JPH0932288A - Support method and tool for gap filling filler for pipe insertion hole - Google Patents

Support method and tool for gap filling filler for pipe insertion hole

Info

Publication number
JPH0932288A
JPH0932288A JP7182898A JP18289895A JPH0932288A JP H0932288 A JPH0932288 A JP H0932288A JP 7182898 A JP7182898 A JP 7182898A JP 18289895 A JP18289895 A JP 18289895A JP H0932288 A JPH0932288 A JP H0932288A
Authority
JP
Japan
Prior art keywords
insertion hole
support
structural element
supporting
embedded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP7182898A
Other languages
Japanese (ja)
Inventor
Naomichi Kimura
尚道 木村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SANKIN ENG
SANKIN KK
TOHO KONETSUKUSU KK
Original Assignee
SANKIN ENG
SANKIN KK
TOHO KONETSUKUSU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SANKIN ENG, SANKIN KK, TOHO KONETSUKUSU KK filed Critical SANKIN ENG
Priority to JP7182898A priority Critical patent/JPH0932288A/en
Publication of JPH0932288A publication Critical patent/JPH0932288A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G15/00Forms or shutterings for making openings, cavities, slits, or channels
    • E04G15/06Forms or shutterings for making openings, cavities, slits, or channels for cavities or channels in walls of floors, e.g. for making chimneys
    • E04G15/063Re-usable forms
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L5/00Devices for use where pipes, cables or protective tubing pass through walls or partitions

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PROBLEM TO BE SOLVED: To flexibly cope with the case where a pipe passing through an insertion hole is dislocated from the center of the insertion hole by burying multiple support tools each having a filled section and a support pawl section in concrete structure element, and radially protruding the support pawl sections toward the center of the insertion hole. SOLUTION: The vertical extension section 5 of a support tool 1 is arranged along the outer peripheral face of a tube body B, and the edge of the tube body B is pinched by it and a pinch pawl 8. A support pawl section 3 is automatically protruded radially toward the center of the tube body B. The tube body B fitted with the support tools 1 at uniform intervals is combined with another formwork, concrete is placed, the tube body B is removed after concrete is hardened, and the operability is good. A plate material having strength, workability, and fire resistance is inserted into one end section of the insertion hole to block it for supporting the unhardened filler, and it is supported by the support pawl sections 3. The utilization range of the system of burying the support tool 1 into a concrete structure element in advance can be expanded.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、例えばスラブなど
のコンクリート構造要素に配線用のパイプや水道管など
のパイプ類を通すために形成する挿通孔におけるパイプ
類との隙間を埋める技術に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a technique for filling a gap between pipes such as slabs and the like in insertion holes formed for passing pipes such as wiring pipes and water pipes in concrete structural elements.

【0002】[0002]

【従来の技術】挿通孔におけるパイプ類との隙間を埋め
るには、一般にモルタルなどの硬化性の充填材を用いて
いる。そのため、隙間に充填した充填材が硬化するま
で、これを挿通孔の一端側から支持しておく必要があ
る。このような支持技術としては、例えば特公平4−3
8862号公報や特開昭61−130687号公報に見
られるような技術が知られている。
2. Description of the Related Art In order to fill gaps between insertion holes and pipes, a hardening filler such as mortar is generally used. Therefore, it is necessary to support the filler from one end side of the insertion hole until the filler filled in the gap is cured. As such a supporting technique, for example, Japanese Patent Publication No. 4-3
Techniques such as those found in JP-A-8862 and JP-A-61-130687 are known.

