JPH08120692A - Masonry block and retaining wall construction method making use thereof - Google Patents
Masonry block and retaining wall construction method making use thereofInfo
- Publication number
- JPH08120692A JPH08120692A JP26293194A JP26293194A JPH08120692A JP H08120692 A JPH08120692 A JP H08120692A JP 26293194 A JP26293194 A JP 26293194A JP 26293194 A JP26293194 A JP 26293194A JP H08120692 A JPH08120692 A JP H08120692A
- Authority
- JP
- Japan
- Prior art keywords
- block
- blocks
- retaining wall
- stacking
- front body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Retaining Walls (AREA)
- Revetment (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本願発明は、2種類のブロックを
組み合わせることにより、曲率のある擁壁築造、特に勾
配のある擁壁築造に、的確に対応することができる組合
せ積みブロック、及びこれを用いた擁壁築造工法に関す
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a combination stacking block capable of accurately responding to a retaining wall construction with a curvature, particularly a retaining wall construction with a slope, by combining two types of blocks, and a combination stacking block for this. Regarding the retaining wall construction method used.
【0002】[0002]
【発明の背景】従来、護岸工事、土留工事、等の擁壁築
造工事は、例えば、図14の正面図、14の断面図に示
すような工法が採られている。すなわち、先ず、土手2
0を一定の勾配に削り、掘削法面21を形成すると共
に、該法面21の下端部の平地22に、擁壁長さ方向に
沿った溝23を、所定の深さに形成する。そして、この
溝23内に栗石24を、一定の厚さに敷き詰めて転圧し
た後、現場施工により区画された型枠(図示省略。)内
に、生コンクリ−トを打設することよって、擁壁の基礎
25が形成される。BACKGROUND OF THE INVENTION Conventionally, for construction of retaining walls such as revetment work, earth retaining work, etc., for example, the construction method shown in the front view of FIG. 14 and the sectional view of 14 has been adopted. That is, first, bank 2
The excavation slope 21 is formed by grinding 0 at a constant gradient, and a groove 23 along the length direction of the retaining wall is formed at a predetermined depth in the flat land 22 at the lower end of the slope 21. Then, after crushing stones 24 in the groove 23 so as to have a certain thickness and rolling them, a raw concrete is placed in a formwork (not shown) partitioned by on-site construction. A retaining wall foundation 25 is formed.
【0003】次に、この基礎25の完成を待って、その
上面に、先ず、第一段目として、例えば、矩形状の積み
ブロック26を、所定個数所定の間隔で配列すると共
に、その背面側に裏込栗石27を敷設し、各積みブロッ
ク26の隙間には、積みブロック26を固定するための
胴込コンクリ−ト28を充填する。Next, after completion of the foundation 25, first, as a first stage, for example, rectangular stacking blocks 26 are arranged at a predetermined number on the upper surface thereof, and the back side thereof. A lining stone 27 is laid in the space, and a gap 28 between the stacking blocks 26 is filled with a barrel concrete 28 for fixing the stacking blocks 26.
【0004】このようにして、順次に、目的の擁壁高さ
まで、積み上げて行くものである。In this way, the desired height of the retaining wall is sequentially piled up.
【0005】[0005]
【従来の技術】ところで、かかる擁壁築造工事に用いら
れる積みブロックの中には、図16に正面図(A)、側
面図(B)、平面図(C)で示すように、所定の厚さを
持った矩形板状の前方体26f及び後方体26bと、該
前方体26fと後方体26bとを所定の間隔をもって一
体に連結する連結体26jとから構成されたものがあ
る。かかる形状の積みブロック26は、通称、「平積
み」と言う積み方が採られ、互いの前方体26fの両側
端面を当接させるように、かつ前面が同一面に揃うよう
にして横一列に並べ、次に互いの目地が上下方向で一致
しないようにして、上記の施工法に則って積み上げて行
くものである。2. Description of the Related Art By the way, as shown in a front view (A), a side view (B) and a plan view (C) of FIG. There is a rectangular plate-shaped front body 26f and a rear body 26b, and a connecting body 26j that integrally connects the front body 26f and the rear body 26b with a predetermined gap. The stacking block 26 having such a shape is generally called "flat stacking", and is arranged in a horizontal row so that both end surfaces of the front bodies 26f are brought into contact with each other and the front surfaces thereof are flush with each other. They are lined up, and then the joints are piled up in accordance with the above-mentioned construction method so that the joints do not coincide with each other in the vertical direction.
【0006】[0006]
【発明が解決しようとする課題】しかしながら、上記擁
壁築造において、擁壁延長がほぼ直線である場合には、
問題がないが、それが一定の勾配をもって傾斜し、かつ
一定の曲率でカーブした擁壁(以下、『勾配カーブ擁
壁』と略称。)であるときには、最下段と最上段とでは
擁壁延長が異なってしまうという問題があった。However, in the above-mentioned retaining wall construction, when the retaining wall extension is almost straight,
If there is no problem, but it is a retaining wall that inclines with a constant slope and curves with a constant curvature (hereinafter abbreviated as "gradient curve retaining wall"), the retaining wall extends at the bottom and top. There was a problem that was different.
【0007】この差異は、勾配カーブ擁壁が凸曲状
(「外カーブ」)であるときは、最上段へ行くほど擁壁
延長が短くなり、逆に凹曲状(「内カーブ」)であると
きは、長くなる。従来はこれを調節するため、積み上げ
の段階で、図17に正面図をもって示すように外カーブ
のときは、(A)下方段の目地29を広めに採り上段へ
行くほどその目地29を漸次狭く採ることにより、逆に
内カーブのときは、(B)上方段に行く程目地29を漸
次広めに採って、差異を吸収するようにしていた。This difference is that when the slope curve retaining wall is convexly curved ("outer curve"), the retaining wall extension becomes shorter toward the uppermost stage, and conversely it is concavely curved ("inner curve"). Sometimes it gets longer. Conventionally, in order to adjust this, at the stacking stage, as shown in the front view in FIG. 17, when the curve is outside, (A) the joint 29 in the lower stage is widened and the joint 29 is gradually narrowed toward the upper stage. On the contrary, in the case of the inner curve, the joint 29 is gradually widened toward the upper stage (B) so as to absorb the difference.
【0008】しかし、かかる方法は、完成後の美観を損
ねるばかりでなく、施工においては、変化する目地間隔
を事前に設定しておき、これに従って石工のような熟練
した特殊技能者が慎重に積み上げて行く必要があった。
さらに、その目地にモルタルを充填する作業も必要であ
った。そのため作業が複雑で作業効率が悪く、施工費用
が嵩む原因ともなっていた。However, such a method not only spoils the aesthetic appearance after completion, but also sets a varying joint spacing in advance in construction, and a special skilled worker such as a mason carefully piles it up accordingly. I had to go.
Further, it was necessary to work to fill the joint with mortar. Therefore, the work is complicated, the work efficiency is low, and the construction cost is high.
