JPH08199623A - Pipe line laying method and its device - Google Patents
Pipe line laying method and its deviceInfo
- Publication number
- JPH08199623A JPH08199623A JP7012489A JP1248995A JPH08199623A JP H08199623 A JPH08199623 A JP H08199623A JP 7012489 A JP7012489 A JP 7012489A JP 1248995 A JP1248995 A JP 1248995A JP H08199623 A JPH08199623 A JP H08199623A
- Authority
- JP
- Japan
- Prior art keywords
- groove
- pipe
- trolley
- pipeline laying
- pipeline
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、ガス、電線、通信線、
水道等のためのパイプラインを地中に敷設する方法及び
装置に関するものである。BACKGROUND OF THE INVENTION The present invention relates to gas, electric wires, communication wires,
The present invention relates to a method and a device for laying a pipeline for water supply or the like in the ground.
【0002】[0002]
【従来の技術】従来、上記のようなパイプラインを地中
に敷設する手段として、次のような方法が知られてい
る。2. Description of the Related Art Conventionally, the following methods have been known as means for laying the above pipeline in the ground.
【0003】まず、図8(a)に示すように、溝掘削
機90で地盤Gに溝Dを掘る。その際、溝Dの掘削領域
の両脇に予め矢板を打ち込んでおくことが好ましい。First, as shown in FIG. 8 (a), a groove D is dug in the ground G with a groove excavator 90. At that time, it is preferable to strike the sheet piles on both sides of the excavation area of the groove D in advance.
【0004】同図(b)に示すように、上記溝Dが敷
設用パイプPの全長よりも長くなった時点で、この溝D
内にパイプPを搬入し、敷設する。なお、このパイプP
が2本目以上の場合は、このパイプPの後端を前回敷設
したパイプの前端に溶接等で連結する。As shown in FIG. 1B, when the groove D becomes longer than the entire length of the laying pipe P, the groove D becomes longer.
The pipe P is carried in and laid. In addition, this pipe P
In the case of the second pipe or more, the rear end of the pipe P is connected to the front end of the previously laid pipe by welding or the like.
【0005】ここで、上記溝掘削機90により掘削した
土砂91は、ダンプトラック92等で後方へ搬送し、同
図(c)に示すように、既に敷いたパイプPの上へ供給
して、このパイプPを地中に埋める。Here, the earth and sand 91 excavated by the groove excavator 90 is conveyed rearward by a dump truck 92 or the like and supplied onto the pipe P already laid as shown in FIG. The pipe P is buried in the ground.
【0006】[0006]
【発明が解決しようとする課題】上記方法では、溝掘削
機90で掘削した土砂91をダンプトラック92に積載
する作業と、このダンプトラック92に積載した土砂9
1をパイプP上へ搬出する作業とが必要であるととも
に、ダンプトラック92を掘削位置と土砂供給位置との
間で何度も往復させなければならず、作業能率が低い。In the above method, the work of loading the earth and sand 91 excavated by the trench excavator 90 on the dump truck 92 and the earth and sand 9 loaded on the dump truck 92 are carried out.
1 is required to be carried out onto the pipe P, and the dump truck 92 has to be reciprocated many times between the excavation position and the earth and sand supply position, resulting in low work efficiency.
【0007】本発明は、このような事情に鑑み、簡単な
作業で能率良くパイプラインを敷設することができる方
法及び装置を提供することを目的とする。In view of such circumstances, it is an object of the present invention to provide a method and apparatus capable of efficiently laying a pipeline with a simple work.
【0008】[0008]
【課題を解決するための手段】上記課題を解決するため
の手段として、本発明は、地盤に溝を掘削しながら、こ
の溝内に順次パイプを敷き、その上に土砂を供給して上
記パイプを地中へ埋めるパイプラインの敷設方法におい
て、上記溝の掘削の進行に伴ってその掘削方向に沿いコ
ンベアを載せた台車を走行させ、掘削された土砂を上記
コンベアにより後方へ搬送して既に敷かれているパイプ
の上へ搬出するものである(請求項1)。As means for solving the above problems, the present invention is to dig a trench in the ground while laying pipes in the trench sequentially and supplying earth and sand to the pipe to feed the pipe. In the method of laying a pipeline in the ground, as the excavation of the groove progresses, a trolley with a conveyor is run along the excavation direction, and the excavated earth and sand is conveyed backward by the conveyor and already laid. It is to be carried out on top of the pipe (claim 1).
【0009】この方法では、上記溝をまたぐようにして
上記台車を走行させたり(請求項2)、上記台車上に敷
設用のパイプを搭載しながらこの台車を走行させたりす
る(請求項3)ことが、より好ましい。In this method, the truck is run so as to straddle the groove (Claim 2), or the truck is run while a pipe for installation is mounted on the truck (Claim 3). Is more preferable.
【0010】上記台車は、溝掘削機で牽引すれば、なお
好ましい(請求項4)。More preferably, the bogie is towed by a groove excavator (Claim 4).
【0011】また本発明は、地盤に溝を掘削しながら、
この溝内に順次パイプを敷き、その上に土砂を供給して
上記パイプを地中へ埋めるためのパイプラインの敷設装
置において、走行可能な台車と、この台車上に搭載され
るコンベアとを備え、このコンベアは、上記台車が上記
溝に沿って走行する際にこの溝から側方に外れた位置で
上記溝の長手方向に沿って土砂を搬送する主搬送部と、
この主搬送部の後端から上記溝へ向けて土砂を搬出する
搬出部とを有するものである(請求項5)。The present invention also provides for excavating a trench in the ground,
In the pipeline laying device for sequentially laying pipes in this groove and supplying earth and sand to the pipes to bury the pipes underground, a trolley capable of traveling and a conveyor mounted on the trolley are provided. , The conveyor is a main transport section for transporting earth and sand along the longitudinal direction of the groove at a position laterally separated from the groove when the carriage travels along the groove,
It has a carrying-out section for carrying out earth and sand from the rear end of the main carrying section toward the groove (claim 5).
【0012】この装置では、上記台車において上記溝か
ら側方に外れた位置に敷設用のパイプを搭載するための
パイプ搭載部を設ければ、なお好ましい(請求項6)。In this apparatus, it is more preferable to provide a pipe mounting portion for mounting a pipe for laying at a position laterally separated from the groove in the truck (claim 6).
【0013】さらに、上記台車に、上記パイプ搭載部に
搭載されたパイプを溝内に搬入するクレーンを搭載すれ
ば、より効果的である(請求項7)。Further, it is more effective if a crane for loading the pipe mounted on the pipe mounting portion into the groove is mounted on the trolley (claim 7).
【0014】上記台車は、溝掘削機に連結してこの溝掘
削機で牽引するのが、より好ましい(請求項8)。More preferably, the bogie is connected to a groove excavator and towed by the groove excavator (claim 8).
【0015】この場合、上記溝掘削機により掘削された
溝をまたいで上記台車が走行するように溝掘削機への台
車の連結位置を設定するとともに、上記溝を常に上方に
開放させるように上記台車を構成すれば、さらに好まし
いものとなる(請求項9)。In this case, the connecting position of the bogie to the groove excavator is set so that the bogie runs across the groove excavated by the groove excavator, and the groove is always opened upward. It is more preferable to construct a carriage (Claim 9).
【0016】また、上記溝掘削機の前方には矢板打設装
置を設けるのが、より好ましい(請求項10)。Further, it is more preferable to provide a sheet pile driving device in front of the groove excavator (claim 10).
【0017】上記台車の下部には、上記コンベアによる
土砂搬出位置よりも前の位置でパイプの端部同士を連結
するパイプ連結機を昇降可能に取付けるのがよい(請求
項11)。この場合、上記パイプ連結機を上記台車に対
してその走行方向にスライド可能に取付ければ(請求項
12)、より効果的となる。It is preferable that a pipe connector for connecting the ends of the pipes to be lifted up and down is attached to the lower part of the carriage at a position before the earth and sand carrying-out position by the conveyor (claim 11). In this case, it is more effective if the pipe connector is slidably attached to the carriage in the traveling direction (claim 12).
【0018】[0018]
【作用】請求項1記載の方法によれば、溝掘削作業の進
行に伴い、その掘削方向に沿ってコンベアを載せた台車
を走行させることにより、ダンプトラックを往復走行さ
せたりすることなく、掘削された土砂を上記コンベアで
連続的に既設パイプ上へ供給でき、溝掘削作業とパイプ
埋設作業とを同時実行できる。According to the method of claim 1, as the ditch excavation work progresses, the bogie on which the conveyor is mounted is caused to travel along the excavation direction without excavating the dump truck back and forth. The thus-prepared earth and sand can be continuously supplied onto the existing pipe by the conveyor, and the trench excavation work and the pipe burying work can be simultaneously executed.
【0019】具体的に、請求項5記載の装置では、上記
台車が上記溝に沿って走行する際、この溝から外れた位
置で上記溝の長手方向に沿って主搬送部によって土砂が
後方へ搬送され、かつこの主搬送部の後端から上記溝へ
向けて搬出部により土砂が搬出される。従って、この搬
出部よりも前方の領域で上記主搬送部が溝内へのパイプ
搬入に支障を来すことはない。Specifically, in the apparatus according to the fifth aspect, when the carriage travels along the groove, the main carrier portion moves the earth and sand backward along the longitudinal direction of the groove at a position deviated from the groove. The soil is carried by the carrying-out section from the rear end of the main carrying section toward the groove. Therefore, in the area in front of the carry-out section, the main carrying section does not hinder the carry-in of the pipe into the groove.
【0020】さらに、請求項3,6記載のように、上記
台車上に敷設用のパイプを搭載しながらこの台車を走行
させるようにすれば、パイプ敷設位置までパイプを搬送
する作業が不要であり、上記台車上のパイプをそのまま
下方の溝に搬入するだけでパイプを敷設できる。Further, according to the third and sixth aspects of the invention, if the trolley is mounted on the trolley while the trolley is run, the work for transporting the pipe to the pipe laying position is unnecessary. The pipe can be laid by simply carrying the pipe on the dolly into the groove below.
【0021】特に、請求項7記載の装置では、上記台車
に、上記パイプ搭載部に搭載されたパイプを溝内に搬入
するクレーンを搭載しているので、上記台車と並行して
走行式クレーン等を走行させる必要がなく、適当なタイ
ミングでいつでも台車上でパイプの搬入作業を行うこと
ができる。Particularly, in the apparatus according to claim 7, since the crane for loading the pipe mounted on the pipe mounting portion into the groove is mounted on the truck, a traveling crane or the like is installed in parallel with the truck. It is not necessary to drive the pipe, and it is possible to carry in the pipes on the trolley at an appropriate timing at any time.
【0022】上記台車の走行手段としては、この台車に
駆動源を搭載したり、専用の先導者で牽引したりしても
よいが、請求項4,8記載のように、上記台車を溝掘削
機に連結してこの掘削機で牽引すれば、特別な駆動源等
を追加せずに台車を走行させることができる。また、台
車を確実に溝掘削機に追従させることができる。As the traveling means of the trolley, a drive source may be mounted on the trolley or it may be pulled by a dedicated leader. However, as described in claims 4 and 8, the trolley is excavated by a groove. If the excavator is connected to the machine and towed, the bogie can be run without adding a special drive source or the like. Further, the truck can be made to follow the groove excavator with certainty.
【0023】上記台車は、掘削溝の側方を走行してもよ
いが、請求項2,9記載のように、上記掘削溝をまたい
で台車が走行するようにすれば、この台車の走行のため
に必要な幅方向のスペースをより削減できる。The trolley may travel beside the excavation groove, but if the trolley travels across the excavation groove as described in claims 2 and 9, the traveling of the trolley can be prevented. Therefore, it is possible to further reduce the space in the width direction.
【0024】さらに、請求項10記載のように、上記溝
掘削機の前方に矢板打設装置を設ければ、溝掘削領域に
予め矢板を打設する作業と、この矢板打設位置に対応し
て溝を掘削する作業とを確実にかつ同時に行うことがで
きる。Further, if a sheet pile driving device is provided in front of the groove excavator as claimed in claim 10, the sheet pile driving operation in advance in the groove excavation area and the sheet pile driving position can be performed. The work of excavating the trench can be reliably and simultaneously performed.
【0025】また、請求項11記載の装置では、上記台
車の下部に、上記コンベアによる土砂搬出位置よりも前
の位置でパイプの端部同士を連結するパイプ連結機を昇
降可能に取付けているので、パイプ連結機を溝内に搬入
するための特別な手段を導入しなくてもよく、台車の下
方で適当なタイミングでパイプを連結できる。Further, in the apparatus according to the eleventh aspect of the present invention, since the pipe connecting machine for connecting the end portions of the pipes to each other is attached to the lower portion of the carriage so as to be able to move up and down, at a position before the earth and sand carrying-out position by the conveyor. It is not necessary to introduce a special means for loading the pipe connecting device into the groove, and the pipes can be connected at a proper timing below the carriage.
【0026】特に、請求項12記載の装置では、上記パ
イプ連結機を上記台車に対してその走行方向にスライド
可能に構成しているので、このパイプ連結機による作業
時に同パイプ連結機と台車とをスライドさせることによ
り、台車を止めることなく走行させながらパイプ連結作
業を行うことができる。Particularly, in the apparatus according to the twelfth aspect, since the pipe connector is configured to be slidable in the traveling direction with respect to the truck, the pipe connector and the truck can be operated when the pipe connector is used. By sliding, the pipe connection work can be performed while the truck is running without stopping.
【0027】[0027]
【実施例】本発明の一実施例を図1〜図7に基づいて説
明する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of the present invention will be described with reference to FIGS.
【0028】図1〜図4において、1はベースマシンで
あり、このベースマシン1は、クローラ4等の走行装置
を備えた下部走行体2と、キャブ等を有する上部旋回体
5とを備えている。1 to 4, reference numeral 1 denotes a base machine, which is provided with a lower traveling body 2 having a traveling device such as a crawler 4 and an upper revolving body 5 having a cab or the like. There is.
【0029】この上部旋回体5の前部には、起伏駆動さ
れるブーム6が装着され、このブーム6の回動端部に矢
板打設装置7が連結されている。この矢板打設装置7
は、従来から一般に用いられている装置と同等のもので
あり、左右の矢板3をベースマシン1の走行方向に沿っ
て順次地盤Gに打ち込むものである。ベースマシン1の
後部にはバケットエレベータ8が連結されており、この
バケットエレベータ8とベースマシン1とで溝掘削機が
構成されている。A boom 6 which is driven up and down is mounted on the front part of the upper swing body 5, and a sheet pile driving device 7 is connected to the rotating end of the boom 6. This sheet pile placing device 7
Is equivalent to an apparatus that has been generally used in the past, in which the left and right sheet piles 3 are sequentially driven into the ground G along the traveling direction of the base machine 1. A bucket elevator 8 is connected to the rear portion of the base machine 1, and the bucket elevator 8 and the base machine 1 constitute a groove excavator.
【0030】図7に示すように、上記バケットエレベー
タ8は縦長のフレーム11を備え、その上下端にスプロ
ケット12,13が回転可能に取付けられており、両ス
プロケット12,13間にチェーン14が掛けわたされ
ている。このチェーン14には、その長手方向に沿って
等間隔で搬送バケット15が取付けられる一方、上記フ
レーム11の下端部には、複数の掘削バケット16aが
周方向に配設された掘削ホイール16が回転可能に装着
されている。そして、この掘削ホイール16が図7の時
計回り方向に回転駆動され、かつ上記チェーン14が同
図矢印A1方向に駆動されることにより、掘削ホイール
16で掘削された土砂がこの掘削ホイール16の掘削バ
ケット16aから各搬送バケット15に渡され、この搬
送バケット15によって上方に搬送され、前記フレーム
11上部の排出口10から下方に排出されるようになっ
ている。As shown in FIG. 7, the bucket elevator 8 is provided with a vertically long frame 11, sprocket wheels 12, 13 are rotatably attached to the upper and lower ends thereof, and a chain 14 is hung between the sprocket wheels 12, 13. I have been passed over. Conveying buckets 15 are attached to the chain 14 at equal intervals along the longitudinal direction thereof, while at the lower end of the frame 11, an excavating wheel 16 having a plurality of excavating buckets 16a arranged in the circumferential direction rotates. It is installed as possible. The excavating wheel 16 is driven to rotate clockwise in FIG. 7 and the chain 14 is driven in the direction of arrow A1 in FIG. 7, so that the earth and sand excavated by the excavating wheel 16 is excavated by the excavating wheel 16. It is passed from the bucket 16a to each of the transport buckets 15, is transported upward by the transport buckets 15, and is discharged downward from the discharge port 10 in the upper portion of the frame 11.
【0031】このバケットエレベータ8は、ベースマシ
ン1の幅方向(図2,4では上下方向)略中央位置の後
方に配されており、既に矢板打設装置7が打設した左右
の矢板3同士の間を上記バケットエレベータ8が掘削す
るように構成されている。The bucket elevator 8 is disposed behind the center position of the base machine 1 in the width direction (vertical direction in FIGS. 2 and 4), and the left and right sheet piles 3 which the sheet pile placing device 7 has already placed. The bucket elevator 8 is configured to excavate the gap.
【0032】上記ベースマシン1の後部には、伸縮シリ
ンダ17を介して前側台車18が連結され、この前側台
車18に長尺の連結棒20を介して後側台車22が連結
されている。各台車18,22は、地盤G上を転動可能
な車輪21を備え、前側台車18は上記バケットエレベ
ータ8のすぐ後方に、後側台車22はさらにその後方
に、それぞれ配されている。従って、上記ベースマシン
1の走行に伴い、このベースマシン1及びバケットエレ
ベータ8に追従して両台車18,22も走行するように
なっている。A front trolley 18 is connected to the rear portion of the base machine 1 via a telescopic cylinder 17, and a rear trolley 22 is connected to the front trolley 18 via a long connecting rod 20. Each trolley | bogie 18 and 22 is equipped with the wheel 21 which can roll on the ground G, the front trolley | bogie 18 is arrange | positioned just behind the said bucket elevator 8, and the back trolley | bogie 22 is further arrange | positioned behind it, respectively. Therefore, as the base machine 1 travels, the two carriages 18 and 22 follow the base machine 1 and the bucket elevator 8 as well.
【0033】ここで、前記バケットエレベータ8による
溝Dの掘削幅は、各台車18,22での左右の車輪21
同士の間隔よりも小さく設定されている。Here, the excavation width of the groove D by the bucket elevator 8 is defined by the left and right wheels 21 of the carriages 18 and 22.
It is set smaller than the interval between them.
【0034】両台車18,22には、第1ベルトコンベ
ア(主搬送部)24が搭載され、後側台車22には第2
ベルトコンベア26が搭載されている。A first belt conveyor (main transport section) 24 is mounted on both carriages 18 and 22, and a second belt conveyor (main transport section) 24 is mounted on the rear carriage 22.
A belt conveyor 26 is mounted.
【0035】第1ベルトコンベア24は、両台車18,
22の並び方向(すなわち溝Dの掘削方向)に延び、敷
設用パイプPの全長よりも長い搬送距離を有している。
そして、この第1ベルトコンベア24の前端が前側台車
18に、後端が後側台車22にそれぞれ支持されてお
り、第1ベルトコンベア24全体はベースマシン1の幅
方向略中央位置(すなわち溝Dの掘削位置)から側方
(図例では進行方向に向かって右側)に外れた位置に配
設されている。また、前側台車18上において、上記バ
ケットエレベータ排出口10の直下方の位置にはホッパ
ー28が設けられ、このホッパー28の下方の位置から
上記第1ベルトコンベア24の前端直上方の位置にかけ
てベルトコンベア30が設けられており、上記バケット
エレベータ排出口10から排出された土砂が上記ホッパ
ー28及びベルトコンベア30を経由して上記第1ベル
トコンベア24前端に供給されるようになっている。The first belt conveyor 24 includes two carriages 18,
It extends in the arrangement direction of 22 (that is, the excavation direction of the groove D) and has a transport distance longer than the entire length of the laying pipe P.
The front end of the first belt conveyor 24 is supported by the front carriage 18 and the rear end of the first belt conveyor 24 is supported by the rear carriage 22. The entire first belt conveyor 24 is located at a substantially central position in the width direction of the base machine 1 (ie, the groove D). The excavation position is located laterally (to the right in the traveling direction in the illustrated example). Further, on the front carriage 18, a hopper 28 is provided at a position directly below the bucket elevator discharge port 10, and a belt conveyor extends from a position below the hopper 28 to a position just above the front end of the first belt conveyor 24. 30 is provided, and the earth and sand discharged from the bucket elevator discharge port 10 are supplied to the front end of the first belt conveyor 24 via the hopper 28 and the belt conveyor 30.
【0036】図2及び図5,6に示すように、第2ベル
トコンベア26の前端は、上記第1ベルトコンベア24
の後端のすぐ下方の位置に配され、第2ベルトコンベア
26の後端は、前記ベースマシン1の幅方向略中央位置
の後方(すなわち掘削溝Dの上方)に位置するように配
されており、この第2ベルトコンベア26により、第1
ベルトコンベア24で後方に搬送された土砂が溝D内に
搬出されるように、第2ベルトコンベア26の配設位置
及び向きが設定されている。As shown in FIGS. 2 and 5 and 6, the front end of the second belt conveyor 26 is the first belt conveyor 24.
