JPH09328907A - Method for repairing peeled part of outer wall finish - Google Patents

Method for repairing peeled part of outer wall finish

Info

Publication number
JPH09328907A
JPH09328907A JP16818196A JP16818196A JPH09328907A JP H09328907 A JPH09328907 A JP H09328907A JP 16818196 A JP16818196 A JP 16818196A JP 16818196 A JP16818196 A JP 16818196A JP H09328907 A JPH09328907 A JP H09328907A
Authority
JP
Japan
Prior art keywords
peeling
suction
space
filler
jig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP16818196A
Other languages
Japanese (ja)
Inventor
Yoshiro Hattori
芳朗 服部
Kazuyuki Goto
一之 後藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
RINOTETSUKU KK
Fujita Corp
Original Assignee
RINOTETSUKU KK
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by RINOTETSUKU KK, Fujita Corp filed Critical RINOTETSUKU KK
Priority to JP16818196A priority Critical patent/JPH09328907A/en
Publication of JPH09328907A publication Critical patent/JPH09328907A/en
Pending legal-status Critical Current

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve the execution capability by installing a filling material supplying unit and a suction unit in communication holes, which are provided in a partial floated exterior material with a space in the vertical direction and which are communicated with a peeling space. SOLUTION: Communication holes 1, 1a, are drilled in a peeled part, which is generated in the surface of an outer wall of a concrete building frame M, at spaced positions in the vertical direction so as to achieve a peeling space K. A filling jig 4 is fixed to an upper hole 1 for temporary sealing and sucking jigs 6, 6a are fixed to lower holes 1a, for temporary sealing by putty or the like. A filling material supplying body at a natural pressure is connected to the jig 4, and a transparent hose of a suction device is connected to the jigs 6, 6a. Each valve of the jigs 4, 6, 6a is opened so as to reduce the pressure of the air inside of the space K, and while, the filling material is sucked into the space K for filling from the filling material supplying body. Furthermore, after recognizing flow-in of the filling material into the transparent hose, the valves of the jigs 6, 6a are closed, and after the filling material is hardened, the jigs 4, 6, 6a are removed. Filling time is thereby remarkably shortened, and the whole of the peeling space can be filled with the filling material.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、コンクリート建築
構造物の外装材に、経年変化により、コンクリート躯体
と外装材の貼着面の間に、部分的な浮き状態(剥離部)
が生じた場合に、部分浮き外装材の非接着、剥離個所に
対して補修用の充填材を注入し、部分浮き外装材の接着
状態を復元する外壁仕上げの剥離部の補修方法に関する
ものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an exterior material of a concrete building structure, and due to aging, a partial floating state (peeling part) between the concrete body and the attachment surface of the exterior material.
In the case of occurrence of the problem, the present invention relates to a method for repairing a peeled part of an outer wall finish, in which a non-adhesive part of a partially floating exterior material is injected, and a filler for repairing is injected into a peeling part to restore the adhesion state of the partially floating exterior material. .

【0002】[0002]

【従来の技術】従来、コンクリート造の建築物、構造物
のコンクリート躯体の壁面に、貼着された外装材が、コ
ンクリート躯体の壁面から部分的に剥離して、部分的な
非接着、浮き状態が発生した場合には、再接着、補修対
策として、部分剥離個所の上部に注入治具及び注入器を
取付け、注入器内のエポキシ樹脂等の接着剤(充填材)
を自然流下状態で剥離空間内に注入することが行われて
いた。
2. Description of the Related Art Conventionally, an exterior material adhered to a wall of a concrete frame of a concrete building or structure is partially peeled off from the wall of the concrete frame, and partially adhered or floated. If a problem occurs, attach the injection jig and the injector to the upper part of the partially peeled part as a measure for re-adhesion and repair, and use an adhesive (filler) such as epoxy resin in the injector.
Was injected into the separation space in a state of natural flow.

【0003】かかる自然流下樹脂注入工法における充填
材の供給、注入は、充填材に圧力を加えていないため
に、注入作業に長時間を必要とする欠点を有していた
り、薄い剥離空間に充填材を万遍なく注入することが出
来ず、補修作業後においても全面的な再接着が不可能な
欠点を有していた。
Supplying and injecting the filler in such a natural flow resin injection method has a drawback that a long time is required for the injection work because pressure is not applied to the filler, or the thin separation space is filled. The material could not be poured evenly, and there was the drawback that full re-adhesion was impossible even after repair work.

【0004】尚、充填材は自然流下状態で剥離空間に注
入していることに関して、例えば、コンクリートクラッ
クの補修に使用されている様な、低圧圧力を付加する低
圧樹脂注入工法を採用すると、剥離空間に低圧圧力を付
加して樹脂を注入した時に、外装材がコンクリート躯体
から更に剥離する方向に押出され、外装材の剥離脱落に
繋がるため、かかる低圧樹脂注入工法の浮き外装材補修
への採用は不可能であった。
Regarding the fact that the filler is poured into the peeling space in a natural flow state, if a low pressure resin injection method for applying a low pressure, such as that used for repairing concrete cracks, is adopted, peeling will occur. When the resin is injected by applying a low pressure to the space, the exterior material is extruded in the direction of further peeling from the concrete skeleton, which leads to peeling and falling of the exterior material. Was impossible.

【0005】[0005]

【発明が解決しようとする課題】本発明は、コンクリー
ト躯体の壁面との間に発生した外装材の部分浮き剥離空
間に、充填材を注入する補修作業を短時間作業と成すと
共に、剥離空間全体に充填材を注入可能とする様にした
外壁仕上げの剥離部の補修方法を提供せんとするもので
ある。
SUMMARY OF THE INVENTION According to the present invention, repair work for injecting a filler into a partially floating peeling space of an exterior material generated between a wall surface of a concrete skeleton and a filling work is performed for a short time, and the entire peeling space is It is intended to provide a method for repairing a peeling portion of an outer wall finish, which enables a filler to be injected into the.

