JPH08199573A - Earth retaining method in excavation work - Google Patents

Earth retaining method in excavation work

Info

Publication number
JPH08199573A
JPH08199573A JP2452495A JP2452495A JPH08199573A JP H08199573 A JPH08199573 A JP H08199573A JP 2452495 A JP2452495 A JP 2452495A JP 2452495 A JP2452495 A JP 2452495A JP H08199573 A JPH08199573 A JP H08199573A
Authority
JP
Japan
Prior art keywords
groove
gas bag
excavation
gas
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2452495A
Other languages
Japanese (ja)
Inventor
Toshio Sugizaki
俊夫 杉崎
Hiroichi Nomura
博一 野村
Takao Yamamura
隆男 山村
Yuji Ichioka
裕司 市岡
Yasuhiro Matsuo
安弘 松尾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Kokan Koji KK
Original Assignee
Nippon Kokan Koji KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Kokan Koji KK filed Critical Nippon Kokan Koji KK
Priority to JP2452495A priority Critical patent/JPH08199573A/en
Publication of JPH08199573A publication Critical patent/JPH08199573A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE: To prevent the collapse of an excavated ditch simply, safely and surely without using any heavy machine. CONSTITUTION: An air-bag 3a forming a semi-circular recessed groove 5 corresponding to a pipe 2 buried when it is expanded with pressure is placed to an excavated ditch 1 excavated from the ground to pressurize and expand, air-bags 3b, 3c are placed above the air-bag 3a to pressurize and expand, and bearing force against side walls of the excavated ditch 1 is ensured by inside pressure of air-bags 3a, 3b and 3c to maintain a channel shape.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、例えばガス管や上下
水道管との配管を地中に布設する場合の開削土木工事に
おける土留工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an earth retaining method for excavation and civil engineering work in the case of laying pipes such as gas pipes and water and sewer pipes in the ground.

【0002】[0002]

【従来の技術】ガス管,石油導管,上下水道管等の配管
や送電ケ−ブル,通信用光ファイバケ−ブルの保護管な
どを地中に布設する場合には、地上から開削により布設
溝を掘削し、配管を布設,接合,検査,防食工事等を施
工した後、埋め戻し土により埋め戻すいわゆる開削工法
が採用されることが多い。この開削から埋め戻しまでの
工事期間中、開削溝1の側壁の崩壊を防止するために、
例えば図7の断面図に示すように鋼製の矢板21を溝の
側面に沿って打設したのち、腹起し22と切り梁23な
どを所定の間隔に配置していた。
2. Description of the Related Art When laying pipes such as gas pipes, oil pipes, water and sewer pipes, power transmission cables, and protective pipes for optical fiber cables for communication in the ground, a laying groove is made by cutting from the ground. A so-called excavation method is often employed in which the material is excavated, pipes are laid, joined, inspected, and anticorrosion work is performed, and then backfilled with backfill soil. During the construction period from this excavation to backfilling, in order to prevent the side wall of the excavation groove 1 from collapsing,
For example, as shown in the cross-sectional view of FIG. 7, a sheet pile 21 made of steel was driven along the side surface of the groove, and then the uprising 22 and the cut beam 23 were arranged at predetermined intervals.

【0003】そして埋設する管2を開削溝1内に搬入し
て配列するときは上記切り梁23を順次一時的に取外し
て管2を搬入してから取り外した切り梁23を再度設置
しなおしている。この管2の搬入工事を順次行った後、
搬入した管2の位置決め,取付け,接合,検査,塗覆装
などの一連の配管作業を行ってから、開削溝1を埋戻し
土によって埋戻しながら、切り梁23,腹起し22,矢
板21などを順次撤去する作業が起重機,矢板引抜機な
どの重機械を用いて行われてきた。
When the pipes 2 to be buried are carried into the excavation groove 1 and arranged, the cut beams 23 are sequentially temporarily removed, the pipes 2 are carried in, and the cut beams 23 removed are re-installed. There is. After sequentially carrying in the pipe 2,
After carrying out a series of piping work such as positioning, attachment, joining, inspection, coating and the like of the pipe 2 which has been carried in, while the backfill groove 1 is backfilled with backfill soil, the cutting beam 23, the uprising 22, and the sheet pile 21. The work of sequentially removing such items has been performed using heavy machinery such as hoists and sheet pile pullers.

【0004】これら矢板21等の使用は、開削溝1内の
作業の安全を確保するために、特に崩壊の生じやすい土
質条件の地域では不可欠であった。
The use of these sheet piles 21 and the like was indispensable to secure the safety of the work inside the excavation groove 1, especially in the area of soil conditions where collapse is likely to occur.

【0005】また、矢板21の打設の代用として、図8
の斜視図に示すように杭24や杭24とパネル25など
を使用することも行われてきた。
As a substitute for driving the sheet pile 21, FIG.
It has also been practiced to use piles 24 or piles 24 and panels 25 as shown in the perspective view of FIG.

