JPH10239141A - Device and method for metering material for construction and ground improvement method - Google Patents

Device and method for metering material for construction and ground improvement method

Info

Publication number
JPH10239141A
JPH10239141A JP3925497A JP3925497A JPH10239141A JP H10239141 A JPH10239141 A JP H10239141A JP 3925497 A JP3925497 A JP 3925497A JP 3925497 A JP3925497 A JP 3925497A JP H10239141 A JPH10239141 A JP H10239141A
Authority
JP
Japan
Prior art keywords
civil engineering
casing
noise
ground
measuring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3925497A
Other languages
Japanese (ja)
Inventor
Takashi Isano
隆 伊佐野
Eiichi Makino
栄一 牧野
Kazuyuki Morii
和幸 森井
Kenji Morita
研志 森田
Atsushi Sugimoto
篤史 杉本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toray Engineering Co Ltd
Original Assignee
Toyo Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toyo Construction Co Ltd filed Critical Toyo Construction Co Ltd
Priority to JP3925497A priority Critical patent/JPH10239141A/en
Publication of JPH10239141A publication Critical patent/JPH10239141A/en
Pending legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve the working efficiency and the metering accuracy by reading a measurement result that is obtained by a weight-measuring means for also measuring the change in a load that is generated owing to vibration in time series, filtering out a noise with an filtering means, and metering a material for contraction based on the measurement result from which the noise is removed. SOLUTION: A dynamic distortion amplifier 25 transducer the potential of load cells 22a, 22b, and 22c into an electrical signal and outputs it. The dynamic distortion amplifier 25 has a noise filtering circuit 25r for filtering out a noise due to vibration. The noise filtering circuit 25r filters out an AC component by passing an electrical signal for indicating the amount of displacement of load cells 22a, 22b, and 22c through an analog filter and at the same time, performs a running average processing through a running averaging circuit. More specifically, a nearly constant electrical signal can be outputted through the noise filtering circuit 25r even if the load of a target to be metered changes and a noise is superposed on the amount of displacement of the load cells 22a-22c, thus resulting in a nearly equal value as an electrical signal that is outputted when the target is measured statically.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、土木工事におい
て、当該土木工事に使用される土木用材の計量を行う土
木用材計量装置および土木用材計量方法、並びに、この
計量装置および計量方法を用いた地盤改良工法に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a civil engineering material measuring device and a civil engineering material measuring method for measuring civil engineering materials used in the civil engineering work, and a ground using the measuring device and the quantitative measuring method. It relates to improved construction methods.

【0002】[0002]

【従来の技術】土木工事として、例えば、液状化対策や
軟弱な地盤の支持力を増加させるための地盤改良工事が
ある。図8に、従来の一般的な地盤改良工法の一例を説
明するための図を示す。同図(a)は上記地盤改良工法
を実施する装置の概観図、(b)は杭柱打設中における
土木用材(補給材)の計量方法を説明するための模式図
である。同図中、P1はケーシング、P2はクローラ式
サンドパイル打設機、P3はバイブロハンマ、P4はス
キップバケット、P5は砂面ゲージ、P6はトラクター
ショベルである。ケーシングP1の先端には開閉蓋P1
aが設けられている。
2. Description of the Related Art Civil works include, for example, ground improvement works for countermeasures against liquefaction and for increasing the supporting force of soft ground. FIG. 8 shows a diagram for explaining an example of a conventional general ground improvement method. FIG. 1A is a schematic view of an apparatus for implementing the above ground improvement method, and FIG. 2B is a schematic diagram for explaining a method of measuring civil engineering materials (supplementary materials) during pile post driving. In the figure, P1 is a casing, P2 is a crawler type sand pile driving machine, P3 is a vibro hammer, P4 is a skip bucket, P5 is a sand surface gauge, and P6 is a tractor shovel. An opening / closing lid P1 is provided at the tip of the casing P1.
a is provided.

【0003】一般的な地盤改良工法では、先ず、バイブ
ロハンマP3でケーシングP1を地盤中に打ち込むと共
に、このケーシングP1の打ち込み中、或いは、打ち込
み後にケーシングP1内に土木用材としての補給材(例
えば砂や礫等)を投入する。補給材の投入は、トラクタ
ーショベルP6で補給材をスキップバケットP4に搬入
した後、スキップバケットP4をケーシングP1の投入
口まで吊り上げて行われる。
In a general ground improvement method, first, a casing P1 is driven into the ground with a vibratory hammer P3, and a replenishing material (for example, sand or the like) is inserted into the casing P1 during or after driving the casing P1. Gravel). The supply of the supply material is performed by carrying the supply material into the skip bucket P4 by the tractor shovel P6 and then lifting the skip bucket P4 to the input port of the casing P1.

【0004】そして、ケーシングP1が地盤の所定の深
さまで打ち込まれた後、クローラ式サンドパイル打設機
でケーシングP1を引き上げることで、ケーシングP1
の先端の開閉蓋P1aが開き、ケーシングP1の先端か
ら地盤中に補給材が補給される。ケーシングP1を所定
量引き上げたら、バイブロハンマP3を作用させて、再
びケーシングP1を地盤中に打ち戻し、地盤中に補給し
た補給材を締め固める。なお、バイブロハンマP3を作
用させながらケーシングP1を徐々に引き上げること
で、地盤中への補給材の補給と該補給材の締め固めをほ
ぼ同時に行う場合もある。
After the casing P1 is driven to a predetermined depth in the ground, the casing P1 is pulled up by a crawler type sand pile driving machine, so that the casing P1 is driven.
The opening / closing lid P1a at the tip of the casing P1 is opened, and a supplement is supplied into the ground from the tip of the casing P1. After the casing P1 is pulled up by a predetermined amount, the casing P1 is driven back into the ground again by operating the vibratory hammer P3, and the replenishing material supplied into the ground is compacted. In some cases, by gradually pulling up the casing P1 while operating the vibratory hammer P3, replenishment of the supply material into the ground and compaction of the supply material may be performed almost simultaneously.

【0005】ケーシングP1を引き上げる過程で、ケー
シングP1内の補給材は地盤中に補給されると共に地盤
の中で締め固められ、その分、ケーシングP1内の補給
材は減少していく。ケーシングP1内の補給材が減少し
たら、上記と同様の方法で再び補給材をケーシングP1
内に投入する。そして、上記のケーシングP1の引き上
げ、打ち戻し、ケーシングP1内への補給材の投入を繰
り返すことで、地盤中に、締め固められた補給材の杭柱
が打設される。
In the process of raising the casing P1, the replenishing material in the casing P1 is supplied to the ground and compacted in the ground, and the replenishing material in the casing P1 decreases accordingly. When the supply material in the casing P1 decreases, the supply material is again supplied to the casing P1 in the same manner as described above.
Put in. Then, by repeatedly raising and driving back the casing P1 and feeding the supplementary material into the casing P1, the pile pillar of the compacted supplementary material is driven into the ground.

【0006】上記のような地盤改良工事において、工程
管理上、並びに、打設する杭柱の品質管理上、ケーシン
グP1内に投入する、土木用材としての補給材の計量は
必須用件である。
[0006] In the above-mentioned ground improvement work, in order to control the process and to control the quality of the pile columns to be cast, it is an essential requirement to measure the amount of replenishing material as civil engineering material to be put into the casing P1.

【0007】従来、上記土木用材としての補給材の計量
は、砂面ゲージP5を用いることで行われている。即
ち、図8(b)に示すように、砂面ゲージP5をケーシ
ングP1内に挿入し、投入した補給材がケーシングP1
のどの位置まで満たされているかを計ることで、投入し
た補給材の計量を行う。
Conventionally, the measurement of the replenishing material as the civil engineering material has been performed by using a sand surface gauge P5. That is, as shown in FIG. 8B, the sand surface gauge P5 is inserted into the casing P1, and the supplied replenishing material is in the casing P1.
By measuring up to which position, the supplied supply material is measured.

【0008】[0008]

【発明が解決しようとする課題】ところが、上記のよう
な砂面ゲージP5を使用した計量では、次に挙げるよう
な幾つかの問題点があった。
However, the measurement using the sand surface gauge P5 as described above has several problems as follows.

【0009】即ち、砂面ゲージP5を使用して補給材を
計量する場合、砂面ゲージP5をケーシングP1上部か
ら挿入し、徐々に降下させて砂面を検出させ、砂面を検
出した後、砂面ゲージP5を引き上げるといった煩雑な
工程が必要であり、更に、その間、砂面ゲージP5が補
給材に埋もれてしまっては困るため、補給材の投入を一
旦中断しなければならず、その分作業効率を低下させて
いる。
That is, when the supply material is measured using the sand surface gauge P5, the sand surface gauge P5 is inserted from the upper part of the casing P1, and is gradually lowered to detect the sand surface. A complicated process, such as raising the sand surface gauge P5, is required. Further, during this time, the sand surface gauge P5 is not buried in the replenishing material, so the supply of the replenishing material must be temporarily interrupted. The work efficiency has been reduced.

【0010】また、砂面ゲージP5を使用した計量で
は、補給材の投入量を正確に制御することが困難である
という問題もあった。即ち、砂面ゲージP5では、補給
材を投入した後にその投入量を計量するのであって、補
給材の投入前にはその投入量が認識できないので、補給
材を所定量だけ投入したい場合でも、大よその見当で所
定量に近い量だけ投入し、その投入後、その投入量を確
認するしかない。
In addition, in the measurement using the sand surface gauge P5, there is a problem that it is difficult to accurately control the supply amount of the supply material. That is, in the sand surface gauge P5, the supply amount is measured after the supply material is supplied, and the supplied amount cannot be recognized before the supply material is supplied. There is no other way than to put the amount close to the predetermined amount at the approximate level and then check the amount after the introduction.

【0011】ところで、近年、本出願人は、ケーシング
外部からケーシング内部に通じる貫通孔を複数有した中
空のケーシングを地盤に貫入し、地上から該ケーシング
の周辺に地盤を改良するための補給材を投入すると共
に、この補給材の一部をケーシングに設けた貫通孔を通
じてケーシング内部に流入させ、該ケーシングを引き抜
きながら該ケーシングの先端から前記補給材を地盤中に
補給し、該ケーシングを引き抜く過程で該ケーシングを
打ち戻すか振動させて地盤中に補給した前記補給材を締
め固め、地盤中に締め固められた前記補給材の杭柱を打
設する地盤改良工法を新たに開発した。
In recent years, the present applicant has penetrated the ground with a hollow casing having a plurality of through-holes communicating from the outside of the casing to the inside of the casing, and supplied a supplementary material for improving the ground from the ground to the periphery of the casing. At the same time, a part of the replenishing material is caused to flow into the inside of the casing through a through hole provided in the casing, and the replenishing material is supplied into the ground from the front end of the casing while the casing is being pulled out. A ground improvement method was newly developed in which the replenishing material replenished in the ground was beaten back or vibrated to compact the replenishing material, and a pile pillar of the replenishing material compacted in the ground was driven.

【0012】当該地盤改良工法によれば、ケーシングに
設けられた貫通孔を通じてケーシング内部へ補給材を流
入させるので、比較的太いケーシングであっても補給材
を円滑に地盤中に補給することが出来ると共に、補給材
をケーシング内部に投入する作業が、常に地表面におい
て行えるという効果が得られる。つまり、従来のケーシ
ングP1では、供給材をスキップバケットP4で高い投
入口まで持ち上げる作業が必要であったのに対し、当該
地盤改良工法ではその必要がなくなり、補給材を常に地
表面においてケーシング内部に投入することができる。
According to the ground improvement method, the replenishing material flows into the casing through the through hole provided in the casing, so that the replenishing material can be smoothly supplied to the ground even in a relatively thick casing. At the same time, an effect is obtained that the operation of charging the supply material into the casing can always be performed on the ground surface. That is, in the conventional casing P1, it was necessary to lift the supply material to the high inlet by the skip bucket P4, but in the ground improvement method, this was not necessary, and the supply material was always kept inside the casing on the ground surface. Can be put in.

【0013】ところで、土木用材としての補給材の計量
は、当該地盤改良工法(貫通孔を有するケーシングを用
いた地盤改良工法)においても、その工程管理、並び
に、品質管理の面から必須用件である。しかしながら、
当該地盤改良工法では、その計量に砂面ゲージP5を用
いると、ケーシングの周辺に投入された補給材が徐々に
ケーシングの内部に流入していくため、砂面ゲージP5
が補給材に埋もれてしまい、うまく計量できないという
問題があった。
[0013] By the way, in the ground improvement method (ground improvement method using a casing having a through-hole), the measurement of the supply material as civil engineering material is an essential requirement from the viewpoint of process control and quality control. is there. However,
In the ground improvement method, if the sand surface gauge P5 is used for the measurement, the supply material charged around the casing gradually flows into the casing.
However, there was a problem that it was buried in the replenishing material and could not be weighed well.

【0014】以上、土木工事として、地盤改良工事の例
を挙げ、その地盤改良工事で行われる補給材の計量に関
して問題点を述べてきたが、一般に、土木工事で、当該
土木工事に使用される土木用材を計量する場合には、土
木工事に伴う振動により大きなノイズが載ってしまうた
め荷重計測で計量することはなく、体積計測により計量
が行われている。
As described above, as an example of civil engineering work, ground improvement work has been taken as an example, and the problem relating to the measurement of replenishing materials performed in the ground improvement work has been described. In general, civil engineering work is used for the civil engineering work. When weighing civil engineering materials, large noise is placed due to vibrations caused by civil engineering work, so that weighing is not performed by load measurement, but by volume measurement.

【0015】しかしながら、土木用材を体積で計量する
には、例えば、所定の容積を有するバケットやホッパー
に土木用材を敷き詰め、表面をならすことで所定の容積
が計量できるなど、その作業性が非常に悪く、また、上
述の補給材のように土木用材は締固め具合で体積が変わ
る場合があるので、その分、計量の精度を欠くなどの問
題があった。
However, in order to measure civil engineering materials by volume, the workability is extremely high, for example, by laying civil engineering materials on a bucket or hopper having a predetermined volume and leveling the surface to measure the predetermined volume. In addition, since the volume of civil engineering materials, such as the above-mentioned replenishing materials, may change depending on the compaction degree, there has been a problem that the accuracy of measurement is correspondingly lacking.

