JPH08135383A - Repairing work method of tunnel in use - Google Patents

Repairing work method of tunnel in use

Info

Publication number
JPH08135383A
JPH08135383A JP6271657A JP27165794A JPH08135383A JP H08135383 A JPH08135383 A JP H08135383A JP 6271657 A JP6271657 A JP 6271657A JP 27165794 A JP27165794 A JP 27165794A JP H08135383 A JPH08135383 A JP H08135383A
Authority
JP
Japan
Prior art keywords
work
ground
tunnel
excavation
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP6271657A
Other languages
Japanese (ja)
Other versions
JP3438113B2 (en
Inventor
Toshihiro Asakura
俊弘 朝倉
Norio Shinomiya
紀郎 四野宮
Yasutada Ikeda
靖忠 池田
Kazuhiro Yasui
和博 安居
Toshio Tamura
寿夫 田村
Hideo Tanaka
秀男 田中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Railway Technical Research Institute
West Japan Railway Co
Original Assignee
Taisei Corp
Railway Technical Research Institute
West Japan Railway Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp, Railway Technical Research Institute, West Japan Railway Co filed Critical Taisei Corp
Priority to JP27165794A priority Critical patent/JP3438113B2/en
Publication of JPH08135383A publication Critical patent/JPH08135383A/en
Application granted granted Critical
Publication of JP3438113B2 publication Critical patent/JP3438113B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE: To carry out a repairing work without stopping the overall running of a train in particular, in a repairing work method of an existing tunnel such as the widening of the tunnel and the repairing of the peripheral wall. CONSTITUTION: A reinforcement of a natural ground 5 by rock bolts; an excavation and exhaust of a repairing area; an erection of a mine timbering 1 to an excavated area; a partitioning which consists of an end plate with an air fence 7 to the clearance between the mine timbering 1 and a natural ground; and the installing of a face protective work 10 to the excavated face; are carried out. Furthermore, a series of works including the installing of a collapse protector to an existing arch in a nonexcavated part; the assembling of a PC plate 2a between the mine timberings; and the pouring and the filling of a backfilling mortar layer 3 to the clearance between the PC plate and the natural ground; are repeated as one cycle, so as to repair the full length of the tunnel.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、既設トンネルの拡幅
やトンネル内アーチ部ないし側壁部の補修工事を行うい
わゆる改修工事方法に関するものである。特に、改修工
事期間中も車両通行を停止することなく工事のできる工
事方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a so-called repair work method for widening an existing tunnel and repairing an arch part or a side wall part in the tunnel. In particular, the present invention relates to a construction method capable of performing construction without stopping the passage of vehicles during the repair work period.

【0002】[0002]

【従来の技術】例えば、既設トンネルを拡幅する工事方
法としてPCL工法(PRECASTCONCRETE
LINING)がある。この工法の特徴は、拡幅すべ
き既設トンネルのアーチ部分および側壁部分を掘削排除
するとともに、トンネル入口側のレール上に、アーチ部
分を組み立てるためのエレクターを搭載した運搬台車を
設置し、この運搬台車のエレクターに、プレキャストコ
ンクリート版からなるアーチ状のパネル、つまり二次覆
工として機能するパネルを据付け、その状態で運搬台車
をトンネル内に誘導するとともに、台車上の前記エレク
レータを作動して前記パネルをトンネル内のアーチ部に
一体的に取り付け、パネルと地山との間には裏込めモル
タルを充填し、固定させる工法である。いわゆるPC版
による一種のパネル工法である。したがって、工期の短
縮に貢献する工法として評価されている。
2. Description of the Related Art For example, the PCL method (PRECAST CONCRETE) is used as a construction method for widening an existing tunnel.
There is LINING). This method is characterized by excavating and eliminating the arch part and side wall part of the existing tunnel to be widened, and installing a trolley equipped with an erector for assembling the arch part on the rail at the entrance side of the tunnel. , The arch-shaped panel made of precast concrete slab, that is, the panel functioning as the secondary lining, is installed, and in that state the transport vehicle is guided into the tunnel, and the above-mentioned panel is operated by operating the above-mentioned electrator on the vehicle. It is a construction method that is integrally attached to the arch part in the tunnel, backfill mortar is filled between the panel and the ground and fixed. This is a kind of panel construction method using a so-called PC plate. Therefore, it is evaluated as a construction method that contributes to shortening the construction period.

【0003】[0003]

【発明が解決しようとする課題】ところが、このPCL
工法による場合は、工期期間中の車両の通行は全面的に
停止される。さらに、パネルを組み立てるためのエレク
ターを装備したきわめて大掛かりな専用機械を配備する
必要があるなどの問題点があった。
However, this PCL
When the construction method is used, the passage of vehicles during the construction period is completely stopped. Further, there is a problem that it is necessary to deploy a very large-scale dedicated machine equipped with an erector for assembling the panel.

【0004】説明するまでもなく鉄道網は経済の動脈で
ある。したがって、一時的とは言え、その使用を全面的
に停止することは、大きな経済的損失となる。そこで、
この経済的損失を排除する趣旨から車両の通行を許容し
ながら、しかも安全面を充分に確保できる拡幅や補修等
の改修工事のできる工事方法の開発が要請されていた。
この発明は、このような要請に応える手段としての既設
トンネル改修工事方法を提供することを目的とするもの
である。
Needless to say, the railway network is an economic artery. Therefore, even if it is temporary, it is a great economic loss to completely stop its use. Therefore,
For the purpose of eliminating this economic loss, there has been a demand for the development of a construction method that allows repairs such as widening and repairs while allowing the passage of vehicles while ensuring sufficient safety.
It is an object of the present invention to provide an existing tunnel repair work method as a means for responding to such a request.

【0005】[0005]

【課題を解決するための手段】そこで前記目的を達成す
る手段として、この発明は車両の運行休止時間帯内に次
のような手順方法による作業工程を踏むことにより、車
両の運行を規制することなく、つまり車両の通行を全面
ストップすることなく、既設トンネルの拡幅ないし補修
のための改修工事を行うようにしたことにある。 (1)まず、拡幅ないし補修すべき既設トンネルの地山
を補強する手段として、側壁部ないしアーチ部にロック
ボルトを打設した。すなわち拡幅ないし補修すべき既設
トンネルの側壁部ないしアーチ部の地山に対しロックボ
ルトによる補強施工を行った。 (2)補強施工が終了したところで、側壁部ないしアー
チ部を拡幅ないし補修幅に応じて掘削し、掘削ズリをト
ンネル外に搬出した。すなわち、既設トンネルの側壁部
ないしアーチ部を拡幅領域ないし補修領域に応じて掘削
するとともに、掘削ズリの搬出作業を行った。 (3)掘削と掘削ズリの搬出作業が終了すると、一定の
ピッチをもって支保工を建て込んだ。具体的には、0.
8〜1.5メートル間隔をもって支保工を建て込んだ。 (4)支保工の建て込みが終了すると、支保工の外周と
地山との間隙部にエアーフェンスによる褄板からなる仕
切りを着脱自在に取り付けた。また前記拡幅ないし補修
のために掘削した切羽部には、切羽部の崩落を防止する
手段として、エアチューブからなる切羽防護工を施し
た。 (5)ついで、前記エアーフェンスによる褄板からなる
仕切りと、切羽防護工の取り付け作業が終了すると、支
保工間にメッシュ筋を介装させるとともに、支保工間に
作業員1人で容易に持ち抱かえることのできるようにあ
らかじめ成形された長方形のPC版を組み込んだ。具体
的には高強度コンクリート版を支保工間に掛けわたす要
領で順次挿入し、側壁部ないしアーチ部または側壁部お
よびアーチ部の全周を前記高強度コンクリート版で構成
するようにした。すなわちPC版を覆工兼型枠として組
み込んだ。そして、さらに未掘削部における既設アーチ
部には、既設アーチ部、すなわち既設二次覆工の剥離崩
落を防止する手段としてのプロテクターを取り付けた。 (6)前記PC版の組み込みとプロテクターの取り付け
作業が終了すると、PC版にあらかじめ埋設してあるソ
ケットに、裏込めモルタルの注入ホースを接続し、この
注入ホースを介して高強度コンクリート版の裏面と地山
との間隙にモルタルを注入充填した。つまり高強度コン
クリート版とモルタル層からなる二次覆工を形成した。
Therefore, as means for achieving the above object, the present invention regulates the operation of a vehicle by performing a work process according to the following procedural method during an operation stop time of the vehicle. No, that is, the repair work for widening or repairing the existing tunnel is performed without completely stopping the passage of vehicles. (1) First, as a means for reinforcing the ground of an existing tunnel to be widened or repaired, a rock bolt was driven in the side wall portion or the arch portion. In other words, rock bolts were used to reinforce the ground of the side walls and arches of the existing tunnel to be widened or repaired. (2) When the reinforcement work was completed, the side wall part or the arch part was excavated according to the expansion or repair width, and the excavation scrap was carried out of the tunnel. That is, the side wall part or the arch part of the existing tunnel was excavated in accordance with the widening region or the repair region, and the excavation gap was carried out. (3) After the excavation and the excavation excavation work was completed, support work was built at a fixed pitch. Specifically, 0.
Support works were built at intervals of 8 to 1.5 meters. (4) When the supporting work was built, a partition made of an air fence was detachably attached to the gap between the outer circumference of the supporting work and the ground. Further, the face portion excavated for widening or repairing was provided with face protector made of an air tube as a means for preventing the face portion from collapsing. (5) Then, when the work of attaching the partition consisting of the siding and the face protection work by the air fence is completed, the mesh muscles are inserted between the support works, and one worker can easily hold it between the support works. It incorporates a preformed rectangular PC plate that can be embraced. Specifically, the high-strength concrete slabs were sequentially inserted in such a manner that they were hung between the supporting works, and the side wall portion or the arch portion or the entire circumference of the side wall portion and the arch portion was constituted by the high-strength concrete slab. That is, the PC plate was incorporated as a lining and formwork. Further, a protector was attached to the existing arch portion in the unexcavated portion as a means for preventing peeling and collapse of the existing arch portion, that is, the existing secondary lining. (6) When the work of assembling the PC plate and the attaching work of the protector are completed, the back filling mortar injection hose is connected to the socket that is embedded in the PC plate in advance, and the back surface of the high-strength concrete plate is connected through this injection hose. Mortar was injected and filled into the gap between the ground and the ground. That is, a secondary lining consisting of a high-strength concrete slab and a mortar layer was formed.

【0006】この改修工事方法の特徴とするところは、
以上説明したように車両の運行休止時間帯内に、前記一
連の作業を1サイクルとし、既設トンネルの入口側から
トンネルの出口側へ向けて順次繰り返し、既設トンネル
全長の改修工事を行うようにしたことにある。つまりサ
イクルとサイクルとの間に列車を通行させ、改修工事期
間中における列車の通過を停止させることなく工事がで
きるようにしたことにある。
The features of this repair work method are:
As described above, the above-mentioned series of work is defined as one cycle during the suspension time of operation of the vehicle, and is sequentially repeated from the entrance side of the existing tunnel to the exit side of the tunnel to perform the repair work on the entire length of the existing tunnel. Especially. In other words, it allows trains to pass between cycles so that construction can be performed without stopping the passage of trains during the repair work period.

【0007】さらに、前記一連の作業からなるサイクル
タイムを短縮する狙いとして、前記アーチ部ないし側壁
部の掘削とズリの搬出作業と、支保工の建て方作業と、
支保工の外周と地山との間隙部にエアーフェンスによる
褄板からなる仕切りの取り付けと、前記掘削した切羽部
に対する切羽防護工の取り付けとを行う作業工程を次の
ような手順で行うようにした。
Further, in order to shorten the cycle time of the above-mentioned series of work, excavation of the arch or the side wall and carrying-out of the slip, construction work of supporting work,
The work process for installing a partition consisting of a siding plate with an air fence in the gap between the outer periphery of the support work and the ground and attaching the face protection work to the excavated face face should be performed in the following procedure. did.

【0008】まず、支保工の建て方間隔の1ピッチ分だ
け掘削して支保工を建てた。そして、この支保工の外周
と地山の間隙部に掘削によって形成される新しいアーチ
部、つまり新しいグランドアーチ部に崩落防止のブロッ
キング手段を取り付けた。そののち、さらに1ピッチ分
の掘削を行って支保工を建てた。ついで、この支保工、
つまり2本目の支保工の外周と地山との間隙部に前記エ
アーフェンスによる褄板からなる仕切りと、切羽防護工
の取り付けとを行うようにした。
First, the support work was built by excavating one pitch of the support work construction interval. Then, a blocking means for preventing collapse is attached to a new arch portion formed by excavation, that is, a new ground arch portion in the gap between the outer periphery of this support work and the ground. After that, one more pitch was excavated to build the support work. Then, this support work,
That is, the partition consisting of the siding plate by the air fence and the face protector are attached to the gap between the outer periphery of the second support work and the ground.

【0009】なお、トンネル内の湧水がある現場におい
ては、前記裏込めモルタルの注入充填作業前に、アーチ
部および側壁部の地山側に沿って、つまり切削面に沿っ
て、かつ一定の間隔を設けてドレン配管を付設した。そ
して、その付設後に裏込めモルタルを注入充填して湧水
をトンネル路床の側溝へ誘導排出させるようにした。
In addition, at the site where there is spring water in the tunnel, before the backfilling mortar injection and filling work, along the ground side of the arch and the side wall, that is, along the cutting surface and at a constant interval. Was installed and a drain pipe was attached. Then, after the installation, backfill mortar was injected and filled so that the spring water was guided and discharged to the gutter of the tunnel roadbed.

【0010】[0010]

【作用】この発明による既設トンネルの改修工事方法
は、以上説明した手順に基づいて施工するようにしたの
で、あらかじめ改修線における列車の通過時刻等から施
工作業の許容時間帯を設定しておく。具体的には、夜間
最終列車の通過後、始発列車の通過時刻までの時間帯に
対応できる工事区間を設定した。そして、前記(1)〜
(6)の1サイクルの作業工程をその時間帯に完了さ
せ、使用重機類をトンネル内から退避させるようにし
た。その結果、工事期間中の車両の運行を停止すること
なく所望の改修工事を行うことができた。
In the method for repairing an existing tunnel according to the present invention, the construction is carried out based on the procedure described above. Therefore, the allowable time zone for construction work is set in advance from the train passage time on the repair line. Specifically, a construction section was set up to accommodate the time zone from the passage of the last train at night to the passage of the first train. And (1) to
The one-cycle work process of (6) was completed during that time period, and the heavy machinery used was evacuated from the tunnel. As a result, the desired repair work could be performed without stopping the operation of the vehicle during the construction period.

【0011】また、アーチ部ないし側壁部の掘削作業
と、支保工の建て方作業と、エアーフェンスによる褄板
からなる仕切りの取り付けと、さらに切羽防護工の取り
付けとを行う作業工程において、まず支保工の建て方間
隔の1ピッチ分だけ掘削して支保工を建て、この支保工
の外周と地山との間隙部に掘削によって形成される新し
いグランドアーチ部に崩落防止のブロッキング手段を取
り付けたのち、さらに1ピッチ分の掘削を行って支保工
を建て、この支保工の外周と地山との間隙部に前記エア
ーフェンスによる褄板からなる仕切りと、切羽防護工の
取り付け作業を行う手順によると、高強度コンクリート
版と地山との間隙部に対する裏込めモルタルの注入充填
作業を前後支保工間の2ピッチ分、つまり2スパン間に
同時に行うことができる。その結果、一連の作業手順の
サイクルタイムを短縮することができた。つまり限られ
た施工可能な時間帯、すなわち車両の運行休止時間帯に
おいて、より効率的な改修工事を行うことができた。
Further, in the work steps of excavating the arch or the side wall, constructing the supporting work, installing the partition consisting of the siding plate by the air fence, and further installing the face protector, first the supporting work is carried out. After constructing the support work by excavating by one pitch of the construction interval of the work, after installing the blocking means for preventing collapse on the new ground arch part formed by excavation in the gap between the outer periphery of this support work and the natural ground. According to the procedure of constructing a supporting work by excavating one pitch, and installing a partition consisting of a seed plate by the air fence and a face protector in the gap between the outer circumference of this supporting work and the ground. It is possible to perform backfilling mortar injection and filling work for the gap between the high-strength concrete slab and the ground for two pitches between the front and rear supports, that is, for two spans at the same time. That. As a result, the cycle time of a series of work procedures could be shortened. In other words, it was possible to perform more efficient repair work during the limited construction time, that is, during the vehicle operation suspension time.

【0012】[0012]

【実施例】さらに、この改修工事方法を図面に示す実施
例に基づいて具体的に説明する。なお、この実施例にお
いては、煉瓦構造の二次覆工からなる既設トンネルにお
けるアーチ部分の拡幅工事に適用した場合に基づいて説
明する。ちなみに図13は、拡幅工事後におけるトンネ
ル断面構造を示す一部斜視図で、100は、煉瓦構造の
既設二次覆工である。また、1は改修のためのに設定し
た支保工、2は高強度コンクリート版2aからなる新規
拡幅されたアーチ部を構成する二次覆工で、3は裏込め
モルタル層を示し、4は地山の補強に打設したロックボ
ルトである。
[Embodiment] Further, this repair work method will be concretely explained based on an embodiment shown in the drawings. In addition, in this embodiment, description will be given based on a case where the present invention is applied to widening work of an arch portion in an existing tunnel including a secondary lining of a brick structure. Incidentally, FIG. 13 is a partial perspective view showing the tunnel cross-sectional structure after the widening work, and 100 is the existing secondary lining of the brick structure. In addition, 1 is a supporting work set for repairing, 2 is a secondary lining that constitutes a newly widened arch portion made of high-strength concrete slab 2a, 3 is a backfill mortar layer, and 4 is ground. It is a rock bolt that was placed to reinforce the mountain.

【0013】まず、図1は、拡幅改修するために使用す
る重機類を当該拡幅改修路線のトンネル内に配備した状
態を示す。なお、図面上における重機類の配置順序は特
に指定したものではない。次に、これら重機類の役割分
担の概略を説明すると、まず上段左からAはロードヘッ
ダである。拡幅すべきアーチ部の掘削作業を分担するも
のである。ついでBはキャリヤダンプで、ロードヘッダ
Aによって掘削された掘削ズリをトンネル外へ搬送する
ものである。Cはキャリヤダンプで、主として支保工の
建て方作業および支保工間に高強度コンクリート版2a
を組み込んだり、裏込めモルタルの注入作業を行う場合
に利用する一種の高所作業車としての役割を分担するも
のである。Dは裏込めモルタルの充填ポンプ、Eは、こ
の充填ポンプDへ裏込めモルタルを供給するモルタル供
給装置としての役割を分担するミキサー車である。この
ミキサー車Eはトンネルの外に設置されたモルタル製造
プラント(図示せず)から適時裏込みモルタルをトンネ
ル内へ搬入する運搬車としての役割を持つ。
First, FIG. 1 shows a state in which heavy machinery used for widening and repairing is installed in a tunnel of the widening and repairing route. The order of arranging the heavy equipment on the drawings is not particularly specified. Next, an outline of the division of roles of these heavy machinery will be described. First, from the upper left, A is a road header. It is responsible for excavating the arch part that should be widened. Next, B is a carrier dump, which conveys the excavation scrap excavated by the load header A to the outside of the tunnel. C is a carrier dump, which is a high-strength concrete slab 2a mainly used during the construction work of the support work and during the support work.
It is intended to be used as a kind of aerial work vehicle to be used when incorporating or filling back-filling mortar. D is a back-filling mortar filling pump, and E is a mixer car that plays a role as a mortar supply device that supplies back-filling mortar to the filling pump D. The mixer truck E has a role as a carrier for loading backfilled mortar into the tunnel from a mortar manufacturing plant (not shown) installed outside the tunnel.

【0014】さらに、図1下段の左側、Fは緊急時にお
ける超急速硬化セメント、具体的には超速硬プレミック
スコンクリートの吹付装置である。湧水や地割れ等の発
生時に対応するもので、いわゆる工事現場における緊急
対策作業車である。Gは油圧式ホイールジャンボで、ア
ーチ部ないし側壁部の補強手段としてのロックボルト4
の打設作業等を分担する穿孔機を搭載したものである。
Hは、モルタルポンプを装備し、前記ロックボルト4の
定着作業や支保工1や二次覆工となる高強度コンクリー
ト版2aのトンネル内への搬入作業等を分担する運搬車
である。なお、これらの重機類はいずれも改修作業時以
外はトンネル外に設置された退避場所に待機し、常に所
望の作業工程の開始に速やかに対応できるようスタンバ
イされている。
Further, F on the left side of the lower part of FIG. 1 is a spraying device for super rapid hardening cement in an emergency, specifically, super quick hardening premix concrete. This is a so-called emergency countermeasure work vehicle at a construction site, which responds to the occurrence of spring water or landslides. G is a hydraulic wheel jumbo, which is a lock bolt 4 as a reinforcing means for the arch part or the side wall part.
It is equipped with a punching machine that shares the work such as placing.
Reference numeral H denotes a carrier vehicle equipped with a mortar pump, which shares the work of fixing the lock bolt 4 and the work of carrying the support 1 and the high-strength concrete slab 2a serving as the secondary lining into the tunnel. It should be noted that all of these heavy equipments are on standby at the evacuation site installed outside the tunnel except during repair work, and are always on standby so that the desired work process can be started promptly at all times.

【0015】次に作業手順を工程順に基づいて説明する
と、まず、図2は前記図1で示した油圧式ホイールジャ
ンボGによってアーチ部および側壁部の地山5に補強手
段としてのロックボルト4の打ち込み作業を終了した時
点の断面図である。つまりロックボルト4による補強施
工の作業工程の終了時を示す。
Next, the working procedure will be described based on the order of steps. First, FIG. 2 shows the lock bolt 4 as a reinforcing means on the ground 5 of the arch portion and the side wall portion by the hydraulic wheel jumbo G shown in FIG. It is sectional drawing at the time of finishing the driving operation. That is, it indicates the end of the work process of the reinforcement work by the lock bolt 4.

【0016】図3は、ロードヘッダAによってアーチ部
の拡幅領域を掘削する作業工程を示す断面図である。な
お、先に説明したように、この実施例ではアーチ部分の
みを拡幅する関係上、図示の通り掘削領域はアーチ部分
に限定される。
FIG. 3 is a sectional view showing a work process of excavating the widened region of the arch portion by the load header A. As described above, in this embodiment, the excavation area is limited to the arch portion as illustrated because of the widening of only the arch portion.

【0017】図4は、キャリヤダンプCを利用し前記拡
幅掘削作業後のアーチ部に支保工1の建て込みと、建て
込みの終った支保工1(1)間に、覆工兼型枠として機
能する高強度コンクリート版2aの組み込み作業を終了
した時点のトンネル断面図である。支保工1としては、
H型鋼を曲げ加工して得られたものを使用した。また、
実施例では、トンネルの長手方向に対し、1.2メート
ルピッチで建て方した。
FIG. 4 shows a case in which the carrier dump C is used to construct a lining / formwork between the erection support 1 (1) after the erection is completed and the erection support 1 is installed in the arch after the widening excavation work. It is a tunnel sectional view at the time of finishing the assembling work of the functioning high-strength concrete slab 2a. For shoring work 1,
The one obtained by bending the H-shaped steel was used. Also,
In the example, the tunnels were built at a pitch of 1.2 meters in the longitudinal direction.

【0018】図5は、前記建て方作業の終了した支保工
1および支保工1と地山5との間隙部6にエアーフェン
ス7による褄板8からなる仕切りを取り付けた作業工程
を示すアーチ部の縦断面図である。エアーフェンス7と
して実施例ではゴムホース状のものに、コンプレッサー
(図示せず)を介して圧縮空気(7Kg/cm2 )を充
填し膨らませた構成とした。そして、その外側(図示に
おいては右側)に止め金具9を介して褄板8を着脱自在
に取り付け、エアーフェンス7による褄板8からなる仕
切り構造とした。すなわち止め金具9を支保工1のフラ
ンジ1aにクランプさせ、エアーフェンス7による褄板
8からなる着脱自在な仕切り構造とした。
FIG. 5 is an arch part showing a work process in which a partition consisting of a plenum 8 by an air fence 7 is attached to the support 1 after the building work and the gap 6 between the support 1 and the ground 5. FIG. In the embodiment, a rubber hose-shaped air fence 7 is filled with compressed air (7 Kg / cm 2 ) through a compressor (not shown) and inflated. Then, on the outer side (on the right side in the figure), the crate plate 8 is detachably attached via a stopper 9, so that the air fence 7 forms the crate plate 8 into a partition structure. That is, the metal stopper 9 is clamped to the flange 1a of the supporting structure 1 so that the air fence 7 serves as a detachable partitioning structure composed of the chest plate 8.

【0019】このエアーンフェンス7による褄板8から
なる仕切りは、二次覆工となる高強度コンクリート版2
aの裏面と地山5との間隙6に裏込めモルタル層3を充
填した際、そのモルタル層3の漏れ止め防止としての役
割を分担するものである。なお、図示における符号16
は、モルタルの注入確認孔で、その役割は後述する。
The partition formed by the siding plate 8 by the air-borne fence 7 is a high-strength concrete slab 2 which serves as a secondary lining.
When the back-filling mortar layer 3 is filled in the gap 6 between the back surface of a and the ground 5, the role of preventing leakage of the mortar layer 3 is shared. Incidentally, reference numeral 16 in the drawing
Is an injection confirmation hole of mortar, the role of which will be described later.

【0020】図6は、拡幅のために掘削したアーチ部に
おける切羽部の崩落を防止する切羽防護工10の施工断
面図である。その構成は、図示のように最先端側(図示
で右側)に位置する支保工1と、その1つ手前の支保工
1との下面に、H型鋼を用いて構成した逆L字状のエア
ーチューブ固定ブラケット11を取り付けた。そして、
このエアーチューブ固定ブラケット11の先端部(図示
で右側)に設けた水平板11aと切羽部、つまり掘削切
羽面からなる円弧状の掘削面との間にエアーバッグ12
を当てて、切羽防護工10とした。なお、エアーバッグ
12に対するエアーの注入は、前記エアーフェンス7の
場合と同様である。
FIG. 6 is a construction sectional view of a face protection work 10 for preventing the face part from collapsing in the arch part excavated for widening. The structure is an inverted L-shaped air structure made of H-shaped steel on the lower surface of the support structure 1 located on the most distal side (the right side in the drawing) as shown in the figure and the support structure 1 in front of it. The tube fixing bracket 11 was attached. And
The air bag 12 is provided between the horizontal plate 11a provided at the tip (right side in the figure) of the air tube fixing bracket 11 and the face of the cutting face, that is, the arc-shaped excavation face composed of the excavation face.
Face protector 10 was applied. The injection of air into the air bag 12 is the same as in the case of the air fence 7.

【0021】図7は、図6で示した切羽防護工10の取
り付け部より先端側、すなわち拡幅のための切削作業を
未だ施していない、つまり既設の煉瓦構造からなる旧二
次覆工の剥離崩落を防止するためのプロテクター13の
取り付け施工を示す断面図である。構造としては、地山
保護のため先に施工したロックボルト4に、サスペンシ
ョンロッド4aを接続し、このサスペンションロッド4
aを利用してプロテクター13を懸吊させた構成とし
た。なお、プロタテクター13は合成樹脂製のコルゲー
ト板を用い、アーチ部分、つまりトンネルの天井に相当
する全周領域をこのプロテクター13で覆う構成とし
た。
FIG. 7 shows the exfoliation of the old secondary lining made of the existing brick structure, that is, the tip side of the mounting portion of the face protector 10 shown in FIG. 6, that is, the cutting work for widening has not been performed yet. It is sectional drawing which shows the attachment construction of the protector 13 for preventing a fall. As for the structure, the suspension rod 4a is connected to the lock bolt 4 previously constructed to protect the natural ground.
The protector 13 was suspended using a. A corrugated board made of synthetic resin is used as the protector 13, and the protector 13 covers the arch portion, that is, the entire circumferential area corresponding to the ceiling of the tunnel.

【0022】なお、前記図6で示した切羽防護工10
も、図7で示したプロテクター13も、その役割は、い
ずれも列車通過時はもちろん、施工作業時において、ア
ーチ部分からの地山5や旧二次覆工部分の崩落事故を未
然に防止するためのものである。図8は、プロテクター
13の取り付け作業を終了したトンネルの断面図であ
る。
The face protector 10 shown in FIG.
Also, the role of the protector 13 shown in FIG. 7 is to prevent a collapse accident of the ground 5 and the old secondary lining part from the arch part before the train is passed and also during the construction work. It is for. FIG. 8 is a sectional view of the tunnel in which the work of attaching the protector 13 has been completed.

【0023】また、この実施例において支保工1および
1間に組み込んだ高強度コンクリート版2aは、熱硬化
性メラミン樹脂をセメント・微粒シリカ・特殊添加材配
合した組成物に混入し、これを熱処理して得た特殊なプ
レキャストコンクリート版を採用した。しかも、その形
状は長さが約120cm、厚さ5cm、幅約20cm,
重量約25kgで、作業員1人によって容易に持ち運び
が可能に成形したPC版とした。つまり、建て方された
支保工1および1のそれぞれ前後フランジ部1aおよび
1a(図5および図6参照)間に1人の作業員によって
容易に組み込み、アーチ状の二次覆工2として迅速に構
築できるPC版2aとした。
Further, in this embodiment, the high-strength concrete slab 2a incorporated between the supports 1 and 1 is prepared by mixing a thermosetting melamine resin into a composition containing cement, finely divided silica and a special additive and heat treating the mixture. The special precast concrete slab obtained by doing was adopted. Moreover, the shape is about 120 cm in length, 5 cm in thickness, about 20 cm in width,
A PC plate having a weight of about 25 kg and formed to be easily carried by one worker was prepared. That is, one worker can easily install between the front and rear flange portions 1a and 1a (see FIGS. 5 and 6) of the erected supports 1 and 1, respectively, to quickly form the arched secondary lining 2. It is a PC version 2a that can be constructed.

【0024】図9(A)(B)は、前記高強度コンクリ
ート版2aの支保工1および1間への組み込み作業を容
易にするため、PC版2aに治具として設けた取付金具
2cおよび2cの一例を示す平面図(A)と正面図
(B)である。図示のようにコンクリート版2aの長手
方向両端部より中央に、それぞれアンカーボルト2b,
2bを介して細長い板状を呈する取付金具2cおよび2
cを保持させた。そして、この取付金具2cおよび2c
と、コンクリート版2aの端部との間に支保工1のフラ
ンジ1aおよび1a(図6参照)を挿入させて固定させ
るようにした。その結果、作業員1人によって迅速に、
しかも効率的に組み付け作業ができるようになった。
9 (A) and 9 (B), in order to facilitate the work of assembling the high-strength concrete slab 2a between the supports 1 and 1, mounting metal fittings 2c and 2c provided as jigs on the PC slab 2a are shown. It is the top view (A) and front view (B) which show an example. As shown in the figure, the anchor bolts 2b,
Mounting brackets 2c and 2 having an elongated plate shape via 2b
c was held. Then, the mounting brackets 2c and 2c
And the flanges 1a and 1a (see FIG. 6) of the supporting structure 1 are inserted between the ends of the concrete slab 2a and the concrete plate 2a so as to be fixed. As a result, one worker can quickly
Moreover, the assembly work can now be done efficiently.

【0025】なお、図面上には表示していないが、各高
強度コンクリート版2aには、あらかじめ裏込めモルタ
ルの注入用ソケットを埋め込んでおき、前記要領で支保
工1および1間に組み込んだのち、この注入用ソケット
を利用して裏込みコンクリートの注入充填作業を行うよ
うにした。また、前記高強度コンクリート版2aの組み
込み作業は、図1で説明したようにキャリヤダンプCを
利用して行った。
Although not shown in the drawings, each high-strength concrete slab 2a was previously embedded with a back-filling mortar injection socket, and was installed between the support works 1 and 1 in the same manner as described above. The injection socket was used to perform backfilling concrete filling work. In addition, the assembling work of the high-strength concrete slab 2a was performed by using the carrier dump C as described in FIG.

【0026】ところで、裏込めモルタルの注入充填作業
においては、アーチ部の最頂部に空隙が残りやすいもの
である。そのため実施例では、この空隙の発生を排除す
る手段として、前記図5および図10で示すように、仕
切りを形成するエアーフェンス7による褄板8からなる
仕切りの頂部に、あらかじめ2インチ程度の注入確認孔
16を設け、注入用ソケットからモルタルを注入したと
き、この確認孔16から連続的にモルタルがリークする
のを確認し、注入作業を完了するという方法をとった。
By the way, in the filling and filling work of the backfilling mortar, it is easy to leave a void at the top of the arch. Therefore, in the embodiment, as a means for eliminating the generation of the voids, as shown in FIGS. 5 and 10, an injection of about 2 inches is preliminarily performed on the top of the partition composed of the seed plate 8 by the air fence 7 forming the partition. When a confirmation hole 16 is provided and mortar is injected from the injection socket, it is confirmed that the mortar continuously leaks from the confirmation hole 16 and the injection work is completed.

【0027】なお、裏込めモルタルとしては、通称スカ
ムモルタルと呼ばれている特殊軽量モルタルを使用し
た。すなわち流動性が高く、注入・充填性が得られ、か
つ適度の粘性と、粒子の分散性が高く、しかも分離しに
くく、その上モルタルグランチング材としての付着性に
優れたモルタルを使用した。
As the back-filling mortar, a special lightweight mortar commonly called scum mortar was used. That is, mortar was used which has high fluidity, can be injected and filled, has an appropriate viscosity, has high particle dispersibility, is difficult to separate, and has excellent adhesiveness as a mortar grounding material.

【0028】また、図面上には表示していないが、各支
保工1および1間の裏込めモルタルの注入充填作業に先
立ち、各スパン間には、メッシュ筋を介装し、そののち
に裏込めモルタルを注入充填した。つまりメッシュ鉄筋
で補強された裏込めモルタル層とし、その強度および付
着性を高めるようにした。
Although not shown in the drawing, a mesh streak is interposed between the spans prior to the filling and filling work of the back-filling mortar between the supports 1 and 1, and then the backing is performed. The filling mortar was injected and filled. That is, a backfill mortar layer reinforced with mesh rebar was used to enhance its strength and adhesiveness.

【0029】図11は、湧水対策としてのドレン配管1
5の配管例を示す改修トンネル断面図で、地山5と裏込
めモルタル層3との間に付設し、側壁部を沿ってトンネ
ル路床の側溝(図示せず)に集水誘導される構成とし
た。図12は、図11のX−X線拡大断面図である。さ
らに図13は、冒頭において説明したように拡幅改修工
事完了後のトンネル断面構造を示す一部破断斜視図であ
る。
FIG. 11 shows a drain pipe 1 as a measure against spring water.
Fig. 5 is a sectional view of a rehabilitated tunnel showing a piping example of No. 5, which is installed between the ground 5 and the backfill mortar layer 3 and has a structure in which water is guided to a side groove (not shown) along the side wall of the tunnel. And FIG. 12 is an enlarged sectional view taken along line XX of FIG. Further, FIG. 13 is a partially cutaway perspective view showing the tunnel cross-sectional structure after the completion of the widening repair work as described at the beginning.

