿って旋回させ、ついで再
び上記袋部材を膨張させた後、同袋部材の上面に沿い鉄
筋コンクリート壁を形成し、以下同様の手順で上記のリ
ング部材と環状基礎との間に所要の鉄筋コンクリート壁
を形成してから、上記の袋部材および支持部材を上記の
リング部材および環状基礎から取り外すことを特徴とす
る、ドーム建設方法。
3. The dome construction method according to claim 1 or 2, wherein the support member and the bag member partially cover the space between the ring member and the annular foundation, and the reinforced concrete on the upper surface of the bag member. After the wall is solidified, the bag member is contracted, and then the bag member is rotated along with the support member along the ring member and the annular foundation, and then the bag member is expanded again. A reinforced concrete wall is formed along the same manner, and a required reinforced concrete wall is formed between the ring member and the annular foundation in the same procedure as described above, and then the bag member and the support member are removed from the ring member and the annular foundation. A method for constructing a dome, comprising removing the dome.
【請求項4】 請求項1〜3のいずれか1つに記載のド
ーム建設方法において、上記リング部材の内部空間を覆
う中央袋部材を設けて膨張させ、同中央袋部材の上面に
も鉄筋網を配置して同鉄筋網を埋設させるように生コン
クリートを吹き付けることにより、上記中央袋部材の上
面に沿い頂部鉄筋コンクリート壁を形成し、同頂部鉄筋
コンクリート壁の固化後に、上記中央袋部材を収縮させ
て取り外すことを特徴とする、ドーム建設方法。
4. The dome construction method according to claim 1, wherein a central bag member that covers an inner space of the ring member is provided and inflated, and a reinforcing bar mesh is also provided on an upper surface of the central bag member. By arranging and spraying ready-mixed concrete so as to bury the same reinforced mesh, a top reinforced concrete wall is formed along the upper surface of the central bag member, and after the top reinforced concrete wall is solidified, the central bag member is shrunk. A method for constructing a dome, comprising removing the dome.
JP09072713A 1997-03-10 1997-03-10 Dome construction method Expired - Fee Related JP3087261B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP09072713A JP3087261B2 (en) 1997-03-10 1997-03-10 Dome construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP09072713A JP3087261B2 (en) 1997-03-10 1997-03-10 Dome construction method

Publications (2)

Publication Number Publication Date
JPH10252202A true JPH10252202A (en) 1998-09-22
JP3087261B2 JP3087261B2 (en) 2000-09-11

Family

ID=13497282

Family Applications (1)

Application Number Title Priority Date Filing Date
JP09072713A Expired - Fee Related JP3087261B2 (en) 1997-03-10 1997-03-10 Dome construction method

Country Status (1)

Country Link
JP (1) JP3087261B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011137328A (en) * 2009-12-28 2011-07-14 Ishii Iron Works Co Ltd Air membrane body structure for constructing domed roof
CN103255866A (en) * 2013-05-15 2013-08-21 中建八局大连建设工程有限公司 Manufacturing method of roof circular arc-shaped dome structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011137328A (en) * 2009-12-28 2011-07-14 Ishii Iron Works Co Ltd Air membrane body structure for constructing domed roof
CN103255866A (en) * 2013-05-15 2013-08-21 中建八局大连建设工程有限公司 Manufacturing method of roof circular arc-shaped dome structure
CN103255866B (en) * 2013-05-15 2015-05-13 中建八局大连建设工程有限公司 Roof circular arc-shaped dome structure and manufacturing method

Also Published As

Publication number Publication date
JP3087261B2 (en) 2000-09-11

Similar Documents

Publication Publication Date Title
US4170093A (en) Method and apparatus for erecting substantially dome-like building structures
JP3087261B2 (en) Dome construction method
JPH03176537A (en) Construction of nuclear reactor-housing container top slab
US4154029A (en) Steel concrete container and a process for erecting the same
JP2004156388A (en) Construction method of arch structure, dome structure and its construction method
JP3056981B2 (en) Arch bridge construction method
JP2942761B1 (en) Construction method of large roof
US6658812B1 (en) Domed construction
JPH08135018A (en) Mixed structure of reinforced concrete column and steel skeleton beam
EP0598797A4 (en) Construction of annular walls.
US3996320A (en) Method for making domed skeletal structures of concrete
JPH09177377A (en) Tent warehouse and constructing method therefor
JP2000160687A (en) Construction method for composite structure and precast concrete column
JP3196955B2 (en) Construction method of dome type storage
JP2019070290A (en) Membrane roof and repair method of existing structure
JPH04131443A (en) Reinforced concrete structure for beam, column, or the like
JPH10159180A (en) Construction method of concrete structure using membranous body
US20240309660A1 (en) Construction of monolithic structures with air forms
JP3072066B2 (en) Construction method of building with arched roof
JPH0742238A (en) Roof structure and construction method
JPS61290137A (en) Construction of columnar pillar
JPH06212829A (en) Method of constructing roof for tank
JPS5942783B2 (en) How to construct a dome with double walls inside and outside
JPH0765339B2 (en) Concrete pillar construction method
JPH11100988A (en) Built-up method of scaffold in concrete structure

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees