JPH0853941A - Construction work method of unit floor - Google Patents

Construction work method of unit floor

Info

Publication number
JPH0853941A
JPH0853941A JP19057794A JP19057794A JPH0853941A JP H0853941 A JPH0853941 A JP H0853941A JP 19057794 A JP19057794 A JP 19057794A JP 19057794 A JP19057794 A JP 19057794A JP H0853941 A JPH0853941 A JP H0853941A
Authority
JP
Japan
Prior art keywords
unit floor
frame
floor
tower crane
stand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP19057794A
Other languages
Japanese (ja)
Inventor
Arata Furuta
新 古田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP19057794A priority Critical patent/JPH0853941A/en
Publication of JPH0853941A publication Critical patent/JPH0853941A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To further shorten a construction period by improving operation efficiency of a tower crane in construction work of a unit floor. CONSTITUTION:A unit floor 8 is temporarily fastened to a suspending frame 4 of a stand K. Next, an anchoring wire 10 of a suspending beam 9 fixed to the stand K is hooked on a hook 9 of a tower crane. The stand K is suspended as it is by the crane up to a floor height of a suspending purpose, and the stand K is supported with a large beam 1. Next, the crane is separated from the present stand K, and is successively installed on a previously used separate stand K, and goes to suspend the next unit floor. In parallel to this work, a unit floor 8 is suspended from the stand K arranged on the large beam 1, and while adjusting a position, installing' construction work is performed.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、タワークレーンを使用
したビル構築におけるユニットフロア取り付けのための
施工方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for mounting a unit floor in building construction using a tower crane.

【0002】[0002]

【従来の技術】ビルの地上部における躯体の建方には、
一般にタワークレーンが使用される。そして、ユニット
フロアは、柱や大梁が組まれた後に、タワークレーンで
直接,吊られて、所定フロア高さの大梁上まで搬送さ
れ、そのクレーンによる吊り込み状態を維持したままユ
ニットフロアの取り付けを行う。その取り付けが完了し
たら、台付けワイヤーを外してタワークレーンを解放
し、該タワークレーンは、再び、ストックヤードまで次
のユニットフロアを吊りに行く。これを繰り返しなが
ら、順次,ユニットフロアを目的の場所に取り付けてい
く。
2. Description of the Related Art To construct a skeleton in the aboveground part of a building,
Tower cranes are commonly used. After the pillars and girders have been assembled, the unit floor is directly hung by a tower crane and transported to the girder of a predetermined floor height, and the unit floor can be mounted while maintaining the suspended state by the crane. To do. When the installation is complete, remove the pedestal wire and release the tower crane, which again hangs the next unit floor to the stockyard. Repeating this process, the unit floor is attached to the desired location in sequence.

【0003】[0003]

【発明が解決しようとする課題】最近の高層ビルにおい
ては相当に工期短縮が図られており、1フロア当たり4
〜5日位のスピードで施工されている。このとき、タワ
ークレーンでは、一日当たり30ピース程度の取り付け
を実施するのが現状であるが、その内訳を調べてみる
と、部材に対する玉掛け→巻上→水平移動(起伏・旋
回)→部材取付け→巻下げの繰り返しによって実施され
る。この内、部材取付けに平均5〜10分程度かかって
いる。
In recent high-rise buildings, the construction period has been considerably shortened, and 4 floors per floor
It is being built at a speed of about 5 days. At this time, the tower crane is currently installed with about 30 pieces per day, but when examining the details, slinging on the member → hoisting → horizontal movement (undulation / swing) → member mounting → It is carried out by repeating the lowering. Of these, it takes about 5 to 10 minutes on average to attach the members.

【0004】部材の中でもユニットフロアは、柱や大梁
が組まれた後に設置するので、精度的にも調整を必要と
し、且つ、平面的にも大きいので取付けボルトが多い。
このため、ユニットフロアの取付け時間は、他の部材に
比べて多く掛かっている。しかしながら、上記従来のユ
ニットフロアの施工方法では、ユニットフロアを吊り上
げて、該ユニットフロアの取付けが完了するまで、タワ
ークレーンが該ユニットフロア取り付け作業に拘束され
ている。このため、タワークレーンの稼働効率が良くな
く、上記タワークレーンの拘束による単位時間当たりの
部材取付け数が制限されてしまう。
Among the members, the unit floor is installed after columns and girders are assembled, so that adjustment is required in terms of accuracy, and since it is large in plan view, it has many mounting bolts.
For this reason, the installation time of the unit floor is longer than that of other members. However, in the above-mentioned conventional method of constructing a unit floor, the tower crane is restrained by the unit floor mounting work until the unit floor is lifted and the mounting of the unit floor is completed. For this reason, the operating efficiency of the tower crane is not good, and the number of members to be attached per unit time is limited due to the restraint of the tower crane.

【0005】本発明は、上記のような問題点に着目して
なされたもので、ユニットフロアの施工におけるタワー
クレーンの稼働効率を向上させて、更なる工期短縮を図
ることを目的としている。
The present invention has been made in view of the above problems, and an object thereof is to improve the operating efficiency of a tower crane in the construction of a unit floor and to further shorten the construction period.

【0006】[0006]

【課題を解決するための手段】上記目的を達成するため
に、本発明のユニットフロアの施工方法は、梁に載置可
能な仮置きフレームと、該仮置きフレームから昇降可能
に吊り下げられていると共にユニットフロアを取付け可
能な吊りフレームとからなる架台を、少なくとも2台,
用意して、架台の吊りフレームにユニットフロアを取り
付けた後、タワークレーンで上記架台を吊り上げて所定
の大梁上に該架台を支持させたら、タワークレーンの台
付けを架台から外し、続いて、タワークレーンは、ユニ
ットフロアを外した別の架台を吊って次のユニットフロ
アを吊りにいくと共に、上記ユニットフロアを吊ってい
る架台は、吊りフレームを降下させ、取付け位置を調整
しながらユニットフロアを目的とする場所に取り付ける
ことを特徴としている。
In order to achieve the above object, in the method for constructing a unit floor of the present invention, a temporary placing frame that can be placed on a beam, and a suspending frame that can be lifted and lowered from the temporary placing frame. There are at least two racks, each of which has a suspension frame to which the unit floor can be attached.
After preparing and attaching the unit floor to the suspension frame of the gantry, hoisting the gantry by a tower crane and supporting the gantry on a predetermined girder, remove the tower crane from the gantry, and then the tower. The crane hangs another frame without the unit floor to hang the next unit floor, and the frame that hangs the above unit floor lowers the hanging frame and aims at the unit floor while adjusting the mounting position. The feature is that it is attached to the place where

【0007】[0007]

【作用】架台を介してユニットフロアを吊るので、該架
台を、対象とするフロア高さの大梁に支持させた後は、
クレーンをユニットフロアから切り離すことが可能とな
る。そして、該タワークレーンは、別のユニットフロア
を吊り上げにいくことが可能となる。
[Operation] Since the unit floor is hung from the pedestal, after the pedestal is supported by the girder of the target floor height,
It is possible to disconnect the crane from the unit floor. Then, the tower crane can lift another unit floor.

【0008】即ち、大梁に架台を支持させてタワークレ
ーンを架台から切り離した後は、大梁に支持されている
仮置きフレームから、吊りフレームを介してユニットフ
ロアを吊り下げ所定の場所に位置調整をしながら該ユニ
ットフロアを取り付ける。そして、上記ユニットフロア
の取り付け作業と並行して、先にユニットフロアを所定
のフロア高さまで搬送して取り付けるために使用した別
の架台をタワークレーンに取り付け、該架台を吊り込ん
で、次のユニットフロアを吊りに行く。
That is, after the gantry is supported by the girder and the tower crane is separated from the gantry, the unit floor is hung from the temporary placing frame supported by the girder via the hoisting frame to adjust the position to a predetermined place. While installing the unit floor. Then, in parallel with the above-mentioned work for mounting the unit floor, another mount that was used for transporting and mounting the unit floor to a predetermined floor height was mounted on the tower crane, the mount was suspended, and the next unit was suspended. Go to hang the floor.

【0009】これによって、タワークレーンによるユニ
ットフロアの搬送サイクルが短縮される。
As a result, the transportation cycle of the unit floor by the tower crane is shortened.

【0010】[0010]

【実施例】本発明の実施例を図面をもとに説明する。ま
ず、ユニットフロアを吊り込むための架台Kについて説
明すると、図1及び図2に示すように、大梁1に載置可
能な仮置きフレーム2と、本体が該仮置きフレーム2に
固定されたホイスト3と、そのホイスト3のワイヤロー
プ3aを介して上記仮置きフレーム2に吊り下げられて
いる吊りフレーム4と、から構成されている。
Embodiments of the present invention will be described with reference to the drawings. First, the pedestal K for suspending the unit floor will be described. As shown in FIGS. 1 and 2, a temporary placement frame 2 that can be placed on the girder 1 and a hoist whose main body is fixed to the temporary placement frame 2. 3 and a suspension frame 4 suspended from the temporary placement frame 2 via the wire rope 3a of the hoist 3.

【0011】上記仮置きフレーム2は、左右に並んで配
設された2本の大梁1間に跨がって載置可能となってい
て、矩形状の枠体からなるフレーム本体2aが水平に配
置され、そのフレーム本体2aの四隅から、軸を上下に
向けた支持柱2bが、それぞれ大梁に向けて延びて構成
されている。その4本の支持柱2bの下端部には、それ
ぞれ各大梁1上面に当接可能な着座プレート2cが設け
られ、該着座プレート2cには、該大梁1上面から突出
しているダボピン6を挿通可能なダボ孔2dが開設され
ている。
The temporary placement frame 2 can be placed so as to straddle two girders 1 arranged side by side, and a frame body 2a consisting of a rectangular frame is horizontally placed. Support pillars 2b, which are arranged and whose axes are oriented vertically, are configured to extend from the four corners of the frame body 2a toward the girder. Seating plates 2c capable of contacting the upper surfaces of the girders 1 are provided at the lower ends of the four support columns 2b, and the dowel pins 6 protruding from the upper surface of the girders 1 can be inserted into the seating plates 2c. A dowel hole 2d is formed.

【0012】また、上記仮置きフレーム2のフレーム本
体2aの中央下端部には、ホイスト3の本体が固定さ
れ、該ホイスト3のワイヤロープ3a先端部の先端部
に、台付けワイヤ7を介して、吊りフレーム4が水平状
態で昇降可能に吊り下げられている。該吊りフレーム4
は、平面視、取り付けるユニットフロア8とほぼ同じ大
きさの枠体を備えている。
Further, the main body of the hoist 3 is fixed to the central lower end of the frame main body 2a of the temporary placing frame 2, and the tip of the wire rope 3a of the hoist 3 is attached to the front end of the hoist 3 via the mounting wire 7. The suspension frame 4 is suspended in a horizontal state so that it can be raised and lowered. The hanging frame 4
Is provided with a frame body having substantially the same size as the unit floor 8 to be mounted in plan view.

【0013】また、該仮置きフレーム2のフレーム本体
2aの中央部には、吊りビーム9がボルト止めされ、該
吊りビーム9には、タワークレーンのフック10に引っ
かける台付けワイヤ11が設けられている。そして、上
記構成の架台Kを2台,用意しておく。次に、上記架台
K、及びタワークレーンを使用したユニットフロア8の
施工を説明する。
A suspension beam 9 is bolted to the central portion of the frame body 2a of the temporary frame 2, and a suspension wire 11 for hooking on a hook 10 of a tower crane is provided on the suspension beam 9. There is. Then, two pedestals K having the above configuration are prepared. Next, the construction of the unit floor 8 using the gantry K and the tower crane will be described.

【0014】まず、架台Kの吊りフレーム4に対してユ
ニットフロア8をワイヤで玉掛けしたりボルト等で仮止
めする。次に、架台Kに吊りビーム9をボルト止めする
と共に、該吊りビーム9の台付けワイヤ10をタワーク
レーンのフック9に引っかける。そのまま、クレーンに
よって、吊りビーム9及び架台Kを介してユニットフロ
ア8を吊り込み、既に組み立てられた大梁1における目
的のフロア高さまで吊り上げる。
First, the unit floor 8 is hung on the suspension frame 4 of the pedestal K with a wire or temporarily fixed with a bolt or the like. Next, the suspension beam 9 is bolted to the pedestal K, and the mounting wire 10 of the suspension beam 9 is hooked on the hook 9 of the tower crane. As it is, the unit floor 8 is hung by the crane through the hanging beam 9 and the pedestal K, and is lifted to the target floor height of the girder 1 already assembled.

【0015】目的の大梁1まで吊り上げたら、架台Kを
吊り下げて、各支持柱2bの着座プレート2cを大梁1
上の載置する。このとき、該着座プレート2cに開設さ
れたダボ孔2d内に、大梁1から突出しているダボピン
6が挿通されるようにする。これによって、架台Kが大
梁1に支持される。次に、ボルトを外して吊りビーム9
を現在の架台Kから外し、続けて、該吊りビーム9を、
先にユニットフロア8吊り上げに使用されて大梁1上に
載置されている別の架台Kに取り付ける。
After hoisting up to the desired girder 1, the pedestal K is hung and the seating plates 2c of the support columns 2b are hung up.
Place on top. At this time, the dowel pin 6 protruding from the girder 1 is inserted into the dowel hole 2d formed in the seating plate 2c. As a result, the gantry K is supported by the girder 1. Next, remove the bolts and suspend the beam 9.
From the current pedestal K, and then the suspension beam 9
First, it is attached to another mount K used for lifting the unit floor 8 and placed on the girder 1.

【0016】そして、吊りビーム9を介して別の架台K
を吊り上げることで、その別の架台Kを大梁1から外
す。さらに、ストックヤードまで吊り下げ、該架台Kを
使用して次のユニットフロア8を吊り込み、次のユニッ
トフロア8を目的のフロア高さまで吊り上げる。上記タ
ワークレーンにおける次のユニットフロア8を吊り込む
作業の間に、上記大梁1に設置した架台Kにおいては、
ホイスト3を作動させて吊りフレーム4及びユニットフ
ロア8を吊り下げ、ユニットフロア8における左右方向
等の位置調整をしながら、該ユニットフロア8を小梁等
にボルト止めする等して取り付けの施工を行う。
Then, another pedestal K is attached via the suspension beam 9.
Then, the other mount K is removed from the girder 1. Further, it is hung up to the stock yard, the next unit floor 8 is hung up using the pedestal K, and the next unit floor 8 is hung up to the target floor height. During the work of suspending the next unit floor 8 in the tower crane, in the mount K installed on the girder 1,
The hoist 3 is operated to suspend the suspension frame 4 and the unit floor 8, and while adjusting the position of the unit floor 8 in the left-right direction, the unit floor 8 is bolted to a beam or the like for installation work. To do.

【0017】以上のサイクルを繰り返しながら、順次,
ユニットフロア8を図4に示すように、組み付けてい
く。なお、図中、11は柱を、12は小梁をそれぞれ示
している。このように、本実施例では、他の部材よりも
時間の掛かる、ユニットフロア8の取り付け作業を実施
するときには、タワークレーンが解放されて、次のユニ
ットフロア8の吊り込みにいくことが可能となる。これ
によって、タワークレーンの稼働効率が向上して、ユニ
ットフロア8の施工作業の効率が向上し、もって、ビル
構築の工期が更に短縮可能となる。
While repeating the above cycle,
The unit floor 8 is assembled as shown in FIG. In the figure, 11 is a pillar and 12 is a beam. As described above, in the present embodiment, when the unit floor 8 mounting work, which takes more time than other members, is performed, the tower crane is released and the next unit floor 8 can be suspended. Become. As a result, the operating efficiency of the tower crane is improved, the efficiency of the construction work of the unit floor 8 is improved, and the construction period of the building can be further shortened.

【0018】なお、上記実施例では、吊りビーム9を架
台Kに着脱可能に取り付け、該吊りビーム9を介して架
台Kをタワークレーンで吊り込む構成としているが、各
架台Kにそれぞれ吊りビーム9を固定しておいて、タワ
ークレーンのフック9を各吊りビーム9の台付けワイヤ
に引っかけたり外したりして吊る架台Kを代えるように
してもよい。
In the above embodiment, the suspension beam 9 is detachably attached to the pedestal K, and the pedestal K is hung by the tower crane via the suspension beam 9. However, the suspension beam 9 is attached to each pedestal K respectively. May be fixed, and the pedestal K to be hung may be replaced by hooking or removing the hook 9 of the tower crane from the mounting wire of each suspension beam 9.

【0019】[0019]

【発明の効果】以上説明してきたように、本発明のユニ
ットフロア施工方法では、時間が掛かる,大梁上でのユ
ニットフロアの取付け作業の際には、タワークレーン
は、そのユニットフロアから解放されて、次のユニット
フロアを吊り込みに行けるので、ユニットフロアの施工
の際におけるタワークレーンの稼働効率が向上して、ユ
ニットフロアの施工のための工期が短縮し、もって全体
としてのビル構築のための工期が短縮するという効果が
ある。
As described above, in the unit floor construction method of the present invention, the tower crane is released from the unit floor during the time-consuming installation work of the unit floor on the girder. Since the next unit floor can be hung up, the operating efficiency of the tower crane at the time of construction of the unit floor is improved, the construction period for the construction of the unit floor is shortened, and thus the construction of the building as a whole This has the effect of shortening the construction period.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る実施例の架台,及び大梁上への支
持状態を示す側面図である。
FIG. 1 is a side view showing a pedestal of an embodiment according to the present invention and a supporting state on a girder.

【図2】本発明に係る実施例の架台,及び大梁上への支
持状態を示す平面図である。
FIG. 2 is a plan view showing a pedestal of an embodiment according to the present invention and a state of being supported on a girder.

【図3】本発明に係る実施例の着座プレートを示す図で
ある。
FIG. 3 is a view showing a seating plate of an embodiment according to the present invention.

【図4】所定フロア高さにおけるユニットフロアの取り
付け完了状態を示す図である。
FIG. 4 is a view showing a state where the unit floor is completely attached at a predetermined floor height.

【符号の説明】[Explanation of symbols]

K 架台 1 大梁 2 仮置きフレーム 3 ホイスト 4 吊りフレーム 6 ダボピン 9 タワークレーンのフック 11 柱 K frame 1 Girder 2 Temporary frame 3 Hoist 4 Lifting frame 6 Dowel pin 9 Tower crane hook 11 Pillar