【0006】[0006]

【課題を解決するための手段】本発明は、上記従来技術
に基づく、剥離空間の全体に充填材を送り込むことが困
難な課題、補修作業に長時間を必要とする課題に鑑み、
コンクリート躯体の部分浮き外装材の上下2個所に対し
て、外装材の剥離部に流通孔を夫々穿孔すると共に、上
部の充填材流通孔及び下部の吸引流通孔に、充填材供給
部及び吸引部を夫々装着することによって、下部側から
剥離空間の空気を吸引して剥離空間の空気圧力を減圧
し、かかる負圧により充填材を剥離空間内に強制的に吸
引して、剥離空間に充填材を注入充填する。
SUMMARY OF THE INVENTION The present invention has been made in view of the problems that it is difficult to feed the filler into the entire separation space and the problem that it takes a long time for repair work based on the above-mentioned conventional technique.
At the upper and lower two places of the partially floating exterior material of the concrete skeleton, the separation holes of the exterior material are respectively provided with circulation holes, and the upper filler circulation hole and the lower suction circulation hole are provided with the filler supply section and the suction section. The air in the peeling space is sucked from the lower side to reduce the air pressure in the peeling space, and the filler is forcibly sucked into the peeling space by the negative pressure, and the filler is filled in the peeling space. Inject and fill.

【0007】かかる減圧方式による充填注入作業によ
り、充填材に負圧圧力を付与して、強制的に剥離空間に
充填材を注入し、又剥離空間の全体が減圧空間となっ
て、剥離空間の全体、細部に充填材を送り込んで、全て
の小さな剥離空間にも充填材を充填する。
By the filling and injecting work by the depressurization method, a negative pressure is applied to the filling material to forcibly inject the filling material into the peeling space, and the entire peeling space becomes a depressurized space. The filling material is fed to the whole and the details, and the filling material is also filled into all the small peeling spaces.

【0008】又、コンクリート躯体の表面に貼着状態の
外装材と部分浮き状態の外装材の境界において、両外装
材はコンクリート躯体表面に対して、接触、非接触状態
で段違いが発生して、両外装材の境界に亀裂が生じてい
る場合には、浮き外装材周囲(境界)の周縁亀裂部を仮
止シールして、密閉状態の剥離空間に対して充填材の注
入作業を行って、上記課題を解決せんとしたものであ
る。
Further, at the boundary between the exterior material adhered to the surface of the concrete skeleton and the exterior material in the partially floating state, both exterior materials have a step difference in contact or non-contact with the concrete skeleton surface, If there is a crack at the boundary between the two exterior materials, temporarily seal the peripheral cracks around the floating exterior material (boundary), and inject the filler into the sealed separation space. It is a solution to the above problems.

【0009】[0009]

【発明の実施の形態】以下、本発明の最も好ましい実施
例を図面に基づいて説明する。本実施例においては、外
部に形成された外壁コンクリートの外装材(外装仕上げ
材)の部分的な非接着、浮き剥離箇所の補修について述
べるものである。Mはコンクリート構造物における外壁
で、図6は外壁の断層断面図を示し、該外壁コンクリー
ト躯体Mは外部に接する外壁表面Pにタイル、モルタル
等の外装材G(図示のものはタイル)が貼着されてい
る。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, the most preferred embodiments of the present invention will be described with reference to the drawings. In the present embodiment, partial non-adhesion of an outer wall concrete exterior material (exterior finishing material) formed outside and repair of a floating separation portion will be described. 6 is a cross-sectional view of the outer wall of the concrete structure, and FIG. 6 is a cross-sectional view of the outer wall. The outer wall concrete skeleton M is attached to the outer wall surface P that is in contact with the outside with an exterior material G (tiles in the figure) such as tiles and mortar. It is worn.

【0010】そして、全体的に接着状態の接着部Aと、
部分的に非接着状態の剥離部Cと、接着部Aと剥離部C
の境界Bで、浮き開始個所の境界Bに亀裂が生じ得るこ
とを示すと共に、コンクリート躯体Mの表面と剥離部C
の間に剥離空間Kが形成されている状況を示し、図4は
外装材Gがタイルの時の外壁表面Pの境界B及び剥離部
C等を表す正面図で、図5は外装材Gがモルタルの時の
境界B及び剥離部C等を表す正面図である。
Then, the adhesive portion A which is in an adhesive state as a whole,
Partly non-bonded peeling part C, bonding part A and peeling part C
At the boundary B of the concrete, it is shown that a crack may occur at the boundary B of the floating start point, and the surface of the concrete skeleton M and the peeled portion C
FIG. 4 is a front view showing the boundary B of the outer wall surface P and the peeling portion C when the exterior material G is a tile, and FIG. 5 shows the exterior material G. It is a front view showing the boundary B and the peeling part C etc. at the time of mortar.

【0011】尚、前記の補修箇所の他に、外壁コンクリ
ート躯体Mの内装材、内部構造躯体のコンクリート壁の
内装材、或いは、床面、天井面にも本発明が適用され、
本明細書では、これらを含みコンクリート躯体Mの外装
材Gとしている。
In addition to the above-mentioned repaired parts, the present invention is also applied to the interior material of the outer wall concrete skeleton M, the interior material of the concrete wall of the internal structural skeleton, or the floor surface and the ceiling surface,
In the present specification, the exterior material G of the concrete skeleton M including these is used.

【0012】次に、本発明の外装仕上げ材Gが剥離した
時に補修する補修装置を説明する。図1は補修装置の全
体を示す斜視図である。補修装置は、外壁表面Pにおけ
る外装材Gの剥離部Cの剥離面に貼着する注入治具4
と、該注入治具4に充填材供給体2が装着され、剥離面
に貼着する吸引治具6、6aと、走行台車1201に搭載され
たエアータンク12と前記キャスター1001が付いた吸引機
10とからなる吸引装置3とで構成され、吸引機10とエア
ータンク12は可撓性を有する接続ホース15で連結し、エ
アータンク12と前記吸引治具6、6aに接続ホース14、14
a により夫々連結されている。以下更に詳細に補修装置
を説明する。
Next, a repairing device for repairing the exterior finishing material G of the present invention when peeled off will be described. FIG. 1 is a perspective view showing the entire repair device. The repair device is an injection jig 4 that is attached to the peeling surface of the peeling portion C of the exterior material G on the outer wall surface P.
And a suction device with the filler supply body 2 attached to the injection jig 4 and attached to the peeling surface, the suction jigs 6 and 6a, the air tank 12 mounted on the traveling carriage 1201 and the casters 1001.
The suction device 3 is composed of 10 and the suction device 10 and the air tank 12 are connected by a flexible connection hose 15, and the connection hoses 14, 14 are connected to the air tank 12 and the suction jigs 6, 6a.
They are connected by a. Hereinafter, the repair device will be described in more detail.

【0013】注入治具4の一例としては、図3に示す様
に、外装材Gの表面に接面する接面部7の中央位置に、
その厚さ方向に貫通する注入口8を突出させると共に、
かかる注入口8に吸引流路を開閉自在なバルブ9を一体
的に設けて構成し、注入口8に充填材容器5の吐出口5a
を連通接続している。
As an example of the injection jig 4, as shown in FIG. 3, at the central position of the contact surface portion 7 contacting the surface of the exterior material G,
While projecting the injection port 8 penetrating in the thickness direction,
A valve 9 that can open and close a suction flow path is integrally provided in the injection port 8, and the discharge port 5a of the filling material container 5 is provided in the injection port 8.
Are connected for communication.

【0014】又、吸引治具6、6aの一例としては、図2
に示す様に、図3に示した注入治具4と同様構成のもの
を使用し、吸引治具6、6aの吸引口8aに吸引装置3の接
続ホース14、14a を接続している。
As an example of the suction jigs 6 and 6a, FIG.
As shown in FIG. 3, a structure similar to that of the injection jig 4 shown in FIG. 3 is used, and the connection hoses 14 and 14a of the suction device 3 are connected to the suction ports 8a of the suction jigs 6 and 6a.

【0015】充填材供給体2は、図3に示す様に、充填
材Wを収容するもので、着脱自在な蓋5bを有する充填材
容器5と、容器下部より吐出口5aが突設され、吐出口5a
は注入治具4の注入口8に差し込まれて連通している。
As shown in FIG. 3, the filler supplying body 2 accommodates the filler W and is provided with a filler container 5 having a detachable lid 5b, and a discharge port 5a projecting from the bottom of the container. Discharge port 5a
Are inserted into the injection port 8 of the injection jig 4 and communicate with each other.

【0016】又、吸引装置3の概略は、図8、9に示す
様に、剥離部Cの下部及び必要に応じてその上方位置に
おいて、外装材Gに穿孔した一定間隔毎の流通孔1、1a
…に吸引治具6、6aを配設し、図1に示す様に、剥離部
C補修近傍に減圧調整するエアータンク12を設置し、同
エアータンク12と吸引治具6、6aは接続ホース14、14a
によって連結され、さらに、エアータンク12に接続ホー
ス15を介して接続されてエアーを吸引する吸引機(バキ
ューム)10によって構成されている。
Further, as shown in FIGS. 8 and 9, the suction device 3 is schematically shown in the lower portion of the peeling portion C and, if necessary, at the upper position thereof, the through holes 1 formed in the exterior material G at regular intervals. 1a
Suction jigs 6 and 6a are installed in the air tank, and an air tank 12 for reducing the pressure is installed near the repair of the peeling portion C as shown in FIG. 1. The air tank 12 and the suction jigs 6 and 6a are connected to a hose. 14, 14a
And a suction device (vacuum) 10 which is connected to an air tank 12 via a connection hose 15 and sucks air.

【0017】吸引装置3の詳細例としては、図1に示す
様に、吸引機10、例えば電気駆動式の掃除機の吸入口11
に接続ホース15を介して比較的大容量のエアータンク12
を接続し、該エアータンク12に設けた複数の減圧分岐吸
入するノズル13、13a と、コンクリート躯体Mに固定し
た吸引治具6、6aの吸引口8aを、透明又は半透明な接続
ホース14、14a で連通接続している。
As a detailed example of the suction device 3, as shown in FIG. 1, a suction device 10, for example, a suction port 11 of an electrically driven vacuum cleaner.
A relatively large capacity air tank 12 connected via a hose 15
, A plurality of decompression branch nozzles 13a provided in the air tank 12, and suction ports 8a of suction jigs 6, 6a fixed to the concrete skeleton M are connected to a transparent or translucent connection hose 14, Connected with 14a.

【0018】次に剥離した外壁面に充填する充填材Wに
ついて説明する。充填材Wは、浮き状況(割れの程度、
広さ、厚さ、進行性)で充填材Wを選択し、接着、防
水、可撓性を考慮し、無機質系、及び有機質系のものが
単独又は混合で使用され、無機質系としては例えば、セ
メントミルク、硅酸ソーダが使われており、有機質系と
して、例えば高分子系のセメント混和材、エポキシ樹
脂、ポリエステル樹脂等が用いられる。
Next, the filler W to fill the peeled outer wall surface will be described. The filler W has a floating state (degree of cracking,
The width, thickness, and progressiveness) of the filler W are selected, and in consideration of adhesion, waterproofing, and flexibility, an inorganic type and an organic type are used alone or as a mixture, and as the inorganic type, for example, Cement milk and sodium silicate are used, and as the organic material, for example, polymer cement admixture, epoxy resin, polyester resin, etc. are used.