【0006】[0006]

【発明が解決しようとする課題】上記のように開削溝1
の側壁の崩壊を防止するために矢板21を打設する場合
は、矢板21や腹起し22,切り梁23等の仮設材料を
現地に搬送するために大がかりな搬送車両を必要とする
とともに容量が大きい起重機(クレ−ン)を必要とし
た。また、矢板21を打設するための矢板打設機や、撤
去するための矢板引抜機などの重機械を使用しなければ
ならなかった。このように仮設材料を搬送する搬送装置
や打設,撤去するために使用する機械装置類の容量は極
めて大きく、場所が制限される狭隘な工事現場でこれら
の機械装置類を仮置きするスペ−スを確保することは困
難であった。
DISCLOSURE OF THE INVENTION Problems to be Solved by the Invention
When the sheet pile 21 is driven to prevent the collapse of the side wall of the building, a large-scale transport vehicle is required to transport the temporary material such as the sheet pile 21, the uprising 22, and the cut beam 23 to the site, and the capacity is increased. Required a large hoist (crane). Further, heavy machines such as a sheet pile driving machine for driving the sheet pile 21 and a sheet pile pulling machine for removing the sheet pile 21 have to be used. As described above, the capacity of the transporting device for transporting the temporary material and the mechanical devices used for placing and removing the temporary material are extremely large, and a space for temporarily placing these mechanical devices at a narrow construction site where the space is limited. It was difficult to secure the space.

【0007】また、矢板21を搬送したり打設するとき
に騒音や振動を発生し、公害の原因になってしまう。
Further, noise or vibration is generated when the sheet pile 21 is conveyed or placed, which causes pollution.

【0008】さらに、腹起し22や切り梁23の設置と
撤去の際には、しばしば作業者が掘削された溝1の中に
入らざるを得なく、非常に危険な作業となってしまう。
Further, when installing and removing the uprising 22 and the sill 23, the operator is often forced to enter the excavated groove 1, which is a very dangerous work.

【0009】また、開削溝1の崩壊を防ぐため溝側壁に
必要な支持力は、土の含水量の変化,外圧の変化などに
応じて変化する。この土の含水量の変化等に対応して溝
側壁の支持力を増加させたい場合には、矢板21や腹起
し22,切り梁23の増設などが必要となるが、これら
の増設が即応できない場合も生じ、適正な支持力を得る
ことができなくなってしまう場合もある。
Further, the supporting force required for the side wall of the groove for preventing the collapse of the excavation groove 1 changes according to the change of the water content of the soil, the change of the external pressure and the like. If it is desired to increase the bearing capacity of the side wall of the trench in response to changes in the water content of the soil, it is necessary to add sheet piles 21, uprisings 22, and beams 23. In some cases, it may not be possible to obtain the proper supporting force.

【0010】また、矢板21打設の代用として杭24や
杭24とパネル25などを使用する場合も、これらの設
置,撤去に際しては重機械の使用が不可欠であり、矢板
21打設の場合と同様な短所を有した。
Also, when the piles 24 or the piles 24 and the panel 25 are used as a substitute for driving the sheet pile 21, it is indispensable to use a heavy machine when installing and removing them. It had similar disadvantages.

【0011】この発明はかかる短所を改善するためにな
されたものであり、重機械類を使用せずに簡単に、且つ
確実に開削溝の崩壊を防止することができる開削工事に
おける土留工法を提供することを目的とするものであ
る。
The present invention has been made in order to solve the above disadvantages, and provides a soil retaining method in excavation work which can prevent collapse of excavation grooves easily and surely without using heavy machinery. The purpose is to do.

【0012】[0012]

【課題を解決するための手段】この発明に係る開削工事
における土留工法は、地上から開削した掘削溝に、機械
的強度が高く気密性を有する弾性体シ−トで袋状に形成
され、内圧を加えて加圧したときに掘削溝に適合した直
方体状に膨張する気体バックを1又は複数個配置し、該
気体バックに掘削部の土質,地下水位,掘削溝の深さの
よって定められる圧力の気体を封入することを特徴とす
る。
According to the earth retaining method in excavation work according to the present invention, an elastic material sheet having high mechanical strength and airtightness is formed into a bag shape in an excavation groove excavated from the ground, and internal pressure is applied. One or more gas bags that expand in a rectangular parallelepiped shape that is suitable for the excavation groove when placed under pressure are arranged, and the pressure determined by the soil, groundwater level, and depth of the excavation groove in the gas bag. It is characterized by enclosing the gas of.

【0013】また、加圧膨張させたときに配管を布設す
る位置に配管の外径に応じた径の半円状の凹溝を有する
気体バックを掘削溝内に配置して加圧膨張し、形成され
た気体バックの凹溝内に埋設する管を配置することが好
ましい。
Further, a gas bag having a semicircular concave groove having a diameter corresponding to the outer diameter of the pipe is arranged at the position where the pipe is laid when pressurized and expanded, and the gas bag is expanded by pressure, It is preferable to arrange a pipe to be buried in the concave groove of the formed gas bag.

【0014】上記気体バック内に埋設する管軸方向に対
して分割する隔壁を有すると良い。
It is preferable to have a partition wall which is embedded in the gas bag and which is divided in the axial direction of the tube.

【0015】[0015]

【作用】この発明においては、地上から開削した掘削溝
に弾性体シ−トからなる気体バックを配置し、気体バッ
クにあらかじめ定めた圧力の気体を封入し、気体バック
の内圧で開削溝側壁に対する支持力を確保し溝形状を保
持する。
In the present invention, a gas bag made of an elastic sheet is arranged in the excavation groove cut from the ground, a gas having a predetermined pressure is enclosed in the gas bag, and the inner pressure of the gas bag is applied to the side wall of the excavation groove. Secures the supporting force and maintains the groove shape.

【0016】また、加圧膨張させたときに埋設する管に
対応した半円状の凹溝を形成する気体バックを掘削溝内
に配置して加圧膨張し、形成された気体バックの凹溝内
に埋設する管を配置し、埋設する管を保持するとともに
溝周辺の土圧に対向して溝形状を保持する。
Further, a gas bag forming a semi-circular concave groove corresponding to the pipe to be buried when pressurized and expanded is arranged in the excavation groove and pressurized and expanded to form a concave groove of the gas bag. A pipe to be buried is arranged inside, and the pipe to be buried is held and the shape of the groove is maintained so as to face earth pressure around the groove.

【0017】さらに、気体バックを内部に設けた隔壁で
埋設する管軸方向に対して分割して、気体バックを加圧
膨張したときに、所定の形状に保持させる。
Further, the gas bag is divided by a partition wall provided inside to divide the gas bag in the axial direction so that the gas bag is held in a predetermined shape when expanded under pressure.

【0018】[0018]

【実施例】図1はこの発明の一実施例を示す断面図であ
る。図に示すように、開削工法により管2を埋設すると
きは、まず地表面から所定の深さまで掘削して開削溝1
を形成する。次ぎに開削溝1の側壁の崩壊を防止するた
めに、複数の気体バック3a,3b,3cを使用して土
留めを行う。気体バック3a,3b,3cは機械的強度
が高く気密性を有する弾性体シ−ト、例えばポリエステ
ルウレタンゴム等の合成ゴム、塩化ビニル樹脂,フッ素
樹脂等をコ−ティングした布やガラス繊維、あるいはエ
チレン−酢酸ビニル共重合体やポリアミド樹脂,ポリプ
ロピレン等の合成樹脂又はポリビニルホルマ−ル繊維等
で形成されている。この気体バック3a,3b,3cの
大きさと形状は、図2,図3の斜視図に示すように、内
圧を加えて加圧したときに掘削溝1の幅Wに適合した幅
Wbを有し、管1の軸心方向の長さLbはハンドリング
し易いような長さ、例えば1m〜3mの長さの直方体状
に膨張するように形成され、高さHbは開削溝1の深さ
Hに対して気体バックを何分割するかで定まるが、製作
し易さやハンドリング作業の容易さなどから適当な値に
定める。そして気体バック3a,3b,3c内には1又
は複数の隔壁4が設けられ、気体バック3a,3b,3
cに内圧を加えて膨張させたときに、直方体形状を保持
して膨張するようになっている。なお、気体バック3
a,3b,3cの長さが短い場合には隔壁4を省略して
も良い。
1 is a sectional view showing an embodiment of the present invention. As shown in the figure, when the pipe 2 is buried by the excavation method, first, the excavation groove 1 is excavated from the ground surface to a predetermined depth.
To form. Next, in order to prevent the side wall of the excavation groove 1 from collapsing, earth retaining is performed using a plurality of gas bags 3a, 3b, 3c. The gas bags 3a, 3b, 3c are elastic sheet having high mechanical strength and airtightness, for example, synthetic rubber such as polyester urethane rubber, cloth or glass fiber coated with vinyl chloride resin, fluororesin, or the like, or It is formed of an ethylene-vinyl acetate copolymer, a synthetic resin such as a polyamide resin or polypropylene, or a polyvinyl formal fiber. As shown in the perspective views of FIGS. 2 and 3, the size and shape of the gas bags 3a, 3b, 3c have a width Wb adapted to the width W of the excavation groove 1 when the internal pressure is applied. The length Lb of the pipe 1 in the axial direction is formed so as to be easily handled, for example, to be expanded in a rectangular parallelepiped shape having a length of 1 m to 3 m, and the height Hb is the depth H of the cut groove 1. On the other hand, it is determined by how many divisions the gas bag is divided into. Further, one or a plurality of partition walls 4 are provided in the gas bags 3a, 3b, 3c, and the gas bags 3a, 3b, 3
When the internal pressure is applied to c to expand it, the rectangular parallelepiped shape is maintained and expanded. In addition, gas bag 3
When the lengths of a, 3b and 3c are short, the partition wall 4 may be omitted.

【0019】布設する管2の下部に設置される気体バッ
ク3aは、図2の斜視図に示すように、加圧膨張させた
ときに形成される直方体の上面中央の配管を布設する位
置に配管の外径に応じた径の半円状の凹溝5を有し、上
面に気体注入口6を有する。この気体バック3aの上部
に設置する気体バック3bは加圧膨張させたときに形成
される直方体の下面中央に配管の外径に応じた径の半円
状の凹溝5を有し、上面に気体注入口6を有する。
As shown in the perspective view of FIG. 2, the gas bag 3a installed in the lower portion of the pipe 2 to be laid has a pipe formed at the center of the upper surface of the rectangular parallelepiped formed when it is expanded by pressure. Has a semicircular concave groove 5 having a diameter corresponding to the outer diameter of the above, and has a gas injection port 6 on the upper surface. The gas bag 3b installed on the upper part of the gas bag 3a has a semicircular groove 5 having a diameter corresponding to the outer diameter of the pipe in the center of the lower surface of the rectangular parallelepiped formed when the gas bag 3a is expanded under pressure. It has a gas inlet 6.

【0020】次ぎに上記のように構成された気体バック
3a,3b,3cを使用して開削溝1の側壁の崩壊を防
止するために土留めを行うときの作業工程を説明する。
Next, the work steps for earth retaining to prevent the side walls of the excavation groove 1 from collapsing by using the gas bags 3a, 3b, 3c configured as described above will be described.

【0021】まず掘削溝1内に気体バック3aを挿入
し、汎用の現地工事用の可搬形エンジン駆動空気圧縮機
を用い、これに付置されているアキュムレ−タ(圧力0.
6〜0.7MPa)内の圧縮空気を圧力調整器により所定圧
力に減圧し、所定圧力の空気を気体バック3aに設けた
注入口6より充填して気体バック3aの内圧を所定圧力
まで加圧し、気体バック3aを図2に示すように所定の
形状に膨張させ、気体バック3aの長手方向の側面を掘
削溝1の側壁に密着させてから注入口6を閉じて密封す
る。この掘削溝1の開削作業と気体バック3aの挿入,
加圧,膨張作業を所定の長さだけ行った後、気体バック
3aの半円状の凹溝5内に布設する管2を配置する。次
ぎに、気体バック3aと管2の上に気体バック3bを配
置し、気体バック3bを加圧,膨張させる。その後、気
体バック3bの上に溝のない直方体状に膨張する気体バ
ック3cを配置し、気体バック3cを加圧,膨張させ
る。
First, the gas bag 3a is inserted into the excavation trench 1 and a general-purpose portable engine-driven air compressor for field construction is used. The accumulator (pressure 0.
(6 to 0.7 MPa) compressed air is reduced to a predetermined pressure by a pressure regulator, and air having a predetermined pressure is filled from an inlet 6 provided in the gas bag 3a to increase the internal pressure of the gas bag 3a to a predetermined pressure. The gas bag 3a is expanded into a predetermined shape as shown in FIG. 2, the side surface in the longitudinal direction of the gas bag 3a is brought into close contact with the side wall of the excavation groove 1, and then the inlet 6 is closed and sealed. The excavation work of this excavation groove 1 and the insertion of the gas bag 3a,
After performing the pressurizing and expanding operations for a predetermined length, the pipe 2 to be laid is placed in the semicircular groove 5 of the gas bag 3a. Next, the gas bag 3a is arranged on the gas bag 3a and the tube 2, and the gas bag 3b is pressurized and expanded. After that, the gas bag 3c that expands in a rectangular parallelepiped shape without grooves is arranged on the gas bag 3b, and the gas bag 3c is pressurized and expanded.

【0022】このように気体バック3a,3b,3cを
掘削溝1内に逐次配置し加圧,膨張することにより気体
バック3a,3b,3cを掘削溝1の側壁に密着させ、
気体バック3a,3b,3cの内圧で開削溝1の側壁に
対する支持力を確保することができ、開削溝1の溝形状
を保持して開削溝1の側壁が崩壊することを防止できる
とともに管2を所定の位置に保持することができる。
In this way, the gas bags 3a, 3b, 3c are sequentially arranged in the excavation groove 1, and the gas bags 3a, 3b, 3c are brought into close contact with the side walls of the excavation groove 1 by applying pressure and expansion.
The inner pressure of the gas bags 3a, 3b, 3c can secure a supporting force for the sidewall of the excavation groove 1, prevent the collapse of the sidewall of the excavation groove 1 while maintaining the groove shape of the excavation groove 1. Can be held in place.

【0023】開削溝1の側壁が崩壊することを防止する
ために気体バック3a,3b,3cに封入する空気の圧
力は土質や地下水位等により経験的に定める。例えば地
下水位が比較的高く、土質が砂質層の場合について、図
4の断面図を参照して説明する。
The pressure of the air filled in the gas bags 3a, 3b, 3c in order to prevent the side walls of the excavation groove 1 from collapsing is empirically determined depending on the soil quality, the groundwater level, and the like. For example, a case where the groundwater level is relatively high and the soil is a sandy layer will be described with reference to the sectional view of FIG.

【0024】地下水位11が図4に示すように地表面よ
り(H−L)のレベルに存在する場合、開削溝1に内接
し上部を開口した液体バック12に液体、例えば水13
を注入し、開削溝1の側壁の崩壊について行った模擬実
験によれば、地下水位11が変化した場合でも、ほぼ液
体バック12内の水位13aを地下水位11より一定レ
ベルΔHだけプラスの水位に保てば開削溝1の崩壊を防
止できることが判明した。すなわち地下水位11より一
定レベルΔHだけプラスの水位13aによる液圧分布P
(h)に相当する圧力で側壁を支持すれば、開削溝1の
崩壊を防止することが可能になる。例えば管径400Aを
布設する場合、開削溝1の深さH=210cmとすると、
開削溝1側壁の崩壊を防止するのに必要とする圧力Pは
地下水位11が極めて高い場合、例えば(H−L)=30
cmの場合でも、P=ρgh=ρg(L+ΔH)=1gf/
cm3(180+20)=200gf/cm3=0.02MPa程度、すなわち
ΔH=20cm程度で十分といえる。ここでρは液体バッ
ク12に注入した水13の密度、gは重力加速度であ
る。したがって、各気体バック3a,3b,3cに0.02
〜0.03MPaの圧力の圧縮空気を封入することにより、
開削溝1の崩壊を十分に防止することができた。
When the groundwater level 11 exists at a level (HL) from the ground surface as shown in FIG. 4, a liquid, for example water 13
According to a simulation experiment conducted on the collapse of the side wall of the excavation groove 1, even if the groundwater level 11 changes, the water level 13a in the liquid bag 12 is increased to a level above the groundwater level 11 by a certain level ΔH. It has been found that if kept, it is possible to prevent collapse of the excavation groove 1. That is, the hydraulic pressure distribution P due to the water level 13a which is a certain level ΔH above the groundwater level 11
If the side wall is supported by the pressure corresponding to (h), collapse of the cut groove 1 can be prevented. For example, when laying a pipe diameter of 400 A, if the depth H of the excavation groove 1 is 210 cm,
When the groundwater level 11 is extremely high, the pressure P required to prevent collapse of the side wall of the excavation groove 1 is, for example, (HL) = 30.
Even in the case of cm, P = ρgh = ρg (L + ΔH) = 1gf /
It can be said that cm 3 (180 + 20) = 200 gf / cm 3 = 0.02 MPa, that is, ΔH = 20 cm is sufficient. Here, ρ is the density of the water 13 injected into the liquid bag 12, and g is the gravitational acceleration. Therefore, 0.02 is added to each gas bag 3a, 3b, 3c.
By enclosing compressed air with a pressure of ~ 0.03 MPa,
The collapse of the excavation groove 1 could be sufficiently prevented.

【0025】なお、上記実施例は開削溝1の下部に管2
の保持用の半円状の凹溝5を有する2個の気体バック3
a,3bを設置した場合について説明したが、図5に示
すように下部が半円状になったU溝7を有する気体バッ
ク8aと、下部に管2の外径と適合する円弧を有しU溝
7に嵌合する気体バック8bと、直方体形状に膨張する
気体バック8c,8dを使用しても、上記実施例と同様
に開削溝1の崩壊を防止することができる。
In the above embodiment, the pipe 2 is provided in the lower part of the cut groove 1.
Two gas bags 3 having a semicircular groove 5 for holding
Although the case where a and 3b are installed has been described, as shown in FIG. 5, a gas bag 8a having a U-shaped groove 7 having a semicircular lower portion and an arc matching the outer diameter of the pipe 2 are provided at the lower portion. Even if the gas bag 8b fitted into the U groove 7 and the gas bags 8c and 8d that expands into a rectangular parallelepiped shape are used, the collapse of the excavation groove 1 can be prevented as in the above embodiment.

【0026】図5に示した実施例で、例えば公称管径40
0Aの鋼管を開削工法を用いて地中に埋設するときの具
体例を説明する。溝深さHは土かぶりS1と管径Dと下
部クリアランスS2の和で決定される。土かぶりS1は基
準,規則などで定まる値であり、管径400Aに対して例
えば1500mmとする。管の下部クリアランスS2は管の
側面のクリアランスS3とともに埋め戻し時に、埋め戻
し土の充填を十分に行いうる最小値であり、ここでは下
部クリアランスS2を200mm、側面のクリアランスS3
を300mmとする。この場合、開削溝1の深さHは2100
mm、幅Wは1000mmとなる。そして気体バック8a〜
8dの材質として例えば合成樹脂を含浸させた厚さ約1.
5mmの綿布を使用した場合、気体バック8aの幅を開
削溝1の幅Wと同じ寸法1000mmとし、高さを800m
m、長さを1500mmとすると、気体バック9aの重量は
約22.4kgとなる。また気体バック8bを幅400mm、
高さ200mm、長さ1500mmとすると重量は約3kgと
なり、気体バック8cを幅1000mm、高さ800mm、長
さ1500mmとすると重量は約10.5kgとなり、気体バッ
ク8dを幅1000mm、高さ500mm、長さ1500mmとす
ると重量は約8.5kgとなる。したがって気体バック8
a〜8dを簡単に搬送することができるとともに、起重
機等の重機械類を使用せずに掘削溝1に設置することが
できる。
In the embodiment shown in FIG. 5, for example, the nominal pipe diameter 40
A specific example of burying a 0 A steel pipe in the ground by using the excavation method will be described. The groove depth H is determined by the sum of the soil cover S 1 , the pipe diameter D and the lower clearance S 2 . The soil cover S 1 is a value determined by standards, rules, etc., and is 1500 mm for a pipe diameter of 400 A, for example. The lower clearance S 2 of the pipe together with the clearance S 3 on the side surface of the pipe is the minimum value that can sufficiently fill the backfill soil at the time of backfilling. Here, the lower clearance S 2 is 200 mm and the clearance S 3 on the side surface.
Is set to 300 mm. In this case, the depth H of the digging groove 1 is 2100
mm, the width W is 1000 mm. And the gas bag 8a-
The material of 8d is, for example, synthetic resin impregnated with a thickness of about 1.
When using a 5 mm cotton cloth, the width of the gas bag 8a is 1000 mm, which is the same as the width W of the cut groove 1, and the height is 800 m.
Assuming m and length of 1500 mm, the weight of the gas bag 9a is about 22.4 kg. The gas bag 8b has a width of 400 mm,
If the height is 200 mm and the length is 1500 mm, the weight is about 3 kg. If the gas bag 8c is 1000 mm in width, 800 mm in height and 1500 mm in length, the weight is about 10.5 kg, and the gas bag 8d is 1000 mm in width, 500 mm in height and long. If it is 1500 mm, the weight will be about 8.5 kg. Therefore, the gas bag 8
The a to 8d can be easily transported and can be installed in the excavation trench 1 without using heavy machinery such as a hoist.

【0027】上記実施例は地山の自立性が比較的高く、
開削溝1を掘削してから管2を吊り降ろす時間的余裕が
ある場合について説明したが、地山の自立性が低く、開
削溝1を掘削したのち直ちに山留めする必要がある場
合、あるいは開削溝1を掘削してから管2を布設するま
での間に時間を要する場合の実施例について説明する。
In the above embodiment, the independence of the ground is relatively high,
The case where there is time to hang the pipe 2 after excavating the excavation groove 1 has been explained, but when the excavation groove 1 has to be excavated immediately after the excavation groove 1 is excavated, or when the excavation groove is excavated, An example in which it takes time from the excavation of the pipe 1 to the installation of the pipe 2 will be described.

【0028】この場合は開削溝1を掘削したら、図6の
断面図に示すように、気体バック3a,3bと同様に一
面に管2の保持用の半円状の凹溝5を有する気体バック
9a,9bを開削溝1内に相対して設置し、気体バック
9a,9bを加圧,膨張させて開削溝1の下部を山留め
する。その後、溝のない気体バック9c、9dを順次設
置して加圧,膨張させて山留めを行う。この工事を逐次
繰り返して所定スパ−ンの掘削と山留めが終了したら、
気体バック9a,9bの半円状の凹溝5で形成している
孔内に管2を水平に引き込む。このようにして開削溝1
を掘削したのち直ちに山留めすることができ、管2を安
全に設置することができる。
In this case, after the excavation groove 1 is excavated, as shown in the sectional view of FIG. 6, a gas bag having a semicircular concave groove 5 for holding the pipe 2 on one surface is formed in the same manner as the gas bags 3a and 3b. 9a and 9b are installed opposite to each other in the excavation groove 1, and the gas bags 9a and 9b are pressurized and expanded to clamp the lower part of the excavation groove 1. After that, gas bags 9c and 9d having no groove are sequentially installed and pressurized and expanded to carry out mountain retaining. After repeating this work one after another, when excavation of the specified span and mountain retaining are completed,
The tube 2 is horizontally drawn into the hole formed by the semicircular groove 5 of the gas bags 9a and 9b. In this way the digging groove 1
After excavating, the mountain can be clamped immediately and the pipe 2 can be installed safely.

【0029】また、上記各実施例は気体バックに封入す
る加圧空気を汎用の現地工事用の可搬形エンジン駆動空
気圧縮機を用いて供給した場合について説明したが、空
気や窒素等が加圧封入された圧力容器を用いて加圧気体
を供給するようにすると、工事中の騒音を著しく低減す
ることができる。
In each of the above embodiments, the case where the pressurized air to be enclosed in the gas bag is supplied by using the general-purpose portable engine-driven air compressor for on-site construction has been described. When the pressurized gas is supplied using the enclosed pressure vessel, noise during construction can be significantly reduced.

【0030】また、上記各実施例は気体バックに加圧気
体を封入する場合について説明したが、開削溝1の周囲
より漏水等があり、開削溝1内に侵入水がある場合は気
体バックに浮力が作用し、気体バックが浮上するおそれ
がある場合には、気体バック内に侵入水の水位と同じ水
位になる水を加圧気体とともに封入することにより、気
体バックの浮上を防止することができる。
In each of the above embodiments, the case where the pressurized gas is enclosed in the gas bag has been described. However, if there is water leaking from the periphery of the excavation groove 1 and there is intruding water in the excavation groove 1, the gas bag is filled with the gas bag. If buoyancy acts and the gas bag may float, it is possible to prevent the gas bag from rising by enclosing water with the pressurized gas in the gas bag at the same level as the water level of the intruding water. it can.

【0031】[0031]

【発明の効果】この発明は以上説明したように、地上か
ら開削した掘削溝に弾性体シ−トからなる気体バックを
配置し、気体バックにあらかじめ定めた圧力の気体を封
入し、気体バックの内圧で開削溝側壁に対する支持力を
確保し溝形状を保持するようにしたから、矢板,腹起
し,切り梁等の仮設材料を使用しなくても確実に開削溝
の山留めを行うことができる。したがって矢板等の仮設
材料を運搬する大型の車両や起重機等の重機械類を使用
しなくても良いから、重機械類の保管スペ−スを不要に
することができるとともに工事中の騒音や振動を低減す
ることができる。
As described above, according to the present invention, the gas bag made of the elastic sheet is arranged in the excavation groove cut from the ground, and the gas having a predetermined pressure is sealed in the gas bag. Since the support force against the side wall of the excavation groove is secured by the internal pressure and the groove shape is maintained, it is possible to securely clamp the excavation groove without the use of temporary materials such as sheet pile, uprising, and cut beams. . Therefore, it is not necessary to use large vehicles such as sheet piles and heavy machinery such as hoists to carry temporary materials, so the storage space for heavy machinery can be eliminated and noise and vibration during construction can be eliminated. Can be reduced.

【0032】また、加圧膨張させたときに埋設する管に
対応した半円状の凹溝を形成する気体バックを掘削溝内
に配置して加圧膨張し、形成された気体バックの凹溝内
に埋設する管を配置するから、埋設する管を確実に保持
することができるとともに溝周辺の土圧に対向して溝形
状を保持することができる。
Further, a gas bag forming a semi-circular concave groove corresponding to the pipe to be buried when pressurized and expanded is arranged in the excavation groove and pressurized and expanded to form a concave groove of the gas bag. Since the pipe to be buried is arranged inside, the pipe to be buried can be reliably held and the groove shape can be held so as to face the earth pressure around the groove.

【0033】さらに、気体バックを内部に設けた隔壁で
埋設する管軸方向に対して分割して、気体バックを加圧
膨張したときに、所定の形状に保持させるから、気体バ
ックの形状を開削溝の形状に合わせて保持することがで
き、開削溝の崩壊を確実に防止することができる。
Further, since the gas bag is divided with respect to the axial direction of the pipe to be embedded by the partition wall provided inside and is held in a predetermined shape when the gas bag is expanded under pressure, the shape of the gas bag is excavated. It can be held according to the shape of the groove, and the collapse of the open-cut groove can be reliably prevented.

【0034】また、気体バックは重量が小さく、気体を
封入する前は折畳むことができるから、容積も極めて小
さくすることができ、容易に運搬できるとともに工事現
場に保管スペ−スを必要としないですむ。
Further, since the gas bag has a small weight and can be folded before enclosing the gas, the volume can be made extremely small, and the bag can be easily transported without requiring a storage space at the construction site. OK.

【0035】また、溝掘り作業の進行に合わせて気体バ
ックを運搬,配列して加圧気体を封入すれば良いから、
特別の重機や装置を必要とせず、容易に人力で作業を行
うことができ、山留め作業の時間を従来の1/10〜1/
50以下に短縮することができる。
Further, since the gas bags may be transported and arranged in accordance with the progress of the trench digging work and the pressurized gas may be enclosed therein,
No special heavy machinery or equipment is required, and the work can be done easily by manpower.
It can be shortened to 50 or less.

【0036】さらに、開削溝の表面を気体バックで覆う
ので、作業者が溝内に転落したり、作業工具等が落下す
ることを防止することができ、作業の安全性を高めると
ともに配管の損傷を防止することができる。
Furthermore, since the surface of the open-cut groove is covered with a gas bag, it is possible to prevent the operator from falling into the groove and the work tools from falling, which improves the safety of the work and damages the pipe. Can be prevented.

【0037】また、気体バックに封入する気体の圧力を
調整することにより側壁支持力を容易に調節できるか
ら、地下水位の変化、降雨等による土砂の流動化等によ
り開削溝の側壁に作用する土圧の変化に対しても簡単に
対応することができる。
Further, since the side wall supporting force can be easily adjusted by adjusting the pressure of the gas filled in the gas bag, the soil acting on the side wall of the excavation groove due to the change of the groundwater level, the fluidization of the sediment due to rainfall, etc. It is possible to easily respond to changes in pressure.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明の実施例を示す断面図である。FIG. 1 is a sectional view showing an embodiment of the present invention.

【図2】上記実施例の気体バックを示す斜視図である。FIG. 2 is a perspective view showing a gas bag of the above embodiment.

【図3】上記実施例の他の気体バックを示す斜視図であ
る。
FIG. 3 is a perspective view showing another gas bag of the above embodiment.

【図4】上記実施例の動作原理を示す断面図である。FIG. 4 is a cross-sectional view showing the operating principle of the above embodiment.

【図5】この発明の第2の実施例を示す断面図である。FIG. 5 is a sectional view showing a second embodiment of the present invention.

【図6】この発明の第3の実施例を示す断面図である。FIG. 6 is a sectional view showing a third embodiment of the present invention.

【図7】従来例を示す斜視図である。FIG. 7 is a perspective view showing a conventional example.

【図8】他の従来例を示す斜視図である。FIG. 8 is a perspective view showing another conventional example.

【符号の説明】[Explanation of symbols]

1 開削溝 2 管 3a,3b,3c 気体バック 4 隔壁 5 凹溝 7a,7b,7c,7d 気体バック 9a,9b,9c,9d 気体バック 1 Open-cut grooves 2 Pipes 3a, 3b, 3c Gas bag 4 Partition walls 5 Recessed grooves 7a, 7b, 7c, 7d Gas bag 9a, 9b, 9c, 9d Gas bag

フロントページの続き (72)発明者 松尾 安弘 神奈川県厚木市下津古久122−6Continuation of the front page (72) Inventor Yasuhiro Matsuo 122-6, Shimotsuko, Atsugi, Kanagawa

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】地上から開削した掘削溝に、機械的強度が
高く気密性を有する弾性体シ−トで袋状に形成され、内
圧を加えて加圧したときに掘削溝に適合した直方体状に
膨張する気体バックを1又は複数個配置し、該気体バッ
クに掘削部の土質,地下水位,掘削溝の深さによって定
められる圧力の気体を封入することを特徴とする開削工
事における土留工法。
1. A rectangular parallelepiped which is formed in a bag shape in an excavation groove excavated from the ground by an elastic sheet having high mechanical strength and airtightness and adapted to the excavation groove when an internal pressure is applied. A soil retaining method in excavation work, characterized in that one or a plurality of expanding gas bags are arranged, and a gas having a pressure determined by the soil quality of the excavation portion, the groundwater level, and the depth of the excavation groove is enclosed in the gas bag.
【請求項2】 加圧膨張させたときに配管を布設する位
置に配管の外径に応じた径の半円状の凹溝を有する気体
バックを掘削溝内に配置して加圧膨張し、形成された気
体バックの凹溝内に埋設する管を配置する請求項1記載
の開削工事における土留工法。
2. A gas bag having a semicircular concave groove having a diameter corresponding to the outer diameter of the pipe at the position where the pipe is laid when pressurized and expanded is placed in the excavation groove and expanded under pressure. The earth retaining method for excavation work according to claim 1, wherein a pipe to be buried is arranged in the formed groove of the gas bag.
【請求項3】 上記気体バック内に埋設する管軸方向に
対して分割する隔壁を有する請求項1又は2記載の開削
工事における土留工法。
3. The earth retaining method for excavation work according to claim 1 or 2, further comprising a partition wall which is embedded in the gas bag and which is divided in a pipe axis direction.
JP2452495A 1995-01-20 1995-01-20 Earth retaining method in excavation work Pending JPH08199573A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2452495A JPH08199573A (en) 1995-01-20 1995-01-20 Earth retaining method in excavation work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2452495A JPH08199573A (en) 1995-01-20 1995-01-20 Earth retaining method in excavation work

Publications (1)

Publication Number Publication Date
JPH08199573A true JPH08199573A (en) 1996-08-06

Family

ID=12140554

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2452495A Pending JPH08199573A (en) 1995-01-20 1995-01-20 Earth retaining method in excavation work

Country Status (1)

Country Link
JP (1) JPH08199573A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005155680A (en) * 2003-11-20 2005-06-16 Hiroshi Shimokawa Underground pipe laying method and laying device used in it
GB2525954A (en) * 2011-10-28 2015-11-11 Perry Williamson Support for an excavation
CN106996902A (en) * 2017-04-28 2017-08-01 浙江科技学院 Foundation Pit bottom stability test device containing artesian water stratum

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005155680A (en) * 2003-11-20 2005-06-16 Hiroshi Shimokawa Underground pipe laying method and laying device used in it
GB2525954A (en) * 2011-10-28 2015-11-11 Perry Williamson Support for an excavation
GB2525954B (en) * 2011-10-28 2016-06-15 Williamson Perry Support for an excavation
US10087595B2 (en) 2011-10-28 2018-10-02 Perry Williamson Support for an excavation
CN106996902A (en) * 2017-04-28 2017-08-01 浙江科技学院 Foundation Pit bottom stability test device containing artesian water stratum
CN106996902B (en) * 2017-04-28 2023-10-13 浙江科技学院 Foundation pit bottom stability testing device containing pressure-bearing water stratum

Similar Documents

Publication Publication Date Title
US5765967A (en) Method and apparatus for backfilling pipeline trenches
US4714379A (en) Pipelay in slurry trench
JPH08199573A (en) Earth retaining method in excavation work
EP0842331B1 (en) Method and apparatus for backfilling padded underground structures
JP3066293B2 (en) Earth retaining method in excavation works
JP2006022551A (en) Continuous underground wall and earth retaining method
JPH09144000A (en) Method and device for retaining earth
JP2000134779A (en) Light-weight unit tube
JP3093937B2 (en) Pipe laying method
JPH08260466A (en) Trench timbering, and bag body for timbering
JPH08261360A (en) Laying method for underground buried pipe
JPH0634076A (en) Subsidence preventive method for buried pipe conduit by civil engineering work sheet
EP0062808A1 (en) Method and apparatus of constructing a novel underground impervious barrier
JP3248441B2 (en) Pipe laying method and apparatus
JPS5914667B2 (en) How to lay pipes
JPH0949222A (en) Construction method for underground buried pipe making use of earth retaining bag body
JP2002275897A (en) Earth retaining method for open-cut ditch
JPH11323887A (en) Method for sinking pipeline and equipment therefor
JP3080840B2 (en) How to remove underground pipes
JPH07180160A (en) Construction method of settlement vertical shaft used for man-hole and edge for settlement acceleration
JP2592901B2 (en) How to put a long pipe into the groove in sheet pile construction
JPH02232429A (en) Foundation execution for pipeline
JPH03241196A (en) Earthwork for underground piping
JPH038999A (en) Construction of large space under soft ground
JP3242534B2 (en) How to install protection pipes for underground pipes