JPH0751816B2 - Beam unit and steel column / beam integrated unit - Google Patents

Beam unit and steel column / beam integrated unit

Info

Publication number
JPH0751816B2
JPH0751816B2 JP63280521A JP28052188A JPH0751816B2 JP H0751816 B2 JPH0751816 B2 JP H0751816B2 JP 63280521 A JP63280521 A JP 63280521A JP 28052188 A JP28052188 A JP 28052188A JP H0751816 B2 JPH0751816 B2 JP H0751816B2
Authority
JP
Japan
Prior art keywords
floor slab
steel frame
unit
concrete
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP63280521A
Other languages
Japanese (ja)
Other versions
JPH02128034A (en
Inventor
忠明 長浜
千賀子 勝野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP63280521A priority Critical patent/JPH0751816B2/en
Publication of JPH02128034A publication Critical patent/JPH02128034A/en
Publication of JPH0751816B2 publication Critical patent/JPH0751816B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 〈産業上の利用分野〉 本発明は、SRC造の梁の改良及びこの梁に鉄骨柱を予め
接合してユニット化した、梁ユニット及び鉄骨柱・梁一
体化ユニットに関するものである。
DETAILED DESCRIPTION OF THE INVENTION <Industrial application> The present invention relates to a beam unit and a steel column / beam integrated unit in which an SRC-made beam is improved and a steel frame column is pre-joined to form a unit. It is a thing.

〈従来の技術〉 従来SRC造の施工は、柱,梁,床スラブの全ての鉄骨,
鉄筋を現場にて組立て、次いで型枠を取付けコンクリー
トを打設するか、あるいは工場等で製造されたPC梁やPC
床等を現場にて組込む等により行われていた。
<Conventional technology> Conventional SRC construction is used for all steel frames of columns, beams, floor slabs,
Reinforcing bars are assembled on site, then formwork is attached and concrete is placed, or PC beams and PC manufactured in factories, etc.
It was done by assembling the floor etc. on site.

このうちPC梁は、第10図に示すように、上面にスターラ
ップ2の上端部を突出した半PC梁1が主流となっている
(例えば、特公昭53−21204号公報等参照)。
Among them, as shown in FIG. 10, the main type of PC beams is a half-PC beam 1 in which an upper end portion of a stirrup 2 is projected on an upper surface (see, for example, Japanese Patent Publication No. 53-21204).

この半PC梁1は、H型梁鉄骨3の両端部、下端筋4の両
端部及びスターラップ2の上端部を露出させるようにコ
ンクリートを打設して製造される。
This half-PC beam 1 is manufactured by placing concrete so that both ends of the H-shaped beam steel frame 3, both ends of the lower end streak 4 and the upper end of the stirrup 2 are exposed.

梁鉄骨3の両端部は図示しない鉄骨柱との接合プレート
として用いられ、下端筋4の両端部は接続(アンカー)
筋として他の半PC梁の接続(アンカー)筋との接合に用
いられ、スターラップ2の上端部は第11図に示すように
床スラブ9との取合部として用いられる。
Both ends of the beam steel frame 3 are used as joint plates with a steel column not shown, and both ends of the lower end bar 4 are connected (anchors).
It is used as a line for joining with the connection (anchor) line of another half-PC beam, and the upper end of the stirrup 2 is used as a connecting part with the floor slab 9 as shown in FIG.

すなわち第11図において、スターラップ2の上端部に梁
上端筋6と床スラブ筋7aが挿入され、更に他の床スラブ
筋7b等を適当に配筋し、その後図示しない型枠を取付け
てコンクリートを現場打ちして床スラブ9が施工され
る。
That is, in FIG. 11, the beam upper end reinforcements 6 and floor slab reinforcements 7a are inserted into the upper end of the stirrup 2, and further floor slab reinforcements 7b and the like are appropriately arranged, and then a formwork (not shown) is attached to the concrete. Then, the floor slab 9 is constructed.

〈発明が解決しようとする課題〉 上記のように従来の半PC梁1の場合、構造上極めて重要
な梁の上部において、工場等で予め打設したコンクリー
トと現場にて打設したコンクリートとの打継ぎが生じる
という問題があった。そして、この打継ぎの品質を確保
するために、高品質・高コストのコンクリートの使用
や、ボイド発生を防止するための細心のコンクリート打
設作業、高強度・高コストの鉄筋の多数の使用等を余儀
なくされていた。
<Problems to be Solved by the Invention> In the case of the conventional semi-PC beam 1 as described above, the concrete poured in advance in a factory or the like and the concrete cast in the field are provided above the beam, which is extremely important in terms of structure. There was a problem that piecing would occur. In order to ensure the quality of this joint, use of high-quality and high-cost concrete, careful concrete placement work to prevent the occurrence of voids, use of many high-strength and high-cost reinforcing bars, etc. Was forced to.

しかも現場における梁上端筋6の挿入や結束,鉄骨柱と
の接合等、煩雑な作業を残しており、工期の長期化の一
因ともなっていた。
Moreover, complicated work such as insertion of the beam upper end reinforcement 6, binding, and joining with the steel column is left on site, which is one of the causes of prolonging the construction period.

また従来の半PC梁1の場合床スラブ9はPC梁の上面から
しか施工できず、梁の下部が天井面に突出してしまう。
このため、建造物の外壁,階段室,コンピュータルーム
等のように外観や設備等の観点からして天井面からの梁
の突出が障害となる場所には、従来の半PC梁1の使用が
できず、専ら現場にて梁鉄骨の組立て、梁・床スラブの
各種配筋、型枠の取付け、コンクリート打設等により、
梁下部に床スラブを配設するいわゆる逆梁方式の施工を
行う必要があった。
Further, in the case of the conventional semi-PC beam 1, the floor slab 9 can be constructed only from the upper surface of the PC beam, and the lower part of the beam projects to the ceiling surface.
For this reason, the conventional half-PC beam 1 should be used in places where the projection of the beam from the ceiling surface is an obstacle from the viewpoint of appearance and equipment, such as the exterior walls of buildings, stair rooms, and computer rooms. I couldn't do it, and on the site exclusively, by assembling beam steel frames, various reinforcements of beams and floor slabs, attaching formwork, placing concrete, etc.
It was necessary to carry out the so-called reverse beam construction in which the floor slab is placed under the beam.

本発明は梁上部の打継ぎがなく、また鉄骨柱との接合等
現場での煩雑な作業を要せず、しかも逆梁方式にも適用
することのできる梁ユニット及び鉄骨柱・梁一体化ユニ
ットを提供することを目的とする。
INDUSTRIAL APPLICABILITY The present invention does not have a splice on the upper part of the beam, does not require complicated work such as joining with a steel column in the field, and can be applied to the reverse beam method and a steel column / beam integrated unit. The purpose is to provide.

〈課題を解決するための手段〉 第1の発明は上記目的を達成するために、梁ユニット
が、長手方向端部に梁鉄骨及び梁鉄筋の接続端部が突出
されると共に幅方向側部に床スラブ取合部が突設され
て、全体がプレキャスト化されたコンクリート梁からな
ることを特徴とする。
<Means for Solving the Problems> In order to achieve the above-mentioned object, a first aspect of the present invention is that a beam unit includes a beam steel frame and a connecting end portion of a beam reinforcing bar projecting from an end portion in the longitudinal direction, and a beam unit on a lateral side portion. It is characterized in that the floor slab joint is projected and the whole is made of precast concrete beams.

また第2の発明は、長手方向端部に梁鉄骨及び梁鉄筋の
接続端部が突出されると共に幅方向側部に床スラブ取合
部が突設されて、全体がプレキャスト化されたコンクリ
ート梁と、該コンクリート梁の梁鉄骨の接続端部に一体
的に接合された鉄骨柱とからなることを特徴とする。
A second aspect of the present invention is a concrete beam in which a beam steel frame and a connecting end portion of a beam reinforcing bar are projected at an end portion in a longitudinal direction and a floor slab connecting portion is projecting at a side portion in a width direction, so that the entire precast concrete beam is formed. And a steel frame pillar integrally joined to the connection end of the beam steel frame of the concrete beam.