【0019】充填材供給体2に内蔵した充填材Wは、上
記の様に各種配合のものを使用可能で、いずれにしても
剥離空間Kへ注入される充填材Wは、剥離の状況と目的
により適宜選択すれば良く、材質、配合を限定するもの
ではない。
As the filler W contained in the filler supply body 2, various kinds of compounds as described above can be used. In any case, the filler W injected into the peeling space K has a peeling condition and a purpose. Therefore, the material and the composition are not limited.

【0020】次に本発明に係る外壁仕上げの剥離部の補
修方法について説明する。外壁表面Pの補修は、例え
ば、図4、6のタイル仕上げの場合や、図5の様にモル
タルの場合があるが、いずれにしても、剥離した場所を
限定しなければならない。
Next, a method of repairing the peeling portion of the outer wall finish according to the present invention will be described. The outer wall surface P may be repaired, for example, in the case of tile finishing shown in FIGS. 4 and 6 or in the case of mortar as shown in FIG.

【0021】剥離部分の診断は、例えば、外見上の浮
き、テストハンマーによる打撃音による判定、赤外線に
よる剥離診断などにより調査し、剥離位置のマーキング
を行う。
For the diagnosis of the peeled portion, for example, the peeling position is marked by investigating it by appearance floatation, judgment by hitting sound with a test hammer, peeling diagnosis by infrared rays, and the like.

【0022】剥離場所の診断後の補修方法は、図12の
補修フローチャートの手順、及び関連する図面に基づい
て説明する。そして、外装材Gがタイルの場合にあって
は、図7、8に示す様に、前記コンクリート躯体Mの外
壁表面Pに発生した剥離部Cに対して、外壁表面Pの剥
離部Cの上下離隔位置に流通孔1、1a…を、剥離空間K
に達する様に穿孔する。
The repair method after the diagnosis of the peeling place will be described based on the procedure of the repair flowchart of FIG. 12 and the related drawings. In the case where the exterior material G is a tile, as shown in FIGS. 7 and 8, with respect to the peeling portion C generated on the outer wall surface P of the concrete skeleton M, the peeling portion C on the outer wall surface P is located above and below. The flow holes 1, 1a ...
Perforate to reach.

【0023】そして、図7、8に示す様に、上下部の流
通孔1、1a…に当てがう様に、1個の注入治具4及び複
数の吸引治具6、6aを粘着テープ、パテその他の接着剤
20で仮止シール固定する。
Then, as shown in FIGS. 7 and 8, one injection jig 4 and a plurality of suction jigs 6 and 6a are attached to the upper and lower flow holes 1, 1a. Putty and other adhesives
Tighten the temporary seal with 20.

【0024】次に、図1、3、11に示す様に、前記の
様に貼着した注入治具4に自然圧力の充填材供給体2を
接続すると共に、図1、2に示す様に、貼着した複数の
吸引治具6、6aに、吸引装置3の分岐した接続ホース1
4、14a を接続する。
Next, as shown in FIGS. 1, 3 and 11, the filling material supplier 2 of natural pressure is connected to the injection jig 4 attached as described above, and as shown in FIGS. , The plurality of suction jigs 6 and 6a attached to the suction hose 3 and the branched connection hose 1
Connect 4 and 14a.

【0025】そして、注入治具4の注入口8に設けたバ
ルブ9を開放すると共に、吸引治具6、6aの吸引口8aに
設けたバルブ9を開放し、吸引機10を作動させると、吸
引装置3の吸引作用はエアータンク12、接続ホース14、
14a を介して吸引治具6、6aに作用し、図2、8、9の
矢印で示す様に、剥離空間K内の空気は吸引機10に吸引
され、その結果、剥離空間K内は空気圧が減圧されて負
圧状態となる。
Then, when the valve 9 provided at the injection port 8 of the injection jig 4 is opened and the valve 9 provided at the suction port 8a of the suction jigs 6 and 6a is opened, the suction device 10 is operated. The suction action of the suction device 3 is the air tank 12, the connection hose 14,
It acts on the suction jigs 6 and 6a via 14a, and the air in the separation space K is sucked by the suction device 10 as shown by the arrows in FIGS. Is depressurized to a negative pressure state.

【0026】かかる剥離空間K内の減圧作用に伴って、
図3、8、9の矢印で示す様に、充填材供給体2から充
填材Wが剥離空間K内に吸入され、充填材Wは剥離空間
Kの両内面に付着しつつ、吸引治具6、6aの方向へ吸引
され、剥離部Cが発生した剥離空間Kの細部が充填材W
で充満する。
With the depressurizing action in the peeling space K,
As shown by the arrows in FIGS. 3, 8 and 9, the filler W is sucked from the filler supply body 2 into the separation space K, and the filler W adheres to both inner surfaces of the separation space K while the suction jig 6 is attached. , 6a, the details of the peeling space K where the peeling portion C is generated are filled with the filling material W.
Filled with.

【0027】そして、充填材Wの一部が吸引治具6、6a
又は接続ホース14、14a 内に流入した段階、即ち、透明
な接続ホース14、14a 内への充填材Wが流入したことを
確認の上で、吸引治具6、6aのバルブ9を操作して当該
の吸引口8aを閉鎖する。
A part of the filler W is sucking jigs 6 and 6a.
Alternatively, by operating the valve 9 of the suction jigs 6 and 6a after confirming that the filling material W has flowed into the connecting hoses 14 and 14a, that is, the transparent connecting hoses 14 and 14a. The suction port 8a is closed.

【0028】そして、全ての吸引口8aに充填材Wの吐露
(排出)を確認した後、バルブ9を閉鎖後には充填材W
の硬化養生を行い、注入治具4及び吸引治具6、6aを外
壁表面Pから剥離すると共に、吸引装置3を撤去する。
After confirming the discharge (discharge) of the filler W to all the suction ports 8a, the filler W is closed after the valve 9 is closed.
Then, the injection jig 4 and the suction jigs 6 and 6a are separated from the outer wall surface P, and the suction device 3 is removed.

【0029】又、外装材Gがモルタルの場合の補修も、
タイルの場合と略同様であり、かかる補修作業を簡単に
説明すると、図10に示す様に、外壁表面Pに流通孔
1、1a…を穿孔し、注入治具4及び吸引治具6、6aを取
付け、図1に示す様に、吸引装置3及び充填材供給体2
を取付け、剥離空間K内を負圧と成して剥離空間K内に
充填材Wを充填し、硬化養生、撤去を行う。
Also, when the exterior material G is mortar,
This is almost the same as the case of the tile, and the repair work will be briefly described. As shown in FIG. 10, the through holes 1, 1a ... Are drilled in the outer wall surface P, and the injection jig 4 and the suction jigs 6, 6a are formed. Attached, as shown in FIG. 1, the suction device 3 and the filler supply body 2
Is attached, the negative pressure is formed in the peeling space K, the filling material W is filled in the peeling space K, and curing curing and removal are performed.

【0030】又、接着状態の接着部Aと非接着状態の剥
離部Cの境界Bにあっては、図11に示す様に、接着部
Aと剥離部Cの境界Bで段差亀裂が生じている様な場
合、或いは剥離空間Kの密閉性が阻害されている個所に
対しては、剥離範囲の周縁亀裂部(境界B)などに対し
て、シール材25で仮止シールし、剥離空間Kの密閉性を
確保する。
At the boundary B between the bonded portion A in the bonded state and the peeled portion C in the non-bonded state, a step crack is generated at the boundary B between the bonded portion A and the peeled portion C as shown in FIG. In the case where the peeling space K is impaired, the peripheral space cracks (boundary B) in the peeling range are temporarily sealed with the sealing material 25 to remove the peeling space K. Ensure the airtightness of.

【0031】尚、かかる周縁亀裂部に対するシールは、
外装材Gがタイルの場合にも適宜適用される。
The seal against the peripheral crack portion is
It is also appropriately applied when the exterior material G is a tile.

【0032】次に、上述の補修方法における作業面、作
用面の適用例、注意事項、詳細作用等を追記する。例え
ば、剥離部Cの上下部に複数の流通孔1、1a…を離隔位
置に穿孔しているが、上下方向の剥離部Cの拡がりが小
さい場合には、外装材Gに取付ける吸引治具6、6aは1
個でも良く、従って流通孔1、1a…は吸引用と注入用の
2個でも良く、又複数の流通孔1、1a…は上下部に穿孔
しているが、剥離部Cが横方向に拡がっている場合に
は、横方向に複数の流通孔1、1a…を穿孔しても良い。
Next, application examples, precautions, detailed actions and the like of the working surface and working surface in the above-mentioned repair method will be added. For example, a plurality of flow holes 1, 1a ... Are drilled in the upper and lower portions of the peeling portion C at spaced positions, but when the spread of the peeling portion C in the vertical direction is small, a suction jig 6 attached to the exterior material G is used. , 6a is 1
.. Therefore, the flow holes 1, 1a ... May be two for suction and injection, and a plurality of flow holes 1, 1a .. In this case, a plurality of flow holes 1, 1a ... May be bored in the lateral direction.

【0033】即ち、剥離部Cの縦横の拡がりに対して、
吸引と注入が夫々可能であれば、その個数及び位置は適
宜選択し、複数の吸引用の流通孔1、1a…を設ける場合
に、その間隔も適宜選択可能であり、又垂直面に限らず
床、天井の水平面においても同様である。
That is, with respect to the vertical and horizontal spread of the peeling portion C,
If suction and injection are possible, respectively, the number and position of the suction holes can be appropriately selected, and when a plurality of suction holes 1, 1a ... Are provided, the intervals can also be appropriately selected, and are not limited to vertical surfaces. The same applies to the horizontal planes of the floor and ceiling.

【0034】尚、吸引治具6、6aの吸引作用は吸引口8a
を中心に作用し、続いて空気圧力の均一性により、剥離
空間K内の空気は全体的に吸引されて、充填材Wが送り
込まれ、全体的な剥離空間Kに対して充填材Wを注入す
ることが出来る。
The suction action of the suction jigs 6 and 6a is the suction port 8a.
Then, due to the uniformity of the air pressure, the air in the peeling space K is totally sucked, the filler W is fed, and the filler W is injected into the entire peeling space K. You can do it.

【0035】又、複数の流通孔1、1a…の穿孔個所は、
剥離部Cの端部が好ましいが、その位置が若干内側であ
っても、本発明による外壁仕上げの剥離部の補修作業は
可能であり、又タイルに対する穿孔個所としては、図
7、8に示す様に、その目地に流通孔1、1a…を穿孔す
るのが、見栄え、作業性の面から好ましいが、図9の上
方の流通孔1、1a…に示す様に、タイル自体に穿孔して
も良い。
Further, the perforation points of the plurality of flow holes 1, 1a ...
The edge of the peeling portion C is preferable, but even if the position is slightly inside, the repair work of the peeling portion of the outer wall finish according to the present invention is possible, and the perforation points for the tile are shown in FIGS. In this way, it is preferable to form the flow holes 1, 1a ... At the joints from the viewpoint of appearance and workability, but as shown in the flow holes 1, 1a. Is also good.

【0036】又、剥離空間Kへの充填材Wの注入時にお
いて、充填材容器5から吸引された充填材Wは、剥離空
間Kの両内面に付着すると共に、先端側の充填材Wは吸
引治具6、6a方向に吸引されて、剥離空間Kの内部を充
満することが遅れて行われ、そして未充填の個所にも負
圧作用が作用するため、剥離空間Kの内面側及び内部、
全体的にも注入され、且つ充填材供給体2近傍の剥離部
C、剥離空間Kに対しても充填が行われる。
Further, when the filling material W is injected into the peeling space K, the filling material W sucked from the filling material container 5 adheres to both inner surfaces of the peeling space K, and the filling material W on the tip side is sucked. The inside of the peeling space K is sucked in the direction of the jigs 6 and 6a to fill the inside of the peeling space K with a delay, and the negative pressure acts on the unfilled portion.
It is also injected as a whole, and the peeling portion C and the peeling space K near the filler supply body 2 are also filled.

【0037】又、所定注入完了した吸引治具6、6aの吸
引口8aのバルブ9の閉鎖時に剥離空間K内の充填材Wに
は若干の減圧作用が残存しているために、バルブ9の閉
鎖後にも充填材Wの吸入、拡散が行われ、又注入未了の
吸引口8aでは剥離空間K内への全体的な充填材Wの注入
が継続する。
Further, when the valve 9 of the suction port 8a of the suction jigs 6 and 6a, which has been injected into a predetermined amount, is closed, the filling material W in the peeling space K still has a slight depressurizing action. The filler W is sucked and diffused even after the closing, and the entire filler W is continuously injected into the separation space K at the suction port 8a where the injection is not completed.

【0038】又、吸引、注入の作用において、剥離空間
K内の状況によっては、空気及び充填材Wは、注入治具
4と吸引治具6、6a間で直線的に作用しない場合も存在
することが想定され、剥離空間K内に万遍なく充填材W
を充填出来ない時には、作業途中において、注入治具4
と吸引治具6、6aの位置を変更したり、追加設定するこ
とも行う。
In the action of suction and injection, the air and the filler W may not act linearly between the injection jig 4 and the suction jigs 6 and 6a depending on the conditions in the separation space K. It is assumed that the filling material W is evenly distributed in the peeling space K.
When the filling jig 4 cannot be filled,
Also, the positions of the suction jigs 6 and 6a can be changed or additional settings can be made.

【0039】尚、剥離空間Kに対する注入作業時、即
ち、負圧作用を与えた状態では、コンクリート躯体Mに
仮止装着した注入治具4、吸引治具6、6a、シール材25
等に対しても剥離空間Kを介して負圧作用が働くため
に、充填材Wの注入作業時に注入治具4、吸引治具6、
6a及びシール材25が離脱せず、又仮止装着も堅固、強固
な固定が不要となることにより、吸引治具6、6a固定用
の接着剤20及びシール材25は剥離性が良好な粘着テープ
又はパテ等を使用し、作業終了後の離脱時においては、
コンクリート躯体Mの損傷が皆無となる。
During the pouring operation into the peeling space K, that is, when a negative pressure is applied, the pouring jig 4, the suction jigs 6 and 6a, and the sealing material 25, which are temporarily fixed to the concrete skeleton M, are attached.
Since a negative pressure action acts on the filling material W through the peeling space K, the filling jig W, the suction jig 6,
The 6a and the sealing material 25 do not separate, and the temporary attachment is firm and does not require strong fixing, so the adhesive 20 for fixing the suction jig 6, 6a and the sealing material 25 are adhesive with good peelability. Use tape or putty, etc., when leaving after work
There is no damage to the concrete skeleton M.

【0040】[0040]

【発明の効果】要するに本発明は、コンクリート躯体M
の壁面仕上げが剥離し、該剥離部Cを補修する方法にお
いて、前記剥離部Cに少なくとも2個所に、剥離空間K
に達するよう流通孔1、1a…を穿孔し、前記流通孔1、
1a…の一方に注入治具4を装着し、他方の流通孔1、1a
…に吸引治具6を装着し、前記注入治具4に剥離空間K
に充填する充填材供給体2を装設し、前記吸引治具6に
吸引装置3を装設し、前記吸引装置3により剥離空間K
の空気を吸引して剥離空間K内を減圧すると共に、前記
注入治具4に装着した充填材供給体2より減圧された剥
離空間K内に充填材Wを強制注入する様にしたので、剥
離空間Kに対する充填材Wの注入作業が強制吸引方式と
成ることにより、従来の自然流下方式に比して、充填材
Wの充填時間を大幅に短縮することが出来、且つ、水平
面での作業を行うことも出来る。
INDUSTRIAL APPLICABILITY In short, the present invention is a concrete skeleton M
In the method of repairing the peeling portion C by peeling off the wall surface finish of the peeling space C, at least two peeling spaces K are provided in the peeling portion C.
Through the flow holes 1, 1a ...
1a: The injection jig 4 is attached to one side, and the other flow holes 1, 1a
The suction jig 6 is attached to the ...
The filler supply body 2 to be filled in is installed, the suction device 3 is installed in the suction jig 6, and the peeling space K is set by the suction device 3.
The air is sucked to reduce the pressure in the separation space K, and the filler W is forcibly injected into the pressure-removed separation space K from the filler supply body 2 mounted on the injection jig 4. Since the filling work of the filling material W into the space K is the forced suction method, the filling time of the filling material W can be significantly shortened as compared with the conventional natural flow-down method, and the work on a horizontal surface can be performed. You can also do it.

【0041】又、注入治具4、吸引治具6、6a、充填材
供給体2並びにシール材25等は、注入作業時にはコンク
リート躯体Mに吸引接着される状態となり、コンクリー
ト躯体Mに対してこれらの部材を取付ける準備作業が容
易となると共に、簡易な準備状態であっても、注入治具
4等は吸着されて脱落せず、充填材Wの注入作業を行う
ことが出来、更に簡単な施工であるために、熟練作業員
でなくても施工を行うことが出来、又注入作業終了後の
吸引部(吸引治具6、6a等)及び充填材供給部(注入治
具4等)の撤去時には容易な作業で行うことが出来る。
Further, the pouring jig 4, the suction jigs 6 and 6a, the filler supplying body 2, the sealing material 25 and the like are in a state of being suction-adhered to the concrete skeleton M at the time of the pouring work, and these are attached to the concrete skeleton M. The preparation work for mounting the member is facilitated, and even in a simple preparation state, the injection jig 4 and the like are not adsorbed and fallen off, and the injection work of the filler W can be performed, and the construction is simpler. Therefore, even an unskilled worker can perform the construction, and the suction part (suction jigs 6, 6a, etc.) and the filler supply part (injection jig 4, etc.) can be removed after the injection work is completed. Sometimes it can be done easily.

【0042】又、コンクリート躯体Mと外装材Gの間の
剥離空間Kに注入する充填材Wは吸引方式となることに
より、充填材供給体2から吸引供給される充填材Wは、
充填材供給体2の注入治具4から吸引作用を受ける吸引
治具6、6aの方向に吸引され、剥離空間K内に吸引注入
された充填材Wは、先ず、剥離空間Kの両内面に付着す
ると共に吸引治具6、6aの方向に流動するために、充填
材供給体2を貼着した剥離空間Kの入口側で充填材Wが
止まることがなく、吸引治具6、6aの方向に流動して剥
離空間Kの全体に充填材Wを注入することが出来る。
Further, since the filler W injected into the separation space K between the concrete skeleton M and the exterior material G is of a suction type, the filler W sucked and supplied from the filler supply body 2 is
The filler W, which is sucked in the direction of the suction jigs 6 and 6a receiving the suction action from the filling jig 4 of the filling material supply body 2 and sucked and injected into the peeling space K, is first applied to both inner surfaces of the peeling space K. Since the filler W adheres and flows in the direction of the suction jigs 6 and 6a, the filler W does not stop at the inlet side of the peeling space K to which the filler supply body 2 is attached, and the direction of the suction jigs 6 and 6a. The filling material W can be injected into the entire separation space K by flowing into.

【0043】又、流通孔1、1a…の一方に注入治具4を
装着し、吸引装置3によって他方の吸引治具6、6aより
充填材Wが吸引されたことを確認後、順次吸引を停止す
るので、所定範囲の剥離空間K内に充填材Wを略注入完
了した部分から吸引治具6、6aの吸引口8aに設けたバル
ブ9を締めて、充填材Wの無駄を省くことが出来、且つ
吸引装置3への充填材Wの流入を防止することが出来
る。
Further, the injection jig 4 is attached to one of the flow holes 1, 1a, ... After confirming that the filler W has been sucked from the other suction jig 6, 6a by the suction device 3, suction is sequentially performed. Since it is stopped, the valve 9 provided at the suction port 8a of the suction jigs 6 and 6a can be tightened from the portion where the filling material W has been substantially injected into the peeling space K within a predetermined range, and the waste of the filling material W can be omitted. In addition, it is possible to prevent the filler W from flowing into the suction device 3.

【0044】又、剥離範囲の周縁亀裂部にシールを施
し、剥離空間Kを密閉するので、接着部Aと剥離部Cの
境界Bに亀裂等が生じて、剥離空間Kの密閉性が確保さ
れていない時にも、容易に仮止シールして作業を行うこ
とが出来る等その実用的効果甚だ大なるものである。
Further, since the peripheral crack portion in the peeling range is sealed to seal the peeling space K, a crack or the like is generated at the boundary B between the adhesive portion A and the peeling portion C, and the sealing property of the peeling space K is secured. Even when not in use, the work can be done by temporarily sealing the temporary seal, which is a great practical effect.

【図面の簡単な説明】[Brief description of drawings]

【図1】外壁仕上げの剥離部の補修装置の全体像を示す
概略図である。
FIG. 1 is a schematic view showing an overall image of a repairing device for a peeling portion for finishing an outer wall.

【図2】吸引治具及び接続ホースの拡大斜視図である。FIG. 2 is an enlarged perspective view of a suction jig and a connection hose.

【図3】注入治具及び充填材供給体の拡大斜視図であ
る。
FIG. 3 is an enlarged perspective view of an injection jig and a filler supply body.

【図4】タイル仕上げにおける剥離部が発生した外壁の
正面図である。
FIG. 4 is a front view of an outer wall in which a peeling portion has occurred in tile finishing.

【図5】モルタル仕上げにおける剥離部が発生した外壁
の正面図である。
FIG. 5 is a front view of an outer wall in which a peeling portion has occurred in mortar finishing.

【図6】図4のの断層縦断面図である。6 is a longitudinal sectional view of the section of FIG.

【図7】剥離部補修工程中、コンクリート躯体の浮き個
所に対する注入治具及び吸引治具の取付状態を示す斜視
図である。
FIG. 7 is a perspective view showing a mounting state of an injection jig and a suction jig with respect to a floating portion of a concrete skeleton during a peeling portion repairing step.

【図8】本発明に係るコンクリート躯体の外壁仕上げの
剥離部の補修時における断層縦断面図である。
FIG. 8 is a vertical cross-sectional view of the concrete skeleton according to the present invention at the time of repairing the peeling portion of the outer wall finish.

【図9】図8の他の実施例である。9 is another embodiment of FIG. 8. FIG.

【図10】図7の他の実施例である。10 is another embodiment of FIG. 7. FIG.

【図11】図10に続く、境界に対するパテによる仮止
シール状態を示す斜視図である。
FIG. 11 is a perspective view illustrating a state of temporary fixing and sealing with a putty on the boundary, following FIG. 10;

【図12】補修方法のフローチャートである。FIG. 12 is a flowchart of a repair method.

【符号の説明】[Explanation of symbols]

M コンクリート躯体 G 外装材 K 剥離空間 W 充填材 A 接着部 B 境界 C 剥離部 1、1a… 流通孔 2 充填材供給体 3 吸引装置 4 注入治具 6、6a 吸引治具 M Concrete frame G Exterior material K Separation space W Filler A Adhesive part B Border C Separation part 1, 1a ... Flow hole 2 Filler supplier 3 Suction device 4 Pouring jig 6, 6a Suction jig

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 コンクリート躯体の壁面仕上げが剥離
し、該剥離部を補修する方法において、前記剥離部に少
なくとも離隔した2個所に、剥離空間に達するよう流通
孔を穿孔し、前記流通孔の一方に注入治具を装着し、他
方の流通孔に吸引治具を装着し、前記注入治具に剥離空
間に充填する充填材供給体を装設し、前記吸引治具に吸
引装置を装設し、前記吸引装置により剥離空間の空気を
吸引して剥離空間内を減圧すると共に、前記注入治具に
装着した充填材供給体より減圧された剥離空間内に充填
材を強制注入することを特徴とする外壁仕上げの剥離部
の補修方法。
1. A method for repairing a wall surface finish of a concrete skeleton and repairing the peeling portion, wherein at least two spaces separated from the peeling portion are perforated with a flow hole to reach a peeling space, and one of the flow holes is provided. The injection jig is attached to the other side, the suction jig is attached to the other flow hole, the filler supply body for filling the peeling space is attached to the injection jig, and the suction device is attached to the suction jig. The suction device sucks air in the peeling space to reduce the pressure in the peeling space, and forcibly injects the filler into the pressure-reduced peeling space from the filler supply body mounted on the injection jig. How to repair the peeled part of the outer wall finish.
【請求項2】 請求項1の記載において、流通孔の一方
に注入治具を装着し、吸引装置によって他方の吸引治具
より、充填材が吸引されたことを確認後、順次吸引を停
止することを特徴とする外壁仕上げの剥離部の補修方
法。
2. The method according to claim 1, wherein an injection jig is attached to one of the flow holes, and after confirming that the filler has been sucked from the other suction jig by the suction device, the suction is sequentially stopped. A method of repairing a peeled portion for finishing an outer wall, which is characterized in that
【請求項3】 請求項1又は2の記載において、剥離範
囲の周縁亀裂部にシールを施し、剥離空間を密閉するこ
とを特徴とする外壁仕上げの剥離部の補修方法。
3. The method for repairing a peeled portion having an outer wall finish according to claim 1 or 2, wherein a peripheral edge cracked portion in the peeled range is sealed to seal the peeling space.
JP16818196A 1996-06-07 1996-06-07 Method for repairing peeled part of outer wall finish Pending JPH09328907A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16818196A JPH09328907A (en) 1996-06-07 1996-06-07 Method for repairing peeled part of outer wall finish

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16818196A JPH09328907A (en) 1996-06-07 1996-06-07 Method for repairing peeled part of outer wall finish

Publications (1)

Publication Number Publication Date
JPH09328907A true JPH09328907A (en) 1997-12-22

Family

ID=15863295

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16818196A Pending JPH09328907A (en) 1996-06-07 1996-06-07 Method for repairing peeled part of outer wall finish

Country Status (1)

Country Link
JP (1) JPH09328907A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756152A (en) * 2018-07-25 2018-11-06 詹凤程 A kind of construction and decoration ceramic tile back side putty auxiliary smears equipment
CN110080550A (en) * 2019-04-03 2019-08-02 由中国 A kind of metope structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756152A (en) * 2018-07-25 2018-11-06 詹凤程 A kind of construction and decoration ceramic tile back side putty auxiliary smears equipment
CN110080550A (en) * 2019-04-03 2019-08-02 由中国 A kind of metope structure

Similar Documents

Publication Publication Date Title
CN112695653A (en) Method for repairing concrete bridge longitudinal crack by pouring glue
CN111945497A (en) Concrete structure pore filling operation device and method
JPH09328907A (en) Method for repairing peeled part of outer wall finish
JP2000297539A (en) Repair construction method for floating part of wall or the like
KR101822867B1 (en) Packer assemblies for repairing cracks in concrete structures and repair methods for cracks using them
JPH09209577A (en) Repairing method for concrete crack and its device
JPH10102789A (en) Repairing device of water leaking concrete crack, and its execution method
KR20130001195A (en) Dry way injection grouting method for concrete structure in water
JPH10245998A (en) Concrete water stopping construction method and two-stage excavating drill used in it
JP2007277809A (en) Curing construction method of curing material
JPH0449376A (en) Crack repairing method and its repairing type for concrete structure
JPH0560020B2 (en)
JPH09217497A (en) Attachment for injecting filler
JPH08135032A (en) Construction method of concrete joint water stop hose
JP2011001786A (en) Float section repair method and device for building finish material
CN210194829U (en) Floor drain waterproof device
KR102598191B1 (en) Epoxy dry repair method for concrete cracks using exhaust port and construction monitoring equipment
JPH1030343A (en) Attachment for injecting filler
JPS626066A (en) Repairing of concrete structure
JP2001107370A (en) Joint sealing method for caisson
JP4435792B2 (en) Tile repair method, tile sticking method, mortar used for tile sticking method, mortar repair method
JP3615332B2 (en) Reinforcement method
JP3023200B2 (en) Crack injection waterproofing method and device
JPH02225770A (en) Repairing work for architectural structure
JP3024531U (en) Fully automatic negative pressure adhesive injection device