JPH09142179A - Trolley wire prefabricating construction method and prefabricated trolley wire - Google Patents

Trolley wire prefabricating construction method and prefabricated trolley wire

Info

Publication number
JPH09142179A
JPH09142179A JP30138595A JP30138595A JPH09142179A JP H09142179 A JPH09142179 A JP H09142179A JP 30138595 A JP30138595 A JP 30138595A JP 30138595 A JP30138595 A JP 30138595A JP H09142179 A JPH09142179 A JP H09142179A
Authority
JP
Japan
Prior art keywords
wire
trolley wire
prefabricated
trolley
hanger
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP30138595A
Other languages
Japanese (ja)
Inventor
Akira Takahata
章 高畑
Akira Asano
暁 浅野
Osamu Nakamura
修 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Cable Ltd
Original Assignee
Hitachi Cable Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Cable Ltd filed Critical Hitachi Cable Ltd
Priority to JP30138595A priority Critical patent/JPH09142179A/en
Publication of JPH09142179A publication Critical patent/JPH09142179A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To integrate a catenary and a trolley wire and string them simultaneously by fitting a trolley wire with the catenary delivered according to a space between supporting poles and hangers. SOLUTION: A prefabricated trolley wire 1 is formed by engaging the upper end parts of hangers 3 with a catenary 2 delivered according to a premeasured space between supporting poles and hanging the hangers 3. A trolley wire 4 of specified length is engaged with the lower end parts of the hangers 3, and the trolley wire 4 is held almost horizontally. The trolley wire 4 has constricted parts 5, continuous in the axial direction of the wire, on both sides of upper half part, and an electric wire grip part 6 forming the lower end part of the hanger 3 is engaged with both constricted parts 5. The electric wire grip part 6 is formed being divided in two pieces along the trolley wire 4 at the top part of the trolley wire 4, and these two pieces are fastened to each other by a screw 7 or the like and grip both constricted parts 5.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、複数の鉄塔等の支
持柱間に吊具線を架設すると共に吊具線にトロリー線を
ハンガを介して吊り下げて架設するトロリー線並びにそ
の架設方法に係り、特に、鉄塔間隔に長さを合わせて終
端処理した吊具線とトロリー線とを一体化して同時に架
設するトロリー線のプレハブ工法並びにプレハブトロリ
ー線に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a trolley wire and a method of installing the suspension wire between the supporting columns such as a plurality of steel towers and suspending the trolley wire from the suspension wire via a hanger. More particularly, the present invention relates to a prefabricated construction method of a trolley wire and a prefabricated trolley wire in which a suspension wire and a trolley wire whose length is adjusted to the interval between steel towers and a terminating wire are integrated and simultaneously installed.

【0002】[0002]

【従来の技術】一般に、トロリー線は、複数の鉄塔等の
支持柱間に掛け渡された吊具線に、多数のハンガを吊り
下げ、このハンガにトロリー線を吊り下げ支持させて架
設される。従来、トロリー線を架設する際には、まず吊
具線及びトロリー線を別個に延線、緊線し、これらが所
定の配置に置かれてから、ハンガを装着する方法が採ら
れている。図4には、従来の方法によるトロリー線架設
状況が示されている。
2. Description of the Related Art Generally, a trolley wire is constructed by suspending a large number of hangers on a suspending wire that is hung between a plurality of supporting columns such as steel towers, and suspending and supporting the trolley wires on the hangers. . Conventionally, when constructing a trolley wire, a method has been adopted in which a hanger wire and a trolley wire are first extended and tightened separately, then these are placed in a predetermined arrangement, and then a hanger is attached. FIG. 4 shows a trolley wire installation situation according to a conventional method.

【0003】図4に示されるように、トロリー線40が
架設される線路に沿って多数の鉄塔(図は省略されてい
る)が配列して設けられ、これに沿ってレール41が布
設されている。レールの上方には、作業用保護接地線4
2が前もって配置されている。レール41上には、吊具
線ドラム43を備えたドラム台車44とトロリー線ドラ
ム45を備えたドラム台車46とが、進行方向に並べて
設けられている。ドラム台車44、46は、レール41
上を前進しながらドラムを回転させて吊具線47或い
は、トロリー線40を所定の張力で送り出すことができ
る。これらのドラム台車44、46の後方レール41上
には、2台の作業台48が設けられている。作業台48
は、車輪を有し、レール41上を移動できる。作業台4
8は、所定の高さの足場を有し、ハンガ取り付け作業に
利用される。前方に配置される作業台48は、仮ハンガ
49取り付け用であり、後方に配置される作業台は、ハ
ンガ50取り付け用である。前方に位置するドラム台車
44から繰り出された吊具線47は、各鉄塔毎に固定さ
れた支持物51間に掛け渡される。このドラム台車44
の後方をドラム台車46が移動し、ドラム台車46から
繰り出されたトロリー線40は、一旦、仮ハンガ49を
介して吊具線47に吊り下げられる。このようにして延
線された吊具線47及びトロリー線40は凹凸に曲がっ
ているので、それぞれ張力を加えて直線状態に矯正し、
規定の位置に張り上げる。この後、トロリー線40の長
さを測定し、この長さをもとにハンガ50の装着間隔を
定めて、仮ハンガ49に代えてハンガ50が取り付けら
れる。
As shown in FIG. 4, a large number of steel towers (not shown) are arranged in an array along the line on which the trolley wire 40 is installed, along which rails 41 are laid. There is. Above the rail, work protective ground wire 4
2 is placed in advance. On the rail 41, a drum carriage 44 having a hanging wire drum 43 and a drum carriage 46 having a trolley wire drum 45 are provided side by side in the traveling direction. The drum carriages 44 and 46 are provided on the rail 41.
The lifting wire 47 or the trolley wire 40 can be sent out with a predetermined tension by rotating the drum while moving forward. Two work platforms 48 are provided on the rear rails 41 of the drum carriages 44 and 46. Work table 48
Has wheels and can move on the rail 41. Workbench 4
8 has a scaffold of a predetermined height and is used for hanger attachment work. The workbench 48 arranged in the front is for mounting the temporary hanger 49, and the workbench arranged in the rear is for mounting the hanger 50. The suspension wire 47 extended from the drum carriage 44 located in the front is bridged between the supports 51 fixed for each steel tower. This drum truck 44
The drum carriage 46 moves behind and the trolley wire 40 fed from the drum carriage 46 is temporarily hung from the suspender wire 47 via the temporary hanger 49. Since the hanging wire 47 and the trolley wire 40 extended in this way are bent in an uneven manner, tension is applied to each to straighten them,
Raise it to the specified position. After that, the length of the trolley wire 40 is measured, the mounting intervals of the hangers 50 are determined based on this length, and the hangers 50 are attached instead of the temporary hangers 49.

【0004】[0004]

【発明が解決しようとする課題】上記従来の架線工法に
あっては、以下に述べるような問題があった。
The above-mentioned conventional overhead wire construction method has the following problems.

【0005】(1)吊具線47及びトロリー線40から
なる2本の線は、それぞれ異なった作業班によって延線
が進められるが、これらの線を乗せたドラム台車44、
46が同一レール41上を前後して移動するので、作業
を同時に進行させるためには、作業速度の遅いドラム台
車に合わせて作業を進めることになり、全体の作業時間
の短縮が図れない。
(1) The two wires consisting of the hanging wire 47 and the trolley wire 40 are extended by different working groups, and the drum carriage 44 carrying these wires,
Since 46 moves back and forth on the same rail 41, in order to proceed with the work at the same time, the work is advanced in accordance with the drum carriage having the slow work speed, and the overall work time cannot be shortened.

【0006】(2)トロリー線40の繰出し量と吊具線
47の繰出し量との整合が必要であるため作業の速度を
同じにする必要があるが、両者の速度を調整することが
難しい。
(2) Since it is necessary to match the feeding amount of the trolley wire 40 and the feeding amount of the hanger wire 47, it is necessary to make the work speeds the same, but it is difficult to adjust both speeds.

【0007】(3)トロリー線40と吊具線47とが規
定の位置に張り上げられてからでないとハンガ50の装
着ができないため作業時間の短縮が困難である。
(3) It is difficult to reduce the working time because the hanger 50 cannot be mounted until the trolley wire 40 and the hanger wire 47 have been pulled up to the prescribed positions.

【0008】(4)ドラム台車が2台、作業台が2台あ
り、それぞれに作業に関わる作業員を配置しなければな
らず、全体では多くの作業員を必要とする。
(4) There are two drum carriages and two worktables, each of which must have a worker involved in the work, which requires a large number of workers as a whole.

【0009】(5)ハンガ50の装着間隔が現地にてト
ロリー線40の長さを測定してから設定されるため、ハ
ンガ装着のための作業時間が長くなる。
(5) Since the mounting interval of the hangers 50 is set after measuring the length of the trolley wire 40 on site, the working time for mounting the hangers becomes long.

【0010】(6)吊具線47及びトロリー線40から
なる2本の線の延線後に、これら2本の線に張力を加え
て凹凸に曲がっていたものを直線状態に矯正するが、こ
の作業は2本の線に個別に施されるので、作業時間がか
かる。
(6) After the two wires consisting of the hanging wire 47 and the trolley wire 40 have been extended, tension is applied to these two wires to straighten the uneven shape. Since the work is performed on the two lines individually, it takes time.

【0011】トロリー線架設の効率を向上するために
は、以上のような問題点を解決しなけらばならない。本
出願人は、予め支持柱間の間隔を計測し、この長さに合
わせたプレハブトロリー線(トロリー線、吊具線及びハ
ンガをほとんど完成状態に組み上げたもの)を使用する
ことにより、一気に架線できないものかと考えた。そう
すれば、作業時間が大幅に短縮され、作業人数も低減で
きることになる。
In order to improve the efficiency of the trolley wire installation, the above problems must be solved. The applicant measured the distance between the supporting columns in advance and used a prefabricated trolley wire (a trolley wire, a hanger wire, and a hanger that were assembled to a nearly completed state) to match the length, and the overhead wire was stretched at once. I thought it was impossible. By doing so, the working time can be significantly shortened and the number of workers can be reduced.

【0012】そこで、本発明の目的は、上記課題を解決
し、鉄塔間隔に長さを合わせて終端処理した吊具線とト
ロリー線とを一体化して同時に架設するトロリー線のプ
レハブ工法並びにプレハブトロリー線を提供することに
ある。
[0012] Therefore, an object of the present invention is to solve the above-mentioned problems, and to construct a prefabricated trolley wire and a prefabricated trolley in which a suspension wire and a trolley wire whose lengths are adjusted to the distance between steel towers and a trolley wire are integrally installed at the same time. To provide the line.

【0013】[0013]

【課題を解決するための手段】上記目的を達成するため
に本発明は、トロリー線に支持柱の間隔に応じて切り出
された吊具線とハンガとを取り付けたプレハブトロリー
線を形成し、このプレハブトロリー線を架設するように
したものである。
In order to achieve the above object, the present invention forms a prefabricated trolley wire having a hanger wire and a hanger attached to the trolley wire, which are cut out in accordance with the distance between the supporting columns. A prefabricated trolley wire was installed.

【0014】上記構成により、プレハブトロリー線は、
トロリー線に支持柱の間隔に応じて切り出された吊具線
とハンガとを取り付けて構成されているので、このプレ
ハブトロリー線を支持柱間に掛け渡すことにより、直ち
に架線が完了する。
With the above structure, the prefabricated trolley wire is
Since the suspension wire and the hanger that are cut out in accordance with the intervals of the support columns are attached to the trolley wire, the prefabricated trolley wire is hung between the support pillars to complete the overhead wire immediately.

【0015】[0015]

【発明の実施の形態】以下本発明の実施の形態を添付図
面に基づいて詳述する。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described in detail below with reference to the accompanying drawings.

【0016】まず、図2に本発明に係るプレハブトロリ
ー線を示す。図2(a)は、プレハブトロリー線の部分
側面図である。プレハブトロリー線1は、予め計測され
た支持柱間の間隔に応じて切り出された吊具線2に、ハ
ンガ3の上端部が係合され、ハンガ3が垂下させて設け
られている。ハンガ3の下端部には所定の長さのトロリ
ー線4が係合され、トロリー線4は略水平に保持されて
いる。図示されないが吊具線2の両端部には、吊具線2
を支持柱に取り付けるための引留金具が取り付けられて
いる。また、吊具線2は、各支持柱間の間隔に応じて切
り出されたものが、トロリー線4に沿ってその順番通り
配置されている。ハンガ3は、1個のみ図示されている
が、プレハブトロリー線1に沿って、間隔を隔てて多数
設けられている。個々のハンガ3の長さ及び各ハンガ3
の設置間隔は、架線完了時を想定して決定されている。
従って、吊具線2とトロリー線4との間隔は、吊具線2
がその両端部で山なりになるように徐々に変化してい
る。図3に架線完了時のプレハブトロリー線1を示す。
First, FIG. 2 shows a prefabricated trolley wire according to the present invention. FIG. 2A is a partial side view of the prefabricated trolley wire. The prefabricated trolley wire 1 is provided in such a manner that the upper end portion of the hanger 3 is engaged with the hanger wire 2 cut out according to the distance between the support columns measured in advance, and the hanger 3 hangs down. A trolley wire 4 having a predetermined length is engaged with the lower end of the hanger 3, and the trolley wire 4 is held substantially horizontally. Although not shown in the drawing, the lifting tool wire 2 is provided at both ends of the lifting tool wire 2.
Is attached to the support column. In addition, the hanging wire 2 cut out according to the intervals between the support columns is arranged along the trolley wire 4 in that order. Although only one hanger 3 is shown, many hangers 3 are provided at intervals along the prefabricated trolley wire 1. Length of individual hanger 3 and each hanger 3
The installation interval is determined by assuming the completion of the overhead line.
Therefore, the distance between the hanging wire 2 and the trolley wire 4 is
Is gradually changing so that it becomes mountainous at both ends. FIG. 3 shows the prefabricated trolley wire 1 when the overhead wire is completed.

【0017】図2(b)は、プレハブトロリー線1の横
断面図である。図示されるようにトロリー線4は、上半
部両側に線軸方向に連続するくびれ5を有しており、ハ
ンガ3の下端部を形成する電線把持部6が両くびれ5に
係合されている。電線把持部6は、トロリー線4の頂部
でトロリー線4に沿って2片に分割形成され、2片はネ
ジ7等により互いに締結されると共に両くびれ5を把持
している。ハンガ3の上端部は、吊具線2に巻き付けら
れている。
FIG. 2B is a cross sectional view of the prefabricated trolley wire 1. As shown in the figure, the trolley wire 4 has constrictions 5 continuous in the axial direction on both sides of the upper half, and the wire gripping portions 6 forming the lower end of the hanger 3 are engaged with both constrictions 5. . The electric wire gripping portion 6 is divided into two pieces along the trolley wire 4 at the top of the trolley wire 4, and the two pieces are fastened to each other by screws 7 or the like and grip both constrictions 5. The upper end of the hanger 3 is wrapped around the hanging wire 2.

【0018】プレハブトロリー線1は、工場等で図2の
ように組み立てられた後、ドラムに巻き込まれる。この
時、ハンガ3がドラムの胴部に沿うようにして巻き付け
られる。また、周回して重なるプレハブトロリー線1の
間には、引留金具やハンガ3の絡み付きを防止するため
の帯状のスペーサが挿入されて、プレハブトロリー線1
と共にドラムに巻き込まれる。なお、このプレハブトロ
リー線1の組み立て時には、予めトロリー線4に所定の
時間、張力負荷を加えたものを使用してもよい。これ
は、架設後のクリープによる伸び量を前もって除去する
ために行う処理であって、例えば、2000Kgの負荷
を30分加えた後、トロリー線4と吊具線2とを並べて
ハンガ3を取り付ける。
The prefabricated trolley wire 1 is assembled in a factory or the like as shown in FIG. 2 and then wound on a drum. At this time, the hanger 3 is wound along the drum body. In addition, a strip-shaped spacer for preventing the entanglement of the anchor fittings and the hanger 3 is inserted between the prefabricated trolley wires 1 that are wound around and overlap each other.
Along with that, he is caught in a drum. When the prefabricated trolley wire 1 is assembled, the trolley wire 4 to which a tension load is applied for a predetermined time may be used. This is a process performed in advance to remove the amount of elongation due to creep after erection. For example, after applying a load of 2000 kg for 30 minutes, the trolley wire 4 and the hanger wire 2 are arranged side by side and the hanger 3 is attached.

【0019】次に、プレハブトロリー線1を用いた架線
工法について説明する。図1に示されるように、トロリ
ー線が架設される線路に沿って多数の鉄塔等の支持柱
(図は省略されている)が配列して設けられ、これに沿
ってレール10が布設されている。レール10の上方に
は、作業用保護接地線11が前もって配置されている。
プレハブトロリー線1は、ドラム12に巻き付けられて
いる。ドラム12はレール10上を移動する移動台車1
3に載置され、胴部を横倒しにして軸承されている。移
動台車13には、プレハブトロリー線1を所望の張力且
つ所望の量だけ送り出すための送出調整装置14と、プ
レハブトロリー線1の送出に伴いドラム12より排出さ
れるスペーサ15を回収するためのスペーサ回収ドラム
16とが設けられている。また、移動台車13には、後
述するワイヤを巻き取るためのワイヤ巻取装置17が設
けられている。
Next, an overhead wire construction method using the prefabricated trolley wire 1 will be described. As shown in FIG. 1, a large number of supporting columns (not shown) such as steel towers are arranged along a line on which a trolley wire is installed, and rails 10 are laid along the supporting columns. There is. Above the rail 10, a working protective ground wire 11 is arranged in advance.
The prefabricated trolley wire 1 is wound around a drum 12. The drum 12 is a moving carriage 1 that moves on the rail 10.
It is mounted on No. 3 and is supported with the trunk lying down. The movable carriage 13 has a feed adjusting device 14 for feeding the prefabricated trolley wire 1 by a desired tension and a desired amount, and a spacer for collecting the spacer 15 discharged from the drum 12 when the prefabricated trolley wire 1 is fed. A collection drum 16 is provided. Further, the movable carriage 13 is provided with a wire winding device 17 for winding a wire, which will be described later.

【0020】作業台車18は、高い場所での作業をする
ためのもので、所定の高さの足場を有し、レール10上
に移動台車13の後方に位置され、移動台車13の移動
に追従して移動できる。プレハブトロリー線1を支持す
るための支持物19は、各支持柱に一体的に取り付けら
れている。架設が進められている支持物19間には、前
方の支持物19にセミ金車連20が取り付けられ、後方
の支持物19に近付くように吊具線把持金具21が設け
られている。ワイヤ巻取装置17と吊具線把持金具21
との間には、セミ金車連20を介してワイヤ22が張設
されている。
The work carriage 18 is for working in a high place, has a scaffold of a predetermined height, is located behind the moving carriage 13 on the rail 10, and follows the movement of the moving carriage 13. Then you can move. A support 19 for supporting the prefabricated trolley wire 1 is integrally attached to each support column. Between the supports 19 that are being installed, the semi-car train 20 is attached to the front support 19 and the hanging wire gripping metal fitting 21 is provided so as to approach the rear support 19. Wire winding device 17 and lifting wire gripping metal fitting 21
A wire 22 is stretched between and via a semi-car train 20.

【0021】図1において、プレハブトロリー線1の区
間1aは、既に延線が終了しており、区間1aの吊具線
2はその前方側端部の引留金具が吊具線把持金具21に
取り付けられている。プレハブトロリー線1の区間1b
は、現在延線されている。区間1bの吊具線2は、その
後方側端部の引留金具が支持物19に取り付けられてい
る。ドラム12に巻き付けられているプレハブトロリー
線1は、ドラム12が回転することにより送出調整装置
14に送出され、同時にスペーサ15がスペーサ回収ド
ラム16に巻き取られて回収される。送出調整装置14
にて、吊具線2が上になるようにプレハブトロリー線1
が起立される。このようにして、プレハブトロリー線1
は、支持物19と送出調整装置14とのあいだに所定の
張力で掛け渡されて延線される。
In FIG. 1, the section 1a of the prefabricated trolley wire 1 has already been extended, and the lifting wire 2 of the section 1a is attached to the lifting wire gripping metal fitting 21 at the front end of the lifting wire 2. Has been. Prefabricated trolley line 1 section 1b
Is currently being extended. In the lifting wire 2 of the section 1b, the retracting metal fitting at the rear end thereof is attached to the support 19. The prefabricated trolley wire 1 wound around the drum 12 is fed to the feed adjusting device 14 by the rotation of the drum 12, and at the same time, the spacer 15 is wound around the spacer collecting drum 16 and collected. Delivery adjusting device 14
At the end, the prefabricated trolley wire 1 with the lifting wire 2 facing up
Is erected. In this way, the prefabricated trolley wire 1
Is stretched over a line between the support 19 and the delivery adjusting device 14 with a predetermined tension.

【0022】一方、ワイヤ巻取装置17はワイヤ22を
巻き取り、ワイヤ22に張力を与える。ワイヤ22は、
支持物19に取り付けらたセミ金車連20を介して略水
平方向に張力の方向が変えられ、吊具線把持金具21を
前方に引き付ける。従って、吊具線把持金具21は、支
持物19に向かって上昇し、吊具線把持金具21にその
前方端部の引留金具を取り付けられた区間1aのプレハ
ブトロリー線1は、張力を増して所定の位置まで張り上
げられる。張り上げが完了したらプレハブトロリー線1
は、引留金具を支持物19に掛け止められて区間1aに
固定される。このようにして区間1aでの緊線が達成さ
れる。
On the other hand, the wire winding device 17 winds the wire 22 and applies tension to the wire 22. Wire 22
The direction of tension is changed in a substantially horizontal direction via the semi-metal wheel train 20 attached to the support 19, and the hanging wire gripping metal fitting 21 is pulled forward. Therefore, the lifting wire gripping metal fitting 21 rises toward the support 19, and the prefabricated trolley wire 1 in the section 1a in which the retracting metal fitting at the front end of the lifting wire gripping metal fitting 21 is attached increases tension. It is pulled up to a predetermined position. Pre-fabricated trolley wire 1 when tension is completed
Is fixed to the section 1a by hooking the detention metal fitting to the support 19. In this way, the tight line in the section 1a is achieved.

【0023】区間1aの緊線が完了すると、ワイヤ巻取
装置17は、区間1bの一つ前方の区間の支持物19に
取り付けられ、同時にワイヤ22が繰り出される。ワイ
ヤ22の先端の吊具線把持金具21は、区間1bの前方
側端部の引留金具に取り付けられる。そして移動台車1
3が前方に移動し、次の区間の延線が開始されると共
に、区間1bの緊線が開始される。このようにして、移
動台車13及び、作業台車18を移動させながら、順次
各支持柱間にプレハブトロリー線1が架設される。
When the tensioning of the section 1a is completed, the wire winding device 17 is attached to the support 19 in the section one front of the section 1b, and the wire 22 is unwound at the same time. The lifting wire gripping metal fitting 21 at the tip of the wire 22 is attached to the retracting metal fitting at the front end of the section 1b. And mobile trolley 1
3 moves forward, the extension of the next section is started, and the tight line of section 1b is started. In this manner, the prefabricated trolley wire 1 is sequentially installed between the support columns while moving the movable carriage 13 and the work carriage 18.

【0024】[0024]

【発明の効果】本発明は次の如き優れた効果を発揮す
る。
The present invention exhibits the following excellent effects.

【0025】(1)延線後に行う緊線の作業が1回でよ
いので、作業時間が短縮される。
(1) Since the work of tightening the wire after the drawing is performed only once, the work time is shortened.

【0026】(2)作業に必要な人員が少なくてよいの
で、人件費が減少する。
(2) Since the number of workers required for the work is small, the labor cost is reduced.

【0027】(3)予めプレハブトロリー線を組み立て
るようにしたので、計画に従った架線工事が可能にな
り、作業の誤りが減少できる。
(3) Since the prefabricated trolley wire is assembled in advance, it is possible to carry out the overhead line work according to the plan and reduce the error in the work.

【0028】(4)クリープの除去を前もって実施でき
るので、架設の際にクリープの除去を行う必要がなく、
そのぶん架設作業時間が短縮できる。
(4) Since it is possible to remove the creep in advance, it is not necessary to remove the creep during the installation.
Therefore, the erection work time can be shortened.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施の形態を示す架線工法の説明図で
ある。
FIG. 1 is an explanatory view of an overhead wire construction method showing an embodiment of the present invention.

【図2】本発明の実施の形態を示すプレハブトロリー線
の部分側面図及び断面図である。
FIG. 2 is a partial side view and a sectional view of a prefabricated trolley wire showing an embodiment of the present invention.

【図3】本発明の実施の形態を示すプレハブトロリー線
の架設仕上がり外観を示す側面図である。
FIG. 3 is a side view showing an appearance of a prefabricated trolley wire installed according to an embodiment of the present invention.

【図4】従来例を示す架線工法の説明図である。FIG. 4 is an explanatory view of an overhead wire construction method showing a conventional example.

【符号の説明】[Explanation of symbols]

1 プレハブトロリー線 2 吊具線 3 ハンガ 4 トロリー線 13 移動台車 1 Prefabricated trolley wire 2 Lifting equipment wire 3 Hanger 4 Trolley wire 13 Mobile trolley

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 複数の鉄塔等の支持柱間に吊具線を架設
すると共に該吊具線にトロリー線をハンガを介して吊り
下げて架設するに際して、トロリー線に支持柱の間隔に
応じて切り出された吊具線とハンガとを取り付けたプレ
ハブトロリー線を形成し、該プレハブトロリー線を架設
するようにしたことを特徴とするトロリー線のプレハブ
工法。
1. A suspension wire is erected between a plurality of support columns such as steel towers, and when a trolley wire is suspended from the suspension wire via a hanger, the suspension wire is hung depending on the distance between the support columns. A prefabricated construction method of a trolley wire, characterized in that a prefabricated trolley wire is formed by attaching the cut out hanging wire and a hanger, and the prefabricated trolley wire is installed.
【請求項2】 鉄塔等の支持柱間に架設された吊具線に
ハンガを介して吊り下げて架設されるトロリー線におい
て、トロリー線と、予め計測された支持柱間の間隔に応
じて切り出された吊具線と、上記トロリー線と上記吊具
線とを連結するハンガとから構成されることを特徴とす
るプレハブトロリー線。
2. A trolley wire suspended by a hanger from a supporting pole such as a steel tower via a hanger and cut out in accordance with the distance between the trolley wire and the support pole measured in advance. A prefabricated trolley wire comprising: a hanging wire and a hanger that connects the trolley wire and the hanging wire.
JP30138595A 1995-11-20 1995-11-20 Trolley wire prefabricating construction method and prefabricated trolley wire Pending JPH09142179A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP30138595A JPH09142179A (en) 1995-11-20 1995-11-20 Trolley wire prefabricating construction method and prefabricated trolley wire

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP30138595A JPH09142179A (en) 1995-11-20 1995-11-20 Trolley wire prefabricating construction method and prefabricated trolley wire

Publications (1)

Publication Number Publication Date
JPH09142179A true JPH09142179A (en) 1997-06-03

Family

ID=17896240

Family Applications (1)

Application Number Title Priority Date Filing Date
JP30138595A Pending JPH09142179A (en) 1995-11-20 1995-11-20 Trolley wire prefabricating construction method and prefabricated trolley wire

Country Status (1)

Country Link
JP (1) JPH09142179A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107962982A (en) * 2017-12-05 2018-04-27 西南交通大学 A kind of three-phase traction electric power system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107962982A (en) * 2017-12-05 2018-04-27 西南交通大学 A kind of three-phase traction electric power system
CN107962982B (en) * 2017-12-05 2023-10-13 西南交通大学 Three-phase traction power supply system and vehicle-mounted power supply system

Similar Documents

Publication Publication Date Title
JP2587684B2 (en) Construction wall construction equipment
JP2006230443A (en) Method for attaching protective net to steel tower
JP2894226B2 (en) Bridge construction method
JPH09142179A (en) Trolley wire prefabricating construction method and prefabricated trolley wire
JP2768280B2 (en) Bridge construction method
CN107524285A (en) A kind of external wall construction suspension bracket and its installation method
JPH11131791A (en) Working frame for overhead pipe laying
CN217840808U (en) High-altitude construction platform
CN216388563U (en) Pole climbing-free pole hanging distribution line pole number plate device
CN217437364U (en) Pay-off rack
CN220704330U (en) Cable body lifting device for steel strand inhaul cable construction
US1972049A (en) Method for the erection of aerial transmission lines
JP3082880B2 (en) Method and apparatus for supplying shaft segment
CN220058762U (en) Hanging basket fixing device for steel structure beam
JPH0226442B2 (en)
CN215482363U (en) Become width of cloth formula catwalk suitable for construction of single-column tower space cable suspension bridge
JP2002220921A (en) Transfer scaffold for constructing roof
SU1447973A1 (en) Method of mounting support blocks with tubular standpipes of stationary offshore platform
JPH0596805U (en) Pillar device for extra length of optical fiber cable
JPH043530Y2 (en)
JP2000102124A (en) Wire installation method with hanging metal sheaves
JPH079558Y2 (en) Overhead wire retention device
JPS6321135Y2 (en)
JPH0635616Y2 (en) Overhead line temporary support device
CN111395772A (en) Cable net installation method of bidirectional single-layer orthogonal cable net structure