【0016】この発明は、上記問題点を解決するために
なされたもので、土木工事において土木用材を計量する
場合に、作業性が良く、正確な計量の行える計量装置お
よび計量方法を提供することを目的とし、加えて、地盤
改良工法において土木用材の計量工程を改善し、地盤改
良工事全体の作業効率の向上、並びに、地盤改良工事に
おける工程管理および品質管理の確実性の向上を目的と
している。
The present invention has been made to solve the above problems, and provides a weighing apparatus and a weighing method that can perform accurate weighing with good workability when weighing civil engineering materials in civil engineering work. In addition, in the ground improvement method, improve the measuring process of civil engineering materials, improve the work efficiency of the entire ground improvement work, and improve the reliability of process management and quality control in the ground improvement work .

【0017】[0017]

【課題を解決するための手段】上記課題を解決するた
め、請求項1記載の発明は、土木工事において、該土木
工事に使用される土木用材の計量を行う土木用材計量装
置であって、土木用材の重量を土木工事に伴う振動によ
り生じる荷重の変化も合わせて計測する重量計測手段
と、この重量計測手段による計測結果を時系列的に取り
込み、この計測結果の時系列から前記振動に伴うノイズ
を除去するノイズ除去手段とを備え、前記ノイズ除去手
段によりノイズの除去された計測結果に基づいて前記土
木用材の計量を行う構成とした。
Means for Solving the Problems In order to solve the above-mentioned problems, an invention according to claim 1 is a civil engineering material measuring device for measuring civil engineering materials used in civil engineering work. A weight measuring means for measuring the weight of the timber, together with a change in load caused by vibrations caused by civil engineering work, and a measurement result obtained by the weight measuring means taken in time series, and a noise accompanying the vibration is obtained from the time series of the measurement results. And a noise elimination unit for elimination of noise, and weighs the civil engineering material based on the measurement result from which the noise has been eliminated by the noise elimination unit.

【0018】この請求項1記載の土木用材計量装置によ
れば、土木用材の計量を重量の計測により行うので、従
来のように体積を計測して計量していたのに比べて、計
量の作業性が向上する。即ち、体積を計測する場合、例
えば、所定の容積を有する器物に土木用材を入れた後、
表面をならすなどして計量を行うのに対して、この発明
の計量装置では、煩雑な作業を必要とせず、任意の量の
土木用材を、例えば重量計測手段に載せるなどして、そ
の重量を計測するだけで計量が可能である。
According to the first aspect of the present invention, since the civil engineering material is measured by measuring the weight, the work of measuring the civil engineering material is performed in comparison with the conventional method of measuring and measuring the volume. The performance is improved. That is, when measuring the volume, for example, after putting civil engineering materials in a vessel having a predetermined volume,
In contrast to performing weighing by smoothing the surface or the like, the weighing device of the present invention does not require complicated work, and an arbitrary amount of civil engineering material is placed on, for example, a weight measuring means to measure the weight. Weighing is possible only by measuring.

【0019】更に、土木用材はその締固め具合によって
体積が変わるため、従来の体積の計量では、土木用材の
締固め具合を考慮しないと、計量の精度を欠いてしまう
のに対して、この発明によれば、重量から計量を行うの
で、常に正確な計量を行うことが出来る。また、一般に
土木工事では振動を伴うが、振動が及ぶ範囲で計量を行
う場合でも、重量計測手段が土木用材の重量を振動によ
る荷重の変化も合わせて計測すると共に、ノイズ除去手
段が、振動に伴う計測結果のノイズを除去するので、振
動の影響を除去して正確な計量を行うことが出来る。
Furthermore, since the volume of civil engineering materials varies depending on the compaction degree, the conventional volume measurement lacks the precision of measurement unless the compaction degree of the civil engineering material is taken into account. According to the method, the measurement is performed from the weight, so that accurate measurement can be always performed. In general, civil engineering involves vibration, but even when weighing in the range of vibration, the weight measuring means measures the weight of the civil engineering material together with the change in load due to vibration, and the noise removing means measures the vibration. Since the noise of the accompanying measurement result is removed, the influence of vibration can be removed and accurate measurement can be performed.

【0020】ここで、上記の土木工事に使用する土木用
材とは、例えば、地盤改良工事において地盤を改良する
ために地盤中に補給される補給材(砂、礫、砕石、スラ
グ、セメント系固化材、高分子系固化材…等々)などが
例示できるが、これに限られず、土木工事において使用
され用材であれば種々のものが含まれる。上記重量計測
手段は、振動に伴う荷重の増加分まで含めて土木用材を
計量可能な計測範囲の広い、例えばロードセルなどから
構成される。上記ノイズ除去手段は、例えば、重量計測
手段の計測結果を示す電気信号を時系列的に取り込み、
この電気信号の時系列から交流成分(低周波から高周波
成分まで)を除去するローパスフィルターや、上記信号
の時系列に対して移動平均の処理を行う移動平均手段な
ど、ノイズを除去する様々な公知技術により構成可能で
ある。更に、最終的な計量値として土木用材の体積を計
量する場合、例えば、該土木用材の単位体積当たりの重
量を予め測定しておき、計量装置による重量の計測結果
から、土木用材の体積値を算定する。
Here, the civil engineering material used in the civil engineering work is, for example, a replenishing material (sand, gravel, crushed stone, slag, cement-based solidified material) supplied to the ground to improve the ground in the ground improvement work. Materials, polymer-based solidifying materials, etc.), but are not limited thereto, and include various materials used in civil engineering work. The weight measuring means is composed of, for example, a load cell having a wide measuring range capable of measuring civil engineering materials including an increase in load due to vibration. The noise removing unit, for example, takes in an electric signal indicating the measurement result of the weight measuring unit in time series,
Various known noise-removing devices, such as a low-pass filter that removes an AC component (from low frequency to high-frequency component) from the time series of the electric signal and a moving average unit that performs a moving average process on the time series of the signal, Configurable by technology. Furthermore, when measuring the volume of the civil engineering material as the final measurement value, for example, the weight per unit volume of the civil engineering material is measured in advance, and the volume value of the civil engineering material is determined from the measurement result of the weight by the measuring device. Calculate.

【0021】請求項2記載の発明は、請求項1記載の土
木用材計量装置において、前記土木用材の計測とほぼ同
時に当該土木用材とほぼ同様の振動が掛かる状態で既知
の重量の計測を行う補助重量計測手段と、この補助重量
計測手段による計測結果から前記ノイズ除去手段と同様
のノイズ除去を行う補助ノイズ除去手段と、この補助ノ
イズ除去手段によりノイズの除去された既知の重量の計
測結果と、当該既知の重量の本来の値との差異に基づ
き、前記土木用材の計測結果を補正する補正手段とを備
えている構成とした。
According to a second aspect of the present invention, there is provided the civil engineering material measuring apparatus according to the first aspect, wherein the measurement of the known weight is performed substantially simultaneously with the measurement of the civil engineering material under substantially the same vibration as the civil engineering material. Weight measuring means, an auxiliary noise removing means for performing the same noise removal as the noise removing means from the measurement result by the auxiliary weight measuring means, a known weight measurement result from which noise has been removed by the auxiliary noise removing means, And a correcting means for correcting the measurement result of the civil engineering material based on the difference from the original value of the known weight.

【0022】この請求項2記載の発明によれば、上記補
助重量計測手段と補助ノイズ除去手段により、土木用材
の重量計測と同様の条件で既知の重量の計測を行い、そ
の計測値と本来の重量との差異に基づき、土木用材の計
測結果(ノイズ除去後の計測結果)を補正するので、土
木用材の計量の精度が更に向上される。
According to the second aspect of the present invention, a known weight is measured by the auxiliary weight measuring means and the auxiliary noise removing means under the same conditions as those for measuring the weight of civil engineering material, and the measured value is compared with the original weight. Based on the difference from the weight, the measurement result of the civil engineering material (measurement result after noise removal) is corrected, so that the accuracy of the measurement of the civil engineering material is further improved.

【0023】ここで、上記補正手段による補正の内容
は、例えば、(土木用材の補正後の計測値)=[(既知
の重量の本来の値)/(既知の重量の計測値)]×(土
木用材の補正前の計測値)とする補正や、(土木用材の
補正後の計測値)=(土木用材の補正前の計測値)+
[(既知の重量の計測値)−(既知の重量の本来の
値)]とする補正や、上記2種類の補正に重みをつけて
合成した補正、並びに、実験により補正式を求め、その
補正式に基づいて行う補正など、色々な補正が有り得
る。補正式を求める実験例としては、土木用材計量装置
により標準的な所定の計測量(実際に計量される量)を
様々な振動に掛けた状態で計量し、既知の重量とその計
測値との差異がとる値に依って、上記所定の計測量が本
来の値からどの程度ずれるかを求める実験などが有り得
る。なお、補正手段の補正内容は、上記の具体例に限ら
れるものではない。
Here, the content of the correction by the correction means is, for example, (measured value of civil engineering material after correction) = [(original value of known weight) / (measured value of known weight)] × ( Correction as (measured value of civil engineering material before correction) or (measured value of civil engineering material after correction) = (measured value of civil engineering material before correction) +
Correction of [(measured value of known weight)-(original value of known weight)], correction combining weights of the above two types of corrections, and correction formulas obtained by experiments and correction There can be various corrections, such as corrections based on equations. As an example of an experiment for obtaining a correction formula, a standard predetermined measurement amount (actually measured amount) is weighed by various types of vibrations by a civil engineering material weighing device, and a known weight is compared with a measured value. An experiment may be performed to determine how much the predetermined measurement amount deviates from the original value depending on the value of the difference. Note that the correction contents of the correction means are not limited to the above specific examples.

【0024】請求項3記載の発明は、土木工事におい
て、該土木工事に使用される土木用材の計量を行う土木
用材計量方法であって、土木用材の重量を土木工事に伴
う振動により生じる荷重の変化も合わせて計測する計測
処理と、この計測処理により得られた計測結果を時系列
的に取り込みこの計測結果の時系列から前記振動に伴う
ノイズを除去するノイズ除去処理とを行い、このノイズ
除去処理によりノイズの除去された計測結果に基づいて
前記土木用材の計量を行う方法とした。
According to a third aspect of the present invention, there is provided a civil engineering material measuring method for measuring a civil engineering material used in the civil engineering work, wherein the weight of the civil engineering material is reduced by a load generated by vibration accompanying the civil engineering work. A measurement process for measuring the change is also performed, and a noise removal process for removing the noise accompanying the vibration from the time series of the measurement results by taking in the measurement results obtained by the measurement process in a time series is performed. The method for weighing the civil engineering material based on the measurement result from which noise has been removed by the processing is adopted.

【0025】この請求項3記載の発明によれば、請求項
1記載の発明と同様の作用・効果を得ることが出来る。
According to the third aspect of the invention, the same functions and effects as those of the first aspect of the invention can be obtained.

【0026】請求項4記載の発明は、請求項3記載の土
木用材計量方法において、前記土木用材の計測とほぼ同
時に前記土木用材とほぼ同様の振動が掛かる状態で既知
の重量の計測を行う補助計測処理と、この補助計測処理
により得られた計測結果から前記ノイズ除去処理と同様
のノイズ除去を行う補助ノイズ除去処理と、この補助ノ
イズ除去処理によりノイズの除去された既知の重量の計
測結果と、当該既知の重量の本来の値との差異に基づ
き、前記土木用材の計測結果を補正する補正処理とを加
えた方法とした。
According to a fourth aspect of the present invention, there is provided the method for measuring civil engineering materials according to the third aspect, wherein the measurement of the known weight is performed substantially simultaneously with the measurement of the civil engineering materials in a state where substantially the same vibration as that of the civil engineering materials is applied. A measurement process, an auxiliary noise removal process for removing noise similar to the noise removal process from the measurement result obtained by the auxiliary measurement process, and a known weight measurement result from which noise has been removed by the auxiliary noise removal process. And a correction process for correcting the measurement result of the civil engineering material based on the difference between the known weight and the original value.

【0027】この請求項4記載の発明によれば、請求項
2記載の発明と同様の作用・効果を得ることが出来る。
According to the fourth aspect of the invention, the same operation and effect as those of the second aspect of the invention can be obtained.

【0028】請求項5記載の発明は、ケーシングを地盤
に貫入し、該ケーシング内に投入された地盤を改良する
ための補給材を該ケーシングを引き抜きながら地盤中に
補給し、該ケーシングを引き抜く過程で該ケーシングを
打ち戻すか振動させて地盤中に補給した前記補給材を締
め固め、地盤中に締め固められた前記補給材の杭柱を打
設する地盤改良工法において、前記補給材の1回分の投
入量を請求項1記載の土木用材計量装置を用いて計量
し、その後、当該補給材を前記ケーシング内に投入する
工法とした。
According to a fifth aspect of the present invention, there is provided a process of penetrating a casing into the ground, supplying replenishing material for improving the ground introduced into the casing into the ground while extracting the casing, and extracting the casing. In the ground improvement method of compacting the replenishing material replenished in the ground by driving back or vibrating the casing in the ground and driving a pile pillar of the replenishing material compacted in the ground, one time of the replenishing material is used. Was measured using the civil engineering material measuring device according to claim 1, and thereafter, the construction material was charged into the casing.

【0029】この請求項5記載の発明によれば、ケーシ
ングに投入する補給材の計量を、上記土木用材計量装置
を使用し、補給材の重量を計測して行うので、従来の砂
面ゲージを用いた計量に比べて、その作業性や計量の精
度が向上し、延いては、地盤改良工事全体の作業効率の
向上、並びに、品質の向上を図ることが出来る。
According to the fifth aspect of the present invention, the supplementary material to be charged into the casing is measured by using the above-mentioned civil engineering material measuring device and measuring the weight of the supplementary material. Compared with the used weighing, the workability and the accuracy of the weighing are improved, and the working efficiency and the quality of the whole ground improvement work can be improved.

【0030】例えば、従来の砂面ゲージを用いた地盤改
良工法では、砂面ゲージでの計測中はケーシングへの補
給材の投入が行えず、作業効率の低下を招いていたのに
対して、この発明の地盤改良工法では、補給材の計量と
補給材の投入とを連続して行うことが出来ると共に、土
木用材計量装置による計量中、ケーシングの引き抜きお
よび打ち戻し(振動を含む)を平行して行うことが出来
る。つまり、地盤へのケーシングの貫入から引き抜きお
よび打ち戻しを、絶え間なく行うことが可能であり、作
業効率が飛躍的に向上する。
For example, in the conventional ground improvement method using a sand surface gauge, while the measurement with the sand surface gauge was not performed, it was not possible to supply the replenishing material to the casing, resulting in a decrease in work efficiency. In the ground improvement method of the present invention, the measurement of the supply material and the supply of the supply material can be performed continuously, and during the measurement by the civil engineering material measuring device, the casing is pulled out and driven back (including vibration) in parallel. Can be done. That is, it is possible to continuously perform pulling out and punching back from the penetration of the casing into the ground, and the working efficiency is dramatically improved.

【0031】また、砂面ゲージを使用した工法では、補
給材の投入後に該投入量を計量するため、補給材の投入
量を正確に制御するのが困難であるといった問題があっ
たのに対して、この発明の工法では、補給材をケーシン
グ内に投入する前にその計量を行うので、補給材の投入
量の正確な計測および制御を行うことができる。故に、
地盤改良工事の品質の向上を図ることが出来る。
Further, in the method using the sand surface gauge, since the amount of the supply material is measured after the supply material is supplied, there is a problem that it is difficult to accurately control the supply amount of the supply material. According to the construction method of the present invention, since the replenishing material is measured before it is charged into the casing, it is possible to accurately measure and control the amount of the replenishing material charged. Therefore,
The quality of the ground improvement work can be improved.

【0032】ここで、地盤を改良する地盤改良工法と
は、例えば、沖積平野に堆積した粘性土、軟弱な海底に
存在する海成粘土やその上に造成された人工埋立地、沼
沢地の腐敗土、ロームなどの特殊土を含む粘性土系軟弱
地盤における支持力の増加、載荷時や掘削時の安定、沈
下対策に対する適用や、さらに、緩い砂地盤、火山灰・
しらすなどの特殊土を含む砂質土系軟弱地盤における支
持力の増加、沈下対策、遮水対策、液状化対策を目的と
するものであり、地盤を改良すべく地盤中に供給する補
給材には、例えば、砂、礫、砕石、スラグ、セメント系
固化材、高分子系固化材などが含まれる。なお、補給材
の投入は、ケーシングを地盤に貫入している間、ケーシ
ングを所定の深さまで貫入した後、ケーシングを引き抜
いている間、ケーシングを打ち戻している間などに行わ
れ、その投入タイミングは限定されるものではない。
Here, the ground improvement method for improving the ground includes, for example, cohesive soil deposited on an alluvial plain, marine clay existing on a soft seabed, artificial landfills formed on the ground, and decay of swamps. Increased bearing capacity in cohesive soil based soft soils including special soils such as soil and loam, stability during loading and excavation, application to settlement measures, loose sandy ground, volcanic ash
It is intended to increase the bearing capacity, countermeasures against settlement, measures against water blocking, and measures against liquefaction in sandy soil based soft ground including special soil such as whitebait, and is used as a supply material to be supplied into the ground to improve the ground. Include, for example, sand, gravel, crushed stone, slag, cement-based solidification material, polymer-based solidification material, and the like. The supply of the supply material is performed while the casing is penetrating the ground, after the casing has penetrated to a predetermined depth, while the casing is being pulled out, or while the casing is being driven back, and the like. Is not limited.

【0033】請求項6記載の発明は、ケーシング外部か
らケーシング内部に通じる貫通孔を複数有した中空のケ
ーシングを地盤に貫入し、地上から該ケーシングの周辺
に地盤を改良するための補給材を投入すると共に、この
補給材の一部をケーシングに設けた貫通孔を通じてケー
シング内部に流入させ、該ケーシングを引き抜きながら
該ケーシングの先端から前記補給材を地盤中に補給し、
該ケーシングを引き抜く過程で該ケーシングを打ち戻す
か振動させて地盤中に補給した前記補給材を締め固め、
地盤中に締め固められた前記補給材の杭柱を打設する地
盤改良工法において、前記補給材の1回分の投入量を請
求項1記載の土木用材計量装置を用いて計量し、その
後、当該補給材を前記ケーシングに投入する工法とし
た。
According to a sixth aspect of the present invention, a hollow casing having a plurality of through-holes extending from the outside of the casing to the inside of the casing is penetrated into the ground, and a supply material for improving the ground is supplied from the ground to the periphery of the casing. And at the same time, a part of the replenishing material is caused to flow into the inside of the casing through a through hole provided in the casing, and the replenishing material is replenished into the ground from the tip of the casing while the casing is being pulled out,
In the process of pulling out the casing, the casing is beaten back or vibrated to compact the replenishing material supplied to the ground,
In the ground improvement method of driving a pile of the supplementary material compacted in the ground, the input amount of the supplementary material for one time is measured using the civil engineering material measuring device according to claim 1, and thereafter, The construction method was such that a replenishing material was charged into the casing.

【0034】この請求項6記載の発明によれば、比較的
太いケーシングであっても補給材を円滑に地盤中に補給
することが出来ると共に、補給材をケーシング内部に投
入する作業が、常に地表面において行えるという効果を
奏する地盤改良工法において、従来の砂面ゲージを用い
た計量方法では、砂面ゲージが補給材に埋まってしま
い、うまく計量できなかったのに対して、この発明によ
れば、なんら問題なく補給材の計量を行うことが出来る
と共に、請求項5記載の地盤改良工法と同様、計量工程
の作業性や計量の精度が向上し、延いては、地盤改良工
事全体の作業効率の向上、並びに、品質の向上を図るこ
とが出来る。
According to the sixth aspect of the present invention, the replenishing material can be smoothly supplied to the ground even if the casing is relatively thick, and the operation of charging the replenishing material into the casing always requires the ground. According to the present invention, in the ground improvement method having an effect of being able to be performed on the surface, in the conventional measuring method using the sand surface gauge, the sand surface gauge was buried in the replenishing material and could not be measured properly. The replenishment material can be measured without any problem, and, similarly to the ground improvement method according to claim 5, the workability of the measurement process and the accuracy of the measurement are improved, and the work efficiency of the entire ground improvement work is extended. And the quality can be improved.

【0035】なお、補給材としての具体例や、補給材の
投入タイミングの具体例は、請求項5の地盤改良工法の
箇所で説明したものと同様である。
A specific example of the supply material and a specific example of the supply timing of the supply material are the same as those described in the section of the ground improvement method according to claim 5.

【0036】[0036]

【発明の実施の形態】以下、この発明の実施の形態の土
木用材計量装置、土木用材計量方法、並びに、地盤改良
工法について、図1〜図7の図面を参照しながら説明す
る。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A civil engineering material measuring device, a civil engineering material measuring method, and a ground improvement method according to an embodiment of the present invention will be described below with reference to the drawings of FIGS.

【0037】[第1の実施の形態]図1には、本発明に
係る地盤改良工法を実施する地盤改良装置10の概観図
を、図2は、図1におけるホッパー6や供給装置8の部
分の詳細図を((a)は側面図、(b)は上面図、
(c)は供給装置8を作動させた状態の側面図)、図3
には、土木用材計量装置20のシステム全体の構成図を
示す。
[First Embodiment] FIG. 1 is a schematic view of a ground improvement apparatus 10 for implementing a ground improvement method according to the present invention, and FIG. 2 is a view of a hopper 6 and a supply device 8 in FIG. (A) is a side view, (b) is a top view,
(C) is a side view of the state in which the supply device 8 is operated), FIG.
2 shows a configuration diagram of the entire system of the civil engineering material weighing device 20.

【0038】この地盤改良装置10は、本発明に係る地
盤改良工法を実施する装置の一例を示すもので、クロー
ラ式サンドパイル打設機1、トラクターショベル2、地
盤中に打ち込まれるケーシング3、ケーシング3に振動
を与えるバイブロハンマ5、ホッパー6、地表付近の締
め固めに作用する載荷板7、供給装置8、土木用材計量
装置20(図2)等から構成される。
The ground improvement apparatus 10 is an example of an apparatus for implementing the ground improvement method according to the present invention, and includes a crawler type sand pile driving machine 1, a tractor shovel 2, a casing 3 driven into the ground, and a casing. 3 includes a vibratory hammer 5, a hopper 6, a loading plate 7 acting on compaction near the ground surface, a supply device 8, a civil engineering material measuring device 20 (FIG. 2), and the like.

【0039】ケーシング3は、ケーシング外部からケー
シング内部に通じる貫通孔3a,3a…を有する中空の
もので、その先端部には地盤中の過剰間隙水を吸水する
吸水機構4や、開閉蓋3bが設けられている。ケーシン
グ3の先端部は、ケーシング3の径よりも大きく構成さ
れ、ケーシング3を地盤中に打設すると、地盤中、ケー
シング3の周囲に空間が形成されるようになっている。
The casing 3 is a hollow body having through holes 3a, 3a,... Communicating from the outside of the casing to the inside of the casing, and a water absorbing mechanism 4 for absorbing excess pore water in the ground and an opening / closing lid 3b are provided at the tip. Is provided. The distal end of the casing 3 is configured to be larger than the diameter of the casing 3, and when the casing 3 is driven into the ground, a space is formed around the casing 3 in the ground.

【0040】ホッパー6は、供給装置8により投入され
た補給材(例えば砂や礫など)が、ケーシング3の内部
又は周囲を介して地盤中に流入していくまで、一時的に
蓄えておくもので、図2にも示すように、上側の開口部
から補給材を受け入れて貯蔵すると共に、下側の開口部
からケーシング3内部或いはケーシング3の周囲に補給
材を送出するようになっている。ケーシング3は、この
ホッパー6の上側および下側の開口部に通されて地盤中
に打ち込まれるようになっている。このホッパー6内に
は、補給材の貯蔵量が限界に達したか否かを検出するリ
ミットスイッチ23(図3)が設けられている。このリ
ミットスイッチ23は、供給装置8から補給材が供給さ
れたときにもその供給を検出するようになっている。
The hopper 6 temporarily stores the replenishing material (eg, sand or gravel) supplied by the supply device 8 until it flows into the ground via the inside or around the casing 3. As shown in FIG. 2, the supply material is received and stored from the upper opening, and the supply material is sent out from the lower opening to the inside of the casing 3 or to the periphery of the casing 3. The casing 3 is passed through the upper and lower openings of the hopper 6 and is driven into the ground. The hopper 6 is provided with a limit switch 23 (FIG. 3) for detecting whether or not the storage amount of the supply material has reached a limit. The limit switch 23 detects the supply of the supply material even when the supply material is supplied from the supply device 8.

【0041】供給装置8は、補給材の収容および投出を
行うバケット8aと、該バケット8aを傾斜させるシリ
ンダー8bとからなり、バケット8a内に補給材を積載
した状態で、図2(c)に示すように、シリンダー8b
を作動させてバケット8aを傾斜させることにより、バ
ケット8a内の補給材をホッパー6内に供給するように
なっている。
The supply device 8 comprises a bucket 8a for storing and discharging the supply material, and a cylinder 8b for tilting the bucket 8a. FIG. 2 (c) shows a state where the supply material is loaded in the bucket 8a. As shown in FIG.
Is operated to incline the bucket 8a so that the supply material in the bucket 8a is supplied into the hopper 6.

【0042】土木用材計量装置20は、図3にも示すよ
うに、基台21、重量計測手段としての第1〜第3のロ
ードセル22a〜22c、動歪みアンプ25、上記バケ
ット8b内に設けられたリミットスイッチ23、計量盤
24、ペンレコーダー26、操作ボックス27等から構
成され、供給装置8のバケット8aに載積された土木材
料(例えば補給材)の重量を計測し、この重量から土木
用材の計量を行うようになっている。
As shown in FIG. 3, the civil engineering material measuring device 20 is provided in a base 21, first to third load cells 22a to 22c as weight measuring means, a dynamic strain amplifier 25, and the bucket 8b. And a limit switch 23, a measuring board 24, a pen recorder 26, an operation box 27, and the like. The weight of the civil engineering material (for example, replenishing material) loaded on the bucket 8a of the supply device 8 is measured, and the civil engineering material is calculated from the weight. Weighing.

【0043】この土木用材計量装置20の重量計測を行
う部分(ロードセル22a〜22cと基台21)は供給
装置8と一体的に構成されている。詳細には、供給装置
8のバケットシリンダー8bは計量装置20の基台21
を回動・傾斜させるようになっており、この基台21に
ロードセル22a〜22cを介してバケット8aが取り
付けられている。この構成により、補給材の計測から投
入までを連続してスムーズに行うことができ、地盤改良
工事の作業効率をより向上させている。
The portion (the load cells 22a to 22c and the base 21) of the civil engineering material measuring device 20 for performing weight measurement is integrally formed with the supply device 8. Specifically, the bucket cylinder 8 b of the supply device 8 is mounted on the base 21 of the measuring device 20.
The bucket 8a is attached to the base 21 via load cells 22a to 22c. With this configuration, it is possible to continuously and smoothly perform the measurement from the supply of the supply material, and the work efficiency of the ground improvement work is further improved.