【0030】図14(A)(B)(C)は、前記既設ト
ンネルの側壁側およびアーチ部の地山を補強するロック
ボルトの打設作業から、高強度コンクリート版の裏面と
地山との間隙部内へのモルタル注入充填までの一連のサ
イクルタイムを短縮するために採った掘削作業と、エア
ーフェンス7による褄板8からなる仕切りの取り付け作
業の他の実施例を工程順に示すものである。 まず(A)は、支保工1の建て方間隔Pの1ピッチ分
だけを掘削し、次の支保工1の建て方を行ったところを
示す。 (B)は、前記建て方の終った支保工1の外周と地山
5と間隙部6に、前記掘削によって形成された新しいア
ーチ部、つまりグランドアーチ部の崩落防止手段として
ブロッキング手段17を取り付け、さらに1ピッチ分の
掘削を行って次位の支保工1(図において右側)の建て
方作業を終ったところを示す。なお、ブロッキング手段
17としては、ホース状を呈する袋体を支保工1の外周
と地山5との間隙部6に介装し、ついで、この袋体にモ
ルタルを注入充填して膨らませ、グランドアーチ部の崩
落防止手段とした。 (C)は、前記建て方の終った右側の支保工1の外周
と地山5との間隙部6にエアーフェンス7による褄板8
からなる仕切りを取り付けた状態を示す。
FIGS. 14 (A), (B), and (C) show a rock bolt for reinforcing the ground on the side wall side and the arch of the existing tunnel. Other examples of the excavation work taken to shorten the cycle time until the filling and filling of the mortar into the gap and the work of attaching the partition made of the seed plate 8 by the air fence 7 are shown in the order of steps. First, (A) shows a case in which only one pitch of the construction method P of the support work 1 is excavated and the next support work 1 is built. (B) shows that a new arch portion formed by the excavation, that is, a blocking means 17 is attached to the ground arch 5 and the gap 6 on the outer periphery of the supporting work 1 that has been built as described above, as a means for preventing the collapse of the ground arch portion. The figure shows the excavation for one pitch and the construction work for the next support 1 (right side in the figure) is completed. As the blocking means 17, a hose-shaped bag body is provided in the gap 6 between the outer periphery of the support structure 1 and the ground 5, and then the bag body is filled with mortar to inflate the ground arch. It was used as a means to prevent the collapse of parts. (C) is a filling plate 8 by an air fence 7 in a gap 6 between the outer periphery of the right side supporting work 1 and the natural ground 5 after the above construction is completed.
The state where the partition consisting of is attached is shown.

【0031】以上の手順を踏んだのち、各支保工1、
1、1間に先に説明した要領で高強度コンクリート版2
aおよび2a(仮想線で示す)を組み付けると、左右2
ピッチ間隔(2P)への裏込めモルタルの注入充填が可
能となる。その結果、前記一連のサイクルタイムが短縮
され限られた時間帯において、より効率的な改修作業を
行うことができるようになった。
After carrying out the above procedure, each support work 1,
1 and 1 High strength concrete plate 2
Assembling a and 2a (shown by phantom lines) causes left and right 2
Injecting and filling backfilling mortar into the pitch interval (2P) is possible. As a result, the cycle time is shortened, and more efficient repair work can be performed in a limited time zone.

【発明の効果】この発明による既設コンクリートの改修
工事方法は、以上実施例をとおして説明したような手順
により、拡幅なり補修工事を行うものであるため、次の
ような効果を発揮することができる。 (1)工事期間中においての車両通行を停止する必要が
ない。つまり、あらかじめ施工区間を車両の通過しない
時間帯に対応して施工区間を設定する。すなわち、車両
が通過しない時間帯の範囲内で施工作業のできる施工区
間を設定しておく。さらに具体的に言えば、車両が通過
しない時間帯の範囲内で施工できる支保工スパンの数を
設定し、掘削作業から支保工の建て方、コンクリート版
の組み込みによる覆工板の構築と、さらには裏込めモル
タルの注入充填という一連の作業を行えば、車両通行に
支配されることなく施工することができる。 (2)また、この発明による施工方法においては、従来
のPCL工法において見られたような専用の大型機械を
要しないこと、施工作業の重要な部分である高強度コン
クリート版の組み込みが小人数の作業員によって容易に
実施でき、しかも、1スパンごとにエアーフェンスによ
る褄板からなる仕切施工を行って裏込めモルタルの注入
充填作業を行うようになっているため、1スパン1スパ
ンを確実に、かつ安全な作業環境のもとで改修すること
ができる。 (3)なお、掘削作業時、支保工の1本置きにブロッキ
ング手段を設けて2スパン分を掘削すると、モルタルの
注入充填が2スパン分1度に施工でき工事のサイクルタ
イムの短縮可能となる。その上、掘削切羽部の防護工は
もとより、未施工領域におけるアーチ部の崩落事故の防
止対策もその分少なくてすむ。その結果、鉄道網として
の重要な役割を中断させることなく、つまり限られた車
両の運行休止時間帯を利用して安全で、しかも効率的で
迅速な施工工事が展開できる。
The method for repairing the existing concrete according to the present invention is to perform the repair work by widening it according to the procedure described above with reference to the embodiments, so that the following effects can be exhibited. it can. (1) There is no need to stop traffic during the construction period. That is, the construction section is set in advance corresponding to the time zone in which the vehicle does not pass through the construction section. That is, a construction section is set in which the construction work can be performed within the time zone in which the vehicle does not pass. More specifically, by setting the number of support spans that can be installed within the time period when the vehicle does not pass, how to construct the support work from excavation work, construction of the lining plate by incorporating the concrete slab, and By performing a series of operations such as backfilling mortar injection and filling, it can be constructed without being controlled by vehicle traffic. (2) In addition, the construction method according to the present invention does not require a dedicated large-scale machine as seen in the conventional PCL construction method, and requires a small number of people to install a high-strength concrete slab, which is an important part of construction work. It can be easily carried out by the worker, and since the partition construction consisting of the siding plate by the air fence is performed for each span to perform the filling and filling work of the backfilling mortar, one span and one span can be reliably performed. And it can be repaired under a safe working environment. (3) During excavation work, if blocking means is provided for every other support work and two spans are excavated, the injection and filling of mortar can be performed once for two spans, and the work cycle time can be shortened. . In addition to the protection work for the excavated face, there are few measures to prevent the collapse of the arch in the unconstructed area. As a result, it is possible to develop a safe, efficient, and quick construction work without interrupting the important role of the railway network, that is, by utilizing the limited vehicle suspension period.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明による改修工事方法により、既設トン
ネルのアーチ部分の拡幅工事を行う場合の使用重機類の
配備例を示すトンネル断面図である。
FIG. 1 is a tunnel cross-sectional view showing an example of deployment of heavy equipment used in a case of performing a widening work on an arch portion of an existing tunnel by a repair work method according to the present invention.

【図2】地山補強手段としてのロックボルトを打設した
トンネル断面図である。
FIG. 2 is a sectional view of a tunnel in which a rock bolt as a ground reinforcement means is installed.

【図3】拡幅領域(アーチ部)の掘削作業工程を示すト
ンネル断面図である。
FIG. 3 is a tunnel cross-sectional view showing an excavation work process of a widened region (arch portion).

【図4】支保工の建て込みと、各支保工間に高強度コン
クリート版の組み込み作業工程が終了した時点のトンネ
ル断面図である。
FIG. 4 is a sectional view of the tunnel at the time when the support work is built and the high-strength concrete slab assembling work process is completed between the support works.

【図5】各支保工と地山との間隙部を仕切るエアーフェ
ンスによる褄板の取り付け作業工程を示す縦断面図であ
る。
FIG. 5 is a vertical cross-sectional view showing a work step of attaching a seed plate by an air fence that partitions a gap between each support work and the ground.

【図6】掘削切羽部の切羽防護工の施工断面図である。FIG. 6 is a construction cross-sectional view of a face protection work for an excavated face.

【図7】未施工領域における旧二次覆工の崩落防止手段
としてのプロテクター取り付け施工部の構造を示す断面
図である。
FIG. 7 is a cross-sectional view showing a structure of a protector mounting construction portion as a collapse prevention means of the old secondary lining in the unconstructed area.

【図8】プロテクターの取り付け施工の終了したトンネ
ル断面図である。
FIG. 8 is a cross-sectional view of the tunnel in which the protector has been attached and installed.

【図9】(A)は、取付金具を設けた高強度コンクリー
ト版の平面図、(B)は、その正面図である。
FIG. 9A is a plan view of a high-strength concrete slab provided with a mounting bracket, and FIG. 9B is a front view thereof.

【図10】モルタルの注入確認孔の設置位置を示すトン
ネル頂部の縦断正面図である。
FIG. 10 is a vertical cross-sectional front view of the top of the tunnel showing the installation position of the injection confirmation hole of the mortar.

【図11】湧水対策としてのドレン配管の付設例を示す
改修トンネルの断面図である。
FIG. 11 is a sectional view of a repair tunnel showing an example of attaching a drain pipe as a measure against spring water.

【図12】図11のX−X線拡大断面図である。12 is an enlarged cross-sectional view taken along line XX of FIG.

【図13】拡幅工事後におけるトンネル断面構造を示す
一部破断斜視図である。
FIG. 13 is a partially cutaway perspective view showing a tunnel cross-sectional structure after widening work.

【図14】アーチ部ないし側壁部の掘削作業と支保工の
建て方作業と、支保工の外周と地山との間隙部にエアー
フェンスによる褄板からなる仕切りの取り付け作業の手
順を示す他の実施例の工程図である。
FIG. 14 shows another procedure for excavating the arch part or the side wall part, constructing the supporting work, and installing a partition made of a mortar plate by an air fence in the gap between the outer periphery of the supporting work and the ground. It is a process drawing of an example.

【符号の説明】[Explanation of symbols]

1………支保工 1a……フランジ部 2………二次覆工(新規) 2a……高強度コンクリート版 2b……インサートアンカーボルト 2c……取付金具 3………裏込めモルタル層 A………ロードヘッダ(掘削機) B………キャリヤダンプ(掘削ズリ搬送用) C………キャリヤダンプ(高所作業車) D………裏込めモルタルの充填ポンプ E………ミキサー車 F………緊急吹付作業車 G………油圧式ホイールジャンボ(穿孔機) H………モルタルポンプを有する搬送車 4………ロックボルト 4a……サスペンションロッド 5………地山 6………間隙部 7………エアーフェンス 8………褄板 9………止め金具 10……切羽防護工 11……固定ブラケット 11a…水平板 12……エアーバック 13……プロテクター 15……ドレン配管 16……注入確認孔 17……ブロッキング手段 1 ………… Supporting work 1a …… Flange part 2 ………… Secondary lining (new) 2a …… High-strength concrete slab 2b …… Insert anchor bolt 2c …… Mounting metal fitting 3 ………… Back filling mortar layer A… …… Roadheader (excavator) B ………… Carrier dump (for excavation transfer) C ………… Carrier dump (high work vehicle) D ………… Back filling mortar filling pump E ………… Mixer truck F… …… Emergency spraying work vehicle G ………… Hydraulic wheel Jumbo (piercing machine) H ………… Transport vehicle with mortar pump 4 ………… Lock bolt 4a …… Suspension rod 5 ………… Solid ground 6 ………… Gap Part 7 ………… Air fence 8 ………… Damping plate 9 ………… Stopper 10 …… Face protector 11 …… Fixed bracket 11a… Horizontal plate 12 …… Air bag 13 …… Protector 15 …… Drain piping 16: Injection confirmation hole 17: Blocking means

───────────────────────────────────────────────────── フロントページの続き (72)発明者 四野宮 紀郎 大阪府大阪市北区芝田二丁目4番24号 西 日本旅客鉄道株式会社内 (72)発明者 池田 靖忠 大阪府大阪市北区芝田二丁目4番24号 西 日本旅客鉄道株式会社内 (72)発明者 安居 和博 大阪府大阪市北区芝田二丁目4番24号 西 日本旅客鉄道株式会社内 (72)発明者 田村 寿夫 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 (72)発明者 田中 秀男 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Norio Shinomiya 2-4-24 Shibata, Kita-ku, Osaka City, Osaka Prefecture West Japan Railway Company (72) Inventor Yasutada Ikeda Shibata, Kita-ku, Osaka City, Osaka Prefecture 2-4-24 West Japan Passenger Railway Co., Ltd. (72) Inventor Kazuhiro Yasui 2-4-24 Shibata Shibata, Kita-ku, Osaka-shi, Osaka Prefecture West Japan Passenger Railway Co., Ltd. (72) Inventor Toshio Tamura Shinjuku, Tokyo 1-25-1 Nishi-Shinjuku, Taisei Construction Co., Ltd. (72) Inventor Hideo Tanaka 1-25-1 Nishi-Shinjuku, Shinjuku-ku, Tokyo Taisei Construction Co., Ltd.

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 既設トンネルの拡幅ないし補修を行う改
修工事方法であって、次の作業工程からなることを特徴
とする。 (1)拡幅ないし補修すべき既設トンネルの側壁部ない
しアーチ部の地山を補強する手段としてロックボルトを
打設する作業工程と、(2)拡幅ないし補修すべき側壁
部ないしアーチ部のそれぞれを拡幅ないし補修領域に応
じて掘削する作業と、掘削ズリの搬出作業とを行う作業
工程と、(3)掘削部に一定のピッチをもって支保工の
建て方を行う作業工程と、(4)支保工の外周と地山と
の間隙部にエアーフェンスによる褄板からなる仕切りの
取り付けと、前記掘削した切羽部に対する切羽防護工の
取り付けとを行う作業工程と、(5)支保工間における
側壁部ないしアーチ部に覆工兼型枠として機能する高強
度コンクリート版の組み込みと、未掘削部における既設
アーチ部の崩落を防止するプロテクターの取り付けとを
行う作業工程と、(6)高強度コンクリート版の裏面と
地山との間隙に裏込めモルタルを注入充填し、高強度コ
ンクリート版とモルタル層からなる二次覆工を形成する
作業工程と、(7)上記(1)から(6)の作業工程を
1サイクルとし、改修すべき既設トンネルの入口側から
出口側に向けて順次繰り返し施工することを特徴とする
既設トンネルの改修工事方法。
1. A repair work method for expanding or repairing an existing tunnel, comprising the following work steps. (1) The work process of placing a rock bolt as a means for reinforcing the ground of the side wall portion or arch portion of the existing tunnel to be widened or repaired, and (2) the side wall portion or arch portion to be widened or repaired. Excavation work according to the widening or repair area and work process for carrying out excavation slip, (3) Work process for constructing support work at a constant pitch in the excavation part, and (4) Support work A step of installing a partition made of a siding plate by an air fence in the gap between the outer periphery of the ground and the ground, and installing a face protector for the excavated face, and (5) a side wall portion between the support works. A work process in which a high-strength concrete slab that functions as a lining and a formwork is installed in the arch part, and a protector that prevents the existing arch part from collapsing in the unexcavated part is attached, 6) A working step of injecting and filling backfill mortar into the gap between the back surface of the high-strength concrete plate and the ground to form a secondary lining composed of the high-strength concrete plate and the mortar layer, (7) above (1) A method for rehabilitating an existing tunnel, characterized in that the work steps from (6) to (6) are defined as one cycle, and the construction is repeated from the entrance side to the exit side of the existing tunnel to be rehabilitated.
【請求項2】 前記アーチ部ないし側壁部の掘削作業と
支保工の建て方作業と、支保工の外周と地山との間隙部
にエアーフェンスによる褄板からなる仕切りの取り付け
と、前記掘削した切羽部に対する切羽防護工の取り付け
とを行う作業工程において、 まず、支保工の建て方間隔の1ピッチ分だけ掘削して支
保工を建て、この支保工の外周と地山との間隙部に掘削
したアーチ部の崩落防止のブロッキング手段を取り付け
たのち、さらに1ピッチ分の掘削を行い支保工を建て、
この支保工の外周と地山との間隙部に前記エアーフェン
スによる褄板からなる仕切りと、切羽防護工の取り付け
とを行うことを特徴とする請求項1記載の既設トンネル
の改修工事方法。
2. The excavation work of the arch portion or the side wall portion, the construction work of the support work, the installation of a partition made of a mortar plate by an air fence in the gap between the outer periphery of the support work and the ground, and the excavation. In the work process of attaching the face protection work to the face part, first, the support work is constructed by excavating the support structure by one pitch, and the excavation is performed in the gap between the outer periphery of this support work and the ground. After installing the blocking means to prevent the collapse of the arch part, excavation for 1 pitch was further carried out to build the support work,
The method for repairing an existing tunnel according to claim 1, characterized in that a partition composed of a siding plate by the air fence and a face protector are attached in a gap between the outer periphery of the support work and the ground.
【請求項3】 前記アーチ部ないし側壁部の掘削面には
湧水用のドレン配管をトンネル内側溝に向けて付設した
ことを特徴とする請求項1記載の既設トンネルの改修工
事方法。
3. The method for repairing an existing tunnel according to claim 1, wherein a drain pipe for spring water is attached to the excavated surface of the arch part or the side wall part toward the inner groove of the tunnel.
【請求項4】 裏込めモルタルの注入充填層には、メッ
シュ筋を埋設介在させたことを特徴とする請求項1記載
の既設トンネルの改修工事方法。
4. The method for repairing an existing tunnel according to claim 1, wherein mesh filling is embedded in the injection filling layer of the backfilling mortar.
JP27165794A 1994-11-07 1994-11-07 Renovation of existing tunnel Expired - Fee Related JP3438113B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27165794A JP3438113B2 (en) 1994-11-07 1994-11-07 Renovation of existing tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27165794A JP3438113B2 (en) 1994-11-07 1994-11-07 Renovation of existing tunnel

Publications (2)

Publication Number Publication Date
JPH08135383A true JPH08135383A (en) 1996-05-28
JP3438113B2 JP3438113B2 (en) 2003-08-18

Family

ID=17503090

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27165794A Expired - Fee Related JP3438113B2 (en) 1994-11-07 1994-11-07 Renovation of existing tunnel

Country Status (1)

Country Link
JP (1) JP3438113B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002307425A (en) * 2001-04-09 2002-10-23 Ohbayashi Corp Method for manufacture of back filling grout material
JP2012207431A (en) * 2011-03-29 2012-10-25 West Japan Railway Co Tunnel lining structure
CN104121027A (en) * 2014-07-24 2014-10-29 中南大学 Method for reinforcing cracked and damaged lining of operation tunnel
JP2016204857A (en) * 2015-04-16 2016-12-08 鹿島建設株式会社 Tunnel reinforcement structure and reinforcement method
CN108301848A (en) * 2018-04-04 2018-07-20 湖南五新隧道智能装备股份有限公司 A kind of lining construction plugging device
JP2019100031A (en) * 2017-11-30 2019-06-24 飛島建設株式会社 Existing tunnel lining cutting and renewing method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002307425A (en) * 2001-04-09 2002-10-23 Ohbayashi Corp Method for manufacture of back filling grout material
JP4506024B2 (en) * 2001-04-09 2010-07-21 株式会社大林組 Manufacturing method of backfill grout material
JP2012207431A (en) * 2011-03-29 2012-10-25 West Japan Railway Co Tunnel lining structure
CN104121027A (en) * 2014-07-24 2014-10-29 中南大学 Method for reinforcing cracked and damaged lining of operation tunnel
JP2016204857A (en) * 2015-04-16 2016-12-08 鹿島建設株式会社 Tunnel reinforcement structure and reinforcement method
JP2019100031A (en) * 2017-11-30 2019-06-24 飛島建設株式会社 Existing tunnel lining cutting and renewing method
CN108301848A (en) * 2018-04-04 2018-07-20 湖南五新隧道智能装备股份有限公司 A kind of lining construction plugging device
CN108301848B (en) * 2018-04-04 2024-03-19 湖南五新隧道智能装备股份有限公司 Plugging device for lining construction

Also Published As

Publication number Publication date
JP3438113B2 (en) 2003-08-18

Similar Documents

Publication Publication Date Title
CN110985025B (en) Method for reconstructing shield tunnel to carry out mine construction
CN107849917B (en) Tunnel construction method using advance support and lag support and device suitable for same
CN106050266A (en) Construction method for undermining connected channel between shield sections in water-rich sand cobble stratum tunnel
CN101736749B (en) Method for constructing soft soil foundation continuous caisson
CN109404012B (en) IV-VI-level surrounding rock overexcavation tunnel primary support method
JP3367013B2 (en) Existing tunnel lining structure
CN111828019B (en) Construction method for large-section special deformation joint based on earthquake fracture zone
CN111379577B (en) Detachable U-shaped primary support method combined with shed cover construction
JP3438113B2 (en) Renovation of existing tunnel
US20200263542A1 (en) Underground support system and method
CN109505612A (en) Big descending bored tunnel shield sky selection structure and construction technology
KR20050020451A (en) Shield tunneling construction method and tunnel structure
KR100770593B1 (en) Construction method of round panel
KR20140082343A (en) Method for constructing tunnel by using pipe
CN113266363B (en) Excavation method for temporary intermediate wall reinforcing structure of large-section tunnel
JP3888993B2 (en) Tunnel widening method
JP4113007B2 (en) Widening method of existing tunnel
JP3011169B2 (en) Shield tunnel and lining method
CN110566237B (en) Subway interval stop line large section undercut construction is first propped up into hole reinforced structure
CN113931638A (en) Underground excavation tunnel structure with ultra-close bottom penetrating existing building bottom plate and construction method
CN114278333A (en) Construction method of ingate
KR102014471B1 (en) Tunnel construction method and tunnel supporting structure
KR102505365B1 (en) Support for tunnel shotcrete drop prevention
JP3554298B2 (en) Repair method of tunnel wall
CN216342178U (en) Shield constructs ring frame roof beam structure

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080613

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090613

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090613

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100613

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110613

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110613

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120613

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120613

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130613

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130613

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140613

Year of fee payment: 11

LAPS Cancellation because of no payment of annual fees