【0003】これらの技術は、シート状の支持具(特公
平4−38862号にあっては補修用補助材、特開昭6
1−130687号にあっては封止材保持用シート)を
用いて隙間を挿通孔の一端側で塞ぐようにしている。そ
のための支持具の設置は、最も多いケースであるコンク
リートスラブにおける挿通孔の場合には、スラブの下側
面から行なうことになる。このような設置作業は、スラ
ブの下側面が高い位置にあるため、何らかの足場がない
と進められない。しかるに労働条件に関する法的規制か
ら、脚立のような簡易な足場は用いることができない。
このため足場の設置のために多くの作業量を必要とする
場合が少なくない。また挿通孔のある位置が隅部に近接
しているような場合には足場の設置が極めて困難である
場合も少なくない。つまりシート状の支持具を用いる方
式は、高い位置にあり作業条件の良くないスラブの下側
面で支持具を設置しなければならないため、他の作業の
ための足場を利用できるなどして簡易に足場を確保でき
ない場合には作業効率が悪く、また労働コストも高くな
るという欠点を持っている。
These techniques are disclosed in Japanese Laid-Open Patent Publication No. 4-38862, which is a sheet-like support tool.
In No. 1-130687, a sealant holding sheet is used to close the gap at one end of the insertion hole. In the case of the insertion hole in the concrete slab, which is the most common case, the installation of the supporting tool for that purpose is performed from the lower surface of the slab. Such installation work cannot proceed without some scaffolding because the lower surface of the slab is at a high position. However, due to legal restrictions on working conditions, a simple scaffolding such as a stepladder cannot be used.
For this reason, it often happens that a large amount of work is required to install the scaffold. Further, when the position of the insertion hole is close to the corner, it is often difficult to install the scaffold. In other words, the method of using a sheet-shaped support tool requires that the support tool be installed on the lower side of the slab that is in a high position and in poor working conditions, so it is easy to use a scaffold for other work. It has the disadvantage that work efficiency is poor and labor costs are high if a foothold cannot be secured.

【0004】このような技術に対し、例えば実開昭63
−41146号公報に開示される技術のように、コンク
リート構造要素の形成の際に支持具(孔埋め用型わく)
を予めコンクリート構造要素に埋め込ませて設けておく
ようにする技術の場合には支持具の設置作業について問
題を招くことはない。しかし実開昭63−41146号
公報におけるような孔埋め用型わくを支持具として用い
る場合には、その孔埋め用型わくの構造から挿通孔に通
るパイプ類の位置が常に挿通孔の中心になければならな
いという制約がある。つまり孔埋め用型わくが1枚の板
状体で形成され、挿通孔の一端を全面的に塞ぐようにな
っているので、その中心に設けられている小孔からパイ
プ類が大きく外れる場合にはパイプ類と孔埋め用型わく
が干渉し合って適用できないという問題である。
For such a technique, for example, the actual exploitation Sho 63
Like the technique disclosed in JP-A-41146, a support tool (hole filling frame) when forming a concrete structural element.
In the case of the technique in which the above is embedded in the concrete structural element in advance, there is no problem in the work of installing the support. However, when a hole-filling frame as in Japanese Utility Model Laid-Open No. 63-41146 is used as a support, the position of the pipes passing through the hole is always located at the center of the hole because of the structure of the hole-filling frame. There is a constraint that it must be. In other words, since the hole-filling frame is formed of a single plate-like member and completely covers one end of the insertion hole, it is possible to remove pipes greatly from the small hole provided in the center of the insertion hole. Is a problem that pipes and hole filling frames interfere with each other and cannot be applied.

【0005】[0005]

【発明が解決しようとする課題】このような事情を背景
になされたのが本発明で、コンクリート構造要素の形成
の際に支持具を予めコンクリート構造要素に埋め込ませ
て設けておくようにする方式について、支持具の設置作
業が容易であるというその利点をさらに有効に活かせる
ように、挿通孔に通るパイプ類の位置が挿通孔の中心か
らずれている場合でも柔軟に対応できるようにすること
を目的としている。
The present invention has been made in view of such circumstances, and is a system in which a support tool is embedded in the concrete structural element in advance when the concrete structural element is formed. In order to make more effective use of the advantage that the installation work of the support is easy, it is possible to flexibly deal with the case where the position of the pipes passing through the insertion hole deviates from the center of the insertion hole. It is an object.

【0006】[0006]

【課題を解決するための手段】このような目的のために
本発明では、コンクリート構造要素に形成する挿通孔に
パイプ類を挿通させた後、パイプ類と挿通孔の隙間をモ
ルタルなどの充填材の充填・硬化により埋める際に、未
硬化の充填材を支持するための支持方法として、埋込み
部と支持爪部を備えた複数の支持具を、コンクリート構
造要素の形成の際に、それぞれの埋込み部を挿通孔の周
囲でコンクリート構造要素に埋め込むと共に、それぞれ
の支持爪部を挿通孔の一端部で挿通孔の中心に向かって
放射状に突出させる状態にして設けておき、挿通孔にパ
イプ類を挿通させた後に、このパイプ類を通すための切
込みを施した板材を前記複数の支持具の支持爪部に支持
させるように挿通孔に落とし込んで挿通孔の一端部に位
置させることにより、当該一端部を未硬化充填材の支持
のために塞ぐようにした支持方法を提供する。
For this purpose, in the present invention, after the pipes are inserted through the through holes formed in the concrete structural element, the space between the pipes and the through holes is filled with a filling material such as mortar. As a supporting method for supporting the uncured filler when filling and hardening by filling, multiple supports equipped with embedded parts and supporting claws are used to form the concrete structural elements. The parts are embedded in the concrete structural element around the insertion hole, and the supporting claws are provided so as to radially project toward the center of the insertion hole at one end of the insertion hole, and pipes are provided in the insertion hole. After the insertion, the cut plate material for passing the pipes is dropped into the insertion hole so as to be supported by the support claw portions of the plurality of support tools, and is positioned at one end of the insertion hole. Provide support method so as to close to the end portion of the support of the uncured filler.

【0007】この支持方法によると、支持具の個数を例
えば3〜4個程度とすれば、挿通孔に通すパイプ類が挿
通孔の中心から外れるようになっても、このパイプ類に
支持具の支持爪部が干渉することを実質的に避けること
ができ、また最終的に挿通孔の一端部を未硬化充填材の
支持のために塞ぐことになる板材もパイプ類の挿通位置
に合わせて切込みを施せるのでやはりパイプ類に干渉す
ることを避けることができる。即ち挿通孔に通るパイプ
類の位置が挿通孔の中心からずれている場合でも柔軟に
対応できる。
According to this supporting method, if the number of supporting tools is set to, for example, 3 to 4, even if the pipes passing through the insertion holes come off the center of the insertion holes, the supporting tools are attached to the pipes. Interference of the support claws can be substantially avoided, and the plate material that will eventually close one end of the insertion hole for supporting the uncured filler is also cut according to the insertion position of the pipes. Since it can be applied, it is possible to avoid interfering with pipes. That is, even if the position of the pipes passing through the insertion hole is deviated from the center of the insertion hole, it is possible to flexibly deal with it.

【0008】このような支持方法については、支持具の
埋込み部に係止手段を設け、コンクリート構造要素の形
成の際に挿通孔用の型枠として用いる筒体に前記係止手
段で支持具を係止させ、この状態でコンクリート構造要
素を形成する、つまり型枠にコンクリートを打ち込んで
硬化させることで支持具の埋込み部をコンクリート構造
要素に埋め込ませるようにすることができる。
With respect to such a supporting method, a locking means is provided in the embedded portion of the supporting tool, and the supporting tool is fitted to the tubular body used as a frame for the insertion hole when the concrete structural element is formed. It is possible to make the concrete structural element formed in the state of being locked, that is, by driving the concrete into the formwork and hardening it, so that the embedded portion of the support is embedded in the concrete structural element.

【0009】このようにすると、各支持具が挿通孔の一
端部でその周囲を取り囲み且つその支持爪部を挿通孔の
中心に向かって放射状に突出させる配置状態を挿通孔用
の型枠である筒体により固定的に与えることができ、各
支持具の設置作業をより簡単なものとすることができ
る。また各支持具を筒体の支持にも機能させることがで
き、筒体をコンクリート構造要素形成用の他の型枠に組
み合わせる作業の省力化にも役立たせることができる。
[0009] With this configuration, the support hole is in a form in which the respective support members surround the periphery of the insertion hole at one end and the supporting claws thereof project radially toward the center of the insertion hole. It can be fixedly provided by the cylindrical body, and the installation work of each support tool can be simplified. In addition, each support can also function as a support for the tubular body, which can be useful for labor saving in the work of assembling the tubular body with another formwork for forming a concrete structural element.

【0010】上記のような支持方法に用いる支持具は、
挿通孔の周囲でコンクリート構造要素に埋め込まれる埋
込み部と、この埋込み部のコンクリート構造要素への埋
込み状態により挿通孔の一端部で挿通孔の中心に向かっ
て突出する状態となる支持爪部を備えた構造とされる。
The support used in the above supporting method is
Equipped with an embedded part that is embedded in the concrete structural element around the insertion hole, and a support claw part that is in a state of protruding toward the center of the insertion hole at one end of the insertion hole depending on the embedded state of the embedded part in the concrete structural element. It has a different structure.

【0011】また上記のように埋込み部に係止手段を設
ける場合には、その係止手段は、平板状に形成された縦
方向延在部と、この縦方向延在部に対向状態に配され且
つ適度なバネ性を与えられた挟持爪とで形成し、縦方向
延在部を外周面に沿わせると共に挟持爪を内周面に沿わ
せることで筒体の縁を挟持させるような構造とするのが
好ましい。
Further, when the locking means is provided in the embedded portion as described above, the locking means is provided in a vertically extending portion formed in a flat plate shape, and is arranged in a state of being opposed to the vertically extending portion. And a clamping claw provided with an appropriate spring property, a structure in which the edge of the cylinder is clamped by arranging the longitudinally extending portion along the outer peripheral surface and the clamping claw along the inner peripheral surface. Is preferred.

【0012】このようにすると縦方向延在部と挟持爪の
間に筒体の縁を挟み込ませだけの簡単な操作で支持具を
筒体に係止させることができる。
With this configuration, the support tool can be locked to the tubular body by a simple operation in which the edge of the tubular body is sandwiched between the vertically extending portion and the holding claw.

【0013】[0013]

【実施の形態】以下、本発明の一実施形態について説明
する。先ず支持具の実施形態について説明する。図1に
示すように、支持具1は、埋込み部2と支持爪部3から
なる構造とする。
BEST MODE FOR CARRYING OUT THE INVENTION An embodiment of the present invention will be described below. First, an embodiment of the support tool will be described. As shown in FIG. 1, the support 1 has a structure including an embedded portion 2 and a support claw portion 3.

【0014】埋込み部2は、平板状に縦方向に延びてい
る縦方向延在部5と、この縦方向延在部5の下端からこ
れに直交する状態で同じく平板状で横方向に延びている
横方向延在部6、及び縦方向延在部5と対になって係止
手段を形成する挟持爪8を備え、さらにその横方向延在
部6と縦方向延在部5はコンクリート構造要素に埋め込
まれた際にコンクリートに対しアンカーとなるアンカー
爪9やアンカー爪10を備える。
The embedded portion 2 extends vertically in the form of a flat plate, and a vertically extending portion 5 extending from the lower end of the vertical extension portion 5 in the state of being orthogonal to the flat portion and extending in the horizontal direction. A laterally extending portion 6 and a vertically extending portion 5 and a holding claw 8 which forms a locking means in pairs with the vertically extending portion 5. Further, the laterally extending portion 6 and the vertically extending portion 5 have a concrete structure. An anchor claw 9 and an anchor claw 10 are provided as an anchor for concrete when embedded in the element.

【0015】縦方向延在部5と横方向延在部6は一枚の
鋼板をプレス加工することで形成するようにする。また
挟持爪8は、縦方向延在部5の中央部を部分的に細長く
切り起こして突っかい状に曲折させることでバネ性を与
えて形成する。このようにすると加工が容易になり、ま
た材料の節約にもなる。同様の理由からアンカー爪9、
10も横方向延在部6や縦方向延在部5を部分的に切り
起こして形成する。
The longitudinally extending portion 5 and the laterally extending portion 6 are formed by pressing one steel plate. Further, the sandwiching claw 8 is formed by giving a spring property by partially cutting and raising the central portion of the vertically extending portion 5 and bending it in a protruding shape. This facilitates processing and saves material. For the same reason, the anchor claw 9,
10 is also formed by partially cutting and raising the laterally extending portion 6 and the longitudinally extending portion 5.

【0016】支持爪部3は、縦方向延在部5と同レベル
にして縦方向延在部5の下端から横方向延在部6とは逆
方向に延設させる。また支持爪部3は、上記のようにし
て挟持爪8を形成させる関係からこの挟持爪8を挟むよ
うにして、左右対にして2個設けるようにする。この両
支持爪部3、3も縦方向延在部5や横方向延在部6と共
に一枚の鋼板から形成するようにすると加工性を上げる
ことできるが、材料の効率的利用という点からは別に形
成して溶接などで接続するようにするのが好ましい。
The supporting claw portion 3 is provided at the same level as the longitudinally extending portion 5 and extends from the lower end of the longitudinally extending portion 5 in the direction opposite to the laterally extending portion 6. Further, two supporting claws 3 are provided as a pair of right and left so as to sandwich the sandwiching claw 8 from the relationship of forming the sandwiching claw 8 as described above. If both supporting claws 3 and 3 are formed from a single steel plate together with the longitudinally extending portion 5 and the laterally extending portion 6, the workability can be improved, but from the viewpoint of efficient use of the material. It is preferable that they are separately formed and connected by welding or the like.

【0017】このような支持具1は、図1に示すよう
に、挿通孔形成用の型枠として用いられる一般にボイド
と呼ばれる筒体Bに係止させて用いる。一つの筒体Bつ
まり一つの挿通孔について好ましい個数は図1に見られ
るように3個あるいは4個程度であり、それぞれを等間
隔で配する。各支持具1は、縦方向延在部5が外周面に
沿う状態にして縦方向延在部5と挟持爪8でその縁を挟
持させることで筒体Bに係止させる。そうするとその支
持爪部3が自ずと筒体Bの中心に向かって放射状に突出
する状態となる。また同時に横方向延在部6が筒体Bの
外方に向けて放射状に突出する状態となる。このことか
ら分かるように、3個の支持具1は、筒体Bに支持され
るだけでなく、逆に筒体Bをコンクリート構造要素形成
用の他の型枠に組み合わる場合の支持に機能する。
As shown in FIG. 1, such a supporting tool 1 is used by being locked to a cylindrical body B generally called a void which is used as a mold for forming an insertion hole. The preferable number of one cylindrical body B, that is, one insertion hole is about 3 or 4 as shown in FIG. 1, and each of them is arranged at equal intervals. Each support 1 is locked to the tubular body B by holding the vertically extending portion 5 along the outer peripheral surface and holding the edge between the vertically extending portion 5 and the holding claw 8. Then, the support claws 3 are naturally in a state of radially projecting toward the center of the cylindrical body B. At the same time, the laterally extending portions 6 are radially projected toward the outside of the cylindrical body B. As can be seen from this, the three support tools 1 are not only supported by the tubular body B, but also function as a support when the tubular body B is conversely combined with another formwork for forming a concrete structural element. To do.

【0018】このようにしてその支持にも機能する支持
具1を取り付けた筒体Bをコンクリート構造要素形成用
の他の型枠に組み合わせた状態でコンクリートの打ち込
みを行ない、コンクリートの硬化後に筒体Bを取り去れ
ば、図2に見られるようにしてコンクリート構造要素C
に埋込み部2が埋め込まれた状態で支持具1が挿通孔H
の周囲に配列し、またそれぞれの支持爪部3が挿通孔の
一端部で挿通孔Hの中心に向かって放射状に突出する状
態が得られる。
In this way, the cylinder B, to which the support 1 which also functions to support it is attached, is combined with another formwork for forming a concrete structural element, concrete is driven, and the cylinder is cured after the concrete is hardened. If B is removed, the concrete structural element C as shown in FIG.
The support 1 is inserted into the insertion hole H with the embedding part 2 embedded therein.
It is possible to obtain a state in which the support claws 3 are arranged around the circumference of the insertion hole H and radially project toward the center of the insertion hole H at one end of the insertion hole.

【0019】このようにして挿通孔Hに沿って設けた各
支持具1を利用して挿通孔Hの一端部を未硬化充填材の
支持のために塞ぐには、例えばロックウール板のように
未硬化充填材の支持に必要な適当な強度がありまた加工
も容易でありしかも耐火性のある板材11を挿通孔Hに
落とし込み、これを支持爪部3に支持させる。板材11
は、図3に示すように、2枚の半割り片11p、11p
を組み合わせて用い、各半割り片11pには、支持具1
に当たる部分に切込み12を入れ、また挿通孔Hに通る
パイプPを避けるための切込み13を入れる。
In order to support one end of the insertion hole H for supporting the uncured filling material by using each support 1 provided along the insertion hole H in this manner, for example, a rock wool plate is used. A plate material 11 having appropriate strength necessary for supporting the uncured filler, easy to process, and fire resistant is dropped into the insertion hole H, and is supported by the support claw portion 3. Plate material 11
Is, as shown in FIG. 3, two halves 11p and 11p.
Used in combination, and the support 1
A notch 12 is made in the portion corresponding to, and a notch 13 for avoiding the pipe P passing through the insertion hole H is made.

【0020】[0020]

【発明の効果】以上説明したように、本発明によると、
挿通孔に通るパイプ類の位置が挿通孔の中心からずれて
いる場合でも柔軟に対応することができ、コンクリート
構造要素の形成の際に支持具を予めコンクリート構造要
素に埋め込ませて設けておくようにする方式の利用範囲
を拡大することができる。
As described above, according to the present invention,
Even if the position of the pipes passing through the insertion hole is deviated from the center of the insertion hole, it is possible to flexibly cope with it, and when forming the concrete structural element, the support tool should be embedded in the concrete structural element in advance. The range of use of the method can be expanded.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施形態による支持具を筒体に係止
させた状態の斜視図。
FIG. 1 is a perspective view showing a state in which a support according to an embodiment of the present invention is locked to a cylinder.

【図2】図1の支持具の挿通孔周囲における配置状態の
断面図。
FIG. 2 is a cross-sectional view of an arrangement state around the insertion hole of the support tool of FIG.

【図3】図1の支持具に支持させて挿通孔の一端部を塞
ぐのに用いる板材の平面図。
FIG. 3 is a plan view of a plate member that is supported by the support tool of FIG. 1 and is used to close one end of the insertion hole.

【符号の説明】[Explanation of symbols]

1 支持具 2 埋込み部 3 支持爪部 5 縦方向延在部 8 挟持爪 11 板材 13 切込み B 筒体 C コンクリート構造要素 H 挿通孔 P パイプ 1 Support Tool 2 Embedded Section 3 Support Claw Section 5 Longitudinal Extension Section 8 Clamping Claw 11 Plate Material 13 Notch B Cylinder C Concrete Structural Element H Insertion Hole P Pipe

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 コンクリート構造要素に形成する挿通孔
にパイプ類を挿通させた後、パイプ類と挿通孔の隙間を
モルタルなどの充填材の充填・硬化により埋める際に、
未硬化の充填材を支持するための支持方法において、埋
込み部と支持爪部を備えてなる複数の支持具を、コンク
リート構造要素の形成の際に、それぞれの埋込み部を挿
通孔の周囲でコンクリート構造要素に埋め込むと共に、
それぞれの支持爪部を挿通孔の一端部で挿通孔の中心に
向かって放射状に突出させる状態にして設けておき、挿
通孔にパイプ類を挿通させた後に、このパイプ類を通す
ための切込みを施した板材を前記複数の支持具の支持爪
部に支持させるように挿通孔に落とし込んで挿通孔の一
端部に位置させることにより、当該一端部を未硬化充填
材の支持のために塞ぐようにしたことを特徴とする支持
方法。
1. When a pipe is inserted through an insertion hole formed in a concrete structural element, and then a gap between the pipe and the insertion hole is filled and hardened with a filling material such as mortar,
In a supporting method for supporting an uncured filler, a plurality of supporting members each having an embedded portion and a supporting claw portion are provided, and when the concrete structural element is formed, each embedded portion is covered with concrete around the through hole. While embedding in the structural element
The supporting claws are provided at one end of the insertion hole in a state of radially projecting toward the center of the insertion hole, and after inserting the pipes into the insertion hole, make a cut for inserting the pipes. The applied plate material is dropped into the insertion hole so as to be supported by the support claw portions of the plurality of support tools and positioned at one end portion of the insertion hole, so that the one end portion is closed for supporting the uncured filler. A supporting method characterized by having done.
【請求項2】 支持具の埋込み部に係止手段を設け、コ
ンクリート構造要素の形成の際に挿通孔用の型枠として
用いる筒体に前記係止手段で支持具を係止させ、この状
態でコンクリート構造要素を形成することで支持具の埋
込み部をコンクリート構造要素に埋め込ませるようにし
た請求項1に記載の支持方法。
2. A locking means is provided in an embedded portion of the support tool, and the support tool is locked by the locking means to a tubular body used as a mold for an insertion hole when forming a concrete structural element, and in this state. The supporting method according to claim 1, wherein the embedded portion of the support is embedded in the concrete structural element by forming the concrete structural element with.
【請求項3】 請求項1に記載の支持方法に用いる支持
具であって、挿通孔の周囲でコンクリート構造要素に埋
め込まれる埋込み部と、この埋込み部のコンクリート構
造要素への埋込み状態により挿通孔の一端部で挿通孔の
中心に向かって突出する状態となる支持爪部を備えてな
る支持具。
3. A support tool used in the supporting method according to claim 1, wherein an embedding portion embedded in the concrete structural element around the insertion hole and an insertion hole depending on an embedding state of the embedding portion in the concrete structural element. A support tool provided with a support claw portion that projects toward the center of the insertion hole at one end of the support.
【請求項4】 請求項2に記載の支持方法に用いる支持
具であって、埋込み部の係止手段は、縦方向に延びてい
る縦方向延在部と、この縦方向延在部に対向状態に配さ
れ挟持爪とからなり、縦方向延在部を外周面に沿わせる
と共に挟持爪を内周面に沿わせることで筒体の縁を挟持
するようにされてなる支持具。
4. The support tool used in the supporting method according to claim 2, wherein the locking means of the embedded portion is a longitudinally extending portion that extends in the longitudinal direction and opposes the longitudinally extending portion. A support tool which is arranged in a state and is configured to hold a rim of a tubular body by arranging a vertically extending portion along an outer peripheral surface and a holding claw along an inner peripheral surface.
JP7182898A 1995-07-19 1995-07-19 Support method and tool for gap filling filler for pipe insertion hole Pending JPH0932288A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7182898A JPH0932288A (en) 1995-07-19 1995-07-19 Support method and tool for gap filling filler for pipe insertion hole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7182898A JPH0932288A (en) 1995-07-19 1995-07-19 Support method and tool for gap filling filler for pipe insertion hole

Publications (1)

Publication Number Publication Date
JPH0932288A true JPH0932288A (en) 1997-02-04

Family

ID=16126318

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7182898A Pending JPH0932288A (en) 1995-07-19 1995-07-19 Support method and tool for gap filling filler for pipe insertion hole

Country Status (1)

Country Link
JP (1) JPH0932288A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1999058199A1 (en) * 1998-05-13 1999-11-18 3M Innovative Properties Company Intumescable fire stop device having quick fasteners
JP2010174525A (en) * 2009-01-30 2010-08-12 Mirai Ind Co Ltd Sleeve fixing implement
KR101217696B1 (en) * 2009-12-21 2013-01-02 이피아이주식회사 A paperboard sleeve with improved size index method and a method for constructing vertical through-holes using the same
KR200489758Y1 (en) * 2018-09-05 2019-08-02 고정석 Sleeve fixing apparatus for construction steel frame
DE102021204139A1 (en) 2021-04-26 2022-10-27 James Hardie Europe Gmbh Pipe collar, fire protection collar with such a pipe collar, ceiling duct, ceiling with such a ceiling duct and method for installing a ceiling duct

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1999058199A1 (en) * 1998-05-13 1999-11-18 3M Innovative Properties Company Intumescable fire stop device having quick fasteners
JP2010174525A (en) * 2009-01-30 2010-08-12 Mirai Ind Co Ltd Sleeve fixing implement
KR101217696B1 (en) * 2009-12-21 2013-01-02 이피아이주식회사 A paperboard sleeve with improved size index method and a method for constructing vertical through-holes using the same
KR200489758Y1 (en) * 2018-09-05 2019-08-02 고정석 Sleeve fixing apparatus for construction steel frame
DE102021204139A1 (en) 2021-04-26 2022-10-27 James Hardie Europe Gmbh Pipe collar, fire protection collar with such a pipe collar, ceiling duct, ceiling with such a ceiling duct and method for installing a ceiling duct

Similar Documents

Publication Publication Date Title
JPH0932288A (en) Support method and tool for gap filling filler for pipe insertion hole
WO2007123329A1 (en) Mold for manufacturing u-type side gutter and its manufacturing method using the mold
JP3851974B2 (en) Steel foundation
JPH07292783A (en) Connective structure of prestressed concrete members
JP3707006B2 (en) New method for opening openings in existing masonry walls
JP2714763B2 (en) Construction method of reinforced concrete structure
JP3788853B2 (en) Forming method for column base part mold and member for connecting dam plate of column base part form
JP3329690B2 (en) Assembling device for reinforcing bars for segments
JPH08189189A (en) Jig for correcting upper part of form
JPH08302705A (en) Method of slope stabilizing construction
JPH0732100U (en) Concrete splicing formwork
JP3655754B2 (en) Connection method of remaining formwork in formwork assembly such as concrete retaining wall
JPH0742186A (en) Waterproof concrete placing device around manhole and method thereof
JPH0355682Y2 (en)
KR200277914Y1 (en) A clamp
KR100288983B1 (en) Unit panel for slip form to form lining wall of vertical tunnel
JPH07239058A (en) Through sleeve fixture to formwork
JPH06272378A (en) Supporting structure for precast concrete form
JPH08239850A (en) Execution method and device for retaining wall
JP4418337B2 (en) Floor forming method and floor forming structure
JPS5942445Y2 (en) Step temporary structure in concrete formwork
JPH0819727B2 (en) Hole filling method for concrete slabs
JPH11293919A (en) Retaining structure of form and method thereof
JPH1121913A (en) Precast-concrete foundation block
JPS6025590B2 (en) Method for joining old and new concrete using studded plates

Legal Events

Date Code Title Description
A601 Written request for extension of time

Effective date: 20040510

Free format text: JAPANESE INTERMEDIATE CODE: A601

A602 Written permission of extension of time

Free format text: JAPANESE INTERMEDIATE CODE: A602

Effective date: 20040513

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040812

RD14 Notification of resignation of power of sub attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7434

Effective date: 20050311