【0009】また曲率半径が小さく上記方法で対応でき
ない場合は、図18に正面図をもって示すように、正面
形略三角形状の間地コンクリ−ト30を敷設する方法も
採られていた。かかる方法も、上記方法と同様に美観を
損ねると共に、作業効率が悪く、施工費用の増加となる
ものである。加えて、隣接するブロック26どうしが胴
込コンクリ−ト28によって一体化されていたものが、
間地コンクリ−ト30によって分断(通称「縁切り」)
されてしまうため、擁壁全体の所定強度を確保し難い恐
れがあった。また実際の現場では、この間地コンクリ−
ト30の施工規格が、遵守されていない場合も多く、さ
らに強度上の不安があった。When the radius of curvature is too small to be handled by the above method, a method of laying a front surface substantially triangular triangular intermediate concrete 30 as shown in a front view of FIG. 18 has been adopted. Similar to the above method, this method also impairs the aesthetics, is inefficient in working, and increases the construction cost. In addition, the blocks 26 that are adjacent to each other are integrated by the body-mounted concrete 28,
Dividing by the intermediate concrete 30 (commonly known as "edge cutting")
Therefore, it may be difficult to secure the predetermined strength of the entire retaining wall. Also, at the actual site, this concrete
In many cases, the construction standard of G.30 was not observed, and there was further concern about strength.
【0010】なお、積みブロック26の形状を上に(又
は下に)行くほど小型にする方法も考えられるが、これ
も数種類の積みブロック26を予め成形して管理してお
かなければならず、これまた非常に煩雑で実現し難いも
のである。そこで本願発明は、上記種々の問題点に着目
してなされたもので、その目的とするところは、2種類
の積みブロックを組み合わせることにより、種々形態の
勾配カーブ擁壁の築造について、簡易的確に対応するこ
とができる組合せ積みブロックと、これを用いた擁壁築
造工法を提供するものである。There may be a method of making the shape of the stacking block 26 smaller as it goes up (or down), but this also requires several kinds of stacking blocks 26 to be formed in advance and managed, This is also very complicated and difficult to realize. Therefore, the present invention has been made by paying attention to the above-mentioned various problems, and an object thereof is to easily and accurately construct a gradient curve retaining wall of various forms by combining two types of stacking blocks. The present invention provides a combination stacking block that can be used and a retaining wall construction method using the combination stacking block.
【0011】[0011]
【課題を解決するための手段】上記目的を達成するため
本願発明の組合せ積みブロックは、次のように構成され
ている。所定の厚さを持った矩形板状の前方体及び後方
体と、該前方体と後方体とを所定の間隔をもって一体に
連結する連結体とからなる積みブロックにおいて、前方
体及び後方体の両側端面を、前後方向に対し一定の傾斜
角をもち、かつ後方へ向かって内側に傾けた面に形成し
たブロック(Aブロック)と、前方体及び後方体の両側
端面を、前後方向に対し一定の傾斜角をもち、かつ後方
に向かって外側に傾けた面に形成したブロック(Bブロ
ック)と、からなることを特徴とする。In order to achieve the above object, the combination stacking block of the present invention is constructed as follows. In a stacking block composed of a rectangular plate-shaped front body and a rear body having a predetermined thickness and a connecting body integrally connecting the front body and the rear body with a predetermined space, both sides of the front body and the rear body The block (A block) whose end face has a constant inclination angle with respect to the front-rear direction and which is inclined inward toward the rear, and both end faces of the front body and the rear body are fixed in the front-rear direction. And a block (B block) formed on a surface having an inclination angle and inclined outward toward the rear.
【0012】また、前方体及び後方体の両側端面を、前
後方向に沿う曲面状に、かつその前後方向の接線(s)
が後方に向かって内側へ傾斜(x)するように形成した
ブロック(Aブロック)と、前方体及び後方体の両側端
面を、前後方向に沿う曲面状に、かつその前後方向の接
線(s)が後方に向かって外側へ傾斜(y)するように
形成したブロック(Bブロック)と、からなることを特
徴とする。Further, both end surfaces of the front body and the rear body are curved along the front-rear direction, and tangents (s) in the front-rear direction thereof.
A block (A block) formed so as to incline (x) toward the rear and both end surfaces of the front body and the rear body in a curved shape along the front-rear direction and a tangent line (s) in the front-rear direction thereof. A block (B block) formed so as to incline (y) outward toward the rear.
【0013】なお、前後方向に沿う曲面状は、凸曲面状
としても良く、また凹曲面状としてもよい。さらに、上
記互いのブロックの前面幅寸法を違えて形成し、幅の大
きい方のブロック(Aブロック、又はBブロック)の前
面に、幅の小さい方のブロック(Bブロック、又はAブ
ロック)の幅と略同じ長さの凸面部(2a)を、形成
し、かつ該凸面部を含む前方体の肉厚と幅の小さい方の
ブロックの前方体の肉厚とを、略同じに設定したことを
特徴とする。The curved surface along the front-rear direction may be a convex curved surface or a concave curved surface. Further, the width of the front side of each block is formed differently, and the width of the block (B block or A block) of the smaller width is formed on the front side of the block of the larger width (A block or B block). A convex portion (2a) having substantially the same length as that of the front body including the convex portion is set to be substantially the same as the front body of the block having a smaller width. Characterize.
【0014】次に、上記の組合せ積みブロックを用いて
行う所定高さの擁壁を築造する擁壁築造工法は、以下の
工程順により行う。 (イ)施工された基礎上面において、AブロックとBブ
ロックとを、その前方体の両側端面どうしを接触させな
がら、何れか一方のブロックを前後方向に摺動させて位
置決めして配置する第1工程、(ロ)上記方法により配
置されたA・Bブロックを一組として、基礎上面にAブ
ロックとBブロックとを交互にして、所望組数を横一列
に配列して第1段目を構築して行く第2工程、(ハ)上
記第2工程により配列された各ブロックの後方体と、掘
削法面との間に裏込栗石を充填する第3工程、(ニ)該
各ブロックの前方体と後方体との間に胴込コンクリ−ト
を充填する第4工程、(ホ)第2工程で構成した第1段
目の各ブロック上に、ブロックの目地が上下で一致しな
いようにして、第1工程及び第2工程と同様の手順によ
って第2段目を構成して行く第5工程、(ヘ)前記第3
工程から第5工程までを繰り返すことによって、所望の
段数を積み上げて行く第6工程。Next, a retaining wall construction method for constructing a retaining wall having a predetermined height, which is performed by using the above-mentioned combination stacking block, is performed in the following order of steps. (A) On the constructed upper surface of the foundation, the A block and the B block are arranged by positioning one of the blocks by sliding one of the blocks in the front-rear direction while contacting both end surfaces of the front body thereof. Step (b) A / B blocks arranged by the above method are set as one set, A blocks and B blocks are alternately arranged on the upper surface of the foundation, and a desired number of sets are arranged in a horizontal row to construct the first stage. The second step to be carried out, (c) the third step of filling back-filled calculi between the rear body of each block arranged in the second step and the excavation slope, (d) the front of each block Make sure that the joints of the blocks do not match up and down on each block of the first stage constructed in the fourth step (e) second step of filling the body-incorporating concrete between the body and the rear body. , The second step is constructed by the same procedure as the first step and the second step. Step 5 go to, (f) said third
A sixth step in which the desired number of stages is accumulated by repeating the steps from the fifth step.
【0015】また、曲面の擁壁に対応させるためには、
前記第1工程において、A・Bブロックの何れか一方を
前後方向に摺動させると共に、ブロックの中心を上下方
向に貫く軸をもって一定の回転移動を与えて配置するよ
うにする。さらにまた、前記第1工程において、先に、
一方のブロック(Aブロック、又はBブロック)のみを
所定個数、他方のブロック(Bブロック、又はAブロッ
ク)が載置し得る間隔を開けて載置して行き、その後、
各間隔に他方のブロックを載置して行くようにしても良
い。Further, in order to correspond to a curved retaining wall,
In the first step, one of the A and B blocks is slid in the front-rear direction, and a certain rotational movement is provided with an axis penetrating the center of the block in the vertical direction. Furthermore, in the first step, first,
Only one block (A block or B block) is placed with a predetermined number, and the other block (B block or A block) is placed with an interval left between them, and then,
The other block may be placed at each interval.
【0016】[0016]
【実施例】次に本願発明にかかる組合せ積みブロックの
具体的実施例を、図面に基づきその詳細を説明する。図
1、図2は本実施例の一組の組合せ積みブロックのそれ
ぞれを示す全体斜視図であり、図3から図6はその組合
せ配置状態を示す平面図である。なお、本説明におい
て、図1、2を基準にして矢印aを上下方向、矢印bを
前後方向、及び矢印cを幅方向と定義して用いる。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, specific embodiments of the combination stacking block according to the present invention will be described in detail with reference to the drawings. FIG. 1 and FIG. 2 are overall perspective views showing a pair of combination stacking blocks of this embodiment, and FIGS. 3 to 6 are plan views showing the combination arrangement state. In this description, with reference to FIGS. 1 and 2, the arrow a is defined as the vertical direction, the arrow b is defined as the front-back direction, and the arrow c is defined as the width direction.
【0017】一方の積みブロック(以下、「Aブロッ
ク」と略称。)1は、所定の厚さを持った矩形板状をな
す前方体2、及び後方体3とから成り、かつ所定の間隔
をもって前後方向に対面配置された前方体2と後方体3
とを連結し、一体化させる2本の連結体4、4とから構
成され、主にコンクリ−ト成形により形成されている。One stacking block (hereinafter abbreviated as "A block") 1 is composed of a rectangular plate-shaped front body 2 and a rear body 3 having a predetermined thickness and having a predetermined space. Front body 2 and rear body 3 facing each other in the front-back direction
It is composed of two connecting bodies 4 and 4 which connect and integrate with each other, and are mainly formed by concrete molding.
【0018】かかる前方体2の両側端面2sは、前後方
向に対して一定の傾斜角αをもち、かつ後方へ向かって
内側へ傾けた面として形成されている。同様に、後方体
3の両側端面3sも、前後方向に対して一定の傾斜角β
をもち、かつ後方へ向かって内側へ傾けた面として形成
されている。これらは別言すれば、平面図において、前
方体2、後方体3の両側端面2s、3sの間隔が、それ
ぞれ後方へ向かってテーパー状に絞られた状態に形成さ
れている。Both end surfaces 2s of the front body 2 are formed as surfaces having a constant inclination angle α with respect to the front-rear direction and inclined inwardly toward the rear. Similarly, both end surfaces 3s of the rear body 3 also have a constant inclination angle β with respect to the front-back direction.
And is formed as a surface inclined inward toward the rear. In other words, in the plan view, the distances between the two end surfaces 2s, 3s of the front body 2 and the rear body 3 are formed in a tapered state toward the rear.
【0019】また、前方体2の前面には、横断面台形状
に前方に突出した凸面部2aが形成されている。次に、
他方の積みブロック(以下、「Bブロック」と略称。)
5は、Aブロックと同様にコンクリ−ト成形により形成
されており、所定の厚さを持った矩形板状をなす前方体
6、及び後方体7とから成り、かつ所定の間隔をもって
前後方向に対面配置された前方体6と後方体7とを連結
し、一体化させる1本の連結体8とから構成されてい
る。Further, on the front surface of the front body 2, there is formed a convex surface portion 2a having a trapezoidal cross section and protruding forward. next,
The other stacking block (hereinafter abbreviated as "B block")
5 is formed by concrete molding similarly to the A block, and is composed of a front body 6 and a rear body 7 each having a rectangular plate shape with a predetermined thickness, and is arranged in the front-rear direction at a predetermined interval. The front body 6 and the rear body 7 arranged facing each other are connected to each other to be integrated with each other.
【0020】かかる前方体6の両側端面6sは、前後方
向に対して一定の傾斜角βをもち、かつ後方に向かって
外側へ傾いた面に形成されている。同様に、後方体7の
両側端面7sも、前後方向に対して一定の傾斜角βをも
ち、かつ後方に向かって外側へ傾いた面に形成されてい
る。これらは別言すれば、平面図において、前方体6、
後方体7の両側端面6s、7sの間隔が、それぞれ後方
へ向かってテーパー状に開いた状態に形成されている。Both end surfaces 6s of the front body 6 are formed as surfaces having a constant inclination angle β with respect to the front-back direction and inclined outward toward the rear. Similarly, the both end surfaces 7s of the rear body 7 are also formed into a surface having a constant inclination angle β with respect to the front-back direction and inclined outward toward the rear. In other words, these are the front body 6, in plan view.
The distance between the both end surfaces 6s, 7s of the rear body 7 is formed in a state of being tapered backward toward the rear.
【0021】また、上記各連結体4、8は、縦断面が矩
形状をなし、前後方向に延びる角柱状をなすが、これに
限定するものではなく、例えば、図7、図8に平面図、
側面図をもって示すように、曲線状4a、8aに形成し
てもよい。上記のA・Bブロックの形成寸法は適宜設定
されるものであるが、本実施例においては、図3に示す
ように、各前方体2、6の幅寸法比L1 :L2 が、Aブ
ロック1の両側端面2sの端部2tと、Bブロック5の
両側端面6sの中間点6cと、を接触させた時の接触点
間の距離が略2:1になるように設定されている。Further, each of the connecting bodies 4 and 8 has a rectangular longitudinal section and a prismatic shape extending in the front-rear direction, but is not limited to this. For example, plan views shown in FIGS. ,
As shown in a side view, it may be formed in curved shapes 4a and 8a. The formation dimensions of the blocks A and B are set appropriately, but in the present embodiment, as shown in FIG. 3, the width dimension ratio L 1 : L 2 of the front bodies 2 and 6 is A The distance between the contact points when the ends 2t of the two end surfaces 2s of the block 1 and the intermediate point 6c of the both end surfaces 6s of the B block 5 are set to be approximately 2: 1.
【0022】また、各ブロックA・Bの前方体2、6の
幅寸法は、後方体3、7のそれよりΔLだけ大きく形成
され、高さ寸法は両ブロックA・B共に同じに設定され
ている。さらにまた、ブロックAの前方体2の凸面部2
aの凸部幅Paと、ブロックBの前方体6の前面幅Pb
が略同じに設定され、かつこの凸面部2aにおける前方
体2の肉厚Qaと、ブロックBの前方体6の肉厚Qbと
が同じになるように設定されている。Further, the width dimension of the front bodies 2 and 6 of each block A and B is formed larger than that of the rear bodies 3 and 7 by ΔL, and the height dimension is set to be the same in both blocks A and B. There is. Furthermore, the convex surface portion 2 of the front body 2 of the block A
The width Pa of the convex portion of a and the front surface width Pb of the front body 6 of the block B
Are set to be substantially the same, and the thickness Qa of the front body 2 in the convex surface portion 2a and the thickness Qb of the front body 6 of the block B are set to be the same.
【0023】さらに、Aブロックの前方体2の両側端面
2sを傾斜角αとし、Aブロックの後方体3の両側端面
3sの傾斜角、並びにBブロックの前方体6、及び後方
体7の各両側端面6s、7sの傾斜角、を同一角のβに
設定し、β>αの関係に設定されている。γ(=β−
α)は、後述する曲面配置の対応によって適宜設定され
るものであって、かかる傾斜角α、βは、各前方体2、
6、及び後方体3、7の厚さ、ブロックの大きさ、強
度、等を考慮して適宜選択されるものである。本実施例
においては、それぞれ略、α=43°、β=45°に設
定している。Further, the both end surfaces 2s of the front body 2 of the A block are set to have an inclination angle α, the inclination angles of both end surfaces 3s of the rear body 3 of the A block, and both sides of the front body 6 and the rear body 7 of the B block. The inclination angles of the end faces 6s and 7s are set to β of the same angle, and β> α is set. γ (= β-
α) is appropriately set according to the correspondence of the curved surface arrangement described later, and the inclination angles α and β are
6, and the thickness of the rear bodies 3 and 7, the size of the block, the strength, etc. are taken into consideration. In this embodiment, α = 43 ° and β = 45 ° are set, respectively.
【0024】また、本実施例では、ブロックを水平面に
置いたとき、各ブロックの前方体、後方体が、垂直にな
るように形成しているが、この他、図示は省略している
が、適宜後方へ一定角度傾斜した状態になるように形成
してもよい。通常、掘削法面21には一定の勾配(通称
「ころび」)が付けられているが、基礎25の上面の傾
斜状態によっては、ブロック自体に傾斜を付けておくこ
とも考えられるからである。 〔A・Bブロックの組合せ配置例〕上記のように形成さ
れたA・Bブロックは、以下のような種々の組合せ配置
が行われて、位置決めされる。Further, in this embodiment, when the blocks are placed on the horizontal plane, the front body and the rear body of each block are formed to be vertical, but in addition to this, although not shown, It may be formed so as to be inclined rearward at a certain angle as appropriate. Normally, the excavation slope 21 is provided with a certain slope (commonly called "rolling"), but it is considered that the block itself may be inclined depending on the inclination state of the upper surface of the foundation 25. [Example of Combination Arrangement of A and B Blocks] The A and B blocks formed as described above are positioned by performing various combination arrangements as described below.
【0025】図4に示すように、先ず、Aブロック1、
Bブロック5を幅方向cに揃えるようにして左右に配置
し、互いの前方体2、6の側端面2sと6sとを当接さ
せ、擦り合わせるようにして配置する。この時、各後方
体3、7の両側端面3s、7sどうしは、接触すること
なく、若干の間隙(2ΔL)ができる(以下、この配置
を「標準配置」と略称する)。As shown in FIG. 4, first, the A block 1,
The B blocks 5 are arranged on the left and right so as to be aligned in the width direction c, and the side end surfaces 2s and 6s of the front bodies 2 and 6 are brought into contact with each other and arranged so as to rub against each other. At this time, a slight gap (2ΔL) is formed between the both end surfaces 3s and 7s of the rear bodies 3 and 7 without contacting each other (hereinafter, this arrangement is abbreviated as “standard arrangement”).
【0026】そして、Aブロックを固定し、両側端面2
s、6sどうしを接触させながら、Bブロック5を、前
方へ、又は後方へ移動させる(二点鎖線表示)ことによ
り、標準配置の時のA・Bブロック1組でできる幅寸法
L0 (=L1 +L2 )を、+m、又は−nだけ変化させ
ることができる。Then, the A block is fixed, and both end faces 2
By moving the B block 5 to the front or the rear while making s and 6s contact each other (indicated by a chain double-dashed line), a width dimension L 0 (= L 1 + L 2 ) can be changed by + m or −n.
【0027】なお、ここでAブロックを固定してBブロ
ックを移動させるようにしているが、逆にAブロックの
方を移動させるようにしても良いことはもちろんであ
る。また、図5、図6の作図に示すように、A・Bブロ
ックの何れか一方を、ブロックの中心を上下方向に貫く
軸Oをもって、一定の回転角θだけ回転させた状態で配
置することにより、A・Bブロックを屈曲させた状態で
配置することができる。Aブロックを挟む両側のBブロ
ックのうち、平面図において左側のBブロックを+θ
(左回転)、右側のBブロックを−θ(右回転)させた
場合は、凸曲面状になり(図5:矢印d)、逆に左側の
Bブロックを−θ(右回転)、右側のBブロックを+θ
(左回転)させた場合は、凹曲面状となる(図6:矢印
e)。Although the A block is fixed and the B block is moved here, it goes without saying that the A block may be moved on the contrary. Further, as shown in the drawing of FIG. 5 and FIG. 6, one of the blocks A and B is arranged in a state of being rotated by a constant rotation angle θ with an axis O penetrating the center of the block in the vertical direction. Thus, the A and B blocks can be arranged in a bent state. Of the B blocks on both sides of the A block, the B block on the left side in the plan view is + θ.
When the B block on the right side is rotated by -θ (rotate right), it becomes a convex curved surface (Fig. 5: arrow d), while the B block on the left side is rotated by -θ (rotate right), B block + θ
When it is rotated to the left, it has a concave curved surface (FIG. 6: arrow e).
【0028】次に、上記実施例のA・Bブロックの両側
端面2s、3s、6s、7sの傾斜面は、平面に形成さ
れているが、他の実施例としては、図9、図10に要部
平面図で示すように、曲面状にしてもよい。すなわち、
Aブロック10の前方体11、及び後方体12の両側端
面11s、12sを、前後方向(矢印b)に対して凸曲
面とし(上下方向においては直線状)、かつその前後方
向の接線sが後方に向かって内側へ傾斜(x)するよう
に形成する。Next, the inclined surfaces of both side end faces 2s, 3s, 6s, 7s of the A / B block of the above embodiment are formed to be flat surfaces, but as another embodiment, they are shown in FIGS. As shown in the plan view of the main part, it may be curved. That is,
The front body 11 of the A block 10 and both end surfaces 11s, 12s of the rear body 12 are convex curved surfaces in the front-back direction (arrow b) (in the vertical direction are linear), and the tangent line s in the front-back direction is rearward. It is formed so as to incline (x) toward the inside.
【0029】一方、Bブロック15の前方体16、及び
後方体17の両側端面16s、17sを、前後方向(矢
印b)に対して凸曲面とし、かつその前後方向の接線s
が後方に向かって外側へ傾斜(y)するように形成す
る。上記の構成により、組合せ配置は、前述のA・Bブ
ロック1、5と同様に、互いの両側端面11s、16s
の曲面どうしを擦り合わせるようにして、前後方向に、
及び(又は)回転させて移動させる(矢印f、g:図1
0参照)。On the other hand, both end surfaces 16s, 17s of the front body 16 and the rear body 17 of the B block 15 are convex curved surfaces in the front-rear direction (arrow b), and the tangent line s in the front-rear direction thereof.
Is formed so as to incline (y) outward toward the rear. With the above configuration, the combined arrangement is similar to that of the A / B blocks 1 and 5 described above, and both side end faces 11s and 16s of each other.
Rub the curved surfaces of the
And / or rotate and move (arrows f, g: FIG. 1).
0).
【0030】上記実施例(図9、10)の曲面状は凸曲
面状に形成しているが、この他図示は省略するが、凹曲
面状にしてもよい。 〔A・Bブロックを用いた擁壁築造工法〕次に、上記の
Aブロック1、10、Bブロック5、15を互いに組合
せ配置して構築される曲面擁壁の築造工法について、図
面を参照しながら以下に説明する。図11は本実施例の
築造状態を示す縦断面図であり、図12はその築造擁壁
の一部を示す正面図である。Although the curved surface of the above-described embodiment (FIGS. 9 and 10) is formed into a convex curved surface, it may be formed into a concave curved surface, although not shown. [Retaining wall construction method using A / B blocks] Next, referring to the drawings, for the construction method of the curved retaining wall constructed by arranging the above A blocks 1, 10, B blocks 5, 15 in combination with each other. However, it will be described below. FIG. 11 is a vertical sectional view showing a building state of this embodiment, and FIG. 12 is a front view showing a part of the building retaining wall.
【0031】なお、土手の掘削法面21の形成、裏込栗
石27の敷設、基礎25の形成、については、既述の従
来工法と同様であるため同一符号を付して説明を省略す
る。本願発明の組合せ積みブロックの築造は、図示する
ように、施工された基礎25の上に、 (イ)先ず、第1工程として、Aブロック1とBブロッ
ク5とを1組として、前述したように、その前方体2、
6の両側端面2s、6sどうしを接触させながら前後方
向に摺動させて、又は何れか一方のブロックを中心軸O
の回りに回転移動させて、位置決めして載置する。 (ロ)第2工程は、上記方法により載置されたA・Bブ
ロック一組を、所望組数を横一列に載置して第1段目を
形成して行く。 (ハ)そして、第3工程として、位置決めして配列した
各ブロック1、5の後方体3、7と、土手法面21との
間に裏込栗石27を充填する。 (ニ)第4工程は、各ブロック1、5の前方体2、6と
後方体3、7との間に胴込コンクリ−ト28を充填す
る。 (ホ)次に、第1段目の各ブロック1、5上に、ブロッ
クの目地が上下で一致しないようにして、上記第1工程
及び第2工程と同様の工程によって各ブロックを載置し
て行き、第2段目を構成して行く。 (ヘ)以上の第3工程から第5工程までを繰り返すこと
によって、各ブロックを複数段に積み上げて行き、所定
高さの擁壁を築造して行く。The formation of the excavation slope 21 of the bank, the laying of the back crushed stone 27, and the formation of the foundation 25 are the same as those of the above-mentioned conventional method, and the same reference numerals are given and the description thereof will be omitted. As shown in the drawing, the construction of the combination stacking block of the present invention is performed on the constructed foundation 25. (a) First, as the first step, the A block 1 and the B block 5 are set as one set, and as described above. And its anterior body 2,
6 are slid in the front-rear direction while contacting both end surfaces 2s and 6s of each other, or one of the two blocks is a central axis O
Rotate and move around to position and place. (B) In the second step, one set of A and B blocks placed by the above method is placed in a horizontal row in a desired number of sets to form the first stage. (C) Then, as a third step, the back-filled rubble 27 is filled between the rear bodies 3 and 7 of the blocks 1 and 5 which are positioned and arranged and the soil surface 21. (D) In the fourth step, the trunk concrete 28 is filled between the front bodies 2 and 6 and the rear bodies 3 and 7 of the blocks 1 and 5, respectively. (E) Next, each block is placed on each of the blocks 1 and 5 of the first stage by the same steps as the above-mentioned first step and second step so that the joints of the blocks are not vertically aligned. And make up the second stage. (F) By repeating the above third to fifth steps, each block is stacked in a plurality of stages to build a retaining wall of a predetermined height.
【0032】また、上記実施例の第1工程において、A
ブロック1、Bブロック5を一組として、交互に横方向
に順に並べるように載置して行く工法を採ったが、この
他、図12に示すように、先ず始めに、Aブロック1の
み(又はBブロック5のみ)を所定個数、Bブロック5
(又はAブロック1)が載置し得る間隔wを開けて並べ
て行き、その後、各間隙w、w、・・にBブロック5
(又はAブロック1)を嵌入して行き横一列段を形成す
るようにしてもよい(かかる工法を「間隔載置工法」と
略称する。)。In the first step of the above embodiment, A
The block 1 and the B block 5 are set as a set, and the blocks 1 and 5 are placed so that they are alternately arranged side by side in the horizontal direction. However, as shown in FIG. 12, first, only the A block 1 ( Or B blocks 5 only), a predetermined number of B blocks 5
(Or the A block 1) is arranged with an interval w left therebetween so that the B block 5 can be placed in each of the spaces w, w ,.
(Or the A block 1) may be fitted to form a horizontal single-row step (this construction method is abbreviated as "spaced construction method").
【0033】本願発明の組合せ積みブロックを用いるこ
とによって初めて上記手順の工法を採ることができ、こ
れにより今までにない顕著な効果が得られる。すなわ
ち、図13の平面図に施工概略を示す通り、一般に曲面
擁壁の積みブロックの横並べ手法は、単位施工区間31
(約20m)の両端部側にそれぞれ丁張18、18を植
設し、この丁張18の間に水糸19を張り渡す。目的の
曲率になるようにこの水糸19から順次一定の後退距離
(矢印h)を設定して行き、これを基準として各積みブ
ロックを載置して行くことにより曲面擁壁が築造されて
いた。The construction method according to the above procedure can be adopted for the first time by using the combination stacking block of the present invention, and thereby a remarkable effect which has never been obtained can be obtained. That is, as shown in the plan view of FIG. 13, generally, the method of horizontally arranging the stacked blocks of the curved retaining wall is the unit construction section 31.
Tensions 18 and 18 are planted on both ends of (about 20 m), and a water thread 19 is stretched between the tensions 18. A curved retaining wall was constructed by sequentially setting a certain retreat distance (arrow h) from the water thread 19 so as to obtain a desired curvature, and mounting each stacking block on the basis of this. .
【0034】この場合従来工法は、一方側から順次隣接
させて並べて行くものであるため、最後の位置で設定し
た後退距離(矢印h)と一致しないときは、最初に戻っ
て修正して行かなければならず、非常に手間と熟練の要
する煩雑な作業であった。しかし、本願発明の組合せ積
みブロック1、5は、上述のように一方のブロック1
(又は5)のみを先に水糸19を基準にして置くことが
でき、しかもその間に置くブロック5(又は1)は積極
的に前後方向へ移動させるものであるため、いわゆる面
を揃えることに神経を使う必要がなく、修正も容易に行
うことができる。そのため、特殊技能者に依らないで一
般作業者によっても効率良く施工することができるもの
である。In this case, since the conventional method is to sequentially arrange the adjacent ones from one side, if the setback distance (arrow h) set at the last position does not match, return to the beginning and correct. This is a complicated work that requires a lot of effort and skill. However, the combination stacking blocks 1 and 5 of the present invention are the same as the one block 1 as described above.
Only (or 5) can be placed on the basis of the water thread 19 first, and the block 5 (or 1) placed between them can be positively moved in the front-back direction. You don't have to use nerves and you can easily make corrections. Therefore, general workers can be efficiently constructed without relying on special skilled workers.
【0035】さらに、従来は、クレーン作業者、特殊技
能者、一般作業者、補助者、等で構成される1組の作業
要員(「1パーティー」)によって、単位施工区間31
毎に順次施工して行ったが、上記本願の間隔載置工法を
採ることにより、2組のパーティーを構成して、第1パ
ーティーに1つの単位施行区間31を一方のブロック1
(又は5)のみの載置させた後、次の単位施行区間32
に移動して同様の載置をさせるようにする。この間に、
第2パーティーは第1パーティーの作業の後を追うよう
にして、形成された間隙に順次他方のブロック5(又は
1)を載置して行くようにすれば、効率的作業を行うこ
とができる。このことは施工期間を短縮でき、ひいては
施工費用の逓減を図れる。Further, conventionally, a unit construction section 31 is constructed by a set of working personnel ("1 party") composed of crane workers, special technicians, general workers, assistants, etc.
However, two sets of parties are formed by adopting the interval placement method of the present application, and one unit enforcement section 31 is provided to the first party on one block 1 side.
After placing only (or 5), the next unit enforcement section 32
Move to and try the same placement. During this time,
If the second party follows the work of the first party and sequentially places the other block 5 (or 1) in the formed gap, efficient work can be performed. . This can shorten the construction period and eventually reduce the construction cost.
【0036】なお、前記第4工程において、胴込コンク
リ−ト28の注入を複数段積み上げた後に同時に行うよ
うにしてもよい。また、上記説明において、A・Bブロ
ック1、5を用いて説明したが、A・Bブロック10、
15を用いた場合も同様である。In the fourth step, the in-wall concrete 28 may be injected at the same time after stacking a plurality of stages. In the above description, the A / B blocks 1 and 5 are used for explanation, but the A / B block 10,
The same applies when 15 is used.
【0037】[0037]
【効果】上記構成により、本願発明は以下に列挙する効
果を奏する。 (1)A・Bブロックの何れか一方を、傾斜した両側端
面どうしを擦り合わせて、適宜前後方向に移動させた
り、わずかに回転させたりすることにより、A・Bブロ
ックを合計した幅寸法を適宜変化させることができると
共に、各種曲率の外カーブ、又は内カーブの勾配カーブ
擁壁の築造に的確に対応することができる。 (2)互いのブロック、特に前方体が当接して擦り合っ
ているため、従来の目地の間隔を変化させる工法、や間
地コンクリ−トを用いる工法よりも、確実な強度を確保
することができると共に、美観を損ねることかない。 (3)横一列段の配置において、先ず所定の間隔を採っ
てAブロックのみを配置し、その後、その間隙にBブロ
ックを配置するようにした間隔載置工法を採った場合
は、従来工法のように一方から順に並べて行く工法よ
り、短時間で施工することができ、ひいては工事費用の
逓減を図ることができる。 (4)Aブロックの前方体の前面に、Bブロックの前面
幅と同じ凸面部を形成しているため、A・Bブロックを
前後方向へ多少移動させても、外観を損なうことはな
い。また、本願発明の組み合わせブロックは、積極的に
前後方向にずらして配置するものであるため、従来例の
ように、ブロック前面を同一面上に正確に揃えると言う
施工上の厳格性は要求されないため、石工等の特殊技能
者でない一般作業員によっても容易に施工を行うことが
できる利点がある。 (5)従来は施工延長がブロック長さ単位に制限を受け
ていたが、A・Bブロックの組み合わせによって幅寸法
を適宜調節することができるため、的確に対応すること
ができる効果がある。[Effects] With the above structure, the present invention has the following effects. (1) By rubbing one of the A and B blocks with their slanted end faces, and moving them in the front-back direction as appropriate, or by slightly rotating them, the total width of the A and B blocks is calculated. It can be appropriately changed, and can be appropriately adapted to the construction of the slope curve retaining wall of the outer curve of various curvatures or the inner curve. (2) Since the blocks, especially the front body, are in contact with each other and rub against each other, it is possible to secure more reliable strength than the conventional construction method in which the joint space is changed or the construction method using the interstitial concrete. It can be done, but it does not spoil the aesthetics. (3) In the horizontal single-row arrangement, if only the A block is first arranged at a predetermined interval and then the B block is arranged in the gap, when the interval placing method is adopted, the conventional method is used. As described above, the construction method of sequentially arranging from one side enables the construction to be performed in a short time, which in turn can reduce the construction cost. (4) Since the front surface of the front body of the A block is formed with the same convex surface portion as the front width of the B block, even if the A and B blocks are moved in the front-rear direction, the appearance is not spoiled. Further, since the combination block of the present invention is arranged to be positively displaced in the front-rear direction, the strictness in construction of accurately aligning the block front surface on the same plane is not required unlike the conventional example. Therefore, there is an advantage that a general worker such as a mason who is not a special skilled worker can easily perform the construction. (5) Conventionally, the construction extension is limited by the block length unit, but since the width dimension can be appropriately adjusted by the combination of the A and B blocks, there is an effect that it is possible to respond appropriately.
【図1】本実施例の1組の組合せ積みブロックの一方を
示す全体斜視図である。FIG. 1 is an overall perspective view showing one of a set of combination stacking blocks of the present embodiment.
【図2】本実施例の1組の組合せ積みブロックの他方を
示す全体斜視図である。FIG. 2 is an overall perspective view showing the other one of the set of combination stacking blocks of this embodiment.
【図3】本実施例の1組の組合せ積みブロックの組合せ
状態を示す平面図である。FIG. 3 is a plan view showing a combined state of one combination stacking block of the present embodiment.
【図4】本実施例の1組の組合せ積みブロックの組合せ
配置例を示す平面図である。FIG. 4 is a plan view showing an example of a combination arrangement of a combination stacking block of this embodiment.
【図5】本実施例の1組の組合せ積みブロックの組合せ
配置例を示す平面図である。FIG. 5 is a plan view showing an example of a combination arrangement of a set of combination stacking blocks according to the present embodiment.
【図6】本実施例の1組の組合せ積みブロックの組合せ
配置例を示す平面図である。FIG. 6 is a plan view showing an example of a combination arrangement of a set of combination loading blocks according to the present embodiment.
【図7】他の実施例の1組の組合せ積みブロックの一方
を示す平面図と側面図である。7A and 7B are a plan view and a side view showing one of a pair of combination stacking blocks of another embodiment.
【図8】他の実施例の1組の組合せ積みブロックの他方
を示す平面図と側面図である。8A and 8B are a plan view and a side view showing the other of the set of combined piling blocks according to another embodiment.
【図9】他の実施例の1組の組合せ積みブロックの要部
を示す平面図である。FIG. 9 is a plan view showing an essential part of a set of combinational stacking blocks of another embodiment.
【図10】他の実施例の1組の組合せ積みブロックの組
合せ状態を示す要部平面図である。FIG. 10 is a main part plan view showing a combined state of a set of combination stacking blocks of another embodiment.
【図11】本実施例のA・Bブロックを用いた擁壁の築
造状態を示す縦断面図である。FIG. 11 is a vertical cross-sectional view showing a built state of a retaining wall using the blocks A and B of the present embodiment.
【図12】本実施例のA・Bブロックを用いた擁壁の築
造状態を示す正面図である。FIG. 12 is a front view showing a construction state of a retaining wall using the blocks A and B of the present embodiment.
【図13】本実施例のA・Bブロックを用いた擁壁の築
造概略を示す平面図である。FIG. 13 is a plan view showing an outline of construction of a retaining wall using the blocks A and B of the present embodiment.
【図14】従来例の築造擁壁を一部断面で示す正面図で
ある。FIG. 14 is a front view showing a partially constructed cross section of a conventional construction retaining wall.
【図15】従来例のブロックを用いた擁壁の築造状態を
示す縦断面図である。FIG. 15 is a vertical cross-sectional view showing a construction state of a retaining wall using a block of a conventional example.
【図16】従来の平積み用のブロック例を示す正面図
(A)、側面図(B)、平面図(C)である。FIG. 16 is a front view (A), a side view (B), and a plan view (C) showing an example of a conventional block for flat stacking.
【図17】勾配カーブ擁壁へ対応させた従来の施工例を
示す正面図である。FIG. 17 is a front view showing a conventional construction example corresponding to a slope curve retaining wall.
【図18】勾配カーブ擁壁へ対応させた従来の施工例を
示す正面図である。FIG. 18 is a front view showing a conventional construction example corresponding to a slope curve retaining wall.
1、10・・・Aブロック 5、15・
・・Bブロック 2、6、11、16・・・前方体 2s、6s、11s、16s・・・(前方体の)両側端
面 3、7、12、17・・・後方体 3s、7s、12s、17s・・・(後方体の)両側端
面 4、8、4a、8a、・・・連結体1, 10 ... A block 5,15
..B blocks 2, 6, 11, 16 ... Front body 2s, 6s, 11s, 16s ... Both end surfaces (of front body) 3, 7, 12, 17 ... Rear body 3s, 7s, 12s , 17s ... Both end surfaces (of the rear body) 4, 8, 4a, 8a ,.
Claims (7)
(2、6)及び後方体(3、7)と、該前方体と後方体
とを所定の間隔をもって一体に連結する連結体(4、
8)とからなる積みブロックにおいて、 前方体(2)及び後方体(3)の両側端面(2s、3
s)を、前後方向に対し一定の傾斜角をもち、かつ後方
に向かって内側に傾けた面に形成したブロック(Aブロ
ック)と、 前方体(6)及び後方体(7)の両側端面(6s、7
s)を、前後方向に対し一定の傾斜角をもち、かつ後方
に向かって外側に傾けた面に形成したブロック(Bブロ
ック)と、 からなることを特徴とする組合せ積みブロック。1. A rectangular plate-shaped front body (2, 6) and rear body (3, 7) having a predetermined thickness, and a connection for integrally connecting the front body and the rear body with a predetermined space. Body (4,
8) in a stacking block consisting of the front body (2) and the rear body (3) on both side end faces (2s, 3).
s) has a constant inclination angle with respect to the front-back direction and is formed on a surface inclined inward toward the rear (A block), and both end surfaces of the front body (6) and the rear body (7) ( 6s, 7
and a block (B block) having a constant inclination angle with respect to the front-rear direction and formed on a surface inclined outward toward the rear, the combination stacking block.
(2、6)及び後方体(3、7)と、該前方体と後方体
とを所定の間隔をもって一体に連結する連結体(4、
8)とからなる積みブロックにおいて、 前方体(2)及び後方体(3)の両側端面(2s、3
s)を、前後方向に沿う曲面状に、かつその前後方向の
接線(s)が後方に向かって内側へ傾斜(x)するよう
に形成したブロック(Aブロック)と、 前方体(6)及び後方体(7)の両側端面(6s、7
s)を、前後方向に沿う曲面状に、かつその前後方向の
接線(s)が後方に向かって外側へ傾斜(y)するよう
に形成したブロック(Bブロック)と、からなることを
特徴とする組合せ積みブロック。2. A rectangular plate-shaped front body (2, 6) and rear body (3, 7) having a predetermined thickness, and a connection for integrally connecting the front body and the rear body with a predetermined space. Body (4,
8) in a stacking block consisting of the front body (2) and the rear body (3) on both side end faces (2s, 3).
a block (A block) in which s) is formed in a curved shape along the front-rear direction, and a tangential line (s) in the front-rear direction inclines (x) toward the rear, and a front body (6) and Both end surfaces (6s, 7) of the rear body (7)
s) is formed in a curved shape along the front-rear direction, and a tangent line (s) in the front-rear direction is formed so as to incline (y) outward toward the rear, a block (B block). Combination stacking block.
状としたことを特徴とする請求項2記載の組合せ積みブ
ロック。3. The combination stacking block according to claim 2, wherein the curved surface along the front-rear direction is a convex curved surface.
成し、 幅の大きい方のブロック(Aブロック、又はBブロッ
ク)の前面に、幅の小さい方のブロック(Bブロック、
又はAブロック)の幅と略同じ長さの凸面部(2a)
を、形成し、かつ該凸面部を含む前方体の肉厚と幅の小
さい方のブロックの前方体の肉厚とを、略同じに設定し
たことを特徴とする請求項1、又は2記載の組合せ積み
ブロック。4. A block having a smaller width (B block, B block) is formed on the front surface of the block having a larger width (A block or B block) by forming the blocks with different front surface width dimensions.
Or, a convex portion (2a) having a length substantially the same as the width of the (A block)
And the thickness of the front body including the convex portion and the thickness of the front body of the block having a smaller width are set to be substantially equal to each other. Combination loading block.
築造する請求項1、2、又は3記載の組合せ積みブロッ
クを用いた擁壁築造工法。 (イ)施工された基礎上面において、AブロックとBブ
ロックとを、その前方体の両側端面どうしを接触させな
がら、何れか一方のブロックを前後方向に摺動させて位
置決めして配置する第1工程、(ロ)上記方法により配
置されたA・Bブロックを一組として、基礎上面にAブ
ロックとBブロックとを交互にして、所望組数を横一列
に配列して第1段目を構築して行く第2工程、(ハ)上
記第2工程により配列された各ブロックの後方体と、掘
削法面との間に裏込栗石を充填する第3工程、(ニ)該
各ブロックの前方体と後方体との間に胴込コンクリ−ト
を充填する第4工程、(ホ)第2工程で構成した第1段
目の各ブロック上に、ブロックの目地が上下で一致しな
いようにして、第1工程及び第2工程と同様の手順によ
って第2段目を構成して行く第5工程、(ヘ)前記第3
工程から第5工程までを繰り返すことによって、所望の
段数を積み上げて行く第6工程。5. A retaining wall construction method using a combination stacking block according to claim 1, 2 or 3, wherein a retaining wall having a predetermined height is constructed in the following order of steps. (A) On the constructed upper surface of the foundation, the A block and the B block are arranged by positioning one of the blocks by sliding one of the blocks in the front-rear direction while contacting both end surfaces of the front body thereof. Step (b) A / B blocks arranged by the above method are set as one set, A blocks and B blocks are alternately arranged on the upper surface of the foundation, and a desired number of sets are arranged in a horizontal row to construct the first stage. The second step to be carried out, (c) the third step of filling back-filled calculi between the rear body of each block arranged in the second step and the excavation slope, (d) the front of each block Make sure that the joints of the blocks do not vertically match on each block of the first stage constructed in the fourth step (e) the second step of filling the body-incorporating concrete between the body and the rear body. , The second step is constructed by the same procedure as the first step and the second step. Step 5 go to, (f) said third
A sixth step in which the desired number of stages is accumulated by repeating the steps from the fifth step.
共に、ブロックの中心を上下方向に貫く軸(O)をもっ
て一定の回転移動を与えて配置することを特徴とする請
求項5記載の組合せ積みブロックを用いた擁壁築造工
法。6. In the first step, one of the A and B blocks is slid in the front-rear direction, and the block is arranged with a certain rotational movement by an axis (O) penetrating the center of the block in the vertical direction. A retaining wall construction method using the combination block according to claim 5.
のみを所定個数、他方のブロック(Bブロック、又はA
ブロック)が載置し得る間隔を開けて載置して行き、そ
の後、各間隔(w)に他方のブロックを載置して行くこ
とを特徴とする請求項5、又は6記載の組合せ積みブロ
ックを用いた擁壁築造工法。7. In the first step, one block (A block or B block) is first formed.
Only a predetermined number, the other block (B block or A
7. The combined stacking block according to claim 5, wherein the blocks are placed with an interval in which they can be placed, and then the other block is placed at each interval (w). Retaining wall construction method using.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP26293194A JP2820629B2 (en) | 1994-10-26 | 1994-10-26 | Combination stacking block and retaining wall construction method using it |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP26293194A JP2820629B2 (en) | 1994-10-26 | 1994-10-26 | Combination stacking block and retaining wall construction method using it |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH08120692A true JPH08120692A (en) | 1996-05-14 |
JP2820629B2 JP2820629B2 (en) | 1998-11-05 |
Family
ID=17382580
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP26293194A Expired - Fee Related JP2820629B2 (en) | 1994-10-26 | 1994-10-26 | Combination stacking block and retaining wall construction method using it |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2820629B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007002586A (en) * | 2005-06-27 | 2007-01-11 | Kankyo Kogaku Kk | Civil engineering structure, unit for civil engineering structure and lifting carrying tool |
JP2014218809A (en) * | 2013-05-07 | 2014-11-20 | 有限会社須崎サブコン | Retaining wall block |
-
1994
- 1994-10-26 JP JP26293194A patent/JP2820629B2/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007002586A (en) * | 2005-06-27 | 2007-01-11 | Kankyo Kogaku Kk | Civil engineering structure, unit for civil engineering structure and lifting carrying tool |
JP4518400B2 (en) * | 2005-06-27 | 2010-08-04 | 環境工学株式会社 | Civil engineering structure |
JP2014218809A (en) * | 2013-05-07 | 2014-11-20 | 有限会社須崎サブコン | Retaining wall block |
Also Published As
Publication number | Publication date |
---|---|
JP2820629B2 (en) | 1998-11-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7244079B1 (en) | Retaining wall system | |
KR20190022240A (en) | block for construct retaining wall | |
CN115492130A (en) | Construction method for grooving underground diaphragm wall of soft-hard interbed stratum | |
JPH08120692A (en) | Masonry block and retaining wall construction method making use thereof | |
JP3010619U (en) | Combination stacking block | |
JP3135826B2 (en) | How to build an arch tunnel structure in embankment | |
KR100393515B1 (en) | Afforestation Retaining-Wall laying Concrete-block | |
KR102122698B1 (en) | Construction method of underground continuous walls for minimizing ground displacements during deep and vertical excavation in urban areas | |
JP2880430B2 (en) | Combination block and retaining wall construction method using it | |
JP4195890B2 (en) | Stacking blocks | |
JPH02140313A (en) | High-rigidity steel sheet pile | |
JP6871597B2 (en) | Disposal formwork for concrete foundation, method of making on-site formwork and method of expanding the width of the base of concrete foundation | |
JP2596733B2 (en) | Block for wall construction | |
JPS5841227Y2 (en) | Element for mountain retainer | |
JP3829705B2 (en) | Circular continuous underground wall drilling rig | |
JPS6312174Y2 (en) | ||
JPH0553888B2 (en) | ||
JP2003213675A (en) | Wall pile | |
KR200235108Y1 (en) | Afforestation Retaining-Wall laying Concrete-block | |
JP2021046705A (en) | Ground improvement structure | |
JPH0641993A (en) | Learned retaining wall | |
JPH0782757A (en) | Laying block for retaining wall and retaining wall construction method using same | |
JPH0738394Y2 (en) | Building blocks | |
JPH11172698A (en) | Block wall face structure | |
SU749977A1 (en) | Method of erecting prefabricated ferroconcrete multilevel wall in earth |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |