JPH09221287A - Renewal method of elevator - Google Patents

Renewal method of elevator

Info

Publication number
JPH09221287A
JPH09221287A JP2944196A JP2944196A JPH09221287A JP H09221287 A JPH09221287 A JP H09221287A JP 2944196 A JP2944196 A JP 2944196A JP 2944196 A JP2944196 A JP 2944196A JP H09221287 A JPH09221287 A JP H09221287A
Authority
JP
Japan
Prior art keywords
new
elevator
existing
elevators
hall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2944196A
Other languages
Japanese (ja)
Inventor
Hitoshi Shimizu
均 清水
Tomoaki Suzuki
智昭 鈴木
Kiyotaka Hiraga
清高 平賀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Building Systems Co Ltd
Original Assignee
Hitachi Building Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Building Systems Co Ltd filed Critical Hitachi Building Systems Co Ltd
Priority to JP2944196A priority Critical patent/JPH09221287A/en
Publication of JPH09221287A publication Critical patent/JPH09221287A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

PROBLEM TO BE SOLVED: To replace an existing elevator with a new one without generation of the time when all elevators are not able to be operated, substantially. SOLUTION: In installing a new elevator in association with removal of an existing elevator 1, operation of the rest elevators 2, 3 is made possible by operation of an existing hall button 4, and then a new hall button 5 is set on the wall surface 11 of building. Through the operation of the button 5 new elevators are made possible to operate respectively while the existing elevators 2, 3 are removed, and after all existing elevators 1, 2, 3 are removed and the existing button 4 is also removed followed by installation of new elevators, all the new elevators can be operated continuously through the new bottom 5.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、複数台設置される
エレベータを、所定の台数ごとに順を追って新設エレベ
ータに交換するエレベータのリニュアル方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an elevator renewal method for sequentially replacing a plurality of elevators installed in a predetermined number with new elevators.

【0002】[0002]

【従来の技術】従来実施されているこの種のエレベータ
のリニュアル方法を、3台並列されるエレベータを1つ
のホール釦で運行させることができるようにしたものを
例に挙げて説明する。従来、例えば2つの方法が実施さ
れている。
2. Description of the Related Art A conventional elevator renewal method of this type will be described with reference to an example in which three hall elevators can be operated by one hall button. Conventionally, for example, two methods are implemented.

【0003】第1の従来のリニュアル方法は以下のとお
りである。 (1−1) 撤去交換する所定の台数を1台と予め設定
する。 (1−2) 最初の1台の既設エレベータを撤去し、対
応する1台の新設エレベータに交換する。この間、残り
の2台の既設エレベータは既設ホール釦による運行を可
能に保つ。また、新設エレベータの運行用に、エレベー
タホールの床上等に設置される養生ボックスに仮設ホー
ル釦を設置する。したがって、この状態では、仮設ホー
ル釦により1台の新設エレベータの運行が可能になり、
既設ホール釦により2台の既設エレベータの運行が可能
になる。
The first conventional renewal method is as follows. (1-1) The predetermined number of units to be removed and replaced is preset to one. (1-2) Remove the first existing elevator and replace it with the corresponding new elevator. During this period, the remaining two existing elevators will continue to operate using the existing hall buttons. In addition, a temporary hall button will be installed in the curing box installed on the floor of the elevator hall for the operation of the new elevator. Therefore, in this state, one new elevator can be operated by the temporary hall button,
The existing hall button allows the operation of two existing elevators.

【0004】(1−3) 次に、2台目の既設エレベー
タを撤去し、対応する2台目の新設エレベータに交換す
る。これにより、残りの既設エレベータは1台となり、
新設エレベータは2台となる。また、既設ホール釦で1
台の残りの既設エレベータの運行が可能に保たれ、仮設
ホール釦で2台の新設エレベータの運行が可能に保たれ
る。
(1-3) Next, the second existing elevator is removed and replaced with a corresponding second new elevator. As a result, the remaining existing elevator becomes one,
There will be two new elevators. Also, with the existing hall button, 1
The existing elevators of the rest of the cars can be operated, and the temporary hall buttons can be used to operate the two new elevators.

【0005】(1−4) 次に、3台目の既設エレベー
タを撤去し、対応する3台目の新設エレベータに交換す
る。これにより、既設エレベータは全て撤去され、3台
とも新設エレベータとなる。これらの新設エレベータは
全て仮設ホール釦による運行が可能に保たれる。
(1-4) Next, the third existing elevator is removed and replaced with a corresponding third newly installed elevator. As a result, all existing elevators will be removed and all three will be new elevators. All of these new elevators can be operated with temporary hall buttons.

【0006】(1−5) 最後に、既設ホール釦を撤去
し、養生ボックスの仮設ホール釦を、既設ホール釦のあ
った位置に新設ホール釦として移設する。この際、仮設
ホール釦と、新設エレベータの運行を制御する既設制御
盤との接続作業がおこなわれる。このようにして、3台
の既設エレベータの新設エレベータへの交換作業、すな
わちリニュアルが完了する。なお、上述した仮設ホール
釦の移設、既設制御盤の接続作業の間、3台の新設エレ
ベータの全てが運行不能な状態になる。
(1-5) Finally, the existing hall button is removed, and the temporary hall button of the curing box is moved to the position where the existing hall button was as a new hall button. At this time, connection work is performed between the temporary hall button and the existing control panel that controls the operation of the new elevator. In this way, the replacement work of the three existing elevators with the new elevators, that is, the renewal is completed. It should be noted that all of the three new elevators become inoperable during the above-mentioned transfer of the temporary hall buttons and connection work of the existing control panel.

【0007】また、第2の従来のリニュアル方法は以下
のとおりである。 (2−1) 撤去交換する所定の台数を1台と予め設定
する。 (2−2) 最初の1台の既設エレベータを撤去し、対
応する1台の新設エレベータに交換する。この間、残り
の2台の既設エレベータは、既設ホール釦により運行可
能に保たれる。
The second conventional renewal method is as follows. (2-1) The predetermined number of units to be removed and replaced is preset to one. (2-2) Remove the first existing elevator and replace it with the corresponding new elevator. During this period, the remaining two existing elevators are kept operable by the existing hall buttons.

【0008】(2−3) 既設ホール釦を撤去し、その
位置に新設ホール釦を設置する。このとき、新設ホール
釦と、新設エレベータの運行を制御する既設制御盤との
接続作業がおこなわれる。この新設ホール釦の設置、既
設制御盤との接続作業の間、1台の新設エレベータと2
台の残りの既設エレベータは全て運行不能な状態にな
る。作業終了後には、1台の新設エレベータが新設ホー
ル釦によって運行が可能になる。
(2-3) The existing hall button is removed and a new hall button is installed at that position. At this time, connection work is performed between the new hall button and the existing control panel that controls the operation of the new elevator. During installation of this new hall button and connection work with the existing control panel, one new elevator and two
All the remaining existing elevators on the car are out of service. After the work is completed, one new elevator can be operated with the new hall button.

【0009】(2−4) 次に、2台目の既設エレベー
タを撤去し、対応する2台目の新設エレベータに交換す
るとともに、この2台目の新設エレベータも上述した新
設ホール釦による運行が可能なようにする。
(2-4) Next, the second existing elevator is removed and replaced with a corresponding second newly installed elevator, and this second newly installed elevator is also operated by the above-mentioned new hall button. Make it possible.

【0010】(2−5) 最後に、3台目の既設エレベ
ータも撤去して、対応する3台目の新設エレベータに交
換し、この3台目の新設エレベータも新設ホール釦によ
る運行が可能なようにする。これにより、3台の既設エ
レベータの新設エレベータへのリニュアルが完了する。
(2-5) Finally, the third existing elevator is also removed and replaced with a corresponding third newly installed elevator, and this third newly installed elevator can also be operated by the new hall button. To do so. This completes the renewal of the three existing elevators to the new elevator.

【0011】[0011]

【発明が解決しようとする課題】上述した従来の第1の
リニュアル方法では、上記手順(1−5)で述べたよう
に、養生ボックスの仮設ホール釦を新設ホール釦として
移設し、この移設した仮設ホール釦と、新設エレベータ
の運行を制御する既設制御盤との接続作業をおこなう
際、3台の新設エレベータの全てが運行不能な状態にな
る。特に移設した仮設ホール釦と既設制御盤との接続作
業は一般に長時間かかるものであり、したがって長時間
にわたって全ての新設エレベータの運行不能を招いてし
まう。
In the above-mentioned first conventional renewal method, as described in the above procedure (1-5), the temporary hole button of the curing box is moved as a new hole button, and this is moved. When connecting the temporary hall button and the existing control panel that controls the operation of the new elevator, all three new elevators are in a non-operational state. In particular, the connection work between the relocated temporary hall button and the existing control panel generally takes a long time, so that the operation of all the new elevators will be stopped over a long time.

【0012】同様に、上述した従来の第2のリニュアル
方法では、上記手順(2−3)で述べたように、既設ホ
ール釦を撤去し、その位置に新設ホール釦を設置し、こ
の新設ホール釦と、新設エレベータの運行を制御する既
設制御盤との接続作業がおこなわれる際、既設エレベー
タと新設エレベータとを含めた全てのエレベータは長時
間にわたって運行不能となってしまう。
Similarly, in the above-mentioned second conventional renewal method, as described in the above procedure (2-3), the existing hole button is removed, a new hole button is installed at that position, and this new hole button is installed. When the button is connected to the existing control panel that controls the operation of the new elevator, all the elevators including the existing elevator and the new elevator will be inoperable for a long time.

【0013】すなわち、従来の第1,第2のリニュアル
方法のいずれも、全てのエレベータを運行不能にさせる
時間が存在し、しかもその運行不能な時間が比較的長く
なってしまう。
That is, in both the conventional first and second renewal methods, there is a time during which all elevators cannot be operated, and the time during which they cannot operate becomes relatively long.

【0014】したがって、これらの従来技術では、エレ
ベータの利用客に不便をかけ、サービス性が低下する問
題がある。また、例えば、全てのエレベータを運行不能
にしてしまう作業を、当該エレベータが設置される建物
の休日におこなうように、全体の作業行程及び作業日程
を設定する等、リニュアルの作業行程、作業日程に制約
を受ける問題がある。
Therefore, these conventional techniques have a problem that inconvenience is caused to elevator users and serviceability is deteriorated. In addition, for example, to perform work that makes all elevators inoperable on holidays of the building in which the elevator is installed, set the overall work schedule and work schedule, etc. for renewal work schedules and work schedules. There is a problem of being constrained.

【0015】なお、従来の第1のリニュアル方法では、
仮設ホール釦を既設制御盤に既設信号線を介して接続す
る際に、あるいは、既設ホール釦を撤去し仮設ホール釦
を移設する際に、誤って既設制御盤に接続される既設信
号線を切断したり、誤って配線してしまう懸念がある。
また、従来の第2のリニュアル方法では、既設ホール釦
を撤去し、新設ホール釦を既設制御盤に既設信号線を介
して接続する際に、誤って既設制御盤に接続される既設
信号線を切断したり、誤って配線してしまう懸念があ
る。このように、既設信号線を誤って切断したり、誤っ
て配線した場合には、全てのエレベータの運行が不能に
なってしまう。したがって、早急に復旧させるための処
理作業が必要になる。
In the first conventional renewal method,
When connecting the temporary hall button to the existing control panel via the existing signal line, or when removing the existing hall button and relocating the temporary hall button, accidentally disconnect the existing signal line connected to the existing control panel. Or there is a concern that wiring may be mistaken.
Also, in the second conventional renewal method, when the existing hall button is removed and the new hall button is connected to the existing control panel via the existing signal line, the existing signal line that is accidentally connected to the existing control panel is disconnected. There is a concern that it may be cut or the wiring may be mistaken. In this way, if the existing signal line is erroneously cut or erroneously wired, operation of all elevators will be disabled. Therefore, it is necessary to perform processing work for prompt recovery.

【0016】本発明は、上記した従来技術における実情
に鑑みてなされたもので、その目的は、全てのエレベー
タが同時に運行不能となる時間をほとんど生じさせない
で、既設エレベータを新設エレベータに交換することが
できるエレベータのリニュアル方法を提供することにあ
る。
The present invention has been made in view of the above-mentioned circumstances in the prior art, and an object thereof is to replace an existing elevator with a new elevator without causing a time in which all the elevators are inoperable at the same time. It is to provide a renewal method of an elevator capable of performing.

【0017】[0017]

【課題を解決するための手段】上記目的を達成するため
に、本発明の請求項1に係る発明は、複数台設置され、
エレベータホールに設けられた特定の既設ホール釦の操
作により運行が可能な既設エレベータを、所定の台数ご
とに複数回に分けて撤去するように予め設定し、順次、
新設エレベータに交換するエレベータのリニュアル方法
において、上記所定の台数の既設エレベータの撤去に伴
う対応する所定の台数の新設エレベータの設置の間、上
記既設ホール釦の操作による残りの既設エレベータの運
行を可能に保ち、上記新設エレベータに係る新設ホール
釦を、上記エレベータホール内の所定の操作可能位置に
設け、この新設ホール釦の操作による上記設置された新
設エレベータの運行を可能に保ち、上記残りの既設エレ
ベータの撤去に伴う対応する新設エレベータの設置の
間、上記新設ホール釦の操作による上記設置された新設
エレベータの運行を可能に保ち、上記全ての既設エレベ
ータの撤去、及び上記既設ホール釦の撤去に伴う全ての
新設エレベータの設置後も、継続的に上記新設ホール釦
による上記全ての新設エレベータの運行を可能に保つよ
うにしてある。
In order to achieve the above object, a plurality of inventions according to claim 1 of the present invention are installed,
An existing elevator that can be operated by operating a specific existing hall button provided in the elevator hall is preset to be removed in multiple times for each predetermined number of units, and in sequence,
In the renewal method of an elevator to be replaced with a new elevator, the remaining existing elevators can be operated by operating the existing hall buttons while installing the specified number of new elevators corresponding to the removal of the specified number of existing elevators. The new hall button related to the new elevator is provided at a predetermined operable position in the elevator hall, the operation of the newly installed elevator is enabled by operating the new hall button, and the remaining existing During the installation of the new elevator corresponding to the removal of the elevator, keep the operation of the new elevator installed by operating the new hall button, to remove all existing elevators, and to remove the existing hall buttons Even after installation of all new elevators, all of the above new It is to keep to enable the operation of the elevator.

【0018】このように構成した本発明の請求項1に係
る発明では、複数台設置された既設エレベータをリニュ
アルする場合、所定の台数の既設エレベータを対応する
所定の台数の新設エレベータに交換する作業の間は、既
設ホール釦によって残りの既設エレベータを運行させる
ことができ、利用客は、この残りの既設エレベータを利
用することができる。
In the invention according to claim 1 of the present invention thus configured, when a plurality of existing elevators are renewed, the work of replacing a predetermined number of existing elevators with a corresponding predetermined number of new elevators During the period, the remaining existing elevators can be operated by the existing hall button, and the customer can use the remaining existing elevators.

【0019】所定の台数の新設エレベータの設置が済
み、エレベータホール内の所定の操作可能位置に設けた
新設ホール釦の操作によって、当該所定の台数の新設エ
レベータの運行が可能になったときには、利用客は、こ
の所定の台数の新設エレベータも併せて利用することが
できる。
When a predetermined number of new elevators have been installed and operation of the new hall button provided at a predetermined operable position in the elevator hall makes it possible to operate the predetermined number of new elevators, use Customers can also use the predetermined number of new elevators together.

【0020】また、残りの既設エレベータを対応する新
設エレベータに交換する作業の間は、前述した新設ホー
ル釦の操作によって、設置済みの新設エレベータを運行
させることができ、利用客は、既設エレベータは利用で
きなくなったものの、設置済みの新設エレベータを利用
することができる。
During the work of replacing the remaining existing elevators with the corresponding new elevators, the new elevators already installed can be operated by operating the above-mentioned new hall button. It is no longer available, but you can use the new elevator already installed.

【0021】全ての既設エレベータが撤去され、また、
既設ホール釦が撤去された後は、利用客は、前述した新
設ホール釦の操作によって全ての新設エレベータを利用
することができる。
All existing elevators have been removed,
After the existing hall button is removed, the customer can use all the new elevators by operating the above-mentioned new hall button.

【0022】このように、本発明の請求項1に記載の発
明では、全てのエレベータが同時に運行不能となる時間
をほとんど生じさせないで、既設エレベータを新設エレ
ベータに交換することができる。
As described above, according to the first aspect of the present invention, the existing elevator can be replaced with the new elevator with almost no time in which all the elevators cannot be operated at the same time.

【0023】[0023]

【発明の実施の形態】以下、本発明のエレベータのリニ
ュアル方法の実施の形態を図に基づいて説明する。図
1,図2は、本発明の一実施形態を説明する図で、図1
はエレベータホールにおける状態を示す図、図2は昇降
路における状態を示す図である。はじめに、これらの図
1,2に示すものについて説明し、次にリニュアル方法
の本実施形態について説明する。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the elevator renewal method of the present invention will be described below with reference to the drawings. 1 and 2 are views for explaining an embodiment of the present invention.
Is a diagram showing a state in an elevator hall, and FIG. 2 is a diagram showing a state in a hoistway. First, what is shown in FIGS. 1 and 2 will be described, and then this embodiment of the renewal method will be described.

【0024】図1において、1は第1の既設エレベー
タ、2は第2の既設エレベータ、3は第3の既設エレベ
ータで、これらの既設エレベータ1,2,3は並列運転
されものである。4はリニュアル以前からある特定の既
設ホール釦である。この1つの既設ホール釦4の操作
で、例えば全ての既設エレベータ1,2,3が運行可能
になっている。5は後述するリニュアルによって新設さ
れる新設ホール釦である。この1つの新設ホール釦5の
操作で、図示しない新設エレベータ、すなわち後述する
ように既設エレベータ1,2,3のそれぞれと交換され
る全ての新設エレベータの運行が可能になる。
In FIG. 1, 1 is a first existing elevator, 2 is a second existing elevator, 3 is a third existing elevator, and these existing elevators 1, 2 and 3 are operated in parallel. Reference numeral 4 is a specific existing hole button that has existed before the renewal. By operating this one existing hall button 4, for example, all existing elevators 1, 2, 3 can be operated. Reference numeral 5 denotes a new hall button which is newly established by a renewal described later. By operating this one new hall button 5, it becomes possible to operate a new elevator (not shown), that is, all new elevators that are replaced with existing elevators 1, 2 and 3, respectively, as will be described later.

【0025】また、図2において、10は昇降路、11
は乗場出入口扉に隣接する建屋の壁面である。前述した
既設ホール釦4、新設ホール釦5は、互いにこの乗場出
入口扉に隣接する建屋の壁面11の異なる位置に配置さ
れる。6は既設エレベータ1,2,3の運行を制御する
既設制御盤、8は既設制御盤6と既設ホール釦4とを接
続する既設信号線である。7は既設エレベータ1,2,
3のそれぞれに対応する図示しない新設エレベータのそ
れぞれの運行を制御する新制御盤、9は新制御盤7と新
設ホール釦5とを接続する新設信号線である。
Further, in FIG. 2, 10 is a hoistway and 11
Is the wall of the building adjacent to the entrance door. The existing hall button 4 and the new hall button 5 described above are arranged at different positions on the wall surface 11 of the building adjacent to the hall door. Reference numeral 6 is an existing control panel for controlling the operation of the existing elevators 1, 2 and 3, and 8 is an existing signal line connecting the existing control panel 6 and the existing hall button 4. 7 is the existing elevator 1,2,
A new control panel for controlling the operation of each new elevator (not shown) corresponding to each of 3 and 9 is a new signal line for connecting the new control panel 7 and the new hall button 5.

【0026】本実施形態は、例えば上述の図1に示す3
台並列運転されるエレベータに適用されるものとして、
以下に説明する。
The present embodiment is, for example, 3 shown in FIG.
As applied to elevators that are operated in parallel with each other,
This will be described below.

【0027】(1) 撤去交換する所定の台数を1台と
予め設定する。 (2) 最初の1台の既設エレベータ1を撤去し、対応
する図示しない1台の新設エレベータに交換する。この
間、残りの2台の既設エレベータ2,3は、既設ホール
釦4の操作による運行を可能に保つ。したがって、利用
客は既設エレベータ2,3の2台のエレベータを利用す
ることができる。
(1) The predetermined number of units to be removed and replaced is preset to one. (2) Remove the first existing elevator 1 and replace it with a corresponding new elevator (not shown). During this time, the remaining two existing elevators 2 and 3 are kept operable by operating the existing hall button 4. Therefore, the customer can use the two elevators of the existing elevators 2 and 3.

【0028】(3) 上述した新設エレベータに係る新
設ホール釦5を、エレベータホール内の所定の操作可能
位置、例えば前述したように乗場出入口扉に隣接する建
屋の壁面11に設ける。このとき、図2に示すように新
設エレベータを制御する新制御盤7を既設制御盤6と別
に設け、この新制御盤7に新設信号線11を介して新設
ホール釦5を接続する。これにより、既設ホール釦4の
操作で既設エレベータ2,3を運行できるとともに、新
設ホール釦5の操作で、図1に示す既設エレベータ1と
交換した新設エレベータを運行させることができる。し
たがって、利用客は既設エレベータ2,3と1台の新設
エレベータとの3台のエレベータを利用することができ
る。
(3) The new hall button 5 relating to the above-mentioned new elevator is provided at a predetermined operable position in the elevator hall, for example, on the wall surface 11 of the building adjacent to the entrance door as described above. At this time, as shown in FIG. 2, a new control panel 7 for controlling the new elevator is provided separately from the existing control panel 6, and the new hall button 5 is connected to this new control panel 7 via a new signal line 11. Thus, the existing elevators 2 and 3 can be operated by operating the existing hall button 4, and the new elevator that is replaced with the existing elevator 1 shown in FIG. 1 can be operated by operating the new hall button 5. Therefore, the customer can use the three elevators, the existing elevators 2 and 3 and the one new elevator.

【0029】(4) 次に、2台目の既設エレベータ2
を撤去し、対応する2台目の新設エレベータに交換し、
この2台目の新設エレベータを新設ホール釦5で運行可
能にする。これにより、既設ホール釦4の操作で既設エ
レベータ3を運行できるとともに、新設ホール釦5の操
作で、図1に示す既設エレベータ1,2と交換した2台
の新設エレベータを運行させることができる。したがっ
て、利用客は既設エレベータ3と2台の新設エレベータ
との3台のエレベータを利用することができる。
(4) Next, the second existing elevator 2
Removed and replaced with a corresponding new elevator,
This new elevator can be operated with the new hall button 5. As a result, the existing elevator 3 can be operated by operating the existing hall button 4, and the two newly installed elevators replaced with the existing elevators 1 and 2 shown in FIG. 1 can be operated by operating the new hall button 5. Therefore, the customer can use the three elevators, the existing elevator 3 and the two new elevators.

【0030】なお、2台目の既設エレベータ2の撤去作
業、及び対応する新設エレベータの設置作業の間は、既
設エレベータ3と、既に設置された1台の新設エレベー
タとの2台のエレベータが運行可能に保たれ、利用者は
2台のエレベータを利用することができる。
During the work of removing the second existing elevator 2 and the work of installing the corresponding new elevator, two elevators, the existing elevator 3 and the one new elevator already installed, operate. Keeping possible, users can use two elevators.

【0031】(5) 次に、3台目の既設エレベータ3
を撤去し、対応する3台目の新設エレベータに交換し、
この3台目の新設エレベータを新設ホール釦5で運行可
能にする。これにより、既設エレベータ1,2,3に代
わり、全ての新設エレベータが新設ホール釦5で操作可
能になる。したがって、その後は新設ホール釦5の操作
により、利用客は3台のエレベータを利用することがで
きる。
(5) Next, the third existing elevator 3
Removed and replaced with a corresponding new 3rd elevator,
This new elevator can be operated with the new hall button 5. As a result, instead of the existing elevators 1, 2 and 3, all new elevators can be operated by the new hall button 5. Therefore, after that, the user can use the three elevators by operating the new hall button 5.

【0032】なお、3台目の既設エレベータ3の撤去作
業、及び対応する新設エレベータの設置作業の間は、既
に設置された2台の新設エレベータが運行可能に保た
れ、利用者は、この2台のエレベータを利用することが
できる。
During the removal work of the third existing elevator 3 and the installation work of the corresponding new elevator, the two newly installed elevators are kept operable and the user can A single elevator is available.

【0033】(6) 最後に、既設ホール釦4、既設信
号線8、及び既設制御盤6を撤去する。これにより、エ
レベータのリニュアルは完了する。
(6) Finally, the existing hall button 4, the existing signal line 8 and the existing control panel 6 are removed. This completes the elevator renewal.

【0034】このようにしてエレベータのリニュアルを
実施する本実施形態では、全てのエレベータが同時に運
行不能となる時間をほとんど生じさせないで、既設エレ
ベータ1,2,3を3台の新設エレベータに交換するこ
とができる。したがって、エレベータの利用客に及ぼす
迷惑を最少限度に止めることができ、リニュアル時の利
用客に対するサービス性を高めることができる。また、
少なくとも2台のエレベータをいつも利用できるように
してあることから、リニュアル作業を建物の休日におこ
なわなくても済み、このリニュアルの作業日程、及び作
業行程の自由度を確保することができる。
In this embodiment in which the elevators are renewed in this way, the existing elevators 1, 2 and 3 are replaced with three new elevators with almost no time in which all the elevators are inoperable at the same time. be able to. Therefore, annoyance to the passengers of the elevator can be minimized, and the serviceability to the passengers at the time of renewal can be improved. Also,
Since at least two elevators are always available, renewal work does not have to be performed on the holidays of the building, and this renewal work schedule and work process flexibility can be secured.

【0035】また、新設ホール釦5、新設信号線9、及
び新制御盤7の信号系統と、既設ホール釦4、既設信号
線8、及び既設制御盤6の信号系統とを互いに独立して
設定してあることから、既設ホール釦4等の撤去に際し
て、信号線の撤去の手順が本来望ましいとされる手順と
異なっていたり、あるいは、信号線の不要な切断を生じ
てしまったとしても、就役中のエレベータの運行には影
響を及ぼすことがなく、したがって利用客に迷惑をかけ
ることがない。
Further, the signal system of the new hall button 5, the new signal line 9 and the new control panel 7 and the signal system of the existing hall button 4, the existing signal line 8 and the existing control panel 6 are set independently of each other. Therefore, when removing the existing hall button 4 or the like, even if the procedure for removing the signal line is different from the originally desired procedure, or if the signal line is unnecessarily disconnected, It does not affect the operation of the elevator inside and therefore does not bother the passengers.

【0036】なお、上記実施形態では、1つの新設ホー
ル釦5により、3台の新設エレベータの運行が可能なよ
うに設定したが、本発明は、このように設定することに
は限られず、例えば撤去した既設ホール釦4の位置にも
別の新設ホール釦を設け、この別の新設ホール釦によっ
ても3台の新設エレベータの運行が可能なようにしても
よい。すなわち、複数の新設ホール釦の操作で複数の新
設エレベータの運行が可能なようにしてもよい。
In the above-mentioned embodiment, the setting is made such that the operation of three new elevators is possible with one new hall button 5, but the present invention is not limited to this setting, and for example, Another new hall button may be provided at the position of the removed existing hall button 4 so that the three new elevators can also be operated by this other new hall button. That is, a plurality of new elevators may be operated by operating a plurality of new hall buttons.

【0037】また、上記実施形態では、3台並列エレベ
ータのリニュアルについて適用した例を挙げたが、2台
並列エレベータのリニュアル、4台以上並列エレベータ
のリニュアルにも同様にして適用できる。また、並列エ
レベータどうしを、エレベータホールを挾むように対向
させて全体を形成したエレベータにあっても、同様にし
て適用することができる。
Further, in the above-mentioned embodiment, an example in which it is applied to the renewal of three parallel elevators is given, but it can be similarly applied to the renewal of two parallel elevators and the renewal of four or more parallel elevators. Further, the present invention can be similarly applied to an elevator in which parallel elevators are opposed to each other so as to sandwich an elevator hall and the whole is formed.

【0038】また、上記実施形態では、新設ホール釦5
を建屋の壁面11に設けたが、エレベータの利用に都合
のよい場所であれば、建屋の壁面11でなくてもよく、
要するにエレベータホール内の操作可能な位置に設けれ
ばよい。
In the above embodiment, the new hall button 5
Is provided on the wall surface 11 of the building, but it is not limited to the wall surface 11 of the building as long as it is a convenient place to use the elevator,
In short, it may be provided at an operable position in the elevator hall.

【0039】また、上記実施形態では、3台並列運行さ
れるエレベータを挙げ、リニュアルに際し、1台ずつ交
換するようにしたが、4台以上エレベータが設けられる
場合などにあっては、リニュアルに際し、交換単位を形
成する所定の台数を2台等の複数に設定してもよい。
Further, in the above embodiment, three elevators that are operated in parallel are cited, and one elevator is replaced at a time of renewal. However, in the case where four or more elevators are provided, at the time of renewal, The predetermined number of units forming the exchange unit may be set to two or more.

【0040】[0040]

【発明の効果】以上のように本発明によれば、全てのエ
レベータが同時に運行不能となる時間をほとんど生じさ
せないで、既設エレベータを新設エレベータに交換する
ことができ、これによりエレベータの利用客に及ぼす迷
惑を最少限度に止めることができ、従来に比べてリニュ
アル時の利用客に対するサービス性を高めることができ
る。また、利用可能なエレベータがいつも存在すること
から、リニュアル作業を建物の休日等の特別な日におこ
なわなくても済み、従来に比べてリニュアルの作業日
程、及び作業行程の自由度を得ることができる。
As described above, according to the present invention, it is possible to replace an existing elevator with a new elevator without causing a time in which all the elevators are inoperable at the same time. It is possible to minimize the inconvenience caused and to improve the serviceability to the customer at the time of renewal as compared with the conventional case. In addition, since there are always available elevators, it is not necessary to perform renovation work on special days such as building holidays, and it is possible to obtain more freedom in renewal work schedules and work processes than before. it can.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施形態を説明する図であって、エ
レベータホールにおける状態を示す図である。
FIG. 1 is a diagram illustrating an embodiment of the present invention and is a diagram illustrating a state in an elevator hall.

【図2】本発明の一実施形態を説明する図であって、昇
降路における状態を示す図である。
FIG. 2 is a diagram illustrating an embodiment of the present invention and is a diagram showing a state in a hoistway.

【符号の説明】[Explanation of symbols]

1 第1の既設エレベータ 2 第2の既設エレベータ 3 第3の既設エレベータ 4 既設ホール釦 5 新設ホール釦 6 既設制御盤 7 新制御盤 8 既設信号線 9 新設信号線 10 昇降路 11 壁面 1 First existing elevator 2 Second existing elevator 3 Third existing elevator 4 Existing hall button 5 New hall button 6 Existing control panel 7 New control panel 8 Existing signal line 9 New signal line 10 Hoistway 11 Wall surface

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 複数台設置され、エレベータホールに設
けられた特定の既設ホール釦の操作により運行が可能な
既設エレベータを、所定の台数ごとに複数回に分けて撤
去するように予め設定し、順次、新設エレベータに交換
するエレベータのリニュアル方法において、 上記所定の台数の既設エレベータの撤去に伴う対応する
所定の台数の新設エレベータの設置の間、上記既設ホー
ル釦の操作による残りの既設エレベータの運行を可能に
保ち、 上記新設エレベータに係る新設ホール釦を、上記エレベ
ータホール内の所定の操作可能位置に設け、この新設ホ
ール釦の操作による上記設置された新設エレベータの運
行を可能に保ち、 上記残りの既設エレベータの撤去に伴う対応する新設エ
レベータの設置の間、上記新設ホール釦の操作による上
記設置された新設エレベータの運行を可能に保ち、 上記全ての既設エレベータの撤去、及び上記既設ホール
釦の撤去に伴う全ての新設エレベータの設置後も、継続
的に上記新設ホール釦による上記全ての新設エレベータ
の運行を可能に保つことを特徴とするエレベータのリニ
ュアル方法。
1. A plurality of existing elevators that can be operated by operating a specific existing hall button provided in an elevator hall are set in advance so as to be removed in a plurality of times for a predetermined number of units, In the renewal method of elevators that are sequentially replaced with new elevators, the operation of the remaining existing elevators by operating the existing hall buttons while installing the specified number of new elevators corresponding to the removal of the specified number of existing elevators The new hall button related to the new elevator is provided at a predetermined operable position in the elevator hall, and the operation of the newly installed elevator can be maintained by operating the new hall button. During the installation of a new elevator corresponding to the removal of the existing elevator of It is possible to operate all newly installed elevators, and even after all the above existing elevators are removed and all the new elevators are installed due to the removal of the above existing hall buttons, all the above new installations by the above new hall buttons are continuously performed. A renewal method for an elevator, characterized by keeping the operation of the elevator possible.
【請求項2】 上記新設ホール釦を、乗場出入口扉に隣
接する建屋の壁面に設けたことを特徴とする請求項1記
載のエレベータのリニュアル方法。
2. The elevator renewal method according to claim 1, wherein the new hall button is provided on a wall surface of a building adjacent to a hall door.
【請求項3】 上記特定の新設ホール釦の数が1つであ
ることを特徴とする請求項1記載のエレベータのリニュ
アル方法。
3. The elevator renewal method according to claim 1, wherein the number of the specific new hall buttons is one.
【請求項4】 上記特定の新設ホール釦の数が複数であ
ることを特徴とする請求項1記載のエレベータのリニュ
アル方法。
4. The elevator renewal method according to claim 1, wherein the number of the specific new hall buttons is plural.
【請求項5】 上記新設エレベータの設置は、この新設
エレベータの運行を制御する新制御盤の設置を含むこと
を特徴とする請求項1記載のエレベータのリニュアル方
法。
5. The elevator renewal method according to claim 1, wherein the installation of the new elevator includes the installation of a new control panel for controlling the operation of the new elevator.
【請求項6】 上記既設エレベータが、複数台並列に運
行するように保たれるエレベータであることを特徴とす
る請求項1記載のエレベータのリニュアル方法。
6. The elevator renewal method according to claim 1, wherein the existing elevator is an elevator that is maintained so that a plurality of existing elevators are operated in parallel.
JP2944196A 1996-02-16 1996-02-16 Renewal method of elevator Pending JPH09221287A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2944196A JPH09221287A (en) 1996-02-16 1996-02-16 Renewal method of elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2944196A JPH09221287A (en) 1996-02-16 1996-02-16 Renewal method of elevator

Publications (1)

Publication Number Publication Date
JPH09221287A true JPH09221287A (en) 1997-08-26

Family

ID=12276226

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2944196A Pending JPH09221287A (en) 1996-02-16 1996-02-16 Renewal method of elevator

Country Status (1)

Country Link
JP (1) JPH09221287A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017218304A (en) * 2016-06-09 2017-12-14 三菱電機ビルテクノサービス株式会社 Elevator renewal method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017218304A (en) * 2016-06-09 2017-12-14 三菱電機ビルテクノサービス株式会社 Elevator renewal method

Similar Documents

Publication Publication Date Title
EP0523601B1 (en) Procedure for modernizing an elevator group
KR101093664B1 (en) Elevator cross-dispatching system with inter group relative system response ?????? dispatching
WO2011001495A1 (en) Elevator renewal method
JPH0710400A (en) Method and equipment to modernize control part of elevator group
MY124558A (en) Group-controlled elevator system
JPH09221287A (en) Renewal method of elevator
US4266632A (en) Elevator system
JP5750034B2 (en) Elevator hall button replacement device and elevator hall button replacement method
JP2009057190A (en) Cleaning operation system for elevator
JP2008143662A (en) Elevator renewal time group supervision control system
JPH1087206A (en) Maintenance running device for elevator
JPH02117571A (en) Renewal method for group management elevator
JP2003081556A (en) Refurbishing method for elevator
JP4097765B2 (en) Elevator old and new control unit replacement method and modernization shielding plate used therefor
JPS6141733Y2 (en)
JPH10279202A (en) Elevator control device
JP3170550B2 (en) Elevator renewal method
JP2004137012A (en) Apparatus for modifying group-controlled elevator, and method for modifying the apparatus
JPS61235383A (en) Method of reconstruction work of elevator
JP3179653B2 (en) How to modify the elevator
JPH10120330A (en) Control system of apposed elevators
JPH0751433B2 (en) Remodeling method of the elevator
JPH09208139A (en) Car operation controller for elevator
JPH063011Y2 (en) Operation buttons for elevator
JPH09183579A (en) Temporary hall button