【0044】ロードセル22a,22b,22cは、供
給装置8のバケット8aを支持する状態に設けられ、バ
ケット8aに負荷された荷重により変位を生じさせるよ
うになっている。つまり、バケット8aに負荷された荷
重を計測する重量計測手段を構成している。
The load cells 22a, 22b, and 22c are provided in a state of supporting the bucket 8a of the supply device 8, and generate displacement by a load applied to the bucket 8a. That is, it constitutes weight measuring means for measuring the load applied to the bucket 8a.

【0045】これらロードセル22a,22b,22c
は、重量の大きな補給材の荷重を、振動に伴い増加され
る荷重分も合わせて計測できるように、定格負荷が大き
なものが使用されている。なお、ロードセル22a,2
2b,22cは、負荷された荷重に対して出力信号が線
形に変化するものを使用することが望ましいが、非線形
成分が無視できない場合は、上記出力信号に補正処理を
施して線形にするようにしても良い。この補正処理は公
知の信号処理により容易に構成可能である。また、構造
的な免震機構を計量装置20の基台21と地面との間に
設けることで、ロードセル22a,22b,22cの定
格負荷を比較的小さなものにすることも出来る。
These load cells 22a, 22b, 22c
A large rated load is used so that the load of a heavy replenishing material can be measured together with the load increased by the vibration. Note that the load cells 22a, 2
As for 2b and 22c, it is desirable to use one in which the output signal changes linearly with respect to the applied load. However, if the non-linear component cannot be ignored, the output signal is corrected to be linear. May be. This correction processing can be easily configured by known signal processing. Further, by providing a structural seismic isolation mechanism between the base 21 of the weighing device 20 and the ground, the rated loads of the load cells 22a, 22b, and 22c can be made relatively small.

【0046】動歪みアンプ25は、上記ロードセル22
a,22b,22cの変位を電気信号に変換して出力す
るものである。この動歪みアンプ25には、振動による
ノイズを除去するためのノイズ除去回路25rが設けら
れている。このノイズ除去回路25rは、アナログフィ
ルタや移動平均回路から構成され、ロードセル22a,
22b,22cの変位量を示す電気信号をアナログフィ
ルターに通して交流成分(例えば1Hzの低周波から高
周波成分まで)を除去すると共に、移動平均回路に通し
て移動平均処理(例えば2秒間隔の移動平均)を施すよ
うになっている。
The dynamic distortion amplifier 25 includes the load cell 22
The displacements a, 22b and 22c are converted into electric signals and output. The dynamic distortion amplifier 25 is provided with a noise removing circuit 25r for removing noise due to vibration. The noise removing circuit 25r is composed of an analog filter and a moving average circuit, and includes the load cells 22a,
An electric signal indicating the displacement amount of each of 22b and 22c is passed through an analog filter to remove an AC component (for example, from a low frequency to a high frequency component of 1 Hz), and is passed through a moving average circuit to perform a moving average process (for example, moving at 2 second intervals) Average).

【0047】つまり、土木工事の振動により、計量する
対象物の荷重が変化して、ロードセル22a〜22cの
変位量にノイズが載った場合でも、その変位量を示す電
気信号がノイズ除去回路25rを通過することでノイズ
が除去され、動歪みアンプ25からはほぼ一定の電気信
号(第1〜第3のロードセル出力信号)が出力されるよ
うになっている。この第1〜第3のロードセル出力信号
は、静時に上記対象物を計測した場合に出力される電気
信号と、ほぼ同値なものになる。
That is, even if the load on the object to be measured changes due to the vibration of the civil engineering work and noise is placed on the displacement of the load cells 22a to 22c, the electric signal indicating the displacement is transmitted to the noise removing circuit 25r. The passage removes noise, and the dynamic distortion amplifier 25 outputs substantially constant electric signals (first to third load cell output signals). The first to third load cell output signals have substantially the same value as the electric signal output when the object is measured at rest.

【0048】操作ボックス27には、オールリセットボ
タン27A、貫入終了ボタン27B、計量ボタン27
D、風袋補正ボタン27E、計量確定ランプ27b、計
量完了ランプ27d、風袋完了ランプ27eが設けら
れ、これらのボタンを操作することで計量装置20のコ
ントロールを行うようになっている。これらボタンの操
作内容については、計量方法の説明の箇所で詳述する。
この操作ボックス27は、通常、ペンレコーダー26と
共にオペレーション室内に設けられる。
The operation box 27 includes an all reset button 27A, a penetration end button 27B, a weighing button 27
D, a tare correction button 27E, a weighing confirmation lamp 27b, a weighing completion lamp 27d, and a tare completion lamp 27e are provided, and the weighing device 20 is controlled by operating these buttons. The operation contents of these buttons will be described in detail in the description of the weighing method.
The operation box 27 is usually provided in an operation room together with the pen recorder 26.

【0049】計量盤24は、操作ボックス27の操作に
基づき、バケット8aに積載された補給材の計量、地盤
に補給した補給材の積算土量の計量、ケーシング3内部
又は周辺の補給材の残土量の演算、ペンレコーダー26
に記録するデータの送信等、土木材料計量装置20の制
御を行うようになっている。詳細は計量方法の説明の箇
所で行うが、補給材の計量や積算土量は、予め計測され
た補給材の単位体積重量に基づいて、重量から体積に変
換されて行われるようになっている。計量盤24には、
動歪みアンプ25(ロードセル22a,22b,22
c)、操作ボックス27、バイブロハンマ5の電流計5
a、ケーシング3の深度を計る深度計3d、ペンレコー
ダー26等が接続されている。
Based on the operation of the operation box 27, the measuring board 24 measures the supply material loaded on the bucket 8a, measures the integrated soil amount of the supply material supplied to the ground, the remaining soil of the supply material inside or around the casing 3. Calculation of quantity, pen recorder 26
The control of the civil engineering material weighing device 20 is performed, such as transmission of data to be recorded in the device. The details will be described in the description of the weighing method, but the weighing and the accumulated soil amount of the supplement material are converted from weight to volume based on the unit volume weight of the supplement material measured in advance. . On the measuring board 24,
Dynamic distortion amplifier 25 (load cells 22a, 22b, 22
c), operation box 27, ammeter 5 of vibro hammer 5
a, a depth gauge 3d for measuring the depth of the casing 3, a pen recorder 26 and the like are connected.

【0050】なお、動歪みアンプ25のノイズ除去回路
25rにより行われるノイズ除去処理で、ノイズが十分
に除去できずに測定精度が出ない場合には、計量盤24
に更なるフィルター回路を設けて、動歪みアンプ25か
ら出力されるロードセル出力信号の交流成分を除去する
ようにしても良い。
If the noise removal processing performed by the noise removal circuit 25r of the dynamic distortion amplifier 25 does not sufficiently remove the noise and the measurement accuracy is not high, the measuring board 24
An additional filter circuit may be provided to remove the AC component of the load cell output signal output from the dynamic distortion amplifier 25.

【0051】次に、上記のような構成の土砂改良装置1
0を用いて実施する、本発明に係る地盤改良工法(本発
明に係る土木用材計量方法も含まれる。)について説明
を行う。
Next, the earth and sand improvement device 1 having the above-described configuration
The ground improvement method according to the present invention (including the method for measuring civil engineering materials according to the present invention), which is carried out using 0, will be described.

【0052】図4(a)〜(e)は、この地盤改良工事
の概略一連の施工手順を示した模式図、図5は、この地
盤改良工事の中で行われる補給材の計量方法の手順を示
した模式図である。
4 (a) to 4 (e) are schematic diagrams showing a series of outline steps of the ground improvement work, and FIG. 5 is a procedure of a replenishing material measuring method performed in the ground improvement work. FIG.

【0053】先ず、地盤改良工事が始まる前に、載荷板
7が安定した状態で土木用材計量装置20のゼロ調整と
スパン調整を行っておく。ゼロ調整は、計量装置20に
負荷を与えない状態で計測値が「0」を示すようにする
調整であり、スパン調整は負荷の増減量に対する計測値
の増減比を調整するもので、例えば、ゼロ調整を行った
後で、所定の負荷(例えば1トン)を与え、その計測値
が所定の負荷の重量と一致するように調整する。
First, before the ground improvement work starts, zero adjustment and span adjustment of the civil engineering material measuring device 20 are performed in a state where the loading plate 7 is stabilized. Zero adjustment is an adjustment to make the measured value show "0" in a state where no load is applied to the weighing device 20, and span adjustment is to adjust the increase / decrease ratio of the measured value to the increase / decrease amount of the load. After performing the zero adjustment, a predetermined load (for example, 1 ton) is given, and the measurement is adjusted so that the measured value matches the weight of the predetermined load.

【0054】更に、地盤改良工事が始まる前に、軽量す
る補給材の単位体積当たりの重量計測を行っておく。こ
の計測は、バケット8aに補給材を満たし、表面をすり
切りでならした後に、バケット8aの補給材の計量を行
うことで行われる。土木用材計量装置20には、予めバ
ケット8aの容量が記憶されており、図示しない土砂比
重スイッチをON操作することで、上記バケット8aに
満たした補給材の重量が計測されると共に、その計測値
を容量で割る演算が行われて、その値が補給材の単位体
積重量として計量盤24中に記憶・設定される。
Further, before the ground improvement work starts, the weight per unit volume of the supplement material to be lightened is measured. This measurement is performed by filling the bucket 8a with the replenishing material, scouring the surface, and then measuring the replenishing material in the bucket 8a. The capacity of the bucket 8a is stored in advance in the civil engineering material weighing device 20, and by turning on an earth / sand specific gravity switch (not shown), the weight of the replenishing material filled in the bucket 8a is measured and the measured value is measured. Is divided by the capacity, and the value is stored and set in the weighing board 24 as the unit weight of the supply material.

【0055】上記のような設定を行った後、地盤改良工
事を開始する。即ち、バイブロハンマ5を作動させなが
ら、クローラ式サンドパイル打設機1によりケーシング
3を地盤中に貫入していく(図4(a)〜(b))。
After the above settings are made, ground improvement work is started. That is, while operating the vibro-hammer 5, the crawler-type sandpile driving machine 1 penetrates the casing 3 into the ground (FIGS. 4A and 4B).

【0056】このケーシング3の貫入中、順次、土木用
材計量装置20により補給材の計量を行う計量工程、計
量済みの補給材をホッパー6内に投入する供給工程を繰
り返し行っていく。
While the casing 3 is penetrating, the measuring step of measuring the supply material by the civil engineering material measuring device 20 and the supply step of putting the measured supply material into the hopper 6 are repeatedly performed.

【0057】補給材の計量は、図5の〜に示す一連
の処理により行われる。即ち、先ず、供給装置8のバケ
ット8aに補給材を投入する前に、操作ボックス27の
風袋ボタン27EをON操作して、風袋補正を行う(図
5の)。
The measurement of the replenishing material is performed by a series of processes shown in FIGS. That is, first, before the replenishing material is supplied to the bucket 8a of the supply device 8, the tare button 27E of the operation box 27 is turned on to perform tare correction (FIG. 5).

【0058】風袋ボタン27EをON操作すると、この
ON信号が計量盤24に入力され、該ON信号に基づ
き、動歪みアンプ25から出力されているロードセル出
力信号が計量盤24に読み込まれ、このロードセル出力
信号に対応する計量値が「0」に補正される。この風袋
補正により、前回の補給材の投入の際にバケット8a内
に補給材が残った場合でも、その残った分を差し引いた
計量を行うことができ、地盤中に補給するトータル的な
補給材の補給量が正確に計量される。
When the tare button 27E is turned ON, this ON signal is input to the weighing panel 24, and based on the ON signal, the load cell output signal output from the dynamic distortion amplifier 25 is read into the weighing panel 24, and the load cell is read. The weighing value corresponding to the output signal is corrected to “0”. By this tare correction, even when replenishing material remains in the bucket 8a at the time of supplying the replenishing material last time, it is possible to perform measurement by subtracting the remaining amount, so that the total replenishing material to be replenished into the ground can be obtained. Is accurately measured.

【0059】計量盤24により風袋補正が完了すると、
計量盤24からパトライトに作動信号が出力されてバケ
ット8a内に補給材の投入を許可するパトライトの点灯
が行われる。風袋補正が完了した後、パトライトの点灯
を確認して、トラクターショベル2により補給材を供給
装置8のバケット8aに投入する(図5の)。
When the tare correction is completed by the measuring board 24,
An operation signal is output from the weighing board 24 to the patrol light, and the patrol light for permitting the supply of the supply material into the bucket 8a is turned on. After the completion of the tare correction, the lighting of the patrol light is confirmed, and the tractor shovel 2 puts the supply material into the bucket 8a of the supply device 8 (FIG. 5).

【0060】バケット8a内に補給材が投入されると、
その補給材の荷重が、ケーシング3の貫入の振動により
生じた荷重の変化分も合わせてロードセル22a,22
b,22cに負荷され、その負荷に応じて、ロードセル
22a,22b,22cに変位が生じる。この変位は動
歪みアンプ25で電気信号に変換され、動歪みアンプ2
5の中でこの電気信号の交流成分(振動に伴うノイズ)
が除去される。そして、この交流成分が除去された信号
がロードセル出力信号として、計量盤24に出力され
る。従って、計量盤24に入力されるロードセル出力信
号は、バケット8aに積載された補給材の重量を示すほ
ぼ一定の値になっている。
When the supply material is put into the bucket 8a,
The load of the replenishing material is adjusted by the load cells 22a, 22a together with the change in the load caused by the vibration of the penetration of the casing 3.
b, 22c, and the load cells 22a, 22b, 22c are displaced according to the load. This displacement is converted into an electric signal by the dynamic distortion amplifier 25,
AC component of this electric signal in 5 (noise due to vibration)
Is removed. Then, the signal from which the AC component has been removed is output to the weighing board 24 as a load cell output signal. Therefore, the load cell output signal input to the weighing board 24 has a substantially constant value indicating the weight of the supply material loaded on the bucket 8a.

【0061】ほぼ1回の供給量(例えば0.9m3)の
補給材をバケット8aに投入した後、計量ボタン27D
をON操作すると、上記のロードセル出力信号に基づき
バケット8a内の補給材の体積が演算・計量され、該計
量値が計量盤24に一旦記憶される。と同時に、計量盤
24からパトライトへの出力が停止されパトライトが消
灯される。
After a supply material (for example, 0.9 m 3 ) is supplied into the bucket 8 a almost once, the weighing button 27 D
Is turned on, the volume of the supply material in the bucket 8a is calculated and measured based on the load cell output signal, and the measured value is temporarily stored in the measuring board 24. At the same time, the output from the weighing board 24 to the patrol light is stopped, and the patrol light is turned off.

【0062】なお、計量ボタン27DをON操作した段
階では、まだ、補給材の計量が確定したわけではなく、
追加の補給材をバケット8aに投入して、再度計量ボタ
ン27DをON操作することで、追加された後の補給材
の重量を示すロードセル出力信号に基づき該補給材の体
積が演算・計量されて、その計量値が記憶されるように
なっている。
At the stage when the weighing button 27D is turned ON, the weighing of the replenishment material has not yet been determined.
By putting additional supply material into the bucket 8a and turning on the weighing button 27D again, the volume of the supply material is calculated and measured based on a load cell output signal indicating the weight of the added supply material. , And the measured value is stored.

【0063】計量ボタン27DをON操作して補給材を
計量したら、供給装置8のバケットシリンダー8bを作
動させて、バケット8aを傾斜(ダンプアップ)させホ
ッパー6内に補給材を投入する。バケット8aから補給
材が投入されると、ホッパー6に設けられたリミットス
イッチ23がその投入を検出して、その検出信号を計量
盤24に出力する。
When the replenishing material is measured by turning on the measuring button 27D, the bucket cylinder 8b of the supply device 8 is operated to incline (dump up) the bucket 8a and supply the replenishing material into the hopper 6. When the supply material is supplied from the bucket 8a, the limit switch 23 provided in the hopper 6 detects the supply and outputs a detection signal to the measuring board 24.

【0064】リミットスイッチ23からの検出信号が入
力されると、計量盤24で先に記憶された補給材の体積
の計量値が確定し、この計量値に基づき積算土量(1回
目の投入からの補給材体積の積算値)が演算され、積算
度量データとして記憶される。
When the detection signal from the limit switch 23 is inputted, the measured value of the volume of the replenishment material previously stored in the measuring board 24 is determined, and based on the measured value, the accumulated soil amount (from the first input) Is calculated and stored as integrated degree data.

【0065】そして、バケット8a内の補給材が全て投
入されると、供給装置8のバケットシリンダー8bが縮
動してバケット8aが元の位置に戻される(ダンプダウ
ン)。ホッパー6に供給された補給材は、ケーシング3
の周囲に沿って、或いは、ケーシング3に設けられた貫
通孔を通ってケーシング3内部に流入して、ケーシング
3の先端に落ちていく。
When all the replenishing materials in the bucket 8a are supplied, the bucket cylinder 8b of the supply device 8 is contracted and the bucket 8a is returned to the original position (dump down). The supply material supplied to the hopper 6 is
Along the periphery of the casing 3 or through a through hole provided in the casing 3 to flow into the inside of the casing 3 and fall to the tip of the casing 3.

【0066】上記のような、補給材の計量および投入を
繰り返しながらケーシング3を貫入していき、ケーシン
グ3が最深度に達した場合(図4(c))には、バケッ
ト8aのダンプアップ後に、貫入終了ボタン27BをO
N操作する(図5の)。
The casing 3 penetrates while repeating the weighing and feeding of the supply material as described above, and when the casing 3 reaches the maximum depth (FIG. 4C), after the bucket 8a is dumped up. , Press the end button 27B
N operations (FIG. 5).

【0067】この貫入終了ボタン27BがON操作によ
り、このスイッチ信号が計量盤24に入力されると、深
度計3dから入力されている深度データに基づき、計量
盤24でケーシング3の最深度と設計土量(この杭柱の
打設に必要な補給材の総量)が演算され、最深度データ
および設計土量データとして記憶される。
When the switch signal is input to the weighing panel 24 by turning on the penetration end button 27B, the maximum depth of the casing 3 is designed on the weighing panel 24 based on the depth data input from the depth gauge 3d. The soil volume (total amount of supply material necessary for placing the pillar) is calculated and stored as the maximum depth data and the design soil volume data.

【0068】ケーシング3が最大深度に達して貫入終了
ボタン27BをON操作したら、次に、ケーシング3の
引き抜き、再貫入(打ち戻し)の工程(図4(d))に
移る。即ち、ケーシング3を所定量引き抜いてケーシン
グ3の先端から補給材を地盤中に補給した後、バイブロ
ハンマ5を再び作動させて、ケーシング3を再度貫入
し、地盤中に補給した補給材を締め固める。この締め固
め具合いは、ケーシング3の先端深度計およびバイブロ
ハンマ5の電流値等を参考に判断される。
After the casing 3 has reached the maximum depth and the penetration end button 27B has been turned ON, the process proceeds to the step of pulling out the casing 3 and re-penetration (returning) (FIG. 4 (d)). That is, after the casing 3 is pulled out by a predetermined amount and replenishing material is replenished from the front end of the casing 3 into the ground, the vibratory hammer 5 is operated again to penetrate the casing 3 again and compact the replenishing material replenished in the ground. The degree of compaction is determined with reference to the tip depth meter of the casing 3 and the current value of the vibratory hammer 5.

【0069】このケーシング3の引き抜き再貫入の工程
中、計量盤24では、深度計3dから入力される深度デ
ータと、計量盤24で演算され記憶されている積算土量
データとから、ケーシング3の内部或いは周囲に残って
いる補給材の残量(ケーシング3内又は周囲の補給材の
上面の深度)が演算され、残土量インジゲータデータと
して記憶される。
During the process of pulling out and re-penetrating the casing 3, the measuring board 24 determines the casing 3 from the depth data input from the depth gauge 3 d and the integrated soil volume data calculated and stored by the measuring board 24. The remaining amount of the replenishment material remaining inside or around (the depth of the upper surface of the replenishment material in or around the casing 3) is calculated and stored as residual soil amount indicator data.

【0070】このケーシング3の引き抜き再貫入の工程
中、上記残土量インジゲータ信号に基づき施工管理を行
いながら、上記と同様に、供給装置8のバケット8a内
への補給材の投入、土木用材計量装置20によるバケッ
ト8a内の補給材の計量、並びに、バケット8aからホ
ッパー6への補給材の供給を行う。そして、ケーシング
3の引き抜き再貫入および補給材の供給を繰り返して、
積算土量が設計土量に達し、且つ、ケーシング3が地上
まで引き抜かれて、一本の杭柱の打設が終了する(図4
(e))。
During the process of pulling out and re-penetration of the casing 3, while performing construction management based on the residual soil amount indicator signal, similarly to the above, charging of the supply material into the bucket 8 a of the supply device 8, 20 measures the supply material in the bucket 8a and supplies the supply material from the bucket 8a to the hopper 6. Then, by repeating the pull-out and re-penetration of the casing 3 and the supply of the supply material,
The accumulated soil volume reaches the design soil volume, the casing 3 is pulled out to the ground, and the placing of one pile pillar is completed (FIG. 4).
(E)).

【0071】なお、杭柱の打設の終了前、積算土量が設
計土量に達する前には、ホッパー6への補給材の投入量
の最終投入調整が行われる。
Before the completion of the installation of the pile columns and before the accumulated soil volume reaches the design soil volume, the final input adjustment of the supply amount of the supply material to the hopper 6 is performed.

【0072】一本の杭柱の打設が終了したら、操作盤2
7のオールリセットボタン27AをON操作する。この
オールリセットボタン27AのON操作により、計量盤
24に記憶されている設計土量データ、積算土量デー
タ、最深度データ、残土量インジゲータデータ等のデー
タが消去されて、次の杭柱の打設に移行する。
When the placing of one pile post is completed, the operation panel 2
7 is turned on. By turning on the all-reset button 27A, data such as design soil volume data, integrated soil volume data, deepest depth data, remaining soil volume indicator data and the like stored in the weighing panel 24 are deleted, and Move to

【0073】上記のケーシング3の貫入開始から、ケー
シング3の貫入工程、ケーシング3の引き抜きおよび再
貫入工程を経て、一本の杭柱が打設終了するまで、計量
盤24からペンレコーダー26に、残土量インジゲータ
データを示す残土量インジケーター信号、設計土量デー
タを示す設計土量信号、積算土量データを示す積算土量
信号が送信される。と同時に、バイブロハンマ5の電流
計5aから電流値データを示す信号、並びに、ケーシン
グ3の深度計3dからケーシング3の深度を示す信号
が、それぞれペンレコーダー26に入力されて、ペンレ
コーダー26により、各データが記録される。
From the start of the penetration of the casing 3 to the penetrating step of the casing 3, the pulling-out of the casing 3 and the re-penetrating step, from the measuring board 24 to the pen recorder 26 until one pile post is completed. A remaining soil indicator signal indicating the remaining soil indicator data, a design soil signal indicating the designed soil data, and an integrated soil signal indicating the integrated soil data are transmitted. At the same time, a signal indicating the current value data from the ammeter 5a of the vibro hammer 5 and a signal indicating the depth of the casing 3 from the depth meter 3d of the casing 3 are input to the pen recorder 26, respectively. The data is recorded.

【0074】図6には、ペンレコーダー26により記録
される各データチャートの表示例を示す。ペンレコーダ
ー26により印字されるデータチャートには次の〜
のデータの時系列が含まれる。 バイブロハンマ5に流れる電流値データ ケーシング3の内部および周囲に残っている補給材
の残量を示す残土インジゲーターデータ、この残土イン
ジゲーターデータは、補給材の上面の深度で表される。 ケーシング3の深度データ 設計土量データ 補給材の投入量の積算値データ
FIG. 6 shows a display example of each data chart recorded by the pen recorder 26. The data chart printed by the pen recorder 26 includes the following
The time series of the data is included. Current value data flowing through vibratory hammer 5 Remaining soil indicator data indicating the remaining amount of replenishing material remaining inside and around casing 3, and the remnant soil indicator data is represented by the depth of the upper surface of the replenishing material. Casing 3 depth data Design soil volume data Replenishment material input volume integrated value data

【0075】上記の残土インジゲーターデータは、ケー
シング3の深度と、補給材の積算値データとから、計量
盤24により演算・算出されたものであり、この残土イ
ンジゲーターデータは、例えば砂面ゲージを用いてケー
シング3内部の補給材の上面を計測した場合の計測デー
タと同等のものである。つまり、この貫通孔3a,3a
…を有するケーシング3を用いた地盤改良工法では、砂
面ゲージを用いて補給材の計量を行うことは出来ない
が、計量装置20を用いた計量データから、砂面ゲージ
を用いた場合と同等のデータを得られるので、従来より
慣例的に行われている砂面ゲージを用いた工法の施工管
理をそのまま使用することが出来る。
The above-mentioned residual soil indicator data is calculated and calculated by the measuring board 24 from the depth of the casing 3 and the integrated value data of the replenishing material. The residual soil indicator data is, for example, a sand gauge. This is equivalent to the measurement data when the upper surface of the supply material inside the casing 3 is measured. That is, the through holes 3a, 3a
In the ground improvement method using the casing 3 having ..., the supply material cannot be measured using the sand surface gauge, but from the measurement data using the measuring device 20, it is equivalent to the case using the sand surface gauge. Since the above data can be obtained, it is possible to use the construction management of the construction method using a sand surface gauge, which is conventionally performed conventionally, as it is.

【0076】以上のように、この実施の形態の土木用材
計量装置20およびこの土木用材計量装置20を用いた
補給材の計量方法によれば、補給材の計量を重量の計測
によって行うので、従来のように例えば砂面ゲージを使
用して補給材投入後の体積を計測していたのに比べて、
計量の作業性および計量の精度が向上する。
As described above, according to the civil engineering material measuring device 20 of this embodiment and the supplementary material measuring method using the civil engineering material measuring device 20, the supplementary material is measured by measuring the weight. Compared to measuring the volume after supplying the replenishing material using a sand surface gauge, for example,
The workability of weighing and the accuracy of weighing are improved.

【0077】なお、この実施の形態の土木用材計量装置
20は、地盤改良工事に使用される場合に限って有用と
いうわけではなく、土木工事全般に渡って、その作業性
および計量精度の向上を期待することができる。
Note that the civil engineering material measuring device 20 of this embodiment is not only useful when used for ground improvement work, but also to improve the workability and the measurement accuracy throughout the civil engineering work. You can expect.

【0078】即ち、従来、土木工事において土木用材の
計量を行う場合、体積により計量を行っていたので、例
えば、計量を行う容器(例えばバケットやホッパーな
ど)に土木用材を積載し、表面をならすなどして計量し
ていたのに対して、この実施の形態の土木用材計量装置
20によれば、バケット8aに土木用材を載積し計量ボ
タン27Dをオン操作するだけで計量が行えるので、そ
の作業性が数段向上している。また、従来の体積による
計量の場合、計量を行う容器(例えばバケットやホッパ
ーなど)に土木用材が付着した場合、その付着分の計量
誤差は計量を重ねる度に累積していくのに対して、この
実施の形態の土木用材計量装置20によれば、風袋補正
によりその誤差を容易に除去することが出来るなど、計
量精度も数段向上している。
That is, conventionally, when weighing civil engineering materials in civil engineering work, the weighing is performed by volume. For example, the civil engineering materials are loaded on a container (for example, a bucket or a hopper) to be weighed and the surface is leveled. In contrast, according to the civil engineering material weighing device 20 of the present embodiment, since the civil engineering material is loaded on the bucket 8a and the measuring button 27D is turned on, the measurement can be performed. Workability has been improved by several steps. In addition, in the case of conventional measurement by volume, when the civil engineering material adheres to a container (for example, a bucket or a hopper) to be measured, a measurement error of the attached amount is accumulated every time measurement is repeated. According to the civil engineering material weighing device 20 of this embodiment, the measurement accuracy is improved by several steps, for example, the error can be easily removed by tare correction.