〈作用〉 第1の発明の作用について述べると、全体をプレキャス
ト化したコンクリート梁であるため、梁の上部において
は打継ぎがなく、梁の構造耐力が向上する。このため、
梁の品質を確保する上で従来不可欠であった高品質・高
コストのコンクリートの使用や、無ボイドでのコンクリ
ート打設作業、あるいは高強度・高コストの鉄筋の多数
使用等は、必要とされず、材料費や工事費を大幅に低減
できる。また、従来の半PC梁において必要であった現場
でのコンクリート打設の際の型枠は不要となり、この点
でもコスト低減を図ることができる。そして、現場にお
ける作業は単純化し、かつ減少し、工期を大幅に短縮で
きる。
<Operation> To describe the operation of the first invention, since it is a precast concrete beam as a whole, there is no joint at the upper part of the beam, and the structural yield strength of the beam is improved. For this reason,
The use of high-quality, high-cost concrete, which was conventionally indispensable for ensuring the quality of beams, concrete pouring work without voids, and the use of many high-strength, high-cost reinforcing bars, etc. are required. In addition, material costs and construction costs can be significantly reduced. In addition, the formwork for pouring concrete on site, which was necessary for conventional half-PC beams, is no longer necessary, and cost reduction can be achieved in this respect as well. Then, the work at the site can be simplified and reduced, and the construction period can be greatly shortened.

そしてこのように全体をプレキャスト化しながらも、梁
鉄骨及び梁鉄筋の接続端部や床スラブ取合部を突出させ
て確保しているので、現場での周辺の柱や梁・スラブと
の接合も簡便に行うことができる。
And while precasting the whole in this way, since the connecting ends of the beam steel and beam reinforcing bars and the floor slab joint are projected and secured, it is also possible to join the surrounding columns and beams / slabs on site. It can be done easily.

殊に、床スラブ取合部の突設位置は必要に応じて高さ設
定できるので、通常の梁方式や、逆梁方式いずれにも対
応させることができる。従って、逆梁方式のものもプレ
キャスト化でき、建造物の外壁,階段室,コンピュータ
ルーム等の施工を容易に行うことができる。
Particularly, since the height of the protruding position of the floor slab connecting portion can be set as required, it is possible to support both the normal beam method and the reverse beam method. Therefore, the reverse beam method can also be precast and the construction of the outer wall of the building, the staircase, the computer room, etc. can be performed easily.

第2の発明の作用について述べると、上記第1の発明と
同様の作用を奏するほか、予め鉄骨柱も接合して構成し
ているので、現場作業をさらに軽減することができる。
The operation of the second invention will be described. In addition to the same operation as that of the first invention, the steel column is also joined in advance, so that the site work can be further reduced.

〈実施例〉 第1図は梁ユニットの一実施例を示す斜視図である。<Embodiment> FIG. 1 is a perspective view showing an embodiment of the beam unit.

第1の発明は基本的には、梁ユニット10が長手方向端部
に梁鉄骨3及び梁鉄筋4,6の接続端部が突出されると共
に幅方向側部に床スラブ取合部11,12が突設されて、全
体がプレキャスト化されたコンクリート梁5で構成され
る。
The first aspect of the invention is basically that the beam unit 10 is such that the connecting ends of the beam steel frame 3 and the beam reinforcing bars 4 and 6 project at the longitudinal ends and the floor slab joints 11 and 12 at the lateral sides. Is formed so as to project, and the whole is made up of precast concrete beams 5.

同図において、10が梁ユニットであり、H形梁鉄骨3の
両端部3aと、上端筋6,下端筋4の両端部6a,4aを残し
て、コンクリートが打込まれ、本実施例ではこの梁5の
一側面下部に例えば第2図,第3図に示す態様で床スラ
ブ取合部11,12が突設されている。
In the figure, 10 is a beam unit, concrete is poured in, leaving both end portions 3a of the H-beam steel frame 3 and both end portions 6a, 4a of the upper end bar 6 and the lower end bar 4, and in this embodiment, Floor slab connecting portions 11 and 12 are provided on the lower part of one side surface of the beam 5 in a manner shown in FIGS. 2 and 3, for example.

先ず、床スラブ取合部11は、第2図に示すように、L形
金物をH形梁鉄骨3の上下両フランジ間に嵌め込み、L
形金物の水平部先端が梁5の側面下部から突出するよう
に構成されている。なお、梁5から突出されたL形金物
の水平部先端にはボルト穴11aが穿設されている。
First, as shown in FIG. 2, the floor slab fitting portion 11 fits the L-shaped metal fitting between the upper and lower flanges of the H-shaped beam steel frame 3,
The tip of the horizontal portion of the shaped metal article is configured to project from the lower portion of the side surface of the beam 5. A bolt hole 11a is formed at the end of the horizontal portion of the L-shaped metal object protruding from the beam 5.

また、図示は省略するが、L形金物とH形梁鉄骨3と
は、ボルト・ナットや溶接等により固定してもよい。
Although not shown, the L-shaped metal and the H-shaped beam steel frame 3 may be fixed to each other by bolts / nuts or welding.

次に、床スラブ取合部12は、第3図に示すように、L形
鉄筋12aと直線状の鉄筋12bを、L形鉄筋12aの先端が梁
5の側面中央部からやや下部に、直線状の鉄筋12bの先
端が梁5の側面下部に、各々突出するように構成されて
いる。
Next, as shown in FIG. 3, the floor slab joining portion 12 includes an L-shaped reinforcing bar 12a and a linear reinforcing bar 12b, in which the tip of the L-shaped reinforcing bar 12a is straight from the center of the side surface of the beam 5 to a slightly lower part. The tips of the bar-shaped reinforcing bars 12b are configured to protrude below the side surfaces of the beam 5, respectively.

なおこの場合も図示は省略するが、L形鉄筋12a,直線状
の鉄筋12bとH形梁鉄骨3とは、ボルト・ナットや溶接
等により固定してもよい。
Also in this case, although not shown, the L-shaped reinforcing bar 12a, the linear reinforcing bar 12b and the H-shaped beam steel frame 3 may be fixed by bolts, nuts or welding.

以上の第1図〜第3図の梁ユニット10は、第2図,第3
図に示すように、梁5の下部に床スラブ9を施工する所
謂逆梁方式のものであるが、床スラブ取合部11,12を第
4図,第5図のように梁5の側面上部に突設させて、梁
5の上方に床スラブ9を施工する通常の梁方式とするこ
ともできる。
The beam unit 10 shown in FIGS. 1 to 3 is shown in FIGS.
As shown in the figure, the so-called reverse beam method is used in which the floor slab 9 is installed on the lower part of the beam 5, but the floor slab joints 11 and 12 are attached to the side surface of the beam 5 as shown in FIGS. 4 and 5. It is also possible to adopt a normal beam system in which the floor slab 9 is installed above the beam 5 by projecting it on the upper part.

なお、第1図〜第5図において、床スラブ取合部11,12
は梁5の両側面に設けることもできる。
In addition, in FIGS. 1 to 5, the floor slab connecting portions 11 and 12 are shown.
Can also be provided on both sides of the beam 5.

第6図及び第7図は梁ユニット10の施工を示す斜視図で
ある。
6 and 7 are perspective views showing construction of the beam unit 10.

図示例では、第1図に示す梁ユニット10の梁鉄骨端部3a
が鉄骨柱20に接合されている。
In the illustrated example, the beam steel frame end portion 3a of the beam unit 10 shown in FIG.
Are joined to the steel column 20.

そして梁5の長手方向端部に突出された梁鉄筋4,6の端
部4a,6aが、同様な構成でなる他の梁ユニット10の梁鉄
筋4,6と接合されると共に、梁鉄骨3の端部3aが鉄骨柱2
0と接合される。そしてこれら梁ユニット10をそれらの
端部4a,6aで互いに接合すると共に、これら梁ユニット1
0を鉄骨柱20に接合することにより、現場での構築作業
が実施されることになる。そしてその後床施工に際し
て、床スラブ取合部11,12が床スラブ9の配筋と接合、
結束される。このとき床スラブ取合部11,12を梁5の上
部に突設しておけば、梁5の上方に床スラブ9が施工さ
れる通常の梁方式となり、下部に突設しておけば下方に
床スラブ9が施工される。所謂逆梁方式となる。また第
7図に示すように鉄骨柱20への配筋21とコンクリートの
打設が行なわれる。
Then, the end portions 4a, 6a of the beam reinforcing bars 4, 6 projecting at the longitudinal ends of the beam 5 are joined to the beam reinforcing bars 4, 6 of another beam unit 10 having the same structure, and the beam steel frame 3 End 3a of steel column 2
Joined with 0. The beam units 10 are joined to each other at their ends 4a and 6a, and the beam units 1
By joining 0 to the steel column 20, construction work will be carried out on site. Then, during floor construction, the floor slab joints 11 and 12 are joined to the reinforcement of the floor slab 9,
Be united. At this time, if the floor slab connecting portions 11 and 12 are provided on the upper portion of the beam 5, the floor slab 9 is constructed above the beam 5, and if it is provided on the lower portion, the floor slab 9 is lowered. A floor slab 9 is installed on the floor. The so-called reverse beam method is used. Further, as shown in FIG. 7, reinforcements 21 and concrete are placed on the steel columns 20.

第8図は第2の発明に係る鉄骨柱・梁一体化ユニットの
実施例を示す斜視図である。
FIG. 8 is a perspective view showing an embodiment of the steel frame pillar / beam integrated unit according to the second invention.

第2の発明は基本的には、長手方向端部に梁鉄骨3及び
梁鉄筋4,6の接続端部3a,4a,6aが突出されると共に幅方
向側部に床スラブ取合部11,12が突設されて、全体がプ
レキャスト化されたコンクリート梁5と、コンクリート
梁5の梁鉄骨3の接続端部3aに一体的に接合された鉄骨
柱20とから構成される。
The second invention is basically such that the beam steel frame 3 and the connecting end portions 3a, 4a, 6a of the beam reinforcing bars 4, 6 are projected at the longitudinal end portions and the floor slab joint portion 11, at the lateral side portions, 12 is projected, and is made up of a precast concrete beam 5 as a whole, and a steel frame column 20 integrally joined to the connecting end 3a of the beam steel frame 3 of the concrete beam 5.

図示例では第1図に示す梁ユニット10を4個使用し、1
本の鉄骨柱20の上下部の両側部に、梁ユニット10の梁鉄
骨端部3aを介して接合一体化したユニットとして構成さ
れている。
In the illustrated example, four beam units 10 shown in FIG.
It is configured as a unit which is joined and integrated to both upper and lower portions of the steel column 20 of the book via the beam steel frame end portions 3a of the beam unit 10.

第9図では、第1図に示す梁ユニット10を3個使用し、
各梁ユニット10間に鉄骨柱20が梁鉄骨端部3aを介して接
合一体化されたユニットとして構成されている。
In FIG. 9, three beam units 10 shown in FIG. 1 are used,
A steel column 20 is formed between the beam units 10 as a unit that is joined and integrated through the beam steel end portions 3a.

なお、第9図では両端の梁ユニット10として中央の梁ユ
ニット10より短いものが使用されているが、3個の梁ユ
ニット10が全て同一長さのものであっても良いことは言
うまでもない。
Although the beam units 10 at both ends are shorter than the central beam unit 10 in FIG. 9, it goes without saying that all three beam units 10 may have the same length.

この実施例では、上述の梁ユニット10の梁鉄骨3の端部
3aに鉄骨柱20が予め接合された構成となっており、現場
での構築作業に際しては、複数の鉄骨柱・梁一体化ユニ
ットの鉄骨柱20同士を接合すると共に梁鉄筋4,6相互を
接合し、その後上記実施例と同様にして床スラブ9を施
工することになる。
In this embodiment, the end portion of the beam steel frame 3 of the beam unit 10 described above is
The structure is made by pre-joining the steel columns 20 to the 3a, and at the time of construction work at the site, the steel columns 20 of a plurality of steel column / beam integrated units are joined together and the beam rebars 4, 6 are also joined together. After that, the floor slab 9 is constructed in the same manner as in the above embodiment.

以上の実施例において、梁鉄骨端部3aと鉄骨柱20との接
合一体化は、溶接,ボルト・ナット等、通常の接合一体
化手法をそのまま採用できる。
In the above embodiment, for the joining and unifying of the steel beam end portion 3a of the beam and the steel column 20, the usual joining and unifying method such as welding, bolts and nuts can be directly adopted.

〈発明の効果〉 以上詳述した本発明においては、次のような効果を奏す
ることができる。
<Effects of the Invention> In the present invention described in detail above, the following effects can be achieved.

(1)全体をプレキャスト化したコンクリート梁である
ため、梁の上部においては打継ぎがなく、梁の構造耐力
が向上する。このため、梁の品質を確保する上で従来不
可欠であった高品質・高コストのコンクリートの使用
や、無ボイドでのコンクリート打設作業、あるいは高強
度・高コストの鉄筋の多数使用等は、必要とされず、材
料費や工事費を大幅に低減できる。
(1) Since the whole is a precast concrete beam, there is no splice at the top of the beam, and the structural strength of the beam is improved. For this reason, the use of high-quality, high-cost concrete, which was previously indispensable for ensuring the quality of the beams, concrete pouring work without voids, or the use of a large number of high-strength, high-cost reinforcing bars, It is not required, and material costs and construction costs can be reduced significantly.

(2)従来の半PC梁において必要であった現場でのコン
クリート打設の際の型枠は不要となり、この点でもコス
ト低減を図ることができる。
(2) Formwork, which was necessary for conventional semi-PC beams, when pouring concrete on site is not required, and cost can be reduced in this respect as well.

(3)現場における作業は単純化し、かつ減少し、工期
を大幅に短縮できる。
(3) Work on the site can be simplified and reduced, and the construction period can be shortened significantly.

(4)そしてこのように全体をプレキャスト化しながら
も、梁鉄骨及び梁鉄筋の接続端部や床スラブ取合部を突
出させて確保しているので、現場での周辺の柱や梁・ス
ラブとの接合も簡便に行うことができる。
(4) And, while precasting the whole in this way, since the connecting ends of the beam steel frames and beam reinforcing bars and the floor slab joints are projected and secured, it is possible to use the surrounding columns, beams and slabs on site. Can be easily joined.

(5)梁の幅方向側部に突設した床スラブ取合部の高さ
位置は、必要に応じて設定できるので、通常の梁方式
や、逆梁方式いずれにも対応させることができる。従っ
て、逆梁方式のものもプレキャスト化でき、建造物の外
壁,階段室,コンピュータルーム等の施工を容易に行う
ことができる。
(5) Since the height position of the floor slab connecting portion projecting on the side portion in the width direction of the beam can be set as necessary, it can be applied to either a normal beam system or a reverse beam system. Therefore, the reverse beam method can also be precast and the construction of the outer wall of the building, the staircase, the computer room, etc. can be performed easily.

(6)予め鉄骨柱も接合して構成することで、現場作業
をさらに軽減することができる。
(6) By constructing the steel frame columns in advance, it is possible to further reduce on-site work.

【図面の簡単な説明】[Brief description of drawings]

第1図は第1の発明の好適な一実施例を示す斜視図、第
2図及び第3図は第1図の要部拡大断面図、第4図及び
第5図は床スラブ取合部の他の例を示す要部拡大断面
図、第6図は鉄骨柱との接合を示す斜視図、第7図は鉄
骨柱部分に配筋した現場における施工態様を示す図、第
8図は第2の発明の好適実施例を示す斜視図、第9図は
他の一実施例を示す斜視図、第10図は従来の半PC梁を示
す斜視図、第11図は第10図に示す半PC梁への床スラブ施
工態様を示す図である。 3……梁鉄骨 4,6……梁鉄筋(梁上端筋,梁下端筋) 5……コンクリート梁 10……梁ユニット 11,12……床スラブ取合部 20……鉄骨柱
FIG. 1 is a perspective view showing a preferred embodiment of the first invention, FIGS. 2 and 3 are enlarged cross-sectional views of an essential part of FIG. 1, and FIGS. 4 and 5 are floor slab joints. FIG. 6 is a perspective view showing a joint with a steel column, FIG. 7 is a diagram showing a construction mode at the site where the steel column portion is reinforced, and FIG. 2 is a perspective view showing a preferred embodiment of the invention of FIG. 2, FIG. 9 is a perspective view showing another embodiment, FIG. 10 is a perspective view showing a conventional half-PC beam, and FIG. 11 is a half shown in FIG. It is a figure which shows the floor slab construction aspect to a PC beam. 3 …… Beam steel 4,6 …… Beam reinforcement (beam top reinforcement, beam bottom reinforcement) 5 …… Concrete beam 10 …… Beam unit 11, 12 …… Floor slab joint 20 …… Steel column

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】長手方向端部に梁鉄骨及び梁鉄筋の接続端
部が突出されると共に幅方向側部に床スラブ取合部が突
設されて、全体がプレキャスト化されたコンクリート梁
からなることを特徴とする梁ユニット。
1. A concrete beam precast as a whole, in which a beam steel frame and a connecting end of a beam reinforcing bar are projected at longitudinal ends and a floor slab joint is projected at lateral sides. A beam unit characterized by that.
【請求項2】長手方向端部に梁鉄骨及び梁鉄筋の接続端
部が突出されると共に幅方向側部に床スラブ取合部が突
設されて、全体がプレキャスト化されたコンクリート梁
と、該コンクリート梁の梁鉄骨の接続端部に一体的に接
合された鉄骨柱とからなることを特徴とする鉄骨柱・梁
一体化ユニット。
2. A concrete beam precast as a whole, in which a connecting end portion of a beam steel frame and a beam reinforcing bar is projected at a longitudinal end portion and a floor slab connecting portion is projectingly provided at a lateral side portion, An integrated unit of steel frame and beam, comprising a steel frame column integrally joined to a connection end portion of a beam steel frame of the concrete beam.
JP63280521A 1988-11-08 1988-11-08 Beam unit and steel column / beam integrated unit Expired - Lifetime JPH0751816B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP63280521A JPH0751816B2 (en) 1988-11-08 1988-11-08 Beam unit and steel column / beam integrated unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP63280521A JPH0751816B2 (en) 1988-11-08 1988-11-08 Beam unit and steel column / beam integrated unit

Publications (2)

Publication Number Publication Date
JPH02128034A JPH02128034A (en) 1990-05-16
JPH0751816B2 true JPH0751816B2 (en) 1995-06-05

Family

ID=17626265

Family Applications (1)

Application Number Title Priority Date Filing Date
JP63280521A Expired - Lifetime JPH0751816B2 (en) 1988-11-08 1988-11-08 Beam unit and steel column / beam integrated unit

Country Status (1)

Country Link
JP (1) JPH0751816B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002097716A (en) * 2000-09-22 2002-04-05 Ando Corp Short support slab supporting structure

Also Published As

Publication number Publication date
JPH02128034A (en) 1990-05-16

Similar Documents

Publication Publication Date Title
JP2001342679A (en) CONNECTING METHOD FOR PCa BEAM MEMBER AT COLUMN/BEAM JUNCTION AND PCa BEAM MEMBER FOR IT
JP3323463B2 (en) Construction method of viaduct
JPH0751816B2 (en) Beam unit and steel column / beam integrated unit
JPH0480444A (en) Connection unit of reinforced concrete pole and steel framed beam
JP2758208B2 (en) Joint method between column and steel reinforced concrete beam
JPH0396544A (en) Jointing method for precast steel frame reinforced concrete column having beam steel frame
JPH0949331A (en) Construction method of concrete building and construction member
JP3284391B2 (en) Reinforced concrete frame and construction method
JPH10280541A (en) Frame of mixed structure and constructing method of the frame
JP2758205B2 (en) Method of joining column or wall to precast beam
JP2917159B2 (en) Column, beam joining method
JPH0781307B2 (en) How to build a skyscraper
JPH0745783B2 (en) Construction method of precast column beam and precast earthquake resistant wall.
JP2893406B2 (en) Precast concrete beam-column joining method
JP2890983B2 (en) Beam connection structure of PC column
JPH06995B2 (en) Method for joining columns and PC beams
JP3125165B2 (en) Warehouse frame
JPH0751802B2 (en) Prefabricated unit made of steel reinforced concrete
JP2814873B2 (en) How to build a reinforced concrete building
JPH07268883A (en) Method of construction of footing section using precast footing beam
JP3114024B2 (en) Frame joint structure
JPH0833021B2 (en) How to build a skyscraper
JPS5891246A (en) Concrete ramen prefabricating construction
JPS61196036A (en) Connection of precast pillar and precast beam
JP3122739B2 (en) Frame consisting of precast RC columns and precast RC beams