JPH082528B2 - Concrete board manufacturing method - Google Patents

Concrete board manufacturing method

Info

Publication number
JPH082528B2
JPH082528B2 JP63226476A JP22647688A JPH082528B2 JP H082528 B2 JPH082528 B2 JP H082528B2 JP 63226476 A JP63226476 A JP 63226476A JP 22647688 A JP22647688 A JP 22647688A JP H082528 B2 JPH082528 B2 JP H082528B2
Authority
JP
Japan
Prior art keywords
work
board
floor plan
work sheet
sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP63226476A
Other languages
Japanese (ja)
Other versions
JPH0274307A (en
Inventor
康文 飛嶋
Original Assignee
日本カイザー株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 日本カイザー株式会社 filed Critical 日本カイザー株式会社
Priority to JP63226476A priority Critical patent/JPH082528B2/en
Publication of JPH0274307A publication Critical patent/JPH0274307A/en
Publication of JPH082528B2 publication Critical patent/JPH082528B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は床板、壁板又は天板等の建築構造物に使用さ
れるプレキャストコンクリート板(以下PC板と言う)等
のコンクリート板の製造方法に関する。
The present invention relates to a method for producing a concrete plate such as a precast concrete plate (hereinafter referred to as a PC plate) used in a building structure such as a floor plate, a wall plate or a ceiling plate. Regarding

(従来の技術) マンションや事務所用ビルディング等の鉄筋コンクリ
ート建築物では、建築現場の作業能率の向上のために予
め工場で製造するPC板を多く使用している。このPC板に
は、電気配線や通信ケーブルや上下水道管などを取付す
るための支持部材(以下先付部品と言う)がその一部を
露出させてPC板に一体に埋設されている。
(Prior Art) In reinforced concrete buildings such as condominiums and office buildings, many PC boards manufactured in advance in factories are used to improve work efficiency at construction sites. In this PC board, a supporting member for attaching electric wiring, communication cables, water and sewer pipes, etc. (hereinafter referred to as "preliminary parts") is partially embedded in the PC board with its part exposed.

このPC板を各階の間取りに合わせて製造するのである
が、その間取りにおける炊事場やお風呂場の水回り又は
事務所用の照明器具や電気機器などの取付位置などは同
階のフロアー横方向には異なるものの、上下各階では同
じであることが多い。
This PC board is manufactured according to the floor plan of each floor, but the layout of the water around the kitchen or bathroom in the floor plan, or the installation position of lighting equipment and electrical equipment for offices, etc., is the horizontal direction of the floor on the same floor. Although different, it is often the same on each floor.

この様な場合に、ある間取りにつき上下各階に必要な
分だけ予めPC板を製造してしまえば、生産能率が向上す
るが、実際には所定階の各間取り用PC板を夫々設置し、
建築作業場を確保しながら、上階へと工事を進めるもの
なので、予め製造したPC板をそれが必要となるまで保管
して置く保管場所が必要になるという問題があった。
In such a case, if PC boards are manufactured in advance for each floor plan required for each floor, the production efficiency will improve, but in reality, each floor plan PC board for each floor will be installed,
Since we are going to work on the upper floor while securing a construction workshop, there was a problem that we needed a storage place to store the PC board manufactured in advance until it was needed.

そこで、従来は次の様にPC板を製造していた。これを
第5図ないし第6図を参照しながら説明すると、所定階
のフロアーの各間取り(ア),(イ),(ウ)…用のPC
板を製造するには、 (a)まず間取り(ア)9の形状に合わせて型枠を原寸
大で組立る、 (b)設計図面より間取り(ア)9の先付部品の取付位
置を原寸寸法で型枠基板へ墨で書き写す(以下墨出しと
言う)、 (c)先付部品を型枠基板の取付位置に設置する、 (d)鉄筋を配筋する、 (e)コンクリートを打設する、 (f)打設コンクリート養生後脱型させる、 以上の様にして間取り(ア)9用のPC板を完成させ
る。
Therefore, conventionally, the PC board was manufactured as follows. Explaining this with reference to FIGS. 5 to 6, a PC for each floor plan (a), (a), (c) ... of a predetermined floor.
In order to manufacture the board, (a) first assemble the formwork in the original size according to the shape of the floor plan (a) 9, (b) from the design drawing, the mounting position of the front end part of the floor plan (a) 9 is the original size. The size is used to write in black on the form board (hereinafter referred to as “inking out”), (c) the pre-attached parts are installed at the mounting positions of the form board, (d) the reinforcing bars are reinforced, and (e) concrete is placed (F) After curing the cast concrete, it is demolded, and the PC board for floor plan (a) 9 is completed as described above.

そしてこの後、間取り(イ)の形状に合わせて型枠を
組立て直し、上記作業手順(b)ないし(f)を同様に
行なうことにより間取り(イ)用のPC板を完成させ、以
降間取り(ウ)ないし間取り(カ)用のPC板を同手順で
製造する。この後、これらPC板を建築現場へ運搬してク
レーンで設置する。
Then, after that, the mold is reassembled according to the shape of the floor plan (a), and the above-described work steps (b) to (f) are similarly performed to complete the PC board for the floor plan (a). C) PC boards for floor plan (f) are manufactured in the same procedure. After that, these PC boards are transported to the construction site and installed by a crane.

更に建築工事が進み上階に致ると、前記所定階と同じ
間取り(ア),(イ),…である各上階毎に上述した間
取り(ア),(イ),…用のPC板製造手順を繰り返すこ
とによりPC板を製造し、このPC板を建築現場へ運搬しク
レーンで持ち上げて設置し、建築物を順次上階へと完成
させて行くものであった。
When the construction work further progresses and reaches the upper floor, the above-mentioned floor plans (A), (A), ... The above-mentioned floor plans (A), (B), ... A PC board was manufactured by repeating the manufacturing procedure, the PC board was transported to a construction site, lifted by a crane and installed, and the buildings were sequentially completed on the upper floors.

(発明が解決しようとする課題) しかしながら上述した従来のPC板等のコンクリート板
製造方法では、所定の間取り形状にした型枠を組立後に
先付部品の取付位置を型枠基板上に墨で書き写す墨出し
作業があり、設計図面から寸法を読み取りながら先付部
品取付位置を写し取るために、この墨出し作業は多大な
時間がかかった。
(Problems to be solved by the invention) However, in the above-described conventional method for manufacturing a concrete board such as a PC board, the mounting position of the pre-attached component is copied in black on the form board after assembling the form frame having a predetermined floor plan shape. There is a marking work, and this marking work took a lot of time because the mounting position of the leading component was copied while reading the dimensions from the design drawing.

しかも異なる間取り毎に墨出し作業をするために、先
付部品取付寸法の読み取り及び書き写しに間違いが発生
しやすかった。
In addition, since the marking work is performed for each different floor plan, it is easy to make an error in reading and copying the mounting dimensions of the leading component.

更に建築工事が進み上階に致ると、各上階毎に間取り
の異なるPC板製造の際は上記墨出し作業を繰り返し行な
ければならず、その墨出し作業時間は多大となりかつ墨
出し作業ミスも増々多くなるという問題があった。
If the construction work progresses further and reaches the upper floor, the above marking work must be repeated when manufacturing PC boards with different floor plans for each upper floor, and the marking time will be great and the marking work There was a problem that mistakes increased more and more.

本発明は、このような問題に鑑みてなされたものであ
り、墨出し作業時間を短縮してPC板等のコンクリート板
の生産性向上を図り、かつ墨出し作業ミスを軽減するこ
とを目的としたPC板等のコンクリート板の製造方法を提
供するものである。
The present invention has been made in view of such a problem, and aims at improving productivity of concrete boards such as PC boards by shortening the staking out work time, and reducing the stakeout work mistakes. The present invention provides a method for producing a concrete board such as a PC board.

(課題を達成するための手段) 以上の目的を達成するための本発明の手段は、建物の
複数階に亘って共通な間取りの実寸外形状にした合成樹
脂製の可撓性シートの表面に、先付部品の取付位置を原
寸寸法で記載すると共に、前記先付け部品の取付位置に
先付け部品の種類に応じて異なる形状の孔を穿設し、該
可撓性シートの一部に各間取り用の識別記号を付与し
て、これを不使用時には全体を丸めて収納可能な作業シ
ートになさしめ、該作業シートを同じ間取りの実寸外形
状に組み立てた型枠の基板に載置し、前記先付部品の取
付位置及び孔形状をマーキング材で前記基材に写し取
り、前記作業シートを型枠より外した後、前記基板の上
に写し取られた先付部品取付位置で、かつ、マーキング
された孔の形状に応じた種類の先付部品を設置したの
ち、鉄筋を配筋するなどしてコンクリートを打設し、打
設コンクリート養生後脱型させて形成することを特徴と
してなるコンクリートの製造方法に存する。
(Means for Achieving the Object) The means for achieving the above-mentioned object of the present invention is that the surface of a flexible sheet made of synthetic resin, which has a floor plan common to a plurality of floors of a building, is formed into an actual size outside shape. , The attachment position of the pre-attached component is described in full size, and holes of different shapes are bored at the attachment position of the pre-attached component depending on the type of the pre-attached component, and a part of the flexible sheet for each floor plan When it is not in use, it is rolled up into a work sheet that can be stored, and the work sheet is placed on the base plate of a form frame assembled to the actual size outside shape with the same floor plan. The mounting position and the hole shape of the attached component are copied on the base material with a marking material, the work sheet is removed from the mold, and then the attached component is attached on the substrate and marked with the attached component. Installed the type of pre-installed parts according to the shape of the hole After that, a concrete manufacturing method is characterized in that concrete is placed by arranging reinforcing bars, and the cast concrete is cured and then demolded.

(作用) 而して上記製造方法によれば、各間取りに適合する作
業シートを夫々用意し、所定形状に型枠を組立て、所定
形状の作業シートを型枠の基板に載置し、該作業シート
に記載された先付部品の取付位置を墨、チョーク等のマ
ーキング材で前記基板に写し取る。このとき、基板上に
写し取られた孔形状は、先付部品の種類に応じた形状で
あるので、一見しただけで複数の先付部品のうち同種類
の先付部品がどこに配置されるかが判るのである。更
に、全体を丸めて作業シートを狭いスペースに収納・保
管できると共に、異種の間取り用の各作業シートに各々
識別記号が付与されているので、管理が容易で所望の作
業シートを保管場所から正確にして素早く取り出して使
用することができる。
(Operation) According to the above manufacturing method, therefore, work sheets suitable for each floor plan are prepared respectively, the mold is assembled into a predetermined shape, the work sheet having the predetermined shape is placed on the substrate of the mold, and the work is performed. The mounting position of the prefabricated component described on the sheet is copied onto the substrate with a marking material such as black ink or chalk. At this time, since the hole shape copied on the board is a shape corresponding to the type of the pre-attached component, at a glance, where is the pre-attached component of the same type among the plurality of pre-attached components arranged? Is understood. Furthermore, the whole work sheet can be rolled up and stored and stored in a narrow space, and since each work sheet for different floor plans has an identification symbol, it is easy to manage and the desired work sheet can be stored accurately from the storage location. It can be quickly taken out and used.

次に作業シートを型枠より取り外し、型枠基板上に写
し取られた先付部品取付位置に先付部品を設置する。
Next, the work sheet is removed from the formwork, and the prefabricated part is installed at the prefabricated part mounting position copied on the formwork substrate.

そして、鉄筋を配筋するなどしてコンクリートを打設
し、打設コンクリート養生後脱型させてPC板等のコンク
リート板を完成する。型枠より取り外した作業シートは
可撓性シートなので、次回に使用するまで、該作業シー
トを折り畳み又は丸めて保管しておく。
Then, concrete is poured by arranging the reinforcing bars, and after the concrete is cured, the concrete is finished by removing the mold. Since the work sheet removed from the mold is a flexible sheet, the work sheet is folded or rolled and stored until the next use.

そして、さらに上階に建築工事が進みその階の各間取
り用のPC板等のコンクリート板を製造するときに、前記
作業シートをその保管場所より運び出して上述の様に型
枠基板上に載置して使用する。
Then, when the construction work further progresses to the upper floor and the concrete board such as the PC board for each floor plan on that floor is manufactured, the work sheet is carried out from the storage place and placed on the formwork board as described above. To use.

(実施例) 本発明に係る実施例を第1図ないし第4図及び第6図
により説明する。
(Embodiment) An embodiment according to the present invention will be described with reference to FIGS. 1 to 4 and 6.

1は間取り(ア)9に使用する作業シートである。該
作業シート1は塩化ビニールからなる可撓性シートであ
り、その形状は間取り(ア)9と同じ形状で原寸大の大
きさである。
Reference numeral 1 is a work sheet used for the floor plan (a) 9. The work sheet 1 is a flexible sheet made of vinyl chloride, and has the same shape as the floor plan (a) 9 and the size of the original size.

そしてこの作業シート1の表面に、先付部品2の取付
位置を原寸寸法L2,L4…で記載する。
Then, on the surface of the work sheet 1, the attachment position of the pre-attached component 2 is described by the original dimensions L 2 , L 4 ...

その取付位置に孔3,4,5を設ける。孔3はインサート
部品6を取付る位置を示し、孔4はスリーブ7を取付る
位置を示し、孔5は電気ボックス(図示せず)を取付る
位置を示す。取付位置の孔3は丸形、孔4は四角形とい
うように孔形状が異なるのは取付る先付部品2が異なる
ことを一目瞭然に判別するためである。又、同じ孔形状
には同種の先付部品2を取付ることを示すものである。
8は識別記号であり、間取り(ア)9用の作業用シート
であることを示すもので、作業シート1の保管運用上の
便宜のために記載したものである。この様にして、他の
間取り(イ),(ウ)…用の作業シート(図示せず)も
予め作っておく。
Holes 3, 4, and 5 are provided at the mounting position. The hole 3 shows a position for mounting the insert part 6, the hole 4 shows a position for mounting the sleeve 7, and the hole 5 shows a position for mounting an electric box (not shown). The holes 3 at the mounting position have different shapes such as a round shape and the holes 4 have a quadrangular shape for the purpose of clearly discriminating different mounting parts 2 to be mounted. Further, it shows that the same type of pre-attached component 2 is attached to the same hole shape.
Reference numeral 8 denotes an identification symbol, which indicates that it is a work sheet for the floor plan (a) 9, and is described for the convenience of storage and operation of the work sheet 1. In this way, work sheets (not shown) for the other floor plans (a), (c) ... Are also prepared in advance.

次に、PC板10の製造手順を説明する。 Next, a procedure for manufacturing the PC board 10 will be described.

間取り(ア)9の型枠11を組立てる。この型枠11の基
板12に向きを合わせて予め作ってある作業シート1を設
置する。そして、作業シート1が浮き上ったりしないよ
うに適宜な重し(図示せず)を作業シート1上へ数ケ所
に置く。
Assemble the formwork 11 of the floor plan (A) 9. The work sheet 1 made in advance is installed by aligning it with the substrate 12 of the frame 11. Then, appropriate weights (not shown) are placed on the work sheet 1 at several places so that the work sheet 1 does not float up.

次に、作業シート1に設けられた孔3,4,5の形状に沿
ってチョークでなぞり、前期基板12上に印を付ける。そ
して、作業シート1を型枠11より取り外す。そして次に
使用するまで作業シート1を小さく丸めて保管してお
く。
Then, a chalk is traced along the shapes of the holes 3, 4, and 5 provided in the work sheet 1 to make a mark on the substrate 12 of the previous period. Then, the work sheet 1 is removed from the form 11. Then, the work sheet 1 is rolled into small pieces and stored until the next use.

次に丸形の孔3にはインサート部品6,四角形の孔4に
はスリーブ7,孔5には電気ボックス(図示せず)という
ように基板12上の印の形に従い先付部品2を基板12上に
設置する。そして、トラス筋13及び鉄筋14を配筋する。
Next, insert part 6 is inserted into round hole 3, sleeve 7 is inserted into square hole 4, and electric box (not shown) is inserted into hole 5. Install on top of 12. Then, the truss bars 13 and the reinforcing bars 14 are arranged.

その後形枠11内にコンクリート15を打設し、コンクリ
ート15養生後脱型し、間取り(ア)用のPC板10を完成さ
せる。
After that, concrete 15 is placed in the form frame 11, the concrete 15 is cured and then demolded to complete the PC board 10 for the floor plan (a).

そして、間取り(イ),(ウ)…用のPC板を、前述の
予め作った作業シート(図示せず)を使用して上記PC板
製造手順と同様にして製造する。
Then, a PC board for the floor plans (a), (c) ... is manufactured in the same manner as the PC board manufacturing procedure using the above-described work sheet (not shown) made in advance.

更に各上階毎に前記同様のPC板製造手順を繰り返すも
のである。
Furthermore, the same PC board manufacturing procedure as described above is repeated for each upper floor.

この様にして試験的に実施したところ従来一つの型枠
において墨出し作業に通常約30〜60分間くらいの時間を
必要としたが、作業シートを使用することにより前記墨
出し作業時間は約1〜2分間くらいとなり大幅に短縮さ
れた。しかも、作業シートの孔位置をマーキングするだ
けなので、作業ミスはほとんどなくなった。
As a result of carrying out a test in this way, conventionally, it took about 30 to 60 minutes to carry out the marking-out work in one mold, but the use of a work sheet reduces the marking-out work time to about 1 minute. It was about 2 minutes, which was a great reduction. Moreover, since the hole positions on the work sheet are only marked, there are almost no mistakes in work.

以上説明したが、上記実施例において、作業シートの
材質は取扱いやすい可撓性のものであれば特に限定する
ものではなく、さらに言えば塩化ビニールやポリプロピ
レン等の合成樹脂材料が好ましい。
As described above, in the above embodiment, the material of the work sheet is not particularly limited as long as it is flexible and easy to handle, and more specifically, a synthetic resin material such as vinyl chloride or polypropylene is preferable.

また、先付部品取付位置を示すために、上述した実施
例では作業シート上に丸形や四角形の孔を設けたが、適
宜なマーキング手段で作業シートに記載された先付部品
取付位置が型枠基板上に写し取られれば良いので、前記
孔を設けるかわりに転写手段や圧接手段等の手段で先付
部品取付位置の表示方法を適宜変更できるのはもちろん
である。
Further, in order to show the mounting position of the pre-attached component, in the above-mentioned embodiment, the circular or quadrangular hole is provided on the work sheet, but the attachment position of the pre-attached component described on the work sheet is marked by an appropriate marking means. Since it suffices to be copied on the frame substrate, it is needless to say that the display method of the mounting position of the leading component can be appropriately changed by means such as transfer means or pressure contact means instead of providing the holes.

(発明の効果) 本発明によれば、PC板等のコンクリート板を製造する
上で、先付部品取付位置を示す作業シートを予め作りこ
の作業シートで先付部品取付位置を型枠基板にマーキン
グするだけなので、従来の墨出し作業に比較し、その作
業時間が大幅に短縮されてPC板等のコンクリート板の生
産性が大きく向上し、 かつ、作業シート使用により図面から寸法を読み取る
必要がなくなり作業ミスが大幅に軽減されるという効果
があり、基板上に写し取られた孔形状は、先付部品の種
類に応じた形状であるので、一見しただけで複数の先付
部品のうち同種類の先付部品がどこに配置されるかが判
って、先付部品の設置作業が容易かつ工期短縮となり、 更に作業シートは可撓性シートにしたので運搬や保管
が極めて容易となり、何回でも作業シートを使用できる
のでPC板等のコンクリート板の生産性の向上や作業ミス
の軽減に著しい効果がある。
(Effects of the Invention) According to the present invention, in manufacturing a concrete plate such as a PC plate, a work sheet indicating a mounting position of a leading component is made in advance and the mounting position of the leading component is marked on the formwork substrate with this working sheet. Compared with conventional marking work, the work time is greatly shortened, the productivity of concrete boards such as PC boards is greatly improved, and it is not necessary to read the dimensions from the drawing by using the work sheet. It has the effect of significantly reducing work mistakes, and the hole shape copied on the board is a shape that corresponds to the type of pre-attached parts, so at first glance it is possible to select the same type among multiple pre-attached parts. By knowing where the pre-mounted parts are placed, the work of installing the pre-mounted parts is easy and the construction period is shortened. In addition, since the work sheet is a flexible sheet, it is extremely easy to transport and store, and the work can be performed many times. Sheet Since it can be used, it has a remarkable effect in improving the productivity of concrete boards such as PC boards and reducing work mistakes.

【図面の簡単な説明】[Brief description of drawings]

第1図ないし第4図は本発明の実施例を示すもので、第
1図は作業シートの平面図、第2図は同使用例を示す斜
視図、第3図はPC板の断面図、第4図はPC板製造方法を
示すブロック図、第5図は従来のPC板製造方法を示すブ
ロック図、第6図は建物の各階の間取りを示す斜視図で
ある。 1……作業シート、2……先付部品 3,4,5……孔、9……間取り 10……PC板、11……型枠 12……基板
1 to 4 show an embodiment of the present invention. FIG. 1 is a plan view of a work sheet, FIG. 2 is a perspective view showing the same use example, and FIG. 3 is a sectional view of a PC board. FIG. 4 is a block diagram showing a PC board manufacturing method, FIG. 5 is a block diagram showing a conventional PC board manufacturing method, and FIG. 6 is a perspective view showing a floor plan of each floor of a building. 1 ... Work sheet, 2 ... Prefabricated parts 3,4,5 ... Hole, 9 ... Floor plan 10 ... PC board, 11 ... Formwork 12 ... Board

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】建物の複数階に亘って共通な間取りの実寸
外形状にした合成樹脂製の可撓性シートの表面に、先付
部品の取付位置を原寸寸法で記載すると共に、前記先付
け部品の取付位置に先付け部品の種類に応じて異なる形
状の孔を穿設し、該可撓性シートの一部に各間取り用の
識別記号を付与して、これを不使用時には全体を丸めて
収納可能な作業シートになさしめ、 該作業シートを同じ間取りの実寸外形状に組み立てた型
枠の基板に載置し、 前記先付部品の取付位置及び孔形状をマーキング材で前
記基板に写し取り、 前記作業シートを型枠より外した後、前記基板の上に写
し取られた先付部品取付位置で、かつ、マーキングされ
た孔の形状に応じた種類の先付部品を設置したのち、 鉄筋を配筋するなどしてコンクリートを打設し、打設コ
ンクリート養生後脱型させて形成することを特徴として
なるコンクリート板の製造方法。
1. A mounting position of a leading component is described in full scale on the surface of a flexible sheet made of a synthetic resin, which has a floor plan common to a plurality of floors of a building and has an actual size outside shape. A hole with a different shape is punched at the mounting position according to the type of pre-attached part, and an identification symbol for each floor plan is attached to a part of the flexible sheet, and when not in use, the whole is rolled and stored. The work sheet is squeezed into a possible work sheet, the work sheet is placed on a board of a form frame assembled in the actual layout with the same floor plan, and the mounting position and hole shape of the pre-attached component are copied on the board with a marking material, After removing the work sheet from the formwork, at the attachment position of the attachment component copied on the substrate, and after installing the attachment component of the type corresponding to the shape of the marked hole, rebar Placing concrete by placing it, etc. A method for producing a concrete plate, which is characterized in that it is formed by demolding after curing concrete.
JP63226476A 1988-09-12 1988-09-12 Concrete board manufacturing method Expired - Lifetime JPH082528B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP63226476A JPH082528B2 (en) 1988-09-12 1988-09-12 Concrete board manufacturing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP63226476A JPH082528B2 (en) 1988-09-12 1988-09-12 Concrete board manufacturing method

Publications (2)

Publication Number Publication Date
JPH0274307A JPH0274307A (en) 1990-03-14
JPH082528B2 true JPH082528B2 (en) 1996-01-17

Family

ID=16845698

Family Applications (1)

Application Number Title Priority Date Filing Date
JP63226476A Expired - Lifetime JPH082528B2 (en) 1988-09-12 1988-09-12 Concrete board manufacturing method

Country Status (1)

Country Link
JP (1) JPH082528B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5361183B2 (en) * 2007-12-25 2013-12-04 株式会社エム・テック Method for marking out PCa member using sheet

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5630803A (en) * 1979-08-22 1981-03-28 Showa Touen Kk Flask for manufacturing tile placing pc board
JPS5967298U (en) * 1982-10-26 1984-05-07 三宅 陽二 Ruler for writing mark cards

Also Published As

Publication number Publication date
JPH0274307A (en) 1990-03-14

Similar Documents

Publication Publication Date Title
US4573302A (en) Method of constructing houses
US4934121A (en) Integrated reinforced concrete wall structure
US5055252A (en) Method of constructing an integrated concrete wall structure
US20030061722A1 (en) Polygrid
US3816931A (en) Architectural templet
CN212105144U (en) Electrical pre-buried wire box positioning device
US20070068114A1 (en) Methods and system to efficiently design and erect buildings
JPH082528B2 (en) Concrete board manufacturing method
US3206823A (en) Means for producing swimming pools
US4800697A (en) Modular interstitial concrete sub-floor
EP1726729B1 (en) Partition wall for integrating with concrete floor
CN110593560A (en) Concrete wall column inner wire box installation method
CN210483034U (en) Embedded module for wire pipes
CN109838023B (en) Method for marking installation direction of prefabricated laminated slab and special concrete column
JP2005240479A (en) Installation article base
JPH0533629Y2 (en)
JPS62102728A (en) Support structure of housing equipment machineries
CN210061517U (en) Mould for precast concrete production
CN114953155B (en) Clearance controller, manufacturing method of laminated slab and laminated slab
JP6963402B2 (en) How to mark the concrete surface
JPS5838893Y2 (en) Air conditioner installation plate structure
JP3364082B2 (en) Embedded material for concrete slab, substrate for concrete slab having the embedded material, and concrete slab using the substrate
JP2835017B2 (en) Floor wiring device and floor wiring method
JPH0119005B2 (en)
JPH09151603A (en) Concrete form panel and concrete form structure