JPH0921231A JP19113595A JP19113595A JPH0921231A JP H0921231 A JPH0921231 A JP H0921231A JP 19113595 A JP19113595 A JP 19113595A JP 19113595 A JP19113595 A JP 19113595A JP H0921231 A JPH0921231 A JP H0921231A
Authority
JP
Japan
Prior art keywords
work
information
time
unit
cad
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP19113595A
Other languages
Japanese (ja)
Inventor
Fumio Hatori
文雄 羽鳥
Yuji Yokoi
裕司 横井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Plant Technologies Ltd
Original Assignee
Hitachi Plant Technologies Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Plant Technologies Ltd filed Critical Hitachi Plant Technologies Ltd
Priority to JP19113595A priority Critical patent/JPH0921231A/en
Publication of JPH0921231A publication Critical patent/JPH0921231A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve the estimation of time by predicting the operating procedure of a specified work utilizing an operating procedure comprising multiple basic operations the required time for which is already known and the work space information and amount of materials information obtained when work drawings by CAD are prepared. SOLUTION: Operating procedure information in which operating procedures for unit work are disassembled into multiple basic operations the required time for which is already known, work space information on work site in which unit work is carried out, CAD information in which amount of materials information on the object to be worked is stored, and existing time information in which the basic operations are carried out under the working site space conditions are stored in advance in a database 1. Next a calculation part 2 takes out necessary data from the database 1, predicts the operating procedure for a specified work, disassembles it into basic operations, and calculates the required time for the basic operations according to the work space conditions. Then, in this case, an interface part 3 displays the work space information on a three-dimensional screen, and prepares a proper procedure while simulating the operating procedure. Thus the working time can be predicted accurately and easily.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は作業時間算出方法に係
り、特に、建築分野において対象とする作業に要する時
間を事前に推測する作業時間算出方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a work time calculation method, and more particularly to a work time calculation method for estimating in advance the time required for a target work in the construction field.

【0002】[0002]

【従来の技術】従来、建設分野では作業時間を事前に推
測する方法として、経験的判定、統計的方法、既定時間
法がある。経験的判定は、担当者が過去に経験した見積
もりの実績から過去の作業条件と新規の作業条件とを照
らし合わせて作業時間を推測する方法である。
2. Description of the Related Art Conventionally, in the construction field, there are empirical judgment, statistical method, and fixed time method as methods for estimating work time in advance. The empirical determination is a method of estimating the work time by comparing the past work condition and the new work condition from the past results of estimations performed by the person in charge.

【0003】統計的方法は、作業条件・作業内容別に過
去の実績値を分析し、求めた標準値を用いて作業時間を
推測する方法である。既定時間法は予め与えられている
人間の動作に要する時間を用いて作業時間を推測する方
法である。
The statistical method is a method in which past performance values are analyzed for each work condition and work content, and the working time is estimated by using the obtained standard value. The predetermined time method is a method of estimating a working time by using a time required for human motion given in advance.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、建設分
野のように単品生産で作業の繰り返し性の少ない分野で
は、経験的判定をするには充分な見積もり経験を積んだ
専門家の知識が必要なこと、統計的方法では高い信頼性
で判定できるだけの多量な実績データが必要であるこ
と、過去に類似例のない新規の作業については推測値の
信頼性が落ちること等の問題があった。
However, in fields such as the construction field, where the repeatability of work is small in the production of a single item, the knowledge of an expert who has sufficient estimation experience is necessary for empirical judgment. However, there are problems that the statistical method requires a large amount of actual data that can be judged with high reliability, and that the reliability of the estimated value decreases for new work that has no similar example in the past.

【0005】既定時間法を適用するには事前に動作レベ
ルまでの詳細な作業手順を記述しなければならない。と
ころが、これについても建設分野では、単品生産である
こと、作業環境等に影響を受け、毎回作業手順が異なる
こと等から詳細な作業手順を事前に予測することは難し
く、そのために既定時間法の適用が困難という問題点が
あった。また、図面を用いて作業手順を推測しようとし
ても対象物の情報(寸法、重量等)は得られても、周り
の作業環境の情報(作業域の広さ、資材、道工具の置場
等)が得られないため既定時間法を適用できる動作レベ
ルまでの作業手順の予測は困難であった。
In order to apply the fixed time method, a detailed work procedure up to the operation level must be described in advance. However, regarding this as well, in the construction field, it is difficult to predict detailed work procedures in advance because it is a single item production, is affected by the work environment, etc., and the work procedures are different each time. There was a problem that it was difficult to apply. In addition, even if you try to guess the work procedure using drawings, you can obtain information about the target object (dimensions, weight, etc.), but information about the surrounding work environment (size of work area, materials, storage space for road tools, etc.) It was difficult to predict the work procedure up to the motion level to which the default time method can be applied, because it is not possible to obtain.

【0006】本発明は、このような問題に鑑みてなされ
たもので、事前に作業手順を予測する際の作業手順決定
のための条件を与え、予測の支援方法を提供し、作業時
間算出方法の1つである既定時間法を用いて精度良く作
業時間を算出する作業時間算出方法を提供することを目
的とする。
The present invention has been made in view of such a problem, and provides conditions for determining a work procedure when predicting a work procedure in advance, provides a prediction support method, and calculates a work time. It is an object of the present invention to provide a work time calculation method for accurately calculating work time using a predetermined time method which is one of the above.

【0007】[0007]

【課題を解決する為の手段】本発明は、前記目的を達成
するために、建設工事等の施行工事における所定作業の
作業時間を算出する作業時間算出方法において、前記施
行工事の単位作業の動作手順を所要時間の既知な複数の
基本動作に分解した動作手順情報と、前記単位作業を行
う作業場の作業空間情報及び作業対象物の物量情報が収
納されたCAD情報と、前記基本動作を前記作業場の空
間条件下で行った時の所要時間である既定時間情報とを
データベースとして予め記憶し、作業時間を算出したい
所定作業の動作手順を前記CAD情報から得られる作業
場の作業空間情報及び作業対象物の物量情報を支援情報
として予測すると共に、予測した動作手順を前記動作手
順情報の基本動作に分解し、前記分解した基本動作を前
記作業場の空間条件下で行った時の所要時間を前記既定
時間情報に基づいて求め、前記求めた各基本動作の所要
時間を加算して前記所定作業の作業時間を算出すること
を特徴としている。
In order to achieve the above object, the present invention provides a work time calculating method for calculating a work time of a predetermined work in a construction work such as a construction work. Operation procedure information obtained by disassembling a procedure into a plurality of basic operations of known required time, CAD information in which the work space information of the work area where the unit work is performed and the physical quantity information of the work target are stored, and the basic operation of the work area Pre-stored time information, which is the required time when performed under the space conditions, is stored in advance as a database, and the operation procedure of the predetermined work whose work time is to be calculated is obtained from the CAD information. Of the physical quantity information as the support information, the predicted operation procedure is decomposed into the basic operation of the operation procedure information, and the decomposed basic operation is the space condition of the workplace. Determined based on the time required when I went under the predetermined time information, by adding the time required for each basic operation determined the are and calculates the operation time of the predetermined operation.

【0008】[0008]

【作用】本発明は、現在、建設工事等の施工図の大半は
CAD(computer aided desig
n)で作成され、CAD情報から作業場の作業空間情報
及び作業対象物の物量情報(作業対象物の質量、寸法、
形状等)が容易に得られることに着目し、このCAD情
報を利用して特に単品生産で作業空間環境がその都度変
化するために所定作業の作業手順を正確に予測しにくい
建設工事等における所定作業の作業時間を算出するもの
である。
According to the present invention, most of construction drawings for construction work and the like are currently CAD (computer aided design).
n), the work space information of the workplace and the physical quantity information of the work target (the mass, the size of the work target, the
Paying attention to the fact that the shape etc.) can be easily obtained, and using this CAD information, it is difficult to accurately predict the work procedure of the predetermined work because the work space environment changes each time especially in single item production. The work time of work is calculated.

【0009】本発明によれば、単位作業の動作手順を所
定時間の既知な複数の基本動作に分解した動作手順情報
と、前記単位作業を行う作業場の作業空間情報及び作業
対象物の物量情報が収納されたCAD情報と、前記基本
動作を前記作業場の空間条件下で行った時の所要時間で
ある既定時間情報とを予めデータベースとして記憶して
おく。そして、前記データベースから必要な情報を取り
出して、作業時間を算出したい所定作業の動作手順を予
測し、予測した動作手順を基本動作に分解し、作業場の
作業空間条件に応じた基本動作の所要時間を算出する。
この時、CAD情報を支援情報として所定作業の動作手
順を予測するようにしたので、単品生産で作業空間環境
がその都度変化する作業の場合でも動作手順を正確に且
つ容易に予測することができる。また、CAD情報から
得られる作業場の作業空間情報を三次元画面で表示する
ことにより、作業の動作手順をシミュレートしながら行
うことができるので、より適切な作業の動作手順を作成
することができる。
According to the present invention, the operation procedure information in which the operation procedure of the unit work is decomposed into a plurality of known basic operations of a predetermined time, the work space information of the work place where the unit work is performed, and the physical quantity information of the work object are provided. The stored CAD information and predetermined time information which is a required time when the basic operation is performed under the space condition of the workplace are stored in advance as a database. Then, the necessary information is taken out from the database, the operation procedure of the predetermined work whose work time is to be calculated is predicted, the predicted operation procedure is decomposed into the basic operation, and the required time of the basic operation according to the workspace condition of the workplace. To calculate.
At this time, since the operation procedure of the predetermined work is predicted by using the CAD information as the support information, it is possible to accurately and easily predict the operation procedure even in the case of the work in which the work space environment changes each time in the single-item production. . Further, by displaying the work space information of the work space obtained from the CAD information on the three-dimensional screen, it is possible to perform the work procedure while simulating the work procedure of the work, so that a more appropriate work procedure can be created. .

【0010】[0010]

【実施例】以下添付図面に従って本発明に係る作業時間
算出方法の好ましい実施例について詳説する。図1は、
本発明に係る作業時間算出方法が適用される作業時間算
出装置の一実施例を示す構成図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A preferred embodiment of a working time calculating method according to the present invention will be described below in detail with reference to the accompanying drawings. FIG.
It is a block diagram which shows one Example of the work time calculation apparatus to which the work time calculation method which concerns on this invention is applied.

【0011】同図に示すように作業時間算出装置は、デ
ータベース部1、演算部2及びインタフェース部3から
構成される。データベース部1は、フロッピーディスク
等の記録媒体によって構成され、インタフェース部3の
モニタに出力する画像データやメッセージデータ1C等
を提供するとともに、演算部2で行われる各種演算に必
要なデータを提供する。
As shown in the figure, the work time calculating device comprises a database unit 1, a computing unit 2 and an interface unit 3. The database unit 1 is composed of a recording medium such as a floppy disk and provides image data and message data 1C to be output to the monitor of the interface unit 3 as well as data necessary for various calculations performed by the calculation unit 2. .

【0012】同図に示すようにデータベース部1には、
作業場に関するCAD情報1A(即ち、作業場の3D画
像を表示するための梁、鉄骨等の位置(座業)を示す情
報や、作業場に設置する配管等の重量や寸法等を示す情
報)、ある単位作業(作業を幾つかの区切りに分割した
もの)を遂行するのに必要な基本的動作の手順(動作手
順)を示す動作手順データ1B、単位作業を遂行するの
に必要な基本的動作の条件(この条件は、動作に付加さ
れる条件(例えば、歩行という動作に対して通路状況の
良否)のことで、以下、動作条件という。)を対話形式
でユーザが入力するためのメッセージデータ1C、歩行
等の基本動作を所定動作条件下で行う際に要する時間を
定めた既定時間データ1Dが記憶されている。
As shown in FIG.
CAD information 1A related to the workplace (that is, information indicating the position (seating) of beams, steel frames, etc. for displaying a 3D image of the workplace, information indicating the weight and dimensions of the pipes and the like installed in the workplace), a certain unit Operation procedure data 1B indicating a basic operation procedure (operation procedure) required to perform a work (a work divided into some divisions), a basic operation condition required to perform a unit work (This condition is a condition added to the motion (for example, the quality of the passage condition with respect to the motion of walking), and is hereinafter referred to as motion condition.) Message data 1C for the user to input in an interactive manner, Stored is preset time data 1D that defines the time required to perform a basic motion such as walking under predetermined motion conditions.

【0013】上記動作手順データ1B及びメッセージデ
ータ1Cの内容の一例を図2に示す。同図(A)は、ユ
ーザが例えば単位作業名にチェーンブロック設定を指定
し、チェーンブロック設定に要する時間を計算しようと
した場合に、演算部2で参照される動作手順データ1B
及びメッセージデータ1Cの内容を示している。同図に
示すように、チェーンブロック設定という単位作業に対
して、参照される動作手順データ1Bには、「チェーン
ブロックを取りにゆく」と、「チェーンブロックを取り
付ける」という内容が記憶されている。つまり、この動
作手順データ1Bは、チェーンブロック設定が、まず、
チェーンブロックを取りにゆき、次にそのチェーンブロ
ックを取り付けるという基本動作の手順によって行われ
ることを示している。
An example of the contents of the operation procedure data 1B and the message data 1C is shown in FIG. FIG. 1A shows the operation procedure data 1B referred to by the calculation unit 2 when the user specifies the chain block setting in the unit work name and tries to calculate the time required for the chain block setting.
And the contents of the message data 1C are shown. As shown in the same figure, for the unit work of setting the chain block, the operation procedure data 1B referred to stores the contents of "getting the chain block" and "attaching the chain block". . In other words, this operation procedure data 1B has the chain block setting
It shows that the basic operation procedure is to take the chain block and then attach the chain block.

