- JPH09317193A JPH09317193A JP16093096A JP16093096A JPH09317193A JP H09317193 A JPH09317193 A JP H09317193A JP 16093096 A JP16093096 A JP 16093096A JP 16093096 A JP16093096 A JP 16093096A JP H09317193 A JPH09317193 A JP H09317193A
- Authority
- JP
- Japan
- Prior art keywords
- sleeve hole
- mounting member
- floor slab
- moving plate
- flange
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、開口部閉塞具に関
し、特に作業の簡易化と迅速性を向上させ、確実に開口
部を閉塞することができる開口部閉塞具に関するもので
ある。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an opening obturator, and more particularly to an opening obturator that can improve the simplification and speed of work and can reliably close an opening.
【0002】[0002]
【従来の技術】建築物等の構築物の床スラブには、上下
水道や電気、ガス等の配管工事用のスリーブ孔を穿設さ
れている。このスリーブ孔に配管を配設するが、配管の
大きさが一定でないことから、床スラブには配管より大
きめのスリーブ孔が形成されており、スリーブ孔に配管
を配設後、配管とスリーブ孔との開口部(隙間)をモル
タル等の閉塞材により閉塞するようにしている。2. Description of the Related Art A floor slab of a structure such as a building is provided with a sleeve hole for plumbing such as water and sewage, electricity and gas. Piping is arranged in this sleeve hole, but since the size of the piping is not constant, there is a sleeve hole that is larger than the piping in the floor slab. The opening (gap) between and is closed by a blocking material such as mortar.
【0003】しかし、工事の関係上、必然的に配管工事
が終了し、閉塞作業が完了するまでには多くの日数がか
かる。この閉塞作業が完了するまでには作業の過程で水
が使用されたり、雨になったりすることにより水、雨が
溜まり、その汚れた水はスリーブ孔から階下に流下す
る。これを防止するためにスリーブ孔をベニヤ板等で閉
塞することが知られている。However, due to the construction work, it takes many days until the piping work is completed and the closing work is completed. By the time the closing work is completed, water is used in the work process or becomes rain, so that water and rain collect and the dirty water flows down from the sleeve hole to the downstairs. In order to prevent this, it is known to close the sleeve hole with a veneer plate or the like.
【0004】[0004]
【発明が解決しようとする課題】しかしながら、前記の
従来技術において、水は階下に流下することは防止でき
るが、実際上ベニヤ板でスリーブ孔を閉塞するには、移
動しないように、そのスリーブ孔の孔径に合ったような
突起部を形成するとか、固定するための手段を施さなけ
ればならないという問題点があった。However, in the above-mentioned prior art, although water can be prevented from flowing downstairs, in order to actually close the sleeve hole with the plywood plate, the sleeve hole must be moved so that it does not move. There has been a problem in that means for forming a protrusion that matches the hole diameter or providing a fixing means must be provided.
【0005】本発明は、これらの事情に鑑み、床スラブ
のスリーブ孔の上面を覆うような載置部材を載置させ
て、この載置部材に設けたフランジ部材と上下動板間に
設けた弾性部材を圧縮で膨出させてスリーブ孔を閉塞さ
せるようにした開口部閉塞具を提供することを目的とす
るものである。In view of these circumstances, the present invention mounts a mounting member that covers the upper surface of the sleeve hole of the floor slab, and mounts it between the flange member provided on the mounting member and the vertical moving plate. An object of the present invention is to provide an opening obturator in which an elastic member is bulged by compression to close a sleeve hole.
【0006】[0006]
【課題を解決するための手段】本発明は、前記課題を解
決するために、次の技術手段を採用した。請求項1記載
の発明においては、建築物の床スラブに穿設した配管工
事用のスリーブ孔の閉塞具で、床スラブのスリーブ孔の
上面を跨ぐような載置部材と、該載置部材下面に規制案
内部材を2本以上設けたスリーブ孔に遊嵌できるフラン
ジ部材を設けて、さらに、載置部材と、スリーブ孔に遊
嵌する上下動板に設けた締め付けボルトとナットとを螺
合するように構成され、この上下動板には前記規制案内
部材が挿入される案内孔が形成され、前記フランジ部材
と上下動板間に圧縮により膨出する弾性部材を介在させ
るという技術手段を採用した。The present invention employs the following technical means in order to solve the above-mentioned problems. According to the first aspect of the present invention, there is provided a mounting member, which is a blocker for a sleeve hole for plumbing provided in a floor slab of a building, and which straddles an upper surface of the sleeve hole of the floor slab, and a lower surface of the mounting member. Is provided with a flange member capable of loosely fitting in a sleeve hole provided with two or more regulating guide members, and further, a mounting member is screwed with a tightening bolt and a nut provided in a vertical moving plate loosely fitted in the sleeve hole. The vertical moving plate is formed with a guide hole into which the regulating guide member is inserted, and an elastic member that bulges due to compression is interposed between the flange member and the vertical moving plate. .
【0007】請求項2記載の発明においては、請求項1
の開口部閉塞具に加えて、弾性部材を圧縮により膨出し
易くするために、フランジ部下面と上下動板上面とを略
球形部に形成するという技術手段を採用した。[0007] According to the second aspect of the present invention, the first aspect is provided.
In addition to the opening obturator, the technical means of forming the lower surface of the flange portion and the upper surface of the upper and lower moving plates into a substantially spherical portion in order to make the elastic member easily bulge due to compression.
【0008】[0008]
【発明の実施の形態】本発明は、床スラブのスリーブ孔
に対して、配管工事に着手する迄の間のスリーブ孔の閉
塞を簡単にできるようにしたものである。BEST MODE FOR CARRYING OUT THE INVENTION The present invention makes it possible to easily close a sleeve hole of a floor slab before starting piping work.
【0009】それは、床スラブのスリーブ孔をフランジ
部材と上下動板の間に介在させた弾性部材を、載置部材
と上下動板に設けたボルト、とナットとで螺合させて締
め付けることによって圧縮させ、外側に膨出させること
によって、スリーブ孔を閉塞させるようにした開口部閉
塞具である。This is because the elastic member having the sleeve hole of the floor slab interposed between the flange member and the vertical moving plate is screwed by the mounting member, the bolt provided on the vertical moving plate, and the nut to be compressed. The opening blocker is configured to block the sleeve hole by bulging outward.
【0010】さらに、この開口部閉塞具を具体的な実施
の形態で説明すると、建築物の床スラブに穿設した配管
工事用のスリーブ孔の閉塞具で、床スラブのスリーブ孔
の上面を覆うような載置部材と、該載置部材下面に規制
案内部材を2本以上設けたスリーブ孔に遊嵌できるフラ
ンジ部材を設けて、さらに、載置部材と、スリーブ孔に
遊嵌する上下動板に設けた締め付けボルトとナットとを
螺合するように構成され、この上下動板には前記規制案
内部材が挿入される案内孔が形成され前記フランジ部材
と上下動板間に圧縮により膨出する弾性部材を介在させ
ることができるものである。The opening obturator will be described in more detail with reference to a specific embodiment. The obstruction device for a sleeve hole for piping work provided in a floor slab of a building covers the upper surface of the sleeve hole of the floor slab. Such a mounting member, and a flange member which can be loosely fitted in a sleeve hole provided with two or more regulation guide members on the lower surface of the mounting member are further provided, and the mounting member and a vertical moving plate loosely fitted in the sleeve hole. Is configured to be screwed with a tightening bolt and a nut, and a guide hole into which the regulation guide member is inserted is formed in the vertical moving plate, and bulges due to compression between the flange member and the vertical moving plate. An elastic member can be interposed.
【0011】[0011]
【実施例】以下、本発明の実施例を添付図面で詳細に説
明する。先ず、図1、図2に基づいて本発明の第1実施
例の開口部閉塞具について説明する。DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments of the present invention will be described below in detail with reference to the accompanying drawings. First, the opening obturator according to the first embodiment of the present invention will be described with reference to FIGS. 1 and 2.
【0012】床スラブ1に配管を配設するスリーブ孔2
を穿設し、該スリーブ孔2に配管を貫通配設するまでス
リーブ孔2を閉塞する必要が生じる。床スラブ1に、配
管外径より若干大きめのスリーブ孔2を穿設し、該スリ
ーブ孔2は配管を配設するまでは閉塞する必要がある。Sleeve hole 2 for arranging piping in floor slab 1
It is necessary to close the sleeve hole 2 until the pipe is penetrated through the sleeve hole 2. The floor slab 1 is provided with a sleeve hole 2 slightly larger than the pipe outer diameter, and the sleeve hole 2 needs to be closed until the pipe is arranged.
【0013】そこで、具体的に第1実施例として図1、
図2に基づいて詳細に説明する。床スラブ1に穿設した
スリーブ孔2を閉塞するように床スラブ上面3を跨ぐ大
きさの載置部材4を設け、該載置部材4に設けたフラン
ジ部材5を床スラブ上面3と遊嵌させて跨らせるように
する。Therefore, as a first embodiment, as shown in FIG.
This will be described in detail with reference to FIG. A mounting member 4 having a size straddling the floor slab upper surface 3 is provided so as to close the sleeve hole 2 formed in the floor slab 1, and the flange member 5 provided on the mounting member 4 is loosely fitted to the floor slab upper surface 3. Let them straddle.
【0014】そして、前記載置部材4下面に、スリーブ
孔2に遊嵌できるようにフランジ部材5を固設し、この
フランジ部材5に規制案内部材6を2本以上設け、さら
に載置部材4とフランジ部材5に締め付けボルト7が挿
入できる孔を穿設し、スリーブ孔2に遊嵌する上下動板
8に一体的に設けたボルト7を挿入してナット15とで
螺合するように設けたものである。この上下動板8に
は、前記規制案内部材6が挿入される案内孔10が形成
され、前記フランジ部材5と上下動板8間での圧縮によ
り膨出する弾性部材11を介在し、フランジ部材5に固
設された規制案内部材6と上下動板8に形成した案内孔
10とによって規制されながら上下動だけ行うように
し、これによって、締め付けボルト7とナット15との
螺合締め付けによって、フランジ部材5と上下動板8と
の間に介在させた弾性部材11は圧縮され、外側に膨出
して、スリーブ孔2を閉塞するものである。A flange member 5 is fixedly mounted on the lower surface of the mounting member 4 so that it can be loosely fitted in the sleeve hole 2. Two or more regulating guide members 6 are provided on the flange member 5, and the mounting member 4 is further provided. A hole into which the tightening bolt 7 can be inserted is bored in the flange member 5, and the bolt 7 integrally provided in the vertical moving plate 8 loosely fitted in the sleeve hole 2 is inserted and screwed with the nut 15. It is a thing. A guide hole 10 into which the regulation guide member 6 is inserted is formed in the vertical moving plate 8, and an elastic member 11 that bulges due to compression between the flange member 5 and the vertical moving plate 8 is interposed, and a flange member is formed. Only the vertical movement is performed while being regulated by the regulation guide member 6 fixedly provided on the No. 5 and the guide hole 10 formed in the vertical movement plate 8, whereby the flange is formed by screwing and tightening the tightening bolt 7 and the nut 15. The elastic member 11 interposed between the member 5 and the vertical moving plate 8 is compressed and bulges outward to close the sleeve hole 2.
【0015】次に、図3、図4に基づいて本発明の第2
実施例を説明する。前記第1実施例との違いは、フラン
ジ部材5と上下動板8との間に介在した圧縮により膨出
する弾性部材11をより膨出が容易に確実に外側に膨出
してスリーブ孔を閉塞できるようにしたもので、フラン
ジ部下面12と、上下動板上面13の形状を略球形部1
4に形成し、さらに載置部材4とフランジ部材5に一体
的に締め付けボルト7を設け、スリーブ孔2に遊嵌する
上下動板8に設けた長ナット9と螺合するように設けた
もので、その他は全て同一なので詳細な説明は省略す
る。Next, the second aspect of the present invention will be described with reference to FIGS.
An embodiment will be described. The difference from the first embodiment is that the elastic member 11 interposed between the flange member 5 and the vertical moving plate 8 that bulges due to compression is bulged more easily and surely to occupy the sleeve hole. In this configuration, the lower surface 12 of the flange portion and the upper surface 13 of the vertical moving plate are formed into a substantially spherical portion 1.
4, the mounting member 4 and the flange member 5 are integrally provided with a tightening bolt 7 so as to be screwed with a long nut 9 provided on a vertical moving plate 8 which is loosely fitted in the sleeve hole 2. However, since all others are the same, detailed description will be omitted.
【0016】[0016]
【発明の効果】本発明は、以上の構成を採用した結果、
次の効果を得ることができる。 (1)ボルト・ナットの締め付けだけで、弾性部材を外
側に膨出させることによりスリーブ孔を閉塞することが
できる。しかも、作業の安全性、容易性、迅速性に優
れ、施工費も安価である。As a result of adopting the above configuration, the present invention provides
The following effects can be obtained. (1) The sleeve hole can be closed by swelling the elastic member outward only by tightening the bolt and nut. Moreover, it is excellent in safety, easiness and speed of work, and the construction cost is low.
【図1】本発明の第1実施例に関する開口部閉塞具の概
略正断面図である。FIG. 1 is a schematic front sectional view of an opening obturator according to a first embodiment of the present invention.
【図2】前記第1実施例の開口部閉塞具を示す概略平面
図である。FIG. 2 is a schematic plan view showing the opening obturator of the first embodiment.
【図3】本発明の第2実施例に関する開口部閉塞具の概
略正断面図である。FIG. 3 is a schematic front sectional view of an opening obturator according to a second embodiment of the present invention.
【図4】前記第2実施例の開口部閉塞具を示す概略平面
図である。FIG. 4 is a schematic plan view showing an opening obturator of the second embodiment.
1‥‥床スラブ 2‥‥スリーブ孔 3‥‥床スラブ上面 4‥‥載置部材 5‥‥フランジ部材 6‥‥規制案内部
材 7‥‥締め付けボルト 8‥‥上下動板 9‥‥長ナット 10‥‥案内孔 11‥‥弾性部材 12‥‥フランジ
部下面 13‥‥上下動板上面 14‥‥略球形部 15‥‥ナット1 ...... Floor slab 2 ...... Sleeve hole 3 ...... Floor slab upper surface 4 ...... Mounting member 5 ...... Flange member 6 ...... Regulation guide member 7 ...... Tightening bolt 8 ...... Vertical moving plate 9 ...... Long nut 10 Guide hole 11 Elastic member 12 Flange bottom surface 13 Vertical moving plate top surface 14 Approximately spherical portion 15 Nut
───────────────────────────────────────────────────── フロントページの続き (72)発明者 浜田 任朗 東京都世田谷区池尻3−21−34 (72)発明者 倉嶋 宏行 東京都世田谷区世田谷4−4−20 メゾン 世田谷 202号 (72)発明者 伊澤 壽博 東京都世田谷区若林4−14−27 ドゥハイ ム若林303 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Jiro Hamada 3-21-34 Ikejiri, Setagaya-ku, Tokyo (72) Inventor Hiroyuki Kurashima 4-4-20 Setagaya, Setagaya-ku, Tokyo Maison Setagaya 202 (72) Invention Toshihiro Izawa 4-14-27 Wakabayashi, Setagaya-ku, Tokyo Duheim Wakabayashi 303
Claims (2)
のスリーブ孔の閉塞具で、床スラブのスリーブ孔の上面
を跨ぐような載置部材と、該載置部材下面に規制案内部
材を2本以上設けたスリーブ孔に遊嵌できるフランジ部
材を設けて、さらに、載置部材と、スリーブ孔に遊嵌す
る上下動板に設けた締め付けボルトとナットとを螺合す
るように構成され、この上下動板には前記規制案内部材
が挿入される案内孔が形成され、前記フランジ部材と上
下動板間に圧縮により膨出する弾性部材を介在させたこ
とを特徴とする開口部閉塞具。1. A mounting member for covering a sleeve hole of a floor slab for a piping work, the mounting member straddling an upper surface of the sleeve hole of the floor slab, and a regulation guide member on a lower surface of the mounting member. A flange member that can be loosely fitted in a sleeve hole provided with two or more is provided, and the mounting member is further screwed with a tightening bolt and a nut provided in the vertical moving plate that is loosely fitted in the sleeve hole. A guide hole into which the regulating guide member is inserted is formed in the vertical moving plate, and an elastic member that bulges due to compression is interposed between the flange member and the vertical moving plate. .
めに、フランジ部下面と上下動板上面とを略球形部に形
成したことを特徴とする請求項1記載の開口部閉塞具。2. The opening obturator according to claim 1, wherein the lower surface of the flange portion and the upper surface of the upper and lower moving plates are formed in a substantially spherical portion so that the elastic member can be easily expanded by compression.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16093096A JPH09317193A (en) | 1996-06-01 | 1996-06-01 | Closing device of opening section |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16093096A JPH09317193A (en) | 1996-06-01 | 1996-06-01 | Closing device of opening section |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH09317193A true JPH09317193A (en) | 1997-12-09 |
Family
ID=15725336
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP16093096A Pending JPH09317193A (en) | 1996-06-01 | 1996-06-01 | Closing device of opening section |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH09317193A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2008013139A1 (en) * | 2006-07-27 | 2008-01-31 | Kyoto Intellectual Property Club, Inc. | Curing cover unit and seal unit |
JP2008163645A (en) * | 2006-12-28 | 2008-07-17 | Toda Constr Co Ltd | Slab dead hole curing device |
WO2011150167A2 (en) * | 2010-05-26 | 2011-12-01 | Audrey Barnes | Method of repairing concrete floors and system for same |
CN105401738A (en) * | 2015-12-15 | 2016-03-16 | 国网北京市电力公司 | Hole cover plate assembly covering hole |
CN109518984A (en) * | 2019-01-09 | 2019-03-26 | 宁夏第建筑有限公司 | A kind of cast-in-situ floor reserved opening protective device and construction technology |
CN109680940A (en) * | 2019-02-01 | 2019-04-26 | 山西三建集团有限公司 | Preserved pipeline passes through the pre-embedded device and built-in process in hole in floor concrete casting |
-
1996
- 1996-06-01 JP JP16093096A patent/JPH09317193A/en active Pending
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2008013139A1 (en) * | 2006-07-27 | 2008-01-31 | Kyoto Intellectual Property Club, Inc. | Curing cover unit and seal unit |
KR100947952B1 (en) * | 2006-07-27 | 2010-03-15 | 가부시키 가이샤 교토 지자이 구락부 | Cure cover unit and seal unit |
JP2008163645A (en) * | 2006-12-28 | 2008-07-17 | Toda Constr Co Ltd | Slab dead hole curing device |
WO2011150167A2 (en) * | 2010-05-26 | 2011-12-01 | Audrey Barnes | Method of repairing concrete floors and system for same |
WO2011150167A3 (en) * | 2010-05-26 | 2012-03-08 | Audrey Barnes | Method of repairing concrete floors and system for same |
CN105401738A (en) * | 2015-12-15 | 2016-03-16 | 国网北京市电力公司 | Hole cover plate assembly covering hole |
CN109518984A (en) * | 2019-01-09 | 2019-03-26 | 宁夏第建筑有限公司 | A kind of cast-in-situ floor reserved opening protective device and construction technology |
CN109680940A (en) * | 2019-02-01 | 2019-04-26 | 山西三建集团有限公司 | Preserved pipeline passes through the pre-embedded device and built-in process in hole in floor concrete casting |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5232008A (en) | Two handle faucet and mounting structure therefor | |
CA2475465A1 (en) | Combined faucet and drain assembly | |
JPH09317193A (en) | Closing device of opening section | |
ATE543956T1 (en) | REGULATING AND SHUT-OFF VALVE AND METHOD FOR FINAL ASSEMBLY | |
AU2005219593B2 (en) | Control valve for door closer | |
KR102231491B1 (en) | Connection structure of open joint exterior panel with seismic resistance and waterproof performance | |
CA2278855A1 (en) | Sealing gasket | |
JP4495324B2 (en) | Permanent water installation method for water control doors | |
US4288059A (en) | Sluice gate | |
JP3695656B2 (en) | Veranda pipe fittings | |
KR20020005251A (en) | Anchor bolt | |
JP2005194770A (en) | Soundproof and deodorant device of manhole | |
KR200215990Y1 (en) | Construction of Door-Hinge Device Having Torsion | |
JP2001208223A (en) | Discharge vale | |
KR200448694Y1 (en) | Complex set fluid valve | |
KR200211315Y1 (en) | an overflow lid to prevent brakeaway and to eliminate noise | |
KR20060053481A (en) | Pipe cover | |
JPH08246530A (en) | Connecting structure between drain ditch and trap | |
KR200356134Y1 (en) | Sealing structure of manhole | |
AU719173B2 (en) | Sealing gasket | |
JPH08284161A (en) | Retaining wall-fixing anchor bolt device | |
JP3025207B2 (en) | Seismic isolation faucet | |
JP4256579B2 (en) | Permanent water installation method for water control doors | |
JPS5923781Y2 (en) | Water control door installation structure | |
KR101027062B1 (en) | Ball valve for waterworks |