JPH0879973A - Power system control device - Google Patents

Power system control device

Info

Publication number
JPH0879973A
JPH0879973A JP6210328A JP21032894A JPH0879973A JP H0879973 A JPH0879973 A JP H0879973A JP 6210328 A JP6210328 A JP 6210328A JP 21032894 A JP21032894 A JP 21032894A JP H0879973 A JPH0879973 A JP H0879973A
Authority
JP
Japan
Prior art keywords
power
generation facility
power generation
voltage
transmission line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6210328A
Other languages
Japanese (ja)
Inventor
Fumio Bito
文男 尾藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuji Electric Co Ltd
Original Assignee
Fuji Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuji Electric Co Ltd filed Critical Fuji Electric Co Ltd
Priority to JP6210328A priority Critical patent/JPH0879973A/en
Publication of JPH0879973A publication Critical patent/JPH0879973A/en
Pending legal-status Critical Current

Links

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Selective Calling Equipment (AREA)

Abstract

PURPOSE: To suppress the oscillation of a power system when a demand balance is lost and at the same time readily throw a generation facility which is released from the system into the power system again. CONSTITUTION: A generation facility for supplying power and a substation for consuming the power are connected to a power transmission system 6 and data including the connection state between the generation facilities and the power/voltage/breaker of the substation are transmitted to a central controller 2 via a data communication line 7. A system condition operation device 3 installed at the central controller 2 transmits a frequency instruction value F, a voltage phase 6 for each generation facility, and a reference time t outputted by a reference clock 5 to each generation facility via an instruction value communication line 8. Each generation facility determines a frequency setting value and a generation power instruction value based on them. The generation facility thrown into the system calculates a voltage phase when it is being thrown in parallel by a system condition modification operation device 4 and sets frequency and voltage phase as the values for standby.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、電力系統の周波数と
電圧を制御する電力系統制御装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a power system controller for controlling frequency and voltage of a power system.

【0002】[0002]

【従来の技術】電力系統の周波数が変動すれば電動機の
回転速度が変動したり時刻の指示値が狂ったりして、産
業や日常生活に大きな影響を及ぼす。従って周波数が常
に目標値で一定しているように維持する必要がある。と
ころで電力系統の周波数は電力需要が発電電力を上回れ
ば低下するし、電力需要が発電電力よりも少なくなれば
周波数は上昇する。更に、送電線に接続して並列運転し
ている各発電設備の回転速度の差異に対応して、各発電
設備が分担する電力に不平衡を生じるのは周知である。
2. Description of the Related Art If the frequency of the electric power system fluctuates, the rotational speed of the electric motor fluctuates and the indication value of time fluctuates, which has a great influence on industry and daily life. Therefore, it is necessary to keep the frequency constant at the target value. By the way, the frequency of the power system decreases when the power demand exceeds the generated power, and rises when the power demand becomes less than the generated power. Further, it is well known that the electric powers shared by the respective power generation facilities are unbalanced in response to the difference in the rotational speed of the respective power generation facilities connected in parallel to the power transmission line and operating in parallel.

【0003】そこで、個々の発電設備が出力する電力と
負荷側の電力需要とのバランスとによって決まる電力系
統の周波数を中央制御所で監視し、各発電設備の発電電
力を当該中央制御所からの指令に基づいて調整すること
で周波数を規定値付近に維持するのが、電力系統の周波
数制御の現状である。
Therefore, the frequency of the power system, which is determined by the balance between the power output from each power generation facility and the power demand on the load side, is monitored at the central control station, and the power generated by each power generation facility is monitored by the central control station. The current state of frequency control of electric power systems is to maintain the frequency near a specified value by adjusting it based on a command.

【0004】[0004]

【発明が解決しようとする課題】前述したように電力系
統の周波数は、当該電力系統内における電力の需給バラ
ンスで決まる。よって、負荷の電力需要が変動したり発
電電力が減少(例えば発電設備が電力系統から解列)す
ることで需給バランスが崩れると、当該電力系統に周波
数変動や電圧変動を生じるが、従来の制御では、これら
の変動を収束して安定した状態に落ち着かせるまでには
時間がかかり、系統全体の動揺が長時間継続する不都合
がある。
As described above, the frequency of the electric power system is determined by the balance between supply and demand of electric power in the electric power system. Therefore, if the power supply / demand balance is disrupted due to fluctuations in the power demand of the load or a decrease in the generated power (for example, the power generation equipment is disconnected from the power grid), frequency fluctuations and voltage fluctuations occur in the power grid. Then, it takes time until these fluctuations are converged and settled to a stable state, and there is a disadvantage that the fluctuation of the entire system continues for a long time.

【0005】又、電力系統から解列した発電設備を当該
電力系統へ再度投入する際には、発電設備の出力電圧と
電圧位相及び周波数を、送電線の接続端の値に合わせな
ければならないが、系統に電力動揺がある場合は送電線
の電圧が不安定である。従って当該発電設備を電力系統
に投入するのに時間がかかる。広い地域で多くの発電設
備が系統から遮断されている場合は、送電線の電圧が確
立していないので、全発電設備が電力系統に投入されて
並列運転をするまでには更に長い時間が必要になる。
Further, when the power generation facility disconnected from the power system is re-introduced into the power system, the output voltage, voltage phase and frequency of the power generation facility must be matched with the values at the connection ends of the power transmission line. If there is power fluctuation in the system, the voltage of the transmission line is unstable. Therefore, it takes time to put the power generation equipment into the power system. When a large number of power generation facilities are cut off from the grid in a large area, the voltage of the transmission line has not been established, so it takes a longer time before all the power generation facilities are put into the power grid and run in parallel. become.

【0006】そこでこの発明の目的は、需給バランスが
崩れたときの電力系統の動揺を抑制すると共に、電力系
統から解列された発電設備の系統への再投入を素早く行
わせることにある。
Therefore, an object of the present invention is to suppress the sway of the power system when the supply and demand balance is disturbed, and to promptly reconnect the power generation equipment disconnected from the power system to the system.

【0007】[0007]

【課題を解決するための手段】前記の目的を達成するた
めにこの発明の電力系統制御装置は、複数の発電設備の
並列運転で発生する電力を需要地へ送電する複数の送電
線と、これら各送電線に接続して負荷へ電力を供給する
複数の変電所とで構成している電力系統において、前記
各発電設備の発電電力と電圧、前記各変電所の受電電力
と電圧、各発電設備及び各変電所と各送電線とを接続す
る開閉器の接続状態と各送電線相互間を接続する開閉器
の接続状態、とを中央制御装置へ伝達するデータ通信回
線と、前記データ通信回線を経て得られるデータを入力
して、前記各送電線に接続している各発電設備が出力す
る電圧と周波数と電圧位相の指示値を演算する系統条件
演算装置を備えた中央制御装置と、前記各発電設備と中
央制御装置とへ周波数と電圧位相の基準となる時刻を与
える基準時計と、前記系統条件演算装置が演算した前記
指示値を前記送電線に接続している各発電設備へ伝達す
る指示値通信回線と、を備えるものとする。
In order to achieve the above-mentioned object, a power system control device of the present invention includes a plurality of power transmission lines for transmitting power generated by parallel operation of a plurality of power generation facilities to a demand area, and a plurality of these power transmission lines. In a power system configured with a plurality of substations connected to each transmission line to supply electric power to a load, generated power and voltage of each power generation facility, received power and voltage of each substation, each power generation facility And a data communication line for transmitting the connection state of the switch connecting each substation and each transmission line and the connection state of the switch connecting each transmission line to the central control device, and the data communication line. A central control device having a system condition calculating device for inputting the data obtained through the above and calculating instruction values of the voltage, frequency and voltage phase output by each power generation facility connected to each transmission line, and Access to power generation equipment and central control unit A reference clock that gives a time that serves as a reference for the number and the voltage phase, and an instruction value communication line that transmits the instruction value calculated by the system condition calculation device to each power generation facility connected to the power transmission line. And