【0014】それに対して、メッセージデータ1Cに
は、「道工具置き場はどこですか」、「チェーンブロッ
クのタイプは? A:2t B:3t C:レバーブロ
ック・・・」、「取付位置を決めてください」、「もう
一つ必要ですか?(Y/N)」等のメッセージの内容が
記憶されている。これらのメッセージは、チェーンブロ
ック設定という単位作業を構成する基本動作に関してユ
ーザが決定すべき動作条件の内容を示し、モニタ画面に
表示されたこれらのメッセージに従ってユーザが対話形
式でこれらの動作条件を決定できるようにしている。
On the other hand, in the message data 1C, "Where is the road tool storage space?", "What is the type of chain block? A: 2t B: 3t C: Lever block ...", "Determine the mounting position" The contents of the message such as "Please,""Do you need another? (Y / N)" are stored. These messages indicate the contents of the operating conditions that the user should decide regarding the basic operations that make up the unit work called chain block setting, and the user interactively determines these operating conditions according to these messages displayed on the monitor screen. I am able to do it.

【0015】同様に、同図(B)は、ユーザが単位作業
名に搬入を指定し、搬入に要する時間を計算しようとし
た場合を示している。また、上記既定時間データ1Dの
内容の一例を図3に示す。同図(A)は、歩行という基
本動作に対する既定時間データ1Dの内容を示してい
る。同図に示すようにこの既存データは、歩行距離に対
する通路状況に応じた歩行時間を示している。例えば、
歩行距離が7〜20mの場合で通路状況が良い場合は、
この歩行に12秒要する。
Similarly, FIG. 3B shows a case where the user specifies carry-in as a unit work name and tries to calculate the time required for carry-in. Further, FIG. 3 shows an example of the contents of the predetermined time data 1D. The same figure (A) has shown the content of predetermined time data 1D with respect to the basic motion called walking. As shown in the figure, this existing data indicates the walking time according to the passage condition with respect to the walking distance. For example,
If the walking distance is 7 to 20 m and the passage is good,
This walk takes 12 seconds.

【0016】同図(B)は、引っ張るという基本動作に
対する既定時間データ1Dの内容を示している。同図に
示すようにこの既存データは、引っ張る時間に対する力
量に応じた引っ張り回数を示している。このように既定
時間データ1Dには、動作条件に応じた基本動作に要す
る時間が各種基本動作に関して記憶されている。
FIG. 1B shows the contents of the preset time data 1D for the basic pulling operation. As shown in the figure, this existing data indicates the number of times of pulling according to the amount of force with respect to the pulling time. As described above, the predetermined time data 1D stores the time required for the basic operation according to the operation condition for various basic operations.

【0017】図1の演算部2は、例えばコンピュータ
で、データベース部1やインタフェース部3に対して各
種データの入出力制御を行うとともに、データベース部
1やインタフェース部3からのデータを参照して各種演
算を行う。同図に示すように、演算部2は、CAD画像
やメッセージ、演算結果等の文字情報等を表示する表示
機能2A、データベース部1のデータを参照するデータ
ベース参照機能2B、作業時間を算出するために必要な
条件(CAD情報、単位作業名、動作手順、動作条件)
を記憶する入力部2C、入力部2Cに記憶された条件に
対し、データベース参照機能2Bによってデータベース
部1の既定時間データ1Dから既定時間を参照し、作業
時間を計算する演算機能2Dを有している。
The computing unit 2 in FIG. 1 is, for example, a computer that controls the input / output of various data with respect to the database unit 1 and the interface unit 3 and refers to the data from the database unit 1 and the interface unit 3 to perform various operations. Calculate. As shown in the drawing, the calculation unit 2 displays a CAD image, a message, a display function 2A for displaying character information such as a calculation result, a database reference function 2B for referring to data in the database unit 1, and a work time for calculating the work time. Conditions (CAD information, unit work name, operation procedure, operation conditions)
For the condition stored in the input unit 2C and the input unit 2C, the database reference function 2B refers to the preset time from the preset time data 1D of the database unit 1 and has a calculation function 2D for calculating the working time. There is.