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 梁に載置可能な仮置きフレームと、該仮
置きフレームから昇降可能に吊り下げられていると共に
ユニットフロアを取付け可能な吊りフレームとからなる
架台を、少なくとも2台,用意して、架台の吊りフレー
ムにユニットフロアを取り付けた後、タワークレーンで
上記架台を吊り上げて所定の大梁上に該架台を支持させ
たら、タワークレーンの台付けを架台から外し、続い
て、タワークレーンは、ユニットフロアを外した別の架
台を吊って次のユニットフロアを吊りにいくと共に、上
記ユニットフロアを吊っている架台は、吊りフレームを
降下させ、取付け位置を調整しながらユニットフロアを
目的とする場所に取り付けることを特徴とするユニット
フロアの施工方法。
1. At least two racks each comprising a temporary frame that can be placed on a beam and a hanging frame that can be lifted up and down from the temporary frame and to which a unit floor can be attached are prepared. Then, after mounting the unit floor on the suspension frame of the frame, lift the frame with a tower crane and support the frame on a specified girder, remove the tower crane from the frame, and then , Another unit without the unit floor is hung to hang the next unit floor, and the pedestal that hangs the unit floor is designed to be the unit floor while lowering the hanging frame and adjusting the mounting position. Installation method of the unit floor, which is characterized by being installed in a place.
JP19057794A 1994-08-12 1994-08-12 Construction work method of unit floor Pending JPH0853941A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP19057794A JPH0853941A (en) 1994-08-12 1994-08-12 Construction work method of unit floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP19057794A JPH0853941A (en) 1994-08-12 1994-08-12 Construction work method of unit floor

Publications (1)

Publication Number Publication Date
JPH0853941A true JPH0853941A (en) 1996-02-27

Family

ID=16260380

Family Applications (1)

Application Number Title Priority Date Filing Date
JP19057794A Pending JPH0853941A (en) 1994-08-12 1994-08-12 Construction work method of unit floor

Country Status (1)

Country Link
JP (1) JPH0853941A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727109A (en) * 2020-12-22 2021-04-30 福州建工(集团)总公司 Construction process for mounting laminated slab by matching laminated slab mounting trolley with tower crane
CN113089453A (en) * 2021-04-09 2021-07-09 中铁三局集团有限公司 Inverted arch trestle capable of being freely adjusted

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727109A (en) * 2020-12-22 2021-04-30 福州建工(集团)总公司 Construction process for mounting laminated slab by matching laminated slab mounting trolley with tower crane
CN112727109B (en) * 2020-12-22 2022-10-11 福州建工(集团)总公司 Construction process for mounting laminated slab by matching laminated slab mounting trolley with tower crane
CN113089453A (en) * 2021-04-09 2021-07-09 中铁三局集团有限公司 Inverted arch trestle capable of being freely adjusted

Similar Documents

Publication Publication Date Title
CN111960249A (en) Laminated slab lifting appliance and steel beam
CN107130517B (en) It is a kind of fine-tuning from promotion closure mould bases base apparatus and its operating method
JPH0853941A (en) Construction work method of unit floor
JPH0220354Y2 (en)
JP2001115422A (en) Dismantling method of supporting for form fixed to concrete slab
CN203127986U (en) Adjustable lifting tool for T joist steel formwork of high-speed rail
CN101723240B (en) Special fixture for hoisting rectangular section steel column and hoisting method by using same
CN114835003A (en) Device and hoisting method suitable for balanced hoisting of large and medium-sized space prefabricated unit parts
JPH092774A (en) Heavy object suspending device
JP3073155B2 (en) How to set product groups for construction buildings
CN218371212U (en) Hoisting tool for web steel bars and top plate steel bars at bottom of box girder
CN220267143U (en) Super high-rise corridor furred ceiling construction structures
JP3297196B2 (en) Composite balance and method for loading heavy objects using composite balance
JP2937683B2 (en) Precast slab construction method in suspended slab bridge construction method and jig used for the construction method
JP3658572B2 (en) Load lifting jig for long members
CN218117153U (en) Elevator shaft operating platform
CN209758835U (en) Bridge T roof beam template hoist
JP3004731U (en) Multi-point hanging jig
CN209538714U (en) A kind of bracket device for overhanging unloading platform
JPS6019101Y2 (en) eye plate
JP2000274080A (en) Wall member fitting method for building skeleton and wall member fitting traverser
JPH07157274A (en) Hanging jig for alc plate
JPH02300081A (en) Installation work method for elevator
JPH0648046Y2 (en) Unit for piping
JP3811419B2 (en) Building material lifting device and building material lifting method