【0008】又は、前記各発電設備の発電電力と電圧、
前記各変電所の受電電力と電圧、各発電設備及び各変電
所と各送電線とを接続する開閉器の接続状態と各送電線
相互間を接続する開閉器の接続状態、とを中央制御装置
へ伝達するデータ通信回線と、前記データ通信回線を経
て得られるデータを入力して、前記各送電線に接続して
いる各発電設備が出力する電圧と周波数と電圧位相の指
示値を演算する系統条件演算装置を備えた中央制御装置
と、前記中央制御装置に設置して前記データ通信回線を
経て得られるデータを入力し、前記各送電線に接続する
予定の各発電設備が出力する電圧と周波数と電圧位相の
指示値を演算する系統条件変更演算装置と、前記各発電
設備と中央制御装置とへ周波数と電圧位相の基準となる
時刻を与える基準時計と、前記系統条件演算装置と系統
条件変更演算装置とが演算した前記指示値を、前記送電
線に接続している各発電設備と送電線に接続する予定の
各発電設備とへ伝達する指示値通信回線と、を備えるも
のとする。
Alternatively, the generated power and voltage of each of the power generation equipment,
The central control unit controls the received power and voltage of each substation, the connection state of switches for connecting each power generation facility and each substation to each transmission line, and the connection state of switches for connecting each transmission line to each other. A system for inputting data obtained through the data communication line and a data communication line to be transmitted to the data communication line, and calculating instruction values of the voltage, frequency and voltage phase output by each power generation facility connected to the power transmission line. A central control device equipped with a condition calculation device, and a voltage and frequency output by each power generation facility that is installed in the central control device and inputs data obtained through the data communication line, and is connected to each power transmission line. And a system condition change calculation device for calculating the indicated value of the voltage phase, a reference clock for giving time as a frequency and voltage phase reference to each of the power generation equipment and the central control device, the system condition calculation device and system condition change Arithmetic unit There shall be provided with the instruction value calculated, and a command value communication line for transmission to the respective power generation equipment will be connected to the transmission line and the power generation equipment that is connected to the transmission line.

【0009】[0009]

【作用】電力系統の周波数は、送電線に接続している発
電設備の発電電力と、当該送電線に接続している変電所
を経て消費される電力との電力需給バランスと、発電設
備の慣性定数とによって決まる。そこで中央制御装置は
データ通信回線を介して得られる各発電設備と各変電所
の電力・電圧・接続状態などの各種データを入力する。
系統条件演算装置はこれら各種データと基準時計からの
時刻信号を受けて、別個の出力周波数指示値と別個の出
力電圧位相指示値を、指示値通信回線を介して各発電設
備へ送り出す。
[Function] The frequency of the power grid is determined by the power supply and demand balance between the generated power of the power generation facility connected to the transmission line and the power consumed through the substation connected to the transmission line, and the inertia of the power generation facility. It depends on the constant and. Therefore, the central control unit inputs various data such as electric power, voltage and connection status of each power generation equipment and each substation obtained through the data communication line.
The system condition computing device receives these various data and the time signal from the reference clock, and sends out a separate output frequency instruction value and a separate output voltage phase instruction value to each power generation facility via the instruction value communication line.

【0010】これから電力系統に並列接続される発電設
備へは、この発電設備が系統に並列接続された場合に予
測される状態を事前に系統条件変更演算装置で計算し、
当該発電設備を演算した状態にして待機させる。
For the power generation equipment to be connected in parallel to the electric power system, the system condition change computing device calculates in advance the expected state when the power generation equipment is connected in parallel to the power system.
The power generation equipment is put into a calculated state and put on standby.

【0011】[0011]

【実施例】図1は本発明の第1実施例を表したブロック
回路図である。図1の第1実施例回路において、第1発
電所10と第2発電所20とは遮断器11と21とを介
して並列運転しており、両発電所の発電電力が送配電系
統6へ送出されている。送配電系統6には遮断器41を
介して変電所40が接続され、発電電力は変電所40か
ら図示していない負荷へ供給される。ここで第1発電所
10が出力する電力,電圧,遮断器の状態などの各種デ
ータがデータ通信回線7を介して中央制御装置2へ送ら
れる。第2発電所20と変電所40についても同様のデ
ータをデータ通信回線7が中央制御装置2へ送出してい
る。
1 is a block circuit diagram showing a first embodiment of the present invention. In the first embodiment circuit of FIG. 1, the first power plant 10 and the second power plant 20 are operating in parallel via the circuit breakers 11 and 21, and the power generated by both power plants is transmitted to the power transmission and distribution system 6. Has been sent out. A substation 40 is connected to the power transmission and distribution system 6 via a circuit breaker 41, and the generated power is supplied from the substation 40 to a load (not shown). Here, various data such as the power output from the first power plant 10, the voltage, and the state of the circuit breaker are sent to the central control unit 2 via the data communication line 7. For the second power plant 20 and the substation 40, the data communication line 7 sends the same data to the central control unit 2.

【0012】中央制御装置2に設置している系統条件演
算装置3は基準時計5からの基準時刻tを入力すると共
に、データ通信回線7を経て前述のデータを入力し、電
力の需給バランスの状態に対応して、各発電所へは指示
値通信回線8を介して前述の基準時刻tと周波数指示値
Fとを送ると共に、第1発電所10へは電圧位相指示値
δ1 を、第2発電所20へは電圧位相指示値δ2 を指示
値通信回線8を介して送る。
The system condition computing unit 3 installed in the central control unit 2 inputs the reference time t from the reference clock 5 and also inputs the above-mentioned data via the data communication line 7 to balance the supply and demand of electric power. In response to the above, the reference time t and the frequency instruction value F described above are sent to each power station via the instruction value communication line 8, and the voltage phase instruction value δ 1 is sent to the first power station 10 and the frequency phase instruction value δ 2 is sent to the second power station. The voltage phase indication value δ 2 is sent to the power plant 20 via the indication value communication line 8.

【0013】各発電所は受信した周波数指示値Fを従来
の周波数設定値とし、電圧位相指示値δ1 又は電圧位相
指示値δ2 と発電所端の電圧位相との差を従来の発電電
力指示値として運転する。図2は本発明の第2実施例を
表したブロック回路図であるが、図2の第2実施例回路
は前述した図1の第1実施例回路に系統条件変更演算装
置4と第3発電所30及び遮断器31を追加して構成し
ている。したがって第1実施例回路と同じ部分の説明は
省略する。
Each power plant uses the received frequency instruction value F as a conventional frequency set value, and determines the difference between the voltage phase instruction value δ 1 or the voltage phase instruction value δ 2 and the voltage phase at the power station end by the conventional power generation instruction. Drive as a value. FIG. 2 is a block circuit diagram showing a second embodiment of the present invention. The second embodiment circuit of FIG. 2 is the same as the first embodiment circuit of FIG. A place 30 and a circuit breaker 31 are added. Therefore, the description of the same parts as those of the first embodiment circuit is omitted.

【0014】図2の第2実施例回路では、第1発電所1
0と第2発電所20とは並列運転してその発電電力を送
配電系統6へ送出しているが、遮断器31は開路してい
るので第3発電所30は未だ系統へ投入されていない。
前述したように系統が不安定状態のときに第3発電所3
0を送配電系統6に並列接続するのは簡単ではない。そ
こで中央制御装置2には系統条件変更演算装置4を設置
して、遮断器31が投入された場合の電圧位相指示値δ
3 を系統条件変更演算装置4で事前に計算し、第3発電
所30の周波数と電圧位相とを計算した状態にして待機
させておく。
In the second embodiment circuit of FIG. 2, the first power plant 1
0 and the second power plant 20 are operated in parallel to send the generated power to the power transmission and distribution system 6, but the circuit breaker 31 is open, so the third power plant 30 has not yet been input to the system. .
As mentioned above, the 3rd power plant 3
It is not easy to connect 0 to the transmission and distribution system 6 in parallel. Therefore, the system condition changing arithmetic unit 4 is installed in the central control unit 2, and the voltage phase instruction value δ when the circuit breaker 31 is turned on.
3 is calculated in advance by the system condition change calculation device 4, and the frequency and voltage phase of the third power plant 30 are calculated and kept in standby.

【0015】[0015]

【発明の効果】この発明によれば、データ通信回線を使
って送配電系統に接続している発電設備や変電所の状態
と電力の需給バランスなどのデータと基準時刻tとをを
中央制御装置へ取り込み、各発電設備の周波数指示値
と、各発電設備ごとの別個の電圧位相指示値とを指示値
通信回線を介して各発電設備へ与えることにより、電力
系統の動揺を抑制できる効果が得られる。又、電力系統
へ発電設備を並列に投入する操作を速やかに行うことが
できる効果も得られる。
According to the present invention, the central control unit obtains data such as the state of the power generation equipment or substation connected to the power transmission and distribution system using the data communication line and the power supply and demand balance and the reference time t. Incorporation into each power generation facility, and by giving the frequency command value of each power generation facility and the separate voltage phase command value of each power generation facility to each power generation facility via the command value communication line, it is possible to suppress the fluctuation of the power system. To be Further, there is an effect that the operation of inserting the power generation equipment into the electric power system in parallel can be quickly performed.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の第1実施例を表したブロック回路図FIG. 1 is a block circuit diagram showing a first embodiment of the present invention.

【図2】本発明の第2実施例を表したブロック回路図FIG. 2 is a block circuit diagram showing a second embodiment of the present invention.

【符号の説明】[Explanation of symbols]

2 中央制御装置 3 系統条件演算装置 4 系統条件変更演算装置 5 基準時計 6 送配電系統 7 データ通信回線 8 指示値通信回線 10 第1発電所 20 第2発電所 30 第3発電所 40 変電所 2 Central control device 3 System condition calculation device 4 System condition change calculation device 5 Reference clock 6 Transmission and distribution system 7 Data communication line 8 Indication value communication line 10 1st power plant 20 2nd power plant 30 3rd power plant 40 Substation

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】複数の発電設備の並列運転で発生する電力
を需要地へ送電する複数の送電線と、これら各送電線に
接続して負荷へ電力を供給する複数の変電所とで構成し
ている電力系統において、 前記各発電設備の発電電力と電圧、前記各変電所の受電
電力と電圧、各発電設備及び各変電所と各送電線とを接
続する開閉器の接続状態と各送電線相互間を接続する開
閉器の接続状態、とを中央制御装置へ伝達するデータ通
信回線と、 前記データ通信回線を経て得られるデータを入力して、
前記各送電線に接続している各発電設備が出力する電圧
と周波数と電圧位相の指示値を演算する系統条件演算装
置を備えた中央制御装置と、 前記各発電設備と中央制御装置とへ周波数と電圧位相の
基準となる時刻を与える基準時計と、 前記系統条件演算装置が演算した前記指示値を前記送電
線に接続している各発電設備へ伝達する指示値通信回線
と、を備えていることを特徴とする電力系統制御装置。
1. A plurality of power transmission lines for transmitting power generated by parallel operation of a plurality of power generation facilities to a demand area, and a plurality of substations connected to these power transmission lines to supply power to a load. In the power system, the generated power and voltage of each power generation facility, the received power and voltage of each substation, the connection state of each power generation facility and the switch that connects each substation and each transmission line, and each transmission line The connection state of the switches connecting each other, and a data communication line for transmitting to and to the central control unit, and the data obtained via the data communication line are input,
A central control device equipped with a system condition computing device that computes a voltage output by each power generation facility connected to each power transmission line, a frequency, and an indication value of a voltage phase, and a frequency to each power generation facility and the central control device. And a reference clock for giving a time as a reference of the voltage phase, and an instruction value communication line for transmitting the instruction value calculated by the system condition calculation device to each power generation facility connected to the power transmission line. A power system control device characterized by the above.
【請求項2】複数の発電設備の並列運転で発生する電力
を需要地へ送電する複数の送電線と、これら各送電線に
接続して負荷へ電力を供給する複数の変電所とで構成し
ている電力系統において、 前記各発電設備の発電電力と電圧、前記各変電所の受電
電力と電圧、各発電設備及び各変電所と各送電線とを接
続する開閉器の接続状態と各送電線相互間を接続する開
閉器の接続状態、とを中央制御装置へ伝達するデータ通
信回線と、 前記データ通信回線を経て得られるデータを入力して、
前記各送電線に接続している各発電設備が出力する電圧
と周波数と電圧位相の指示値を演算する系統条件演算装
置を備えた中央制御装置と、 前記中央制御装置に設置して前記データ通信回線を経て
得られるデータを入力し、前記各送電線に接続する予定
の各発電設備が出力する電圧と周波数と電圧位相の指示
値を演算する系統条件変更演算装置と、 前記各発電設備と中央制御装置とへ周波数と電圧位相の
基準となる時刻を与える基準時計と、 前記系統条件演算装置と系統条件変更演算装置とが演算
した前記指示値を、前記送電線に接続している各発電設
備と送電線に接続する予定の各発電設備とへ伝達する指
示値通信回線と、を備えていることを特徴とする電力系
統制御装置。
2. A plurality of power transmission lines for transmitting power generated by parallel operation of a plurality of power generation facilities to a demand area, and a plurality of substations connected to these power transmission lines to supply power to a load. In the power system, the generated power and voltage of each power generation facility, the received power and voltage of each substation, the connection state of each power generation facility and the switch that connects each substation and each transmission line, and each transmission line The connection state of the switches connecting each other, and a data communication line for transmitting to and to the central control unit, and the data obtained via the data communication line are input,
A central control device equipped with a system condition computing device that computes voltage, frequency, and voltage phase indication values output by each power generation facility connected to each power transmission line; and the data communication installed in the central control device. Inputting data obtained through the line, a system condition change calculation device that calculates the voltage, frequency, and voltage phase instruction value output by each power generation facility that is to be connected to each transmission line, and each power generation facility and the central unit A reference clock that gives a time that is a reference of frequency and voltage phase to a control device, and the instruction value calculated by the system condition calculation device and the system condition change calculation device, and each power generation facility connected to the power transmission line. And an instruction value communication line for transmitting to each power generation facility to be connected to the power transmission line.
JP6210328A 1994-09-05 1994-09-05 Power system control device Pending JPH0879973A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6210328A JPH0879973A (en) 1994-09-05 1994-09-05 Power system control device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6210328A JPH0879973A (en) 1994-09-05 1994-09-05 Power system control device

Publications (1)

Publication Number Publication Date
JPH0879973A true JPH0879973A (en) 1996-03-22

Family

ID=16587607

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6210328A Pending JPH0879973A (en) 1994-09-05 1994-09-05 Power system control device

Country Status (1)

Country Link
JP (1) JPH0879973A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104917196A (en) * 2015-06-04 2015-09-16 重庆大学 Large-scale photovoltaic power plant power system low-frequency oscillation suppression controller design method
CN106033909A (en) * 2015-03-09 2016-10-19 国家电网公司 Testing system and testing method for safety and sensitivity of relay protection setting value

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106033909A (en) * 2015-03-09 2016-10-19 国家电网公司 Testing system and testing method for safety and sensitivity of relay protection setting value
CN104917196A (en) * 2015-06-04 2015-09-16 重庆大学 Large-scale photovoltaic power plant power system low-frequency oscillation suppression controller design method

Similar Documents

Publication Publication Date Title
EP0535631B1 (en) Power demand control
CN103595052A (en) Method for stably controlling switchover from micro-grid connection into island state
US5258652A (en) Distributed plant control system
JP3044640B2 (en) Monitoring and control system for voltage regulator
JPH0879973A (en) Power system control device
CA1098583A (en) Control installation for at least two hydraulic turbines
JPH11299110A (en) Counter power flow preventive device for private generation equipment
JP2000116195A (en) Power installation for consumer
KR100699352B1 (en) Electric power generating system for peak control and method thereof
CN219717945U (en) Island operation control device and power plant control system of self-contained power plant of industrial park
JPH0382337A (en) System stabilizing apparatus
JP2005261070A (en) Distributed power supply control device
JP7487633B2 (en) Distributed Power Systems and Power Conditioners
JP4062704B2 (en) Control method and control device for private power generation auxiliary generator
SU1427478A1 (en) Arrangement for coupling two power systems
JPH04275029A (en) Load interrupting device at time of parallel off fault
JPH06225459A (en) Controlling method for power of non-utility generator facility
US1159040A (en) Electrical distribution.
JP2557056B2 (en) Governor operation constant switching circuit
JP2645000B2 (en) Hydroelectric power plant load regulator
JPH0317567Y2 (en)
JPS599723A (en) Electric power control device
JP3669043B2 (en) Hydropower plant control equipment
JPH09117063A (en) Protective system for system interconnection
JPS60209694A (en) Air flow amount control device