It is arranged at a position just below the rear end of the second belt conveyor 26, and the rear end of the second belt conveyor 26 is arranged behind the substantially central position in the width direction of the base machine 1 (that is, above the excavation groove D). The second belt conveyor 26
The arrangement position and orientation of the second belt conveyor 26 are set so that the earth and sand conveyed rearward by the belt conveyor 24 are carried into the groove D.
【0037】前後台車18,22上において、第1ベル
トコンベア24の支持位置と反対側(図例では進行方向
左側)の位置には、図3〜図6に示すような左右一対の
パイプ支持板31が立設されている。両パイプ支持板3
1同士の間隔は、パイプPの直径よりも僅かに大きく設
定されており、両パイプ支持板31同士の間に、複数の
パイプPを積載可能なパイプ搭載部が形成されている。On the front and rear carriages 18 and 22, a pair of left and right pipe support plates as shown in FIGS. 3 to 6 is provided at a position opposite to the support position of the first belt conveyor 24 (left side in the traveling direction in the illustrated example). 31 is erected. Both pipe support plates 3
The space between the pipes 1 is set to be slightly larger than the diameter of the pipe P, and a pipe mounting portion capable of stacking a plurality of pipes P is formed between the pipe support plates 31.
【0038】さらに、両台車18,22上には、上記パ
イプPを搬送するためのクレーン32が搭載されてい
る。具体的に、各台車18,22上においてその幅方向
中央位置から前記パイプ搭載部側(進行方向左側)の端
部に至るまでの領域には、ガイドレール33が敷設さ
れ、このガイドレール33に沿って基台34が走行可能
とされており、この基台34上に伸縮ジャッキ36が立
設されている。この伸縮ジャッキ36の伸縮ロッド37
の端部(すなわち上端部)には、この端部から相手方の
台車に向かう方向(前側台車18では後方、後側台車2
2では前方)に延びるアーム38が固定され、このアー
ム38の端部に伸縮シリンダ40が下向きに固定されて
いる。そして、この伸縮シリンダ40の伸縮ロッド41
の端部(すなわち下端部)に、パイプPを上からつかむ
状態と解放する状態とに切換えられるパイプ把持部42
が設けられている。Further, a crane 32 for transporting the pipe P is mounted on both carriages 18 and 22. Specifically, a guide rail 33 is laid in a region from the center position in the width direction on each of the carriages 18 and 22 to the end portion on the pipe mounting portion side (the left side in the traveling direction). A base 34 is allowed to travel along the base 34, and a telescopic jack 36 is erected on the base 34. Telescopic rod 37 of this telescopic jack 36
At the end portion (that is, the upper end portion) of the other side of the vehicle (the rear side of the front carriage 18 and the rear side of the rear carriage 2).
In FIG. 2, the arm 38 extending forward is fixed, and the telescopic cylinder 40 is fixed downward at the end of the arm 38. Then, the telescopic rod 41 of the telescopic cylinder 40
At the end (that is, the lower end) of the pipe P, the pipe gripping portion 42 can be switched between a state of grasping the pipe P from above and a state of releasing it.
Is provided.
【0039】上記後部台車22の下面において、その幅
方向略中央部には、前後に延びるガイドレール46が固
定され、このガイドレール46に沿ってスライド可能に
シリンダ装置47が取付けられている。このシリンダ装
置47は、下向きに延びる前後一対の伸縮シリンダを備
え、各シリンダの伸縮ロッド48の端部(すなわち下端
部)に溶接・検査機(パイプ連結機)44が結合されて
いる。この溶接・検査機44は、把持用伸縮シリンダ4
9を備え、この伸縮シリンダ49の伸縮により、パイプ
Pを把持する状態と解放する状態とに切換えられるよう
になっており、図5二点鎖線に示すように両パイプP同
士の当接位置を把持した状態で、両パイプP同士を溶接
により結合し、かつその検査を行うように構成されてい
る。この溶接・検査機44は、従来から用いられている
ものと同等のものが適用可能である。On the lower surface of the rear carriage 22, a guide rail 46 extending in the front-rear direction is fixed at a substantially central portion in the width direction, and a cylinder device 47 is attached slidably along the guide rail 46. The cylinder device 47 includes a pair of front and rear telescopic cylinders extending downward, and a welding / inspecting machine (pipe connecting machine) 44 is coupled to an end portion (that is, a lower end portion) of the telescopic rod 48 of each cylinder. This welding / inspection machine 44 is equipped with a telescopic cylinder 4 for gripping.
9, the expansion and contraction of the expansion and contraction cylinder 49 enables switching between a state in which the pipe P is gripped and a state in which the pipe P is released. As shown by the two-dot chain line in FIG. In the gripped state, both pipes P are connected by welding and the inspection is performed. As the welding / inspecting machine 44, the same one as conventionally used can be applied.
【0040】次に、この装置を用いたパイプライン敷設
方法を説明する。Next, a pipeline laying method using this apparatus will be described.
【0041】1)まず、掘削すべき溝と略同等の深さを
もつ穴を地盤に掘削し、この穴内にバケットエレベータ
8を挿入する。1) First, a hole having a depth substantially equal to the groove to be excavated is excavated in the ground, and the bucket elevator 8 is inserted into this hole.
【0042】2)上記バケットエレベータ8及び矢板打
設装置7を作動させながらベースマシン1を走行させ
る。これにより、矢板打設装置7が地盤Gに左右一対の
矢板3を走行方向に沿って順次打ち込み、そのすぐ後方
で、既打設の矢板3同士の間をバケットエレベータ8が
掘削し、上記走行方向に溝Dを形成する。この時、前後
台車18,22はベースマシン1に追従し、上記溝Dを
またぐ状態で溝Dの掘削方向に沿って走行する。また、
第1ベルトコンベア24は溝Dの右側に、パイプ搭載部
は溝Dの左側にそれぞれ位置しているので、前後の台車
18,22同士の間で溝Dの上方には何もなく開放され
た状態となっている。2) The base machine 1 is run while operating the bucket elevator 8 and the sheet pile driving device 7. As a result, the sheet pile driving device 7 sequentially drives the pair of left and right sheet piles 3 into the ground G along the traveling direction, and immediately behind it, the bucket elevator 8 excavates between the already piled sheet piles 3 and travels as described above. A groove D is formed in the direction. At this time, the front and rear bogies 18 and 22 follow the base machine 1 and travel along the excavation direction of the groove D while straddling the groove D. Also,
The first belt conveyor 24 is located on the right side of the groove D, and the pipe mounting portion is located on the left side of the groove D, so that there is nothing above the groove D between the front and rear carriages 18, 22. It is in a state.
【0043】3)上記溝Dの長さが1本のパイプPの全
長よりも長くなった時点で、前後のクレーン32の伸縮
ジャッキ36及び伸縮シリンダ40を適宜伸縮させるこ
とにより、パイプ搭載部に積まれたパイプPのうち最も
上のパイプPをパイプ把持部42でつかみ、その後伸縮
ジャッキ36を伸ばしてパイプPを持ち上げ、基台34
を走行させてパイプPを進行方向左側の位置から中央位
置(すなわち溝Dの上方位置)へ搬送する。その後、伸
縮ジャッキ36を収縮させ、かつ伸縮シリンダ40を伸
ばすことにより、パイプPを下降させ、溝Dの底面に載
置する。3) When the length of the groove D becomes longer than the entire length of one pipe P, the telescopic jacks 36 and telescopic cylinders 40 of the front and rear cranes 32 are appropriately extended and retracted so that the pipes are mounted on the pipe mounting portion. The uppermost pipe P among the piled pipes P is grasped by the pipe grip portion 42, and then the telescopic jack 36 is extended to lift the pipe P, and the base 34
To convey the pipe P from the position on the left side in the traveling direction to the central position (that is, the position above the groove D). Thereafter, the telescopic jack 36 is contracted and the telescopic cylinder 40 is extended to lower the pipe P and place it on the bottom surface of the groove D.
【0044】4)このパイプPが2本目以上の場合に
は、このパイプPの後端と前回敷設したパイプPの前端
とを溶接により連結する。具体的には、シリンダ装置4
7のシリンダを伸ばして溶接・検査機44を下降させ、
両パイプPの当接個所を把持させた状態でこの溶接・検
査機44を作動させることにより、両パイプPを連結す
る。4) When this pipe P is the second pipe or more, the rear end of this pipe P and the front end of the pipe P laid previously are connected by welding. Specifically, the cylinder device 4
Extend the cylinder 7 and lower the welding / inspection machine 44,
By operating the welding / inspecting machine 44 while gripping the contact points of both pipes P, both pipes P are connected.
【0045】なお、溝Dにおいて溶接個所に対応する部
分では、他の部分よりも掘削深さを大きく設定して溶接
用溝D1を特設しておくことが好ましい。これにより、
上記溶接・検査機44による溶接作業がより円滑にな
る。It should be noted that it is preferable to specially set the welding groove D1 by setting the excavation depth larger in the portion corresponding to the welding point in the groove D than in the other portions. This allows
The welding work by the welding / inspection machine 44 becomes smoother.
【0046】5)上記バケットエレベータ8により掘削
が進行すると、このバケットエレベータ8の排出口10
から掘削土砂が排出される。この土砂は、ホッパー28
及びベルトコンベア30を経て第1ベルトコンベア24
の前端に運ばれ、この第1ベルトコンベア24によって
後方へ搬送された後、第2ベルトコンベア26により溝
D内において既敷設のパイプP上へ搬出される。これに
より、パイプPは地中に埋設される。5) When excavation proceeds by the bucket elevator 8, the outlet 10 of the bucket elevator 8
Excavated earth and sand are discharged from. This earth and sand is hopper 28
And the first belt conveyor 24 via the belt conveyor 30.
Is conveyed to the front end of the first belt conveyor 24, is conveyed backward by the first belt conveyor 24, and is then conveyed by the second belt conveyor 26 onto the existing pipe P in the groove D. As a result, the pipe P is buried in the ground.
【0047】なお、この埋立て部分G1については、そ
の上面を地ならし機50でならしたり、振動締固め機5
2で締固めておくようにする。The top surface of the landfill portion G1 is smoothed by the earthmoving machine 50 or the vibration compactor 5
Try to compact with 2.
【0048】この実施例方法及び装置では、溝Dの掘削
作業の進行に伴い、その掘削方向に沿って台車18,2
2を走行させ、ベルトコンベア24,26を移送するよ
うにしているので、従来のようにダンプトラックを往復
走行させたりすることなく、掘削された土砂を上記ベル
トコンベア24,26で連続的に既設パイプP上へ供給
でき、溝掘削作業とパイプ埋設作業とを連続的に同時実
行して能率よく円滑にパイプラインを敷設できる。In the method and apparatus of this embodiment, as the excavation work of the groove D progresses, the carriages 18, 2 are moved along the excavation direction.
2, the belt conveyors 24 and 26 are moved, so that the excavated earth and sand are continuously installed on the belt conveyors 24 and 26 without the conventional reciprocating dump truck. The pipe can be supplied onto the pipe P, and the trench excavation work and the pipe burying work can be continuously performed simultaneously to lay the pipeline efficiently and smoothly.
【0049】また、上記第1ベルトコンベア24を溝D
の形成位置から側方に外れた位置に配し、その後方で第
2ベルトコンベア26により溝D内へ搬出するようにし
ているので、上記第1ベルトコンベア24が溝D内への
パイプPの円滑な搬入作業を妨げるのを防ぐことができ
る。Further, the first belt conveyor 24 is provided with a groove D.
The first belt conveyor 24 is arranged at a position laterally away from the forming position and is carried out to the inside of the groove D by the second belt conveyor 26, so that the first belt conveyor 24 moves the pipe P into the groove D. It is possible to prevent the smooth carrying-in work from being disturbed.
【0050】なお、本発明はこのような実施例に限定さ
れるものでなく、例として次のような態様をとることも
可能である。The present invention is not limited to such an embodiment, and the following modes can be adopted as an example.
【0051】(1) 本発明では、台車18,22の走行と
並行して別個トラック等によりパイプを搬送し、このパ
イプをクローラクレーン等で溝D内に搬入するようにし
てもよい。ただし、上記実施例のように台車18,22
にパイプ搭載部を設けてこれにパイプPを搭載すれば、
トレーラー等のパイプ搬送手段を特に用いることなく、
上記パイプ搭載部のパイプPをそのまま下方の溝に搬入
するだけでパイプPを敷設できる。さらに、上記実施例
のように台車18,22にクレーンも搭載すれば、台車
18,22と並行してわざわざ走行式クレーン等を走行
させなくても、小さなスペースで、しかも適当なタイミ
ングでいつでも台車上でパイプPの搬入作業を行うこと
ができ、作業能率をさらに高めることができる利点があ
る。(1) In the present invention, a pipe may be conveyed by a separate truck or the like in parallel with the traveling of the carriages 18 and 22, and the pipe may be conveyed into the groove D by a crawler crane or the like. However, as in the above embodiment,
If a pipe mounting part is provided on this and the pipe P is mounted on it,
Without using a pipe transportation means such as a trailer,
The pipe P can be laid by simply carrying the pipe P of the pipe mounting portion into the groove below. Further, if a crane is also mounted on the carriages 18 and 22 as in the above-described embodiment, the carriage can be carried in a small space at any time with appropriate timing without the need to run a traveling crane in parallel with the carriages 18 and 22. There is an advantage that the work of loading the pipe P can be performed and the work efficiency can be further enhanced.
【0052】(2) 本発明では、コンベアを搭載した台車
に原動機等の走行手段を搭載してもよい。ただし、上記
実施例のように、上記台車18,22に溝掘削機(ベー
スマシン1)を連結してこのベースマシン1で牽引すれ
ば、特別な駆動源を追加せずとも台車18,22を走行
させることができ、しかも、これらの台車18,22を
確実にベースマシン1に追従させることができる。さら
に、上記実施例のように、上記ベースマシン1の前方に
矢板打設装置7を設ければ、溝掘削領域に予め矢板3を
打設する作業と、この矢板打設位置に対応して溝を掘削
する作業とを確実にかつ同時に行うことができる利点が
生じる。(2) In the present invention, traveling means such as a prime mover may be mounted on a carriage equipped with a conveyor. However, as in the above-mentioned embodiment, if a groove excavator (base machine 1) is connected to the bogies 18 and 22 and towed by the base machine 1, the bogies 18 and 22 can be moved without adding a special drive source. It is possible to drive the carts 18 and 22 and to reliably follow the base machine 1. Further, if the sheet pile driving device 7 is provided in front of the base machine 1 as in the above-described embodiment, the work of driving the sheet pile 3 in advance in the groove excavation area and the groove corresponding to the sheet pile driving position. There is an advantage that the work of excavating the ground can be reliably and simultaneously performed.
【0053】(3) 本発明において、パイプP同士を結合
する手段は特に問わず、フランジ継ぎ手等を用いてもよ
い。ただし、上記実施例のように、後側台車22の下部
に、上記第2ベルトコンベア26による土砂搬出位置よ
りも前の位置でパイプの端部同士を連結する溶接・検査
機44を昇降可能に取付ければ、溶接・検査機44を溝
内に搬入するための手段を特に用いなくても、溝の進行
に伴い走行する後側台車22の下方から適宜溶接・検査
機44を繰り出すことにより、適当なタイミングで溶接
・検査をすることができる。特に、上記実施例のよう
に、上記溶接・検査機44を後側台車22に対してその
走行方向にスライド可能に構成すれば、このスライドを
行いながら台車22を走行させることにより、台車22
を止めることなく溶接・検査機44による溶接・検査作
業を行うことができる利点がある。(3) In the present invention, the means for connecting the pipes P is not particularly limited, and a flange joint or the like may be used. However, as in the above embodiment, the welding / inspection machine 44 that connects the ends of the pipes to the lower part of the rear carriage 22 can be moved up and down at a position before the earth and sand carrying-out position by the second belt conveyor 26. If attached, the welding / inspection machine 44 can be appropriately fed out from below the rear carriage 22 that travels as the groove advances, without using any means for bringing the welding / inspection machine 44 into the groove. Welding and inspection can be performed at appropriate timing. In particular, if the welding / inspecting machine 44 is configured to be slidable in the traveling direction with respect to the rear carriage 22 as in the above-described embodiment, the carriage 22 is made to travel while the carriage 22 is traveling.
There is an advantage that welding / inspection work can be performed by the welding / inspection machine 44 without stopping.
【0054】(4) 上記実施例では、本発明における主搬
送部及び搬出部としてそれぞれ別個の第1ベルトコンベ
ア24及び第2ベルトコンベア26を用いているが、上
記主搬送部と搬出部とを一体とした形状の単一のベルト
コンベアを用いるようにしてもよい。(4) In the above embodiment, the first belt conveyor 24 and the second belt conveyor 26, which are separate from each other, are used as the main carrying section and the carrying-out section in the present invention. A single belt conveyor having an integral shape may be used.
【0055】(5) 上記実施例では、溝Dをまたいで台車
18,22が走行するものを示したが、これらの台車1
8,22をバケットエレベータ8の中央位置から側方に
外れた位置に連結し、掘削溝Dの側方を台車18,22
が走行するようにしてもよい。ただし、上記のように台
車18,22が溝Dをまたぐようにすれば、この台車1
8,22を走らせるための幅方向スペースをより削減で
き、施工時に交通に与える影響をより低減できる利点が
ある。この場合、例えば上記実施例のように台車を前側
台車18と後側台車22とに分けて両台車18,22同
士の間で溝Dを上方に開放させるようにすれば、この溝
D内への円滑なパイプ搬入作業を確保できる。(5) In the above embodiment, the carts 18 and 22 travel across the groove D, but these carts 1
8 and 22 are connected to a position deviated laterally from the central position of the bucket elevator 8 and the side of the excavation groove D is trolleyed by the carriages 18 and 22.
May run. However, if the carriages 18 and 22 straddle the groove D as described above, the carriage 1
There is an advantage that the space in the width direction for running 8, 22 can be further reduced, and the influence on the traffic at the time of construction can be further reduced. In this case, for example, if the carriage is divided into the front carriage 18 and the rear carriage 22 and the groove D is opened upward between the carriages 18 and 22 as in the above-described embodiment, the inside of the groove D can be increased. The smooth pipe loading work can be secured.
【0056】[0056]
【発明の効果】以上のように、本発明によれば次の効果
を得ることができる。As described above, according to the present invention, the following effects can be obtained.
【0057】請求項1記載の方法は、溝掘削作業の進行
に伴い、その掘削方向に沿いコンベアを載せた台車を走
行させ、上記コンベアにより掘削土砂を既敷設のパイプ
上へ搬送するようにしたものであるので、ダンプトラッ
クを往復走行させたりすることなく、掘削された土砂を
上記コンベアで連続的に既設パイプ上へ供給し、溝掘削
作業とパイプ埋設作業とを連続的に同時実行することに
より、パイプラインの敷設作業を能率よく円滑に行うこ
とができる効果がある。According to the method of claim 1, as the trench excavation work progresses, a carriage with a conveyor is run along the excavation direction, and the excavated earth and sand is conveyed by the conveyor onto an existing pipe. Therefore, without exchanging the dump truck back and forth, the excavated earth and sand is continuously supplied onto the existing pipe by the above conveyor, and the groove excavation work and the pipe burying work are continuously executed simultaneously. Thus, there is an effect that the pipeline laying work can be efficiently and smoothly performed.
【0058】そして、請求項5記載の装置では、上記台
車が上記溝に沿って走行する際、この溝から外れた位置
に主搬送部を設け、この主搬送部の後端から上記溝へ向
けて搬出部により土砂を搬出するようにしているので、
この搬出部の前方で上記主搬送部が溝内への円滑なパイ
プ搬入作業を妨げるのを防ぐことができる。Further, in the apparatus according to the fifth aspect, when the carriage travels along the groove, a main transport section is provided at a position deviated from the groove, and the main transport section is directed from the rear end to the groove. Since the earth and sand are carried out by the carry-out section,
It is possible to prevent the main carrier section from hindering the smooth pipe carry-in operation into the groove in front of the carry-out section.
【0059】さらに、請求項3,6記載の方法及び装置
では、上記台車上に敷設用のパイプを搭載しながらこの
台車を走行させるようにしているので、パイプ敷設位置
までパイプを搬送するための特別な手段が不要であり、
上記台車上のパイプをそのまま下方の溝に搬入するだけ
の簡単な構成でパイプを敷設できる効果がある。Further, in the method and apparatus according to the third and sixth aspects, since the pipe for laying is mounted on the dolly while the dolly is run, the pipe is transported to the pipe laying position. No special means needed,
There is an effect that the pipe on the dolly can be laid with a simple structure in which the pipe is directly carried into the lower groove.
【0060】特に、請求項7記載の装置では、上記台車
に、上記パイプ搭載部に搭載されたパイプを溝内に搬入
するクレーンを搭載しているので、上記台車と並行して
クレーンを走行させる必要がなく、より少ないスペース
で、かつ簡単な構成で、適当なタイミングでいつでも台
車上でパイプの搬入作業を行うことができる効果があ
る。Particularly, in the apparatus according to the seventh aspect, since the crane for loading the pipe mounted on the pipe mounting portion into the groove is mounted on the truck, the crane is run in parallel with the truck. There is an effect that a pipe can be carried in on a trolley at an appropriate timing at any time with a simple structure that does not require use and requires a smaller space.
【0061】請求項4,8記載の方法及び装置では、上
記台車に溝掘削機を連結してこの掘削機で台車を牽引す
るようにしているので、特別な駆動源を追加することな
く、確実に溝掘削機に追従させながら台車を走行させる
ことができる効果がある。In the method and the apparatus according to claims 4 and 8, since the groove excavator is connected to the bogie and the bogie is towed by the excavator, it is possible to reliably perform the operation without adding a special drive source. In addition, there is an effect that the truck can be driven while following the groove excavator.
【0062】また、請求項2,9記載の方法及び装置で
は、上記掘削溝をまたいで台車が走行するようにしてい
るので、この台車の走行のための幅方向のスペースをよ
り削減でき、交通に与える影響をさらに低減できる効果
がある。しかも、掘削溝が常に上方に開放されるように
台車を構成しているので、溝内へのパイプの円滑な搬入
作業を確保できる。Further, in the method and apparatus according to the second and ninth aspects, since the carriage travels across the excavation groove, the space in the width direction for running the carriage can be further reduced, and the traffic can be reduced. This has the effect of further reducing the effect on the. Moreover, since the bogie is constructed so that the excavation groove is always opened upward, it is possible to ensure the smooth loading work of the pipe into the groove.
【0063】請求項10記載の装置では、上記溝掘削機
の前方に矢板打設装置を設けているので、溝掘削領域に
予め矢板を打設する作業と、この矢板打設位置に対応し
て溝を掘削する作業とを確実にかつ同時に行うことがで
き、作業をより円滑化できる効果がある。In the apparatus according to the tenth aspect of the present invention, since the sheet pile driving device is provided in front of the groove excavating machine, the sheet pile driving operation is carried out in advance in the groove excavating area and the sheet pile driving position is set. The work of excavating the groove can be reliably and simultaneously performed, and the work can be smoothed.
【0064】また、請求項11記載の装置では、上記台
車の下部に、上記コンベアによる土砂搬出位置よりも前
の位置でパイプの端部同士を連結するパイプ連結機を昇
降可能に取付けているので、パイプ連結機を溝内に搬入
する手段を特に設けなくても、台車の下方からパイプ連
結機を繰り出すだけの簡単な構造で適当なタイミングで
パイプ連結をすることができる。Further, in the apparatus according to the eleventh aspect of the present invention, since a pipe connector for connecting the end portions of the pipes to each other is attached to the lower part of the carriage so as to be able to move up and down, at a position prior to the position where the conveyor carries out the sediment. It is possible to connect the pipes at an appropriate timing with a simple structure in which the pipe connector is unwound from the lower side of the carriage, even if no means is specifically provided to carry the pipe connector into the groove.
【0065】特に、請求項12記載の装置では、上記パ
イプ連結機を上記台車に対してその走行方向にスライド
可能に構成しているので、このパイプ連結機による作業
時に同パイプ連結機と台車とをスライドさせることによ
り、台車を止めることなく走行させながらパイプ連結作
業を行うことができ、作業能率をさらに高めることがで
きる効果がある。Particularly, in the device according to the twelfth aspect, since the pipe connector is configured to be slidable with respect to the carriage in the traveling direction, the pipe connector and the carriage can be operated when the pipe connector is operated. By sliding, the pipe connection work can be performed while the carriage is traveling without stopping, and the work efficiency can be further enhanced.
【図1】本発明の一実施例におけるパイプラインの敷設
装置を示す断面側面図である。FIG. 1 is a cross-sectional side view showing a pipeline laying apparatus in an embodiment of the present invention.
【図2】上記パイプラインの敷設装置を示す平面図であ
る。FIG. 2 is a plan view showing the pipeline laying device.
【図3】上記パイプラインの敷設装置の前半部を示す断
面側面図である。FIG. 3 is a sectional side view showing a front half of the pipeline laying device.
【図4】上記パイプラインの敷設装置の前半部を示す平
面図である。FIG. 4 is a plan view showing a front half of the pipeline laying device.
【図5】上記パイプラインの敷設装置の後半部を示す断
面側面図である。FIG. 5 is a cross-sectional side view showing the latter half of the pipeline laying device.
【図6】上記パイプラインの敷設装置の後半部を示す平
面図である。FIG. 6 is a plan view showing the latter half of the pipeline laying device.
【図7】上記パイプラインの敷設装置に設けられるバケ
ットエレベータの内部構造を示す側面図である。FIG. 7 is a side view showing an internal structure of a bucket elevator provided in the pipeline laying device.
【図8】従来方法によるパイプラインの敷設状況を示す
断面側面図である。FIG. 8 is a cross-sectional side view showing a situation of laying a pipeline by a conventional method.
1 ベースマシン(溝掘削機を構成) 3 矢板 7 矢板打設装置 8 バケットエレベータ(溝掘削機を構成) 18 前側台車 22 後側台車 24 第1ベルトコンベア(主搬送部) 26 第2ベルトコンベア(搬出部) 31 パイプ支持板(パイプ搭載部を形成) 32 クレーン 44 溶接・検査機(パイプ連結機) D 溝 G 地盤 P パイプ 1 Base Machine (Constructing a Groove Excavator) 3 Sheet Pile 7 Sheet Pile Driving Device 8 Bucket Elevator (Constructing Groove Excavator) 18 Front Bogie 22 Rear Bogie 24 First Belt Conveyor (Main Conveying Section) 26 Second Belt Conveyor ( Carrying out part 31 Pipe support plate (forming a pipe mounting part) 32 Crane 44 Welding / inspecting machine (pipe connecting machine) D groove G Ground P pipe
Claims (12)
次パイプを敷き、その上に土砂を供給して上記パイプを
地中へ埋めるパイプラインの敷設方法において、上記溝
の掘削の進行に伴ってその掘削方向に沿いコンベアを載
せた台車を走行させ、掘削された土砂を上記コンベアに
より後方へ搬送して既に敷かれているパイプの上へ搬出
することを特徴とするパイプラインの敷設方法。1. A method of laying a pipeline in which a pipe is laid in the groove while digging a groove in the ground, and earth and sand are supplied on the groove to bury the pipe in the ground. With this, a trolley with a conveyor is run along the excavation direction, and the excavated earth and sand is conveyed backward by the conveyor and carried out onto the already laid pipe. Method.
において、上記溝をまたぐようにして上記台車を走行さ
せることを特徴とするパイプラインの敷設方法。2. The pipeline laying method according to claim 1, wherein the trolley is run while straddling the groove.
敷設方法において、上記台車上に敷設用のパイプを搭載
しながらこの台車を走行させることを特徴とするパイプ
ラインの敷設方法。3. The pipeline laying method according to claim 1, wherein the trolley is run while the laying pipe is mounted on the trolley.
ラインの敷設方法において、上記台車を溝掘削機で牽引
することを特徴とするパイプラインの敷設方法。4. The pipeline laying method according to claim 1, wherein the bogie is towed by a groove excavator.
次パイプを敷き、その上に土砂を供給して上記パイプを
地中へ埋めるためのパイプラインの敷設装置において、
走行可能な台車と、この台車上に搭載されるコンベアと
を備え、このコンベアは、上記台車が上記溝に沿って走
行する際にこの溝から側方に外れた位置で上記溝の長手
方向に沿って土砂を搬送する主搬送部と、この主搬送部
の後端から上記溝へ向けて土砂を搬出する搬出部とを有
することを特徴とするパイプラインの敷設装置。5. A pipeline laying device for laying a pipe in the trench while excavating the trench in the ground, and supplying earth and sand to the pipe to bury the pipe in the ground,
It comprises a trolley capable of traveling and a conveyor mounted on the trolley, and the conveyor is in a longitudinal direction of the groove at a position laterally offset from the groove when the trolley travels along the groove. An apparatus for laying a pipeline, comprising: a main carrying section for carrying earth and sand along with a carrying-out section for carrying earth and sand from the rear end of the main carrying section toward the groove.
において、上記台車において上記溝から側方に外れた位
置に敷設用のパイプを搭載するためのパイプ搭載部を設
けたことを特徴とするパイプラインの敷設装置。6. The pipeline laying device according to claim 5, wherein a pipe mounting portion for mounting a pipe for laying is provided at a position laterally offset from the groove in the truck. Pipeline laying equipment.
において、上記台車に、上記パイプ搭載部に搭載された
パイプを溝内に搬入するクレーンを搭載したことを特徴
とするパイプラインの敷設装置。7. The pipeline laying device according to claim 6, wherein the carriage is equipped with a crane for loading the pipe mounted on the pipe mounting portion into a groove. .
ラインの敷設装置において、上記台車を溝掘削機に連結
してこの溝掘削機で台車を牽引するように構成したこと
を特徴とするパイプラインの敷設装置。8. The pipeline laying device according to any one of claims 5 to 7, wherein the truck is connected to a groove excavator, and the truck is towed by the groove excavator. Pipeline laying equipment.
において、上記溝掘削機により掘削された溝をまたいで
上記台車が走行するように溝掘削機への台車の連結位置
を設定するとともに、上記溝を常に上方に開放させるよ
うに上記台車を構成したことを特徴とするパイプライン
の敷設装置。9. The pipeline laying device according to claim 8, wherein the connecting position of the bogie to the groove excavator is set so that the bogie runs across the groove excavated by the groove excavator, A pipeline laying device, characterized in that the carriage is configured so that the groove is always opened upward.
の敷設装置において、上記溝掘削機の前方に矢板打設装
置を設けたことを特徴とするパイプラインの敷設装置。10. The pipeline laying device according to claim 8 or 9, wherein a sheet pile driving device is provided in front of the groove excavator.
イプラインの敷設装置において、上記台車の下部に、上
記コンベアによる土砂搬出位置よりも前の位置でパイプ
の端部同士を連結するパイプ連結機を昇降可能に取付け
たことを特徴とするパイプラインの敷設装置。11. The pipeline laying device according to any one of claims 5 to 10, wherein a pipe is provided at a lower portion of the trolley for connecting end portions of the pipe at a position prior to a position for carrying out earth and sand by the conveyor. A pipeline laying device in which a coupling machine is mounted so that it can be moved up and down.
装置において、上記パイプ連結機を上記台車に対してそ
の走行方向にスライド可能に取付けたことを特徴とする
パイプラインの敷設装置。12. The pipeline laying device according to claim 11, wherein the pipe connector is attached to the carriage slidably in the traveling direction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7012489A JPH08199623A (en) | 1995-01-30 | 1995-01-30 | Pipe line laying method and its device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7012489A JPH08199623A (en) | 1995-01-30 | 1995-01-30 | Pipe line laying method and its device |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH08199623A true JPH08199623A (en) | 1996-08-06 |
Family
ID=11806819
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP7012489A Pending JPH08199623A (en) | 1995-01-30 | 1995-01-30 | Pipe line laying method and its device |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH08199623A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109296376A (en) * | 2018-07-13 | 2019-02-01 | 滨州职业学院 | Pipeline is laid with development machine |
JP2020204212A (en) * | 2019-06-18 | 2020-12-24 | 鹿島建設株式会社 | Linear body installation device, and linear body installation method |
CN113718875A (en) * | 2021-09-07 | 2021-11-30 | 安徽信息工程学院 | Communication pipeline buries device underground |
-
1995
- 1995-01-30 JP JP7012489A patent/JPH08199623A/en active Pending
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109296376A (en) * | 2018-07-13 | 2019-02-01 | 滨州职业学院 | Pipeline is laid with development machine |
CN109296376B (en) * | 2018-07-13 | 2023-10-17 | 滨州职业学院 | Pipeline laying tunneller |
JP2020204212A (en) * | 2019-06-18 | 2020-12-24 | 鹿島建設株式会社 | Linear body installation device, and linear body installation method |
CN113718875A (en) * | 2021-09-07 | 2021-11-30 | 安徽信息工程学院 | Communication pipeline buries device underground |
CN113718875B (en) * | 2021-09-07 | 2022-08-12 | 安徽信息工程学院 | Communication pipeline buries device underground |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5009548A (en) | Apparatus for and a method of facilitating the excavating and refilling of a trench | |
JPH08199623A (en) | Pipe line laying method and its device | |
JP5528049B2 (en) | Tunnel drilling equipment | |
JP2006188907A (en) | Segment carrying system | |
JP3179690B2 (en) | Crane for pipe laying work | |
WO2020100586A1 (en) | Mining system | |
JP4057763B2 (en) | Segment supply method when laying gas pipes | |
JP5279676B2 (en) | Box assembly equipment | |
JP2000008405A (en) | Ground excavating and back-filling device | |
JP2000179286A (en) | Open shield machine | |
JPH0848492A (en) | Suspending transfer device | |
JP2608519B2 (en) | Open shield method for burying small diameter pipes | |
JPH09196235A (en) | Method and device for transporting and laying steel pipe | |
JP3153766B2 (en) | Long object transport trolley | |
JPH0813542A (en) | Digged sediment conveyor | |
JP2703067B2 (en) | Drilling equipment | |
JP3151146B2 (en) | Crane for pipe laying work | |
EA006586B1 (en) | Process and system for the installation of pipelines in shallow or very shallow water | |
JP2001049603A (en) | Ballast scraping machine and ballast scraping method | |
JPH0388610A (en) | Belt conveyer apparatus | |
JPH03228933A (en) | Method and device for laying gutter | |
JP3068496B2 (en) | Caisson Hakouchi drilling rig | |
JP2002364019A (en) | Repair method for embedded pipe | |
JP2001254595A (en) | Tunnel excavating equipment | |
JPH1149483A (en) | Movable crane for underground construction |