JPH10231700A - Method for building tunnel timbering - Google Patents
Method for building tunnel timberingInfo
- Publication number
- JPH10231700A JPH10231700A JP9049869A JP4986997A JPH10231700A JP H10231700 A JPH10231700 A JP H10231700A JP 9049869 A JP9049869 A JP 9049869A JP 4986997 A JP4986997 A JP 4986997A JP H10231700 A JPH10231700 A JP H10231700A
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- bag
- timbering
- shoring
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明はトンネル支保工の建
て込み方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for erection of a tunnel supporter.
【0002】[0002]
【従来の技術】近年、トンネル工事においては、上部に
構造物があったり、被りが薄い崩壊性地山での構築が多
くなっている。このような施工の場合、地山の先行緩み
の防止や切羽・天端の崩壊を防止する目的で先受け工法
が採用されている。2. Description of the Related Art In recent years, in tunnel construction, there has been an increasing number of constructions on collapsed soils having a structure on the top or a thin covering. In the case of such a construction, a precedent construction method is adopted for the purpose of preventing the advance loosening of the ground and the collapse of the face and the top end.
【0003】先受け工法は、図3に示すように、トンネ
ルの掘削断面外周に沿って複数の先受け鋼材aを切羽前
方に打ち込み、それらの先受け鋼材a群の内側に、鋼ア
−チ支保工b等を建て込んで掘削を行う方法である。As shown in FIG. 3, in the pre-receiving method, a plurality of pre-receiving steel members "a" are driven in front of the cutting face along the outer periphery of the excavated cross section of the tunnel, and a steel arch is inserted inside the pre-receiving steel members "a" group. This is a method of digging by shoring a support b or the like.
【0004】また従来は、この先受け工法において、支
保工bを建て込んだ後に、支保工bの外周面と地山との
間隙に袋体cを押し込み、この袋体c内にモルタルdを
充填して膨脹させ、周囲地山にプレロ−ドを導入する方
法も行われている。Conventionally, in this prior receiving method, after the support b is erected, the bag c is pushed into the gap between the outer peripheral surface of the support b and the ground, and the mortar d is filled in the bag c. In addition, a method of introducing a preload into the surrounding mountain is also performed.
【0005】[0005]
【発明が解決しようとする課題】従来のプレロ−ドを導
入する方法は、地山の先行緩みや切羽・天端の崩壊を確
実に防止できる点で優れているが、以下のような問題が
未解決である。 <イ>袋体を支保工の外周面と地山との狭い間隙に押し
込む作業は労力を要し、作業に要する時間が長くなって
しまう。The conventional method of introducing a preload is excellent in that the loosening of the ground and the collapse of the face and the top can be reliably prevented, but the following problems are encountered. Unresolved. <B> The work of pushing the bag into the narrow gap between the outer peripheral surface of the support and the ground requires labor, and the time required for the work becomes long.
【0006】<ロ>押し込んだ袋体はゴムバンドのみで
支保工に止められているが、膨脹した際にゴムバンドが
はずれて袋体が支保工からずれたり、落下するおそれが
あるため、ずれ直しや再取付などの無駄な時間を要し
た。<B> The pushed-in bag is stopped by the support with only the rubber band. However, when the bag is inflated, the rubber band may come off and the bag may be shifted from the support or fall. Wasted time such as fixing and reattachment was required.
【0007】<ハ>上記イ、ロのような作業の遅延が原
因となり、袋体にモルタルを注入してプレロ−ドを導入
するまでに長時間が経過してしまう。そのため、掘削初
期の最も特性曲線の傾きが大きくなる時点に、即ち、最
も緩みの進行が激しい時点に、トンネル周辺地山の緩み
域の進行が抑制できなくなってしまう。<C> Due to the delay in the operation described in (a) and (b) above, a long time elapses before the mortar is injected into the bag and the preload is introduced. Therefore, at the time when the slope of the characteristic curve becomes the largest in the initial stage of excavation, that is, at the time when the progress of the loosening is the most intense, the progress of the loose area around the tunnel around the tunnel cannot be suppressed.
【0008】<ニ>袋体の押し込み作業は、高所作業車
に乗って作業員が手作業で行うため、切羽直下の危険な
作業となる。<4> The pushing operation of the bag body is a dangerous operation immediately below the face because the worker manually rides on an aerial work vehicle.
