JPH089955B2 - Vertical double shield tunnel segment lining structure and its construction method - Google Patents

Vertical double shield tunnel segment lining structure and its construction method

Info

Publication number
JPH089955B2
JPH089955B2 JP1271649A JP27164989A JPH089955B2 JP H089955 B2 JPH089955 B2 JP H089955B2 JP 1271649 A JP1271649 A JP 1271649A JP 27164989 A JP27164989 A JP 27164989A JP H089955 B2 JPH089955 B2 JP H089955B2
Authority
JP
Japan
Prior art keywords
segment
joining
tunnel
floor slab
ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP1271649A
Other languages
Japanese (ja)
Other versions
JPH03137396A (en
Inventor
▲しょう▼ 田代
文男 天野
征彦 山本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP1271649A priority Critical patent/JPH089955B2/en
Publication of JPH03137396A publication Critical patent/JPH03137396A/en
Publication of JPH089955B2 publication Critical patent/JPH089955B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、鉄道用トンネルや道路用トンネル等とし
て用いられる縦型2連シールドトンネルのセグメント覆
工構造およびその施工法に関するものである。
Description: TECHNICAL FIELD The present invention relates to a segment lining structure of a vertical double shield tunnel used as a railway tunnel, a road tunnel and the like, and a construction method thereof.

〔従来の技術〕[Conventional technology]

シールド工法により鉄道トンネルや道路トンネル等の
トンネルを掘進する場合、複線区間の施工法として、2
本の単線トンネルを横方向に独立して並べて掘進する方
式、あるいは1本の大断面の円形トンネルを掘進する方
式が採用されている。
When excavating tunnels such as railway tunnels and road tunnels by the shield method, there are two
A method of arranging and arranging two single-line tunnels independently in the lateral direction, or a method of digging one circular tunnel having a large cross section is adopted.

前者の方式の場合は、単線トンネルを2本横方向に並
設すると、トンネル上部の用地専有幅が広くなるので、
道路下のみでのトンネル施工が不可能になり、道路以外
の用地買収が必要になるという問題が発生する。また後
者の方式の場合は、前者の方式程、トンネル上部の用地
幅を必要としないが、トンネル断面が著しく大きくなっ
て、トンネル断面内の上部および下部にデッドスペース
が生じ、そのデッドスペースの部分をコンクリートで埋
め戻すことになるので不経済である。
In the case of the former method, if two single-line tunnels are installed side by side, the land occupation width at the top of the tunnel will become wider,
There is a problem that tunnel construction only under the road becomes impossible and land acquisition other than road is required. In the case of the latter method, the land width above the tunnel is not required as much as the former method, but the tunnel cross section becomes significantly large, and dead spaces occur at the upper and lower parts of the tunnel cross section. Is uneconomical because it will be backfilled with concrete.

最近、これらの問題点を解決できる複線用トンネルの
施工法として、横方向に並べて設けられる2本の単線ト
ンネルの断面の一部を重ね合わせた断面形状のシールド
トンネルが提案され実施されている。
Recently, as a method of constructing a double-track tunnel that can solve these problems, a shield tunnel having a cross-sectional shape in which a part of the cross-sections of two single-track tunnels arranged side by side in the lateral direction are overlapped is proposed and implemented.

しかしながら、横方向に並ぶ2本の単線トンネルの断
面の一部を重ね合わせた断面形状のシールドトンネルの
場合は、2本の単線トンネルを分離して横方向に並べて
設置する場合に比べて、用地幅が僅かに小さくなるだけ
であって、トンネル上部の用地専有幅はあまり小さくな
らない。したがって、道路の幅員の狭い道路下に左右複
合型のシールドトンネルを建設することは無理である。
However, in the case of a shield tunnel having a cross-sectional shape in which the cross-sections of two single-line tunnels lined up in the horizontal direction are overlapped, compared to the case where two single-line tunnels are separated and installed side by side, Only the width is slightly reduced, and the land occupation width above the tunnel is not reduced so much. Therefore, it is not possible to construct a combined left and right shield tunnel under a narrow road.

そこで、前述の問題点を解消できる上下複合型のシー
ルドトンネルとして、特開昭60−141993号公報により公
表されているように、数箇のセグメントピースの連結体
からなる上部切欠円形の下部トンネル本体の上端部と、
数箇のセグメントピースの連結体からなる下部切欠円形
の上部トンネル本体の下単部とを、それらの間に水平仕
切りセグメントを介在させて結合した上下複合型のシー
ルドトンネルが知られている。
Therefore, as a shield tunnel of an upper and lower composite type capable of solving the above-mentioned problems, as disclosed in Japanese Patent Laid-Open No. 60-141993, an upper notched circular lower tunnel body composed of a connecting body of several segment pieces. The upper end of
2. Description of the Related Art There is known a combined upper and lower shield tunnel in which a lower cutout circular upper tunnel body consisting of a connected body of several segment pieces and a lower single part of the upper tunnel body are joined with a horizontal partition segment interposed therebetween.

また特開昭64−33398号公報により公表されているよ
うに、数箇のセグメントピースの連結体からなる上部切
欠円形の下部トンネル用セグメント連結体と、数箇のセ
グメントピースの連結体からなる下部切欠円形の上部ト
ンネル用セグメント連結体とが、上下方向に間隔をおい
て配置され、各セグメント連結体の両端部が、上部長翼
版および下部短翼版付きの接合用セグメントと、下部長
翼版および上部短翼版付きの接合用セグメントを介して
結合されて、上下複合型のセグメントリングが構成さ
れ、前記上部長翼版および下部短翼版付きの接合用セグ
メントと、前記下部長翼版および上部短翼版付きの接合
用セグメントとがトンネル長手方向に交互に配置され、
左右の接合用セグメントにわたって、梁材または床版等
の支持部材が架設固定されている上下複合型のシールド
トンネルも知られている。
Further, as disclosed in Japanese Patent Laid-Open No. 64-33398, an upper cut-out circular segment connecting body for a lower tunnel composed of a connecting body of several segment pieces and a lower connecting body composed of a connecting body of several segment pieces. A notched circular segment connecting body for the upper tunnel is arranged at intervals in the vertical direction, and both end portions of each segment connecting body have a joining segment with an upper long blade version and a lower short blade version, and a lower long blade. The upper and lower wing plates and the joining segment with the lower long wing plate and the lower long wing plate are joined together through a joining segment with the plate and the upper short wing plate to form an upper and lower composite segment ring. And the joining segment with the upper short blade version are alternately arranged in the tunnel longitudinal direction,
There is also known an upper and lower combined type shield tunnel in which a supporting member such as a beam or a floor slab is erected and fixed over the left and right joining segments.

〔発明が解決しようとする課題〕[Problems to be Solved by the Invention]

前記従来の各上下複合型のシールドトンネルの場合
は、セグメントの組立順序として、最初に下部トンネル
用セメント,次いで接合用セグメント,続いて梁または
水平仕切セグメント,次に上部トンネル用セグメントの
順に組立てるため、トンネル断面が大きくなる程、セグ
メントリングの組立に多大な時間を要するので、施工能
率が低下し、かつセグメントの分割数が増加するので、
セグメントリングのピース間継手およびリング間継手の
箇所が増加し、そのため最初に組立てられたセグメント
ピースから組立が進行するにしたがって組立誤差が順次
累積されて行き、最終的には、キーセグメントの挿入が
困難になることがある。また下部トンネル用セグメント
と上部トンネル用セグメントの組立が、トンネル長手方
向の同一位置において行なわれるので、下部トンネル用
セグメントの組立作業時に、上部トンネルから器物が落
下してくる恐れがあり危険である。
In the case of the conventional shield tunnels of upper and lower combined type, the segments are assembled in the following order: cement for the lower tunnel, then segment for joining, then beam or horizontal partition segment, and then segment for upper tunnel. Since the larger the tunnel cross section, the more time it takes to assemble the segment ring, the construction efficiency will decrease and the number of segment divisions will increase.
The number of segment ring-to-piece joints and the number of ring-to-ring joints increase, so that as the assembly progresses from the first assembled segment piece, the assembly error gradually accumulates, and finally the insertion of the key segment is It can be difficult. Further, since the lower tunnel segment and the upper tunnel segment are assembled at the same position in the longitudinal direction of the tunnel, there is a risk that a container may drop from the upper tunnel during the assembling work of the lower tunnel segment.

この発明は、下部切欠円形の上部セグメントリングお
よび上部切欠円形の下部セグメントリングを組立てる際
に、左右方向の一方に位置する上部腕付き接合用セグメ
ントと、左右方向の他方に位置する下部腕付き接合用セ
グメントと、それらの接合用セグメントの間に配置され
る中間床版セグメントとの組立てを先行して行なうこと
により、下部切欠円形の上部セグメントリングおよび上
部切欠円形の下部セグメントリングの組立てを並行して
安全に行なうことができると共に、組立作業時間を短縮
することができ、しかも高精度の縦型2連シールドトン
ネルのセグメント覆工を容易に組立てることができる縦
型2連シールドトンネルセグメント覆工構造およびその
施工法を提供することを目的とするものである。
The present invention, when assembling a lower notched circular upper segment ring and an upper notched circular lower segment ring, joins an upper arm joint segment located in one of the left and right directions and a lower arm joint segment located in the other of the left and right directions. The assembly of the lower cut-out circular upper segment ring and the upper cut-out circular lower segment ring is performed in parallel by precedingly assembling the work segment and the intermediate floor slab segment arranged between the joining segments. Vertical shield tunnel segment lining structure that can be assembled safely and safely, can shorten the assembly work time, and can easily assemble the high-precision vertical double shield tunnel segment lining. And its construction method.

〔課題を解決するための手段〕[Means for solving the problem]

前記目的を達成するために、この発明の縦型2連シー
ルドトンネルのセグメント覆工の施工法においては。上
部腕付き接合用セグメント6および下部腕付き接合用セ
グメント7を左右方向に間隔をおいて配置し、かつ中間
床版セグメント8の両端部を各接合用セグメント6,7に
結合し、次に各接合用セグメント6,7の下端部に、キー
セグメント5を含む上部切欠円形の下部セグメントリン
グ1を組立連結し、かつ各接合用セグメント6,7の上端
部に、キーセグメント5を含む下部切欠円形の上部セグ
メントリング2を組立連結し、トンネル長手方向に隣り
合う一方の接合用セグメントに固定されている複数の位
置決め用ピン10を他方の接合用セグメントに設けられた
複数のピン孔20に挿入する。
In order to achieve the above object, in the construction method of the segment lining of the vertical double shield tunnel of the present invention. The joining segment 6 with the upper arm and the joining segment 7 with the lower arm are arranged at an interval in the left-right direction, and both ends of the intermediate floor slab segment 8 are joined to the joining segments 6 and 7, respectively. An upper cutout circular lower segment ring 1 including the key segment 5 is assembled and connected to the lower ends of the joining segments 6 and 7, and a lower cutout circle including the key segment 5 is provided at the upper end of each joining segment 6 and 7. The upper segment rings 2 are assembled and connected, and the plurality of positioning pins 10 fixed to one joining segment adjacent in the tunnel longitudinal direction are inserted into the plurality of pin holes 20 provided in the other joining segment. .

またこの発明の縦型2連シールドトンネルのセグメン
ト覆工構造においては、上部腕付き接合用セグメント6
および下部腕付き接合用セグメント7が左右方向に間隔
をおいて配置され、中間床版セグメント8の両端部が各
接合用セグメント6,7に結合され、各接合用セグメント
6,7の下端部に、キーセグメント5を含む上部切欠円形
の下部セグメントリング1が組立連結され、前記各接合
用セグメント6,7の上端部に、キーセグメント5を含む
下部切欠円形の上部セグメントリング2が組立連結さ
れ、トンネル長手方向に隣り合う一方の接合セグメント
に固定されている複数の位置決め用ピン10が他方の接合
用セグメントに設けられた複数のピン孔20に挿入されて
いる。
Further, in the segment lining structure of the vertical double shield tunnel of the present invention, the joining segment 6 with the upper arm is used.
And joining segments with lower arms 7 are arranged at intervals in the left-right direction, and both ends of the intermediate floor slab segment 8 are joined to the joining segments 6 and 7, respectively.
An upper notched circular lower segment ring 1 including a key segment 5 is assembled and connected to lower ends of 6,7, and a lower notched circular upper segment including the key segment 5 is connected to upper ends of the joining segments 6,7. The rings 2 are assembled and connected, and a plurality of positioning pins 10 fixed to one joint segment adjacent in the tunnel longitudinal direction are inserted into a plurality of pin holes 20 provided in the other joint segment.

また下部セグメントリングの組立作業を安全に行なう
ために、下部セグメントリング1または上部セグメント
リング2の何れか一方の組立作業を先行して行なう。
Further, in order to safely carry out the assembly work of the lower segment ring, the assembly work of either the lower segment ring 1 or the upper segment ring 2 is carried out in advance.

さらにまた、左右の接合用セグメントと中間床版セグ
メントの端部との結合を高精度で迅速に行なうために、
上部腕付き接合用セグメント6および下部腕付き接合用
セグメント7と中間床版セグメント8とのうちの一方に
固定した垂直な連結ピン13を、他方に設けた垂直なピン
孔22に挿入する。
Furthermore, in order to quickly and accurately join the left and right joining segments and the ends of the intermediate floor slab segments,
A vertical connecting pin 13 fixed to one of the upper arm joining segment 6 and the lower arm joining segment 7 and the intermediate floor slab segment 8 is inserted into a vertical pin hole 22 provided in the other.

〔実施例〕〔Example〕

次にこの発明を図示の例によって詳細に説明する。 The present invention will now be described in detail with reference to the illustrated example.