【0018】インタフェース部3は、モニタ等の端末装
置を有する表示装置及びキーボード、マウス等の端末装
置を有する入力装置から構成され、表示装置は、CAD
画像を表示するCAD画面表示部3A、メッセージを表
示するメッセージ表示部3B、演算結果を表示するアウ
トプット表示部3Cを有している。また、入力装置は、
作業時間を算出する単位作業名及び動作条件を入力する
作業動作入力機能3Dを有している。
The interface unit 3 comprises a display device having a terminal device such as a monitor and an input device having a terminal device such as a keyboard and a mouse, and the display device is a CAD.
It has a CAD screen display section 3A for displaying an image, a message display section 3B for displaying a message, and an output display section 3C for displaying a calculation result. Also, the input device is
It has a work operation input function 3D for inputting a unit work name for calculating a work time and an operation condition.

【0019】次に図5のフローチャートを用いて上記作
業時間算出装置の作用を説明する。尚、適宜、配管合わ
せ作業を例に図4に示すモニタ画面を用いて説明する。
先ず、分析対象の作業場のCAD情報1Aが記録された
フロッピーディスクをディスクドライバに装填し、作業
が行われる場所を指定する(ステップS10)。例え
ば、「1F東南の角部」のようにキーボードから入力す
る。このように作業場が指定されると、演算部2は、デ
ータベース参照機能2Bによってデータベース部1のC
AD情報1Aを参照し、表示機能2Aによって図4に示
すCAD画面表示部4に指定された作業場の3D画像を
表示する(ステップS12)。
Next, the operation of the working time calculating device will be described with reference to the flowchart of FIG. Incidentally, the pipe alignment work will be described as an example using the monitor screen shown in FIG.
First, a floppy disk in which the CAD information 1A of the work area to be analyzed is recorded is loaded into the disk driver, and the place where the work is performed is designated (step S10). For example, input from the keyboard such as "1F Southeast corner". When the work place is designated in this way, the computing unit 2 uses the database reference function 2B to C of the database unit 1.
With reference to the AD information 1A, the display function 2A displays the 3D image of the designated workplace on the CAD screen display unit 4 shown in FIG. 4 (step S12).

【0020】次に、ユーザは作業時間を分析する作業を
単位作業に分解し、初めに行う単位作業の名称を図4に
示すモニタ画面上の単位作業名入力部5にキーボードに
よって入力する(ステップS14)。単位作業名が入力
されると、演算部2はデータベース参照機能2Bによっ
て、入力された単位作業名に該当する動作手順データ1
Bをデータベース部1から検索する(ステップS1
6)。そして、この動作手順データ1Bから単位作業を
構成する基本動作の手順を決定する。次いで単位作業に
対応するメッセージデータ1Cを検索し、単位作業を構
成する各基本動作の動作条件の入力を促すメッセージを
モニタ画面のメッセージ表示部7に表示する(ステップ
S18)。
Next, the user decomposes the work whose work time is to be analyzed into unit works, and inputs the name of the unit work to be performed first into the unit work name input section 5 on the monitor screen shown in FIG. S14). When the unit work name is input, the operation unit 2 causes the database reference function 2B to operate the operation procedure data 1 corresponding to the input unit work name.
B is searched from the database unit 1 (step S1)
6). Then, the procedure of the basic operation constituting the unit work is determined from the operation procedure data 1B. Then, the message data 1C corresponding to the unit work is searched, and a message prompting the user to input the operation condition of each basic operation constituting the unit work is displayed on the message display portion 7 of the monitor screen (step S18).

【0021】図4に示す画面で説明すると、図4に示す
画面は配管合わせの作業手順のうち既に4番目の単位作
業まで作業時間の算出がされており、次に、5番目の単
位作業としてチェーンブロック設定の作業時間を算出す
る場合の様子を示している。同図では、作業には、二人
の作業員があたり(作業員の人数は初期に設定可能)、
同図Bに示す作業員は現在配管を取り付けている所で、
同図Aに示す作業員が道工具置場のある1Fに位置して
いる。ここで同図に示すように単位作業名入力部5にチ
ェーンブロック設定と入力すると、動作手順データ1B
に対応するメッセージデータ1Cが順にメッセージ表示
部7に表示される。チェーンブロック設定という単位作
業に対しては、図(A)に示したメッセージが順に表示
される。ユーザはこのメッセージに従って、動作条件を
入力する。例えば、同図に示すように「チェーンブロッ
ク取り付け位置を決めてください」と表示された場合に
は、同図ポインタ8の位置をマウスで操作して取り付け
位置を指定する。
Explaining with the screen shown in FIG. 4, the screen shown in FIG. 4 has already calculated the working time up to the fourth unit work in the work procedure for pipe alignment, and next, as the fifth unit work. It shows how to calculate the working time for setting the chain block. In the figure, two workers are involved in the work (the number of workers can be set at the beginning),
The worker shown in Fig. B is currently installing the piping,
The worker shown in FIG. A is located on the 1st floor where the road tool yard is located. Here, if chain block setting is input to the unit work name input section 5 as shown in FIG.
The message data 1C corresponding to is sequentially displayed on the message display unit 7. For the unit work of chain block setting, the messages shown in FIG. The user inputs operating conditions according to this message. For example, as shown in the figure, when "Please determine the chain block mounting position" is displayed, the position of the pointer 8 in the figure is operated with the mouse to specify the mounting position.

【0022】このようにしてユーザは、メッセージ表示
部7に表示されるメッセージに従って、動作条件をキー
ボードやマウス等によって入力する(ステップS2
0)。上記のようにデータベース部1やユーザによって
決定された動作手順や動作条件等の単位作業の作業時間
を演算するために必要な演算条件は演算部2の入力部2
Cに記録される(ステップS22)。
In this way, the user inputs operating conditions with a keyboard, a mouse or the like according to the message displayed on the message display section 7 (step S2).
0). As described above, the calculation conditions necessary for calculating the work time of the unit work such as the operation procedure and the operation conditions determined by the database unit 1 and the user are the input unit 2 of the calculation unit 2.
It is recorded in C (step S22).

【0023】これらのユーザによる動作条件の入力作業
が終了し、作業時間の演算に必要な演算条件の設定が終
了すると、演算部2はこれらの演算条件に従って、既定
時間データ1Dを参照して作業時間を求める際に必要な
パラメータを算出し、このパラメータに適合する既定時
間を求める(ステップS24)。例えば、上記のように
チェーンブロック設定を行った場合、作業員Aが道工具
置場にチェーンブロックを取りに行く通路の歩行距離
と、チェーンブロックを道工具置場から取り付け位置ま
で運ぶ通路の歩行距離をCAD情報1Aから算出し、そ
れぞれの歩行距離での通路状況や、チェーンブロックの
重量に基づいてこれらの歩行距離を移動するのに要する
時間を既定時間データ1Dから求める。尚、図3(A)
で示した歩行の既定時間データ1Dは運搬物の重量を考
慮して作成されたものではないが、歩行速度はチェーン
ブロックの重量によらないと仮定すれば、例えば、作業
員Aが現地点から道工具置場を経由してチェーンブロッ
ク取り付け位置まで歩行する距離が25mで、通路状況
が不良であった場合、このチェーンブロックをチェーン
ブロック取り付け位置まで運搬するのに27秒要する。
同様に、チェーンブロックを取り付け位置に取り付ける
作業の時間をチェーンブロックの重量やCAD情報1A
として記録されている取り付け場所の環境条件(動作条
件)等に基づいて求める。
When the operation condition input work by these users is completed and the setting of the calculation conditions necessary for the calculation of the work time is completed, the calculation unit 2 refers to the preset time data 1D according to these calculation conditions and performs the work. A parameter required for obtaining the time is calculated, and a preset time that matches this parameter is obtained (step S24). For example, when the chain block setting is performed as described above, the walking distance of the passage in which the worker A goes to the road tool yard to get the chain block and the walking distance of the passage that carries the chain block from the road tool yard to the attachment position are set. It is calculated from the CAD information 1A, and the time required to move these walking distances is calculated from the predetermined time data 1D based on the passage condition at each walking distance and the weight of the chain block. In addition, FIG.
Although the predetermined time data 1D of the walking shown in is not created in consideration of the weight of the transported object, if it is assumed that the walking speed does not depend on the weight of the chain block, for example, the worker A is If the walking distance to the chain block mounting position via the tool storage is 25 m and the passage condition is poor, it takes 27 seconds to transport the chain block to the chain block mounting position.
Similarly, the time for attaching the chain block to the attachment position can be determined by the weight of the chain block and CAD information 1A.
It is calculated based on the environmental conditions (operating conditions) of the installation location, etc.

【0024】このようにして単位作業に要する時間を基
本動作毎に求めて、その合計を算出し、その合計を分析
結果表示部6に表示する(ステップS26)。以上、同
様にしてユーザは対象とする作業に必要な全ての単位作
業に要する作業時間を順に単位作業名入力部5に入力す
ると、全ての単位作業に関して作業時間が算出される。
これらの単位作業の作業時間の結果は分析結果表示部6
に累積的に表示されるとともに、これらの作業時間の総
和が分析結果表示部6に表示される。これによって対象
とする作業に要する総作業時間が求められる。
In this way, the time required for the unit work is obtained for each basic operation, the total is calculated, and the total is displayed on the analysis result display unit 6 (step S26). As described above, in the same manner, when the user sequentially inputs the work times required for all the unit work required for the target work to the unit work name input unit 5, the work time is calculated for all the unit work.
The results of the work time of these unit work are displayed in the analysis result display unit 6
And the total sum of these working times is displayed on the analysis result display unit 6. As a result, the total work time required for the target work is obtained.

【0025】以上により、追加工事の時期のように充分
にCADの設計がなされていれば、過去の実績のない新
規の工事内容についても作業時間が予測でき、コスト試
算などの工事計画に活用できる。尚、上記実施例におい
ては、作業時間の予測として説明したが、これは作業手
順をパラメータとしたシミュレーションをしていること
となるので、作業時間を評価の対象として最適な作業手
順を検討する装置としても応用できる。
As described above, if the CAD is sufficiently designed as in the time of additional work, the work time can be predicted even for new work contents with no past record, and it can be used for work planning such as cost estimation. . It should be noted that, in the above-mentioned embodiment, the explanation was made as the prediction of the working time, but since this is a simulation using the working procedure as a parameter, an apparatus for examining the optimal working procedure with the working time as the object of evaluation. Can also be applied as

【0026】[0026]

【発明の効果】以上説明したように、本発明に係る作業
時間算出方法によれば、CAD情報を支援情報として所
定作業の動作手順を予測するようにしたので、単品生産
で作業空間環境がその都度変化する作業の場合でも作業
時間を正確に且つ容易に予測することができる。
As described above, according to the work time calculating method of the present invention, the CAD work information is used as the support information to predict the operation procedure of the predetermined work. Even in the case of work that changes from time to time, the work time can be accurately and easily predicted.

【図面の簡単な説明】[Brief description of drawings]

【図1】図1は、本発明に係る作業時間算出方法が適用
される作業時間算出装置の一実施例を示す構成図であ
る。
FIG. 1 is a configuration diagram showing an embodiment of a work time calculation device to which a work time calculation method according to the present invention is applied.

【図2】図2は、動作手順データ及びメッセージデータ
の内容の一例を示す説明図である。
FIG. 2 is an explanatory diagram showing an example of contents of operation procedure data and message data.

【図3】図3は、既定時間データの内容の一例を示す説
明図である。
FIG. 3 is an explanatory diagram showing an example of contents of preset time data.

【図4】図4は、作業時間算出装置のモニタ画面を示す
説明図である。
FIG. 4 is an explanatory diagram showing a monitor screen of the working time calculation device.

【図5】図5は、作業時間算出装置の作用を示すフロー
チャートである。
FIG. 5 is a flowchart showing an operation of the work time calculating device.

【符号の説明】[Explanation of symbols]

1…データベース部 1A…CAD情報 1B…動作手順データ 1C…メッセージデータ 1D…既定時間データ 2A…表示機能 2B…データベース参照機能 2C…入力部 2D…演算機能 3A…CAD画面 3B…メッセージ表示部 3C…アウトプット表示部 3D…作業動作入力機能 1 ... Database part 1A ... CAD information 1B ... Operating procedure data 1C ... Message data 1D ... Default time data 2A ... Display function 2B ... Database reference function 2C ... Input part 2D ... Calculation function 3A ... CAD screen 3B ... Message display part 3C ... Output display section 3D ... Work motion input function

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 建設工事等の施行工事における所定作業
の作業時間を算出する作業時間算出方法において、 前記施行工事の単位作業の動作手順を所要時間の既知な
複数の基本動作に分解した動作手順情報と、前記単位作
業を行う作業場の作業空間情報及び作業対象物の物量情
報が収納されたCAD情報と、前記基本動作を前記作業
場の空間条件下で行った時の所要時間である既定時間情
報とをデータベースとして予め記憶し、 作業時間を算出したい所定作業の動作手順を前記CAD
情報から得られる作業場の作業空間情報及び作業対象物
の物量情報を支援情報として予測すると共に、予測した
動作手順を前記動作手順情報の基本動作に分解し、 前記分解した基本動作を前記作業場の空間条件下で行っ
た時の所要時間を前記既定時間情報に基づいて求め、 前記求めた各基本動作の所要時間を加算して前記所定作
業の作業時間を算出することを特徴とする作業時間算出
方法。
1. A work time calculating method for calculating a work time of a predetermined work in a construction work such as a construction work, in which the operation procedure of the unit work of the construction work is decomposed into a plurality of basic movements of known required time. Information, CAD information in which the work space information of the work space where the unit work is performed and the physical quantity information of the work target are stored, and predetermined time information which is the time required when the basic operation is performed under the space condition of the work space. Are stored in advance as a database, and the operation procedure of a predetermined work whose work time is to be calculated is described in the CAD
The work space information of the workplace and the physical quantity information of the work target obtained from the information are predicted as support information, and the predicted operation procedure is decomposed into the basic operation of the operation procedure information, and the decomposed basic operation is the space of the workplace. A work time calculating method characterized in that a work time required under the condition is obtained based on the predetermined time information, and the work time of the predetermined work is calculated by adding the required time of each basic motion thus obtained. .
【請求項2】 前記CAD情報から得られる作業場の作
業空間情報を三次元画面で表示することを特徴とする請
求項1の作業時間算出方法。
2. The work time calculating method according to claim 1, wherein the work space information of the work place obtained from the CAD information is displayed on a three-dimensional screen.
JP19113595A 1995-07-04 1995-07-04 Working time calculation method Pending JPH0921231A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP19113595A JPH0921231A (en) 1995-07-04 1995-07-04 Working time calculation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP19113595A JPH0921231A (en) 1995-07-04 1995-07-04 Working time calculation method

Publications (1)

Publication Number Publication Date
JPH0921231A true JPH0921231A (en) 1997-01-21

Family

ID=16269471

Family Applications (1)

Application Number Title Priority Date Filing Date
JP19113595A Pending JPH0921231A (en) 1995-07-04 1995-07-04 Working time calculation method

Country Status (1)

Country Link
JP (1) JPH0921231A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2024009537A1 (en) * 2022-07-06 2024-01-11 日本電信電話株式会社 Path planning device and path planning method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2024009537A1 (en) * 2022-07-06 2024-01-11 日本電信電話株式会社 Path planning device and path planning method

Similar Documents

Publication Publication Date Title
JP4240504B2 (en) Apparatus and method for analyzing influence of design change in product development process
US20090187384A1 (en) Method for Generating Data of Plant Construction Simulation and System Thereof
JP7330712B2 (en) Material property prediction device and material property prediction method
Choi et al. Application of virtual assembly tools for improving product design
JP2003044115A (en) Method and device for designing manufacture line, and process designing method
Mohamed et al. An integrated knowledge-based system for alternative design and materials selection and cost estimating
JP2001025805A (en) Rolling simulation device and computer readable recording medium recording rolling simulation program
JP2006259940A (en) Statistical information presentation device
JPH0921231A (en) Working time calculation method
JP2000027458A (en) Cad system for construction and method for designing building
JP2000024850A (en) Manual assembly line efficiency evaluation device
US7092854B2 (en) Computer-implemented method and system for designing a workcell layout
JPH09101947A (en) Time series forcasting method
JP3787579B2 (en) Ultrasonic flaw detection simulation system, ultrasonic flaw detection simulation system method and recording medium thereof
JP2002207002A (en) Atmospheric environment simulation system
WO2002029518A2 (en) Construction information and management system
JP2800714B2 (en) Component cost estimation method and component cost estimation device
JPH09179850A (en) Demand prediction model evaluating method
JP3814143B2 (en) Operation monitoring method, apparatus and computer-readable recording medium in blast furnace operation
JPH09212683A (en) Structure analysis system and method
JP3588484B2 (en) Work man-hour prediction support system and method for determining work man-hour prediction approximate expression used in this system
JP3229773B2 (en) Product sales volume forecasting device
JP2001081968A (en) System for selecting working method
JP2002014811A (en) Device for measuring project progress and method for the same and computer readable recording medium recorded with program for allowing computer to execute the same method
Blažević et al. Modelling regional economic development