【0009】[0009]
【発明の目的】本発明は、上記のような問題点を解決す
るためになされたもので、支保工の建込作業から袋体を
膨脹させてプレロ−ドを導入するまでの作業時間を短縮
し、トンネル周辺地山の緩み域の進行を早期に抑制する
と共に、作業の安全性を確保できるトンネル支保工の建
て込み方法を提供することを目的とする。SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and shortens the working time from the work of erecting a supporter to inflating a bag and introducing a preload. In addition, it is an object of the present invention to provide a method for installing a tunnel shoring capable of suppressing the progress of a loose area in the ground around the tunnel at an early stage and securing work safety.
【0010】[0010]
【課題を解決するための手段】上記課題を解決するため
の手段として、トンネルの掘削断面外周に沿って支保工
を建て込む方法において、支保工の外周面にプレロ−ド
導入用の袋体を配備した後に、トンネルの掘削断面外周
に沿って支保工を建て込むことを特徴とした、トンネル
支保工の建て込み方法を提供する。As a means for solving the above-mentioned problems, in a method of erection of a shoring along a perimeter of an excavated cross section of a tunnel, a bag for introducing a preload is provided on an outer peripheral surface of the shoring. After the deployment, a method of erection of a tunnel shoring is provided, wherein the shoring is erected along the outer periphery of the excavated cross section of the tunnel.
【0011】また、上記のトンネル支保工の建て込み方
法において、前記支保工の外周面の切羽と反対側の縁部
あるいは両縁部に、前記袋体のずれ防止部材を突設した
ことを特徴とした、トンネル支保工の建て込み方法を提
供する。Further, in the above-described method for mounting a tunnel support, the slip prevention member for the bag body is protruded at an edge or both edges of the outer peripheral surface of the support opposite to the face. Provide a method of building tunnel support.
【0012】[0012]
<イ>先受け鋼材の打込み 図1に示すように、トンネル掘削に先立ち、掘削断面外
周に沿って複数の先受け鋼材1を打ち込む。先受け鋼材
1としては、鋼管やH型鋼などが用いられる。<A> Driving of Precedent Steel Material As shown in FIG. 1, prior to tunnel excavation, a plurality of precedent steel materials 1 are driven along the outer periphery of the excavation section. As the first steel material 1, a steel pipe, an H-shaped steel, or the like is used.
【0013】先受け鋼材1の打込み方向は、トンネルの
軸線と平行かやや傾斜させて切羽前方に打ち込み、又は
掘削後に挿入して設置する。そして、先受け鋼材1の一
端側は、切羽面から所定長(支保工を設置できる長さ)
トンネル内に突出させておく。The driving direction of the front receiving steel material 1 is parallel or slightly inclined with respect to the axis of the tunnel, and is driven in front of the face or inserted after excavation. Then, one end side of the front receiving steel material 1 is a predetermined length from the face face (the length at which the shoring can be installed).
Protrude into the tunnel.
【0014】<ロ>支保工 支保工2は、先受け鋼材1群によって形成したル−フを
直接支承するためのものである。支保工2には、図1に
示すような鋼ア−チ支保工などを使用する。鋼ア−チ支
保工はコンクリ−ト覆工の中に埋め込むのが原則であ
る。<B> Shoring The shoring 2 is for directly supporting the roof formed by the first group of steel members. For the support 2, a steel arch support as shown in FIG. 1 is used. In principle, steel arch supports are embedded in concrete lining.
【0015】鋼ア−チ支保工は種々のタイプがあるが、
トンネルの地質、断面形状、掘削方法、覆工の施工法な
どを考慮して適切なものを使用する。用いる鋼材として
はI形、H形、V形、レ−ルなどが使用される。There are various types of steel arch supports,
Use appropriate ones considering the geology, cross-sectional shape, excavation method, lining method, etc. of the tunnel. As the steel material to be used, I type, H type, V type, rail and the like are used.
【0016】<ハ>ずれ防止部材 ずれ防止部材3は、支保工2の外周面に突設され、袋体
のずれや落下を防止するためのものである。例えば図2
に示すようなアングル鋼材を、支保工2の両縁部に沿っ
て、支保工建て込み前に予め溶接しておくことが考えら
れる。<C> Displacement Prevention Member The displacement prevention member 3 is provided on the outer peripheral surface of the support 2 to prevent the bag body from being displaced or dropped. For example, FIG.
It is conceivable that an angle steel material as shown in FIG. 1 is welded in advance along the both edges of the support 2 before embedding the support.
【0017】ずれ防止部材3には、棒状体や板状体など
種々の形状が採用できるが、袋体が膨脹した際にずれ防
止部材3によって袋体が破損しない形状とする。また、
ずれ防止部材3の支保工2外周面からの高さは、袋体膨
脹時に十分なずれ防止効果が得られるように、袋体の膨
脹時の大きさなどを考慮して設定する。さらに、袋体の
膨脹圧で変形しない強度も付与する必要がある。Although various shapes such as a rod-like body and a plate-like body can be adopted as the slip prevention member 3, the shape is such that the bag is not damaged by the slip prevention member 3 when the bag is inflated. Also,
The height of the slip prevention member 3 from the outer peripheral surface of the support 2 is set in consideration of the size of the bag when inflated and the like so that a sufficient slip prevention effect can be obtained when the bag is inflated. Further, it is necessary to provide a strength that does not cause deformation due to the expansion pressure of the bag.
【0018】図2の場合は、ずれ防止部材3を支保工2
外周面の両縁部に設けた場合であるが、切羽と反対側の
縁部21のみに設ける場合もある。この場合、袋体の切
羽側はトンネルの切羽面に支保されることになる。In the case of FIG. 2, the slip prevention member 3 is
This is the case where it is provided on both edges of the outer peripheral surface, but it may also be provided only on the edge 21 opposite to the face. In this case, the face side of the bag is supported by the face face of the tunnel.
【0019】また、図2のように、ずれ防止部材3を断
続的に設ける場合のほか、支保工2の外周面に沿って連
続して設ける場合もある。なお、ずれ防止部材3の取り
付け方法は、溶接のほかにボルト止めでもよく、また予
め支保工2に一体に形成しておく場合もある。In addition to the case where the slip preventing member 3 is provided intermittently as shown in FIG. 2, there may be a case where it is provided continuously along the outer peripheral surface of the support 2. The slip prevention member 3 may be attached by bolting instead of welding, or may be formed integrally with the support 2 in advance.
【0020】<ニ>上部袋体 上部袋体4は、先受け鋼材1群によって形成したル−フ
と支保工2間に配備する撓性を有する袋体である。上部
袋体4は、全長にわたって連通する一体ものや、内部が
複数の部屋に分割されたもの、または独立した複数の袋
体により構成してもよい。<D> Upper Bag 4 The upper bag 4 is a flexible bag disposed between the roof formed by the first group of steel members and the support 2. The upper bag body 4 may be constituted by an integral body communicating over the entire length, a body whose inside is divided into a plurality of rooms, or a plurality of independent bag bodies.
【0021】上部袋体4の材質は、内部にモルタルを充
填するため、モルタルの流出を抑止でき、かつ空気のみ
が外部に排出される通気性を有するものを使用する。例
えば、細かい目の布などで形成するとよい。また、モル
タル中の水分のみを排出できるよう脱水性を有する材質
(粗目の布など)で形成してもよい。The material of the upper bag body 4 is filled with mortar, so that the mortar can be prevented from flowing out, and a material having air permeability that allows only air to be discharged to the outside is used. For example, it is good to form with a fine cloth. Further, the mortar may be formed of a material having a dehydrating property (a coarse cloth or the like) so that only water in the mortar can be discharged.
【0022】上部袋体4をゴムなどの止水性部材で形成
する場合は、モルタル充填時の袋体内の空気を外部に逃
がすために、排気管を連通しておくとよい。なお、上部
袋体4には、適宜箇所にモルタル注入口を開設してお
き、この注入口は逆止弁構造にするとよい。When the upper bag 4 is formed of a water-blocking member such as rubber, it is preferable to connect an exhaust pipe to release air in the bag when filling the mortar to the outside. In addition, it is good to open a mortar inlet at an appropriate place in the upper bag body 4 and to make this inlet a check valve structure.
【0023】<ホ>上部袋体の支保工への取付 支保工2の建て込みの前に、切羽から離れた床面上など
の低所において、上部袋体4を支保工2の外周面に取り
付ける。上部袋体4を支保工2へ取り付ける構造は色々
考えられるため特に限定しない。一例として、上部袋体
4と支保工2とを、ゴムなどの伸縮性部材で形成した止
めバンド5で適宜間隔をおいて拘束することが考えられ
る。<E> Attachment of the upper bag to the shoring Before the shoring of the shoring 2, the upper sack 4 is attached to the outer peripheral surface of the shoring 2 at a low place such as on the floor away from the face. Attach. The structure in which the upper bag body 4 is attached to the support 2 is not particularly limited because various structures can be considered. As an example, it is conceivable that the upper bag body 4 and the shoring 2 are restrained at appropriate intervals by a stop band 5 formed of an elastic member such as rubber.
【0024】<ヘ>支保工・上部袋体の建て込み 予め上部袋体4を装着した支保工2を、先受け鋼材1群
のトンネル内に突出する部分の内側に建て込む。この
際、支保工2の脚部22の下にも底部袋体6を配備する
とよい。この底部袋体6は上部袋体4と同様の材質及び
構成のものを採用する。<F> Embankment / Embedment of upper bag body The embankment 2 to which the upper bag body 4 is mounted in advance is installed inside a portion of the group of first steel members protruding into the tunnel. At this time, the bottom bag 6 may be provided below the leg 22 of the support 2. The bottom bag 6 has the same material and configuration as the upper bag 4.
【0025】<ト>モルタル加圧注入 各部材のセットが終了したら、上部袋体4及び底部袋体
6内にモルタル7を加圧注入する。これによって、上部
袋体4及び底部袋体6が膨脹するため、周囲地山にプレ
ロ−ドを導入することができ、トンネル周辺地山の緩み
域の進行を抑制することができる。そして、このような
安全な切羽状況の下において、トンネルの掘削を進め
る。<G> Mortar Pressure Injection When the setting of each member is completed, the mortar 7 is injected under pressure into the upper bag body 4 and the bottom bag body 6. As a result, the upper bag body 4 and the bottom bag body 6 are inflated, so that the preload can be introduced into the surrounding ground, and the progress of the loose area around the tunnel surrounding ground can be suppressed. Then, under such a safe face condition, the excavation of the tunnel is advanced.
【0026】[0026]
【発明の効果】本発明は以上説明したようになるため、
次のような効果を得ることができる。 <イ>袋体を支保工に取り付けた後に、支保工の建て込
みを行うため、建て込み作業が容易になり、作業に要す
る時間を短縮できる。Since the present invention has been described above,
The following effects can be obtained. <B> After the bag is attached to the shoring, the shoring is erected, so that the erection work is facilitated and the time required for the operation can be reduced.
【0027】<ロ>ずれ防止部材により、膨脹した際に
袋体が支保工からずれたり、落下するおそれがないた
め、ずれ直しや再取付などで無駄な時間を費やさなくて
済む。<B> Since the bag body is not likely to be displaced or dropped from the support when inflated by the displacement prevention member, it is not necessary to waste time for displacing or reattaching the bag.
【0028】<ハ>上述のように作業の迅速化が図れる
ため、袋体にモルタルを注入してプレロ−ドを導入する
までの作業時間が短時間で済む。そのため、早期に、ト
ンネル周辺地山の緩み域の進行を抑制できる。従って、
地山の緩み防止や切羽・天端の崩壊防止を確実に図るこ
とができ、上部構造物への影響を少なくすることができ
る。<C> Since the work can be sped up as described above, the work time from injecting the mortar into the bag and introducing the preload can be shortened. Therefore, it is possible to suppress the progress of the loose area around the tunnel at an early stage. Therefore,
Prevention of loosening of the ground and prevention of collapse of the face and top end can be ensured, and the influence on the upper structure can be reduced.
【0029】<ニ>袋体を支保工へ取り付ける作業は切
羽から離れた床面上などの低所で行えるため、作業の安
全性を確保することができる。<D> Since the work of attaching the bag body to the shoring work can be performed at a low place such as on the floor away from the face, safety of the work can be ensured.
【図1】 本発明の一実施の形態の説明図FIG. 1 is an explanatory diagram of an embodiment of the present invention.
【図2】 ずれ防止部材の一例の説明図FIG. 2 is an explanatory view of an example of a slip prevention member.
【図3】 従来技術の説明図FIG. 3 is an explanatory view of a conventional technique.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 青木 俊彦 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 ────────────────────────────────────────────────── ─── Continued on the front page (72) Inventor Toshihiko Aoki 1-25-1, Nishishinjuku, Shinjuku-ku, Tokyo Taisei Corporation
Claims (3)
を建て込む方法において、 支保工の外周面にプレロ−ド導入用の袋体を配備した後
に、 トンネルの掘削断面外周に沿って支保工を建て込むこと
を特徴とした、 トンネル支保工の建て込み方法。1. A method of erection along a perimeter of an excavation section of a tunnel, comprising: providing a bag for introducing a preload on an outer peripheral surface of the support; A method of building a tunnel shoring, characterized in that it is built.
込み方法において、前記支保工の外周面の切羽と反対側
の縁部に、前記袋体のずれ防止部材を突設したことを特
徴とした、トンネル支保工の建て込み方法。2. The method for erection of a tunnel shoring according to claim 1, wherein a member for preventing displacement of the bag body is protruded from an edge of the outer peripheral surface of the shoring opposite to the face. How to build tunnel support.
込み方法において、前記支保工の外周面の両縁部に、前
記袋体のずれ防止部材を突設したことを特徴とした、ト
ンネル支保工の建て込み方法。3. The tunnel supporting method according to claim 1, wherein the bag body is prevented from slipping at both edges of an outer peripheral surface of the supporting structure. How to build the shoring.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9049869A JPH10231700A (en) | 1997-02-18 | 1997-02-18 | Method for building tunnel timbering |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9049869A JPH10231700A (en) | 1997-02-18 | 1997-02-18 | Method for building tunnel timbering |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH10231700A true JPH10231700A (en) | 1998-09-02 |
Family
ID=12843061
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP9049869A Pending JPH10231700A (en) | 1997-02-18 | 1997-02-18 | Method for building tunnel timbering |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH10231700A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006328861A (en) * | 2005-05-27 | 2006-12-07 | Okumura Corp | Filling method |
JP2020023867A (en) * | 2018-08-02 | 2020-02-13 | フジモリ産業株式会社 | Filling body and filling method in civil engineering structure |
WO2024027772A1 (en) * | 2022-08-03 | 2024-02-08 | 山东建筑大学 | Composite support structure combining bag-based backfill grouting and high-strength support frame, and construction method |
-
1997
- 1997-02-18 JP JP9049869A patent/JPH10231700A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006328861A (en) * | 2005-05-27 | 2006-12-07 | Okumura Corp | Filling method |
JP2020023867A (en) * | 2018-08-02 | 2020-02-13 | フジモリ産業株式会社 | Filling body and filling method in civil engineering structure |
WO2024027772A1 (en) * | 2022-08-03 | 2024-02-08 | 山东建筑大学 | Composite support structure combining bag-based backfill grouting and high-strength support frame, and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107849917B (en) | Tunnel construction method using advance support and lag support and device suitable for same | |
KR100851062B1 (en) | Magnetic attached jack stiffener | |
KR101640449B1 (en) | Construction method for open cutting in tunnel portal area | |
KR100966148B1 (en) | Ground adhering soil nailing structure and ground reinforcement method using the same | |
KR20150088406A (en) | Soil guard structure and construction method thereof | |
KR20150010419A (en) | Connecting structure of mid supporting beam for temporary soil sheathing work | |
WO2015186969A1 (en) | Method for constructing linear support member of large-section tunnel having small flattening | |
JPH10231700A (en) | Method for building tunnel timbering | |
KR20160000792A (en) | Natm tunnel structure and construction method thereof | |
US5465535A (en) | Method of installing a soil anchor and a soil anchor | |
KR101012756B1 (en) | Grouting anchor bolt install device | |
KR101988460B1 (en) | pressure grouting method using high molecular compound absorber packer | |
KR102413264B1 (en) | Multi-functional tube and injection method using thereof | |
CN114776330A (en) | Tunnel primary support structure of diaphragm bag concrete and corrugated steel plate combination | |
KR101787366B1 (en) | A Retaining wall using Precast pile and Construction method thereof | |
KR101665516B1 (en) | Construction method of duel tunnel using composite capable of bidirectional tensioning, pressure casting and tiebolting, and its duel tunnel | |
JPH04357293A (en) | Flexible pipe and executing method thereof | |
KR20160109032A (en) | Earth Anchor | |
KR100697333B1 (en) | A packer for pressure type soil nailing | |
JP2000297590A (en) | Excavation wall construction method | |
KR20100013070A (en) | Interval fills tool of soil guard work | |
JPH0813494A (en) | Fixing method of earth retaining wall and timbering | |
KR101158416B1 (en) | Punching inlet hole sealing apparatus in an anchoring working | |
KR100869369B1 (en) | The ground reinforcement apparatus and method grouting type using bundle steel pipe | |
US5199817A (en) | Process of providing an elongate underground cavity |