JPH09296416A - Diagonally hanging structure and construction method - Google Patents
Diagonally hanging structure and construction methodInfo
- Publication number
- JPH09296416A JPH09296416A JP8109722A JP10972296A JPH09296416A JP H09296416 A JPH09296416 A JP H09296416A JP 8109722 A JP8109722 A JP 8109722A JP 10972296 A JP10972296 A JP 10972296A JP H09296416 A JPH09296416 A JP H09296416A
- Authority
- JP
- Japan
- Prior art keywords
- cable
- stayed
- socket member
- socket
- main
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、土木、建築、橋梁
分野における斜張吊り架構の構造及びその構築方法に関
する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structure of a cable-stayed suspension structure and a construction method thereof in the fields of civil engineering, architecture and bridges.
【0002】[0002]
【従来の技術】従来のコンクリート斜張橋は、例えば、
特公平7−21165号公報に示されるように、斜張橋
の桁施工区分ごとにメラン材を架設して斜張ケーブルで
保持し、メラン材を順次延長することにより構築してい
た。2. Description of the Related Art Conventional concrete cable-stayed bridges are, for example,
As disclosed in Japanese Examined Patent Publication No. 7-21165, a construction was made by constructing a melanin material for each girder construction section of a cable-stayed bridge, holding the cable with a cable-stayed cable, and sequentially extending the melanin material.
【0003】[0003]
【発明が解決しようとする課題】しかしながら、上記公
報に記載された技術は、以下に示すような問題点を有し
ている。即ち、 1.メラン材の施工区分ごとの接合延伸が通常、現場で
のメラン材の上先端部での溶接またはボルト接合とな
り、高所での危険なメラン材接合や斜材ケーブル接続保
持作業が手間取る。 2.メラン材の施工区分ごとの接合延伸時、現場でのメ
ラン材の接合部での延伸方向精度補正が通常の溶接また
はボルト接合では修正自由度が少なく、現場合わせの煩
雑な施工と施工低品質化につながると同時に価格上昇を
招来する。However, the technique described in the above publication has the following problems. That is, 1. Normally, the joining and stretching of the melanin material for each construction category is welding or bolting at the top end of the melanin material on site, and it takes time and labor to perform dangerous melanin material joining and diagonal cable connection holding work at high places. 2. At the time of joining and stretching the melanin for each construction segment, the accuracy of the stretching direction accuracy at the joint of the melanin material on site cannot be corrected by normal welding or bolt joining, and complicated construction and poor quality of construction can be performed on site. Will lead to higher prices at the same time.
【0004】本発明は従来技術の有する叙上の問題点に
鑑み創出されたものであり、その目的とするところは、
斜張吊り架構の主桁や主塔の接続延伸施工を溶接なしの
ワンタッチ式の挿入部材とソケット部材との嵌合による
接続構造とし、延伸方向誤差吸収自由度を大きくするこ
とにより、現場での接続作業の効率を飛躍的に向上させ
た斜張吊り架構の構造及びその構築方法を提供すること
である。The present invention was created in view of the above-mentioned problems of the prior art, and its purpose is to:
Connection extension of the main girder and main tower of the cable-stayed suspension structure is done by connecting the one-touch type insertion member and the socket member without welding to increase the degree of freedom in absorbing the error in the extension direction. It is an object of the present invention to provide a structure of a cable-stayed suspension frame that dramatically improves the efficiency of connection work and a method for constructing the structure.
【0005】[0005]
【課題を解決するための手段】上記課題を解決するため
に、本発明は、斜張吊り架構の主桁構造において、挿入
部材とソケット部材より構成される主桁組み合わせ単位
部材の挿入部材またはソケット部材を斜張ケーブルによ
って接続保持することにより単位主桁施工区分を構成す
ることを特徴とするものである。従って、大きな軸力と
曲げを受ける斜張吊り架構の主桁構造の施工単位ごとに
必要な現場継手としてソケット部材は優れた継手性能を
発揮すると同時に継手部加工が簡便且つ低コストで部材
製作ができる。また、斜張ケーブルはソケット部材の抜
け出しとは反対の押し込み方向に力が働き安全で信頼性
の高い継手となっている。In order to solve the above-mentioned problems, the present invention provides an insertion member or socket of a main girder combination unit member composed of an insertion member and a socket member in a main girder structure of a cable-stayed suspension frame. It is characterized in that a unit main girder construction section is configured by connecting and holding members by a cable-stayed cable. Therefore, the socket member exhibits excellent joint performance as a site joint required for each construction unit of the main girder structure of the cable-stayed frame subject to large axial force and bending, and at the same time, the joint portion can be processed easily and at low cost. it can. Further, the cable-stayed cable has a safe and highly reliable joint in which force is applied in the pushing direction opposite to the direction in which the socket member is pulled out.
【0006】また、上記課題を解決するために、本発明
は、斜張吊り架構の主桁構造の構築方法において、単位
主桁施工区分ごとに挿入部材とソケット部材を嵌合延伸
した後、挿入部材またはソケット部材を斜張ケーブルで
接続保持しながら単位主桁施工区分を順次延長すること
を特徴とするものである。従って、ソケット部材は主桁
延伸時の高所強風作業時に簡便に挿入出来、斜張ケーブ
ルの接続引張力導入で抜け出し不安のない安全方向に向
かい信頼性の高い急速施工が可能となる。また、斜張吊
り架構の主桁構築工事のプレファブ化が可能となる。In order to solve the above-mentioned problems, the present invention is a method of constructing a main girder structure of a cable-stayed suspension frame, wherein after inserting and inserting an insertion member and a socket member for each unit main girder construction section, insertion is performed. It is characterized in that the unit main girder construction section is sequentially extended while the member or socket member is connected and held by the cable-stayed cable. Therefore, the socket member can be easily inserted during high-force strong work at the time of extension of the main girder, and by introducing the connection pulling force of the cable-stayed cable, it is possible to perform a reliable and rapid construction in the safe direction in which there is no fear of slipping out. In addition, prefabricated construction of main girder construction for cable-stayed suspension frames will be possible.
【0007】さらに、上記課題を解決するために、本発
明は、斜張吊り架構の主塔構造において、挿入部材とソ
ケット部材より構成される主塔組み合わせ単位部材の挿
入部材またはソケット部材に斜張ケーブルを接続設置す
ることにより単位主塔施工区分を構成することを特徴と
するものである。従って、大きな軸力と曲げを受ける斜
張吊り架構の主塔構造の施工単位ごとに必要な現場継手
としてソケット部材は優れた継手性能を発揮すると同時
に継手部加工が簡便で低コストで部材製作ができる。ま
た、斜張ケーブルはソケット部材の抜け出しとは反対の
押し込み方向に力が働き安全で信頼性の高い継手となっ
ている。Further, in order to solve the above-mentioned problems, the present invention is a main tower structure of a cable-stayed suspension frame, in which an insertion member or a socket member of a main tower combination unit member composed of an insertion member and a socket member is obliquely attached. It is characterized in that a unit main tower construction section is configured by connecting and installing cables. Therefore, the socket member exhibits excellent joint performance as a site joint required for each construction unit of the main tower structure of the cable-stayed frame subject to a large axial force and bending, and at the same time, the joint portion can be easily processed at low cost. it can. Further, the cable-stayed cable has a safe and highly reliable joint in which force is applied in the pushing direction opposite to the direction in which the socket member is pulled out.
【0008】そして、上記課題を解決するために、本発
明は、斜張吊り架構の主塔構造の構築方法において、単
位主塔施工区分ごとに挿入部材とソケット部材を嵌合積
み上げした後、挿入部材またはソケット部材に斜張ケー
ブルを接続設置しながら単位主塔施工区分を順次嵩上げ
することを特徴とするものである。従って、ソケット部
材は主塔の積み上げ時の高所強風作業時に簡便に挿入出
来、斜張ケーブルの接続引張力導入で抜け出し不安のな
い安全方向に向かい信頼性の高い急速施工が可能とな
る。また、斜張吊り架構の主塔構築工事のプレファブ化
が可能となる。In order to solve the above-mentioned problems, the present invention is a method of constructing a main tower structure of a cable-stayed suspension frame, in which an insertion member and a socket member are fitted and stacked for each unit main tower construction section, and then inserted. It is characterized in that the unit main tower construction section is gradually increased while connecting and installing the cable-stayed cable to the member or the socket member. Therefore, the socket member can be easily inserted during a strong wind work at a high place at the time of stacking the main tower, and by introducing the connection pulling force of the cable-stayed cable, it is possible to perform a reliable and rapid construction in a safe direction without fear of coming out. In addition, prefabricated construction of the main tower construction for cable-stayed suspension frames will be possible.
【0009】また、上記課題を解決するために、本発明
は、斜張吊り架構の構造において、挿入部材とソケット
部材より構成される主桁組み合わせ単位部材の挿入部材
またはソケット部材と、挿入部材とソケット部材より構
成される主塔組み合わせ単位部材の挿入部材またはソケ
ット部材の各々に斜張ケーブルを接続設置することによ
り単位施工区分を構成することを特徴とするものであ
る。従って、主桁部と主塔部の各々に斜張ケーブルを接
合設置してテンションを導入する事により主桁ソケット
部材および主塔ソケット部材に押し込み方向の力が同時
に導入され、継手としての抜け出し安全性が高まる。In order to solve the above-mentioned problems, the present invention is, in a structure of a cable-stayed suspension frame, an insertion member or a socket member of a main girder combination unit member composed of an insertion member and a socket member, and an insertion member. It is characterized in that a unit construction section is configured by connecting and installing a cable-stayed cable to each of the insertion member or the socket member of the main tower combination unit member configured by the socket member. Therefore, by installing tension cables and installing tension cables to the main girder and the main tower, respectively, the force in the pushing direction is simultaneously introduced to the main girder socket member and the main tower socket member, and the exit safety as a joint is safe. The nature is enhanced.
【0010】さらに、上記課題を解決するために、本発
明は、斜張吊り架構の構築方法において、単位主桁施工
区分ごとに挿入部材とソケット部材を嵌合延伸した単位
主桁部材の挿入部材またはソケット部材と、単位主塔施
工区分ごとに挿入部材とソケット部材を嵌合積み上げし
た単位主塔部材の挿入部材またはソケット部材の各々に
斜張ケーブルを接続設置することにより単位施工区分を
順次構築していくことを特徴とするものである。従っ
て、主桁と主塔の施工が同時に実施され斜張橋の完全プ
レファブ化が可能となる。また、現場での施工が効率よ
く行なわれる。Further, in order to solve the above-mentioned problems, the present invention provides a method for constructing a cable-stayed suspension frame, wherein an insert member for a unit main girder member in which an insert member and a socket member are fitted and extended for each unit main girder construction section. Or, the unit construction section is constructed sequentially by connecting and installing cable-stayed cables to each of the insertion member or socket member of the unit main tower member in which the socket member and the insertion member and the socket member are fitted and stacked for each unit main tower construction section. It is characterized by doing. Therefore, the main girder and the main tower will be constructed at the same time, and the cable-stayed bridge will be fully prefabricated. In addition, construction at the site can be performed efficiently.
【0011】そして、挿入部材の内部、又は、該挿入部
材及びソケット部材で形成されるクリアランスにコンク
リートを充填固化したので、ソケット部材と挿入部材の
差し込み接続部にクリアランスを設けコンクリート等の
不定形硬化材を充填固化することで継手部材の製作誤差
や施工誤差を吸収補正できると同時に高強度で高い信頼
性の継手を容易に構築出来る。また、挿入部材の内部、
又は、該挿入部材及びソケット部材で形成されるクリア
ランス、又は、該挿入部材及びソケット部材で形成され
る径方向間隙にモルタルを充填固化したので、斜張吊り
架構の主桁接続延伸や主塔接続伸張は通常延伸方向の誤
差修正を頻繁にやる必要が多く、従来の溶接継手やボル
ト接合では現場合わせでの継手部修正加工が煩雑となり
継手品質にも悪影響を与えることが多かったが、本願発
明ソケット継手接続システムは挿入部材とソケット部材
にクリアランスを設けることにより、容易に修正が出
来、修正後のモルタル充填固化で継手構造を構築でき
る。さらに、挿入部材の外周又はソケット部材の内周に
ストッパを設けたので、ソケット部材への挿入部材の嵌
挿時、両部材の位置決めが可能となる。Since the concrete is filled and solidified inside the insertion member or in the clearance formed by the insertion member and the socket member, a clearance is provided at the insertion connection portion of the socket member and the insertion member to cure the amorphous shape of concrete or the like. By filling and solidifying the material, manufacturing errors and construction errors of joint members can be absorbed and corrected, and at the same time, a joint with high strength and high reliability can be easily constructed. Also, inside the insertion member,
Alternatively, since the clearance formed by the insertion member and the socket member, or the radial gap formed by the insertion member and the socket member is filled with mortar and solidified, the main girder connection extension and the main tower connection of the cable-stayed suspension frame are connected. The stretching usually requires frequent correction of the error in the stretching direction, and in the conventional welded joints and bolt joints, the joint part correction process in the field alignment was complicated and often adversely affects the joint quality. The socket joint connection system can be easily corrected by providing a clearance between the insertion member and the socket member, and the joint structure can be constructed by mortar filling and solidifying after the correction. Further, since the stopper is provided on the outer circumference of the insertion member or the inner circumference of the socket member, both members can be positioned when the insertion member is fitted into the socket member.
【0012】[0012]
【発明の実施の形態】本発明の第1の実施形態を図1か
ら図3に基づいて説明する。本発明の斜張吊り架構は斜
張ケーブルにより桁を支持する構造、例えば斜張橋、吊
り尾根などの各種構造物に適用されるが、本明細書にお
いては、本発明を、例えば、斜張橋に適用した実施形態
について説明することとする。図1は中央径間400
m、側径間200m、全長800mの斜張橋の全体構造
を示す側面図であり、図2は、主桁の第1実施形態の要
部を示す一部欠截斜視図であり、図3は、主桁の要部一
部断面図である。図において、斜張橋の一構成要素であ
る主桁は背面部1と前面部2を有する中空のソケット部
材3と、該ソケット部材3に嵌挿される挿入部材5から
なる。ソケット部材3、挿入部材5ともに鋼管構造であ
る。ソケット部材3の外周には斜張ケーブル6が接続さ
れるための孔を有する接続具7が固設されている。上記
ソケット部材3、該ソケット部材3に嵌挿される挿入部
材5、及び、ソケット部材3又は挿入部材5に接続され
る斜張ケーブル6により単位主桁施工区分構造が構成さ
れ、該単位施工区分構造を順次延長することにより斜張
橋の主桁が構築されていくのである。そして、斜張橋の
主桁は、斜張ケーブルの緊張により、主桁方向軸圧縮と
曲げの断面力を受けるため、抜け出し引張力に弱いソケ
ット継手でも何等不都合はなく、信頼性の高いワンタッ
チ低コスト継手構造とすることができる。また、主桁
は、図2に示すように、平行に延設し、横つなぎ材8を
掛け渡し固設する。尚、符号10は床版である。BEST MODE FOR CARRYING OUT THE INVENTION A first embodiment of the present invention will be described with reference to FIGS. The cable-stayed suspension structure of the present invention is applied to various structures such as cable-stayed bridges and suspension ridges that support a girder by a cable-stayed cable. An embodiment applied to a bridge will be described. Figure 1 shows the center span 400
3 is a side view showing the overall structure of a cable-stayed bridge having a length of m, a side span of 200 m, and a total length of 800 m, and FIG. 2 is a partially cutaway perspective view showing a main part of the first embodiment of the main girder, and FIG. [FIG. 3] is a partial cross-sectional view of a main part of a main girder. In the figure, a main girder, which is one component of a cable-stayed bridge, is composed of a hollow socket member 3 having a back surface portion 1 and a front surface portion 2, and an insertion member 5 fitted into the socket member 3. Both the socket member 3 and the insertion member 5 have a steel pipe structure. On the outer periphery of the socket member 3, a connector 7 having a hole for connecting the cable-stayed cable 6 is fixed. A unit main girder construction division structure is configured by the socket member 3, the insertion member 5 fitted and inserted in the socket member 3, and the cable-stayed cable 6 connected to the socket member 3 or the insertion member 5, and the unit construction division structure The main girder of the cable-stayed bridge will be constructed by sequentially extending the. The main girder of the cable-stayed bridge receives axial compression and bending cross-sectional force due to the tension of the cable stayed cable, so there is no inconvenience even with a socket joint that is weak in pulling out pulling force, and a highly reliable one-touch low It can be a cost joint structure. As shown in FIG. 2, the main girders are extended in parallel and the horizontal connecting members 8 are bridged and fixed. Reference numeral 10 is a floor slab.
【0013】挿入部材5をソケット部材3に挿入する
際、両部材間に間隙がある場合には該間隙にモルタル等
の不定形硬化材を充填固化させると極めて高強度で信頼
性の高い継手を構築出来ると同時に斜張ケーブルの主桁
保持力を高めることができる。また、図3に示すよう
に、ソケット部材3の内周には挿入部材5の嵌挿時、該
挿入部材5の端部をソケット部材3内で停止固定させる
ための仕切板等のストッパ11が固設されている。該ス
トッパ11は環状のフランジでもよい。また、該ストッ
パ11は挿入部材5とソケット部材3との間の位置決め
をするためのものであるため、挿入部材5の外周に環状
フランジを固設してもよい。挿入部材5とソケット部材
3との位置決め固定をするためには、上述したモルタル
等の不定形硬化材を間隙に充填固化させることも類似技
術であるので、上記ストッパは必ずしも必須構成要件で
はない。When inserting the insertion member 5 into the socket member 3, if there is a gap between the two members, it is possible to obtain an extremely high-strength and highly reliable joint by filling and solidifying the gap with an irregular hardening material such as mortar. It can be constructed and at the same time can increase the main girder holding force of the cable-stayed cable. Further, as shown in FIG. 3, a stopper 11 such as a partition plate for stopping and fixing the end portion of the insertion member 5 in the socket member 3 when the insertion member 5 is fitted and inserted into the inner periphery of the socket member 3. It is fixed. The stopper 11 may be an annular flange. Further, since the stopper 11 is for positioning between the insertion member 5 and the socket member 3, an annular flange may be fixedly provided on the outer periphery of the insertion member 5. In order to position and fix the insertion member 5 and the socket member 3, it is a similar technique to fill and solidify the above-mentioned irregular shaped hardening material such as mortar into the gap, so the stopper is not always an essential constituent element.
【0014】斜張橋の主桁接続延伸は通常延伸方向の誤
差修正を頻繁にやる必要が多く、従来の溶接継手やボル
ト接合では現場合わせでの継手部修正加工が煩雑となり
継手品質にも悪影響を与えることが多かったが、本願発
明ソケット継手接続システムは挿入部材5とソケット部
材3に、図4に示すように、クリアランス12を設ける
ことにより、容易に延伸方向の誤差修正が出来、修正後
のモルタル99充填固化で何等不安のない継手構造を構
築できる。In the main girder connection extension of a cable-stayed bridge, it is usually necessary to frequently correct the error in the extension direction, and in conventional welded joints and bolt joints, it is complicated to correct the joint portion in the field and the joint quality is adversely affected. However, the socket joint connection system of the present invention can easily correct the error in the extending direction by providing the insertion member 5 and the socket member 3 with the clearance 12 as shown in FIG. By filling and solidifying the mortar 99, a joint structure without any worries can be constructed.
【0015】斜張橋は斜張ケーブル6から主桁内に大き
な軸力が入るので、主桁内の挿入部材5または挿入部材
5とソケット部材3との間のクリアランス12にコンク
リート9を充填固化すると高強度で信頼性の高い主桁を
構築することができると同時に継手部材の設計誤差や施
工誤差を吸収補正できる。また、主桁の挿入部材5やソ
ケット部材3の内面にコンクリートを充填したコンクリ
ート充填鋼管構造とする場合や、その外周にコンクリー
トを複覆した鉄骨コンクリート構造にしても高強度で信
頼性の高い主桁を構築することができる。Since a large axial force is applied from the cable-stayed cable 6 to the main girder of the cable-stayed bridge, concrete 9 is filled and solidified in the insertion member 5 in the main girder or the clearance 12 between the insertion member 5 and the socket member 3. This makes it possible to construct a high-strength and highly reliable main girder, and at the same time, to absorb and correct design errors and construction errors of joint members. In addition, when a concrete-filled steel pipe structure in which the inner surfaces of the main girder insertion member 5 and the socket member 3 are filled with concrete is used, or even a steel-framed concrete structure in which concrete is double-covered on the outer periphery of the main girder has high strength and high reliability. Digits can be built.
【0016】次に、斜張橋の一構成要素である主塔の実
施形態について図5に基づいて説明する。主塔も主桁と
同様に、背面部51と前面部52を有する中空のソケッ
ト部材53と、該ソケット部材53に嵌挿される挿入部
材55からなる。ソケット部材53、挿入部材55とも
に鋼管構造である。ソケット部材53の外周には斜張ケ
ーブル6が接続されるための孔を有する接続具57が固
設されている。本実施形態においては、接続具57は2
個固設されているが、1個でも3個以上でもよい。上記
ソケット部材53、該ソケット部材53に嵌挿される挿
入部材55、及び、ソケット部材53又は挿入部材55
に接続される斜張ケーブル6により単位主塔施工区分構
造が構成され、該単位施工区分構造を順次延長すること
により斜張橋の主塔が構築されていくのである。そし
て、斜張橋の主塔は、斜張ケーブルの緊張により、主塔
方向軸圧縮と曲げの断面力を受けるため、抜け出し引張
力に弱いソケット継手でも何等不都合はなく、信頼性の
高いワンタッチ低コスト継手構造とすることができる。
また、主塔も、図5に示すように、平行に延設し、横つ
なぎ材58を掛け渡し固設する。Next, an embodiment of the main tower, which is one component of the cable-stayed bridge, will be described with reference to FIG. Similarly to the main girder, the main tower also includes a hollow socket member 53 having a back surface portion 51 and a front surface portion 52, and an insertion member 55 fitted and inserted into the socket member 53. Both the socket member 53 and the insertion member 55 have a steel pipe structure. On the outer periphery of the socket member 53, a connector 57 having a hole for connecting the cable-stayed cable 6 is fixedly installed. In this embodiment, the number of connecting members 57 is two.
Although individually fixed, the number may be one or three or more. The socket member 53, the insertion member 55 fitted and inserted in the socket member 53, and the socket member 53 or the insertion member 55.
The cable-stayed cable 6 connected to the above constitutes a unit main tower construction division structure, and the main tower of the cable-stayed bridge is constructed by sequentially extending the unit construction division structure. And, the main tower of the cable-stayed bridge receives cross-sectional force of axial compression and bending in the main tower due to the tension of the cable-stayed cable, so there is no inconvenience even with socket joints that are weak in pulling out pulling force, and highly reliable one-touch low-touch. It can be a cost joint structure.
Further, as shown in FIG. 5, the main tower is also extended in parallel, and a horizontal connecting member 58 is bridged and fixed.
【0017】挿入部材55をソケット部材53に挿入す
る際、両部材間に径方向間隙がある場合には該間隙にモ
ルタル等の不定形硬化材を充填固化させると極めて高強
度で信頼性の高い継手を構築出来ると同時に斜張ケーブ
ルの主塔保持力を高めることができる。また、図3に示
すように、ソケット部材53の内周には挿入部材55の
嵌挿時、該挿入部材55の端部をソケット部材53内で
停止固定させるための仕切板等のストッパ11が固設さ
れている。該ストッパ11は環状のフランジでもよい。
また、該ストッパ11は挿入部材55とソケット部材5
3との間の位置決めをするためのものであるため、挿入
部材55の外周に固設してもよい。挿入部材55とソケ
ット部材53との位置決め固定をするためには、上述し
たモルタル等の不定形硬化材を間隙に充填固化させるこ
とも類似技術であるので、上記ストッパは必ずしも必須
構成要件ではない。When the insertion member 55 is inserted into the socket member 53, if there is a radial gap between the two members, it is extremely strong and highly reliable if the gap is filled and solidified with an amorphous hardening material such as mortar. It is possible to build a joint and at the same time enhance the main tower holding power of the cable-stayed cable. Further, as shown in FIG. 3, a stopper 11 such as a partition plate for stopping and fixing the end portion of the insertion member 55 in the socket member 53 when the insertion member 55 is fitted and inserted into the inner periphery of the socket member 53. It is fixed. The stopper 11 may be an annular flange.
Further, the stopper 11 includes the insertion member 55 and the socket member 5
Since it is for positioning between the insertion member 55 and the insertion member 3, it may be fixed to the outer periphery of the insertion member 55. In order to position and fix the insertion member 55 and the socket member 53, it is a similar technique to fill and solidify the above-mentioned indeterminate hardening material such as mortar into the gap, so the stopper is not always an essential constituent element.
【0018】斜張橋の主塔接続延伸は通常延伸方向の誤
差修正を頻繁にやる必要が多く、従来の溶接継手やボル
ト接合では現場合わせでの継手部修正加工が煩雑となり
継手品質にも悪影響を与えることが多かったが、本願発
明ソケット継手接続システムは挿入部材55とソケット
部材53に、図4に示すように、クリアランス12を設
けることにより、容易に延伸方向の誤差修正が出来、修
正後のモルタル99充填固化で何等不安のない継手構造
を構築できる。In the extension of the cable-stayed bridge connected to the main tower, it is usually necessary to frequently correct the error in the extension direction. With conventional welded joints and bolt joints, it is complicated to correct the joint portion in the field and the joint quality is adversely affected. However, in the socket joint connection system of the present invention, by providing the insertion member 55 and the socket member 53 with the clearance 12 as shown in FIG. By filling and solidifying the mortar 99, a joint structure without any worries can be constructed.
【0019】斜張橋は斜張ケーブル6から主塔内に大き
な軸力が入るので、主塔内の挿入部材55または挿入部
材55とソケット部材53との間のクリアランス12に
コンクリート9を充填固化すると高強度で信頼性の高い
主塔を構築することができると同時に継手部材の設計誤
差や施工誤差を吸収補正できる。Since a large axial force is applied from the cable-stayed cable 6 to the main tower of the cable-stayed bridge, the insertion member 55 in the main tower or the clearance 12 between the insertion member 55 and the socket member 53 is filled with concrete 9 and solidified. Then, a high-strength and highly reliable main tower can be constructed, and at the same time, design errors and construction errors of joint members can be absorbed and corrected.
【0020】次に、主桁、主塔を組合せた斜張橋の構築
方法である施工を図6及び図7に基づいて説明する。図
6は主桁の施工について、図7は主塔の施工について示
したものである。 (第1ステップ)まず、図6及び図7に示すように、主
塔基礎13を構築し、その上に下部主塔14を立設す
る。 (第2ステップ)次に、図6に示すように、主桁の主頭
部の挿入部材5を設置し、該挿入部材5にソケット部材
3の背面部1を被せて取付ける。ここで挿入部材5とソ
ケット部材3との間に径方向の間隙がある場合、ソケッ
ト部材3の背面部1内にモルタル等の不定形硬化材を充
填固化させる。次に、下部主塔14の下部接続具57と
主桁のソケット部材3の接続具6とを斜張ケーブル7に
て接続する(一次緊張)。ここで、挿入部材5の強度を
増加させたい場合、挿入部材5内にコンクリートを充填
固化後、斜張ケーブルの張線度合を再度調節する(二次
緊張)。 (第3ステップ)次に、図6に示すように、ソケット部
材3の前面部2に第2の挿入部材5′を嵌挿する。そし
て、主桁の延伸精度を補正する場合、ソケット部材3の
前面部2内にモルタルを充填し固化させる。 (第4ステップ)次に、図6に示すように、第2のソケ
ット部材3′の背面部を第2の挿入部材5′に被せて取
付ける。ここで第2の挿入部材5′と第2のソケット部
材3′との間に径方向の間隙がある場合モルタルを第2
のソケット部材3′の背面部内に充填固化させる。次
に、下部主塔14の上部接続具57′と第2のソケット
部3′の接続具とを斜張ケーブル6′にて接続する(一
次緊張)。ここで、第2の挿入部材5′の強度を増加さ
せたい場合、第2の挿入部材5′内にコンクリートを充
填固化後、斜張ケーブル7の張線度合を再度調節する
(二次緊張)。 (第5ステップ)次に、図7に示すように、下部主塔1
4内に挿入部材35を嵌挿する。 (第6ステップ)そして、図7に示すように、挿入部材
35にソケット部材33の背面部31を被せて取付け
る。第6ステップ以降は同一の単位主塔施工区分及び主
桁施工区分を繰返し、順次、主塔及び主桁を延長する。Next, construction, which is a method of constructing a cable-stayed bridge in which main girders and main towers are combined, will be described with reference to FIGS. 6 and 7. FIG. 6 shows the construction of the main girder, and FIG. 7 shows the construction of the main tower. (First Step) First, as shown in FIGS. 6 and 7, a main tower foundation 13 is constructed, and a lower main tower 14 is erected on it. (Second Step) Next, as shown in FIG. 6, the insertion member 5 of the main head of the main girder is set, and the insertion member 5 is attached by covering the back surface portion 1 of the socket member 3. Here, if there is a radial gap between the insertion member 5 and the socket member 3, the rear surface portion 1 of the socket member 3 is filled and solidified with an amorphous hardening material such as mortar. Next, the lower connector 57 of the lower main tower 14 and the connector 6 of the socket member 3 of the main girder are connected by the cable-stayed cable 7 (primary tension). Here, when it is desired to increase the strength of the insertion member 5, the inside of the insertion member 5 is filled with concrete and solidified, and then the tension degree of the cable-stayed cable is adjusted again (secondary tension). (Third step) Next, as shown in FIG. 6, the second insertion member 5'is inserted into the front surface portion 2 of the socket member 3. Then, when correcting the extension accuracy of the main girder, the front portion 2 of the socket member 3 is filled with mortar and solidified. (Fourth Step) Next, as shown in FIG. 6, the back surface of the second socket member 3'is placed over the second insertion member 5 '. Here, if there is a radial gap between the second insertion member 5'and the second socket member 3 ', the mortar
The inside of the back surface of the socket member 3'is filled and solidified. Next, the upper connecting member 57 'of the lower main tower 14 and the connecting member of the second socket portion 3'are connected by the cable-stayed cable 6' (primary tension). Here, if it is desired to increase the strength of the second insertion member 5 ', concrete is filled and solidified in the second insertion member 5', and then the tension degree of the cable-stayed cable 7 is adjusted again (secondary tension). . (Fifth Step) Next, as shown in FIG.
The insertion member 35 is fitted into the inside of the connector 4. (Sixth Step) Then, as shown in FIG. 7, the back surface 31 of the socket member 33 is covered and attached to the insertion member 35. After the 6th step, the same unit main tower construction section and main girder construction section are repeated, and the main tower and main girder are sequentially extended.
【0021】尚、主塔は単独で、また主桁も吊線等を使
用することにより単独で単位施工区分構造ごとに施工で
きるが、上述したように、主塔構造も主桁構造に準ずる
構造で単位主桁施工区分構造ごとに同時並行的に積み上
げ施工すると、斜張橋全体を更に効率よく施工できる。It should be noted that the main tower can be constructed independently and the main girder can be constructed independently for each unit construction section structure by using a suspension wire or the like. However, as mentioned above, the main tower structure is also a structure conforming to the main girder structure. By constructing the unit main girder construction structures in parallel at the same time, the entire cable-stayed bridge can be constructed more efficiently.
【0022】図8は主桁の第2実施形態を示したもので
ある。第2実施形態は挿入部材25として鋼管の角鋼管
を使用したものであり、また、ソケット部材23として
は角鋼管の閉断面構造が挿入部材を周辺から強く拘束出
来るため大きな継手構造性能を示す。そして、ソケット
部材23と挿入部材25の差し込み接続部にクリアラン
スを設けモルタル99またはコンクリート9等の不定形
硬化材を充填固化することで継手部材の製作誤差や施工
誤差を吸収補正できると同時に高強度で高い信頼性の継
手を容易に構築できる。FIG. 8 shows a second embodiment of the main girder. The second embodiment uses a square steel pipe of a steel pipe as the insertion member 25, and the socket member 23 has a large joint structure performance because the closed cross-section structure of the square steel pipe can strongly constrain the insertion member from the periphery. Then, a clearance is provided at the insertion connection portion between the socket member 23 and the insertion member 25 to fill and solidify an irregular shaped hardening material such as mortar 99 or concrete 9 so that manufacturing errors and construction errors of the joint member can be absorbed and corrected, and at the same time high strength can be achieved. It is easy to build a highly reliable joint.
【0023】図9は主桁の第3実施形態を示したもので
ある。第3実施形態は挿入部材35としてH型鋼を使用
したものである。そして、ソケット部材33と挿入部材
35の差し込み接続部にクリアランスを設けモルタル9
9またはコンクリート9等の不定形硬化材を充填固化す
ることで継手部材の製作誤差や施工誤差を吸収補正でき
ると同時に高強度で高い信頼性の継手を容易に構築でき
る。FIG. 9 shows a third embodiment of the main girder. The third embodiment uses H-section steel as the insertion member 35. Then, a clearance is provided at the insertion connection portion between the socket member 33 and the insertion member 35 to provide the mortar 9
By filling and solidifying an indeterminate hardening material such as 9 or concrete 9, manufacturing errors and construction errors of the joint member can be absorbed and corrected, and at the same time, a joint having high strength and high reliability can be easily constructed.
【0024】図10は主桁の第4実施形態を示したもの
である。第4実施形態は挿入部材45として角鋼材また
はプレキャストコンクリート梁を使用したものであり、
また、ソケット部材43としては角鋼材やプレキャスト
コンクリート梁等の閉断面構造が挿入部材を周辺から強
く拘束出来るため大きな継手構造性能を示す。そして、
ソケット部材43と挿入部材45の差し込み接続部にク
リアランスを設けモルタル99またはコンクリート9等
の不定形硬化材を充填固化することで継手部材の製作誤
差や施工誤差を吸収補正できると同時に高強度で高い信
頼性の継手を容易に構築できる。図11は主桁の第5実
施形態を示したもので、主桁の外周にコンクリートを被
覆して、鉄骨コンクリート構造としたものである。これ
により、更に高強度で信頼性の高い主桁構造とすること
ができる。なお、この実施形態では主桁は図9に示した
第3実施形態の構造としているが、本発明の他の構造の
主桁としてもよい。FIG. 10 shows a fourth embodiment of the main girder. The fourth embodiment uses a square steel material or a precast concrete beam as the insertion member 45,
Further, as the socket member 43, a closed cross-section structure such as a square steel material or a precast concrete beam can strongly restrain the insertion member from the periphery, and thus exhibits a large joint structure performance. And
By providing a clearance at the insertion connecting portion of the socket member 43 and the insertion member 45 and filling and solidifying an indeterminate hardening material such as mortar 99 or concrete 9, it is possible to absorb and correct manufacturing error and construction error of the joint member, and at the same time high strength and high strength. A reliable joint can be easily constructed. FIG. 11 shows a fifth embodiment of the main girder, in which the outer circumference of the main girder is covered with concrete to form a steel concrete structure. Thereby, a main girder structure having higher strength and higher reliability can be obtained. In addition, in this embodiment, the main girder has the structure of the third embodiment shown in FIG. 9, but it may be a main girder of another structure of the present invention.
【0025】[0025]
【発明の効果】本発明は、以上説明したように構成され
ているので、以下に記載されるような優れた効果を奏す
ることができる。Since the present invention is constructed as described above, the following excellent effects can be obtained.
【0026】斜張吊り架構の主桁や主塔の接続延伸施工
がワンタッチ式の挿入部材とソケット部材との嵌合によ
る接続構造であり、延伸方向誤差吸収自由度も大きいた
め、現場での接続作業の効率を飛躍的に向上させること
ができる。Connection of main girder and main tower of cable-stayed suspension structure The connection is a connection structure in which the insertion member and the socket member of the one-touch type are used for the extension work, and the flexibility in absorbing the error in the extension direction is large. The work efficiency can be dramatically improved.
【0027】斜張吊り架構の主桁や主塔は主桁及び主塔
方向の軸圧縮と曲げの断面力を受けるため、抜け出し引
張力に弱いソケット継手でも何等不都合はなく、信頼性
の高いワンタッチ低コスト継手となることができる。Since the main girder and main tower of the cable-stayed suspension frame are subjected to axial compression and bending sectional forces in the direction of the main girder and main tower, there is no inconvenience even with socket joints that are weak in pulling out pulling force, and highly reliable one-touch Can be a low cost joint.
【0028】挿入部材とソケット部材のクリアランスに
モルタルやコンクリート等の不定形硬化材を充填固化さ
せると極めて高強度で信頼性の高い継手を構築出来ると
同時に、斜張ケーブルの主桁や主塔の保持力を高めるこ
とができる。また、モルタル等を充填するソケット継手
は誤差吸収自由度が大きいと同時に、優れた斜張吊り架
構の構造を構築することができ、効率的で容易な構築施
工が可能となる。When the clearance between the insertion member and the socket member is filled and solidified with an indeterminate hardening material such as mortar or concrete, an extremely high-strength and highly reliable joint can be constructed, and at the same time, the main girder of the cable-stayed cable and the main tower can be constructed. The holding power can be increased. Further, the socket joint filled with mortar or the like has a large degree of error absorption freedom, and at the same time, an excellent cable-stayed frame structure can be constructed, which enables efficient and easy construction work.
【図1】本発明の実施形態の斜張橋の全体構造を示す側
面図である。FIG. 1 is a side view showing an overall structure of a cable-stayed bridge according to an embodiment of the present invention.
【図2】主桁の第1実施形態の要部を示す一部欠截斜視
図である。FIG. 2 is a partially cutaway perspective view showing a main part of the first embodiment of the main girder.
【図3】主桁の一実施例の要部一部断面図である。FIG. 3 is a partial cross-sectional view of an essential part of an embodiment of a main girder.
【図4】主桁の別の実施例の要部一部断面図である。FIG. 4 is a partial cross-sectional view of a main portion of another embodiment of the main girder.
【図5】主塔の実施形態の要部を示す一部欠截斜視図で
ある。FIG. 5 is a partially cutaway perspective view showing a main part of an embodiment of a main tower.
【図6】主桁の施工手順を示す説明図である。FIG. 6 is an explanatory view showing a procedure for constructing a main girder.
【図7】主塔の施工手順を示す説明図である。FIG. 7 is an explanatory diagram showing a procedure for constructing a main tower.
【図8】主桁の第2実施形態の要部を示す一部欠截斜視
図である。FIG. 8 is a partially cutaway perspective view showing a main part of a second embodiment of a main girder.
【図9】主桁の第3実施形態の要部を示す一部欠截斜視
図である。FIG. 9 is a partially cutaway perspective view showing an essential part of a third embodiment of a main girder.
【図10】主桁の第4実施形態の要部を示す一部欠截斜
視図である。FIG. 10 is a partially cutaway perspective view showing a main part of a fourth embodiment of a main girder.
【図11】主桁の第5の実施形態の要部を示す一部欠
截、斜視図である。FIG. 11 is a partially cutaway perspective view showing an essential part of a fifth embodiment of a main girder.
3,23,33,43,53…ソケット部材 5,25,35,45,55…挿入部材 6,6′…斜張ケーブル 7,57,57′…接続具 8,58…横つなぎ材 9…コンクリート 11…ストッパ 12…クリアランス 13…主塔基礎 14…下部主塔 99…モルタル 3, 23, 33, 43, 53 ... Socket member 5, 25, 35, 45, 55 ... Insert member 6, 6 '... Cable-stayed cable 7, 57, 57' ... Connecting tool 8, 58 ... Horizontal connecting member 9 ... Concrete 11 ... Stopper 12 ... Clearance 13 ... Main tower foundation 14 ... Lower main tower 99 ... Mortar
───────────────────────────────────────────────────── フロントページの続き (72)発明者 天野 玲子 東京都調布市飛田給二丁目19番1号 鹿島 建設株式会社技術研究所内 (72)発明者 日紫喜 剛啓 東京都調布市飛田給二丁目19番1号 鹿島 建設株式会社技術研究所内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Reiko Amano No. 19-1 Tobita, 2-chome, Chofu City, Tokyo Kashima Construction Co., Ltd. Technical Research Institute (72) Inventor Takehiro Hisashi Takenaka 2-1-1, Tobita, Chofu-shi, Tokyo Kashima Construction Co., Ltd. Technical Research Center
Claims (12)
部材とソケット部材より構成される主桁組み合わせ単位
部材の挿入部材またはソケット部材を斜張ケーブルによ
って接続保持することにより単位主桁施工区分を構成す
ることを特徴とする斜張吊り架構の主桁構造。1. In the main girder structure of a cable-stayed suspension frame, the unit main girder construction classification is achieved by connecting and holding the insertion member or socket member of the main girder combination unit member composed of the insertion member and the socket member with a cable-stayed cable. The main girder structure of the cable-stayed suspension frame, which is characterized in that
いて、単位主桁施工区分ごとに挿入部材とソケット部材
を嵌合延伸した後、挿入部材またはソケット部材を斜張
ケーブルで接続保持しながら単位主桁施工区分を順次延
長することを特徴とする斜張吊り架構の主桁構造の構築
方法。2. A method for constructing a main girder structure of a cable-stayed suspension frame, wherein after inserting and extending an insert member and a socket member for each unit main girder construction section, the insert member or the socket member is connected and held by a cable-stayed cable. However, the method of constructing the main girder structure of the cable-stayed suspension frame is characterized by sequentially extending the unit main girder construction sections.
部材とソケット部材より構成される主塔組み合わせ単位
部材の挿入部材またはソケット部材に斜張ケーブルを接
続設置することにより単位主塔施工区分を構成すること
を特徴とする斜張吊り架構の主塔構造。3. In a main tower structure of a cable-stayed suspension frame, a unit main tower construction section is constructed by connecting and installing a cable-stayed cable to an insert member or socket member of a main tower combination unit member composed of an insert member and a socket member. The main tower structure of the cable-stayed suspension frame, which is characterized by
いて、単位主塔施工区分ごとに挿入部材とソケット部材
を嵌合積み上げした後、挿入部材またはソケット部材に
斜張ケーブルを接続設置しながら単位主塔施工区分を順
次嵩上げすることを特徴とする斜張吊り架構の主塔構造
の構築方法。4. A method of constructing a main tower structure of a cable-stayed suspension frame, wherein after inserting and stacking an insertion member and a socket member for each unit main tower construction section, a cable-stayed cable is connected and installed to the insertion member or the socket member. However, the construction method of the main tower structure of the cable-stayed suspension frame is characterized by gradually increasing the unit main tower construction classification.
とソケット部材より構成される主桁組み合わせ単位部材
の挿入部材またはソケット部材と、挿入部材とソケット
部材より構成される主塔組み合わせ単位部材の挿入部材
またはソケット部材の各々に斜張ケーブルを接続設置す
ることにより単位施工区分を構成することを特徴とする
斜張吊り架構の構造。5. A structure of a cable-stayed suspension frame, wherein an insert member or socket member of a main girder combination unit member composed of an insert member and a socket member, and a main tower combination unit member composed of an insert member and a socket member. A structure of a cable-stayed suspension structure, in which a unit construction section is configured by connecting and installing a cable-stayed cable to each of the insertion member or the socket member.
主桁施工区分ごとに挿入部材とソケット部材を嵌合延伸
した単位主桁部材の挿入部材またはソケット部材と、単
位主塔施工区分ごとに挿入部材とソケット部材を嵌合積
み上げした単位主塔部材の挿入部材またはソケット部材
の各々に斜張ケーブルを接続設置することにより単位施
工区分を順次構築していくことを特徴とする斜張吊り架
構の構築方法。6. A method for constructing a cable-stayed suspension frame, wherein an insert member or socket member of a unit main girder member obtained by fitting and extending an insert member and a socket member for each unit main girder construction section, and each unit main tower construction section. A cable-stayed suspension structure characterized by sequentially constructing unit construction sections by connecting and installing cable-stayed cables to each of the insert member or socket member of the unit main tower member in which the insert member and the socket member are fitted and stacked. How to build.
ソケット部材で形成されるクリアランスにコンクリート
を充填固化したことを特徴とする請求項1,3,5のい
ずれか1項に記載の斜張吊り架構の構造。7. The slant according to claim 1, wherein concrete is filled and solidified in the inside of the insert member or in the clearance formed by the insert member and the socket member. Suspended frame structure.
ソケット部材で形成されるクリアランスにコンクリート
を充填固化したことを特徴とする請求項2,4,6のい
ずれか1項に記載の斜張吊り架構の構築方法。8. The slant according to claim 2, wherein concrete is filled and solidified in the inside of the insertion member or in the clearance formed by the insertion member and the socket member. How to build a suspension frame.
ソケット部材で形成されるクリアランス、又は、該挿入
部材及びソケット部材で形成される径方向間隙にモルタ
ルを充填固化したことを特徴とする請求項1,3,5の
いずれか1項に記載の斜張吊り架構の構造。9. The mortar is filled and solidified inside the insert member, the clearance formed by the insert member and the socket member, or the radial gap formed by the insert member and the socket member. The structure of the cable-stayed suspension frame according to any one of claims 1, 3, and 5.
びソケット部材で形成されるクリアランス、又は、該挿
入部材及びソケット部材で形成される径方向間隙にモル
タルを充填固化したことを特徴とする請求項2,4,
6,8のいずれか1項に記載の斜張吊り架構の構築方
法。10. The mortar is filled and solidified inside the insert member, the clearance formed by the insert member and the socket member, or the radial gap formed by the insert member and the socket member. Claims 2, 4,
The method for constructing a cable-stayed suspension frame according to any one of 6 and 8.
周にストッパを設けたことを特徴とする請求項1,3,
5,7のいずれか1項に記載の斜張吊り架構の構造。11. A stopper is provided on the outer circumference of the insertion member or the inner circumference of the socket member.
5. The structure of the cable-stayed suspension frame according to any one of 5 and 7.
周にストッパを設けたことを特徴とする請求項2,4,
6,8のいずれか1項に記載の斜張吊り架構の構築方
法。12. A stopper is provided on the outer circumference of the insertion member or the inner circumference of the socket member.
The method for constructing a cable-stayed suspension frame according to any one of 6 and 8.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP10972296A JP3669766B2 (en) | 1996-04-30 | 1996-04-30 | Structure and construction method of cable-stayed suspension frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP10972296A JP3669766B2 (en) | 1996-04-30 | 1996-04-30 | Structure and construction method of cable-stayed suspension frame |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH09296416A true JPH09296416A (en) | 1997-11-18 |
JP3669766B2 JP3669766B2 (en) | 2005-07-13 |
Family
ID=14517574
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP10972296A Expired - Fee Related JP3669766B2 (en) | 1996-04-30 | 1996-04-30 | Structure and construction method of cable-stayed suspension frame |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3669766B2 (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001262513A (en) * | 2000-03-17 | 2001-09-26 | Nippon Steel Corp | Cable stayed bridge having composite synthetic steel tube beam material with slab and method of installing the beam material |
JP2010261154A (en) * | 2009-04-30 | 2010-11-18 | Kunio Honma | Pressing connection method for bridge through through-crossbeam |
CN104264578A (en) * | 2014-10-21 | 2015-01-07 | 天津市市政工程设计研究院 | Steel-concrete combining bridge of self-anchored suspension cable-cable-stayed cooperative system |
CN104294748A (en) * | 2014-09-23 | 2015-01-21 | 同济大学 | Joint section structure for hybrid beam cable-stayed bridge and construction method thereof |
CN104775365A (en) * | 2015-02-28 | 2015-07-15 | 张跃平 | Cable-stayed bridge construction method |
JP2017020199A (en) * | 2015-07-08 | 2017-01-26 | 三菱樹脂インフラテック株式会社 | Construction/civil engineering structure and bridge |
CN106702910A (en) * | 2016-12-29 | 2017-05-24 | 中交第三航务工程局有限公司 | Main girder construction process for extradosed cable-stayed bridge with double towers and double cable planes |
WO2018052030A1 (en) * | 2016-09-13 | 2018-03-22 | 清水建設株式会社 | Bridge construction method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0564208U (en) * | 1992-01-29 | 1993-08-27 | 株式会社カナエ | Prefabricated patrol bridge |
JPH05311746A (en) * | 1992-05-07 | 1993-11-22 | Nippon Steel Corp | Concrete-filled steel pipe structure |
JPH07216844A (en) * | 1994-02-08 | 1995-08-15 | Nippon Steel Corp | Underwater framed structure and construction method thereof |
JPH0820910A (en) * | 1994-07-05 | 1996-01-23 | Kajima Corp | Construction method of pc cable stayed bridge |
-
1996
- 1996-04-30 JP JP10972296A patent/JP3669766B2/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0564208U (en) * | 1992-01-29 | 1993-08-27 | 株式会社カナエ | Prefabricated patrol bridge |
JPH05311746A (en) * | 1992-05-07 | 1993-11-22 | Nippon Steel Corp | Concrete-filled steel pipe structure |
JPH07216844A (en) * | 1994-02-08 | 1995-08-15 | Nippon Steel Corp | Underwater framed structure and construction method thereof |
JPH0820910A (en) * | 1994-07-05 | 1996-01-23 | Kajima Corp | Construction method of pc cable stayed bridge |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001262513A (en) * | 2000-03-17 | 2001-09-26 | Nippon Steel Corp | Cable stayed bridge having composite synthetic steel tube beam material with slab and method of installing the beam material |
JP2010261154A (en) * | 2009-04-30 | 2010-11-18 | Kunio Honma | Pressing connection method for bridge through through-crossbeam |
CN104294748A (en) * | 2014-09-23 | 2015-01-21 | 同济大学 | Joint section structure for hybrid beam cable-stayed bridge and construction method thereof |
CN104294748B (en) * | 2014-09-23 | 2016-08-24 | 同济大学 | A kind of hybrid beam cable-stayed bridge adapter section structure and construction method thereof |
CN104264578A (en) * | 2014-10-21 | 2015-01-07 | 天津市市政工程设计研究院 | Steel-concrete combining bridge of self-anchored suspension cable-cable-stayed cooperative system |
CN104775365A (en) * | 2015-02-28 | 2015-07-15 | 张跃平 | Cable-stayed bridge construction method |
JP2017020199A (en) * | 2015-07-08 | 2017-01-26 | 三菱樹脂インフラテック株式会社 | Construction/civil engineering structure and bridge |
WO2018052030A1 (en) * | 2016-09-13 | 2018-03-22 | 清水建設株式会社 | Bridge construction method |
CN106702910A (en) * | 2016-12-29 | 2017-05-24 | 中交第三航务工程局有限公司 | Main girder construction process for extradosed cable-stayed bridge with double towers and double cable planes |
Also Published As
Publication number | Publication date |
---|---|
JP3669766B2 (en) | 2005-07-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11680401B2 (en) | Precast wall panels and method of erecting a high-rise building using the panels | |
US8074414B2 (en) | Precast wall panels and method of erecting a high-rise building using the panels | |
CN112695952B (en) | Building roof truss support structure and construction method | |
JP2010065378A (en) | Hanging scaffold and method for erecting the same | |
KR20180069554A (en) | Prestressed steel circular tube girder with partial filled concrete and structure construction method by using it | |
JPH09296416A (en) | Diagonally hanging structure and construction method | |
KR20040079917A (en) | Doubly prestressed roof-ceiling construction with grid flat-soffit for extremely large spans | |
JP3690437B2 (en) | Seismic reinforcement structure for existing buildings | |
KR100578641B1 (en) | Steel-Concrete Hybrid Column, Hybrid Structure System Using the Same, and Construction Method Thereof | |
JP4398876B2 (en) | Structure pier structure | |
CN109914616A (en) | A kind of dry construction connection structure of assembling frame structural construction corner post and beam | |
JPH10331437A (en) | Earthquake resistant reinforcing construction for existing beam and column | |
CN212053974U (en) | Lattice column and truss girder combined frame type large-span steel structure factory building | |
JPH10299088A (en) | Joint member for precast concrete column | |
JP3020343B2 (en) | Column base structure using hollow tube and method of constructing the same | |
WO1990005220A1 (en) | Adjustable space frames and trusses | |
CN111364774A (en) | Assembly tensioning process of large-span cable net | |
CN220133153U (en) | Assembled concrete type steel frame column-steel frame beam joint connection structure | |
JP3552691B2 (en) | Reinforcement structure of wooden building | |
CN114045928B (en) | Assembled beam column and column foundation splicing structure and construction method | |
JP7229634B2 (en) | Support jig for work scaffold in shaft, support jig unit, work scaffold in shaft, and method for constructing work scaffold in shaft | |
JP2003193564A (en) | Column-beam structural body, its construction method, and connection metal fitting | |
JPH0941565A (en) | Reinforcing structure of structural body | |
KR101832605B1 (en) | Transition pieces of offshore wind tiurbines and whole structure of wind turbines having it | |
JPH01111937A (en) | Opening structure and construction method of pillar and beam of building body |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040915 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040921 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20041122 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050315 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050412 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313122 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080422 Year of fee payment: 3 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313122 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080422 Year of fee payment: 3 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100422 Year of fee payment: 5 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100422 Year of fee payment: 5 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110422 Year of fee payment: 6 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110422 Year of fee payment: 6 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110422 Year of fee payment: 6 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110422 Year of fee payment: 6 |
|
R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110422 Year of fee payment: 6 |
|
R370 | Written measure of declining of transfer procedure |
Free format text: JAPANESE INTERMEDIATE CODE: R370 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110422 Year of fee payment: 6 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110422 Year of fee payment: 6 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120422 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130422 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130422 Year of fee payment: 8 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130422 Year of fee payment: 8 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130422 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140422 Year of fee payment: 9 |
|
LAPS | Cancellation because of no payment of annual fees |