JPH079555Y2 - Wiring / Piping duct - Google Patents

Wiring / Piping duct

Info

Publication number
JPH079555Y2
JPH079555Y2 JP356491U JP356491U JPH079555Y2 JP H079555 Y2 JPH079555 Y2 JP H079555Y2 JP 356491 U JP356491 U JP 356491U JP 356491 U JP356491 U JP 356491U JP H079555 Y2 JPH079555 Y2 JP H079555Y2
Authority
JP
Japan
Prior art keywords
wiring
cable
passage portion
pipe
piping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP356491U
Other languages
Japanese (ja)
Other versions
JPH065324U (en
Inventor
昭八 清水
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mirai Kogyo KK
Original Assignee
Mirai Kogyo KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mirai Kogyo KK filed Critical Mirai Kogyo KK
Priority to JP356491U priority Critical patent/JPH079555Y2/en
Publication of JPH065324U publication Critical patent/JPH065324U/en
Application granted granted Critical
Publication of JPH079555Y2 publication Critical patent/JPH079555Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Details Of Indoor Wiring (AREA)
  • Installation Of Indoor Wiring (AREA)

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】この考案は、建造物の天井壁等に
沿って配設され、内部に電線や信号線等のケーブルを配
線したり、電線管やガス管等の管を配管したりする配線
・配管用ダクトに関し、主として二重天井内におけるケ
ーブルの配線や管の配管に適した配線・配管用ダクトに
関するものである。
[Industrial application] This invention is arranged along a ceiling wall of a building, for wiring cables such as electric wires and signal lines, and for piping electric wires and gas pipes. The present invention mainly relates to a wiring / pipe duct suitable for cable wiring and pipe piping in a double ceiling.

【0002】[0002]

【従来の技術】従来、建造物の天井壁等に沿って配設さ
れる配線・配管用ダクトとしては、例えば図12に示す
ように、ダクト本体22が、金属材料よりなるチャネル
部材23と蓋体24とにより四角筒状に形成され、複数
の吊り下げ金具6により建造物の天井壁等に沿って吊り
下げ配置される配線・配管用ダクト21が知られてい
る。
2. Description of the Related Art Conventionally, as a wiring / piping duct arranged along a ceiling wall of a building, for example, as shown in FIG. 12, a duct body 22 includes a channel member 23 made of a metal material and a lid. A wiring / piping duct 21 is known which is formed in a rectangular tube shape by a body 24 and is hung and arranged along a ceiling wall or the like of a building by a plurality of hanging metal fittings 6.

【0003】この従来構成の配線・配管用ダクト21の
場合には、ケーブルCの配線や管の配管を行う場合、呼
び線をダクト本体22の一端開口部より挿入して他端開
口部から引き出し、この呼び線の先端部にケーブルCや
管を連結した後、呼び線を引き戻すことにより、ダクト
本体22の通路内にケーブルCや管を引き込んで配線又
は配管するようにしていた。
In the case of the wiring / piping duct 21 of this conventional structure, when wiring the cable C or piping a pipe, the nominal line is inserted from one end opening of the duct main body 22 and pulled out from the other end opening. After the cable C and the pipe are connected to the tip of the call line, the call line is pulled back to pull the cable C and the pipe into the passage of the duct main body 22 for wiring or piping.

【0004】[0004]

【考案が解決しようとする課題】しかしながら、この従
来の配線・配管用ダクトにおいては、例えば、ダクト本
体22内に複数本のケーブルCを配線する場合、既にダ
クト本体22の通路内に配線されたケーブルCが、次の
ケーブルCの配線作業時における呼び線の挿入の邪魔に
なって、配線作業をスムーズに行うことができないとい
う問題があった。
However, in this conventional wiring / piping duct, for example, when a plurality of cables C are laid in the duct body 22, they are already laid in the passage of the duct body 22. There is a problem in that the cable C interferes with the insertion of the nominal line during the wiring work of the next cable C, and the wiring work cannot be performed smoothly.

【0005】この考案は、このような従来の技術に存在
する問題点に着目してなされたものであって、ダクト本
体の通路内に既に配線又は配管されたケーブルや管に阻
害されることなく、新たなケーブルや管の配線及び配管
作業を効率よく行うことができる配線・配管用ダクトを
提供することを目的としている。
The present invention has been made by paying attention to the problems existing in such a conventional technique, without being obstructed by the cables or pipes already wired or piped in the passage of the duct body. , It is an object of the present invention to provide a wiring / pipe duct capable of efficiently performing new cable / pipe wiring and piping work.

【0006】また、この考案は、二重天井内に配設され
て、天井に取り付けられる照明器具等へのケーブル等の
引き込みやダクト途中からのケーブル等の引き出しを容
易に行うことができる配線・配管用ダクトを提供するこ
とを目的としている。
Further, the present invention is a wiring / wiring which is arranged in a double ceiling and which can easily pull in a cable or the like to a lighting fixture or the like mounted on the ceiling or pull out the cable or the like from the middle of a duct. It is intended to provide a duct for piping.

【0007】[0007]

【課題を解決するための手段】上記の目的を達成するた
めに、この考案では、「内部にケーブルや管が配線又は
配管される中空通路部を有する配線・配管用ダクトであ
って、通路部上方又は側方に、軸方向に連続するスリッ
トが通路部内に臨むように設けられると共に通路部にケ
ーブルや管を引き込むためケーブル、管又は呼びロープ
を連結する引込具が挿通される挿通部が長手方向に連続
して形成され、通路部の下方又は側方に、人の手及びケ
ーブル又は管が挿通可能な開口部が所定間隔で形成され
ることを特徴とする配線・配管用ダクト」をその要旨と
している。
In order to achieve the above object, in the present invention, "a wiring / piping duct having a hollow passage portion in which a cable or a pipe is wired or piped, the passage portion A slit that is continuous in the axial direction is provided in the upper or side direction so as to face the inside of the passage part, and the insertion part through which a pulling tool that connects the cable, the pipe or the nominal rope is inserted to draw the cable or pipe into the passage part is long. The wiring / piping duct "is characterized in that it is formed continuously in the direction, and that openings at which human hands and cables or tubes can be inserted are formed at predetermined intervals below or at the side of the passage. It is a summary.

【0008】[0008]

【作用】上記のように構成された配線・配管用ダクトに
あっては、ケーブルや管を配線又は配管する場合、例え
ば、図4に示すロープ13を備えたシャトル12からな
る引込具を通路部2の一端開口部側から挿通部9内に挿
入し、引込具を挿通部9に沿って移動させる。そして、
通路部2の他端開口部側においてシャトル12にケーブ
ルCや管を連結した後、ロープ13を通路部2の一端開
口部側に引き戻し、ケーブルCや管を通路部2内に引き
込んで、配線又は配管することができるようになってい
る。
In the wiring / piping duct constructed as described above, when a cable or pipe is to be wired or laid, for example, a pulling tool consisting of the shuttle 12 provided with the rope 13 shown in FIG. One end of 2 is inserted into the insertion portion 9 from the opening side, and the retractor is moved along the insertion portion 9. And
After connecting the cable C and the pipe to the shuttle 12 at the other end opening side of the passage part 2, the rope 13 is pulled back to the one end opening side of the passage part 2 and the cable C and the pipe are drawn into the passage part 2 for wiring. Or it can be plumbed.

【0009】また、通路部2の他端開口部側においてシ
ャトル12に呼びロープを連結した場合には、ロープ1
3を通路部2の一端開口部側に引き戻すことで呼び線を
通路部2内に挿通させ、次いで、呼びロープにケーブル
Cや管を連結し、呼びロープを引っ張って通路部2内に
ケーブルCや管を引き込んで、配線又は配管することが
できるようになっている。
If a shuttle rope is connected to the shuttle 12 at the opening of the other end of the passage portion 2, the rope 1
3 is pulled back to the opening portion side of the passage portion 2 so that the call wire is inserted into the passage portion 2, and then the cable C or the pipe is connected to the call rope, and the call rope is pulled to pull the cable C into the passage portion 2. It is possible to draw wires or pipes for wiring or piping.

【0010】このように、通路部2の内周壁に設けられ
た挿通部9に沿って引込具を挿通させて往復動させるこ
とにより、既に通路部2内にケーブルCや管が配線又は
配管されていても、その通路部2内のケーブルCや管に
阻害されることなく、通路部2内にケーブルC等を容易
に配線・配管することができる。
As described above, by inserting the retracting tool along the insertion portion 9 provided on the inner peripheral wall of the passage portion 2 and reciprocating it, the cable C or the pipe is already wired or piped in the passage portion 2. However, the cable C and the like in the passage portion 2 can be easily wired and piped in the passage portion 2 without being hindered by the cable C and the pipe.

【0011】そして、天井に取り付けられる照明器具等
へケーブルを引き込む場合には、図9に示すように、通
路部2の下方に所定間隔で形成された開口部4の任意の
位置から通路部2内に配線されたケーブルCを引き出し
て、照明器具Gへの配線を行うことができるようになっ
ている。
When the cable is pulled into a lighting fixture or the like mounted on the ceiling, as shown in FIG. 9, the passage portion 2 is formed from an arbitrary position of the openings 4 formed below the passage portion 2 at predetermined intervals. The cable C wired inside can be pulled out to perform wiring to the lighting fixture G.

【0012】また、前記開口部4により、図11に示す
ように、側方の開口部4からケーブルC等を引き出し
て、他の通路部2内や天井内への配線をすることができ
る。これにより、通路部2内外へのケーブルCの配線や
管の配管を必要に応じて、効率よく行うことができる。
Further, as shown in FIG. 11, the opening 4 allows the cable C or the like to be drawn out from the side opening 4 to be wired in another passage 2 or in the ceiling. Thereby, the wiring of the cable C and the piping of the pipe to the inside and outside of the passage portion 2 can be efficiently performed as necessary.

【0013】[0013]

【実施例】以下、この考案を具体化した配線・配管用ダ
クトの実施例を、図1〜図11に基づいて詳細に説明す
る。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a wiring / piping duct embodying the present invention will be described below in detail with reference to FIGS.

【0014】図1〜図3に示すように、配線・配管用ダ
クト1の通路部2は、内部にケーブルや管が配線又は配
管されるように四角筒状に形成されている。図1に示す
配線・配管用ダクト1の通路部2は下方に向かって開放
する金属製の本体2aと、その本体2aの下方開放部に
梯子状に架け渡された複数の架設部材2bとにより四角
筒状に形成され、前記架設部材2bの上面はケーブルや
管を載置するための載置部3を構成し、架設部材2b間
には開口部4が形成されている。又、図2に示す配線・
配管用ダクト1の通路部2は、上方に向かって開放する
金属製の本体2aと、その本体2aの上方開放部に着脱
可能に取り付けられた蓋部材2cとにより四角筒状に形
成され、前記本体2aの下面はケーブルや管を載置する
ための載置部3を構成し、さらに本体2aの下面には開
口部4が形成されている。図3に示す配線・配管用ダク
ト1は本体2aの下方及び側方に開口部4が形成されて
いる。
As shown in FIGS. 1 to 3, the passage portion 2 of the wiring / piping duct 1 is formed in a rectangular tube shape so that a cable or a pipe can be wired or laid inside. The passage portion 2 of the wiring / piping duct 1 shown in FIG. 1 is composed of a metal main body 2a that opens downward, and a plurality of erection members 2b that are laid in a ladder shape on the lower open portion of the main body 2a. It is formed in a rectangular tube shape, the upper surface of the erection member 2b constitutes a mounting portion 3 for mounting a cable or a pipe, and an opening 4 is formed between the erection members 2b. In addition, the wiring shown in FIG.
The passage portion 2 of the duct 1 for piping is formed in a square tubular shape by a metal main body 2a that opens upward and a lid member 2c that is detachably attached to the upper open portion of the main body 2a. A lower surface of the main body 2a constitutes a mounting portion 3 for mounting a cable or a tube, and an opening 4 is formed on the lower surface of the main body 2a. The wiring / piping duct 1 shown in FIG. 3 has openings 4 formed below and laterally of the main body 2a.

【0015】その本体2aの両側上端には係止溝5が通
路部2の長手方向に沿って形成されている。吊り下げ金
具6は掛止溝5に係合する掛止具7と調整ボルト8とか
らなり、この吊り下げ金具6を複数個使用することによ
り、通路部2が建造物の天井壁等に沿って所定高さ位置
に配設されるようになっている。
Locking grooves 5 are formed in the upper ends of both sides of the main body 2a along the longitudinal direction of the passage portion 2. The hanging metal fitting 6 is composed of a hook 7 that engages with the hanging groove 5 and an adjusting bolt 8. By using a plurality of the hanging metal fittings 6, the passage portion 2 can be formed along the ceiling wall of a building or the like. Are arranged at a predetermined height position.

【0016】挿通部9は、通路部2の本体2a又は蓋部
材2cの内面の中央部に突出して略円筒形状に形成さ
れ、通路部2の長手方向に沿って延びている。スリット
10は挿通部9の下端縁に軸線方向へ連続して形成さ
れ、このスリット10を介して挿通部9が通路部2内に
開口している。一対の係合溝11は通路部2の長手方向
に沿って延びるように、挿通部9の外周両側部に形成さ
れ、通路部2を他の通路部2に連結するとき、両通路部
2の係合溝11間に位置決めピン等を嵌合して、挿通部
9の位置合わせを行うようになっている。なお、この挿
通部9は任意の位置でスリット10を容易に押し広げる
ことができるように、アルミニウム等の軟らかくて脆性
破壊されにくい金属材料により作製されるのがよい。
The insertion portion 9 is formed in a substantially cylindrical shape so as to protrude from the center of the inner surface of the main body 2a of the passage portion 2 or the lid member 2c, and extends along the longitudinal direction of the passage portion 2. The slit 10 is formed continuously on the lower end edge of the insertion portion 9 in the axial direction, and the insertion portion 9 is opened in the passage portion 2 through the slit 10. The pair of engaging grooves 11 are formed on both sides of the outer periphery of the insertion portion 9 so as to extend along the longitudinal direction of the passage portion 2, and when the passage portion 2 is connected to another passage portion 2, both passage portions 2 are formed. A positioning pin or the like is fitted between the engaging grooves 11 to align the insertion portion 9. The insertion portion 9 is preferably made of a metal material such as aluminum that is soft and less likely to be brittlely broken so that the slit 10 can be easily spread at any position.

【0017】そして、図4に示すように、通路部2内に
ケーブルCの配線や管の配管を行う際に、鋼線、合成樹
脂製の棒状体、又はそれらの撚り線等よりなる所定の剛
性及び引っ張り強度を有したロープ13を、紡錘円柱状
をなす軽量のシャトル12に連結した引込具が前記挿通
部9に沿って案内されるようになっている。
As shown in FIG. 4, when the cable C and the pipe are laid in the passage portion 2, a predetermined wire made of a steel wire, a synthetic resin rod, or a twisted wire thereof is used. A pulling tool, in which a rope 13 having rigidity and tensile strength is connected to a lightweight shuttle 12 having a spindle columnar shape, is guided along the insertion portion 9.

【0018】なお、この考案にあっては、通路部2や挿
通部9の形状は四角形や円形状の構成に限定されるもの
ではない。また、この考案にあっては、通路部2に沿っ
て形成される挿通部9は、実施例のように通路部2の上
方に設けられた場合の他、側方に設けられてもよく、そ
の個数は複数であってもよい。
In this invention, the shape of the passage portion 2 and the insertion portion 9 is not limited to the rectangular or circular shape. Further, in this invention, the insertion portion 9 formed along the passage portion 2 may be provided on the side other than the case where it is provided above the passage portion 2 as in the embodiment, The number may be plural.

【0019】次に、前記のように構成された配線・配管
用ダクト1にケーブルCの配線や管の配管を行う場合の
作業手順の一例を、図5〜図8に基づいて説明する。
Next, an example of a work procedure for wiring the cable C and piping the pipe in the wiring / piping duct 1 configured as described above will be described with reference to FIGS.

【0020】さて、図5に示すように、配線・配管用ダ
クト1が複数の吊り下げ金具6により、建造物の天井壁
等に沿って吊り下げ配置された状態で、その通路部2に
ケーブルCの配線や管の配管を行う場合には、まず、図
6に示すように、ロープ13を連結したシャトル12を
通路部2の一端開口部側から挿通部9内に挿入して、そ
のシャトル12の下端取付部12aをスリット10から
通路部2内に突出させる。この状態で、ロープ13を介
してシャトル12を通路部2の他端開口部側に押し込
み、シャトル12及びロープ13を挿通部9内に挿通さ
せる。
As shown in FIG. 5, the wiring / piping duct 1 is suspended by a plurality of suspending metal fittings 6 along a ceiling wall of a building or the like, and a cable is provided in the passage portion 2. When the wiring of C or the piping of the pipe is performed, first, as shown in FIG. 6, the shuttle 12 to which the rope 13 is connected is inserted into the insertion portion 9 from one end opening side of the passage portion 2 and the shuttle 12 is inserted. The lower end mounting portion 12 a of the protrusion 12 is projected from the slit 10 into the passage portion 2. In this state, the shuttle 12 is pushed toward the other end opening side of the passage portion 2 via the rope 13 to insert the shuttle 12 and the rope 13 into the insertion portion 9.

【0021】その後、図7に示すように、通路部2の他
端開口部側においてシャトル12の取付部12aにケー
ブルCや管を連結し、この状態でロープ13を通路部2
の一端開口部側に引き戻し、図8に示すように、ケーブ
ルCや管を天井14の点検口15間に配置された配線・
配管用ダクト1の通路部2内に引き込む。
Thereafter, as shown in FIG. 7, the cable C and the pipe are connected to the mounting portion 12a of the shuttle 12 at the other end opening side of the passage portion 2, and the rope 13 is connected to the passage portion 2 in this state.
One end of the cable is pulled back toward the opening side, and as shown in FIG.
It is drawn into the passage portion 2 of the piping duct 1.

【0022】そして、天井14に取り付けられた照明器
具Gへ配線する場合には、図9に示すように、シャトル
12からケーブルC又は管の連結を解除し、通路部2の
下方に所定間隔で形成された開口部4の任意の位置から
ケーブルCを引き出して、天井14に取り付けられた照
明器具Gへの配線を行う。
When wiring to the luminaire G mounted on the ceiling 14, the cable C or the pipe is disconnected from the shuttle 12 and is provided at a predetermined interval below the passage 2 as shown in FIG. The cable C is pulled out from an arbitrary position of the formed opening portion 4, and wiring to the lighting fixture G mounted on the ceiling 14 is performed.

【0023】このように、この実施例においては、ロー
プ13を備えたシャトル12から成る引込具が、ダクト
本体2の頂壁内面に設けられた挿通部9に沿って案内さ
れるようになっているため、ダクト本体2内に複数本の
ケーブルCや管を配線又は配管する作業時において、既
にダクト本体2内にケーブルCや管が挿通されていて
も、そのダクト本体2内のケーブルCや管に阻害される
ことなく、ダクト本体2内にロープ13やケーブルC等
を順次容易に挿通することができる。従って、ケーブル
Cや管の配線及び配管作業をスムーズに効率よく行うこ
とができる。
As described above, in this embodiment, the retractor including the shuttle 12 having the rope 13 is guided along the insertion portion 9 provided on the inner surface of the top wall of the duct body 2. Therefore, even when the cable C or the pipe is already inserted in the duct body 2 during the work of wiring or piping the plurality of cables C or the pipe in the duct body 2, The rope 13, the cable C, and the like can be sequentially and easily inserted into the duct body 2 without being hindered by the pipe. Therefore, the wiring of the cable C and the pipe and the piping work can be performed smoothly and efficiently.

【0024】上記図5〜図8に示す配線作業は、天井1
4が取付けられた後にケーブルCを配線した場合である
が、配線作業は天井14が取付けられる前であっても、
勿論行うことができる。この場合は、照明器具Gの取付
けられる位置に配線されたケーブルCの端を開口部4か
ら予め引き出しておけばよい。
The wiring work shown in FIGS.
4 shows the case where the cable C is laid after being installed, but the wiring work is performed even before the ceiling 14 is installed.
Of course it can be done. In this case, the end of the cable C wired at the position where the lighting fixture G is attached may be pulled out from the opening 4 in advance.

【0025】なお、通路部2の途中までケーブルCの配
線や管の配管を行いたい場合には、挿通部9がアルミニ
ウム等の軟かくて脆性破壊されにくい金属材料により作
製されていれば図10に示すように、ケーブルCや管を
引き込みたい位置の開口部4から引込具を挿し入れ、挿
通部9のスリット10をペンチ等を用いて押し広げ、こ
こから挿通部9内に引込具を挿入し、引込具を挿通部9
内で往復動させることにより、通路部2内へのケーブル
Cの配線や管の配管を必要に応じて、効率よく行うこと
ができる。又、図11に示すように通路部2の途中から
ケーブルCや管を他の通路部2あるいは天井内へ配線・
配管したい場合には、通路部2の側方に設けられた開口
部4よりケーブルCや管を引き出して、配線・配管する
ことができる。
When it is desired to carry out the wiring of the cable C or the piping of the pipe up to the middle of the passage portion 2, if the insertion portion 9 is made of a metal material such as aluminum which is soft and is not easily brittlely broken, FIG. As shown in FIG. 5, insert the pulling tool from the opening 4 at the position where the cable C or the tube is desired to be pulled in, push the slit 10 of the insertion portion 9 open with pliers or the like, and insert the pulling tool into the insertion portion 9 from here. Insert the retractor into the insertion part 9
By reciprocating inside, the wiring of the cable C into the passage portion 2 and the piping of the pipe can be efficiently performed as necessary. Further, as shown in FIG. 11, the cable C and the pipe are routed from the middle of the passage 2 to another passage 2 or the ceiling.
When piping is desired, the cable C or the pipe can be drawn out from the opening 4 provided on the side of the passage portion 2 for wiring / piping.

【0026】[0026]

【考案の効果】この考案は、以上説明したように構成さ
れているため、例えば、通路部内に複数本のケーブルや
管を配線又は配管する場合でも、通路部内において既に
配線又は配管されたケーブルや管に阻害されることな
く、通路部の挿通部内に引込具を挿通して往復させるこ
とでケーブルや管の配線及び配管作業を効率よく行うこ
とができる。また、二重天井内に配設された場合には、
天井に取り付けられる照明器具等へのケーブル等の引き
込みを容易に行うことができるという優れた効果を奏す
る。さらに、通路部の下方又は側方に設けられた開口部
により通路部途中までのケーブル等の配線・配管や通路
部途中からのケーブル等の引き出し配線や配管を必要に
応じて行うことができる。
Since the present invention is configured as described above, even when a plurality of cables or pipes are wired or piped in the passage, the cables or pipes already wired or piped in the passage can be used. It is possible to efficiently perform the wiring and piping work of the cable and the pipe by inserting and retracting the retractor into the insertion portion of the passage portion and reciprocating without being hindered by the pipe. Also, when installed in the double ceiling,
This has an excellent effect that a cable or the like can be easily pulled into a lighting device or the like attached to the ceiling. Furthermore, the opening or the like provided below or on the side of the passage portion allows wiring / piping of the cable or the like up to the middle of the passage portion and lead-out wiring or piping of the cable or the like from the middle of the passage portion.

【図面の簡単な説明】[Brief description of drawings]

【図1】この考案を具体化した配線・配管用ダクトの一
実施例を示す部分斜視図である。
FIG. 1 is a partial perspective view showing an embodiment of a wiring / piping duct embodying the present invention.

【図2】この考案を具体化した配線・配管用ダクトの別
の実施例を示す部分斜視図である。
FIG. 2 is a partial perspective view showing another embodiment of a wiring / piping duct embodying the present invention.

【図3】この考案を具体化した配線・配管用ダクトの別
の実施例を示す部分斜視図である。
FIG. 3 is a partial perspective view showing another embodiment of a wiring / pipe duct embodying the present invention.

【図4】第1図に示す配線・配管用ダクトの通路部内に
ケーブルを配線する状態を示す一部破断斜視図である。
FIG. 4 is a partially cutaway perspective view showing a state in which a cable is wired in the passage portion of the wiring / piping duct shown in FIG.

【図5】通路部内にケーブルを配線する作業過程を順に
示す部分断面図である。
5A and 5B are partial cross-sectional views sequentially showing a work process of wiring a cable in a passage portion.

【図6】通路部内にケーブルを配線する作業過程を順に
示す部分断面図である。
FIG. 6 is a partial cross-sectional view sequentially showing a work process of wiring a cable in a passage portion.

【図7】通路部内にケーブルを配線する作業過程を順に
示す部分断面図である。
FIG. 7 is a partial cross-sectional view sequentially showing a work process of wiring a cable in a passage portion.

【図8】通路部内にケーブルを配線する作業過程を順に
示す部分断面図である。
FIG. 8 is a partial cross-sectional view sequentially showing a work process of wiring a cable in a passage portion.

【図9】照明器具への配線状態を示す部分断面図であ
る。
FIG. 9 is a partial cross-sectional view showing a wiring state to a lighting fixture.

【図10】通路部の途中からのケーブルを配線する作業
過程を示す部分断面図である。
FIG. 10 is a partial cross-sectional view showing a work process of wiring a cable in the middle of a passage portion.

【図11】通路部の途中からのケーブルを配線する作業
過程を示す部分断面図である。
FIG. 11 is a partial cross-sectional view showing a work process of wiring a cable in the middle of a passage portion.

【図12】従来の配線・配管用ダクトを示す部分斜視図
である。
FIG. 12 is a partial perspective view showing a conventional wiring / piping duct.

【符号の説明】[Explanation of symbols]

1 配線・配管用ダクト 2 通路部 4 開口部 9 挿通部 10 スリット 13 ロープ C ケーブル 1 Wiring / Piping Duct 2 Passage 4 Opening 9 Insert 10 Slit 13 Rope C Cable

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 内部にケーブルや管が配線又は配管され
る中空通路部を有する配線・配管用ダクトであって、 通路部上方又は側方に、軸方向に連続するスリットが通
路部内に臨むように設けられると共に通路部にケーブル
や管を引き込むためケーブル、管又は呼びロープを連結
する引込具が挿通される挿通部が長手方向に連続して形
成され、 通路部の下方又は側方に、人の手及びケーブル又は管が
挿通可能な開口部が所定間隔で形成されることを特徴と
する配線・配管用ダクト。
1. A wiring / piping duct having a hollow passage portion in which a cable or a pipe is wired or piped, wherein an axially continuous slit faces the inside of the passage portion above or to the side of the passage portion. Is provided at the same time, and an insertion part through which a pulling tool for connecting a cable, a pipe, or a call rope for inserting a cable or a pipe into the passage is inserted is formed continuously in the longitudinal direction. A wiring / piping duct, characterized in that openings for inserting hands and cables or tubes are formed at predetermined intervals.
JP356491U 1991-02-04 1991-02-04 Wiring / Piping duct Expired - Lifetime JPH079555Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP356491U JPH079555Y2 (en) 1991-02-04 1991-02-04 Wiring / Piping duct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP356491U JPH079555Y2 (en) 1991-02-04 1991-02-04 Wiring / Piping duct

Publications (2)

Publication Number Publication Date
JPH065324U JPH065324U (en) 1994-01-21
JPH079555Y2 true JPH079555Y2 (en) 1995-03-06

Family

ID=11560926

Family Applications (1)

Application Number Title Priority Date Filing Date
JP356491U Expired - Lifetime JPH079555Y2 (en) 1991-02-04 1991-02-04 Wiring / Piping duct

Country Status (1)

Country Link
JP (1) JPH079555Y2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10371916B2 (en) * 2017-01-20 2019-08-06 Clearfield, Inc. Optical fiber pathway duct

Also Published As

Publication number Publication date
JPH065324U (en) 1994-01-21

Similar Documents

Publication Publication Date Title
KR970013550A (en) How to construct the spiral area where cables are hanging
US5363525A (en) Ceiling wire tool
JPH079555Y2 (en) Wiring / Piping duct
US4878653A (en) Apparatus and method for pre-wire routing for buildings
US20180051827A1 (en) Magnetic loop hanger
JPH079554Y2 (en) Wiring / Piping duct
JPH0734615B2 (en) Cable laying method
KR101206886B1 (en) Suspension for communication cable
JP2565852Y2 (en) Ducts for wiring and piping
JPH0515034A (en) Wiring/piping duct
JP2529851Y2 (en) Ducts for wiring and piping
US888376A (en) Extensible chandelier.
JP3380887B2 (en) Wiring and piping material drop-in tool and wiring and piping equipment
JP2568898Y2 (en) Ducts for wiring and piping
JPH0219072Y2 (en)
JP3032848B2 (en) Wiring and piping material installation equipment
JPH04271215A (en) Method for laying pipe and cable and laying equipment
JPH0322812Y2 (en)
JP3264908B2 (en) Wiring and piping installation shooter
JP3032847B2 (en) Wiring and piping material installation equipment
JP7451248B2 (en) Arrangement structure of hook body and wiring/piping materials
JP3005696B2 (en) Wiring and piping material laying shooter and wiring and piping material laying device
JP3000338B2 (en) Wiring / Piping Duct Device and Method for Pulling Cables and Pipes into Wiring / Piping Duct
JP2000104862A (en) High altitude suspension tool
JPS587794Y2 (en) Cable horizontal overhead line support structure

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term