第4図ないし第6図は第1実施例において用いられる
下部腕付き接合用セグメント7を示すものであって、コ
ンクリート製セグメント本体25の下部の外側に、そのセ
グメント本体25の幅(トンネル長手方向の幅)と同一幅
のコンクリート製下部腕26が一体に連設され、前記セグ
メント本体25の外側上端部に、下部切欠円形の上部セグ
メントリングの下端面に接合される接合面12が設けられ
ると共に、ボルト孔を有する溝形の継手金具14が埋込固
定され、前記下部腕26の下端部に、キーセグメント接合
面11が設けられると共に、溝形の継手金具14が埋込固定
され、かつセグメント本体25の内側にコンクリート製床
版支持腕27が一体に連設され、その床版支持腕27の上部
に垂直な連結ピン13の下部が埋込固定され、その連結ピ
ン13の先端側に設けられた雄ねじ部に、截頭円錐形の先
端部を有する保護キャップ47が螺合され、さらに床版支
持腕27よりも高レベルにおいて、セグメント本体25の内
側に、ボルト孔を有する溝形の継手金具28が埋込固定さ
れている。
4 to 6 show the joining segment 7 with a lower arm used in the first embodiment, in which the width of the segment body 25 (in the tunnel longitudinal direction) is provided outside the lower portion of the concrete segment body 25. Width) and a lower arm 26 made of concrete having the same width as that of the segment main body 25, and a joint surface 12 to be joined to the lower end surface of the upper segment ring of the lower cut circular shape is provided at the outer upper end portion of the segment body 25. , A groove-shaped joint fitting 14 having a bolt hole is embedded and fixed, a key segment joining surface 11 is provided at the lower end portion of the lower arm 26, and the groove-shaped joint fitting 14 is embedded and fixed, and A concrete floor slab support arm 27 is integrally provided inside the main body 25, the lower part of the vertical connecting pin 13 is embedded and fixed to the upper part of the floor slab support arm 27, and provided on the tip side of the connecting pin 13. You ’re the male A protective cap 47 having a frustoconical tip portion is screwed into the threaded portion, and at a higher level than the floor slab support arm 27, inside the segment body 25, a groove-shaped joint fitting 28 having a bolt hole is formed. Is embedded and fixed.

セグメント本体25の前部の上下両側に、前後方向に延
長すると共に先端にテーパーを有する位置決め用ピン10
の基端側部分が埋込固定され、かつセグメント本体25の
前部の上下両側および下部腕26の前部に前後方向に延長
する連結ピン9の基端側部分が埋込固定され、さらにセ
グメント本体25の下部に雌ねじ孔を有する複数の吊り具
係合金具18が埋込固定されている。また前記セグメント
本体25の後部の上下両側に、位置決め用ピン10を挿入す
るピン孔20を有するピン挿入金具29が埋込固定され、か
つセグメント本体25の後部の上下両側および下部腕26の
後部に、連結ピン9を挿入するピン孔21を有するピン挿
入金具16が埋込固定されている。
A positioning pin 10 that extends in the front-rear direction and has a tapered tip on both the upper and lower sides of the front portion of the segment body 25.
The base end portion of the connecting pin 9 extending in the front-rear direction is embedded and fixed to both upper and lower sides of the front portion of the segment body 25 and the front portion of the lower arm 26. A plurality of suspender engaging fittings 18 having female screw holes are embedded and fixed in the lower portion of the main body 25. Further, pin insertion fittings 29 having pin holes 20 for inserting the positioning pins 10 are embedded and fixed on the upper and lower sides of the rear portion of the segment body 25, and on the upper and lower sides of the rear portion of the segment body 25 and the rear portion of the lower arm 26. A pin insertion fitting 16 having a pin hole 21 into which the connecting pin 9 is inserted is embedded and fixed.

第7図ないし第9図は第1実施例において用いられる
上部腕付き接合用セグメント6を示すものであって、コ
ンクリート製セグメント本体25の上部の外側に、そのセ
グメント本体25の幅と同一幅のコンクリート製上部腕30
が一体に連設され、前記セグメント本体25の外側下端部
に、上部切欠円形の下部セグメントリングの上端面に接
合される接合面31が設けられ、かつ前記上部腕30の上端
部に、下部切欠円形の上部セグメントリングの下端面に
接合される接合面12が設けられ、さらにセグメント本体
25の上部に雌ねじ孔を有する複数の吊り具係合金具18が
埋込固定されているが、その他の構成は、前記下部腕付
き接合用セグメント7の場合と同様である。
FIG. 7 to FIG. 9 show the joining segment 6 with an upper arm used in the first embodiment, which has the same width as the width of the segment body 25 on the outer side of the upper portion of the concrete segment body 25. Concrete upper arm 30
Are integrally connected to each other, a joining surface 31 joined to an upper end surface of an upper notched circular lower segment ring is provided at an outer lower end portion of the segment body 25, and a lower notch is provided at an upper end portion of the upper arm 30. A joining surface 12 to be joined to the lower end surface of the circular upper segment ring is provided, and the segment body is further provided.
A plurality of suspender engaging fittings 18 having female screw holes are embedded and fixed in the upper part of 25, but other configurations are the same as in the case of the connecting segment 7 with the lower arm.

第10図および第11図は第1実施例において用いられる
中間床版セグメント8を示すものであって、コンクリー
ト製床版本体32の中間上部に複数の吊り具係合金具18が
埋子固定され、かつ前記床版本体32の両端部に、ボルト
孔を有する溝形の継手金具28が設けられると共に、垂直
なピン孔22が設けられている。
10 and 11 show the intermediate floor slab segment 8 used in the first embodiment, in which a plurality of hanger engaging metal fittings 18 are embedded and fixed to the intermediate upper portion of the concrete floor slab main body 32. At the both ends of the floor slab body 32, groove-shaped joint fittings 28 having bolt holes are provided, and vertical pin holes 22 are provided.

第1図ないし第3図は、第4図ないし第6図に示す下
部腕付き接合用セグメント7と、第7図ないし第9図に
示す上部腕付き接合用セグメント6と、第10図および第
11図に示す中間床版セグメント8と、円弧状セグメント
およびキーセグメントとを使用して、第1実施例の縦型
2連シールドトンネルのセグメント覆工を組立てた状態
を示すものであって、第1図に示すセグメント配置のセ
グメントリングと第2図に示すセグメント配置のセグメ
ントリングとがトンネル長手方向に交互に配置されてい
る。
FIGS. 1 to 3 show a lower arm joining segment 7 shown in FIGS. 4 to 6, an upper arm joining segment 6 shown in FIGS. 7 to 9, and FIGS.
11 shows a state in which the segment lining of the vertical double shield tunnel of the first embodiment is assembled using the intermediate floor slab segment 8 shown in FIG. 11 and the arcuate segment and the key segment. The segment rings having the segment arrangement shown in FIG. 1 and the segment rings having the segment arrangement shown in FIG. 2 are alternately arranged in the tunnel longitudinal direction.

また第12図は第1実施例におけるトンネル長手方向に
隣り合う接合用セグメント6,7の位置決め連結部を示
し、第13図は第1実施例における接合用セグメント6,7
と中間床版セグメント8との結合部を示し、第14図およ
び第15図は第1実施例におけるセグメント相互の連結部
を示している。
Further, FIG. 12 shows a positioning connecting portion of the joining segments 6 and 7 which are adjacent to each other in the tunnel longitudinal direction in the first embodiment, and FIG. 13 is a joining segment 6 and 7 in the first embodiment.
And the intermediate floor slab segment 8 are connected to each other, and FIGS. 14 and 15 show the connection between the segments in the first embodiment.

第1図に示すセグメントリングを組立施工する場合
は、まず上部腕付き接合用セグメント6を上下複合型の
シールドトンネルにおける中間部の左側に配置すると共
に、下部腕付き接合用セグメント7を前記シールドトン
ネルにおける中間部の右側に配置し、次いで中間床版セ
グメント8の両端部を左右の接合用セグメント6,7にお
けるコンクリート製床版支持腕27に載置すると共に、中
間床版セグメント8の端部のピン孔22を接合用セグメン
ト6,7の連結ピン13に嵌挿し、次いで前記保護キャップ4
7を連結ピン13の雄ねじ部48から螺脱したのち、その雄
ねじ部48に螺合したナット44を緊締し、かつ中間床版セ
グメント8の端部の継手金具28と各接合用セグメント6,
7の継手金具28とを、それらにわたって挿通したボルト3
3により締付結合する。
When assembling and constructing the segment ring shown in FIG. 1, first, the joining segment 6 with the upper arm is arranged on the left side of the middle portion in the upper and lower combined type shield tunnel, and the joining segment 7 with the lower arm is arranged in the shield tunnel. Is placed on the right side of the middle floor slab, and then both ends of the middle floor slab segment 8 are placed on the concrete floor slab support arms 27 of the left and right joining segments 6 and 7, and The pin hole 22 is fitted into the connecting pin 13 of the joining segments 6 and 7, and then the protective cap 4 is inserted.
After the 7 is unscrewed from the male screw portion 48 of the connecting pin 13, the nut 44 screwed to the male screw portion 48 is tightened, and the joint fitting 28 at the end portion of the intermediate floor slab segment 8 and each joining segment 6,
7 Fittings 28 and bolts 3
Tighten by 3.

次に上部切欠円形の下部セグメントリング1および下
部切欠円形の上部セグメントリング2を組立てる。
Next, a lower segment ring 1 having an upper cutout circular shape and an upper segment ring 2 having a lower cutout circular shape are assembled.

下部セグメントリング1の組立順序は、多数の円弧状
セグメント3を、上部腕付き接合用セグメント6におけ
る下部の接合面31に連続して上部切欠円形に組立てたの
ち、円弧状セグメント3の列の先端に、キーセグメント
接合面11を有する円弧状セグメント4を連結し、次いで
下部腕付き接合用セグメント7における下部のキーセグ
メント接合面11と前記円弧状セグメント4のキーセグメ
ント接合面11との間の楔形空間に、楔形断面のキーセグ
メント5を挿入して連結する。
The lower segment ring 1 is assembled in the order of assembling a large number of arcuate segments 3 into an upper cutout circle that is continuous with the lower joining surface 31 of the joining segment 6 with upper arms, and then the tips of the rows of the arcuate segments 3 are assembled. , The arcuate segment 4 having the key segment joint surface 11 is connected, and then the wedge shape between the lower key segment joint surface 11 and the key segment joint surface 11 of the arcuate segment 4 in the lower arm joint segment 7 is joined. A key segment 5 having a wedge-shaped cross section is inserted and connected to the space.

また上部セグメントリング2の組立順序は、上部腕付
き接合用セグメント6における上部の接合面12および下
部腕付き接合用セグメント7における上部の接合面12に
連続して、それぞれ複数の円弧状セグメント3を組立て
たのち、各円弧状セグメント列の先端に、キーセグメン
ト接合面11を有する円弧状セグメント4を連結し、次に
各円弧状セグメント4のキーセグメント接合面11の間の
楔形空間にキーセグメント5を挿入して連結する。
In addition, the assembly order of the upper segment ring 2 is such that a plurality of arcuate segments 3 are formed in succession to the upper joint surface 12 of the upper arm joint segment 6 and the upper joint surface 12 of the lower arm joint segment 7. After assembling, the arcuate segment 4 having the key segment joining surface 11 is connected to the tip of each arcuate segment row, and then the key segment 5 is inserted in the wedge-shaped space between the key segment joining surfaces 11 of each arcuate segment 4. Insert and connect.

トンネル周囲方向に隣り合う各セグメントは、第15図
に示すように、継手金具14に挿通されたボルト34により
締付結合される。
As shown in FIG. 15, the segments adjacent to each other in the tunnel circumferential direction are tightened and coupled by bolts 34 inserted in the joint fitting 14.

第2図に示すセグメントリングも、第1図に示すセグ
メントリングの場合と同様の順序で組立てが行なわれ、
かつトンネル長手方向に隣り合う一方のセグメントの前
後方向端面から突出している連結ピン9は、他方のセグ
メントの前後方向端部に埋込固定されている溝形のピン
挿込金具16に挿通され、そのピン挿込金具16内において
連結ピン9の雄ねじ部に螺合されたナット36により、ト
ンネル長手方向に隣り合うセグメントが締付結合され
る。また第1図に示すセグメントリングにおける各セグ
メント相互の接合部と、第2図に示すセグメントリング
における各セグメント相互の接合部とは、トンネル長手
方向に直列に配置されないで、千鳥状に配置されてい
る。第12図は接合用セグメント6,7における位置決め用
ピン10の取付状態およびピン挿込金具29の取付状態を示
すものであって、先端にテーパー37を形成した円形断面
の鋼製位置決め用ピン10の中間部に、鋼製補強板38が嵌
合されて溶接により固着され、かつ前記ピン10の基端側
に鋼製アンカー部材39が溶接により固着され、前記ピン
10の基端側部分とアンカー部材39と補強板38とが接合用
セグメント6,7のコンクリートに埋込固定されている。
The segment ring shown in FIG. 2 is also assembled in the same order as that of the segment ring shown in FIG.
Also, the connecting pin 9 protruding from the front-rear direction end surface of one segment adjacent in the tunnel longitudinal direction is inserted into the groove-shaped pin insertion metal fitting 16 embedded and fixed in the front-rear direction end portion of the other segment, A nut 36 screwed into the male screw portion of the connecting pin 9 in the pin insertion fitting 16 tightly couples adjacent segments in the tunnel longitudinal direction. Further, the joints between the segments in the segment ring shown in FIG. 1 and the joints between the segments in the segment ring shown in FIG. 2 are not arranged in series in the tunnel longitudinal direction but are arranged in a staggered manner. There is. FIG. 12 shows the mounting state of the positioning pin 10 and the mounting state of the pin insertion metal fitting 29 in the joining segments 6 and 7, wherein the steel positioning pin 10 having a circular cross section with a taper 37 formed at its tip is shown. A steel reinforcing plate 38 is fitted and fixed by welding to an intermediate portion of the steel anchor member 39 and a steel anchor member 39 is fixed to the base end side of the pin 10 by welding.
The base end side portion of 10, the anchor member 39 and the reinforcing plate 38 are embedded and fixed in the concrete of the joining segments 6 and 7.

また鋼製筒体4の一端部に鋼製底板41が溶接により固
着されると共に、前記筒体40の他端部に円形孔を有する
鋼製補強板42が溶接により固着されて、ピン孔20を有す
るピン挿込金具29が構成され、そのピン挿込金具29は接
合用セグメント6,7のコンクリートに埋込固定され、前
記ピン10がピン挿込金具29のピン孔20に挿入されてい
る。
Further, a steel bottom plate 41 is fixed to one end of the steel cylinder 4 by welding, and a steel reinforcing plate 42 having a circular hole is fixed to the other end of the cylinder 40 by welding to form a pin hole 20. A pin insertion metal fitting 29 having a pin insertion metal fitting 29 is embedded and fixed in the concrete of the joining segments 6 and 7, and the pin 10 is inserted into the pin hole 20 of the pin insertion metal fitting 29. .

第16図ないし第22図はこの発明の第2実施例を示すも
のであって、第16図および第17図は下部腕付き接合用セ
グメント7を示し、第18図および第19図は上部腕付き接
合用セグメント6を示し、第20図および第21図は中間床
版セグメント8を示している。下部腕付き接合用セグメ
ント7および上部腕付き接合用セグメント6における床
版支持腕27に、垂直なピン孔22とそのピン孔22の下部に
連続する締付用大径孔43とが設けられ、中間床版セグメ
ント8の両端部に垂直な連結ピン13の上部が埋込固定さ
れている。
FIGS. 16 to 22 show a second embodiment of the present invention. FIGS. 16 and 17 show a joining segment 7 with a lower arm, and FIGS. 18 and 19 show an upper arm. 20 and 21 show the intermediate floor slab segment 8. The floor slab support arm 27 in the lower arm joining segment 7 and the upper arm joining segment 6 is provided with a vertical pin hole 22 and a large tightening large diameter hole 43 continuous to the lower part of the pin hole 22, The upper portions of the connecting pins 13 which are vertical to both ends of the intermediate floor slab segment 8 are embedded and fixed.

前記中間床版セグメント8の端部が接合用セグメント
6,7におけるコンクリート製床版支持腕27に載置される
と共に、中間床版セグメント8の端部に固定された連結
ピン13がコンクリート製床版支持腕27のピン孔22に挿入
され、かつ連結ピン13の下部に設けられた雄ねじに固定
用ナット44が螺合され、さらに中間床版セグメント8の
端部の継手金具28と各接合用セグメント6,7の継手金具2
8とが、それらにわたって挿通されたボルト33により締
付結合されているが、その他の構成は第1実施例の場合
と同様である。
The end portion of the intermediate floor slab segment 8 is a joining segment
The connecting pins 13 fixed to the end portions of the intermediate floor slab segments 8 are inserted into the pin holes 22 of the concrete floor slab support arms 27 while being placed on the concrete floor slab support arms 27 in 6, 7, and A fixing nut 44 is screwed into a male screw provided on the lower portion of the connecting pin 13, and further, the fitting fitting 28 at the end of the intermediate floor slab segment 8 and the fitting fitting 2 of each joining segment 6 and 7 are joined.
8 and 8 are tightened and coupled by bolts 33 inserted therethrough, but the other structures are the same as in the case of the first embodiment.

第23図ないし第32図はこの発明の第3実施例を示すも
のである。
23 to 32 show a third embodiment of the present invention.

第27図および第28図は下部腕付き接合用セグメント7
を示すものであって、コンクリート製セグメント本体25
の外側下端部にコンクリート製下部腕26が一体に連設さ
れ、前記セグメント本体25の内端部に、上方から下方に
向かってトンネル中央側に接近するように傾斜すると共
に、前方から後方に向かってトンネル中央側に接近する
ように傾斜する床版支承斜面45が形成され、かつその床
版支承斜面45の上部に継手金具28が埋込固定されている
が、その他の構成は第1実施例における下部腕付き接合
用セグメント7の場合と同様である。
27 and 28 show the connecting segment 7 with the lower arm.
The concrete segment body 25
A lower arm made of concrete 26 is integrally connected to the outer lower end of the segment main body 25, and is inclined to the inner end of the segment main body 25 so as to approach the tunnel center side from the upper side to the lower side, and from the front side to the rear side. The floor slab support slope 45 is formed so as to approach the central side of the tunnel, and the joint fitting 28 is embedded and fixed to the upper part of the floor slab support slope 45, but other configurations are the first embodiment. This is similar to the case of the joining segment 7 with the lower arm in FIG.

第29図および第30図は上部腕付き接合用セグメントを
示すものであって、コンクリート製セグメント本体25の
外側上端部にコンクリート製上部腕30が一体に連設され
ているが、その他の構成は第27図および第28図に示す接
合用セグメントの場合と同様である。
FIG. 29 and FIG. 30 show a joining segment with an upper arm, in which the concrete upper arm 30 is integrally connected to the outer upper end of the concrete segment main body 25, but other configurations are This is similar to the case of the joining segment shown in FIGS. 27 and 28.

第31図および第32図は中間床版セグメント8を示すも
のであって、コンクリート製床版本体32の中間上部に複
数の吊り具係合金具18が埋込固定され、かつ床版本体32
の左右両端部に、上方から下方に向かって床版本体中央
側に接近すると共に、前方から後方に向かって床版本体
中央側に接近するように傾斜する傾斜端面46が形成さ
れ、その傾斜端面46の上部に複数の継手金具28が埋込固
定され、さらに床版本体32の後面(狭幅側の面)に、前
後方向に延長すると共に先端にテーパーを有する複数の
位置決め用ピン10の基端側部分が埋込固定され、また床
版本体32の前面(広幅側の面)には、位置決め用ピン10
を挿入するピン孔20を有するピン挿込金具29が埋込固定
されている。
31 and 32 show the intermediate floor slab segment 8, in which a plurality of hanger engaging metal fittings 18 are embedded and fixed in the upper middle portion of the concrete floor slab main body 32, and the floor slab main body 32 is shown.
At both left and right ends, an inclined end surface 46 is formed so as to approach the floor slab body center side from the upper side to the lower side, and to incline toward the floor slab body center side from the front side to the rear side. A plurality of joint fittings 28 are embedded and fixed on the upper part of 46, and further, on the rear surface (surface on the narrow side) of the floor slab main body 32, a base of a plurality of positioning pins 10 extending in the front-rear direction and having a taper at the tip. The end side is embedded and fixed, and the positioning pin 10 is provided on the front surface (wide side) of the floor slab body 32.
A pin insertion fitting 29 having a pin hole 20 for inserting is fixed.

第23図ないし第26図は、第27図および第28図に示す下
部腕付き接合用セグメント7と、第29図および第30図に
示す上部腕付き接合用セグメント6と、第31図および第
32図に示す中間床版セグメント8と、円弧状セグメント
およびキーセグメントとを使用して、第3実施例の縦型
2連シールドトンネルのセグメント覆工を組立てた状態
を示すものであって、第23図に示すセグメント配置のセ
グメントリングと第24図に示すセグメント配置のセグメ
ントリングとがトンネル長手方向に交互に配置されてい
る。また中間床版セグメント8の両端の傾斜端面46が左
右の接合用セグメント6,7における床版支承斜面45に載
置され、かつ中間床版セグメント8の端部の継手金具28
と各接合用セグメント6,7の継手金具28とが、それらに
わたって挿通したボルト33により締付結合されている。
23 to 26 are splicing segment 7 with a lower arm shown in FIGS. 27 and 28, splicing segment 6 with an upper arm shown in FIGS. 29 and 30, and FIGS.
32 shows a state in which the segment lining of the vertical double shield tunnel of the third embodiment is assembled using the intermediate floor slab segment 8 shown in FIG. 32 and the arcuate segment and the key segment. The segment rings of the segment arrangement shown in FIG. 23 and the segment rings of the segment arrangement shown in FIG. 24 are alternately arranged in the tunnel longitudinal direction. Further, the inclined end faces 46 at both ends of the intermediate floor slab segment 8 are placed on the floor slab support slopes 45 of the left and right joining segments 6 and 7, and the fitting fitting 28 at the end of the intermediate floor slab segment 8 is also placed.
And the joint fitting 28 of each of the joining segments 6 and 7 are tightened and coupled by a bolt 33 inserted therethrough.

第3実施例の場合も、第1実施例の場合と同様の順序
でセグメントの組立てが行なわれる。
Also in the case of the third embodiment, the segments are assembled in the same order as in the case of the first embodiment.

第33図ないし第35図は縦型2連シールドトンネルのセ
グメント覆工の組立施工例を示すものであって、円内の
数字は各セグメントの組立順序を示している。すなわ
ち、第33図の場合は上部セグメントリングおよび下部セ
グメントリングの組立を並行して行なっている例であ
り、第34図の場合は上部セグメントリングの組立を先行
して行なっている例であり、第35図は下部セグメントリ
ングの組立を先行して行なっている例である。
33 to 35 show an example of assembling and constructing a segment lining of a vertical double shield tunnel, and the numbers in the circles show the assembling order of each segment. That is, the case of FIG. 33 is an example in which the upper segment ring and the lower segment ring are assembled in parallel, and the case of FIG. 34 is an example in which the upper segment ring is assembled in advance. FIG. 35 shows an example in which the lower segment ring is assembled in advance.

第36図は連結ピン13に対する保護キャップ47の取付状
態を示すものであって、連結ピン13の先端側に雄ねじ部
48が設けられ、截頭円錐形の先端部を有する合成樹脂ま
たは金属製の保護キャップ47が、前記雄ねじ部48に螺合
され、かつ保護キャップ47の先端に回動工具係合用角孔
49が設けられている。
FIG. 36 shows a state in which the protective cap 47 is attached to the connecting pin 13, and a male screw portion is provided on the tip side of the connecting pin 13.
A protective cap 47 made of synthetic resin or metal, which is provided with 48 and has a truncated cone-shaped tip, is screwed into the male screw portion 48, and the tip of the protective cap 47 has a square hole for engaging a rotary tool.
49 are provided.

この発明を実施する場合、ピン孔22の部分を補強する
ために、コンクリート製床版本体32およびコンクリート
製床版支持腕27におけるピン孔形成予定位置に金属管を
埋設し、その金属管によりピン孔を形成してもよい。
In the case of carrying out the present invention, in order to reinforce the portion of the pin hole 22, a metal pipe is embedded in the concrete floor slab body 32 and the concrete floor slab support arm 27 at the pin hole formation planned position, and the pin is formed by the metal pipe. You may form a hole.

トンネル長手方向に隣り合う接合用セグメント6,7お
よび円弧状セグメント3,4ならびにキーセグメント5等
を連結する手段としては、第15図に示すような連結手
段、すなわち、セグメントにおけるトンネル長手方向の
側部に継手金具を埋込固定し、トンネル長手方向に隣り
合うセグメントの継手金具をそれらにわたって挿通した
ボルトおよびナットにより連結する手段を採用してもよ
い。
As means for connecting the joining segments 6 and 7, the arcuate segments 3 and 4, and the key segment 5 which are adjacent to each other in the tunnel longitudinal direction, the connecting means as shown in FIG. A means may be adopted in which a joint metal fitting is embedded and fixed in the section, and the joint metal fittings of the segments adjacent in the tunnel longitudinal direction are connected by bolts and nuts inserted therethrough.

また連結ピン9の雄ねじ部および第2実施例における
連結ピン13の雄ねじ部にも、保護キャップを螺合しても
よい。
Further, a protective cap may be screwed onto the male screw portion of the connecting pin 9 and the male screw portion of the connecting pin 13 in the second embodiment.

〔発明の効果〕〔The invention's effect〕

この発明は前述のように構成されているので、以下に
記載するような効果を奏する。
Since the present invention is configured as described above, it has the following effects.

左右の接合用セグメント6,7の中間床版セグメント8
とを最初に組立てると共に、左右の接合用セグメント6,
7に結合される上部切欠円形の下部セグメントリング1
および下部切欠円形の上部セグメントリング2にキーセ
グメント5を採用したので、下部セグメントリング1お
よび上部セグメントリング2の組立てを同時に行なうこ
とができ、そのため縦型2連シールドトンネルのセグメ
ント覆工の組立を迅速に行なって、工期を短縮すると共
に施工費を安くすることができかつ最初に組立てられた
左右の接合用セグメント6,7および中間床版セグメント
8が、下部セグメントリング1および上部セグメントリ
ング2の組立作業空間を遮断するので、下部セグメント
リング1の組立作業を行なう際に、上部トンネル空間か
ら下部トンネル空間に器物が落下することはなく、その
ため下部セグメントリング1の組立作業を行なう際の安
全性を確保することができ、さらにトンネル長手方向に
隣り合う一方の接合用セグメントに固定されている複数
の位置決め用ピン10が他方の接合用セグメントに設けら
れている複数のピン孔20に挿入されているので、トンネ
ル長手方向に隣り合うセグメントリングにおける継手部
の目ずれ(トンネル周囲方向の位置の狂い)がなくな
り、そのため上下方向複合型のセグメントリングの最初
の位置を正確に設定することにより、完成セグメント覆
工の精度を向上させることができ、また接合用セグメン
ト6,7および中間床版セグメント8のうちの一方に固定
された垂直な連結ピン13を、他方に設けられた垂直なピ
ン孔22に挿入すれば、左右両側の接合用ゼグメント6,7
に対する中間床版セグメント8の架設固定を高精度でか
つ迅速に行なうことができる。
Middle floor slab segment 8 of left and right joining segments 6 and 7
Assemble and first, and the left and right joining segments 6,
Rounded lower segment ring 1 with upper notch joined to 7
Since the key segment 5 is adopted for the upper segment ring 2 having the lower cutout circular shape, the lower segment ring 1 and the upper segment ring 2 can be assembled at the same time. Therefore, the segment lining of the vertical double shield tunnel can be assembled. It can be carried out quickly to shorten the construction period and reduce the construction cost, and the left and right joining segments 6 and 7 and the intermediate floor slab segment 8 which were first assembled are the lower segment ring 1 and the upper segment ring 2. Since the assembling work space is shut off, when the assembling work of the lower segment ring 1 is performed, no articles fall from the upper tunnel space to the lower tunnel space, and therefore the safety at the time of assembling the lower segment ring 1 is ensured. Can be secured, and one of the joints adjacent to each other in the tunnel longitudinal direction can be secured. Since the plurality of positioning pins 10 fixed to the segment are inserted into the plurality of pin holes 20 provided in the other joining segment, the misalignment of the joint portion in the segment rings adjacent in the tunnel longitudinal direction ( Position deviation in the direction around the tunnel) is eliminated, so that by accurately setting the first position of the vertical composite segment ring, the accuracy of the completed segment lining can be improved, and the joining segment 6, If the vertical connecting pin 13 fixed to one of the 7 and the intermediate floor slab segment 8 is inserted into the vertical pin hole 22 provided in the other, the joining segments 6, 7 on both the left and right sides are inserted.
The intermediate floor slab segment 8 can be erected and fixed to and with high precision and speed.

さらにまた、下部セグメントリング1または上部セグ
メントリング2の何れか一方の組立作業を先行して行な
うことにより、下部セグメントリング1の組立作業空間
と上部セグメントリング2の組立作業空間とが上下方向
に重ならないので、安全にセグメント組立施工を行なう
ことができる。
Furthermore, by performing the assembling work of either the lower segment ring 1 or the upper segment ring 2 in advance, the assembling work space of the lower segment ring 1 and the assembling work space of the upper segment ring 2 are vertically overlapped. Therefore, it is possible to safely perform segment assembly work.

【図面の簡単な説明】[Brief description of drawings]

第1図ないし第15図はこの発明の第1実施例を示すもの
であって、第1図は縦型2連シールドトンネルのセグメ
ント覆工における一組のセグメントリングを示す正面
図、第2図は第1図のセグメントリングの前後に隣接し
て組立てられるセグメントリングの正面図、第3図は縦
型2連シールドトンネルのセグメント覆工の一部を示す
側面図、第4図は下部腕付き接合用セグメントの正面
図、第5図はその接合用セグメントをトンネル内側から
見た側面図、第6図は下部腕付き接合用セグメントの背
面図、第7図は上部腕付き接合用セグメントの正面図、
第8図はその接合用セグメントをトンネル内側から見た
側面図、第9図は上部腕付き接合用セグメントの背面
図、第10図は中央床版セグメントの正面図、第11図はそ
の平面図、第12図は接合用セグメントに取付けられた位
置決め用ピンを接合用セグメントに取付けられたピン挿
込金具に対向させた状態を示す断面図、第13図は接合用
セグメントと中間床版セグメントとの結合状態を示す縦
断正面図、第14図はトンネル長手方向に隣り合うセグメ
ントの連結部を示す側面図、第15図はトンネル周囲方向
に隣り合うセグメントの継手金具およびボルトによる連
結部を示す図である。 第16図ないし第22図はこの発明の第2実施例を示すもの
であって、第16図は下部腕付き接合用セグメントの正面
図、第17図はその接合用セグメントをトンネル内側から
見た側面図、第18図は上部腕付き接合用セグメントの正
面図、第19図はその接合用セグメントをトンネル内側か
ら見た側面図、第20図は中間床版セグメントの正面図、
第21図はその平面図、第22図は接合用セグメントと中間
床版セグメットとの結合状態を示す縦断正面図である。 第23図ないし第32図はこの発明の第3実施例を示すもの
であって、第23図は縦型2連シールドトンネルのセグメ
ント覆工における一組のセグメントリングを示す正面
図、第24図は第23図のセグメントリングの前後に隣接し
て組立てられるセグメントリングの正面図、第25図は縦
型2連シールドトンネルのセグメント覆工の一部を示す
側面図、第26図は接合用セグメントと中間床版セグメン
トとの結合状態を示す縦断正面図、第27図は下部腕付き
接合用セグメントの正面図、第28図はその接合用セグメ
ントをトンネル内側から見た側面図、第29図は上部腕付
き接合用セグメントの正面図、第30図はその接合用セグ
メントをトンネル内側から見た側面図、第31図は中間床
版セグメントの正面図、第32図はその平面図である。 第33図ないし第35図は縦型2連シールドトンネルのセグ
メント覆工の組立施工例を示すものであって、第33図は
上部セグメントリングおよび下部セグメントリングの組
立を並行して行なっている例を示す斜視図、第34図は上
部セグメントリングの組立を先行して行なっている例を
示す斜視図、第35図は下部セグメントリングの組立を先
行して行なっている例を示す斜視図である。第36図は連
結ピンに対する保護キャップの取付状態を示す一部縦断
側面図である。 図において、1は下部セグメントリング、2は上部セグ
メントリング、3および4は円弧状セグメント、5はキ
ーセグメント、6は上部腕付き接合用セグメント、7は
下部腕付き接合用セグメント、8は中間床版セグメン
ト、9は連結ピン、10は位置決め用ピン、11はキーセグ
メント接合面、12は接合面、13は連結ピン、14は継手金
具、16はピン挿込金具、20はピン孔、22はピン孔、25は
コンクリート製セグメント本体、26はコンクリート製下
部腕、27はコンクリート製床版支持腕、28は継手金具、
29はピン挿込金具、30はコンクリート製上部腕、31は接
合面、32はコンクリート製床版本体、33および34はボル
ト、36はナット、44は固定用ナット、45は床版支承斜
面、46は傾斜端面である。
1 to 15 show a first embodiment of the present invention, and FIG. 1 is a front view showing a pair of segment rings in a segment lining of a vertical double shield tunnel, and FIG. Is a front view of the segment ring assembled adjacent to the front and rear of the segment ring of FIG. 1, FIG. 3 is a side view showing a part of the segment lining of the vertical double shield tunnel, and FIG. 4 is a lower arm A front view of the joining segment, FIG. 5 is a side view of the joining segment as seen from the inside of the tunnel, FIG. 6 is a rear view of the joining segment with a lower arm, and FIG. 7 is a front view of the joining segment with an upper arm. Figure,
FIG. 8 is a side view of the joining segment as seen from the inside of the tunnel, FIG. 9 is a rear view of the joining segment with an upper arm, FIG. 10 is a front view of a central floor slab segment, and FIG. 11 is a plan view thereof. , FIG. 12 is a cross-sectional view showing a state in which a positioning pin attached to a joining segment is opposed to a pin insertion fitting attached to the joining segment, and FIG. 13 is a joining segment and an intermediate floor slab segment. Fig. 14 is a vertical sectional front view showing a joined state of Fig. 14, Fig. 14 is a side view showing a connecting portion of adjacent segments in the tunnel longitudinal direction, and Fig. 15 is a view showing a connecting portion by joint fittings and bolts of adjacent segments in the tunnel circumferential direction. Is. 16 to 22 show a second embodiment of the present invention. FIG. 16 is a front view of a joining segment with a lower arm, and FIG. 17 is a view of the joining segment from the inside of the tunnel. Side view, FIG. 18 is a front view of a joining segment with an upper arm, FIG. 19 is a side view of the joining segment as viewed from the inside of the tunnel, and FIG. 20 is a front view of an intermediate floor slab segment,
FIG. 21 is a plan view thereof, and FIG. 22 is a vertical sectional front view showing a joined state of the joining segment and the intermediate floor segmet. 23 to 32 show a third embodiment of the present invention, and FIG. 23 is a front view showing a pair of segment rings in a segment lining of a vertical double shield tunnel, and FIG. Is a front view of the segment ring assembled adjacent to the front and rear of the segment ring of FIG. 23, FIG. 25 is a side view showing a part of the segment lining of the vertical double shield tunnel, and FIG. 26 is a joining segment. And a vertical front view showing the connection state between the intermediate floor slab segment, Fig. 27 is a front view of the joining segment with a lower arm, Fig. 28 is a side view of the joining segment as seen from the inside of the tunnel, and Fig. 29 is FIG. 30 is a front view of a joining segment with an upper arm, FIG. 30 is a side view of the joining segment as viewed from the inside of the tunnel, FIG. 31 is a front view of an intermediate floor slab segment, and FIG. 32 is a plan view thereof. 33 to 35 show an example of assembling the segment lining of the vertical double shield tunnel, and FIG. 33 shows an example of assembling the upper segment ring and the lower segment ring in parallel. FIG. 34 is a perspective view showing an example in which the upper segment ring is assembled in advance, and FIG. 35 is a perspective view showing an example in which the lower segment ring is assembled in advance. . FIG. 36 is a partially longitudinal side view showing how the protective cap is attached to the connecting pin. In the figure, 1 is a lower segment ring, 2 is an upper segment ring, 3 and 4 are arc-shaped segments, 5 is a key segment, 6 is a joining segment with an upper arm, 7 is a joining segment with a lower arm, and 8 is an intermediate floor. Plate segment, 9 is a connecting pin, 10 is a positioning pin, 11 is a key segment joining surface, 12 is a joining surface, 13 is a joining pin, 14 is a fitting fitting, 16 is a pin insertion fitting, 20 is a pin hole, and 22 is a Pin holes, 25 is a concrete segment main body, 26 is a concrete lower arm, 27 is a concrete floor slab support arm, 28 is a joint fitting,
29 is a pin insertion metal fitting, 30 is a concrete upper arm, 31 is a joint surface, 32 is a concrete floor slab body, 33 and 34 are bolts, 36 is a nut, 44 is a fixing nut, 45 is a floor slab bearing slope, 46 is an inclined end face.

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】上部腕付き接合用セグメント6および下部
腕付き接合用セグメント7を左右方向に間隔をおいて配
置し、かつ中間床版セグメント8の両端部を各接合用セ
グメント6,7に結合し、次に各接合用セグメント6,7の下
端部に、キーセグメント5を含む上部切欠円形の下部セ
グメントリング1を組立連結し、かつ各接合用セグメン
ト6,7の上端部に、キーセグメント5を含む下部切欠円
形の上部セグメントリング2を組立連結し、トンネル長
手方向に隣り合う一方の接合用セグメントに固定されて
いる複数の位置決め用ピン10を他方の接合用セグメント
に設けられた複数のピン孔20に挿入する縦型2連シール
ドトンネルのセグメント覆工の施工法。
1. A joining segment 6 with an upper arm and a joining segment 7 with a lower arm are arranged at intervals in the left-right direction, and both ends of an intermediate floor slab segment 8 are joined to each joining segment 6, 7. Then, the lower segment ring 1 having an upper notched circular shape including the key segment 5 is assembled and connected to the lower end portions of the joining segments 6 and 7, and the key segment 5 is attached to the upper end portions of the joining segments 6 and 7. A plurality of positioning pins 10 fixed to one joining segment adjacent to each other in the longitudinal direction of the tunnel are assembled and connected to each other, and a plurality of pins provided on the other joining segment. Construction method for segment lining of vertical double shield tunnel to be inserted into hole 20.
【請求項2】下部セグメントリング1または上部セグメ
ントリング2の何れか一方の組立作業を先行して行う請
求項1記載の縦型2連シールドトンネルのセグメント覆
工の施工法。
2. The method for constructing a segment lining of a vertical double shield tunnel according to claim 1, wherein the assembling work of either the lower segment ring 1 or the upper segment ring 2 is performed in advance.
【請求項3】上部腕付き接合用セグメント6および下部
腕付き接合用セグメント7と中間床版セグメント8との
うちの一方に固定した垂直な連結ピン13を、他方に設け
た垂直なピン孔22に挿入する請求項1記載の縦型2連シ
ールドトンネルのセグメント覆工の施工法。
3. A vertical connecting pin 13 fixed to one of the upper arm connecting segment 6 and the lower arm connecting segment 7 and the intermediate floor slab segment 8 and a vertical pin hole 22 provided in the other. The method for constructing a segment lining of a vertical double shield tunnel according to claim 1, which is inserted into the.
【請求項4】上部腕付き接合用セグメント6および下部
腕付き接合用セグメント7が左右方向に間隔をおいて配
置され、中間床版セグメント8の両端部が各接合用セグ
メント6,7に結合され、各接合用セグメント6,7の下端部
に、キーセグメント5を含む上部切欠円形の下部セグメ
ントリング1が組立連結され、前記各接合用セグメント
6,7の上端部に、キーセグメント5を含む下部切欠円形
の上部セグメントリング2が組立連結され、トンネル長
手方向に隣り合う一方の接合用セグメントに固定されて
いる複数の位置決め用ピン10が他方の接合用セグメント
に設けられた複数のピン孔20に挿入されている縦型2連
シールドトンネルのセグメント覆工構造。
4. An upper arm joining segment 6 and a lower arm joining segment 7 are arranged at intervals in the left-right direction, and both ends of an intermediate floor slab segment 8 are joined to each joining segment 6,7. , A lower segment ring 1 having an upper notched circular shape including a key segment 5 is assembled and connected to the lower end portions of the respective joining segments 6 and 7,
A lower notched circular upper segment ring 2 including a key segment 5 is assembled and connected to the upper ends of 6, 7 and a plurality of positioning pins 10 fixed to one of the joining segments adjacent in the tunnel longitudinal direction is the other. A vertical double shield tunnel segment lining structure that is inserted into a plurality of pin holes 20 provided in the joining segment.
JP1271649A 1989-10-20 1989-10-20 Vertical double shield tunnel segment lining structure and its construction method Expired - Fee Related JPH089955B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1271649A JPH089955B2 (en) 1989-10-20 1989-10-20 Vertical double shield tunnel segment lining structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1271649A JPH089955B2 (en) 1989-10-20 1989-10-20 Vertical double shield tunnel segment lining structure and its construction method

Publications (2)

Publication Number Publication Date
JPH03137396A JPH03137396A (en) 1991-06-11
JPH089955B2 true JPH089955B2 (en) 1996-01-31

Family

ID=17502985

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1271649A Expired - Fee Related JPH089955B2 (en) 1989-10-20 1989-10-20 Vertical double shield tunnel segment lining structure and its construction method

Country Status (1)

Country Link
JP (1) JPH089955B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5090232B2 (en) * 2008-03-31 2012-12-05 株式会社熊谷組 Steel segment and method of connecting steel segments
CN107130967B (en) * 2017-06-08 2019-01-01 重庆工程职业技术学院 The construction method of extra-large cross-section deep tunnel and accessory structure
CN108915723B (en) * 2018-07-27 2023-06-27 中铁第四勘察设计院集团有限公司 Shield tunnel segment structure crossing vertical dislocation movable fault

Also Published As

Publication number Publication date
JPH03137396A (en) 1991-06-11

Similar Documents

Publication Publication Date Title
US4545701A (en) Tunnel wall structure
JP7371113B2 (en) Road structure, formwork jig, and road structure construction method
JPH089955B2 (en) Vertical double shield tunnel segment lining structure and its construction method
JP4359376B2 (en) Joint structure and joining method of single shields in outer shell advanced tunnel method
JP3896179B2 (en) Steel joint structure
JPH077438Y2 (en) Cylindrical wall for lining drill holes
JP2002070489A (en) Segment and its joint structure
JP2004293113A (en) Latticed point structure of floor slab and coupler in bridge
JP2750353B2 (en) Tubular wall for excavation hole lining
JP2670483B2 (en) Joining structure of inner wall in tubular wall for lining excavation hole
JPH0634474Y2 (en) Joint structure of middle pillar in tubular wall for lining excavation hole
JP2683644B2 (en) Tubular wall for excavation hole lining
JPH0330478Y2 (en)
JP2534576Y2 (en) Multi-segment structure and branch segment
JPH06180097A (en) Repairing method of horseshoe type tunnel lining
JPS6032239Y2 (en) Joint structure of concrete segment for tunnel lining
JP2717643B2 (en) Prefabricated retaining wall
JPH07247602A (en) Connection method and tool for concrete products
JP3122245B2 (en) Segment joint structure
JP2654500B2 (en) Tubular wall for excavation hole lining
JPH04155028A (en) Pillar beam joining part construction
JPS60255266A (en) Manufacture of steel plate cell
JPH04198535A (en) Column and beam jointing equipment of steel pipe construction
JPH0321800A (en) Different arm branch segment
JP2700152B2 (en) Drilling hole lining structure

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees