JPH0814350B2 - Civil engineering method for underground pipes - Google Patents

Civil engineering method for underground pipes

Info

Publication number
JPH0814350B2
JPH0814350B2 JP2134154A JP13415490A JPH0814350B2 JP H0814350 B2 JPH0814350 B2 JP H0814350B2 JP 2134154 A JP2134154 A JP 2134154A JP 13415490 A JP13415490 A JP 13415490A JP H0814350 B2 JPH0814350 B2 JP H0814350B2
Authority
JP
Japan
Prior art keywords
pipe
groove
space
work
civil engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2134154A
Other languages
Japanese (ja)
Other versions
JPH0429689A (en
Inventor
治 荒田
利昭 河合
桂樹 大野
文彦 岩下
紀美夫 佐藤
Original Assignee
日本鋼管工事株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 日本鋼管工事株式会社 filed Critical 日本鋼管工事株式会社
Priority to JP2134154A priority Critical patent/JPH0814350B2/en
Publication of JPH0429689A publication Critical patent/JPH0429689A/en
Publication of JPH0814350B2 publication Critical patent/JPH0814350B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Sewage (AREA)

Description

【発明の詳細な説明】 [産業上の利用分野] この発明は、例えば石油導管やガス管,水道管,通信
用ケーブルを通す管等の地中埋設管の土木施工法,特に
施工能率の向上に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Industrial field of application] The present invention relates to a method for civil engineering construction of underground buried pipes such as oil pipes, gas pipes, water pipes, and pipes for communication cables, and particularly improvement of construction efficiency. It is about.

[従来の技術] 石油導管やガス管,水道管等を地中に埋設するとき
は、石油導管等を保護するために地表から一定の深さ以
上の所に埋設する必要がある。
[Prior Art] When burying oil pipes, gas pipes, water pipes, etc. in the ground, it is necessary to bury them at a certain depth or more from the ground surface to protect the oil pipes.

この石油導管やガス管等を埋設するときは、まず埋設
する一の路面の舗装こわしを行ない、単位長さ分だけ掘
削して土砂を撤去してから山留めと水替えを行なう。次
に、掘削した溝内に管を配設して、先に埋設した管と溶
接・接合した後埋戻しを行なう。このように管を埋設す
るときは施工開始から終了まで土木作業と配管作業が一
連の順序で行なわれる。
When burying these oil pipes and gas pipes, first, the road surface to be buried is torn down, the unit length is excavated to remove the earth and sand, and then earth retaining and water replacement. Next, a pipe is arranged in the excavated groove, and after being welded / joined with the previously buried pipe, backfilling is performed. When burying pipes in this way, civil works and piping work are performed in a series of sequence from the start to the end of construction.

そして、溝を形成するときには、配管作業中に路盤等
が崩壊することを防ぐために充分な注意をして山留め及
び水替えを行なう。また管を配設してから埋戻しを行な
うときは裏込めの部分で管が偏圧を受けないように、受
戻しの土砂を厚さが20〜30cm程度になるように左右同厚
にまき出し、まき出した土砂の上をランマーやタンパな
どにより丁寧に締固める転圧を行なって、まき出した土
砂の水密性と強度を増大させている。この転圧を繰返し
て行ない掘削した溝の埋戻しを行なっている。
Then, when forming the groove, the mountain retaining and water change should be performed with sufficient care to prevent the roadbed or the like from collapsing during the piping work. Also, when backfilling is performed after the pipe is placed, spread the earth and sand of the receiving back to the same thickness on the left and right so that the backfilling part does not receive unbalanced pressure. By carefully compacting the unloaded and unwound earth and sand with a rammer or tamper, compaction is performed to increase the watertightness and strength of the unwound earth and sand. This rolling is repeated to backfill the excavated trench.

[発明が解決しようとする課題] 上記のように管を埋設する場合には、掘削,埋戻し等
の土木作業との間に、配管,溶接,検査等の鉄工作業が
入る。例えば、1日に8時間の作業を行なうとすると、
掘削作業を3時間行なった後に配管,溶接等の鉄工作業
を3時間行ない、その後埋戻作業を2時間行なう。この
ため、土木作業を行なっている作業者は鉄工作業中は遊
んでしまい、鉄工作業は1日のうち2〜3時間しか仕事
がなく、土木作業を5人の作業者が行ない、溶接,検査
等の鉄工作業を3人の作業者が行なっても1日の埋設距
離は20m程度であり、非常に能率が悪いという短所があ
った。
[Problems to be Solved by the Invention] In the case of burying a pipe as described above, an ironworking work such as piping, welding, and inspection is performed between civil works such as excavation and backfilling. For example, if you work 8 hours a day,
After excavation work is performed for 3 hours, ironing work such as piping and welding is performed for 3 hours, and then backfilling work is performed for 2 hours. For this reason, the workers who are doing the civil engineering work are idle during the ironworking work, and the ironworking work is done only for 2 to 3 hours a day, and the civil engineering work is performed by 5 workers, welding, and inspection. Even if three workers perform the ironing work, etc., the burial distance per day is about 20 m, which is very inefficient.

また、配管作業の安全を図るために堅固な山留め,水
替を行なう必要があり、その作業が容易でなかった。
Further, in order to secure the safety of the piping work, it is necessary to firmly mount the mountain and perform water replacement, which is not easy.

さらに、溶接時の管合せを行なう場合に、管端面の直
角度が多少出ていない場合には、新しく設置した管を左
右,上下に若干傾けて溶接部のクリアランスを均一にし
ている。このため、掘削口を広く、かつ深くとる必要が
あるという短所があった。
Further, when the pipes are aligned at the time of welding, if the squareness of the pipe end faces does not appear to a certain extent, the newly installed pipe is tilted slightly to the left and right and up and down to make the weld clearance uniform. Therefore, there is a disadvantage that the excavation hole needs to be wide and deep.

また、埋戻しには良質な土砂を大量に必要とし、その
土砂を丁寧に締固めるため費用がかかるという短所があ
った。
In addition, there is a disadvantage in that a large amount of good quality sand is required for backfilling, and it is expensive to carefully compact the sand.

また、実際に埋設管を設置し埋度しを行なうときに、
長い埋設管のすべての範囲にわたって十分な転圧を行な
うことは困難であり、場合によっては締固めが不充分な
箇所が生じる危険性がある。このような不正確の転圧部
があると管埋設部に陥没が生じ、過大な土圧が埋設管に
作用して管本体に亀裂が折損が生じたり、あるいは径手
部が抜けるなどの損傷事故を起こす可能性があるという
短所があった。
Also, when actually installing a buried pipe and performing filling,
It is difficult to achieve sufficient compaction over the entire range of a long buried pipe, and in some cases there is a risk of insufficient compaction. If there is such an inaccurate rolling part, the buried part of the pipe will be depressed, and excessive earth pressure will act on the buried pipe, causing cracks in the pipe body or damage such as falling out of the diameter part. It had the disadvantage that it could cause an accident.

さらに、土木作業に時間がかかると交通規制時間が長
くなり、交通の渋滞等が生じ易いという短所もあった。
Further, if the civil engineering work takes a long time, the traffic regulation time becomes long, and there is a disadvantage that traffic congestion is likely to occur.

この発明はかかる短所を解決するためになされたもの
であり、土木作業と配管等の鉄工作業を分離し、管の埋
設を能率良く行なうことができる地中埋設等の土木施工
法を提案することを目的とするものである。
The present invention has been made in order to solve the above disadvantages, and proposes a civil engineering method such as underground burial that can efficiently perform the burial of pipes by separating the civil engineering work and the ironwork work such as piping. The purpose is.

[課題を解決するための手段] この発明に係る地中埋設管の土木施工法は、土砂を掘
削して形成した溝内部に埋設管の断面積より大きな中空
空間のU字溝を有する空間確保材をU字溝を下に向けて
設置し、空間確保材上の溝を埋度して空間確保材を固定
し、固定した空間確保材の中間空間に埋設管を引き込み
配管してから、空間確保材と埋設管との空隙に充填材を
充填することを特徴とする。
[Means for Solving the Problem] A method for constructing an underground buried pipe according to the present invention is to secure a space having a U-shaped groove having a hollow space larger than a cross-sectional area of the buried pipe inside a groove formed by excavating earth and sand. Install the material with the U-shaped groove facing down, fill the groove on the space securing material to fix the space securing material, draw the embedded pipe into the intermediate space of the fixed space securing material, and then pipe the space. It is characterized in that the space between the securing material and the buried pipe is filled with a filling material.

[作用] この発明においては、土砂を掘削して形成した溝に中
空空間を有する空間確保材を設置し、空間確保材で溝側
壁の土砂が崩壊することを防ぎ、山留めを不要とする。
[Operation] In the present invention, the space securing material having a hollow space is installed in the groove formed by excavating the soil, and the space securing material is prevented from collapsing the soil on the side wall of the groove, thereby eliminating the need for mountain retaining.

また、空間確保材を設置した後、空間確保材上部の溝
を埋戻して土木作業を終了し、短時間で交通規制を解除
する。
In addition, after installing the space securing material, the groove above the space securing material is backfilled to finish the civil engineering work, and the traffic regulation is lifted in a short time.

また、固定した空間確保材の中空空間内に埋設用の管
を吹き込み配管することにより、配管作業を容易かつ迅
速に行なうことができる。
In addition, the piping work can be performed easily and quickly by blowing a pipe for embedding into the hollow space of the fixed space securing material.

さらに、配管後中空空間内に充填材を充填して埋設管
を固定し、埋設管を充填材と空間確保材で覆うことによ
り、埋設管に作用する鉛直土圧等の付加荷重を軽減する
ことができる。
Furthermore, by filling the hollow space after piping with the filling material to fix the buried pipe and covering the buried pipe with the filling material and the space securing material, the additional load such as vertical earth pressure acting on the buried pipe is reduced. You can

[実施例] 第1図(a)〜(f)はこの発明の一実施例の施工工
程を示す断面図である。地中1に管3を埋設する場合
は、第1図(a)に示すように、まず、地中1を単位長
さ掘削して所定の土かぶりとなる深さDの溝2を形成す
る。次に、第1図(b)に示すように、溝2に空間確保
材として中空部4を有し、コンクリートや鋼材等からな
るU字側溝5を上部が覆われるようにして設置する。こ
のようにU字側溝5を溝2内に設置することにより、溝
2側壁の土砂をU字側溝5のU字部で抑えることがで
き、山留めなしに次工程の作業を行なうことができる。
[Embodiment] FIGS. 1 (a) to 1 (f) are sectional views showing construction steps of an embodiment of the present invention. When burying the pipe 3 in the ground 1, first, as shown in FIG. 1 (a), the ground 1 is excavated by a unit length to form a groove 2 having a depth D that provides a predetermined soil cover. . Next, as shown in FIG. 1 (b), the groove 2 has a hollow portion 4 as a space securing member, and a U-shaped groove 5 made of concrete or steel is installed so that its upper portion is covered. By installing the U-shaped groove 5 in the groove 2 in this way, the sediment on the side wall of the groove 2 can be suppressed by the U-shaped portion of the U-shaped groove 5, and the work of the next step can be performed without clogging.

単位長さ掘削して形成した溝2内にU字側溝5を全て
設置してから、第1図(c)に示すようにU字側溝5の
上部を土砂6で埋戻して、U字側溝5を固定する。この
埋戻しのときに、U字側溝5の上部のみを土砂6で埋戻
せば良いから埋戻土を減少することができ、埋戻し工事
の時間を低減することができる。
After installing all the U-shaped gutters 5 in the groove 2 formed by excavating the unit length, the upper part of the U-shaped gutter 5 is backfilled with earth and sand 6 as shown in FIG. Fix 5 At the time of this backfilling, since only the upper part of the U-shaped gutter 5 needs to be backfilled with the earth and sand 6, the backfilling soil can be reduced and the time for backfilling work can be shortened.

溝2を土砂6で埋戻しした後、土砂6上にアスファル
トコンクリート及び砕石7を敷き、転圧して溝2を完全
に埋戻す。
After the groove 2 is backfilled with the earth and sand 6, the asphalt concrete and the crushed stone 7 are spread on the earth and sand 6, and the groove 2 is completely backfilled by rolling.

溝2を埋戻したら配管作業部に、第2図に示すよう
に、埋設する管3の径と長さに応じた大きさの配管・接
合用溝8を掘削する。この配管・接合用溝8を通して、
第1図(e)に示すようにU字側溝5の中空部4に管3
を引き込む。そして中空部4に設けられた前後の管3を
溶接等により接合し配管する。その後、第1図(f)に
示すように、管3とU字側溝5との間の中空部4に、例
えば発泡スチロール等の充填材9を充填して管3を固定
する。管3の固定が終ったら配管・接合用溝8を埋戻
す。
After the groove 2 is backfilled, as shown in FIG. 2, a pipe / joining groove 8 having a size corresponding to the diameter and length of the pipe 3 to be buried is excavated in the pipe working portion. Through this piping / joining groove 8,
As shown in FIG. 1 (e), the pipe 3 is inserted in the hollow portion 4 of the U-shaped groove 5.
Pull in. Then, the front and rear pipes 3 provided in the hollow portion 4 are joined by welding or the like to form a pipe. Thereafter, as shown in FIG. 1 (f), the hollow portion 4 between the pipe 3 and the U-shaped groove 5 is filled with a filling material 9 such as styrofoam to fix the pipe 3. When the fixing of the pipe 3 is completed, the pipe / joining groove 8 is backfilled.

このようにU字側溝5からなる空間確保材の中空部4
に埋設用の管3を引き込み配管することができるから、
配管作業を容易かつ迅速に行うことができる。
In this way, the hollow portion 4 of the space securing member including the U-shaped side groove 5
Since the pipe 3 for burying can be drawn in and piped,
The piping work can be performed easily and quickly.

また、管3を配管後中空部4内に従て材9を充填して
管3を固定し、埋設された管3を充填材9とU字側溝5
で覆うことにより、埋設された管3に作用する鉛直土圧
等の付加荷重を大幅に軽減することができる。
Further, the pipe 3 is filled with the material 9 in accordance with the inside of the hollow portion 4 after the pipe 3 is fixed, and the buried pipe 3 is filled with the filling material 9 and the U-shaped groove 5.
By covering with, it is possible to significantly reduce the additional load such as vertical earth pressure acting on the buried pipe 3.

このようにして管3を埋設するときに、土木作業と入
か等の鉄工作業を分離して行なうことができる。したが
って、土木作業の間に鉄工作業を入れる必要はなく、掘
削したあとから順次U字側溝5の配列と埋戻を行なって
いくと、例えば、1日に8時間の作業を行なう場合に、
掘削作業,配列作業及び埋戻作業を1日にそれぞれ6時
間行なうことができ、5人の作業者で土木作業を40m行
なうことができる。
In this way, when the pipe 3 is buried, the civil engineering work and the ironing work such as entering can be performed separately. Therefore, it is not necessary to enter ironwork during civil engineering work, and if the arrangement of U-shaped gutters 5 and backfilling are sequentially performed after excavation, for example, when performing work for 8 hours a day,
Excavation work, array work and backfill work can be performed for 6 hours each day, and 5 workers can perform civil engineering work for 40 m.

このため、例えば80mの距離を埋設するとすると、従
来の施工法によると土木作業と鉄工作業に4日間の施工
日数を必要とするが、この実施例によると、土木作業を
5人の作業者で2日間で行なうことができ、その後、従
来と同様に3人の作業者で配管等の鉄工作業を1人で行
なうことができ、施工日数と施工工数を大幅に低減する
ことができる。
Therefore, for example, if a distance of 80 m is buried, according to the conventional construction method, the civil engineering work and the ironworking work require four working days, but according to this embodiment, the civil engineering work is performed by five workers. The work can be performed in two days, and thereafter, as in the conventional case, three workers can perform the ironing work such as piping by one person, and the working days and the working man-hours can be significantly reduced.

なお、上記実施例においては、溝2内に中空部4を形
成する空間確保材としてU字割溝5を使用した場合につ
いて説明したが、空間確保材として中空空間を有するコ
ンクリート・ボックスや角形鋼管,硬質塩化ビニル管あ
るいは強化プラスチック管等を使用しても、上記実施例
と同様な作用を奏することができる。
In the above-mentioned embodiment, the case where the U-shaped dividing groove 5 is used as the space securing material for forming the hollow portion 4 in the groove 2 has been described, but a concrete box or a rectangular steel pipe having a hollow space as the space securing material is described. Even if a hard vinyl chloride pipe, a reinforced plastic pipe or the like is used, the same operation as in the above embodiment can be achieved.

[発明の効果] この発明は以上説明したように、土砂を掘削して形成
した溝にU字溝からなる中空空間を有する空間確保材を
設置し、空間確保材で溝側壁の土砂が崩壊することを防
ぐことができるから、掘削した溝の山留めを省略するこ
とができる。
[Effects of the Invention] As described above, according to the present invention, a space securing material having a hollow space composed of a U-shaped groove is installed in a groove formed by excavating the earth and sand, and the soil on the side wall of the groove collapses by the space securing material. Since this can be prevented, the retaining of the excavated trench can be omitted.

また、埋戻しを行なうときに、空間確保材の上部のみ
を埋戻せば良いから、埋戻土を減少することができ、埋
戻し工事の費用と時間を低減することができる。
In addition, since only the upper part of the space securing material needs to be backfilled when performing backfilling, backfilling soil can be reduced and the cost and time for backfilling work can be reduced.

また、固定した空間確保材の中空空間内に埋設用の管
を引き込み配管することにより、配管作業を容易かつ迅
速に行なうことができる。
Further, the piping work can be performed easily and quickly by drawing the pipe for embedding into the hollow space of the fixed space securing member and piping it.

さらに、配管後中空空間内に充填材を充填して埋設管
を固定し、埋設管を充填材と空間確保材で覆うことによ
り、埋設管に作用する鉛直土圧等の付加荷重を軽減する
ことができ、埋設管に損傷が生じることを防止すること
ができる。
Furthermore, by filling the hollow space after piping with the filling material to fix the buried pipe and covering the buried pipe with the filling material and the space securing material, the additional load such as vertical earth pressure acting on the buried pipe is reduced. Therefore, it is possible to prevent the buried pipe from being damaged.

また、掘削等の土木作業と配管,溶接等の鉄工作業を
分離して行なうことができるから、管埋設作業を能率よ
く行なうことができる。
Further, since civil works such as excavation and iron works such as piping and welding can be performed separately, the pipe burying work can be efficiently performed.

また、土木作業終了後、直ちに交通開放を行なうこと
ができるから、管埋設による交通規制を最低限に抑える
ことができる。
In addition, since the traffic can be opened immediately after the completion of the civil engineering work, the traffic regulation due to the pipe burying can be minimized.

【図面の簡単な説明】[Brief description of drawings]

第1図(a)〜(f)はこの発明の実施例の施工工程を
示す断面図、第2図は配管・接合用溝を示す斜視図であ
る。 2……溝、3……管、4……中空部、5……U字側溝、
6……埋戻土、7……アスファルトコンクリート、8…
…配管・接合用溝、9……充填材。
1 (a) to 1 (f) are cross-sectional views showing a construction process of an embodiment of the present invention, and FIG. 2 is a perspective view showing a pipe / joining groove. 2 ... Groove, 3 ... Pipe, 4 ... Hollow part, 5 ... U-shaped groove,
6 ... Backfill soil, 7 ... Asphalt concrete, 8 ...
… Piping / joining groove, 9… Filling material.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 佐藤 紀美夫 神奈川県藤沢市柄沢566―4 (56)参考文献 特開 昭61−40937(JP,A) 特開 昭57−96142(JP,A) 特開 平2−183025(JP,A) 実開 昭56−71590(JP,U) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Kimio Sato 566-4 Karasawa, Fujisawa City, Kanagawa Prefecture (56) References JP-A-61-40937 (JP, A) JP-A-57-96142 (JP, A) Japanese Unexamined Patent Publication No. 2-183025 (JP, A) Actual exploitation Sho 56-71590 (JP, U)

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】土砂を掘削して形成した溝の中に埋設管を
設置して埋戻す土木施工法において、 上記溝内部に埋設管の断面積より大きな中空空間のU字
溝を有する空間確保材をU字溝を下に向けて設置し、 該空間確保材上の掘削した溝を埋戻して空間確保材を固
定し、 固定した空間確保材の中空空間に埋設管を引込み配管
し、 空間確保材と埋設管との空隙に充填材を充填することを
特徴とする地中埋設管の土木施工法。
1. A civil engineering construction method in which a buried pipe is installed and backfilled in a groove formed by excavating earth and sand, and a space having a U-shaped groove having a hollow space larger than the cross-sectional area of the buried pipe is secured inside the groove. The material is installed with the U-shaped groove facing down, the excavated groove on the space securing material is backfilled to fix the space securing material, and the embedded pipe is drawn into the hollow space of the fixed space securing material to pipe the space. A civil engineering method for an underground buried pipe, characterized by filling a gap between the securing material and the buried pipe with a filler.
JP2134154A 1990-05-25 1990-05-25 Civil engineering method for underground pipes Expired - Lifetime JPH0814350B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2134154A JPH0814350B2 (en) 1990-05-25 1990-05-25 Civil engineering method for underground pipes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2134154A JPH0814350B2 (en) 1990-05-25 1990-05-25 Civil engineering method for underground pipes

Publications (2)

Publication Number Publication Date
JPH0429689A JPH0429689A (en) 1992-01-31
JPH0814350B2 true JPH0814350B2 (en) 1996-02-14

Family

ID=15121735

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2134154A Expired - Lifetime JPH0814350B2 (en) 1990-05-25 1990-05-25 Civil engineering method for underground pipes

Country Status (1)

Country Link
JP (1) JPH0814350B2 (en)

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5796142A (en) * 1980-12-02 1982-06-15 Kasei Co C I Method and apparatus for installing inner pipe in sleeve pipe
JPS6142213A (en) * 1984-07-31 1986-02-28 日本ゼニスパイプ株式会社 Concrete box-shaped covered conduit for setting cable under ground
JPS6140937A (en) * 1984-07-31 1986-02-27 末松 大吉 Construction of block for culvert

Also Published As

Publication number Publication date
JPH0429689A (en) 1992-01-31

Similar Documents

Publication Publication Date Title
KR101664368B1 (en) A cast-in place pile arrangement method for head of concrete pile exposed to outside using geo tube
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JP3185190B2 (en) Construction method of PC hollow pile and underground structure
JP2764149B2 (en) Construction method of concrete box culvert
CN108797609A (en) Environmentally protective steel pipe steel plate combination construction method for supporting
JPH0814350B2 (en) Civil engineering method for underground pipes
JP3403345B2 (en) Invert formation method and block in existing mountain tunnel
JP3495412B2 (en) Pipe laying method
JP2002317430A (en) Method and structure for burying material to be buried under ground
JPS6117696A (en) Construction of underground head
KR102571803B1 (en) Pipe laying method using the earth frame
JP2830717B2 (en) Protection method of buried pipe under footing foundation
JPH0814349B2 (en) Civil engineering method for underground pipes
JP3101371B2 (en) Temporary backfill method
KR20040023915A (en) Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method and construction method thereof
JPH02300430A (en) Civil engineering method for embedding pipe
JPS6016535B2 (en) How to form retaining walls and underground walls
JP3352951B2 (en) Installation method of invert and underground drainage in mountain tunnel
JP3178357B2 (en) Construction method of large section tunnel
JPH0827765A (en) Burial construction method of road occupying object and road occupying object protecting device
JPH0663269B2 (en) Pipe burying method
JP3996162B2 (en) Propulsion pipe underground propulsion base and construction method thereof
JP3292824B2 (en) Burial method of pipe
JP3080840B2 (en) How to remove underground pipes
CN116220064A (en) Construction method for backfilling engineering of fluid-state solidified soil backfilling steel sheet pile supporting pipeline