【0079】なお、本発明の土木用材計量装置は、この
実施の形態の土木用材計量装置20に限られるものでは
なく、例えば、計量手段としてのロードセル22a〜2
2cや、ノイズ除去手段としてのノイズ除去回路25r
(アナログフィルター、移動平均回路)、並びに、計量
装置20と供給装置8とが一体的に設けられている点な
ど、具体的に示した細部構造等は発明の趣旨を逸脱しな
い範囲で変更可能である。
The civil engineering material weighing device of the present invention is not limited to the civil engineering material weighing device 20 of this embodiment, but may be, for example, load cells 22a to 2 as weighing means.
2c and a noise removing circuit 25r as noise removing means
(Analog filter, moving average circuit) and the detailed structure specifically shown such that the weighing device 20 and the supply device 8 are integrally provided can be changed without departing from the spirit of the invention. is there.

【0080】また、本発明の土木用材計量方法は、この
実施の形態で示した補給材の計量方法に限られるもので
なく、例えば、ゼロ点調整やスパン調整、並びに、風袋
補正などは、本発明にとって付加的なものであるし、ま
た、最終的な計量結果を体積値で出力する点など、具体
的に示した細部方法は発明の趣旨を逸脱しない範囲で変
更可能である。
Further, the method for measuring civil engineering materials according to the present invention is not limited to the method for measuring replenishing materials shown in this embodiment. For example, zero point adjustment, span adjustment, and tare correction are performed in accordance with the present invention. The detailed method specifically shown in addition to the invention and outputting the final measurement result as a volume value can be changed without departing from the spirit of the invention.

【0081】また、この実施の形態の地盤改良工法によ
れば、補給材を土木用材計量装置20によりその重量を
計測して計量し、その後、この補給材をポッパー6に投
入するので、従来のように砂面ゲージを使用して補給材
の計量を行っていた場合に較べて、地盤改良工法の作業
効率が数段に向上する。即ち、砂面ゲージを用いて補給
材の計量を行う場合、砂面ゲージの使用中、ケーシング
内に補給材を投入することが出来ず、作業効率を低下さ
せていたのに対して、この実施の形態の地盤改良工法に
よれば、補給材の計量中、ケーシング3の貫入や引き抜
きを連続的に行えるし、その計量方法も供給装置8のバ
ケット8aに補給材を投入して計量ボタン27DをON
操作するだけなので、地盤改良工事全体の作業効率が数
段に向上する。
According to the ground improvement method of this embodiment, the replenishing material is measured and weighed by the civil engineering material measuring device 20, and then the replenishing material is put into the popper 6. As compared with the case where the supply material is measured using the sand surface gauge, the work efficiency of the ground improvement method is improved by several steps. In other words, in the case where the replenishing material is measured using the sand surface gauge, the replenishing material cannot be put into the casing during use of the sand surface gauge, and the work efficiency is reduced. According to the ground improvement method of the form, during the measurement of the supply material, the casing 3 can be continuously penetrated or pulled out, and the measurement method is also such that the supply material is put into the bucket 8a of the supply device 8, and the measurement button 27D is pressed. ON
Since only the operation is performed, the work efficiency of the entire ground improvement work is improved by several steps.

【0082】なお、この実施の形態では、複数の貫通孔
3a,3a…が設けられたケーシング3を使用し、補給
材の投入を地上面付近で行う地盤改良工法を示したが、
ケーシング3の代わりに貫通孔なしのケーシングを使用
し、該貫通孔なしのケーシングの上部に設けられたホッ
パー内に補給材を投入する方式の地盤改良工法でも、本
発明の土木用材計量装置並びに該装置を用いた補給材の
計量方法を適用することは容易である。
In this embodiment, the ground improvement method is described in which the casing 3 provided with the plurality of through holes 3a is used to supply the replenishing material near the ground surface.
In the ground improvement method of using a casing without a through-hole instead of the casing 3 and charging a supplementary material into a hopper provided at an upper portion of the casing without the through-hole, the civil engineering material measuring apparatus and the civil engineering material measuring apparatus of the present invention are also used. It is easy to apply the method of measuring the supply material using the device.

【0083】例えば、補給材は、従来のようにスキップ
バケットに積んで、ケーシング上部まで吊り上げ、その
後、ケーシング上部のホッパーに投入するとすれば、こ
の実施の形態の計量装置20と同様の計量装置を地上に
設け、スキップバケットに補給材を積載したときに、こ
のスキップバケットの重量を上記計量装置で計測するこ
とで、スキップバケットによる補給材の投入量の計量を
行ことが出来るし、また、この実施の形態で示したバケ
ット8a、ロードセル22a,22b,22cおよび基
台21と同様に、スキップバケットと計量装置(ロード
セルおよび基台)とを一体にして、計量装置(ロードセ
ルおよび基台)ごとケーシング上部まで吊り上げるよう
にしても良い。いずれにせよ、この実施の形態の地盤改
良工法と同様の効果を得ることが出来る。
For example, if the replenishing material is piled up in a skip bucket as in the prior art, lifted to the upper part of the casing, and then put into the hopper on the upper part of the casing, a weighing device similar to the weighing device 20 of this embodiment can be used. It is provided on the ground, and when the supply material is loaded on the skip bucket, by measuring the weight of the skip bucket with the weighing device, the supply amount of the supply material by the skip bucket can be measured. Similarly to the bucket 8a, the load cells 22a, 22b, 22c and the base 21 shown in the embodiment, the skip bucket and the weighing device (load cell and base) are integrated, and the weighing device (load cell and base) and the casing It may be lifted to the upper part. In any case, the same effect as the ground improvement method of this embodiment can be obtained.

【0084】[第2の実施の形態]次に、本発明の第2
の実施の形態である土木用材計量装置200およびこの
装置を用いた土木用材の計量方法について説明する。
[Second Embodiment] Next, a second embodiment of the present invention will be described.
A description will be given of a civil engineering material measuring apparatus 200 according to an embodiment of the present invention and a civil engineering material measuring method using this apparatus.

【0085】図7(a)には、この実施の形態の土木用
材計量装置200の構成図を示す。図7(b)は、基台
21およびロードセル22a〜22dの上面図である。
FIG. 7A is a configuration diagram of a civil engineering material measuring apparatus 200 according to this embodiment. FIG. 7B is a top view of the base 21 and the load cells 22a to 22d.

【0086】この実施の形態の土木用材計量装置200
は、第4のロードセル22dとそれに付随する新たな構
成が加わった点で、第1の実施の形態の土木用材計量装
置20と異なり、その他の構成は、第1の実施の形態の
土木用材計量装置20とほぼ同様のものである。従っ
て、第1の実施の形態の土木用材計量装置20と同様の
構成については、同符号を振って説明を省力し、異なる
点についてのみ説明を行う。
[0086] Civil engineering material measuring device 200 of this embodiment.
Is different from the civil engineering material weighing device 20 of the first embodiment in that a fourth load cell 22d and a new configuration accompanying the fourth load cell 22d are added, and the other configuration is different from the civil engineering material weighing device of the first embodiment. It is almost the same as the device 20. Therefore, the same components as those of the civil engineering material weighing device 20 of the first embodiment are denoted by the same reference numerals, and description thereof will be omitted, and only different points will be described.

【0087】この実施の形態の土木用材計量装置200
は、土木用材の計量と共に該土木用材とほぼ同様の振動
が掛かる状態でダミーの測定を行い、このダミーの測定
の測定値に基づき土木用材の計量値を補正する機能を有
するもので、基台21、第1〜第3のロードセル22a
〜22c、補助重量計測手段としての第4のロードセル
22d、動歪みアンプ250、計量盤240、並びに、
図示略のペンレコーダー26や操作ボックス27等から
構成されている。
[0107] Civil engineering material measuring apparatus 200 of this embodiment
Has a function of performing dummy measurement in a state where substantially the same vibration as the civil engineering material is applied together with the measurement of the civil engineering material, and correcting the measured value of the civil engineering material based on the measured value of the dummy measurement. 21, first to third load cells 22a
To 22c, a fourth load cell 22d as auxiliary weight measuring means, a dynamic strain amplifier 250, a weighing board 240, and
It comprises a pen recorder 26, an operation box 27 and the like, not shown.

【0088】第4のロードセル22dは、第1〜第3の
ロードセル22a〜22cと同様の特性を有するもの
で、第1〜第3のロードセル22a〜22cと同様に基
台21に設けられている。この第4のロードセル22d
には、既知の重量負荷が掛けられており、土木工事に伴
う振動から生じる上記既知の重量の荷重の変化に応じ
て、第4のロードセル22dの変位量が変化するように
なっている。ここでは、第4のロードセル22dに負荷
される荷重は「0トン」つまり無負荷の状態に設定さ
れ、土木工事の振動に伴い第4のロードセル22dの自
重から生じる荷重の変化に応じて、第4のロードセル2
2dの変位量が変化するようになっている。
The fourth load cell 22d has the same characteristics as the first to third load cells 22a to 22c, and is provided on the base 21 similarly to the first to third load cells 22a to 22c. . This fourth load cell 22d
Is subjected to a known weight load, and the amount of displacement of the fourth load cell 22d changes in accordance with a change in the load of the known weight caused by vibration caused by civil engineering work. Here, the load applied to the fourth load cell 22d is set to “0 ton”, that is, a state of no load, and the fourth load cell 22d is set to a state of no load according to a change in load caused by the weight of the fourth load cell 22d due to the vibration of the civil engineering work. 4 load cell 2
The displacement amount of 2d changes.

【0089】なお、第4のロードセル22dに有量の重
量を負荷させるようにしても良く、そうすることで、補
正内容を実際により適したものにすることが出来る。ま
た、第4のロードセル22dは、第1〜第2のロードセ
ル22a〜22cとほぼ同様の振動が掛けられる状態に
あれば、その特性や配置は特に限定されるものでない。
The fourth load cell 22d may be loaded with a certain amount of weight, so that the contents of correction can be made more suitable in practice. The characteristics and arrangement of the fourth load cell 22d are not particularly limited as long as the fourth load cell 22d can be subjected to substantially the same vibration as the first and second load cells 22a to 22c.

【0090】動歪みアンプ250は、第1の実施の形態
の動歪みアンプ25と同様に、第1〜第3のロードセル
22a〜22cの変位量を電気信号に変換して出力する
他、第4のロードセル22dに対しても同様にその変位
量を電気信号に変換して出力するようになっている。
Similarly to the dynamic distortion amplifier 25 of the first embodiment, the dynamic distortion amplifier 250 converts the displacement of the first to third load cells 22a to 22c into electric signals and outputs the electric signals. Similarly, the displacement amount is converted into an electric signal and output to the load cell 22d.

【0091】この動歪みアンプ250には、ノイズ除去
手段および補助ノイズ除去手段としてのノイズ除去回路
250rが設けられている。このノイズ除去回路250
rは、第1〜第3のロードセル22a〜22cの変位量
を示す信号に対して、第1の実施の形態のノイズ除去回
路25rと同様のノイズ除去の作用を及ぼすと共に、第
4のロードセル22dの変位量を示す信号に対しても、
同様のノイズ除去の作用を及ぼすようになっている。第
1〜第4のロードセル22a〜22dの変位量を示す電
気信号は、これらノイズ除去回路250rによりノイズ
が除去された上で、第1〜第4のロードセル出力信号と
して計量盤240に出力される。
The dynamic distortion amplifier 250 is provided with a noise removing circuit 250r as noise removing means and auxiliary noise removing means. This noise removal circuit 250
r exerts the same noise elimination function as the noise elimination circuit 25r of the first embodiment on a signal indicating the amount of displacement of the first to third load cells 22a to 22c, and the fourth load cell 22d For the signal indicating the amount of displacement of
The same effect of noise removal is provided. The electric signals indicating the displacement amounts of the first to fourth load cells 22a to 22d are output to the weighing panel 240 as first to fourth load cell output signals after the noise is removed by the noise removing circuit 250r. .

【0092】計量盤240は、第1の実施の形態の計量
盤24の機能に加え、補正手段としての補正モジュール
を備えてなる。補正モジュールは、第4のロードセル2
2dから出力される第4のロードセル出力信号に基づい
て、バケット8a内に積載された土木用材の計量値を次
のように補正するようになっている。
The weighing board 240 includes a correction module as a correcting means in addition to the functions of the weighing board 24 of the first embodiment. The correction module includes a fourth load cell 2
Based on the fourth load cell output signal output from 2d, the measured value of the civil engineering material loaded in the bucket 8a is corrected as follows.

【0093】ΔW4 : 第4のロードセル出力信号が
示す重量計測値 W0 : 第1〜第3のロードセル出力信号が示すバケ
ット内に積載された計測対象物の重量計測値 WR : バケット内の計測対象物の補正された重量計
測値 として、 WR = W0 − ΔW4
ΔW4: Weight measurement value indicated by the fourth load cell output signal W0: Weight measurement value of the measurement object loaded in the bucket indicated by the first to third load cell output signals WR: Measurement object in the bucket WR = W0−ΔW4 as the corrected weight measurement value of

【0094】なお、第4のロードセル出力信号に基づく
補正方法は、上記のものに限られるものではなく、例え
ば、第4のロードセル22dに有量の重量を負荷させた
場合には、 W4’: 第4のロードセル出力信号が示す重量計測値 W4 : 第4のロードセル22dに負荷される重量の
真値 W0 : 第1〜第3のロードセル出力信号が示すバケ
ット内に積載された計測対象物の重量計測値 WR : バケット内の計測対象物の補正された重量計
測値 として、WR = W0 × ( W4 / W4’)
といった補正や、WR = W0 + ( W4 −
W4’)といった補正、或いは、上記の補正を重みをつ
けて合成した補正など、種々の補正処理が有り得る。ま
た、実験により、第4のロードセル出力信号に応じた適
切な補正量を導き出して、導出した補正式に基づき補正
する方式も有り得る。
The correction method based on the fourth load cell output signal is not limited to the above method. For example, when a large weight is loaded on the fourth load cell 22d, W4 ': Weight measurement value indicated by fourth load cell output signal W4: True value of weight applied to fourth load cell 22d W0: Weight of measurement target loaded in bucket indicated by first to third load cell output signals Measurement value WR: WR = W0 × (W4 / W4 ′) as a corrected weight measurement value of the measurement object in the bucket.
And WR = W0 + (W4−
There may be various correction processes such as a correction such as W4 ′) or a correction obtained by combining the above corrections with weights. Further, there is a method in which an appropriate correction amount corresponding to the fourth load cell output signal is derived through an experiment, and the correction amount is corrected based on the derived correction expression.

【0095】次にこの実施の形態の土木用材計量装置2
00を用いて行う土木用材計量方法について説明する。
この実施の形態の土木用材計量装置200を用いて土木
用材の計量を行うには、第1の実施の形態と同様、予
め、振動のない静かなところでゼロ調整とスパン調整、
並びに、計量する土木用材の単位体積重量の計測を行っ
ておく。そして、土木工事中において、先ず、風袋ボタ
ン27Eをオン操作して、風袋補正を行った後、計量す
る土木用材をバケット8a内に積載する。
Next, the civil engineering material measuring device 2 of this embodiment
A method for measuring civil engineering materials using the method No. 00 will be described.
In order to measure civil engineering materials using the civil engineering material measuring device 200 of this embodiment, as in the first embodiment, zero adjustment and span adjustment are performed in advance in a quiet place without vibration.
In addition, the unit volume weight of the civil engineering material to be measured is measured. Then, during the civil engineering work, first, the tare button 27E is turned on to correct the tare, and then the civil engineering material to be weighed is loaded in the bucket 8a.

【0096】土木用材をバケット8a内に積載すると、
その土木用材の重量が振動(土木工事に伴う振動)によ
る荷重の変化も合わせて第1〜第3のロードセル22a
〜22cに負荷され、その荷重に応じて第1〜第3のロ
ードセル22a〜22cに変位が生じる。一方、第4の
ロードセル22dでは、自重と振動による荷重の変化が
生じて、その荷重に応じた変位が生じている。そして、
それら第1〜第4のロードセル22a〜22dの変位が
動歪みアンプ250で電気信号に変換されると共に、ノ
イズ除去回路250rにより同様のノイズ除去処理が施
されて、交流成分(1Hzの低周波から高周波成分ま
で)の除去された第1〜第4のロードセル信号が計量盤
240に出力される。
When the civil engineering material is loaded in the bucket 8a,
The weight of the civil engineering material is changed in accordance with the load due to vibration (vibration accompanying civil engineering work) together with the first to third load cells 22a.
To 22c, and the first to third load cells 22a to 22c are displaced according to the load. On the other hand, in the fourth load cell 22d, a change in load occurs due to its own weight and vibration, and a displacement occurs according to the load. And
The displacements of the first to fourth load cells 22a to 22d are converted into electric signals by the dynamic distortion amplifier 250, and the same noise removal processing is performed by the noise removal circuit 250r. The first to fourth load cell signals from which high-frequency components have been removed are output to the weighing panel 240.

【0097】これらの内、第1〜第3のロードセル出力
信号は、計測している土木用材の、ほぼ静時における重
量を示す信号となっており、第4のロードセル出力信号
は、静時における計測値と振動を伴った場合の計測値と
のずれに関する情報を与える信号となっている。
Of these, the first to third load cell output signals are signals indicating the weight of the civil engineering material being measured substantially at rest, and the fourth load cell output signal is at rest. The signal is a signal that gives information on a difference between the measured value and the measured value accompanied by vibration.

【0098】土木用材をバケット8aに積載して、計量
ボタン27Dをオン操作すると、計量盤240に上記第
1〜第4のロードセル出力信号が読み込まれて、バケッ
ト8a内の土木用材の計量が行われる。即ち、第1〜第
3のロードセル出力信号から上記土木用材の重量測定値
が演算され、次いで、第4のロードセル出力信号に基づ
き上記補正モジュールにより上記に示した補正処理が行
われ、その後、補正された重量測定値から上記土木用材
の体積値が演算・記憶される。
When the civil engineering material is loaded on the bucket 8a and the weighing button 27D is turned on, the first to fourth load cell output signals are read into the measuring board 240, and the civil engineering material in the bucket 8a is measured. Will be That is, the weight measurement value of the civil engineering material is calculated from the first to third load cell output signals, and then the above-described correction processing is performed by the correction module based on the fourth load cell output signal. The volume value of the civil engineering material is calculated and stored from the measured weight value.

【0099】計量ボタン27Dのオン操作後は、第1の
実施の形態と同様、それで計量を確定させてよければ、
供給装置8を作動させてバケット8a内の土木用材を投
入し、その投入を感知したリミット信号により、先に記
憶されていた土木用材の体積値が計量値として確定す
る。
After the weighing button 27D is turned on, as in the case of the first embodiment, if the weighing can be confirmed with the operation,
The supply device 8 is operated to input the civil engineering material in the bucket 8a, and the volume value of the civil engineering material previously stored is determined as the measured value by the limit signal detected by the input.

【0100】以上のように、この実施の形態の土木用材
計量装置200および土木用材計量方法によれば、第1
の実施の形態の土木用材計量装置20および土木用材計
量方法による効果に加え、第4のロードセル22dや計
量盤240中の補正モジュールにより、振動に伴う誤差
を補正することができるので、更に精度の高い計量を行
うことが可能となる。
As described above, according to the civil engineering material measuring apparatus 200 and the civil engineering material measuring method of this embodiment, the first
In addition to the effects of the civil engineering material measuring device 20 and the civil engineering material measuring method of the embodiment, the error caused by the vibration can be corrected by the fourth load cell 22d and the correction module in the measuring board 240, so that the accuracy is further improved. High weighing can be performed.

【0101】なお、この実施の形態の土木用材計量装置
200を、第1の実施の形態と同様に地盤改良工事に使
用することで、更に精度の高い補給材の計量が行え、延
いては、地盤改良工事全体の工程管理、品質管理の確実
性の向上を図ることが出来る。
By using the civil engineering material measuring apparatus 200 of this embodiment for ground improvement work in the same manner as in the first embodiment, it is possible to measure the supply material with higher accuracy. The process control and quality control of the entire ground improvement work can be improved.

【0102】[0102]

【発明の効果】請求項1記載の発明によれば、土木用材
の計量を重量の計測により行うので、従来のように体積
を計測して計量していたのに比べて、計量の作業性が向
上すると共に、計量の精度が向上する。また、ノイズ除
去手段により振動に伴うノイズを除去して計量が行える
ので、振動を伴う土木工事においても、正確な計量を行
うことが出来る。
According to the first aspect of the present invention, since the civil engineering materials are measured by measuring the weight, the workability of the measuring is improved as compared with the conventional method of measuring and measuring the volume. As well as the accuracy of weighing is improved. In addition, since noise can be measured by removing noise due to vibration by the noise removing means, accurate measurement can be performed even in civil engineering work involving vibration.

【0103】請求項2記載の発明によれば、補助重量計
測手段と補助ノイズ除去手段により、土木用材の重量計
測と同様の条件で既知の重量の計測を行い、その計測値
と本来の重量との差異に基づき、土木用材の計測結果か
ら振動による計量誤差を補正することができるので、強
い振動を伴う土木工事などにおいても精度よく計量が行
え有用である。
According to the second aspect of the present invention, the known weight is measured by the auxiliary weight measuring means and the auxiliary noise removing means under the same conditions as the weight measurement of the civil engineering material, and the measured value is compared with the original weight. Based on this difference, the measurement error due to vibration can be corrected from the measurement result of the civil engineering material, so that the measurement can be performed accurately even in civil engineering work involving strong vibration and is useful.

【0104】請求項3と4に記載の発明によれば、請求
項1と2に記載の発明による効果と同様の効果をそれぞ
れ奏する。
According to the third and fourth aspects of the invention, the same effects as those of the first and second aspects of the invention can be obtained.

【0105】請求項5記載の発明によれば、ケーシング
に投入する補給材を、上記請求項1記載の土木用材計量
装置を用いて、その重量を計測して行うので、次の、
の例に示すように、従来の砂面ゲージを用いた計量に
比べて、その作業性や計量の精度が向上し、延いては、
地盤改良工事全体の作業効率の向上、並びに、品質の向
上を図ることが出来る。 従来の砂面ゲージを用いた地盤改良工法では、砂面
ゲージでの計測中はケーシングへの補給材の投入が行え
ず、作業効率の低下を招いていたのに対して、この発明
の地盤改良工法では、補給材の計量と補給材の投入とを
連続して行うことが出来ると共に、土木用材計量装置に
よる計量中、ケーシングの引き抜き又は打ち戻し(振動
を含む)を平行して行うことが出来る。つまり、地盤中
へのケーシングの貫入から引き抜きおよび打ち戻しを、
絶え間なく行うことが可能であり、作業効率が飛躍的に
向上する。 砂面ゲージを使用した工法では、補給材の投入後に
該投入量を計量するため、補給材の投入量を正確に制御
するのが困難であるといった問題があったのに対して、
この発明の工法では、補給材をケーシング内に投入する
前にその計量を行うので、補給材の投入量の正確な計測
および制御を行うことができる。故に、地盤改良工事の
品質の向上を図ることが出来る。
According to the fifth aspect of the present invention, the weight of the replenishing material to be put into the casing is measured by using the civil engineering material measuring device according to the first aspect of the present invention.
As shown in the example, compared to conventional weighing using a sand gauge, the workability and accuracy of weighing are improved,
It is possible to improve the work efficiency and the quality of the entire ground improvement work. In the conventional soil improvement method using a sand surface gauge, while the measurement with the sand surface gauge did not allow the supply of replenishing material to the casing, resulting in a decrease in work efficiency, the ground improvement method of the present invention In the construction method, the measurement of the replenishment material and the supply of the replenishment material can be performed continuously, and during the measurement by the civil engineering material measuring device, the casing can be pulled out or knocked back (including vibration) in parallel. . In other words, pulling out and punching back from the penetration of the casing into the ground,
It can be performed continuously, and work efficiency is dramatically improved. In the construction method using the sand surface gauge, since the amount of the supply material is measured after the supply material is supplied, there is a problem that it is difficult to accurately control the supply amount of the supply material,
According to the construction method of the present invention, since the replenishing material is measured before it is charged into the casing, it is possible to accurately measure and control the amount of the replenishing material. Therefore, the quality of the ground improvement work can be improved.

【0106】請求項6記載の発明によれば、比較的太い
ケーシングであっても補給材を円滑に地盤中に補給する
ことが出来ると共に、補給材をケーシング内部に投入す
る作業が、常に地表面において行えるという効果を奏す
る地盤改良工法において、従来の砂面ゲージを用いた計
量では、砂面ゲージが補給材に埋まってしまい、うまく
計量できなかったのに対して、この発明によれば、補給
材を精度良く計量できると共に、請求項5記載の地盤改
良工法と同様、計量工程の作業性や計量の精度が向上
し、延いては、地盤改良工事全体の作業効率の向上、並
びに、品質の向上を図ることが出来る。
According to the sixth aspect of the invention, even if the casing is relatively thick, the replenishing material can be smoothly supplied to the ground, and the operation of putting the replenishing material into the casing always requires the ground surface. According to the present invention, in the ground improvement method having an effect that can be performed, the sand surface gauge was buried in the replenishing material in the measurement using the conventional sand surface gauge, and the measurement was not successfully performed. In addition to being able to accurately measure the material, the workability of the measuring process and the accuracy of the measurement are improved as in the case of the ground improvement method according to claim 5, thereby improving the work efficiency of the entire ground improvement work and improving the quality. Can be improved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の地盤改良工法を実施する地盤改良装置
の概略構成を示す概観図である。
FIG. 1 is a schematic view showing a schematic configuration of a ground improvement apparatus for implementing a ground improvement method of the present invention.

【図2】図1の地盤改良装置における補給材の供給装置
の付近の詳細を示すもので、(a)はその側面図、
(b)は上面図、(c)は供給装置が作動した状態の側
面図である。
2A and 2B show details in the vicinity of a supply device of a replenishing material in the ground improvement device of FIG. 1, wherein FIG.
(B) is a top view, and (c) is a side view in a state where the supply device is operated.

【図3】本発明の第1の実施の形態の土木用材計量装置
のシステム構成を示す構成図である。
FIG. 3 is a configuration diagram showing a system configuration of the civil engineering material weighing device according to the first embodiment of the present invention.

【図4】本発明の地盤改良工法の概略一連の施工手順
(a)〜(e)を示した模式図である。
FIG. 4 is a schematic view showing a schematic series of construction procedures (a) to (e) of the ground improvement method of the present invention.

【図5】図4の地盤改良工法の中で行われる本発明の特
徴である補給材の計量方法の一連の手順を示した模式図
である。
FIG. 5 is a schematic diagram showing a series of procedures of a method of measuring a supply material, which is a feature of the present invention, performed in the ground improvement method of FIG.

【図6】図3のペンレコーダーにより印字・出力された
チャート図の一例である。
FIG. 6 is an example of a chart diagram printed and output by the pen recorder of FIG. 3;

【図7】本発明の第2の実施の形態の土木用材計量装置
のシステム構成を示すもので、(a)はその構成図、
(b)は基台およびロードセルを上方から観た上面図で
ある。
FIG. 7 shows a system configuration of a civil engineering material measuring apparatus according to a second embodiment of the present invention, wherein (a) is a configuration diagram thereof,
(B) is a top view of the base and the load cell viewed from above.

【図8】従来の土木工事における土木用材の計量に関す
る問題点を説明するためのもので、(a)は従来の地盤
改良工法を実施する地盤改良装置の概観図、(b)は従
来の地盤改良工法で行われる補給材の計量方法を示す模
式図である。
8A and 8B are diagrams for explaining a problem related to the measurement of civil engineering materials in a conventional civil engineering work, in which FIG. 8A is a schematic view of a ground improvement device that performs a conventional ground improvement method, and FIG. It is a schematic diagram which shows the measuring method of the replenishment material performed by the improvement method.

【符号の説明】[Explanation of symbols]

1 地盤改良装置 3 ケーシング 3a… ケーシングに設けられた複数の貫通孔 8 供給装置 20 土木用材計量装置(第1の実施の形態) 21 基台 22a〜22c 第1〜第3のロードセル(重量計測手
段) 24 計量盤 25 動歪みアンプ 25r ノイズ除去回路(ノイズ除去手段) 26 ペンレコーダー 27 操作ボックス 200 土木用材計量装置(第2の実施の形態) 22d 第4のロードセル(補助重量計測手段) 240 計量盤(第2の実施の形態:内部に補正手段
としての補正モジュールを含む。) 250 動歪みアンプ(第2の実施の形態) 250r ノイズ除去回路(第2の実施の形態:補助ノ
イズ除去手段を含んでいる。)
DESCRIPTION OF SYMBOLS 1 Ground improvement device 3 Casing 3a ... Plural through-holes provided in the casing 8 Supply device 20 Civil engineering material measuring device (1st Embodiment) 21 Base 22a-22c 1st-3rd load cell (weight measuring means) 24 weighing board 25 dynamic distortion amplifier 25r noise elimination circuit (noise elimination means) 26 pen recorder 27 operation box 200 civil engineering material weighing device (second embodiment) 22d fourth load cell (auxiliary weight measuring means) 240 weighing board (Second Embodiment: Includes a correction module as a correction unit inside.) 250 Dynamic Distortion Amplifier (Second Embodiment) 250r Noise Removal Circuit (Second Embodiment: Includes Auxiliary Noise Removal Unit) In.)

───────────────────────────────────────────────────── フロントページの続き (72)発明者 森田 研志 大阪府大阪市中央区高麗橋4丁目1番1号 東洋建設株式会社内 (72)発明者 杉本 篤史 大阪府大阪市中央区高麗橋4丁目1番1号 東洋建設株式会社内 ──────────────────────────────────────────────────続 き Continuing from the front page (72) Inventor Kenshi Morita 4-1-1 Komyobashi, Chuo-ku, Osaka-shi, Osaka Inside Toyo Construction Co., Ltd. (72) Inventor Atsushi Sugimoto 4-1-1 Komyobashi, Chuo-ku, Osaka-shi, Osaka No. 1 Toyo Construction Co., Ltd.

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 土木工事において、当該土木工事に使用
される土木用材の計量を行う土木用材計量装置であっ
て、 土木用材の重量を土木工事に伴う振動から生じる荷重の
変化も合わせて計測する重量計測手段と、 この重量計測手段による計測結果を時系列的に取り込
み、この計測結果の時系列から前記振動に伴うノイズを
除去するノイズ除去手段とを備え、 前記ノイズ除去手段によりノイズの除去された計測結果
に基づき前記土木用材の計量を行うことを特徴とする土
木用材計量装置。
1. A civil engineering material measuring device for measuring civil engineering materials used in the civil engineering work, wherein the weight of the civil engineering materials is measured together with a change in a load caused by vibration accompanying the civil engineering work. A weight measuring unit; and a noise removing unit that fetches a measurement result of the weight measuring unit in a time series and removes noise accompanying the vibration from the time series of the measurement result, wherein the noise is removed by the noise removing unit. And measuring the civil engineering material based on the measurement result.
【請求項2】 前記土木用材の計測とほぼ同時に該土木
用材とほぼ同様の振動が掛かる状態で既知の重量の計測
を行う補助重量計測手段と、 この補助重量計測手段の計測結果から前記ノイズ除去手
段と同様のノイズ除去を行う補助ノイズ除去手段と、 この補助ノイズ除去手段によりノイズの除去された既知
の重量の計測結果と、当該既知の重量の本来の値との差
異に基づき、前記土木用材の計測結果を補正する補正手
段とを備えたことを特徴とする請求項1記載の土木用材
計量装置。
2. An auxiliary weight measuring means for measuring a known weight under substantially the same vibration as that of the civil engineering material at substantially the same time as the measurement of the civil engineering material, and the noise removal from the measurement result of the auxiliary weight measuring means. Auxiliary noise removing means for removing noise similar to the means; and a measurement result of a known weight from which noise has been removed by the auxiliary noise removing means and a difference between an original value of the known weight and the civil engineering material. The civil engineering material weighing device according to claim 1, further comprising a correction unit configured to correct the measurement result.
【請求項3】 土木工事において、当該土木工事に使用
される土木用材の計量を行う土木用材計量方法であっ
て、 土木用材の重量を土木工事に伴う振動により生じる荷重
の変化も合わせて計測する計測処理と、 この計測処理により得られた計測結果を時系列的に取り
込みこの計測結果の時系列から前記振動に伴うノイズを
除去するノイズ除去処理とを行い、 このノイズ除去処理によりノイズの除去された計測結果
に基づき前記土木用材の計量を行うこと特徴とする土木
用材計量方法。
3. A civil engineering material weighing method for weighing civil engineering material used in the civil engineering work, wherein the weight of the civil engineering material is measured together with a change in a load caused by vibration accompanying the civil engineering work. A measurement process and a noise removal process for removing the noise accompanying the vibration from the time series of the measurement results obtained by the measurement process in a time-series manner are performed, and the noise is removed by the noise removal process. And measuring the civil engineering material based on the measurement result.
【請求項4】 前記土木用材の計測とほぼ同時に前記土
木用材とほぼ同様の振動が掛かる状態で既知の重量の計
測を行う補助計測処理と、 この補助計測処理により得られた計測結果から前記ノイ
ズ除去処理と同様のノイズ除去を行う補助ノイズ除去処
理と、 この補助ノイズ除去処理によりノイズの除去された既知
の重量の計測結果と、当該既知の重量の本来の値との差
異に基づき、前記土木用材の計測結果を補正する補正処
理とを加えたことを特徴とする請求項3記載の土木用材
計量方法。
4. An auxiliary measurement process for measuring a known weight in a state where substantially the same vibration as that of the civil engineering material is applied substantially simultaneously with the measurement of the civil engineering material, and the noise obtained from the measurement result obtained by the auxiliary measurement process. An auxiliary noise elimination process for performing the same noise elimination as the elimination process; and a measurement result of a known weight from which noise has been eliminated by the auxiliary noise elimination process, and a difference between the original value of the known weight and the civil engineering 4. The method for measuring civil engineering materials according to claim 3, further comprising a correction process for correcting a measurement result of the material.
【請求項5】 ケーシングを地盤に貫入し、該ケーシン
グ内に投入された地盤を改良するための補給材を該ケー
シングを引き抜きながら地盤中に補給し、該ケーシング
を引き抜く過程で該ケーシングを打ち戻すか振動させて
地盤中に補給した前記補給材を締め固め、地盤中に締め
固められた前記補給材の杭柱を打設する地盤改良工法に
おいて、 前記補給材の1回分の投入量を請求項1記載の土木用材
計量装置を用いて計量し、その後、当該補給材を前記ケ
ーシング内に投入することを特徴とする地盤改良工法。
5. A casing penetrates into the ground, and a supplementary material for improving the ground introduced into the casing is supplied into the ground while pulling out the casing, and the casing is beaten back in the process of pulling out the casing. In the ground improvement method of compacting the supplementary material supplied into the ground by vibrating or shaking, and placing a pile pillar of the supplementary material compacted in the ground, an input amount of the supplementary material for one time is claimed. A ground improvement method, comprising: weighing using the civil engineering material weighing device according to (1), and then charging the supplementary material into the casing.
【請求項6】 ケーシング外部からケーシング内部に通
じる貫通孔を複数有した中空のケーシングを地盤に貫入
し、地上から該ケーシングの周辺に地盤を改良するため
の補給材を投入すると共に、この補給材の一部をケーシ
ングに設けた貫通孔を通じてケーシング内部に流入さ
せ、該ケーシングを引き抜きながら該ケーシングの先端
から前記補給材を地盤中に補給し、該ケーシングを引き
抜く過程で該ケーシングを打ち戻すか振動させて地盤中
に補給した前記補給材を締め固め、地盤中に締め固めら
れた前記補給材の杭柱を打設する地盤改良工法におい
て、 前記補給材の1回分の投入量を請求項1記載の土木用材
計量装置を用いて計量し、その後、当該補給材を前記ケ
ーシングに投入することを特徴とする地盤改良工法。
6. A hollow casing having a plurality of through holes extending from the outside of the casing to the inside of the casing penetrates the ground, and a replenishing material for improving the ground is supplied from the ground to the periphery of the casing. Is supplied into the casing through a through-hole provided in the casing, the supplementary material is supplied into the ground from the tip of the casing while the casing is pulled out, and the casing is knocked back or vibrated in the process of pulling out the casing. The ground improvement method of compacting the replenishing material replenished in the ground and placing a pile of the replenishing material compacted in the ground, wherein the input amount of the replenishing material for one time is added. Weighing using a civil engineering material weighing device, and then charging the supplementary material into the casing.
JP3925497A 1997-02-24 1997-02-24 Device and method for metering material for construction and ground improvement method Pending JPH10239141A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3925497A JPH10239141A (en) 1997-02-24 1997-02-24 Device and method for metering material for construction and ground improvement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3925497A JPH10239141A (en) 1997-02-24 1997-02-24 Device and method for metering material for construction and ground improvement method

Publications (1)

Publication Number Publication Date
JPH10239141A true JPH10239141A (en) 1998-09-11

Family

ID=12548014

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3925497A Pending JPH10239141A (en) 1997-02-24 1997-02-24 Device and method for metering material for construction and ground improvement method

Country Status (1)

Country Link
JP (1) JPH10239141A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002286534A (en) * 2001-03-28 2002-10-03 Chubu Regional Bureau Ministry Of Land Infrastructure & Transport Outflowing sediment observation system and device therefor
JP2016223133A (en) * 2015-05-29 2016-12-28 株式会社ガイナ Construction method of filler pile, and excavation head used therewith
JP2020204153A (en) * 2019-06-14 2020-12-24 株式会社不動テトラ Sand material supply method for sand pile creation method
CN115012440A (en) * 2022-06-24 2022-09-06 福建全顺计量检测有限公司 Foundation construction method for pier-type installation for weighing apparatus calibration

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002286534A (en) * 2001-03-28 2002-10-03 Chubu Regional Bureau Ministry Of Land Infrastructure & Transport Outflowing sediment observation system and device therefor
JP4721207B2 (en) * 2001-03-28 2011-07-13 国土交通省中部地方整備局長 Runoff sediment observation system, runoff sediment measurement device, and sediment separator
JP2016223133A (en) * 2015-05-29 2016-12-28 株式会社ガイナ Construction method of filler pile, and excavation head used therewith
JP2020204153A (en) * 2019-06-14 2020-12-24 株式会社不動テトラ Sand material supply method for sand pile creation method
CN115012440A (en) * 2022-06-24 2022-09-06 福建全顺计量检测有限公司 Foundation construction method for pier-type installation for weighing apparatus calibration

Similar Documents

Publication Publication Date Title
Shiraishi Variation in Bearing Capacity Factors of Dense Sane Assessed by Model Loading Tests
Tzang et al. Laboratory flume studies on monochromatic wave-fine sandy bed interactions: Part 1. Soil fluidization
CN109778927A (en) A kind of pile foundation autobalanced detection system and method for load-compensating
CN108505548B (en) Pile-bearing type embankment pile-soil load ratio test device and test method
CN108661091A (en) A kind of in due course test device of Deep Plate Load Test and test method
Schneider et al. Asimplified weighing lysimeter for monolithic or reconstructed soils
JPH10239141A (en) Device and method for metering material for construction and ground improvement method
JP3413374B2 (en) In-situ pile tester
Filz et al. Earth pressures due to compaction: comparison of theory with laboratory and field behavior
CN112255064B (en) Method for testing relative density of coarse soil and measuring and calculating rolling parameters
Noorany 3 Iraj Noorany,'William S. Gardner, 2 David J. Corley, and James L. Brown* Variability in Field Density Tests
CN208251186U (en) A kind of Piled Embankments stake soil loading ratio experimental rig
JP2003155736A (en) Method for discriminating support force of back filled soil and device therefor
CN112359887A (en) Shallow foundation bearing capacity test device and method based on large equipment
CN212254953U (en) Earthwork backfill compactness detection device
Klosky Behavior of composite granular materials and vibratory helical anchors
CN115492173A (en) On-site testing method for relative density test of inviscid coarse-grained soil
CN117468446A (en) Stirring pile construction method and control system
JP4111263B2 (en) Specimen generation system and method for cone index measurement and cone index measurement system and method
USRE33176E (en) Method for measuring density of a bulk material in a stockpile
JPH10266181A (en) Underwater ground improvement work and its improved underwater bottom
Lee et al. A Study on the Behavior of Soft Clay Foundation Reinforced with Soil Cement Piles by Centrifugal Model Tests
McManus et al. Constant force shaking of a group of four drilled shafts
SU1148924A1 (en) Apparatus for determining deformation properties of foundation soils at a depth
McNamara et al. The influence of enhanced excavation base stiffness on prop loads and ground movements during basement construction

Legal Events

Date Code Title Description
A977 Report on retrieval

Effective date: 20040823

Free format text: JAPANESE INTERMEDIATE CODE: A971007

A131 Notification of reasons for refusal

Effective date: 20041214

Free format text: JAPANESE INTERMEDIATE CODE: A131

A02 Decision of refusal

Effective date: 20050405

Free format text: JAPANESE INTERMEDIATE CODE: A02